Vous êtes sur la page 1sur 341

L

GRAND ELENA AND GRAND ARIVA Machinery System Operation Manual

PROVISIONAL

ISSUESD FEB. 20, 2007

Introduction
General Although the ship is supplied with shipbuilder's plans and manufacturers instruction books, there is no single handbook which gives guidance on operating complete systems as installed on board, as distinct from individual items of machinery. The purpose of this manual is to fill some of the gaps and to provide the ships officers with additional information not otherwise available on board. It is intended to be used in conjunction with the other plans and instruction books already on board and in no way replaces or supersedes them. Information pertinent to the operation of the vessel has been carefully collated in relation to the systems of the vessel and is presented in two on board volumes consisting of CARGO OPERATING MANUAL and MACHINERY OPERATING MANUAL. The Cargo Operating Manual and the Machinery Operating Manual are designed to complement MARPOL 73/78, ISGOTT and Company Regulations. The vessel is constructed to comply with MARPOL 73/78. These regulations can be found in the Consolidated Edition, 1991 and in the Amendments dated 1992, 1994 and 1995. Officers should familiarise themselves with the contents of the International Convention for the Prevention of Pollution from Ships. Particular attention is drawn to Appendix IV of MARPOL 73/78, the form of Ballast Record Book. It is essential that a record of relevant ballast operations are kept in the Ballast Record Book and duly signed by the officer in charge. In many cases the best operating practice can only be learned by experience. If any information in these manuals is believed to be inaccurate or incomplete, the officer must use his professional judgment and other information available on board to proceed. Any such errors or omissions or modifications to the ships installations, set points, equipment or approved deviation from published operating procedures, must be reported immediately to Technical Operations Office. Safe Operation The safety of the ship depends on the care and attention of all on board. Most safety precautions are a matter of common sense and good housekeeping and are detailed in the various manuals available on board. However, records show that even experienced operators sometimes neglect safety precautions through over-familiarity and the following basic rules must be remembered at all times. 1. Never continue to operate any machine or equipment which appears to be potentially unsafe or dangerous and always report such a condition immediately. 2. Make a point of testing all safety equipment and devices regularly. Always test safety trips before starting any equipment. 3. Never ignore any unusual or suspicious circumstances, no matter how trivial. Small symptoms often appear before a major failure occurs. 4. Never underestimate the fire hazard of petroleum products, especially fuel oil vapour. 5. Never start a machine remotely from the control room without checking visually if the machine is able to operate satisfactorily. Auto standby machinery should be checked by observation during duty rounds. In the design of equipment and machinery, devices are included to ensure that, as far as possible, in the event of a fault occurring, whether on the part of the equipment or the operator, the equipment concerned will cease to function without danger to personnel or damage to the machine. If these safety devices are neglected, the operation of any machine is potentially dangerous. Description The concept of this Machinery Operating Manual is to provide information to technically competent ships officers, unfamiliar to the vessel, in a form that is readily comprehensible and thereby aiding their understanding and knowledge of the specific vessel. Special attention is drawn to emergency procedures and fire fighting systems. The manual consists of a number of parts and sections which describe the systems and equipment fitted and their method of operation related to a schematic diagram where applicable. . Illustrations All illustrations are referred to in the text and are located either in the text when sufficiently small or below the text on a separate page, so that both the text and illustration are accessible when the manual is laid face up. Where texts are shown with a blue colour in the manual, they can be jumped to linked page or space by clicking them. Symbols given in the manual adhere to international standards and keys to the symbols used throughout the manual are given on the symbols pages.

Notices The following notices occur throughout this manual :


WARNING

Warnings are given to draw readers attention to operations where DANGER TO LIFE OR LIMB MAY OCCUR.
CAUTION

Cautions are given to draw readers attention to operations where DAMAGE TO EQUIPMENT MAY OCCUR. (Note : Notes are given to draw readers attention to points of interest or to supply supplementary information.)

Index - Machinery System Operation Manual


PART 1 : GENERAL
1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.5a 1.5b 1.5c 1.5d 1.5e 1.5 f 1.5g General Arrangement Tank Capacity Table Principal Particulars of Hull Principal Particulars of Machinery Machinery Arrangement Glossary of Symbols Ship Speed Power Curve Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement - Tank Top Plan - 4th Deck Plan - 3rd Deck Plan - 2nd Deck Plan - Engine Casing Deck Plan - Engine Casing Deck Plan - Elevation Plan

3.1

Steam Systems
3.1.1 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 3.1.1a 3.1.2a 3.1.3a 3.1.4a 3.1.5a 3.1.6a Superheated Steam System 6.0 MPa Desuperheated Steam System Auxiliary Steam System N/A 1.0 MPa Desuperheated Steam System Exhaust and Dump Steam System Superheated Steam System 6.0 MPa Desuperheated Steam System Auxiliary Steam System N/A 1.0 MPa Desuperheated Steam System Exhaust and Dump Steam System

3.6

Fuel Oil and Fuel Gas Service Systems


3.6.1 3.6.2 3.6.3 3.6.4 3.6.5 3.6.6 3.6.7 3.6.1a 3.6.1b 3.6.2a 3.6.3a 3.6.4a 3.6.4b 3.6.5a 3.6.6a 3.6.7a Fuel Oil Bunkering System Heavy Fuel Oil Transfer System Diesel Oil and Gas Oil Transfer System Boiler Fuel Oil Service System Boiler Fuel Gas Service System Boil-off Gas System in Cargo Machinery Room Diesel Oil and Gas Oil Service System Fuel Oil Viscosity - Temperature Graph Fuel Oil Bunkering System Heavy Fuel Oil Transfer System Diesel Oil and Gas Oil Transfer System No.1 Boiler Fuel Oil Service System No.2 Boiler Fuel Oil Service System Boiler Fuel Gas Service System Boil Off Gas System in Cargo Machinery Room Diesel Oil and Gas Oil Service System

Illustrations

Illustrations

Illustrations

3.2

Condensate and Feed Water Systems


3.2.1 3.2.2 3.2.3 3.2.4 3.2.5 3.2.6 3.2.1a 3.2.1b 3.2.2a 3.2.3a 3.2.4a 3.2.5a 3.2.6a Condensate Water System Boiler Feed Water System Boiler Water Sampling and Treatment System N/A Clean Drains System Contaminated Drains System Condensate Water System Deaerator Boiler Feed Water System Boiler Water Sampling and Treatment System N/A Clean Drains System Contaminated Drains System

PART 2: MACHINERY COMMISSIONING OPERATIONAL OVERVIEW


2.1 2.2 2.3 2.4 2.5 2.6 2.7 To Bring Vessel into Live Condition To Prepare Main Plant for Operation (Raising Steam) To Prepare Main Plant for Manoeuvring from In Port Condition To Change Main Plant from Manoeuvring to Normal Conditions To Change Main Plant from Normal to Manoeuvring Conditions To Secure Plant at Finished with Engines To Secure Plant for Dry Dock

3.7

Lubricating Oil Systems


3.7.1 3.7.2 3.7.3 3.7.4 3.7.1a 3.7.2a 3.7.3a 3.7.4a Main Turbine Lubricating Oil System Lubricating Oil Purification System Lubricating Oil Filling and Transfer System Stern Tube Lubricating Oil System Main Turbine Lubricating Oil System Lubricating Oil Purification System Lubricating Oil Filling and Transfer System Stern Tube Lubricating Oil System

Illustrations

Illustrations

PART 3: SHIPS SYSTEMS


3.0 Heat Balance for Steam Turbine Plant Illustrations
3.0.1 3.0.2 3.0.3 3.0.4 3.0.5 3.0.6 3.0.7 3.0.8 3.0.9 3.0.10 3.0.11 3.0.12 3.0.13 3.0.14 100% MCR On Fuel Oil Burning (FOC Guarantee Condition) 100% MCR On Fuel Oil Burning 100% MCR On Dual Fuel Burning 100% MCR On Gas Fuel Burning Cargo Unloading Full Dump by Main Condenser Cargo Loading Full Dump by Auxiliary Condenser Hotel Load 100% MCR On Fuel Oil Burning 90% MCR On Fuel Oil Burning Half Ahead On Fuel Oil Burning Slow Ahead On Fuel Oil Burning Hotel Load

3.8 3.3 Compressed Air Systems


3.3.1 3.3.2 3.3.1a 3.3.2a Compressed Air System Starting Air System Compressed Air System Starting Air System

Engine Room Bilge Systems


3.8.1 3.8.2 3.8.1a Engine Room Bilge System Bilge Separator Engine Room Bilge System Domestic Fresh Water System Sewage Treatment System Domestic Fresh Water System Sewage Treatment System

Illustrations 3.9 Sanitary and Fresh Water Service Systems


3.9.1 3.9.2 3.9.1a 3.9.2a

Illustrations

3.4
- Winter Condition - Winter Condition - Winter Condition - Winter Condition - Winter Condition

Fresh Water Cooling Systems


3.4.1 3.4.1a Central Fresh Water Cooling System Central Fresh Water Cooling System

Illustrations

Illustrations 3.5 Sea Water Systems


3.5.1 3.5.2 3.5.1a 3.5.2a Sea Water Circulating System Cooling Sea Water Service System Sea Water Circulating System Cooling Sea Water Service System

Illustrations

Index - Machinery System Operation Manual


PART 4: MAIN MACHINERY AND CONTROL
4.1 Control Room
4.1.1 4.1.1a Machinery Control Room Overview Machinery Control Room Console

PART 5: ELECTRIC POWER GENERATING SYSTEM


5.1 5.2 5.3 5.4
5.4.1 5.4.2 5.4.3 5.4.4 5.4.5 5.4.6 5.4.7

PART 7: ENGINE ROOM BALLAST SYSTEM


7.1 7.2 7.1a 7.2a Engine Room Ballast System Ballast and Fuel Oil Valves Control System Engine Room Ballast System Ballast and Fuel Oil Valves Control System

Illustrations

Turbo Generator Diesel Generator Emergency Diesel Generator Power Distribution System
Electrical Equipment Main Switchboard and Generator Operation Shore Power Main Alternators Emergency Alternator Preferential Tripping and Sequential Restarting 24 Volt Battery and Uninterruptible Power Supply Turbo Generator Overview Turbo Generator Alternator Turbo Generator Steam and Exhaust Systems Turbo Generator Lubrication and Control Oil Systems Diesel Generator Alternator Diesel Generator Piping Systems Emergency Diesel Generator Overview Emergency Diesel Generator Alternator Emergency Diesel Generator Piping Systems

Illustrations

4.2

Main Turbine
4.2.1 4.2.2 4.2.3 4.2.4 4.2.1a 4.2.1b 4.2.1c 4.2.2a 4.2.3a 4.2.3b Main Turbine Overview Main Turbine Operation Main Turbine Control System Main Turbine Warming-up System Main Turbine Overview Main Turbine Overview Main Turbine Gear Arrangement Main Turbine Operation Main Turbine Remote Control System Main Turbine Control System

PART 8: INTEGRATED CONTROL AND AUTOMATION SYSTEM


8.1 8.2 8.3 8.1a 8.3a ICAS Overview ICAS Operator Station Operations Graphic Displays Integrated Control and Automation System Overview Machinery Part Graphic Displays

Illustrations

Illustrations
5.1a 5.1b 5.1c 5.1d 5.2a 5.2b 5.3a 5.3b 5.3c 5.4a 5.4.7a

Illustrations

PART 9: EMERGENCY PROCEDURES


9.1 9.2 9.3 9.4 9.5 9.6 9.3a Flooding in the Engine Room Steaming on One Boiler Solo Running of the Main Turbine Steaming with One Forced Draft Fan Emergency Steering Fire in the Engine Room Emergency Operation of Main Turbines

4.3

Main Boiler
4.3.1 4.3.2 4.3.3 4.3.4 4.3.1a 4.3.2a 4.3.2b 4.3.2c 4.3.2d 4.3.3a 4.3.3b 4.3.4a 4.3.4b Main Boiler Overview Main Boiler Operation Burner Characteristics Boiler Control Systems Main Boiler Overview Main Boiler Mounting System Combination Burner System Boiler Pressure Rising Charts Combustion Air, Seal Air and Flue Gas System Burner Characteristics Burner Assembly Boiler Gauge Board Automatic Combustion Control (ACC)

Power Distribution System


24 Volt Battery and Uninterruptible Power Supply

Illustrations

Illustrations

PART 6: AUXILIARY MACHINERY


6.1 Main Feed Water Pump 6.2 Distilling Plant 6.3 Incinerator 6.4 Nitrogen Generator System 6.5 Inert Gas Generator System Illustrations
6.1a 6.1b 6.1c 6.2a 6.3a 6.4a 6.5a Main Feed Water Pump Sectional View Main Feed Water Pump Turbine Sectional View Main Feed Water Pump Trip System Distilling Plant Systems Incinerator Nitrogen Generator System Inert Gas Generator System

Part 10: FIRE FIGHTING SYSTEMS


10.1 Fire Fighting Systems 10.2 Fire Detection System 10.3 Engine Room Fire Fighting Systems 10.3.1 Engine Room Fire Main System 10.3.2 Engine Room CO2 Fire Extinguishing System 10.3.3 Engine Room Hot Foam Fire Extinguishing System 10.3.4 10.3.5 10.3.1a 10.3.2a 10.3.3a 10.3.4a 10.3.5a Engine Room Local Fire Extinguishing System Quick-Closing Valves and Fire Dampers System Engine Room Fire Main System Engine Room CO2 Fire Extinguishing System Engine Room Hot Foam Fire Extinguishing System Engine Room Local Fire Extinguishing System Quick-Closing Valves and Fire Dampers System

Illustrations

PART 1 : GENERAL

1.1 1.2 1.3 1.4 1.5 1.6 1.7

General Arrangement Tank Capacity Table Principal Particulars of Hull Principal Particulars of Machinery Machinery Arrangement Glossary of Symbols Ship Speed Power Curve

Illustrations
1.5a 1.5b 1.5c 1.5d 1.5e 1.5f 1.5g Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement Machinery Arrangement - Tank Top Plan - 4th Deck Plan - 3rd Deck Plan - 2nd Deck Plan - Engine Casing Deck Plan - Engine Casing Deck Plan - Elevation Plan

1.1

General Arrangement

GENERAL ARRANGEMENT
ABT.72,000 ABOVE B.L.
COMP.BRI.DK

COMP.BRI.DECK (CENT.)

3,650
NAV. BRI. DECK AN.LT.

NAV. BRI. DECK

3,650
G-DECK

G-DECK

F-DECK

M.H.LT.

3,650
F-DECK
ST.LT

3,000
E-DECK

E-DECK

3,000
D-DECK

D-DECK

3,000
C-DECK

C-DECK

B-DECK

3,000
A-DECK
S.L. S.L.

NO. 4 TANK

CARGO MACHINERY ROOM

NO. 3 TANK
COMPRESSOR MOTOR ROOM

NO. 2 TANK
S.L.

NO. 1 TANK

3,000
B-DECK

A-DECK

4,000
AN.LT. UPPER DECK

UPPER DECK (CENT.)


STRAIGHT CAMBER 45/1000

UPPER DECK (SIDE)

NO.1 DIST.W.TK.(P) F.W.TK.(S) 2ND DECK(22,850)


NO .2 D DR IN IST. K.W W.T .TK K (P (S ) )

(P& S)

ER O.S ER D. O.S G/E D. .1 G/E NO .2 NO

FORWARD STORE
UNDER DECK PASSAGE (P & S)(22,850)
ACC. TRUNK

2,400

UNDER DECK PASSAGE (P & S)(22,850)


AIN

FORWARD STORE FLAT (22.850m)

2ND DK

F.O. SETT . TK

I.G.G.GAS OIL TK(P)

SULPH UR F.O .SIDE . TK(S) TK (P)

ER G. P. FIRE RM .

FO
BITT BITT

R'D

EM

(P &S )

STEER. ENG. FLAT (16,550) 3RD DECK(15,650)


E P.R

F.O. SID E F.O. SID TK (P) E TK (S)

W .B .T K

LOW

F.O

A.P.VOID
ER

AF T

ESCAPE TRUNK

W .B .S .T K

.T

.T

.T

L.W.L.

.S

.S

.S

W .B

W .B

W .B

4TH DECK(9,470)

NO .8

NO

L.F. W.T

OO

.T.C

TANK TOP(3,800)
B. W.
ST. T. L.O. DRAIN TK L.O. DRAIN TK (S)

ST

TANK TOP(2,500)
L.O. SUMP TK B.W.(P)
GE (S) . BIL SEP OIL TK
) .(S S.C
A

Y BA

B.W.(P) ECHO SOUND. & MAG. LOG COMP.

SE

ECHO SOUND. COMP.


B.L. B.L.

5,000

F.O.DRAIN TK (S)

.3

.2

.1

00 ,6 R2

W.B

.S.T

B.L.

DOUBLE BOTTOM PIPE PASSAGE


10,100 24,500 9,350 5,050

1,590

LO

LO

LO

.B

BILGE PRIMARY SECT. (S)

11,230

BIL

.S

OLD EH

ER

ER

ER

LO

R WE

.T

. TK

NO

NO

(S)

.6 NO

.7

.B

.5

.B

.3

.T

.4 NO

.T

NO

.2

.B

.T

.1 NO

FO R'D (P W.B &S ) .T

W . F.O RFLO OVE

.B

K.

TK

(S)

K .T .S .B W

K .T .S .B W

.S

.T

K .T .S .B W

FOR'D PUMP RM

L.W.L.

L.W.L.

L.W.L.

W.B

.TK

B.L.

0
A.P.

10

15

20

25

30

35

40

45

50

55
CLEAN DRAIN TK (S)

60

65

70

75

80

85

90

95

100

105

110

115

1,600
FRP 5,000 .S.
1,800

FRP 00 . S. 8 6,000 15,200

FRP 900 . S. 45,000

FRP 4,700 .S.

FRP 5,300 .S. 45,000

FRP 5,000 .S.

FRP 4,700 .S.

FRP 5,300 .S.

FRP 5,000 .S. 45,000

FRP 4,700 .S.

FRP 5,300 .S. 45,300

FRP 5,000 .S.

FRP 3,200 .S. 32,000


F.P.

44,700

8,000

VIEW OF BRIDGE FRONT & TANK SECTION

MAX. WORKING RADIUS ABT. 21,000

OUTREACH 4.0m FROM SHIP'S PARALLEL LINE

MAX. WORKING RADIUS ABT. 9,000

MAX. WORKING RADIUS ABT. 9,000

OUTREACH 2.0m FROM SHIP'S PARALLEL LINE MIN. WORKING RADIUS ABT. 3,000 4-R.FL. 4-R.FL. LR. (25PX2) MIN. WORKING RADIUS ABT. 4,500
E N RA D.C ) AN H 1M -2

MIN. WORKING RADIUS ABT. 3,000 E.C.FL. CAPS. B. PILOT LADD.REEL


UP

LIFE BOAT (50P) (OV.)

5T HOSE HANDRING CRANE (SWL 49kN-22M) E.C.FL. CAPS. B. DUTY MEN RM. UP UP (TO JIB REST)
DN

E.C.FL.

S.L.

E.C.FL. CAPS.

C.FL.

4-R.FL.

4-R.FL.

UPPER DECK
4-R .FL . 4-R .FL . 4-R .FL .

3T

ACCOMM. LADD. STOW. SP.

L.P.
NO OBSTRUCTIONS

L.P. B.

PR (SW OVISI L 29

B.
E AN CR ) N -9M ISIOkN OV 29 PR WL (S

V.& O PR 5T

TS kN AR 49 .P G L EN (SW

ON kN CRAN -9M E )
CAPS.
3T

UP DN

DN

HYD.M.W. A.O.

UP SECURITY GUARD HOUSE

DN

SECURITY WATCH SHELTER

UP JIB REST

B.

I.G.G. RM N2 GEN. RM
POSITION HAND.CRANE STORAGE 5T PROV.& ENG.PARTS
SAFTY EQUIP. STORE

C.P. FIRE STATION


SUEZ CANAL WORKER'S RM

B. B.

C.F L.

DN

L.O. & GREASE STORE


V. T.

5-R .FL . 5-R .FL .

AO
H.R
M

V.

T.

SUEZ CANAL WORKER'S LAV.

HYD. M.W. D.S.R. HYD. M.W.

HYD.PUMP UNIT RM DN
M

DN DN UP UP

DECK WORK SHOP

HOTEL LAUND.

FEMALE CHANG. RM. NO.2 CARGO SWBD. RM.


OFF'S CHANG. RM. CREW'S CHANG. RM.

NO. 4 TANK

NO. 3 TANK

NO. 2 TANK

NO. 1 TANK
HYD. WIND. C.C.

H.P.

DN

LINEN LKR
UP

B. L.R. EMB. (6P) LADD. HYD. M.W.

DOME LIFT 35 40 45 HATCH 50 55 AIR COND.UNIT RM & REF.PROV.MACHI.RM & UP UP UP V.T. 60


M

V.P. L.P. 75 80

DOME

V.P.
L.P.

DOME

V.P.
L.P.

DOME V.P. 105 D.S.R. D.S.R. 110

DN D.S.R. DAVIT 115 F.P. H. H.

DN 5 A.P. 10 15 20 25

30

65

70

85

90

95

PIPE PASSAGE
E.C.T. H.

WALK WAY
A.T .

D.S.R.

ELECT. CABLE PASSAGE

M.H. HYD. WIND.

UP DN DN INCINE.RM GARBAGE STR E.C.T.


COMM.LAV

C.C. H.P.

H.R

PIPE PASSAGE

PIPE PASSAGE
H.

PIPE PASSAGE
D.S.R.

WALK WAY
BATH NO.1 CARGO SWBD. RM.
V. T. V. T.

WALK WAY

WALK WAY
UP

HYD. M.W.

ELECT. CABLE PASSAGE


CHEMICAL LKR PAINT STORE UP

ELECT. CABLE PASSAGE CO2 BOTT.RM


C.P. MIN. WORKING RADIUS ABT.4,600

ELECT. CABLE PASSAGE

HYD. M.W. B. B.
L. C.F

.FL 5-R .FL .

EMERG.GENE.& EMERG.SWBD.RM.

HYD.M.W.

HOSP.

DISP.

5-R

A.O. DN UP
5T PR (S W O L 49 V.& EN -2 G 1M ) .P AR TS H AN D.C

SECURITY GUARD HOUSE


3T

CARGO MACHI.RM
DN

JIB REST UP

UP SPARE ANCHOR STOW.SPACE (TO JIB REST) UP LNG LIQUID LINE LNG LIQUID LINE DN LNG VAPOUR LINE LNG LIQUID LINE LNG LIQUID LINE UP B. CAPS. DUTY MEN RM. E.C.FL. L.P. CAPS. S.L. E.C.FL. C.FL. 4-R.FL. 4-R.FL. B.
. .FL 4-R

&
UP

DN

B.
. .FL 4-R . .FL 4-R

PRO (SW VISION L 29k CRAN N-9 E M)

MOTOR RM (OVER)
UP
NO OBSTRUCTIONS

MIN. WORKING RADIUS ABT. 4,500

kN

UP LR. (25PX2)
RA N E( O

UP UP B.

ACCOMM. LADD. STOW. SP. CAPS. LIFE/RESCUE BOAT (50P) (OV.) B. E.C.FL.

CAPS.

3,500

UP PILOT LADD.REEL

5-R.FL.

M.P.

T.B.

5-R.FL.

R.PL. UP

. FL C.

DECK STORE

4-R.FL. V.)

4-R.FL.

E.C.FL. OUTREACH 2.0m FROM SHIP'S PARALLEL LINE

PRINCIPAL PARTICULARS
ABT.288.0 m LENGTH (O.A.) 274.00 m LENGTH (B.P.) 49.00 m BREADTH (MLD) 26.80 m DEPTH (MLD) 11.25 m DRAUGHT (MLD)(DESIGNED) 12.30 m DRAUGHT (MLD)(SCANTLING) ABT. 71,200 t DEADWEIGHT (d = 11.25m) ABT. 123000 GROSS TONNAGE MHI STEAM TURBINE X 1 MAIN ENGINE
CAPTAN CLASS

COMPLEMENT
2 P. 4 P. 5 P. 3 P. 16 P.

MAX. WORKING RADIUS ABT. 21,000

OUTREACH 4.0m

FROM SHIP'S PARALLEL LINE

TUG

MIN. WORKING RADIUS ABT. 3,000

TUG
MAX. WORKING RADIUS ABT. 9,000

TUG

3,000
abt. 11,800

3,000

3,000

3,000

TUG

TUG

5T HOSE HANDRING CRANE (SWL 49kN-22M)

SENIOR OFFICER CLASS JUNIOR OFFICER CLASS PETTY OFFICER CLASS RATING CREW CLASS

MAX. WORKING RADIUS ABT.22,000

PILOT(JUNIOR OFFICER CLASS)(1P x 1RM) LOADING MASTER(JUNIOR OFFICER CLASS)(1P x 1RM) OFFICER SPARE(JUNIOR OFFICER CLASS)(1P x 6RMS) CREW SPARE(CREW CLASS)(1P X 1RM)

22,850

ENGINE ROOM

F. P. VO ID

5,580

EM

26,800

BITT

ACC.TRUNK

G.FIR

M.

CH

STEER.GEAR ROOM

D.O.STOR.TK.(S) D.O.STRO.TK.(P)

F.O

.TK

(C

B.W.

LK

ABT. 1,075

) (S TK R. TO O.S L.

L. O.R EN OV. TK (O UT) (S )

3,950

) .(S ) TK V. TK.(S V.

UNDER DECK PASSAGE

UNDER DECK PASSAGE

HAND.CRANE 5T PROV.& ENG.PARTS

STORAGE POSITION

1 P. 1 P. 6 P. 1 P. 39 P. 6 P.

MCR 23,600 kW x 80 rpm SPEED (SERVICE SPEED) ABT.

19.5 kn

AFT MOORING DECK

2ND DECK
(P)
N.) (U
E.T K. (P )

BOTTOM PLAN

BOTTOM PLAN

FORWARD STORE

CLASS Lloyd's Register of Shipping +100A1 Liquefied gas carrier, Ship Type 2G, Methane in independent spherical tanks type B, Maximum vapour pressure 0.25 bar G at sea Minimum cargo temperature -163C Maximum cargo density 500kg/m3 ShipRight(SDA), Ice Class 1B FS(hull), *IWS, LI, +LMC, UMS, ICC, NAV1, IBS,EP with the descriptive notes"ShipRight(FDA,CM,SCM,TCM, BWMP) Russian Maritime Register Ice Class LU2(propeller and shaft)

GRAND TOTAL
SUEZ CANAL WORKERS (CREW CLASS) (6P x 1RM)

CARGO TANK CAPACITY


CARGO TANKS (98.5%full, -163C, atmospheric pressure,excluding dome space) NO.1 CARGO TANK NO.2 CARGO TANK NO.3 CARGO TANK NO.4 CARGO TANK TOTAL CARGO TANK CAPACITY ABT. 36,250 m3 ABT. 36,250 m3 ABT. 36,250 m3 ABT. 36,250 m3 ABT. 145,000 m3

TT .TK.

K.

.B

TK. AF T W

F.O. SE

F.

O.S

.T

ID

DN
.FL. 4-R .FL. 4-R

OIL

(P )

I. G. G. RM.

D.O .S TO R.T K.

COFF

GAS

C.F

L.

UP

.S .T

C.F

L.

5-R

.FL

K(P

5-R

.FL

I.G.G.

UP

.7 NO

) K(P .T .S W.B

. (U N.)

NO.6

W.B

.S.T

K(P)

.5 NO

) K(P .T .S W.B

NO.4

W.B

.S.T

K(P)

.3 NO

) K(P .T .S W.B

NO.2

W.B

.S

P) .TK(

(P) S.TK W.B. NO.1


M.H.

.TK

DIS T.W .TK

.W

DIST

NO .2

UP

C.F

L.

B.

NO

.1

4-R

.FL

NO

4-R

.FL

.8

V.

T.

V.

T.

B.

LABORATORY

FO

R'D

W.B

.B

.T

K.

(P

DECK HEIGHT
UPPER DECK A-DECK B-DECK C-DECK D-DECK E-DECK F-DECK G-DECK NAV.BRI.DECK SHEER CAMBER
M.H.

ELECTRICAL & INSTR.WORK SHOP


UP UP

NO.2 F.O. HEATING RM

NO. 4 TANK
NO.2 SWBD.RM.

NO. 3 TANK

NO. 2 TANK

NO. 1 TANK
M.H.

HYD.M.W. B.
UP UP

C.LKR
M.H.

UP

HYD.M.W.

DN

FO R'D

SP AC E

.B.T

.B.T

.B.T

LI FT

DN

V.

FAIRLEAD & STRONGPOINT

STORAGE DRUM UP A.P. STORAGE BOX 5 10 15 20


BOG PIPE HOOD

E.F .P .R M .

STORAGE DRUM
M.H.

FOR'D PUMP RM
110
LIFTING SPACE

UP

DN
T.

RW

RW

DN

30

35

40

45

50

WE

LO

LO

.3

.2

.1

LO

MACHINERY CONTROL ROOM


DN

WE

WE

A.

T LIF 60

RW

M.H.

EMERG.TOW.CHAIN STOW. SP. F.P.

65

70

75

80

85

90

95

100

105

115
F.W.R.

NO

NO

NO

UP

FT

DN

T.

COFF.

FOR'D ELECT. RM.

A-DECK B-DECK C-DECK D-DECK E-DECK F-DECK G-DECK NAV.BRI.DECK COMP.BRI.DECK


NIL

4.00 m 3.00 m 3.00 m 3.00 m 3.00 m 3.00 m 3.65 m 3.65 m 3.65 m


45/1000 20/1000 15/1000

DN

SP

R.H.

A.

LI

T.

F.O .T K. (C )

NO.1 SWBD.RM.

C.LKR

DN

B. HYD.M.W.

NO.1 F.O. HEATING RM


UP

UP UP

UPPER DECK ABT. 1,075mm at C.L. AFT MOOR. DECK 417mm at C.L. A-DECK & ABOVE HELI. WINCHING DECK WEATHER DECK

W .B .T K. (S )

.FL

IN

4-R

F.W .T K

L.

B.

K.W

C.F

INSIDE NIL 15/1000FORE) (

.T

4-R

.FL

DR

.
B.

ACE. BOTT. ROOM

L.

.TK

C.F

F.O

ENG. WORK SHOP


HATCH

L.
4-R .FL. 4-R

SULP

SE TT

C.F

HUR

V.

F.O

5-R

.FL

UP

.TK. (S)

. TK .1 G/E RV NO . SE D.O

.S ID

5-R

.FL

L.O

.S

TO

E.T K.( S

OXY. BOTT. ROOM

R.T

K.

. .2 G/E NO . SERV D.O

TK

M.H.

L.O .R AF EN OV T W .T K. .B .T K. (U N.)

TK

.FL.

.8 NO

K .S.T W.B

D.O

.S

TO

(S)

.7 NO

) K(S .T .S W.B

LOW

NO.6

W.B

R.

.S.T

K(S)

.5 NO

) K(S .T .S W.B

NO.4

W.B

.S.T

K(S)

.3 NO

) K(S .T .S W.B

.(S

F.O.

NO.2

W.B

.S.T

K(S)

.B.S .1 W NO

(S) .TK

FO R'D

V.

T.

V.

T.

1.2

Tank Capacity Table


Low Sulpher Fuel Oil Tanks (S.G. = 0.870)
Center of Gravity 98.8% Full (163) Excluding Dome (m3) 36,250.000 36,250.000 36,250.000 36,250.000 145,000.000 NAME 100% Full AP G(m) 219.5 174.5 129.5 84.5 KG (m) 23.39 23.39 23.39 23.39 LOW F.O.T. SULPHER TOTAL ITEM Side C Position FR. NO. 64 - 69 100% Full (m3) 485.6 485.6 Capacity 90% Full (m3) L.F.O.(t) 437.0 437.0 380 380 Center of Gravity 100% Full AP G (m) KG (m) 57.95 17.48 MT of I (Max. F.S.) (m4) 392 392 Capacity 100% Full 100% Full 100% Full (163) (160) (163) Excluding Including Dome Including Dome Dome (m3) (m3) (m3)

Cargo Tanks (preliminary) (S.G. = 0.470)


ITEM NAME Side NO.1 CARGO TANK C NO.2 CARGO TANK C NO.3 CARGO TANK C NO.4 CARGO TANK C TOTAL FR. NO. 97.39 - 105.65 88.35 - 96.69 79.39 - 87.65 70.35 - 78.69 Position

Diesel Oil Tanks (S.G. = 0.920)


ITEM NAME D.O.T. D.O.T. G/E D.O. SERV. T. Side P S S TOTAL Position FR. NO. 49 54 49 54 49 54 100% Full (m3) 156.0 101.5 54.6 312.1 Capacity 90% Full (m3) D.O.(t) 140.4 129 91.4 84 *1 48.9 45 280.7 258 Center of Gravity MT of I 100% Full (Max. F.S.) AP G (m) KG (m) (m4) 44.45 24.58 392 44.45 24.54 115 44.45 24.65 15 522

Water Ballast Tanks (S.G. = 1.025)


ITEM NAME Side FOR'D W.B.T. P FOR'D W.B.T. S NO.1 W.B.S.T. P NO.1 W.B.S.T. S NO.2 W.B.S.T. P NO.2 W.B.S.T. S NO.3 W.B.S.T. P NO.3 W.B.S.T. S NO.4 W.B.S.T. P NO.4 W.B.S.T. S NO.5 W.B.S.T. P NO.5 W.B.S.T. S NO.6 W.B.S.T. P NO.6 W.B.S.T. S NO.7 W.B.S.T. P NO.7 W.B.S.T. S NO.8 W.B.S.T. P NO.8 W.B.S.T. S NO.1 LOWER W.B.T. C NO.2 LOWER W.B.T. C NO.3 LOWER W.B.T. C AFT W.B.T. P AFT W.B.T. S TOTAL Position FR. NO. 106 - 110 106 - 110 100 - 106 100 - 106 94 - 100 94 - 100 91 - 94 91 - 94 85 - 91 85 - 91 82 - 85 82 - 85 76 - 82 76 - 82 73 - 76 73 - 76 69 - 73 69 - 73 96 - 98 87 - 89 78 - 80 42 - 54 42 - 54 (m3) 2,616.9 2,633.5 2,687.4 2,687.4 3,251.0 3,251.0 1,802.4 1,802.4 3,668.7 3,668.7 1,835.3 1,835.3 3,624.3 3,624.3 1,648.2 1,648.2 3,633.6 3,633.6 1,675.2 1,674.3 1,675.2 1,493.9 1,493.9 57,564.7 Capacity 100% Full S.W.(t) AP G (m) 2,682 247.80 2,699 247.77 2,755 228.77 2,755 228.77 3,332 196.42 3,332 196.42 1,847 174.46 1,847 174.46 3,760 151.99 3,760 151.99 1,881 129.50 1,881 129.50 3,715 107.11 3,715 107.11 1,689 84.67 1,689 84.67 3,724 67.38 3,724 67.38 1,717 196.99 1,716 152.00 1,717 106.99 1,,531 41.47 1,531 41.47 58,999 KG (m) 12.58 12.56 12.57 12.57 9.05 9.05 8.06 8.06 7.95 7.95 7.94 7.94 8.03 8.03 8.65 8.65 10.56 10.56 6.47 6.47 6.47 16.63 16.63 MT of I (Max. F.S.) (m4) 3,215 3,251 2,136 2,136 1,914 1,914 1,287 1,287 2,576 2,576 1,288 1,288 2,574 2,574 1,163 1,163 4,699 4,699 5,362 5,362 5,362 1,416 1,416 60,658

*189.6 % FULL (OVERFLOW LEVEL)

This section will be rectified after completion of the test.


ITEM Position NAME I.G.G. GAS OIL T. Side P TOTAL FR. NO. 45 - 49 100% Full (m3) 124.8 124.8

I.G.G. Gas Oil Tank (S.G. = 0.870)

Capacity 90% Full (m3) G.O.(t) 112.3 98 112.3 98

Center of Gravity MT of I 100% Full (Max. F.S.) AP G (m) KG (m) (m4) 40.40 24.58 314 314

Fresh Water Tanks (S.G. = 1.000)


Tank Side S S P P SUM ATH TOTAL

Position

NO.1 FRESH W. T. NO.2 FRESH W. T. NO.1 DIST. W.T. NO.2 DIST. W.T. ST. T.C.F.W.T.

FR. NO. 14 - 19 9 - 14 14 - 19 9 - 14 19

(m3)

10.38

204.9 164.2 204.9 164.2 738.2 57.6 795.8

Capacity 100% Full F.W. (t) AP G (m) 205 13.26 164 9.28 205 13.26 164 9.28 738 58 13.09 796

MT of I (Max. F.S.) KG (m) (m4) 19.92 229 19.99 134 19.92 229 19.99 134 726 4.67 10 736

Lubricating Oil Tanks (S.G. = 0.880)


Tank L.O. STOR. T. L.O. RENOV. T. L.O. GRAVITY T. S/T L.O. SUMP T. L.O. DRAIN T. L.O. SUMP T. Side S S S C C C TOTAL Position FR. NO. 45 - 48 42 - 45 55 - 59 27 - 29 39 - 41 36 - 43 Capacity (m3) 56.1 56.1 40.4 4.8 3.9 57.4 218.7 Center of Gravity 100% Full AP G (m) KG (m) 39.95 37.25 49.40 23.30 34.10 33.80 MT of I (Max. F.S.) (m4) 24.62 24.62 17.65 3.00 3.15 2.69 47 47 7 1 1 49 152

Fuel Oil Tanks (S.G. = 0.950)


ITEM NAME FORD F.O.T. F.O. SIDE T. F.O. SIDE T. NO.1 F.O. SETT. T. NO.2 F.O. SETT. T. SUM F.O. OVERFLOW T. S F.O. DRAIN T. S TOTAL Side C P S S S Position FR. NO. 106 - 110 54 - 69 54 - 69 59 - 64 54 - 59 64 - 69 64 - 66 100% Full (m3) 1,262.5 2,152.4 865.2 350.1 333.9 4,964.1 117.0 3.0 5,084.1 Capacity 90% Full (m3) F.O.(t) 1,136.3 1,079 1,937.2 1,840 778.7 740 315.1 299 300.5 285 4,467.8 4,243 105.3 100 2.7 3 4,575.8 4,346 Center of Gravity 100% Full AP G (m) KG (m) 248.63 19.25 53.60 17.75 52.40 17.73 53.45 19.28 49.04 19.03 57.97 10.80 56.60 2.00 MT of I (Max. F.S.) (m4) 3,171 1,176 651 79 79 5,156 392 1 5,549

Other Tanks
Tank BILGE HOLD T. BILGE PRIMARY S SECTION DECK WASH T. P SEP. BILGE OIL T. S CLEAN DRAIN T. P TOTAL Side S Position FR. NO. 54 - 64 54 54 55 58 59 69 59 63 Capacity (m3) 240.9 19.2 446.2 15.1 44.6 766.0 Center of Gravity 100% Full AP G (m) KG (m) 51.86 7.48 48.95 54.27 49.40 52.78 8.62 7.44 1.25 1.07 MT of I (Max. F.S.) (m4) 528 6 1,226 1 50 1,811

1.3

Principal Particulars of Hull


5. CAPACITY S.NO.2229GRAND ELENA S.NO.2230GRAND ARIVA Cargo Capacity Cargo tank including dome space (at cryogenic temperature = -163) Cargo tank excluding dome space (at cryogenic temperature = -163) Tank Capacity Water Ballast Fresh Water (excluding ST.T.C.F.W.T.) Fuel Oil (Including Low Sulphur F.O. tank, excluding F.O. Overflow tank and F.O. Drain ank) Diesel Oil I.G.G. Gas Oil 6. SPEED Trial max. Service Delivery S.NO.2229 January 15th, 2006 (preliminary) S.NO.2230 March 15th, 2006 (preliminary) p.p. : 274.00 m * : preliminary abt. 19.5 knots on the designed draught at 100% MCR of main engine with 21% sea margin 100 % 100 % 98.5 % 100 % 100 % 100 % 100 % 100 % * 147,208.122 m3 * 147,208.122 m3 * 145,000.000 m3 54,600 m3 795.8 m3 4,800 m3 370 m3 200 m3 S.NO.2229NYK-SCF LNG SHIPPING No.1 LTD S.NO.2230NYK-SCF LNG SHIPPING No.2 LTD Lloyds Register of Shipping +1A1 Liquefied Gas Carrier, Ship Type 2G, Methane in independent spherical tanks type B, Maximum vapour pressure 0.25 barG at sea Minimum cargo temperature -163 Maximum cargo density 500 kg/m3 ShipRight (SDA), Ice Class 1B FS (hull), *IWS, LI, +LMC, UMS, SCM with the descriptive notes ShipRight (FDA, CM,SERS, SCM,TCM, BWMP(S)) pt higher tensile steel, ETA Russian Maritime Register Ice Class LU2 (propeller and shaft) Port OSLO Official Number S.NO.2229 S.NO.2230 Launching S.NO.2229 February 4th, 2005 S.NO.2230 May 20th, 2005 Call Letter S.NO.2229 S.NO.2230

1. GENERAL Ships Name Owner Classification

Registration

Date

Keel Laying

S.NO.2229 August 17th, 2004 S.NO.2230 November 29th, 2004 2. PRINCIPAL DIMENSION Length Breadth Depth Design Draught Summer Draught Scantling Draught Normal Ballast Draught Heavy Ballast Draught Gross Tonnage Net Tonnage 4. DEADWEIGHT At Summer Draft o.a. mld. mld. mld. mld. mld. mld. mld. : : : : : : :

: abt.288.00 m 49.00 m 26.80 m 11.25 m 12.30 m 9.20 m 9.80 m

12.30 m

This section will be rectified after completion of the test.

3. TONNAGE (International, 1969) *abt.123,000

*abt.71,200 metric tons

1.4

Principal Particulars of Machinery


1. Main Turbine
PARTICULARS Type & Number DESCRIPTION Impulse, reaction, two cylinders, cross-compounded marine steam turbine with articulated type double reduction type gear Mitsubishi MS36-2 1 set MCR (=NR) : 23,600kW (32,090PS)~ 80.0 rpm Astern Turbine: Output (Reference) abt. 8,100kw Operating conditions : For a period of 2 hours continuous running at 70 % of the max. ahead revolution (56.0 rpm) Design torque : 80 % of the max. ahead torque at 50 % of the max. ahead revolution ( 40.0 rpm) 5.88MPaG (60kg/cm2g)~ 510 Planetary gear type : 11kW ~ at Ahead stop valve inlet 1,800rpm

Abbreviation List MCR NR S.W. F.W. L.O. F.O. D.O. G.S. K. D.P. TH M/T T/G D/G E/G IGG M.D. H. V. G. S. C. P. F.A. B.P. S. & T. D.D. T. CCS ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... ........................... Maximum Continuous Rating Normal Rating Sea Water Fresh Water Lubrication Oil Fuel Oil Diesel Oil General Service kg/cm2G Delivery Pressure Total Head Main Turbine Turbo Generator Diesel Generator Emergency Generator Inert Gas Generator Motor Driven Horizontal Vertical Gear Screw Centrifugal Piston Free Air Back Pressure Shell and Tube Type Diesel Driven Turbo Central Cooling System

Shaft Horsepower & Revolution Astern Turbine

Steam Conditions Turning Motor Vacuum Remarks

5.1kPaA (722mmHgV) at MCR (Sea water temperature=27 ) Main condenser : Scoop / pump cooling

2. Main Boiler
PARTICULARS Type & Number DESCRIPTION Two-drum, water tube marine boiler with dual fuel burners Mitsubishi MB-3E 2 sets 6.0MPaG (61.5kg/cm2g)~ 515 : : : Maximum flow Temperature up Maximum MCR at MCR condition

Steam Conditions at Superheater Outlet Evaporation (per each set) Internal Desuperheater Air Heater Economizer Ambient Room Temp Feed Water Temp. Fuel Oil

55,000 kg/h 47,200 kg/h (at gas burning) 46,600 kg/h (at oil burning) : 38,000 kg/h limit at max. steam flow : 350

Steam heating type Extended surface type 50 145 at Forced draught fan suction at Economizer inlet

RMH55 as specified in ISO 8217:1996

1.4

Principal Particulars of Machinery


3. Shafting
PARTICULARS Thrust Shaft Intermediate Shaft No.1 Intermediate shaft No.2 Intermediate shaft Propeller Shaft Stern Tube Stern Tube Sealing DESCRIPTION Located on aft of the main reduction gear 1 set PARTICULARS Main Turbo Turbine Generator Set
NO.

5. Electric Generating Set


2 TYPE 6-stage impulse, condensing turbine with single reduction CAPACITY NOTES Steam condition:: 5.88MPaG~ 510 , Exhaust condition: 6.7kPaA (710mmHgV) abt. 2,250kw at atmospheric back pressure

Mitsubishi AT42CT-B
abt. 600 mm ~ abt. 600 mm ~ abt. 880 mm ~ abt. 5,600 mm in length abt.11,800 mm in length abt.11,960 mm in length Main Diesel Generator Set Diesel 2 Generator 2 AC 6.6kV 3 phase, 60Hz, totally enclosed, brushless marine type 4,000 kVA (3,200 kW) 1,800rpm 1,690 kw 720 rpm 2,000 kVA (1,600 kW) 720 rpm 768 kW 1,800rpm 787.5 kVA (630 kW) 1,800rpm

Taiyo HPW 65B-4


Fabricated steel welded construction with oil lubricating bearing of white metal facing (WJ-2) Air seal type Generator 2 Four cycle single acting turbo-charged trunk piston type Yanmar 6EY26L AC 6.6kV 3 phase, 60Hz, totally enclosed, brushless marine type

Taiyo HPW 558C-10

4. Propeller
PARTICULARS Type, Material & Number Diameter Pitch Area (Expandedj DESCRIPTION Six (6) blades, solid wet-fit keyless type, of Nickel aluminium bronze 1 set 8,800mm 7,770mm 41.0 m2

Emergency Generator Set

Diesel

Four cycle radiator cooled type

STX KTA38DMGE
Generator 1 AC 450V 3 phase, 60Hz, totally enclosed, brushless marine type

Taiyo HPW 558C-10

1.4

Principal Particulars of Machinery


6. Pump for Fresh Water Handling
PARTICULARS Main condensate pump Drain pump Main feed water pump Cold start feed water pump Main condenser vacuum pump Central cooling fresh water pump Cargo mach. Cooling F.W. boost pump Fresh water pump Drink water pump Fire fighting fresh water pump Hot water circulating pump W/H & CCR unit cooler F.W. boost pump D/G cooling fresh water pump Dist. plant circ. water pump Dist water tank recirc. pump Fresh water tank recirc. pump Drink. water tank recirc. pump NO. 2 3 2 1 2 2 2 2 2 1 2 1 2 2 1 1 1 TYPE M.D.V.C. M.D.V.C. T.D.H.C. M.D.H.C. M.D.H.C. M.D.V.C. M.D.H.C. M.D.V.C. M.D.V.C. M.D.H.C. M.D.H.C. M.D.H.C. M.D.H.C. M.D.V.C. Diaphragm Diaphragm Diaphragm CAPACITY m /h ~ 90 ~ 45 ~
3

7. Pump for Sea Water Handling


MOTOR kW ~ rpm 45 ~ 1,800 22 ~ 1,800 PARTICULARS Main circulating pump Auxiliary circulating pump Main cooling S.W. pump 22 ~ 22 ~ 55 ~ 5.5 ~ 11 ~ 5.5 ~ 7.5 ~ 1.5 ~ 5.5 ~ 7.5 ~ 7.5 ~ 3,600 1,800 1,800 1,800 1,800 3,600 3,600 3,600 1,800 1,800 1,200 Diesel generator cooling S.W. pump Water ballast Pump Water spray pump Main circulating pump Bilge & G.S. pump Fire & bilge pump Fire pump Eductor driving. & IGG cooling S.W. pump Engine room bilge pump Sewage discharge pump Distilling plant cooling S.W. pump Fire line pressurizing pump Bilge sep. service pump NO. 1 1 2 2 3 1 1 1 1 1 1 1 1 2 1 1 TYPE M.D.V.C. M.D.V.C. M.D.V.C M.D.V.C M.D.V.C. M.D.V.C. M.D.V.C. M.D.V.C. M.D.V.C. M.D.V.C. M.D.V.C. M.D.H.P M.D.V.C M.D.V.C. M.D.H.C M.D.H Snake CAPACITY m /h ~ mTH 5,000/2,600 X 3/6 5,000/2,600 X 3/6 650~ 20 200~ 25 2,800~ 35 1,050~ 100 5,000/2,600~ 3/6 255~ 35 (88~ 50) 170/255 ~ 100/35 (88 ~ 50) 170~ 100 1,000~ 40 5~ 4~ 40 20 With self-priming With self-priming
3

mTH 85 70

NOTES

NOTES

MOTOR kW ~ rpm 80~ 360 80~ 360 55~ 1,800 22~ 1,800 375~ 1200 420 ~ 1,800 80~ 360 45~ 1,800 100/30~ 1,800/1,200 100~ 1,800 185~ 1,800 1.5~ 1,200 1.5~ 3,600 30~ 1,800 11~ 3,600 1.5~ 1,200

140~ 7.84 Mpa D.P. 5~ 2.45MPa.D.P. 5.1 kPaA (722 mmHgV) 600 ~ 55 ~ 10 ~ 5 ~ 5 ~ 5 ~ 55 ~ 90 ~ 130 ~ 3 ~ 3 ~ 3 ~ 22 20 65 65 110 15 20 20 10 Pneumatic Pneumatic Pneumatic

105~ 50 13~ 100 5~ 0.343 MPa D.P

70 (max) 70 (max) 70 (max)

1.4

Principal Particulars of Machinery


8. Pump for Lub. Oil & Fuel Oil Handling
PARTICULARS Main L.O. pump Auxiliary L.O. pump. Control oil pump Stern tube L.O. pump L.O. transfer pump L.O. purifier feed pump T/G main L.O. pump T/G L.O. priming pump D/G main L.O. pump D/G L.O. priming pump F.O. burning pump Heavy F.O. transfer pump Diesel oil transfer pump Waste oil transfer pump NO. 1 2 2 2 1 1 2 2 2 2 4 1 1 1 TYPE M/T D.V.G. M.D.V.C. M.D.H. Vane M.D.H.G. M.D.H.G M.D.H.G. G/T D.V.G. M.D.H.G. G/E D.V.G. M.D.V.G. M.D.H.S. M.D.V.G. M.D.H.G. M.D.H. Snake CAPACITY m /h ~ Mpa D.P. 150~ 0.294 150~ 0.294 2.4~ 1.47 1~ 0.196 1~ 0.294 3.1~ 0.294 24~ 0.6 9~ 0.2 40~ 0.9 7.5~ 0.15 5.0~ 2.74 50~ 0.294 10~ 0.294 10~ 0.392 2.2~ 1,800 15~ 1,800 18.5~ 1,200 3.7~ 1,200 5.5~ 1,200 Engine room supply fan Engine room exhaust fan F.O. pump room exhaust fan F.O. heating room exhaust fan Gland exhaust fan Vent duct exhaust fan Boiler flame eye seal air fan Waste oil settling tank exhaust fan W/S welding space exhaust fan 4 2 2 2 1 2 2 1 1 M.D.V. Axial M.D.V. Axial M.D.V. Axial M.D.V. Axial M.D.H.C M.D.H.C M.D.H.C M.D.H.C M.D.V. Axial PARTICULARS Forced draught fan NO. 2 TYPE M.D.H.C. 3.7~ 1,800
3

9. Air Compressor and Air Reservoir


MOTOR kW ~ rpm PARTICULARS Air compressor NO. 3 2 1 2 1 1 2 1 1 4 TYPE M.D. screw
M.D.H.P 2 stage

NOTES

CAPACITY m /h ~ Mpa D.P. 550~ 0.9 20~ 5~ 2.45 2.45


3

NOTES F.W. cooled Oil injection Air cooled Air cooled


Dew point -40 at atmos.

MOTOR kW ~ rpm 75~ 1,800 5.5~ 1,800 abt.2 PS

Submerged

37~ 3,600 2.2~ 1,800 0.75~ 1,200 0.75~ 1,200 1.5~ 1,200

D/G starting air compressor E/G starting air compressor Control air dryer Control air receiver General service air receiver D/G. starting air receiver E/G starting air receiver Nitrogen buffer tank Air press. lighting system air receiver

D.D.H. Duplex adsorption Cylindrical. Cylindrical. Cylindrical. Cylindrical. Cylindrical. Cylindrical.

400 Nm3/h 5 ~ 5 ~ 0.5~ 0.2 ~ 10 ~ 0.1 ~ 0.9 0.9 2.45 2.45 0.9 0.9

10. Fan
CAPACITY m /min ~ mmAq 950/1,110/1,900 ~ 500/650/500 1,650~ 50 1,800~ 15 100~ 40 50~ 40 100~ 40 7~ 300 50~ 150 4~ 900 10~ 150 20~ 20 No.1 No.2
3

NOTES

MOTOR kW ~ rpm 130/300/300 ~ 900/1,200/1,200 30~ 900 18.5~ 900 1.5~ 1,800 1.5~ 1,800 1.5~ 3,600 3.7~ 3,600 3.7~ 3,600 1.5~ 3,600 0.2~ 1,800

No1 is reversible

1.4

Principal Particulars of Machinery


11. Miscellaneous Machinery
PARTICULARS Distilling plant NO. 2 TYPE Plate type 1.5 ppm M.D.C. Total discharge Automatic discharge type
Sludge & solid waste disposal Ultraviolet Silver ion

12. Engine Workshop Machinery


NOTES MOTOR kW ~ rpm PARTICULARS
Lathe

CAPACITY 45 T/D

NO. 1 1

TYPE M.D. M.D.

CAPACITY C.D. : 2,000mm C.H. : 300mm Boring: Max. dia.: 32mm Milling: Table size : 800mm x 220mm Max. dia : 50mm Wheel dia.: 300mm 3-O2, 2-C2H2 200A

NOTES

MOTOR kW ~ rpm 5.5~ 900 5.5~ 1,800

1-S.W. cooled (S.W. Temp:30 ) 1-condens.cooled 5.5~ 1,800

L.O. purifier

3.1m3/h 5 m3/h (15ppm) 1,465 MJ/h (350 Mcal / h) 5 m3/h 90 T/D 2-Mineral

Combination Boling / milling Machine

Bilge separator

Pedestal drilling machine Pedestal grinder Gas welder

1 1 1 1 1 1 1

M.D. M.D. 2 wheels Acetylene D.C. arc

0.75~ 1,800 1.5~ 1,800

Incinerator Sterilizer Sterilizer Mineral injection unit Boiler water management system Chlorinator Sewage unit Unit cooler for switchboard room Unit cooler for mach. control room Unit cooler for instrument.& electric. workshop Unit cooler for engine workshop Unit cooler for laboratory Engine room heater N2 generator

1 1 1 1 1 1 1 2 2 1

0.75~ 1,800 11~ 1,800

Electric welder Plasma arc welder Electric hoist

Naltrack 3000HP

M.D. hoist Electrolyze

0.95ton Injection rate 0.2 ppm

For work shop

1.5~ 1,800

Electrolyze

Injection rate 0.2 ppm 40 persons 100% capacity for each room 100% capacity 100% capacity

Chlorinator

Packaged Packaged Packaged

P 1 2 2

Packaged Packaged Steam heating Membrane

100% capacity 100% capacity 890kW 60 Nm3/h

1.4

Principal Particulars of Machinery


13. Heat Exchanger 14. Tank for L.O. Handling
PARTICULARS Main condenser Auxiliary condenser 1st stage feed water heater Deaerator feed water heater 3rd stage feed water heater Gland condenser CCS F.W. cooler Drain cooler L.O. cooler Stern tube L.O. cooler Hot water heater Boiler fuel oil heater Purifier L.O. heater D/G cooling fresh water cooler Stern tube L.O. fresh water heater Hydrant heater NO. 1 1 1 1 1 1 2 1 2 1 1 4 1 2 1 1 TYPE Vacuum type H.S. & T. Atmos. type H.S. & T. H.S. & T. Direct contact H.S. & T. H.S. & T. Plate H.S. & T. H.S. & T. H.S. & T. Electric & steam heating Steam heating Steam heating Plate Steam heating Steam heating 5 m3/h (20 to 80 ) 5.0 m3/h (60 to 150 ) 3.1 m3/h (40 to 85 ) F.W. 37 2.0 m3/h (0 to 10 ) 200 m3/h (0 to 10 ) 16~ 1.2
Storage 360 liter

14. Tank for L.O. Handling


REMARKS S.W. 27 S.W. 32 C.W. 75 PARTICULARS L.O. sump tank L.O. gravity tank L.O. storage tank L.O. renovating tank Control oil tank NO. 1 1 1 1 1 1 1 1 1 1 1 1 1 CAPACITY Storage: abt. 40 m3 Normal : 15 m3 abt.20 m3 abt.60 m3 abt.60 m3 0.5 m3 1.5 m3 0.015 m3 0.18 m3 5.0 m3 5.0 m3 5.0 m3 5.0 m3 0.4 m3 H.R. 0.2m2/m3 H.R. 0.2m2/m3 In double bottom H.R. 0.2m2/m3 H.R. 0.2m2/m3 HEATING COIL Fitted
(Around suction pipe)

CAPACITY 5.1 kPaA

TUBE O.D.~ t. 19~ 0.7 19~ 0.7 19~ 1.2

REMARKS In double bottom Hull construction Hull construction Hull construction


Attached on M/T

Storage capacity: 22.5 m3

F.W. 37 16~ 1.2 Each 100% cap. S.W. 32 F.W. 37 Each 100% cap. S.W. 27 F.W. 37 With 2~ 20 kW electric heater Each 100% capacity of a boiler

Stern tube L.O. drain tank Stern tube FWD seal oil tank Stern tube AFT seal oil tank Aux. turbine L.O storage tank Aux. turbine L.O. renovating tank Gen. engine L.O. storage tank Gen. engine L.O. renovating tank L.O. sludge tank

In double bottom

Each 100% cap S.W. 30

1.4

Principal Particulars of Machinery


15. Tank for F.O. Handling
PARTICULARS Forward F.O. tank F.O. side tank F.O. settling tank Low sulphur F.O. tank D.O. storage tank Gen. engine D.O. service tank E/G engine D.O. service tank Incinerator D.O. service tank F.O. overflow tank IGG gas oil tank Waste oil settling tank F.O. drain tank F.O. additive tank NO. 1 2 2 1 2 2 1 1 1 1 2 1 1 CAPACITY abt. 1,200 m3 Total abt. 3,000 m3 Total abt. 1,000 m3 Total abt. 600 m3 abt. 370 m3 Total abt. 50 m3 3 m3 1 m3 abt. 75 m3 abt. 100 m3 1 m3 2 m3 4 m3 HEATING COIL H.R. 0.06m2/m3 H.R. 0.06m2/m3 H.R. 0.1m2/m3 H.R. 0.06m2/m3 H.R. 0.1m2/m3 H.R. 0.1m2/m3 H.R. 0.1m2/m3 H.R. 0.1m2/m3 H.R. 0.12m2/m3 H.R. 0.1m2/m3 H.R. 0.6m2/m3 H.R. 0.1m2/m3 In double bottom Hull construction Hull construction REMARKS Hull construction Hull construction Hull construction Hull construction Hull construction Hull construction Hull construction PARTICULARS Fresh water tank Drink. Water tank Distilled water tank Drain inspection tank Atmospheric drain tank CCS F.W. expansion tank Fresh water pressure tank Fire fight F.W. pressure tank Boiler compound tank
Oxygen scavenging chemical tank

16. Tank for Fresh Water & Bilge Handling


NO. 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 CAPACITY abt. 100 m3 abt. 100 m3 Total abt. 200 m3 1.5 m3 6 m3 1.0 m3 2.0 m3
1.5 m3

HEATING COIL

REMARKS Hull construction Hull construction Hull construction

H.R. 0.06m2/m3 H.R. 0.1m2/m3 H.R. 0.1m2/m3

Hull construction Hull construction Hull construction

0.15 m3 0.15 m3 Abt.100 m3 Abt.20 m3 Abt.10 m3 5.0 m3 2.0 m3 1.0 m3 H.R. 0.12m2/m3 Hull construction In double bottom

Bilge hold tank Clean drain tank Separated bilge oil tank Vacuum Unit tank for vacuum toilet system Dist. Plant Circ. Water Tank Drinking water Pressure tank

1.5a

Machinery Arrangement -Tank Top Plan

69

64

54
WATER SPRAY PUMP

49

BALLAST STRIP. EDUCTOR EDUCTOR DRIVING & IGG C.S.W. PUMP DN

FIRE LINE PRESS. PUMP

45
DN

FIRE PUMP

DIST. PLANT COOL. S.W. PUMP DN SOLENOID V. BOARD FOR BALLAST LINE

42 39 36
S/T AIR CONT. UNIT UP BILGE & G.S. PUMP NO.3 WATER BALLAST PUMP
W.

HIG

59

HS

.C.

FIRE & BILGE PUMP


UP

ATMOS DRAIN TK MAIN CONDR DN


. W B. UP

33

B.

28 19
B. W

S/T AFT SEAL OIL TK

UP

HO

DN

WE

24
UP UP AUX. L.O. PUMP

MAIN COND. PUMP

DRAIN PUMP

LL

AUX. CONDR

SEA BA

REDUCT. GEAR

S/T FWD SEAL OIL TK


N AI DR TK

19

S/T L.O. PUMP

24 28

S/T L.O. CLR

DN L.O. TRANSF. PUMP

UP

DRAIN COLLECT. UNIT

ESC

ALARM CHAMBER

AP

ET

S/T

RU

NK

O. L.

UP

AUX. L.O. PUMP


) OW . (L S.C

L.O. PURIF. FEED PUMP

TK IN RA .D L.O

MAIN L.O. PUMP

NO.1WATER BALLAST PUMP

UP
PA CE

ECHO SO

.S L.O

PT UM

UP

CL

DN

SP

33 36 39 42
UP

LIF

AUX. CIRC. PUMP AUTO BACK-WASH FILTER L.O. COOLER

LIF

AC

TS

MAIN CIRC. PUMP

T.

SLUDGE COLLECTOR UP

F.O
L.O. STRAINER

.D

RA

IN

TK

DN

BILGE SEP.UNIT

MAIN COOL. S.W. PUMP BILGE SEP.SERV. PUMP E/R BILGE PUMP D/G C.S.W. PUMP UP

49

54
BIL GE PR IM .S

EC

59
.T K

LG BI

EH

OL

TK

DN

45

TK OIL GE . BIL SEP

WASTE OIL TRANS. PUMP DN

B.

UND. & MA G. LO G

EA

DN

DR

COM P.

NO.2 WATER BALLAST PUMP

AI

TK

B.

W.

NO

.8

.B

.T

C L

64
VOID

NO

.8

W.B

69

TANK TOP PLAN

1.5b

Machinery Arrangement -4th Deck Plan


69 64 59 54
F. COF

49
ND ER )

45 42
AF T .T LL

(P)

.S

TT.

F.O

39

. V.T

F.O

. SE

F.O

. SI

W.

IDE

TK

BA

TK

(P)

DE

TK

(P)

(P

F.O

.S

ID

K ET

(P

)(U

36

MAIN DUMP V. UP

UP

33

1ST STAGE FEED W. HTR

MAIN CONDR VACUUM PUMP

F.O. BURN. PUMP

CHLORINATOR

DN GREASE EXTRACT.

28
V.T .

DN

DN

UP

UP

DIST. PLANT CIRC.W. TK DN

24
UP

19
DN DN N

REDUCT.GEAR

L.P.TURB.

DIST. PLANT CIRC.W. PUMP

F.O .PU MP RO OM (P )
DIST.PLANT (C.C.) DIST.PLANT (S.W.C.)

ESCAPE TRU NK
V.L.

GAUGE BOARD

LI

FT

CENTRAL COOL.F.W.PUMP

C L

19 24

H.P.TURB.

GLAND CONDR & EXH.FAN

V.T

DN DN DN
SP LIFT AC . E

TEL.BOOTH UP DN

LI

FT

SP

AC

CCS F.W. CLR

28

UP DN

SPARE MOTOR FOR AUX. CIRC. P'P

PIPE PASS.

UP

UP

PURIF. L.O. HTR L.O.SLUDGE TK CLEAN. TABLE

33
DRAIN INSPECT. TK CUNO FILTER

F.O. BURN. PUMP D.O.TRANS.PUMP H.F.O. TRANS. PUMP

D/G COOL. F.W. PUMP

D/G COOL. F.W. CLR UP

36
DRAIN CLR

) M(S ROO UMP F.O.P

L.O. PURIF. UP

. V.T

.TK

(S)

LP

.S

F.O

45

F.O

.S

ID

U K(

ND

49

54 59

LO

ER

COFF.

64 69

F.O

SU

F.O. SIDE TK(S)

.OV

42

RF

HU

ET

ER

T.

FLO

.O

TK

WT

K(U N

AFT W

DE

R)

39

. BAL

L. TK

(S)

4TH DECK PLAN

1.5c

Machinery Arrangement -3rd Deck Plan


42 45 49 54 59
COFF.

64

69

39 36 33

TK

(P

F.O . SE TT. TK(P )

F.O . SID ET K(P )

AS

BA

UP

UP

24 19 14
E OR ST

COMBUSTION AIR BLOWER

I.G. GENERATOR

AL IC EM CH

M .R .G I. G

AF

28

AT

I.G.G.F.O. PUMP UNIT

F.O

. SID

ER

ET

LL

K(P

V.T.

CONT. PANEL
V

NO
.T.

.8

W.

B.

TK

SHO WER SPA CE

.W

.T

9
.T W T. K
NO .1 DI

COLD START FD W. PUMP 3RD STG FD.W.HTR

CONT.PANEL F.O. PUMP RM EXH. FAN MAIN FD W. PUMP NO.9 BALLAST SOL.V. BOARD

NO

.2

DI

ST

NO.3 AIR COMP.

GENE. SERV. AIR RECEIVER

CONT. AIR RECEIVER


UP

UP

CONT. AIR DRYER NO.2 AIR COMP. NO.2 NO.1 DN UP


UP

NO.2 MAIN TURBO GENERATOR

NO.2
UP

MAIN BLR

NO.1 AIR COMP. STEERING ENGINE ROOM

DOSING & DILUTION STATION

UP

UP

NO.1 MAIN TURBO GENERATOR

UP

UP UP

CE PA TS LIF

NO.2 H/V TRANS. SPACE

REMOV. GRAT.

AY IR W STA
ESCAPE TRUNK FIRE FIGHT. F.W. PRESS. TK
LIF T

LIF

TM

OT

R OR

C L

UP

NO.1 H/V TRANS. SPACE


STERILISER (SILVER ION) FIRE FIGHT. F.W. PUMP
LIF TS

PA

CE

E AC

UP

D.W. PRESS. TK & PUMP UNIT

LOCAL FIRE CONT. PANEL MICRO FOG PUMP PANEL LOCAL FIRE FIGHT SYS. F.W. TK LOCAL FIRE PUMP UNIT UP UP

LIF TS

NO.1

MAIN BLR

UP

UP

UP

F.W. PRESS. TK & PUMP UNIT

CARGO MACH. RM COOL. F.W. BOOST PUMP

F.O. PUMP RM EXH. FAN

UP

SEWAGE UNIT
. TK

DRIN

K. W

W F.

.T

MINERAL INJECT. UNIT VACCUM TOILET SYS. L.O. DAIRY TK

UP

UP

LO

GR

AV

IT

TK

NO.2 AUX.DIESEL GENE. UP UP

NO.1 AUX. DIESEL GENE.

9 14

V.T.

V.T.

ENG

. ST

ORE

SPARE MOTORS

24
LIF T.

28 33 36 39 42
NO .8 W. B. TK
COFF.

45

49

54

LOW

SP

E AC

SUL

PHU

T AF

RF

ER AT W

.O.

59

F.O

. SE

TK

TT.

19

T AS LL BA

64

F.O . SID E TK (S)

TK(S

TK

) (S

UP

STERILIZER(UV TYPE)

NO.2 D/G START. AIR COMP.

NO.2 AIR RECEIV.

NO.1 AIR RECEIV.

NO.1 D/G START. AIR COMP.

69

3RD DECK PLAN

1.5d

Machinery Arrangement -2nd Deck Plan


45 49 54
COFF.

59

64

69

36 33 28 24
DN

39

42
CONDENSING UNIT

I.G.G . GA SO IL T K

W AT ER

BA LL .T K( P)

COFF.

AF T

TK(P

NDE

TT.

F.(U

. SE

19
LS TO RE ICA

COF

F.O

I. G. COOLER & DRYER

EM

CH

D.

PACKAGE AIR COND.

O.

ST

OR

GAS BLOWER

.TK

(P

F.O

. SID

ET

K(P

R)

LAB OR ATO RY

NO

W.

.1 D

TK

IST

M .R .G I. G

. TK

. NO
UP UP

8W

.B

.T

.W

DIS

BLR SAMPLE COND. & ANALY. UNIT

T.

SINK

NO

.2

V.T

V.T.

ELECTRICAL & INSTR.WORK SHOP


FEED W. SAMPLE COND. & ANALY. UNIT NO.2 F.O. HTG RM EXH. FAN VISCO. CONT. UP PACKAGE AIR COND.

PACKAGE AIR COND.

NO HEA .2 F.O TIN . GR M

UP UP UP HOT W.CIRC.PUMP W/H & CCR UNIT COOL. F.W. BOOST PUMP UP

UP

HOT W.HTR

(U) NO.1/(D) NO.2

BLR F.O. HTR (2 SETS)

D AR BO CH IT W S
UP DN

) (P RM

BOG PIPE HOO D

BNR CLEAN. TABLE

DN

TS

PA

CE

DN

AFT MOOR. DK

BLR GAUGE BOARD

LIF

PACKAGE AIR COND.

ROO

DN
CE

DN

UP

BLR F.O. HTR (2 SETS) (U) NO.1/(D) NO.2

LIF

TS

DN

PA

NO HEA .1 F.O TIN . GR M

DN

DRINK. W. FOUNTAIN UP BLR SOLENOID VALVE BOARD UP AUX. TURB. L.O. RENOV. TK AUX. TURB. L.O. STOR. TK UP OIL MIST DETECT. SYS.

MAC

HI. C

ONT

ROL

FT LI

C L

DN

PACKAGE AIR COND.

NO.1 F.O. HTG RM EXH. FAN

VISCO. CONT. BLR FLAME EYE SEAL AIR FAN

TK

F.W

E AC

.T

O .B

DR

TT

K.

.R

M
CLEAN. OIL TK
V.T V.T

W.

RE

NO

G/E V.T

L.O K

ST

G/E OR

L.O

.TK

IN

AIR PURGE LIGHT. SYS.

TT

SINK

R F.O

TK(S

PHU

. SE TT.

AT

28 33 36 39 42
AF

ER

BA

LL

.T

K(

S)

24

L.O

. NG

HATCH

.R

EN

19

WELD. SPACE EXH. FAN

WO

RK

OV

SH

OP

D. O. ST OR .T K( S)

.T

LOW

F.O

/E TK .1 G NO SERV. . D.O

SUL

F.O

. SID

ET

K(S

PACKAGE AIR COND.

COFF.

. TK

O L.

OX

.S

Y.

TO

BO

R.

TK

G/E . TK NO.2 SERV . D.O

.R

SW IT CH BO AR D

RM (S )
)

TK B. W. .8 NO
COFF.

45

49

54

59

64

69

2ND DK PLAN

1.5e

Machinery Arrangement -Engine Casing Deck Plan

28

33
SHORE POWER CONN. BOX

36
N2 BUFF. TANK

42
N2 GE NE .R M
COMPRESSOR

I.G

.G

.RM
DN

N2 GENE. UNIT

B O2

OTT

F . &

OA

MT

AN

KR

EXH. DAMPER
V.T

WET GAS BLOWER

L.O. & HYD. OIL STORE


V.T

49

28
V.T

33

36
V.T

42

49

28
V.T

33

36
V.T

42

F.O. ADD. TK

HYD.PUMP UNIT RM

DECK WORK SHOP


NO.2 EXH.GAS ECO.

DN DN

DN

DN UP UP

DECK STORE
UP

F.D. FAN SPARE MOTOR


DN DN UP

DEAERAT. FD W. HTR
TS PA

BOLTED PLATE

VENTURI

CE

F.D. FAN

33

36

C L

CABLE DRUM FOR SHIP TO SHIP

33

36
CCS F.W. EXP. TK

C L
SMALL HATCH

DEAERAT.FD.W.HTR

33

36

C L

VENTURI
DN

INCINE. RM
UP UP UP UP

DN

INCINERATOR
DN

UP

VENT DUCT EXH. FAN

A/C UNIT RM & REF.PROV.MACH.RM

DN

NO.1 EXH.GAS ECO.

SILENCER FOR D/G EHX. PIPE

CONTROL PANEL

GARBAGE STR
NO.1 EXH.GAS ECONOMIZER

INCINE. D.O. SERV. TK ECO. SPARE TUBE SPACE


V.T

WASTE OIL SETT.TK

D/G C.F.W. EXP. TK


V.T V.T V.T V.T V.T

DAMPER

COFF.

WALL VENT. EMERG.GENE.START AIR RESERV.

COFF.
. SE RV. TK

CHEMICAL LKR

PAINT STORE

RM HTR EXH.DAMPER

EMERG.GENE.AIR COMP.

.DU

RM HTR

E/G CONT.PANEL

BATTERY

SUC.D

UCT

28 28 33 36 39 42

33

36

39

DN

R G. DE ER UN EM FF.( CO

EXH

N GE

E.

SW

RM BD ) DK P. UP

M NE.R .GE ERG EM

E/G

D.O

28

33

36

DN

UP

F.D. FAN

LIF

39

42

UP

CT

EMERG. GENE. ENG.

LOUVER BATTERY CHARGER

42

UPPER DECK PLAN

A DECK PLAN

B DECK PLAN

1.5f

Machinery Arrangement -Engine Casing Deck Plan

28
NO.4 E/R SUPPLY VENT FAN
V. T

33

36

39
V.T

42

28

33
LOUVER

36
LOUVER

39
V.T

42

28

33

36

39

42

MIST SEPARATOR

MIST SEPARATOR

BOLTED PLATE

SU PP LY VE NT FA NR M

RM

SU

NO.2 E/R SUPPLY VENT FAN

E/R

NO .2 E/R

.4

NO

.2

E/R

SU

PP

NO

LY

.4 E

/R S

VE

UPP

PP

NT

LY

EN YV

FA

VE

TF

AN

NT

RM

NR M

FA

BOLTED PLATE

NO.2 E/R EXH. VENT FAN LOUVER

RM

DN

LOUVER

UP

DEAERAT. FD. W. HTR


UP DN

33

36

C L
RM

NO

.2

E/R

EX

H.

VE NT FA N

DN

NO

BOLTED PLATE

33

36

C L

33

36

C L

FUNNEL

UP

EX

H.

VE

NT

FA

DN

NO

.1

E/R

BOLTED PLATE

FA

NR

NO.1 E/R SUPPLY VENT FAN (REV.)

NO.1 E/R EXH. VENT FAN

DN

BOLTED PLATE

NR

FA

V.

NT

VE

RM

PP

SU

SU

MIST SEPARATOR WASTE OIL SETT. TK EXH. FAN

NO
V.T

E/R

.3

E/R

SU

PP

L PP

LY

NO

YV

VE

.1

EN

NT

TF

E/R

MIST SEPARATOR

28

NO

LOUVER

LOUVER

.3

NO

AN

FA

.1

RM

E/R

NO.3 E/R SUPPLY VENT FAN

LY

SU

PP

LY

VE

NT

BOLTED PLATE

V.T

33

36

39

42

28

33

36

39

42

28

33

36

39

42

C DECK PLAN

D DECK PLAN

CASING TOP PLAN

1.5g

Machinery Arrangement -Elevation Plan

COMP. BRI. DK

NAV. BRI. DK

G DECK

F DECK

E DECK

EX

H.

VE

F NT

AN

M NR FA NT VE LY PP SU

SU P FA PLY N R VE NT M

RM

D DECK E/R SUPPLY VENT FAN E/R SUPPLY VENT FAN

C DECK

B DECK DEAERATOR FD.W.HTR

V.T.

A DECK
V.T.

F.D. FAN

EXH. GAS ECONOMIZER

LIFT TRUNK

49

54

59

64

UPP.DK 27875
S)

STAIR WAY

OO

BLR GAUGE BOARD STEAM AIR HEATER


CON T. RM

BO

SW

IT

B CH

PIP

OA

RD

EH

RM

(P&

AFT MOOR. DK

23267

MA

CH.

2ND DK 22,850 MAIN BOILER

K(S .T

)
TK (P)

F.W DIS . TK( S) T. W. TK (P)

INK

.W

T.

W.

DR

DIS

.2

OT

OR

RM

NO

TM

NO

.1

LIF

14

STEER ENG. 16,550 FLAT RAIL FOR M/T RAIL FOR PROP. SHAFT

NO

.2

H/

TA R

AN

S.

SP

AC

MAIN TURBO GENE.

3RD DK 15,650

A.P.

ESCAPE TRUNK
VOID

AUX. CONDR
.F .W .T K

4TH DK 9,470

CO

OL

S/T

WATER BALLAST PUMP

AUX. L.O. PUMP

ATMOS. DRAIN TK
(S)

B. W.
S/T
SEA CHEST (S) FOR EMERG. FIRE PUMP

L.O

. DR

AIN

TK
L.O .D

IN RA

TK

K TAN MP . SU L.O

SE

P.

BI

LG

SEA CHEST (S)

IL

CL

EA

N.

DR

AIN

TK

(S)

13

16

19

24

28

33

36

39

42

45

49

54

59

64

45,000 (FR SP.900 X 50)

E & CHO MA S G. OU LO ND G . CO MP

B.W

.(P)
TK

(S

)
SE

BA

) .(P B.W

TANK TOP
.

69

1.6 Glossary of Symbols

ABBREVIATION A A/C ACC ACCOM. AHD AST ATMOS. AUX. BD BLR BMS BNR BOG B.W. C CAP. CCR CCS CLR CMR COFF. COMPR COND. COND.W. CONDR CONDS D.D. D/G DIST. DK D.O. D.P. Absolute

GLOSSARY

ABBREVIATION DP DSH ECR E.F.P. ENG. E/R EXH. EXT. F.G. F.O. F.W. FD.W. FWR G G.O. G.S. G/E GEN. H H.P. H/D HDR HFO HTD HTG HTR HYD. ICAS IGG IR L LCL

GLOSSARY Differential Pressure Desuperheater Engine Control Room Emergency Fire Pump Engine Engine Room Exhaust External Fuel Gas Fuel Oil Fresh Water Feed Water Feed Water Regulator Gauge or Gear Gas Oil General Service Generator Engine Generator High or Horizontal High Pressure High Duty Header Heavy Fuel Oil Heated Heating Heater Hydraulic or Hydrant Integrated Control and Automation System Inert Gas Generator Infrared Low or Level Local

ABBREVIATION L/D L.O. L.P. LPSG M M/B MCR M.D. MSB M/T NOR NR OVBD P P.C.V. P.R.V. R/G RM S S.C. S/T STBD STBY STC STD STG STM STR S.W. SW T TBN Low Duty Lubricating Oil Low Pressure

GLOSSARY

ABBREVIATION T.C.V. T.H. T/C T/G TK UV V V.T. W. WB W.B. WC W/H W.O.

GLOSSARY Temperature Control Valve Total Head Turbo Charger Turbo Generator Tank Ultraviolet Vacuum or Vertical or Valve Vent Trunk Water or Working Wash Basin Water Ballast Water Closet Wheel-House Waste Oil

Air Conditioner Automatic Combustion Control Accommodation Ahead Astern Atmosphere Auxiliary Board Boiler Burner Management System Burner Boil Off Gas Bilge Well Compound or Centrifugal Capacity Cargo Control Room Central Cooling System Cooler Cargo Machinery Room Cofferdam Compressor Condition or Conditioner Condensate Water Condenser Condensate Diesel Driven Diesel Generator Distilling or Distilled Deck Diesel Oil Discharge Pressure

Low Pressure Steam Generator Motor Main Boiler Maximum Continuous Rating or Machinery Control Room Motor Driven Main Switch Board Main Turbine Normal Normal Rating Overboard Pressure or Piston or Pump or Pipe Pressure Control Valve Pressure Reducing Valve Reduction Gear Room Solenoid or Screw Sea Chest Stern Tube Starboard Standby Steam Temperature Control Standard Stage Steam Store Sea Water Switch Temperature or Turbine Turbine

1.6 Glossary of Symbols

SYMBOLS FOR PIPE DIAGRAM IN MACHINERY PART (1/6) Crossing Pipes, Not Connected Hopper

SYMBOLS FOR PIPE DIAGRAM IN MACHINERY PART (2/6) Stop Valve Geared Valve

Crossing Pipes, Not Connected

Hopper with Cover

Stop Valve

Screw Down Stop Check Valve Electric Moter Operated Screw Down Stop Check Valve Lift Check Valve

Crossing Pipes, Connected

Air Vent Pipe

Stop Valve Welded End

Joint , Flanged

Air Pipe Head without Wire Net

Three Way Valve

Joint , Welded

Air Pipe Head with Wire Net

Electric Moter Operated Valve

Swing Check Valve

Reducer Penetration, Water Tight Bulkhead Crossing Blank Flange Spectacle Flange "O" . . . Normal Open "C" . . . Normal Close Orifice

Sounding Head with Wire Cap Sounding Head with Self Closing Cock Deck Filling Piece

Hose Valve

Butterfly Check Valve

Pressure Reducing Valve

Float Check Valve

Safety or Relief Valve

Diaphragm Valve

Deck Scupper

Self Closing Valve

Ball Valve

Deck Scupper with Plug

Emergency Shut Off Valve


S

Needle Valve

Flexible Pipe or Hose

Boss

Regulating Valve

Solenoid Valve

Expansion Joint

Boss with Plug

Butterfly Valve Electric Moter Operated Butterfly Valve Hydraulically Operated Butterfly Valve Gate Valve Electric Moter Operated Gate Valve

Piston Valve

Open Bilge

Driving Oil Line

Diaphragm Operated Valve Diaphragm Operated Valve with Positioner Three Way Rotary Valve Self Contained Pressure Control Valve

Hose Coupling

Control Air Line

Bellmouth

Capillary Tube

Sprinkler

Electric Cable

1.6 Glossary of Symbols

SYMBOLS FOR PIPE DIAGRAM IN MACHINERY PART (3/6) Self Contained Temperature Control Valve (With Handle) Wax Type Temperature Control Valve Air Vent Valve Y-Type Strainer or Filter

SYMBOLS FOR PIPE DIAGRAM IN MACHINERY PART (4/6) Tray or Coaming Float Type Flow Gauge

Mud Box

Salinity Cell

Seal Pot with Ethylene Glycol

Rose Box

Gauge Glass with Valve

PS

Pressure Switch

Separator

Flat Glass Level Gauge

DPS

Differential Pressure Switch

Degassing Valve

Pump

Float Level Gauge

TS

Thermal Switch

Drain Trap with Filter Regulating and Stop Valve with Filter Cock

Hand Pump

LI

Diaphragm Level Gauge

FS

Float Switch

Ejector or Eductor

Local Indication

LS

Limit Switch Electric Current/Pneumatic Converter Transmitter

Silencer

Remote Indication

I/P

Three Way Cock (L-Port)

Steam Horn or Air Horn

Thermometer

Three Way Cock (T-Port)

Flame Arrester

Pressure Gauge

For Trial Use

Four Way Cock

Sea Chest

Compound Gauge

Cock with Lock

Overboard Distance Piece

Vacuum Gauge

Self Closing Cock

Rose Plate

DP

Differential Pressure Gauge

Fauset

Bilge Hat

Level Indicator

Simlex Strainer or Filter

Sight Glass in Line

SI

Salinometer

Duplex Strainer or Filter

Sight Glass on Tank

FS

Flow Meter

1.6 Glossary of Symbols

SYMBOLS FOR PIPE DIAGRAM IN MACHINERY PART (5/6) AC Automatic Changeover FM Flow Monitoring PM

SYMBOLS FOR PIPE DIAGRAM IN MACHINERY PART (6/6) Pressure Monitoring TA Temperature Alarm

AOS

Automatic Open and Shut

FR

Flow Recording

PR

Pressure Recording

TI

Temperature Indication

AS

Automatic Stop

High

QA

Quality Alarm

TIC

Temperature Control

ASLD

Automatic Slow Down

Low

QI

Quality Indication

TM

Temperature Monitoring

ASS

Automatic Start and Stop

LA

Level Alarm

QM

Quality Monitoring

TR

Temperature Recording

AST

Automatic Stop

LI

Level Indication

QR

Quality Recording

VA

Viscosity Alarm

DPA

Differential Pressure Alarm

LIC

Level Control

RI

Running Indication

VI

Viscosity Indication

DPI

Differential Pressure Indication

LM

Level Monitoring

RM

Running Monitoring

VIC

Viscosity Control

DPM

Differential Pressure Monitoring

LR

Level Recording

RO

Remote Operation

VM

Viscosity Monitoring

DPR

Differential Pressure Recording

MFA

Malfunction Alarm

SA

Stop Alarm

VR

Viscosity Recording

ES

Emergency Stop Operation

OI

Opening Indication

SAH

Salinity Alarm

XA

Miscellaneous Alarm

ESA

Emergency Stop Alarm

OIO

Open Position Indication

SI

Salinity Indication

XI

Miscellaneous Indication

ESD

Emergency Shut Down

OIS

Shut Position Indication

SM

Salinity Monitoring

XM

Miscellaneous Monitoring

FA

Flow Alarm

PA

Pressure Alarm

SR

Salinity Recording

XR

Miscellaneous Recording

FI

Flow Indication

PI

Pressure Indication

FIC

Flow Control

PIC

Pressure Control

1.7 Ship Speed Power Curve

30,000

28,000

26,000

24,000

22,000

Output SHP(kw)

20,000

18,000

16,000

This section will be rectified after completion of the test.

14,000

12,000

10,000

8,000

6,000 14 15 16 17 18 19 20 21 22 23

Ship's Speed Vs(kn)

PART 2 : MACHINERY COMMISSIONING OPERATIONAL OVERVIEW

2.1 2.2 2.3 2.4 2.5 2.6 2.7

To Bring Vessel into Live Condition To Prepare Main Plant for Operation (Raising Steam) To Prepare Main Plant for Manoeuvring from In Port Condition To Change Main Plant from Manoeuvring to Normal Conditions To Change Main Plant from Normal to Manoeuvring Conditions To Secure Plant at Finished with Engines To Secure Plant for Dry Dock

2.1 To Bring Vessel Into Live Condition


Note: This procedure assumes that the main turbine and the main condenser are not readily available.

Dead Ship Condition

Shore Supply Available


Establish shore supply.

No Shore Supply Available 5.4.3


Prepare the emergency generator for operation. If necessary fill the emergency diesel generator fuel tank from drums.

5.3

Fill a boiler to 100mm below the normal water level by using the cold start feed water pump, with suction from the distilled water tank.

3.2.2 4.3.2

Start the emergency generator and supply the emergency and main switchboards through the respective breakers

5.3 5.4.5

Supply main and emergency lighting throughout the vessel, together with necessary ventilation.

3.2.1

With a burner in a boiler, supply diesel oil to the burner using atomizing air. Supply main and emergency lighting throughout the vessel, together with necessary ventilation.

4.3.2

5.4.2

Put the generator air start system into operation. Start up the main diesel generator and place in parallel with emergency generator. The emergency generator will automatically disconnect from the switchboard

3.3.2 5.4.4

Start the boiler forced draught fan. With all required vents and drains open, begin to flash up the boiler. Ensure that the furnace is adequately purged prior to ignition. If the boiler has been shut down for a long period, use a low fuel pressure to ensure heat and boiler pressure rise slowly. Start the E R vent fans.

4.3.2

Put the following into operation: Cooling sea water system, cooling fresh water system, hydraulic power pack for the ship side valves.

3.5.2 3.4.1 7.2


Open the boiler stop valves to: The superheated steam system. The 6.0Mpa desuperheated steam system. The auxiliary steam system. The 1.0Mpa desuperheated steam system. The superheater vent valve Ensure all steam line drains are open. Open the valves to the heating coils of one F O settling tank, placing the coil drains to the contaminated drains system.

3.1.1 3.1.2 3.1.3 3.1.5 3.2.5 3.2.6

Check all main turbine LO system lines are satisfactory, with the LO cooler drain valves closed. Ensure that the level in the main sump is correct. Start one main LO pump and allow the system to circulate. Check all sight glasses on bearings and gearing for oil flow. Ensure the LO gravity tank is overflowing.

3.7.1

Put the control air systems into operation.

3.3.1
Shut the drum vent when steam issues from it, at approximately 0.1MPa. Open the steam inlet and drains to one fuel oil heater and allow the fuel temperature to rise slowly

4.3.2 3.1.5

Put the fire detection system into operation.

10.2

Next Page

2.1 To Bring Vessel Into Live Condition

Previous Page Recirculate DO around the fuel rail until its temperature reaches approximately 70. Change the burner over to HFO and shut down the diesel oil supply. 4.3.2 With the boiler superheater being circulated, and steam being supplied to the feed pump and turbine generator, all the boiler drains and vents can now be closed in. Continue to raise steam pressure, with fuel and air under the control of the ICAS. Check each system is now operational and gradually change over all control systems to automatic and/or remote. Ensure systems and components that have been used are put back on standby condition or isolated e.g. cold start feed water pump, emergency diesel generator etc. 4.3.2

As the steam pressure rises, use the cold start feed water pump to maintain the boiler water level. With the boiler now being fired on HFO, the fuel oil pressure will require adjusting to maintain a steady and safe pressure rate. Raise HFO temperature steadily.

4.3.2

Start the auxiliary sea water circulating pump to supply the auxiliary condenser. At 1.5MPa put one main feed pump into operation to maintain the boiler level. The turbine exhaust will go the either the deaerator or the auxiliary condenser.

3.5.1 4.3.2 3.1.6

Ensure that the ICAS has taken the control of the boiler out of the flashing ramp to the normal control mode. The boiler should now be providing normal steam pressure to the turbine generator, main feed pump and fuel oil heating etc. Unload and shut down the diesel generator.

4.3.4

5.4.2

Put the auxiliary condenser condensate and drain system into operation pump.

3.2.1

Start up all the remaining auxiliaries, such as refrigeration units, air conditioning units, fans not in use, galley and accommodation supplies etc.

At approximately 2.0MPa, warm through and start up a turbine generator. The exhaust will dump to the auxiliary condenser. Unload the diesel generator and parallel the turbine generator with the diesel generator.

5.1 3.1.6 5.4.4

(Note: If the vessel is in dry dock or alongside a shore installation, electrical power may be supplied through the shore breaker. However, this is normally used for dry dock purposes when separate arrangements are made for cooling sea water supplies to cooling fresh water cooler.

3.5.2

Having warmed through and drained the atomising steam system, when boiler pressure reaches 1.5Mpa, change the burner atomising to steam. Close the atomising air supply valve 025VPB or 035VPB.

3.1.3

Vessel in Live Condition

2.2 To Prepare Main Plant for Operation (Raising Steam)

One Boiler in Operation And Auxiliary Plant Operation

Open the vents on the superheater inlet pipe, and the drains on the desuperheater and superheater, on the non-operational boiler.

4.3.2

Allow the fuel temperature to rise to approx. 90C. Purge the boiler furnace. When the purge sequence is completed, flash the boiler and adjust the air and fuel to the minimum for good combustion. (Note: The length of time the boiler has been out of operation governs the amount of time to allow for raising steam. The longer the unit has been off line, the greater the number of flashes and soaks should be allowed, before continuous firing.)

4.3.2

At approximately 5MPa, open up the desuperheated system main valve bypass valve. Allow the pressure to increase to that of the in-use boiler and float the boiler on-line by opening the main valve and closing the drains and the bypass valve.

4.3.2

Fill the boiler to approximately 80mm above the normal operating level, using the main feed pump on the auxiliary feed system, with suction and recirculation from the deaerator. Ensure careful use of the filling valve and closely monitor the deaerator and boiler water levels.

4.3.2

Before opening the superheater valves, ensure the line drains to the in-use main feed pump and turbine generator are open. When the superheated temperature approaches the in-use boiler, slowly open the superheater system stop valves.

4.3.2

Slowly raise the steam pressure. At approx. 0.1MPa and with steam emitting from the superheater inlet pipe vent, close the vent valve.

4.3.2

Fit clean burner atomizers. Commence circulating fuel oil through the main fuel rail to raise the temperature.

4.3.2 Continue to raise the steam pressure, closing in the various drains as required to maintain good drainage without excessive water loss. 4.3.2

Close all drains and vents. Ensure that the IAS has normal control of combustion and level control, and the firing ramp has reset. The plant is now operating with two boilers, one turbine generator and one main feed pump, with exhausts and dumps to the auxiliary condenser.

4.3.2

Start a forced draft fan. Open atomising steam to the burners. Supply steam to the air heater. Reset all boiler trips. Place the boiler controls on manual and local in the ICAS.

4.3.2 4.3.4

Ensure that all drains from the main condenser sea water pipes are closed. Start a main sea water circulating pump to the main condenser, ensuring all valves on the system are open. 3.5.2 Start the stern tube and shaft seal LO system.

3.5.1

Isolate the auxiliary feed line to normal condition and line up the main feed line from the main feed pump. Maintain water level control on manual.

3.7.4

Next Page

2.2 To Prepare Main Plant for Operation (Raising Steam)

Previous Page Start the main turbine turning gear. 4.2.2 The plant is now operating with both boilers, all exhaust dumps to the main condenser and both main condensate and atmospheric drain systems in use. The main turbine has its vacuum raised with gland steam in use. The main turbine and stern tube LO systems are in use. The main turbine is being turned with the turning gear. 4.3.2

Crack open the main turbine gland steam make-up bypass valve and allow the turbine to warm through slowly.

3.1.3 4.2.2

Open the cooling sea water circulating system to a main turbine LO cooler.

3.5.1 4.2.2 3.1.6

Open the gland steam inlet valve 057VPB. Adjust the controller set steam pressure.

3.1.3 4.2.2

Ensure all the exhaust and drain systems are transferred from the auxiliary to the main condenser. Isolate and shut down the auxiliary condenser.

3.1.6

Start the gland condenser exhaust fan.

3.1.6

Place all pumps in use to remote start and their second pumps to standby conditions, with all required valves open.

Open the suction, discharge and casing vent to one of the main condensate pumps. Fill the main condenser to a working level from a distilled water tank. Start the main condensate pump.

3.2.1

When the auxiliary condenser has cooled down, shut down the SW cooling system and stop the auxiliary circulating water pump.

3.5.1

Start the one of main condenser vacuum pumps. When the vacuum approaches 700mmHg, transfer the turbine generator and other exhausts to the main condenser.

3.1.6

Main Plant Ready For Operation

2.3 To Prepare Main Plant for Manoeuvring from In Port Condition

Two Boilers in Operation Main Condenser Vacuum Established. Main Turbine Gear in Operation Bypass valve on main boiler superheated steam stop valves to the main turbine adjusted to maintain a pressure of 1.4Mpa on the main steam line.

Prepare and run up the second turbine generator. Place the second generator on the main switchboard in parallel with the generator in use.

5.1 5.4.2

Slowly open the main boiler stop valves and close the by-pass valves to the main turbine once the main steam line pressure is at normal.

3.1.1

After the Turbine has been warmed through, turning in the manual mode, place the controls in automatic mode, and allow the engine to continue to warm through by spinning manually (ahead and astern abt. 10rpm).

4.2.2

Ensure that the diesel generators are on standby and ready to run, should it be required.

5.2

Advise the bridge that the main turbine will be operated and confirm that the propeller area is clear. As required by international rules, ensure all the information concerning the above being carried out is recorded along with the times at which each section is completed. 4.3.2

Once loading arms are confirmed as disconnected, commence raising the main steam line pressure to the main turbine by slowly opening the main boiler's stop superheated steam valves to the main turbine.

3.1.1 Close the warming through steam line valves for main turbine. Open the astern guardian valve. 3.1.1 4.2.4

When the deck officer is available on the bridge, proceed with following test: With the main turbine controls on manual stop, move the telegraph lever to all its points, and prove the turbine remote control unit follows and answers the bridge unit.

4.2.3

Reset the main turbine trip, ensuring that the control oil pressure is correct for the manoeuvring system. Disengage the turning gear.

4.2.3

Ensure that if any burners are off, they are in place and ready to be used.

Check and inspect the steering gear systems, ensuring the LO levels and hydraulic oil levels are correct. As each unit is tested, check all movements of the rams and rudder are satisfactory and as required. Maintain contact with the bridge as these tests are undertaken. (Note: When steering gear tests are completed, to prevent the pumps delivering in the same mode for long periods and risk overheating the unit, ensure the deck officer alters the rudder angle regularly to overcome this.)

With the manoeuvring controls in manual mode, from the MCR with some attendance at the turbine side, operate the control to allow main steam into the turbine and rotate ahead and astern at 5 revolutions per minute. DEC. for astern and INC. for ahead. While the above is being undertaken, the main turbine is checked to ensure it turns satisfactorily in both directions.

Inform the bridge that the main engines are ready for use.

At standby, put the main turbine controls to bridge control mode and monitor their response as manoeuvring proceeds.

4.2.2

Using the controls in manual mode, repeat the ahead and astern movements to warm through the turbine to a superheated temperature approaching that of the boiler.

4.2.2

The Main Turbine is Now Ready to Put to Sea

2.4 To Change Main Plant from Manoeuvring to Normal Conditions

Vessel Is Manoeuvring On Bridge Control Put the boiler firing controls to the required firing mode in the ICAS, whereby boil-off gas may be used in conjunction with fuel oil if this is available. 4.3.4 Stop and isolate the off load turbine generator. Check that the electric LO pump starts as the LO pressure drops. Engage the turning gear when the turbine stops. 5.1

Bridge informs the MCR that the vessel is full away on passage, and indicates as such by moving the telegraph to full sea revolutions.

Record the following: Time Main engine revolution counter reading Fuel oil counter reading Fuel oil service tank levels Diesel oil service tank level Fuel and gas oil bunker tank levels Gas flow meter reading

Confirm the automatic stop of the main turbine standby auxiliary LO pump and that all LO pressures remain normal.

3.7.1

Ensure that the live steam make-up valves close and the main turbine bleed steam valves open as the main turbine revolutions increase. The main circulating system changes over from pump to scoop.

4.3.2 3.1.3 3.5.1

Pump the contents of the bilge tank overboard through the oily water separator unit. Note that MARPOL regulations apply.

3.8.1 3.8.2 Check that the changeover of the auxiliary heating steam system, from live to HP bleed, has occurred. 6.2 Confirm with the bridge that the boilers may be sootblown and proceed as appropriate. 3.1.5

Confirm that the astern guard valve is closed, the main turbine drains are automatically closed and the main feed water pump automatic recirculating valve is closed.

4.2.3 6.1

Evaporators may be used to fill the fresh and the distilled water tanks as long as the ship is in permitted waters. Run up and use these units as required.

Change to BOG burning only if required or remain on dual fuel burning. Allow the main engine revolutions to increase as per the timed program, which will open the manoeuvring valve a set amount over a period of time until it is fully open. This will take approximately 40 minutes from full ahead manoeuvring revolutions to full sea revolutions. 4.2.3

4.3.2 When full sea speed has been achieved, make final adjustments to the plant to give optimum performance at the required speed. Refer to the heat balance diagrams. 3.0

Remove one turbine generator from the main switchboard, allow it to run light for a few minutes to cool down. (Note: It is possible to test the turbine generator trips while the unit is in this condition.)

5.1 The vessel is now at Normal conditions, on bridge control.

The Main Turbine is Nav. Full On Bridge Control

2.5 To Change Main Plant from Normal to Manoeuvring Conditions

Vessel Is At Full Revolutions On Bridge Control

Approximately 2 hours before manoeuvring operations are to commence, run up and parallel the standby turbine generator. (Note: Trips may be tested at this time. When the unit is up to speed, parallel with the unit already on the main switchboard.)

5.1 5.4.4

As the main turbine revolutions reduce, the operating mode select switch will automatically change over to manoeuvring mode.

4.2.3

Approximately 1 hour before manoeuvring operations is to commence, request the bridge to bring the telegraph position to standby full ahead rpm gradually on the telegraph vernier over 40 minutes. The revolutions will be at the full ahead.

4.2.2

At manoeuvring rpm, the astern guardian valve opens, the turbine drains open and the feed pump recirculating valve opens.

4.2.3 6.1

When the bridge notifies the engine room of end of passage, record the following: Time Main engine revolution counter Fuel oil counter Fuel oil settling tank levels Diesel oil service tank level Fuel and diesel oil bunker tank levels Distilled and FW tanks levels Gas meter reading

As the turbine rpm continues to fall, the main condensate recirculation valve will open. As the main turbine rpm reduces, ensure that the following occurs: As the bleed steam pressures reduce, ensure the automatic valves close and the make-up valves open as required. 3.1.3 This allows condensate to return to the main condenser hot well, ensuring a level is maintained for the condensate pump and cooling the gland condenser..

3.2.1 The main turbines are now ready for movements via bridge control.

If the main boilers are on BOG burning only, change to dual fuel burning on both.

4.3.2

Shut down the evaporators, unless only distilled water is required to be produced.

6.2

The Plant Is Prepared For Manoeuvring

2.6 To Secure Plant at Finished with Engines

Vessel Is Manoeuvring On Bridge Control Close the main boiler's superheated steam stop valves to the main turbine and open the by-pass valve. When all movements of the main turbine are completed, the bridge will transfer the control of the main turbines to the engine room and place the telegraph at stop position. 3.1.1 4.2.4

Close the main turbine stop valve and open the warming through line valves.

4.2.4

Although the telegraph is indicating stop, the turbine controls are still on automatic, and as such the turbine will turn on the auto-spin steam system. This system allows the main turbine to rotate ahead and astern at approximately 5 rpm, preventing the turbine from sitting in one position for a prolonged period of time which may cause the rotor to sag.

4.2.3

Engage and start the turning gear.

4.2.2

Stop both steering gear motors.

The main turbine is now stopped and turning slowly with warming steam on line. Switch off the auto-spin system and trip the turbine. 4.2.2 Unless the turbine is to be shut down for repairs or another specific reason, this is the condition the plant is normally left in while awaiting port operations.

Push F/E button on Sub telegraph.

4.2.3 Ensure the boilers are firing on dual fuel if possible when in port, thus preventing gas being vented to the atmosphere. 4.3.2

The Engine Room Is Now Ready for Cargo Operations

2.7 To Secure Plant for Dry Dock

Vessel is at Finished with Engines And in a Live Condition

Take one of the turbine generators off load, allow it to run light for a few minutes before stopping it. Check that the LO pump starts as the turbine slows down. Engage the turning gear when the turbine stops Close the steam inlet and exhaust valves. Close the gland steam make up and spill valves.

4.3.2

Start the auxiliary circulating water pump to the auxiliary condenser.

3.5.1

Put one boiler controls to manual and reduce the fuel and air supply, alternatively, alter the ratio control within the ICAS increasing the load on the boiler.

4.3.2

Change all the exhaust dumps to the auxiliary condenser, isolating from the main condenser.

3.1.6

Allow the other boiler automatic controls to take more of the load. When the second boiler has taken the entire load, the first boiler can be tripped.

4.3.2

Start up the diesel generator and place on the switchboard in parallel with the in-use turbine generator.

5.2
5.4.2

Ensure that all the main feed pump gland seal water and all other spray or cooling condensate water is supplied from the drain pump.

3.2.1 Close the superheated and desuperheated steam master and intermediate valves. Close the main feed valves, put the feed control to manual. 3.5.2 Open the superheated vent valve, throttling to avoid dropping the pressure too rapidly. 4.3.2 3.1.1

Ensure the main boiler's superheated steam stop valves, by-pass valve and warming through steam line valves are shut.

3.1.1

Stop the main condenser vacuum pump. The main condenser vacuum will now fall.

Isolate the fuel oil and steam valves at the burner rail. When condenser vacuum drops to atmospheric pressure, shut the gland steam make-up and spill valves to the main turbine. Stop the gland steam exhaust fan. 3.5.2 Stop the FD fan and close the vanes. Shut off the steam to the air heater.

4.3.2 3.1.3

Isolate and take off standby all non-running pumps and machinery.

the

Shut down the evaporators.

6.2

Stop the in-use main condensate pump. Close the main condensate recirculating valve, to prevent any water returning to the main condenser.

3.2.1

Allow the shut down boiler pressure to fall away, opening the vent valves of steam drum, superheater outlet header and the drain valve of desuperheater inlet when the pressure is approximately 0.1MPa.

4.3.2 3.1.1 3.1.2

Shut down the purifier.

3.7.2

When the main condenser has cooled, the main circulating water pump can be stopped and all valves closed.

3.5.1

Stop the main turbine turning gear after approximately 6 hours. Stop the main turbine LO pump. Stop and isolate the stern tube seal LO systems.

4.2.2 3.7.1 3.7.4

Next Page

2.7 To Secure Plant for Dry Dock

Previous Page The plant now has one boiler operating and supplying one turbine generator and one main feed water pump. The exhaust system is diverted to the auxiliary condenser. The main turbine is stopped, with all steam and oil supplies shut down Stop the in-use main feed pump and close all valves. 3.2.2 6.1 Start the emergency diesel generator to supply the lighting, ventilation, SW and FW cooling systems to cool down the main diesel generator and air compressors. Unload the main diesel generator from the switchboard, allow it to run light to cool down before stopping. With the boiler shut down, there should be no more drains returning to the atmospheric drain tank. Shut the deaerator outlet valve to the main feed pump suction. Shut the in use distilled tank outlet valve to the make-up line. 3.2.2 3.2.1 Stop the in-use cooling sea water pumps and the fresh water cooling pumps. 3.4.1 3.5.2 5.4.2 5.2 5.3 Trip the in-use boiler, allowing the main feed pump to run and use up the steam while maintaining the boiler level. Place all boiler controls to manual. 4.3.2 Stop the air compressors. Stop the air dryers. 3.3.1

When the main condenser has cooled, the main circulating water pump can be stopped and all valves closed.

3.5.1

Shut off the steam supply to the in-use boiler fuel oil heater. When the fuel temperature falls to approximately 90C, open the fuel supply to the boiler fuel oil burning pump from the diesel oil service tank and close all valves from the heavy fuel oil settling tanks. Change the atomising steam supply over to atomising air supply, from the general service air system, to the in-use boiler.

3.1.5 3.6.4 3.3.1

As diesel oil is used throughout the system, the HFO will be replaced by the diesel oil. This will be required in preparation for the flash-up cycle when no heat will be available for the HFO. Allow the DO to flow through both fuel heaters, and through the recirculation rail at the burner manifolds on both boilers.

3.3.1 3.6.4

As the boiler pressure falls, maintain the water level in the boiler using the cold start feed water pump.

3.2.2

The main plant is now shut down.

Allow the auxiliary circulating water pump to run until the auxiliary condenser has cooled, then stop and isolate the pump.

3.5.1

Close the LO supply valves 210 / 217VPK and air supply valves 156 / 228VPE for stern tube aft seal at dry dock.

3.7.4

Allow the diesel generator to take the entire switchboard load and take the in-use turbine generator off load. Stop the turbine generator, close all steam / exhaust and gland steam valves. Engage the turning gear.

5.4.2 5.1 Stop the refrigeration and air conditioning units and wait for the shore cooling water supply before restarting. 3.4.1

When the dockyard has connected the electrical supply to the shore breaker, the emergency generator can be tripped from the emergency switchboard and the shore supply breaker put on.

5.4.5

The Plant is Now Secure in Dry Dock and On Shore Power

PART 3 : SHIPS SYSTEMS

3.0

Heat Balance for Steam Turbine Plant


3.0.1 100% MCR On Fuel Oil Burning (FOC Guarantee Condition) 3.0.2 3.0.3 3.0.4 3.0.5 3.0.6 3.0.7 3.0.8 3.0.9 3.0.10 3.0.11 3.0.12 3.0.13 3.0.14 100% MCR On Fuel Oil Burning 100% MCR On Dual Fuel Burning 100% MCR On Gas Fuel Burning Cargo Unloading Full Dump by Main Condenser Cargo Loading Full Dump by Auxiliary Condenser Hotel Load 100% MCR On Fuel Oil Burning 90% MCR On Fuel Oil Burning Half Ahead On Fuel Oil Burning Slow Ahead On Fuel Oil Burning Hotel Load - Winter Condition - Winter Condition - Winter Condition - Winter Condition - Winter Condition

3.2

Condensate and Feed Water Systems


3.2.1 3.2.2 3.2.3 3.2.4 3.2.5 3.2.6 Condensate Water System Boiler Feed Water System Boiler Water Sampling and Treatment System N/A Clean Drains System Contaminated Drains System

3.6

Fuel Oil and Fuel Gas Service Systems


3.6.1 3.6.2 3.6.3 3.6.4 3.6.5 3.6.6 3.6.7 Fuel Oil Bunkering System Heavy Fuel Oil Transfer System Diesel Oil and Gas Oil Transfer System Boiler Fuel Oil Service System Boiler Fuel Gas Service System Boil-off Gas Systems in Cargo Machinery Room Diesel Oil and Gas Oil Service System

Illustrations

Illustrations
3.2.1a 3.2.1b 3.2.2a 3.2.3a 3.2.4a 3.2.5a 3.2.6a Condensate Water System Deaerator Boiler Feed Water System Boiler Water Sampling and Treatment System N/A Clean Drains System Contaminated Drains System

Illustrations
3.6.1a 3.6.1b 3.6.2a 3.6.3a 3.6.4a 3.6.4b 3.6.5a Fuel Oil Viscosity - Temperature Graph Fuel Oil Bunkering System Heavy Fuel Oil Transfer System Diesel Oil and Gas Oil Transfer System No.1 Boiler Fuel Oil Service System No.2 Boiler Fuel Oil Service System Boiler Fuel Gas Service System Boil-off Gas Systems in Cargo Machinery Room Diesel Oil and Gas Oil Service System

3.3

Compressed Air Systems


3.3.1 Compressed Air System Starting Air System 3.3.2

3.6.6a 3.6.7a

3.1

Steam Systems
3.1.1 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 Superheated Steam System 6.0 MPa Desuperheated Steam System Auxiliary Steam System N/A 1.0 MPa Desuperheated Steam System Exhaust and Dump Steam System

Illustrations
3.3.1a 3.3.2a Compressed Air System Starting Air System

3.7

Lubricating Oil Systems


3.7.1 3.7.2 3.7.3 Main Turbine Lubricating Oil System Lubricating Oil Purification System Lubricating Oil Filling and Transfer System Stern Tube Lubricating Oil System

3.4

Fresh Water Cooling Systems


3.4.1 Central Fresh Water Cooling System

3.7.4

Illustrations
3.7.1a 3.7.2a 3.7.3a Main Turbine Lubricating Oil System Lubricating Oil Purification System Lubricating Oil Filling and Transfer System Stern Tube Lubricating Oil System

Illustrations
3.1.1a 3.1.2a 3.1.3a 3.1.4a 3.1.5a 3.1.6a Superheated Steam System 6.0 MPa Desuperheated Steam System Auxiliary Steam System N/A 1.0 MPa Desuperheated Steam System Exhaust and Dump Steam System

Illustrations
3.4.1a Central Fresh Water Cooling System

3.5

Sea Water Systems


3.5.1 3.5.2 Sea Water Circulating System Cooling Sea Water Service System

3.7.4a

3.8

Engine Room Bilge Systems


3.8.1 3.8.2 Engine Room Bilge System Bilge Separator

Illustrations
3.5.1a 3.5.2a Sea Water Circulating System Cooling Sea Water Service System

Illustrations
3.8.1a Engine Room Bilge System

3.9

Sanitary and Fresh Water service Systems


3.9.1 3.9.2 Domestic Fresh Water System Sewage Treatment System

Illustrations
3.9.1a 3.9.2a Domestic Fresh Water System Sewage Treatment System

91,790 Kg/H 850 Kg/H

88,540 Kg/H

84,010 Kg/H

0 Kg/H 130 Kg/H

LOSSES
3,250 Kg/H 0 Kg/H
92,640 Kg/H 6.0/1.0MPaG PRV 850 Kg/H 6.0MPaG 287 6.03MPaG 515

84,010 Kg/H

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 23,600 kW 80.0 RPM 5.88 MPaG 510 5.07 KPaA
S.W. TEMP. AT 27

A
90 Kg/H
GLAND LEAK

4,530 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO. S.A.H.

5.88MPaG 510

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 510

MAIN FD.P.T.

5.88MPaG 510
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

3,160 Kg/H

1,410 Kg/H

8,940 Kg/H

8,010 Kg/H

0.130MPaA

MAIN BOILER
0 Kg/H 4,350 Kg/H 0 Kg/H

1.62MPaG341

0.65MPaG225

0 Kg/H

0 Kg/H

4,480 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE 6.03 MPaG 515 145.0 88.5 % 43.03 MJ/Kg

0 Kg/H

92,640 Kg/H

145

BURNER ATOMIZ.
1,140 Kg/H 200

460 Kg/H DESUPERHTR

1,410 Kg/H 1.0MPaG PRV


0 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

4,480 Kg/H

CONSUMPTION
DESUPERHTR

F.O.

6,726 Kg/H

0 Kg/H 0 Kg/H 0 Kg/H 4,480 Kg/H 65,520Kg/H 0 Kg/H

7,210 Kg/H 4,890Kg/H 2,860 Kg/H 190 Kg/H 4,350 Kg/H 644.0KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

FUEL OIL CONSUMPTION RATE

285.0 g/kW/H

1,730 Kg/H 8,010 Kg/H 50 Kg/H


270 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 36.2 T/DAY 940 kW

MAIN CONDR.
0 Kg/H GLAND CONDR.

DIST. PLANT
103,210 Kg/H 70,000 Kg/H 44.5 125,800 Kg/H 87.6 T.C.V. 79 70,000 Kg/H 32.5

5.07KPaA

DEAERATOR
92,830 Kg/H 3RD STG. FD.W.HTR 128.4 2,870 Kg/H 0.15 MPa 127

103,210 Kg/H 100 12,360 Kg/H 60.3 1ST STG. FD.W.HTR 0 Kg/H 52.3 320 Kg/H 90

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

50.9

12,360 Kg/H

22,490 Kg/H 127

2,860 Kg/H 573.5KJ/Kg 430 Kg/H 460 Kg/H 120 Kg/H PURIF.L.O.HTR 10 Kg/H TRACING STM BLR F.O.HTR F.O.SETT.& SIDE TK 430 Kg/H 460 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

0 Kg/H

PUMP GENERATOR

18,080 Kg/H 33,210 Kg/H 1,510 Kg/H 79.0 64.6

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR.

1,140 Kg/H

1,310 Kg/H

ACCOMODATION 0.3MPaG P.R.V. 0 Kg/H FUEL GAS HTR 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FORCING VAPORIZER

100 Kg/H DRAIN CLR GAS VENT. DRAIN TK

12,680 Kg/H

18,080 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

DIST.W.TK
0 Kg/H

0 Kg/H 0 Kg/H

0 Kg/H

Heat Balance Diagram


Normal Sea Going Operation 100% MCR On Fuel Oil Burning (F.O.C. Guarantee Condition)

ATMOS DRAIN TK
0 Kg/H 0 Kg/H

12229/30

MA1-ZB01-0

92,140 Kg/H 860 Kg/H

88,890 Kg/H

84,020 Kg/H

0 Kg/H 130 Kg/H 84,020 Kg/H

LOSSES
3,250 Kg/H 0 Kg/H

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 23,600 kW 80.0 RPM 5.88 MPaG 510 5.07 KPaA
S.W. TEMP. AT 27

93,000 Kg/H 6.0/1.0MPaG PRV 860 Kg/H 6.0MPaG 287 6.03MPaG 515

A
90 Kg/H
GLAND LEAK

4,870 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO.

5.88MPaG 510

S.A.H.

5.88MPaG 510

MAIN FD.P.T.

5.88MPaG 510
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
GLAND SEAL

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

0 Kg/H

0 Kg/H

3,160 Kg/H

4,820 Kg/H

0 Kg/H

0 Kg/H

1,410 Kg/H

8,870 Kg/H

8,140 Kg/H

0.130MPaA

MAIN BOILER
0 Kg/H 4,360 Kg/H 0 Kg/H

1.62MPaG341

0.65MPaG225

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE 6.03 MPaG 515 145.0 88.5 % 43.03 MJ/Kg

0 Kg/H

93,000 Kg/H

145

BURNER ATOMIZ.
1,140 Kg/H 200

460 Kg/H DESUPERHTR

1,520 Kg/H 1.0MPaG PRV


0 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

4,420 Kg/H

CONSUMPTION
DESUPERHTR

F.O.

6,750 Kg/H

0 Kg/H 0 Kg/H 0 Kg/H 4,820 Kg/H 65,470Kg/H 0 Kg/H

7,230 Kg/H 4,800Kg/H 2,870 Kg/H 190 Kg/H 4,360 Kg/H 644.0KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

FUEL OIL CONSUMPTION RATE

287.0 g/kW/H

1,640 Kg/H 8,140 Kg/H 50 Kg/H


270 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 31.7 T/DAY 1025kW

MAIN CONDR.
0 Kg/H GLAND CONDR. 101,290 Kg/H 100 12,500 Kg/H 58.9 1ST STG. FD.W.HTR 0 Kg/H 50.4 320 Kg/H 90 101,290 Kg/H 49.1 70,290 Kg/H 42.7 125,800 Kg/H 86.4 T.C.V. 79

DIST. PLANT
70,290 Kg/H 32.3

5.07KPaA

DEAERATOR
93,190 Kg/H 3RD STG. FD.W.HTR 128.4 2,870 Kg/H 0.15 MPa 127

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

12,500 Kg/H

15,720 Kg/H 127

2,870 Kg/H 573.5KJ/Kg 430 Kg/H 460 Kg/H 120 Kg/H 10 Kg/H BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM 430 Kg/H 460 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

0 Kg/H

PUMP GENERATOR

15,720 Kg/H 31,000 Kg/H 1,320 Kg/H 79.0 63.5

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR.

1,140 Kg/H

ACCOMODATION 0.3MPaG P.R.V. 0 Kg/H 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FUEL GAS HTR FORCING VAPORIZER

1,320 Kg/H

100 Kg/H DRAIN CLR

12,820 Kg/H

15,720 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

DIST.W.TK
0 Kg/H

0 Kg/H 0 Kg/H

GAS VENT. DRAIN TK

0 Kg/H

Heat Balance Diagram


Normal Sea Going Operation 100% MCR On Fuel Oil

ATMOS DRAIN TK
0 Kg/H 0 Kg/H

12229/30

MA1-ZB01-1

92,930 Kg/H 860 Kg/H

89,670 Kg/H

84,200 Kg/H

0 Kg/H 130 Kg/H 84,200 Kg/H

LOSSES
3,260 Kg/H 0 Kg/H

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 23,600 kW 80.0 RPM 5.88 MPaG 510 5.07 KPaA
S.W. TEMP. AT 27

94,010 Kg/H 6.0/1.0MPaG PRV 860 Kg/H 6.0MPaG 287 6.03MPaG 515

A
90 Kg/H
GLAND LEAK

5,470 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO.

5.88MPaG 510

S.A.H.

5.88MPaG 510

MAIN FD.P.T.

5.88MPaG 510
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
GLAND SEAL

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

0 Kg/H

0 Kg/H

3,170 Kg/H

5,420 Kg/H

0 Kg/H

0 Kg/H

1,610 Kg/H

8,900 Kg/H

8,200 Kg/H

0.130MPaA

MAIN BOILER
0 Kg/H 4,320 Kg/H 0 Kg/H

1.62MPaG342

0.65MPaG224

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE GAS 6.03 MPaG 515 144.9 85.3 % 43.03 MJ/Kg 55.59 MJ/Kg

0 Kg/H

94,010 Kg/H

144.9

BURNER ATOMIZ.
1,340 Kg/H 200

490 Kg/H DESUPERHTR

1,610 Kg/H 1.0MPaG PRV


0 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

5,420 Kg/H

CONSUMPTION
DESUPERHTR

F.O. GAS

2,037 Kg/H 3,850 Kg/H 86.3 g/kW/H

0 Kg/H 0 Kg/H 0 Kg/H 5,420 Kg/H 65,350Kg/H 0 Kg/H

7,210 Kg/H 4,860Kg/H 2,890 Kg/H 220 Kg/H 4,320 Kg/H 644.0KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

FUEL OIL CONSUMPTION RATE

1,690 Kg/H 8,200 Kg/H 50 Kg/H


270 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 32.4 T/DAY 1,180 kW

MAIN CONDR.
0 Kg/H GLAND CONDR. 102,460 Kg/H 100 12,520 Kg/H 59.2 1ST STG. FD.W.HTR 0 Kg/H 50.7 320 Kg/H 90 102,460 Kg/H 49.4 70,770 Kg/H 43.0 125,800 Kg/H 86.4 T.C.V. 79

DIST. PLANT
70,770 Kg/H 32.4

5.07KPaA

DEAERATOR
94,010 Kg/H 3RD STG. FD.W.HTR 128.4 2,890 Kg/H 0.15 MPa 127

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

12,520 Kg/H

16,160 Kg/H 127

2,890 Kg/H 573.5KJ/Kg 130 Kg/H 400 Kg/H 120 Kg/H 10 Kg/H BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM 130 Kg/H 400 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

0 Kg/H

PUMP GENERATOR

16,160 Kg/H 31,690 Kg/H 1,350 Kg/H 79.0 63.8

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR.

0.3MPaG P.R.V. 560 Kg/H 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FUEL GAS HTR FORCING VAPORIZER 560 Kg/H 0 Kg/H

DRAIN CLR

GAS VENT. DRAIN TK

560 Kg/H

780 Kg/H

ACCOMODATION

1,350 Kg/H

100 Kg/H

12,840 Kg/H

16,160 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

DIST.W.TK
0 Kg/H

Heat Balance Diagram


Normal Sea Going Operation 100% MCR On Fuel Oil & Gas Fuel

ATMOS DRAIN TK
0 Kg/H 560 Kg/H

12229/30

MA1-ZB01-2

93,520 Kg/H 870 Kg/H

90,250 Kg/H

84,630 Kg/H

0 Kg/H 130 Kg/H 84,630 Kg/H

LOSSES
3,270 Kg/H 0 Kg/H

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 23,600 kW 80.0 RPM 5.88 MPaG 510 5.07 KPaA
S.W. TEMP. AT 27

94,390 Kg/H 6.0/1.0MPaG PRV 870 Kg/H 6.0MPaG 287 6.03MPaG 515

A
90 Kg/H
GLAND LEAK

5,620 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO.

5.88MPaG 510

S.A.H.

5.88MPaG 510

MAIN FD.P.T.

5.88MPaG 510
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
GLAND SEAL

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

0 Kg/H

0 Kg/H

3,180 Kg/H

5,570 Kg/H

0 Kg/H

0 Kg/H

1,930 Kg/H

9,240 Kg/H

8,260 Kg/H

0.130MPaA

MAIN BOILER
0 Kg/H 4,330 Kg/H 0 Kg/H

1.62MPaG342

0.65MPaG225

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY 6.03 MPaG 515 147.8 84.0 % GAS 55.59 MJ/Kg

0 Kg/H

94,390 Kg/H

147.8

BURNER ATOMIZ.
2,010 Kg/H 200

180Kg/H DESUPERHTR

1,930 Kg/H 1.0MPaG PRV


0 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

HIGH CALORIFIC VALUE


5,570 Kg/H

CONSUMPTION
DESUPERHTR

0 Kg/H 0 Kg/H 0 Kg/H 5,570 Kg/H 65,060Kg/H 0 Kg/H

GAS

5,533 Kg/H 86.3 g/kW/H

7,760 Kg/H 4,670Kg/H 3,430 Kg/H 270 Kg/H 4,330 Kg/H 662.8KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

FUEL OIL CONSUMPTION RATE

1,490 Kg/H 8,260 Kg/H 50 Kg/H


270 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 25.2 T/DAY 1,240 kW

MAIN CONDR.
0 Kg/H GLAND CONDR. 99,130 Kg/H 100 12,590 Kg/H 57.2 1ST STG. FD.W.HTR 0 Kg/H 48.3 320 Kg/H 90 99,130 Kg/H 46.8 70,630 Kg/H 40.6 125,800 Kg/H 86.0 T.C.V. 79

DIST. PLANT
70,630 Kg/H 32.4

5.07KPaA

DEAERATOR
94,750 Kg/H 3RD STG. FD.W.HTR 128.4 3,430 Kg/H 0.15 MPa 127

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

12,590 Kg/H

12,530 Kg/H 127

3,430 Kg/H 583.2KJ/Kg 0Kg/H 380 Kg/H 120 Kg/H 10 Kg/H BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM 0Kg/H 380 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

0 Kg/H

PUMP GENERATOR

12,530 Kg/H 28,500 Kg/H 1,050 Kg/H 79.0 62.5

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR.

0.3MPaG P.R.V. 680 Kg/H 700 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FUEL GAS HTR FORCING VAPORIZER 680 Kg/H 700 Kg/H

DRAIN CLR

GAS VENT. DRAIN TK

1,380Kg/H

630 Kg/H

ACCOMODATION

1,050 Kg/H

100 Kg/H

12,910 Kg/H

12,530 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

DIST.W.TK
0 Kg/H

Heat Balance Diagram


Normal Sea Going Operation 100% MCR On Gas Fuel

ATMOS DRAIN TK
0 Kg/H 1,380 Kg/H

12229/30

MA1-ZB01-3

24,320 Kg/H 460 Kg/H

21,540 Kg/H

11,030 Kg/H

500 Kg/H

0 Kg/H Kg/H

LOSSES
0 Kg/H 2,780 Kg/H 10.520 Kg/H 10.520 Kg/H 500 Kg/H 4,550 Kg/H
5,010 Kg/H 94,390 Kg/H 6.03MPaG 515 6.0/1.0MPaG PRV 6.0MPaG 297

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 0 kW 0 RPM 5.88 MPaG 463 4.37 KPaA
S.W. TEMP. AT 27

A
90 Kg/H
GLAND LEAK

A
50 Kg/H
GLAND LEAK

A
50 Kg/H
GLAND LEAK

GLAND LEAK

ECO. S.A.H.

MPaG

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 458

MAIN FD.P.T.

5.88MPaG 458
GLAND SEAL

MAIN T/G
10,470 Kg/H

5.88MPaG 458
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

500 Kg/H

10,470 Kg/H

4,550 Kg/H

2,690 Kg/H

0 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER
1,640 Kg/H

MPaG

MPaG

0 Kg/H

0 Kg/H

MAIN BOILER
MPaA

0 Kg/H

STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE

6.03 MPaG 468 139.6 86.7 % 43.03 MJ/Kg

500 Kg/H

29,330 Kg/H

139.6

BURNER ATOMIZ.
540 Kg/H 200

360 Kg/H DESUPERHTR

Kg/H 1.0MPaG PRV


3,660 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

10,470 Kg/H
DESUPERHTR

20,940 Kg/H

CONSUMPTION
0 Kg/H 0 Kg/H 0 Kg/H 20,940 Kg/H 1,000Kg/H 0 Kg/H

F.O.

2,012 Kg/H

2,180 Kg/H 3,670Kg/H 1,640 Kg/H 759.9 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

1,480 Kg/H Kg/H 50 Kg/H


190 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 4,980 kW

540 Kg/H

10 Kg/H

MAIN CONDR.
20,000 Kg/H GLAND CONDR.

DIST. PLANT
25,720 Kg/H 24,120 Kg/H 29.9 Kg/H T.C.V. 24,120 Kg/H 29.9

5.07KPaA

DEAERATOR
94,750 Kg/H 3RD STG. FD.W.HTR 128.4 0 Kg/H 0.15 MPa 127

25,720 Kg/H 45.8 2,180 Kg/H 51.8 1ST STG. FD.W.HTR 540 Kg/H 34.6 240 Kg/H 90

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

31.2

0 Kg/H

Kg/H 540 Kg/H 549.3KJ/Kg 130 Kg/H 160 Kg/H 120 Kg/H PURIF.L.O.HTR 10 Kg/H TRACING STM BLR F.O.HTR F.O.SETT.& SIDE TK 130 Kg/H 160 Kg/H

DIST.PLANT CIRC.W. TK DRAIN CLR Kg/H Kg/H 1,600 Kg/H 52.1

2,180 Kg/H

PUMP GENERATOR

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR. DIST.W.TK

540 Kg/H

Kg/H

ACCOMODATION 0.3MPaG P.R.V. 0 Kg/H FUEL GAS HTR 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FORCING VAPORIZER

100 Kg/H DRAIN CLR GAS VENT. DRAIN TK

240 Kg/H

820 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

0 Kg/H

0 Kg/H 0 Kg/H

0 Kg/H

Heat Balance Diagram


ATMOS DRAIN TK

Unload

0 Kg/H 0 Kg/H

12229/30

MA1-ZB01-4

10,520 Kg/H 780 Kg/H

7,110Kg/H

500 Kg/H

500 Kg/H

0 Kg/H 0 Kg/H

LOSSES
0 Kg/H 3,410 Kg/H 500 Kg/H 6,610 Kg/H 69,750 Kg/H
70,530 Kg/H 81,050 Kg/H 6.03MPaG 515 6.0/1.0MPaG PRV 5.15MPaG339

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 0 kW 0 RPM 5.88 MPaG 510 7.40 KPaA
S.W. TEMP. AT 27

A
90 Kg/H
GLAND LEAK

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
50 Kg/H
GLAND LEAK

GLAND LEAK

ECO. S.A.H.

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 510

MAIN FD.P.T.

5.88MPaG 510
GLAND SEAL

MAIN T/G

5.88MPaG 510
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

500 Kg/H

3,300 Kg/H

12,710 Kg/H

57,040 Kg/H

0 Kg/H

3,320 Kg/H

0 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER

6,560 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY 6.03 MPaG 515 136.6 84.5 % F.O. HIGH CALORIFIC VALUE GAS F.O. GAS 43.03 MJ/Kg 55.59 MJ/Kg 608 Kg/H 3,852 Kg/H

500 Kg/H

81,050 Kg/H

136.6

BURNER ATOMIZ.
990 Kg/H 200

490 Kg/H DESUPERHTR

0 Kg/H

1.0MPaG PRV
11,320 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

6,560 Kg/H
DESUPERHTR

6,560 Kg/H

CONSUMPTION
62,670 Kg/H 0 Kg/H 6,560 Kg/H 62,670 Kg/H 1,000Kg/H 0 Kg/H

4,480 Kg/H 9,660 Kg/H 1,180 Kg/H 3,300 Kg/H 759.9 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

6,840 Kg/H 0 Kg/H 50 Kg/H


140 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 1,571 kW

80 Kg/H

5,640 Kg/H

39.8

MAIN CONDR. DIST. PLANT


69,070 Kg/H 39.8 Kg/H 74,710 Kg/H 39.8

20,000 Kg/H GLAND CONDR.

7.40 KPaA

DEAERATOR
101,130 Kg/H 3RD STG. FD.W.HTR 128.2 0 Kg/H 0.15 MPa 127

71,520 Kg/H 48.7 1ST STG. FD.W.HTR 1,180 Kg/H 41.0 4,880 Kg/H 240 Kg/H 42.0 90

71,520 Kg/H 39.8

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM

Kg/H 1,180 Kg/H 543.0 KJ/Kg 40 Kg/H 140 Kg/H 120 Kg/H PURIF.L.O.HTR 10 Kg/H TRACING STM BLR F.O.HTR F.O.SETT.& SIDE TK 40 Kg/H 140 Kg/H

T.C.V.

0 Kg/H

EXHAUST STEAM FEED or CONDENSATE DRAIN

DIST.PLANT CIRC.W. TK DRAIN CLR Kg/H Kg/H 2,450 Kg/H 51.3

4,480 Kg/H

PUMP GENERATOR

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR. DIST.W.TK

430 Kg/H

190 Kg/H

Kg/H

ACCOMODATION 0.3MPaG P.R.V. 560 Kg/H FUEL GAS HTR 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FORCING VAPORIZER

100 Kg/H DRAIN CLR GAS VENT. DRAIN TK

1,270 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

0 Kg/H

560 Kg/H 0 Kg/H

560 Kg/H

Heat Balance Diagram


Port Hotel Load and Full Dump
ATMOS DRAIN TK

with Design BOR

0 Kg/H 560 Kg/H

12229/30

MA1-ZB01-5

18,210 Kg/H 400 Kg/H

15,380Kg/H

7,940 Kg/H

500 Kg/H

0 Kg/H Kg/H

LOSSES
0 Kg/H 2,830 Kg/H 7,440 Kg/H 7,440 Kg/H 500 Kg/H 2,920 Kg/H
3,320 Kg/H 21,530 Kg/H 6.03MPaG 460 6.0/1.0MPaG PRV 6.0MPaG 290

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 0 kW 0 RPM 5.88 MPaG 455 4.15 KPaA
S.W. TEMP. AT 27

A
90 Kg/H
GLAND LEAK

A
50 Kg/H
GLAND LEAK

A
50 Kg/H
GLAND LEAK

GLAND LEAK

ECO. S.A.H.

MPaG

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 455

MAIN FD.P.T.

5.88MPaG 455
GLAND SEAL

MAIN T/G

5.88MPaG 455
GLAND SEAL

MAIN T/G
M M

7,390 Kg/H

GLAND SEAL

500 Kg/H

2,740 Kg/H

0 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER

MPaG

MPaG

1,290 Kg/H

2,920 Kg/H

0 Kg/H

0 Kg/H

7,390 Kg/H

0 Kg/H

MAIN BOILER
MPaA

STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE

6.03 MPaG 460 140.1 85.7 % 43.03 MJ/Kg

500 Kg/H

21,530 Kg/H

140.1

BURNER ATOMIZ.
500 Kg/H 200

360 Kg/H DESUPERHTR

Kg/H

1.0MPaG PRV
2,070 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

7,390 Kg/H
DESUPERHTR

14,780 Kg/H

CONSUMPTION
0 Kg/H 0 Kg/H 0 Kg/H 14,780 Kg/H 1,000Kg/H 0 Kg/H

F.O.

1,480 Kg/H

1,700 Kg/H 2,610 Kg/H 1,290 Kg/H 759.9 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

370 Kg/H
Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 3,140 kW

410 Kg/H

10 Kg/H

50 Kg/H
20,000 Kg/H GLAND CONDR.

190 Kg/H

MAIN CONDR. DIST. PLANT


18,980 Kg/H 35.8 1,700 Kg/H 240 Kg/H 36.3 90 30.7 17,480 Kg/H 29.0 Kg/H T.C.V. 17,480 Kg/H 29.0

7.40 KPaA

DEAERATOR
41,540 Kg/H 3RD STG. FD.W.HTR 130.1 0 Kg/H 0.15 MPa 127

18,980 Kg/H 47.1 1ST STG. FD.W.HTR 410 Kg/H

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

0 Kg/H

Kg/H 410 Kg/H 550.0 KJ/Kg 100 Kg/H 160 Kg/H 120 Kg/H PURIF.L.O.HTR 10 Kg/H TRACING STM BLR F.O.HTR F.O.SETT.& SIDE TK 100 Kg/H 160 Kg/H

DIST.PLANT CIRC.W. TK DRAIN CLR Kg/H Kg/H 1,500 Kg/H 52.2

1,700 Kg/H

PUMP GENERATOR

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR. DIST.W.TK

500 Kg/H

240 Kg/H

Kg/H

ACCOMODATION 0.3MPaG P.R.V. 0 Kg/H FUEL GAS HTR 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FORCING VAPORIZER

100 Kg/H DRAIN CLR GAS VENT. DRAIN TK

760 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

0 Kg/H

0 Kg/H 0 Kg/H

0 Kg/H

Heat Balance Diagram


ATMOS DRAIN TK

Loading

0 Kg/H 0 Kg/H

12229/30

MA1-ZB01-6

13,220 Kg/H 780 Kg/H

7,110Kg/H

0 Kg/H

0 Kg/H

0 Kg/H 0 Kg/H

LOSSES
3,090 Kg/H 10,130 Kg/H 0 Kg/H 66,820 Kg/H
67,600 Kg/H 80,820Kg/H 6.03MPaG 515 6.0/1.0MPaG PRV 5.15MPaG339

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 0 kW 0 RPM 5.88 MPaG 510

A
90 Kg/H
GLAND LEAK

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO. S.A.H.

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE

5.88MPaG 450

MAIN FD.P.T.

5.88MPaG 450
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

3,310 Kg/H

10,740 Kg/H

56,080 Kg/H

10,080 Kg/H

0 Kg/H

0 Kg/H

3,000 Kg/H

0 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER

0 Kg/H

0 Kg/H

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY 6.03 MPaG 515 138.7 84.5 % F.O. HIGH CALORIFIC VALUE GAS F.O. GAS 43.03 MJ/Kg 55.59 MJ/Kg 608 Kg/H 3,852 Kg/H

0 Kg/H

80,820 Kg/H

138.7

BURNER ATOMIZ.
980 Kg/H 200

490 Kg/H DESUPERHTR

0 Kg/H

1.0MPaG PRV
9,350 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

6,560 Kg/H
DESUPERHTR

10,080 Kg/H

CONSUMPTION
61,970 Kg/H

4,720 Kg/H 7,630 Kg/H 1,410 Kg/H 3,310 Kg/H 759.9 KJ/Kg

MAIN DUMP V. 0 Kg/H 0 Kg/H 0 Kg/H 61,920 Kg/H 10,080 Kg/H 0.5/0.17MPaG P.R.V.

4,630 Kg/H 0 Kg/H 50 Kg/H


140 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 1,571 kW

80 Kg/H

5,840 Kg/H

29.5

MAIN CONDR. DIST. PLANT


0 Kg/H Kg/H 0 Kg/H

20,000 Kg/H GLAND CONDR.

DEAERATOR
100,900 Kg/H 3RD STG. FD.W.HTR 127.4 0 Kg/H 0.15 MPa 127

73,320 Kg/H 78.4 1ST STG. FD.W.HTR 1,410 Kg/H 72.3 4,720 Kg/H 240 Kg/H 61.0 90

73,320 Kg/H 69.9

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM

Kg/H 1,41 Kg/H 553.0 KJ/Kg 30 Kg/H 140 Kg/H 120 Kg/H PURIF.L.O.HTR 10 Kg/H TRACING STM BLR F.O.HTR F.O.SETT.& SIDE TK 30 Kg/H 140 Kg/H 120 Kg/H 10 Kg/H

T.C.V.

4,720 Kg/H

EXHAUST STEAM FEED or CONDENSATE DRAIN

DIST.PLANT CIRC.W. TK DRAIN CLR Kg/H 79,160 Kg/H Kg/H 69.9

0 Kg/H

PUMP GENERATOR

MAKE-UP V.

AUX. CONDR. DIST.W.TK

420 Kg/H

Kg/H

ACCOMODATION 0.3MPaG P.R.V. 560 Kg/H FUEL GAS HTR 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FORCING VAPORIZER

100 Kg/H DRAIN CLR GAS VENT. DRAIN TK

4,910 Kg/H

1,270 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

72,000 Kg/H 75.0

560 Kg/H 0 Kg/H

560 Kg/H

Heat Balance Diagram


Port Hotel Load and Full Dump to AUX. COND.
ATMOS DRAIN TK

0 Kg/H 560 Kg/H

with Design BOR

12229/30

MA1-ZB01-7

8,090 Kg/H 330 Kg/H

5,550 Kg/H

500 Kg/H

500 Kg/H

0 Kg/H 0 Kg/H

LOSSES
0 Kg/H 0 Kg/H 2,540 Kg/H 5,050 Kg/H 500 Kg/H 1,780 Kg/H

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 0 kW 0 RPM 5.88 MPaG 415 3.80 KPaA
S.W. TEMP. AT 27

2,110 Kg/H

10,200 Kg/H 6.03MPaG 420

A
90 Kg/H
GLAND LEAK

A
50 Kg/H
GLAND LEAK

A
GLAND LEAK

GLAND LEAK

6.0/1.0MPaG PRV

6.0MPaG 287

0 Kg/H

ECO.

S.A.H.

5.88MPaG 415

MAIN FD.P.T.

5.88MPaG 415
GLAND SEAL

MAIN T/G

5.88MPaG 415
GLAND SEAL

MAIN T/G
GLAND SEAL

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

670 Kg/H

1,780 Kg/H

0 Kg/H

0 Kg/H

0 Kg/H

0 Kg/H

2,450 Kg/H

5,000 Kg/H

500 Kg/H

0 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY 6.03 MPaG 420 140.1 83.2 % F.O. HIGH CALORIFIC VALUE 43.03 MJ/Kg

500 Kg/H

10,200 Kg/H

140.1

BURNER ATOMIZ.
440 Kg/H 200

490 Kg/H DESUPERHTR

0 Kg/H

1.0MPaG PRV
850 Kg/H 1.0/0.24 MPaG PRV 770 kg/H EXH.STEAM DUMP V.

5,770 Kg/H
DESUPERHTR

5,770 Kg/H

CONSUMPTION
0 Kg/H 0 Kg/H 0 Kg/H 5,770 Kg/H 1,000Kg/H 0 Kg/H

F.O.

787 Kg/H

850 Kg/H 1,180 Kg/H 670 Kg/H 0 Kg/H 759.9 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

0 Kg/H
0 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 900 kW

180 Kg/H

50 Kg/H
20,000 Kg/H

140 Kg/H

MAIN CONDR.
GLAND CONDR. 9,070 Kg/H 49.4 1ST STG. FD.W.HTR 180 Kg/H 37.0 850 Kg/H 190 Kg/H 38.0 90 9,070 Kg/H 30.8 7,620 Kg/H 27.5 Kg/H T.C.V.

DIST. PLANT
7,620 Kg/H 27.5

7.40 KPaA

DEAERATOR
30,200 Kg/H 3RD STG. FD.W.HTR 130.8 0 Kg/H 0.15 MPa 127

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

0 Kg/H

Kg/H 180 Kg/H 553.5 KJ/Kg 50 Kg/H 140 Kg/H 120 Kg/H 10 Kg/H BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM 50 Kg/H 140 Kg/H

DIST.PLANT CIRC.W. TK Kg/H Kg/H 1,450 Kg/H 49.3

850 Kg/H

PUMP GENERATOR

DRAIN CLR

120 Kg/H 10 Kg/H

MAKE-UP V.

AUX. CONDR.

440 Kg/H

150 Kg/H

Kg/H

ACCOMODATION 0.3MPaG P.R.V. 0 Kg/H 0 Kg/H 0 Kg/H DECK USE 0.6MPaG P.R.V. FUEL GAS HTR FORCING VAPORIZER

100 Kg/H DRAIN CLR

820 Kg/H

20 Kg/H 100 Kg/H

HOT W. HTR

20 Kg/H

DIST.W.TK
0 Kg/H

0 Kg/H 0 Kg/H

GAS VENT. DRAIN TK

0 Kg/H

Heat Balance Diagram


ATMOS DRAIN TK

Port Rest

0 Kg/H 0 Kg/H

12229/30

MA1-ZB01-8

100,570 Kg/H 910 Kg/H

97,220 Kg/H

91,240 Kg/H

0 Kg/H 130 Kg/H

LOSSES
3,350 Kg/H 0 Kg/H
101,480 Kg/H 6.0/1.0MPaG PRV 910 Kg/H 6.0MPaG 287 6.03MPaG 515

91,240 Kg/H

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 23,600 kW 80.0 RPM 5.88 MPaG 510 3.41 KPaA
S.W. TEMP. AT 16

A
90 Kg/H
GLAND LEAK

5,980 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO. S.A.H.

5.88MPaG 510

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 510

MAIN FD.P.T.

5.88MPaG 510
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

3,260 Kg/H

10,110 Kg/H

10,080 Kg/H

9,120 Kg/H

0.106MPaA 101

MAIN BOILER
0 Kg/H 4,840 Kg/H 0 Kg/H

1.65MPaG343

0.48MPaG215

0 Kg/H

0 Kg/H

5,930 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE 6.03 MPaG 515 144.4 87.2 % 43.03 MJ/Kg

0 Kg/H

101,480 Kg/H

144.5

BURNER ATOMIZ.
10,910 Kg/H 200

460 Kg/H DESUPERHTR

10,110 Kg/H 1.0MPaG PRV


0 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

5,930 Kg/H

CONSUMPTION
DESUPERHTR

F.O.

7,400 Kg/H

0 Kg/H 61,800 Kg/H 0 Kg/H 0 Kg/H 5,930 Kg/H 0 Kg/H

7,920 Kg/H 5,420 Kg/H 3,080 Kg/H 1,260 Kg/H 4,840 Kg/H 644.0 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

2,160 Kg/H 9,120 Kg/H 50 Kg/H


270 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 32.9 T/DAY 1,370 kW

MAIN CONDR.
0 Kg/H GLAND CONDR.

DIST. PLANT
111,660 Kg/H 67,730 Kg/H 36.7 125,800 Kg/H 86.4 T.C.V. 79 67,730 Kg/H 25.4

3.41 KPaA

DEAERATOR
102,740 Kg/H 3RD STG. FD.W.HTR 128.3 3,080 Kg/H 0.15 MPa 127

111,660 Kg/H 99.4 13,960 Kg/H 58.6 1ST STG. FD.W.HTR 0 Kg/H 49.1 320 Kg/H 90

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

47.9

13,960 Kg/H

17,370 Kg/H 127

3,080 Kg/H 3,200 Kg/H 480 Kg/H 550 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 820 Kg/H 0.3MPaG P.R.V. 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 0.6MPaG P.R.V. CMR / MOTOR RM HTR FUEL GAS HTR FORCING VAPORIZER CMR F.W. HTR DECK USE 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 5,690 Kg/H DRAIN CLR GAS VENT. DRAIN TK 3,980Kg/H 574.4 KJ/Kg ENG RM HTR BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM HYDRANT HTR HOT W. HTR ACCOMODATION 3,200 Kg/H 480 Kg/H 43,930 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 5,220 Kg/H 14,280 Kg/H 17,370 Kg/H 1,370 Kg/H 820 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

0 Kg/H

PUMP GENERATOR

17,370 Kg/H 1,370 Kg/H 79.0 65.2

550 Kg/H

MAKE-UP V.

AUX. CONDR.

DIST.W.TK
0 Kg/H

Heat Balance Diagram


Normal Sea Going Operation 100% MCR On Fuel Oil in Winter Condition

ATMOS DRAIN TK

12229/30

MA1-ZB01-9

91,900 Kg/H 860 Kg/H

88,640 Kg/H

82,750 Kg/H

0 Kg/H 130 Kg/H

LOSSES
3,250 Kg/H 0 Kg/H
92,750 Kg/H 6.0/1.0MPaG PRV 860 Kg/H 6.0MPaG 287 6.03MPaG 515

82,750 Kg/H

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 21,240 kW 77.3 RPM 5.88 MPaG 510 3.33 KPaA
S.W. TEMP. AT 15

A
90 Kg/H
GLAND LEAK

5,980 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO. S.A.H.

5.88MPaG 510

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 510

MAIN FD.P.T.

5.88MPaG 510
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

3,160 Kg/H

10,110 Kg/H

8,700 Kg/H

7,940 Kg/H

0.140MPaA 109

MAIN BOILER
0 Kg/H 4,430 Kg/H 0 Kg/H

1.45MPaG332

0.37MPaG211

0 Kg/H

0 Kg/H

5,840 Kg/H

0 Kg/H

0 Kg/H

MAIN BOILER
STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE 6.03 MPaG 515 144.8 87.2 % 43.03 MJ/Kg

0 Kg/H

92,750 Kg/H

140.2

BURNER ATOMIZ.
10,870 Kg/H 200

460 Kg/H DESUPERHTR

10,110 Kg/H 1.0MPaG PRV


0 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

5,840 Kg/H

CONSUMPTION
DESUPERHTR

F.O.

6,800 Kg/H

0 Kg/H 55,870 Kg/H 0 Kg/H 0 Kg/H 5,840 Kg/H 0 Kg/H

6,480 Kg/H 4,620 Kg/H 2,050 Kg/H 1,220 Kg/H 4,430 Kg/H 614.0 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

1,460 Kg/H 8,700 Kg/H 50 Kg/H


270 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 31.7 T/DAY 1,340 kW

MAIN CONDR.
0 Kg/H GLAND CONDR.

DIST. PLANT
103,880 Kg/H 61,710 Kg/H 37.3 125,800 Kg/H 86.4 T.C.V. 79 61,710 Kg/H 25.5

3.33 KPaA

DEAERATOR
93,970 Kg/H 3RD STG. FD.W.HTR 128.4 2,050 Kg/H 0.15 MPa 127

103,880 Kg/H 101.8 13,130 Kg/H 58.6 1ST STG. FD.W.HTR 0 Kg/H 50.0 320 Kg/H 90

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

48.7

13,130 Kg/H

16,530 Kg/H 127

2,050 Kg/H 3,200 Kg/H 440 Kg/H 550 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 820 Kg/H 0.3MPaG P.R.V. 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 0.6MPaG P.R.V. CMR / MOTOR RM HTR FUEL GAS HTR FORCING VAPORIZER CMR F.W. HTR DECK USE 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 5,690 Kg/H DRAIN CLR GAS VENT. DRAIN TK 3,980Kg/H 559.4 KJ/Kg ENG RM HTR BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM HYDRANT HTR HOT W. HTR ACCOMODATION 3,200 Kg/H 440 Kg/H 42,170 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 5,180 Kg/H 13,450 Kg/H 16,530 Kg/H 1,320 Kg/H 820 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

0 Kg/H

PUMP GENERATOR

16,420 Kg/H 1,320 Kg/H 79.0 65.5

550 Kg/H

MAKE-UP V.

AUX. CONDR.

DIST.W.TK
0 Kg/H

Heat Balance Diagram


Normal Sea Going Operation 90% MCR On Fuel Oil in Winter Condition

ATMOS DRAIN TK

12229/30

MA1-ZB01-10

16,380 Kg/H 610 Kg/H

13,680 Kg/H

8,490 Kg/H

0 Kg/H 0 Kg/H 8,940 Kg/H

LOSSES
2,700 Kg/H 36,390 Kg/H
37,000 Kg/H 5.79 MPaG 325 53,380 Kg/H 6.03MPaG 504 6.0/1.0MPaG PRV

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 2,190 kW 35.0 RPM 5.88 MPaG 499 3.33 KPaA
S.W. TEMP. AT 17

A
90 Kg/H
GLAND LEAK

4,740 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO. S.A.H.

5.88MPaG 499

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 499

MAIN FD.P.T.

5.88MPaG 499
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

320 Kg/H

2,480 Kg/H

18,460 Kg/H

17,930 Kg/H

2,610 Kg/H

Kg/H

Kg/H

Kg/H

MAIN BOILER

MPaG

MPaG

0 Kg/H

0 Kg/H

4,690 Kg/H

0 Kg/H

MAIN BOILER
MPaA

STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE

6.03 MPaG 504 140.0 86.6 % 43.03 MJ/Kg

320 Kg/H

53,380 Kg/H

140.0

BURNER ATOMIZ.
10,600 Kg/H 200

470 Kg/H DESUPERHTR

0 Kg/H 1.0MPaG PRV


8,010 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

4,690 Kg/H

CONSUMPTION
DESUPERHTR

F.O.

3,470 Kg/H

19,500 Kg/H 0 Kg/H 4,690 Kg/H 19,500 Kg/H 9,260 Kg/H 0 Kg/H

3,470 Kg/H 6,830 Kg/H 620 Kg/H 2,480 Kg/H 613.4 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

4,540 Kg/H 0 Kg/H 50 Kg/H


140 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 25.9 T/DAY 1,025 kW

990 Kg/H

1,570 Kg/H

0 Kg/H GLAND CONDR.

25.0

MAIN CONDR. DIST. PLANT


35,350 Kg/H 41.9 125,800 Kg/H 86.4 36,920 Kg/H 25.0

3.33 KPaA

DEAERATOR
54,000Kg/H 3RD STG. FD.W.HTR 129.6 0 Kg/H 0.15 MPa 127

59,660 Kg/H 61.7 3,470 Kg/H 57.5 1ST STG. FD.W.HTR 990 Kg/H 56.4 190 Kg/H 90

59,660 Kg/H 53.9

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM

T.C.V.

79

0 Kg/H

EXHAUST STEAM FEED or CONDENSATE DRAIN

12,440 Kg/H 127

980 Kg/H 3,200 Kg/H 220 Kg/H 500 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 820 Kg/H 0.3MPaG P.R.V. 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 0.6MPaG P.R.V. CMR / MOTOR RM HTR FUEL GAS HTR FORCING VAPORIZER CMR F.W. HTR DECK USE 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 5,690 Kg/H DRAIN CLR GAS VENT. DRAIN TK 3,980Kg/H 558.5 KJ/Kg ENG RM HTR BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM HYDRANT HTR HOT W. HTR ACCOMODATION 3,200 Kg/H 220 Kg/H 24,310 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 4,910 Kg/H 12,440 Kg/H 1,080 Kg/H 190 Kg/H 820 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

3,470 Kg/H

PUMP GENERATOR

12,440 Kg/H 1,080 Kg/H 79.0 71.5

500 Kg/H

MAKE-UP V.

AUX. CONDR.

DIST.W.TK
0 Kg/H

Heat Balance Diagram


Half Ahead ( Winter Condition )

ATMOS DRAIN TK

12229/30

MA1-ZB01-11

13,930 Kg/H 600 Kg/H

11,240 Kg/H

6,500 Kg/H

0 Kg/H 0 Kg/H 6,500 Kg/H

LOSSES
2,690 Kg/H 38,060 Kg/H
38,660 Kg/H 5.78 MPaG 326 52,590 Kg/H 6.03MPaG 502 6.0/1.0MPaG PRV

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER 1,470 kW 30.0 RPM 5.88 MPaG 497 3.33 KPaA
S.W. TEMP. AT 19

A
90 Kg/H
GLAND LEAK

4,740 Kg/H

A
50 Kg/H
GLAND LEAK

0 Kg/H

A
GLAND LEAK

GLAND LEAK

0 Kg/H

ECO. S.A.H.

5.88MPaG 497

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 497

MAIN FD.P.T.

5.88MPaG 497
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

350 Kg/H

2,420 Kg/H

18,320 Kg/H

19,740 Kg/H

2,600 Kg/H

Kg/H

Kg/H

Kg/H

MAIN BOILER

MPaG

MPaG

0 Kg/H

0 Kg/H

4,690 Kg/H

0 Kg/H

MAIN BOILER
MPaA

STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE

6.03 MPaG 502 140.1 86.7 % 43.03 MJ/Kg

350 Kg/H

52,590 Kg/H

140.1

BURNER ATOMIZ.
10,600 Kg/H 200

470 Kg/H DESUPERHTR

0 Kg/H 1.0MPaG PRV


7,870 Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

4,690 Kg/H

CONSUMPTION
DESUPERHTR

F.O.

3,360 Kg/H

21,500 Kg/H 0 Kg/H 4,690 Kg/H 21,500 Kg/H 6,850 Kg/H 0 Kg/H

3,400 Kg/H 6,720 Kg/H 620 Kg/H 2,420 Kg/H 759.9 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

4,470 Kg/H 0 Kg/H 50 Kg/H


140 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 25.7 T/DAY 1,025 kW

980 Kg/H

1,760 Kg/H

0 Kg/H GLAND CONDR.

25.0

MAIN CONDR. DIST. PLANT


34,680 Kg/H 42.1 125,800 Kg/H 86.4 36,440 Kg/H 25.0

3.33 KPaA

DEAERATOR
53,210Kg/H 3RD STG. FD.W.HTR 129.7 0 Kg/H 0.15 MPa 127

58,900 Kg/H 61.8 3,400 Kg/H 57.8 1ST STG. FD.W.HTR 980 Kg/H 56.7 190 Kg/H 90

58,900 Kg/H 54.2

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM

T.C.V.

79

0 Kg/H

EXHAUST STEAM FEED or CONDENSATE DRAIN

12,360 Kg/H 127

980 Kg/H 3,200 Kg/H 220 Kg/H 500 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 820 Kg/H 0.3MPaG P.R.V. 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 0.6MPaG P.R.V. CMR / MOTOR RM HTR FUEL GAS HTR FORCING VAPORIZER CMR F.W. HTR DECK USE 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 5,690 Kg/H DRAIN CLR GAS VENT. DRAIN TK 3,980Kg/H 548.9 KJ/Kg ENG RM HTR BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM HYDRANT HTR HOT W. HTR ACCOMODATION 3,200 Kg/H 220 Kg/H 24,220 Kg/H 120 Kg/H 30 Kg/H 0 Kg/H 20 Kg/H 4,910 Kg/H 12,360 Kg/H 1,070 Kg/H 190 Kg/H 820 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

3,400 Kg/H

PUMP GENERATOR

12,360 Kg/H 1,070 Kg/H 79.0 71.5

500 Kg/H

MAKE-UP V.

AUX. CONDR.

DIST.W.TK
0 Kg/H

Heat Balance Diagram


Slow Ahead ( Winter Condition )

ATMOS DRAIN TK

12229/30

MA1-ZB01-12

10,080 Kg/H 430 Kg/H

7,120 Kg/H

500 Kg/H

0 Kg/H 0 Kg/H 500 Kg/H

LOSSES
0 Kg/H 2,960 Kg/H 15,390 Kg/H
15,800 Kg/H 5.98 MPaG 318 25,900 Kg/H 6.03MPaG 468 6.0/1.0MPaG PRV

DESIGN CONDITION
MAIN TURBINE
SHAFT HORSEPOWER kW RPM 5.88 MPaG 463 1.36 KPaA
S.W. TEMP. AT 3

A
90 Kg/H
GLAND LEAK

6,620 Kg/H

A
50 Kg/H
GLAND LEAK

A
GLAND LEAK

0 Kg/H

0 Kg/H

GLAND LEAK

ECO. S.A.H.

5.88MPaG 463

H.P. TURB.

L.P.TURB.

ASTERN TURB.

SHAFT REVOLUTION STEAM PRESSURE STEAM TEMPERATURE CONDR PRESS.

5.88MPaG 463

MAIN FD.P.T.

5.88MPaG 463
GLAND SEAL

MAIN T/G
GLAND SEAL

MAIN T/G
M M

GLAND SEAL

500 Kg/H

1,620 Kg/H

15,390 Kg/H

0 Kg/H

2,870 Kg/H

Kg/H

Kg/H

Kg/H

MAIN BOILER

MPaG

MPaG

0 Kg/H

0 Kg/H

6,570 Kg/H

0 Kg/H

MAIN BOILER
MPaA

STEAM PRESSURE STEAM TEMPERATURE FEED W. TEMPERATURE BOILER EFFICIENCY F.O. HIGH CALORIFIC VALUE

6.03 MPaG 468 140.1 81.9 % 43.03 MJ/Kg

500 Kg/H

25,900 Kg/H

140.1

BURNER ATOMIZ.
12,920 Kg/H 200

490 Kg/H DESUPERHTR

Kg/H 1.0MPaG PRV


2,640Kg/H 1.0/0.24 MPaG PRV 0 kg/H EXH.STEAM DUMP V.

6,570 Kg/H

CONSUMPTION
DESUPERHTR

F.O.

1,750 Kg/H

0 Kg/H 0 Kg/H 0 Kg/H 6,570 Kg/H 1,000 Kg/H 0 Kg/H

2,100 Kg/H 2,910Kg/H 660 Kg/H 1,620 Kg/H 759.9 KJ/Kg

MAIN DUMP V. 0.5/0.17MPaG P.R.V.

540 Kg/H Kg/H 50 Kg/H


140 Kg/H

OTHERS
DIST.W.PRODUCT TOTAL GENERATOR LOAD 1,370 kW

480 Kg/H

MAIN CONDR.
20,000 Kg/H GLAND CONDR.

DIST. PLANT
23,700 Kg/H 9,670 Kg/H 3.7 Kg/H T.C.V. 9,670 Kg/H 3.7

1.36 KPaA

DEAERATOR
46,560 Kg/H 3RD STG. FD.W.HTR 128.4 0 Kg/H 0.15 MPa 127

23,700 Kg/H 55.4 2,100 Kg/H 45.6 1ST STG. FD.W.HTR 480 Kg/H 44.6 190 Kg/H 90

SYMBOLS : SUPERHEATED STEAM AUXILIARY STEAM BLEED STEAM EXHAUST STEAM FEED or CONDENSATE DRAIN

42.2

0 Kg/H

Kg/H

480 Kg/H 3,200 Kg/H 110 Kg/H 480 Kg/H 120 Kg/H 30 Kg/H 2,450 Kg/H 20 Kg/H 820 Kg/H 0.3MPaG P.R.V. 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 0.6MPaG P.R.V. CMR / MOTOR RM HTR FUEL GAS HTR FORCING VAPORIZER CMR F.W. HTR DECK USE 180 Kg/H 0 Kg/H 0 Kg/H 3,800 Kg/H 1,710 Kg/H 5,690 Kg/H DRAIN CLR GAS VENT. DRAIN TK 3,980Kg/H 550.1 KJ/Kg ENG RM HTR BLR F.O.HTR F.O.SETT.& SIDE TK PURIF.L.O.HTR TRACING STM HYDRANT HTR HOT W. HTR ACCOMODATION 3,200 Kg/H 110 Kg/H 24,220 Kg/H 120 Kg/H 30 Kg/H 2,450 Kg/H 20 Kg/H 0 Kg/H 7,230 Kg/H 190 Kg/H 920 Kg/H 820 Kg/H DRAIN CLR

DIST.PLANT CIRC.W. TK

2,100 Kg/H

PUMP GENERATOR

Kg/H 71.5 Kg/H

480 Kg/H

MAKE-UP V.

AUX. CONDR. DIST.W.TK


0 Kg/H

Heat Balance Diagram


ATMOS DRAIN TK

Port Hotel Load ( Winter Condition )

12229/30

MA1-ZB01-13

3.1.1

Superheated Steam System


Procedure for Putting the Superheated Steam System into Service Mitsubishi Heavy Industries Ltd 2 sets Mitsubishi MB-3E Two drum water tube natural circulation 55,000kg/h 46,200kg/h at 100% MCR 6.03 MPa x 515C at superheated steam Drum 7.65 MPa and 7.60 Mpa Superheat outlet 6.40 Mpa It is important when bringing any steam system into service to slowly raise the temperature of the pipes, valves and joints. Heating the various parts of the system too quickly can lead to thermal distortion and damage to joints and packing. The system must be carefully drained of any water during this warming process to prevent steam hammer or water hammer taking place. Mechanical damage can be caused to the surrounding materials. For this reason any water is to be removed from the system before the pressure and temperature are increased. The pressure must be increased gradually to allow expansion of the components to take place at a rate that will not lead to material failure. Any sudden increase in pressure can send shock waves throughout the system which are very likely to cause damage. The superheated steam system has been arranged to allow each section to be warmed though, drained and pressurized at a controlled rate. The boiler main superheat stop valves and the intermediate valves have drains and warming through bypass valves. In principle the section or sections of line to be put into service should have all drains along the line open when shutting down the system and should be found in the same condition prior to commencing warming through. With the section main stop valve closed the bypass valve should be gradually, partially opened. This admits a controlled quantity of steam at low pressure to enter the system. The expansion of the steam across the valve requires some of its internal energy to be used thus lowering its temperature. As the steam pressure builds and the water is driven from the system the drains can be closed in. Similar actions should be taken with the machinery being put into service so that the steam system and the machinery are being drained and gradually warmed though. The time taken and the rate of increase of the pressure in the system are dependant upon the length of the system, the materials and types of jointing and the machinery being prepared. Where temperature and pressure gauges are fitted the increase can be monitored and controlled. Great care must be taken, safety being the governing factor. When sufficient drainage and warming through has taken place the system should be at a similar pressure and temperature as the steam supply with the drains closed in to allow sufficient flow to keep the system clear of water and the bypass valve fully opened. The main section stop valve can now be carefully opened giving due consideration to the pressure and temperature increase that may take place. With the stop valve fully open the drains and bypass valves can now be closed. The drain valves should be closed when the system is in use with a steam flow demand. The procedure for bringing the superheated steam system into operation is described in detail in section 4.3.2 Main Boiler Operation and the procedure for warming up of main turbine is referred to section 4.2.4 Main Turbine Warming-up System. The main feed water pump in stand-by should be warmed up to prepare for automatic changeover of the pumps. The warming up valves fitted around motor steam stop valves 021 and 023VPA should be opened anytime and the stand-by pump turbine is run at revolution 300 to 700rpm.

Boiler Details Maker : No. of sets : Model : Type : Maximum evaporation : Normal evaporation : Steam condition : Safety valve settings :

All the steam requirements for the vessel are generated in the two main boilers. Steam from the steam drum passes to the primary superheater section through an orifice where the pressure drop is measured and converted to a signal for steam flow, which serves as a function of the boiler control system. The steam flows through the primary section of the superheater and then to the secondary superheater section. Taking steam from the primary superheater and leading it through the temperature control desuperheater, situated in the water drum regulates the outlet temperature of the superheated steam. A control valve regulates the outlet from the desuperheater to the secondary superheater depending on the outlet temperature of the steam leaving the boiler. To ensure that there is always a flow through the secondary superheater, a line fitted with an orifice bypasses the temperature control desuperheater and the control valve. The temperature control valve also has a bypass orifice. The main turbine main stop valves 001and 002VPA interconnect both boilers, where a common line supplies the main turbine. A similar arrangement with two main stop valves, 011 and 012VPA, interconnects both supplying turbine generators and boiler feed pump turbines. These circuits are designed to supply the auxiliary machinery from either boiler giving greater flexibility. Warming through bypass valves are provided at all the principal stop valves. Steam from the superheater outlet is led to the internal desuperheater, situated in the steam drum via valve 141B, from where it is distributed to the various desuperheated steam services via valves 145B. Services Supplied from the Superheated Steam System The following machinery is operated from the superheated steam system : Main turbine Main generator turbines Main feed water pump turbines Desuperheated steam system

Controls The warm-up steam shut-off valve for main turbine is automatic closed by any of following signals at auto mode.

High supply steam pressure (1.25MPa) High shaft revolution (0.204rpm)

The auxiliary diesel generator engine will automatically start when the inlet main steam pressure of generator turbine goes down (4.9MPa).

Alarms Sensor Tag No. Function Set point PAH PAL ESD TA H TA L 6.2 MPa 5.2 MPa 530 525 480

(Main boiler superheater outlet steam) PT 502 Pressure PT 502 TS TR TR 467 511 511 Temperature

(Main turbine inlet superheated steam) PT 101 Pressure PT 084 TR TR 111 085 Temperature

PAL 5.2 MPa ASLD 5.15 MPa TA H 5 2 8 ASLD 538

(Main feed pump turbine inlet superheated steam) PT 574 Pressure

PAL

5.5 MPa

3.1.1a

Superheated Steam System


PAL 574 AOS 556 RO 556 OIO 556 OIS 556 PM 574 OIS 556 OIO 556 RO 556 AOS 556
NOTE

P
FOR MASTER

P
M
022VPA

(2) TO ATMOSPHERE (3) TO CLEAN DRAIN TK

NO.1 MAIN FD.W.P.T.


125B 125B

M
021VPA

50

50

NO.2 MAIN FD.W.P.T.


15

(4) TO ATMOS DRAIN TK (5) TO FLASH CHAMBER

15
PM 502
121B

P
(3) 122B

PAH 502

PAL 502
(4)

023VPA

(4)

(4)

024VPA (4)

1ST STG AUX.D/G AUTO START


272

(3) (2) 37B

50

PM 221

(2)

NO.2 MAIN BOILER


TAH 511 TAL 511 H ESD 467 TM 511 PM 501 G

PS P

6.0 MPa DESUPERHTD STM

50B

TS T

125

100
015VPA

P
(4)

NO.2 MAIN GENE.TURB.

74B

141B

STM FLOW
144B 81B 71B 083VPA 084VPA (3) (3) (3) 79B (3) 143B 132B 78B (3)

(3)

125

136B

100

135B

134B

525

1ST STG

AUX.D/G AUTO START


272

PM 221

PS P

OIS 413

OIO 413

131B

408 STC 408


(3)

014VPA

NO.1 MAIN GENE.TURB.

FOR STC

125
012VPA 76B

(4) (3)

(3) 138B

150
002VPA

150

200

150

TM 118

150

150
138B 76B

001VPA

150

XA 046 TAH 115

OIO 046 TM 115

OIS 046

AOS 046

TAL 118

AOS 0454 OIS 0454 OIO 0454

ASTERN MANEUV.V.

(3)

(3)

011VPA

125

(2)

OIS 413 OIO 413

STC 408

EMERG. CONN.

OI 042

RO 042

FOR STC 408


034VPA

LP TURBINE

ASTERN GUARD V.

082VPA 081VPA

(3)

79B

131B

P
150
78B 1ST STG

PM 102

PM 106

P
OIS OIO 0451 0451
(5) (5)

71B (3) 132B 74B 37B 141B (3)

81B (2)

(3)

136B 135B 134B

6.0 MPa DESUPERHTD STM


STM FLOW
525 OIO 0452 OIS 0452

TM 1161 TM 1162

AHEAD NOZZLE V.

HP TURBINE

RO 041

TM 111

TAH 111

TAL 111

ASD 085

25

FOR MASTER

144B

143B

T TS
TM 511

(5)

H
(3) 125B (3) 125B (3)

ESD 467

P
PM 501

50B

076VPA

OIO 050 OIS 050

072VPA

PAH 110 TRIP

AHEAD STOP V.

PS

PM 110

PIC 110

50
6.0 MPa DESUPERHTD STM

110

ASD 084 L

PM 101 PAL 101

122B

TAH 511

TAL 511

NO.1 MAIN BOILER


121B

25 50
075VPA

073VPA

25
074VPA

077VPA 071VPA

(5)

PM 502

PAH 502

PAL 502

(4)

200

3.1.2

6.0 MPa Desuperheated Steam System


Main Boiler Soot Blow The soot blow steam isolating valves 052 / 053VPA should be closed and the manual drain valves 056 / 059VPA should be opened at soot blower not using condition. a) b) c) d) Open soot blow steam isolating valves 052 / 053VPA. Select control mode (Both BLR or No.1 BLR or No.2 BLR). Start sequence Sequence start : Soot blow of boiler and economizer Economizer start : Soot blow of only economizer Following operation will be carried out automatically. Close drain piston valve 472B. Open soot blow steam shut-off valve 284B. Close drain piston valve 285B after warming-up (timer) Start soot blowing. After the soot blowing is finished, the steam shut-off valve 284B is closed and the drain piston valves 285B and 472B are opened. Alarms Sensor TR Tag No. 512 Function BLR desuperheated steam outlet temperature BLR soot blow steam pressure (Soot blow abnormal) Set point TA H 400

Internal Desuperheaters Superheated steam from the outlet of each boiler is led to an internal desuperheater fitted in the steam drum of each boiler. Superheated steam is led to the internal desuperheater through valve 141B, which then allows a heat exchange to take place between the superheated steam entering the desuperheater and the saturated steam / water within the steam drum. Consequently the heat given up by the previously superheated steam is recovered and no loss of energy should result. The desuperheated steam exits the internal desuperheater and is led to the desuperheated steam system through a primary and a secondary stop valves 145B and 031and 032VPA. Both boilers feed a common range from which the steam is branched away to the auxiliary services.

PS

533

PAL

4.0 MPa

Systems Supplied from the Main Desuperheated Steam System Boiler soot blower system Main dump steam system Main turbine emergency steaming connection Auxiliary steam system through reducing valves One (1) long retractable soot blower for boiler superheater, two (2) rotary soot blowers for boiler bank tube and four (4) rotary soot blowers for economizer are provided per one (1) boiler. One (1) air piston valve 033VPA, two (2) identical main dump valves 037VPA and 038VPA and two (2) external desuperheaters are provided for dump steam treatment. They are controlled by command from the boiler automatic combustion control system (ACC). The steam pressure is reduced by throttling of main dump valves and the temperature is lowered by external desuperheaters with injection of spray water from condensate water system. (See 3.1.6 Exhaust and Dump Steam System) The boiler desuperheated steam is supplied for auxiliary steam system via 6.0/1.0MPa PRV 040VPA. (See 3.1.3 Auxiliary Steam System or 3.1.5 1.0MPa Desuperheated Steam System)

Main Turbine Emergency Operation


(See 9.3 Solo Running of Main Turbine)

HP Turbine Sole Running If failure occurs in the LP turbine or associated gearing, the HP turbine can be operated singly at reduced power by ordinal superheated steam. In this case, the HP turbine exhaust is connected directly to the LP turbine exhaust casing using the emergency piping. When the damage has been to the LP turbine and the ship is to be operated on the HP turbine only, then no astern power will be available.

LP Turbine Sole Running If failure occurs in the HP turbine or associated gearing, the LP turbine can be operated singly at reduced power by internal desuperheated steam. In this case, the desuperheated steam is connected to the crossover pipe using the emergency piping. When the ship is to be operated on the LP turbine only, the steam chest pressure of the LP turbine must not exceed 0.32MPa. Astern running will be carried out by opening the astern manoeuvring valve at the engine side.

System Starting (See 4.3.2 Main Boiler Operation) a) Open all drain valves on desuperheated steam lines. b) Slowly open stop valves 031 / 032VPA for both internal desuperheaters. c) After the lines are pressurized and drained, close the line drain valves. d) When the desuperheated line pressure equals boiler pressure, fully open the stop valves 031 / 032VPA.

3.1.2a

6.0 MPa Desuperheated Steam System

TRIP PS

NOTE
PM 532

P
FOR BLR WASHING

(2) TO ATMOSPHERE (3) TO CLEAN DRAIN TK (4) TO ATMOS DRAIN TK


50

472B

15 15
285B

059VPA

15

50

SOOT BLOWER STM HDR

50

50

50

50

(2)

50

284B

AOS 533

OIO 533

OIS 533

50

50

TO ECO. SOOT BLOWER

NO.2 MAIN BLR


141B 145B

PM 503

TAH 512 TM 512

T
125
047VPA 048VPA

053VPA 032VPA

125

142B 143B

SUPERHTD STM
71B

(3) (3)

125

50

FOR TURBINE SOLE RUNNING

71B

034VPA

SUPERHTD STM
P
PM 503 TAH 512 TM 512
141B 145B

(4)
042VPA

80
6/1.0 MPa P.R.V.

150

T
125
045VPA 046VPA

031VPA

125
052VPA

200

150

80

A 803

PIC 803

100

100
039VPA 040VPA 041VPA

TO 1.0 MPA AUX.STM LINE

142B 143B

(3)

NO.1 MAIN BLR

AOS 812

OIO 812

OIS 812

MAIN DUMP V.

FROM ACC

ACC 412

(3)
50

150
033VPA 036VPA 038VPA

TO MAIN OR AUX. CONDR

TO ECO. SOOT BLOWER


50 50
285B

TRIP

PS

50

PM 532

P
284B

(4)
AOS 533 OIO 533 OIS 533

(4)
035VPA 037VPA

TO MAIN OR AUX. CONDR

50

50

50

(2)
472B

15
056VPA

15

50

50

15

50

FOR BLR WASHING

SOOT BLOWER STM HDR

3.1.3 Auxiliary Steam System


Steam Ranges
Five reduced pressure steam ranges are provided at a 1.0MPa, 0.24MPa, and 0.17MPa. These are supplied from boiler internal desuperheaters, main turbine bleeders and main feed pump turbine exhaust. The 1.0MPa range is supplied from either the 1st bleed steam on the HP turbine while the 1st bleed steam is available or the boiler internal desuperheater steam through reducing valve 040VPA and it supplies to the following services : 1) 2) 3) 4) Main boiler burner atomizing, purging and cooling steam Main boiler smothering (for wind box) 1.0Mpa desuperheated heating steam Make up for 2nd bleed line via pressure reducing valve The 0.17MPa range is supplied from the 0.24MPa range through control valve 052VPB and from the main feed water pump turbine exhaust steam. (See 3.1.6 Exhaust & Dump Steam System) The primary steam feed for this system comes from the feed water pump turbine exhausts. During normal plant operations, one of the two turbine feed pumps is always operating. These turbines both exhaust joins the 0.17MPa range. The 0.17MPa steam is supplied to following services. 1) Deaerating feed water heater (Deaerator) 2) Main turbine and generator turbine(s) gland packing steam On occasions it is possible for the supply of steam to exceed the demand. Excess pressure from the system is dumped to the main condenser by a controller with a set point of over 0.17MPa. If the main condenser is shut down, the excess pressure can be diverted to the auxiliary condenser. Exhaust steam spill valve 052VPC dumps excess steam to the condensers with valve 055VPC directing the steam to the main condenser or valve 056VPC directing steam to the atmospheric auxiliary condenser. CAUTION Do not open both the dump to the main condenser and the dump to the auxiliary condenser at the same time if the main condenser is under normal vacuum. Doing so will cause a sudden loss of vacuum within the main condenser and subsequent trip of the main turbine. The 3rd bleed steam is supplied for the 1st stage feed water heater through swing type non-return valve when the main turbine is operated under the appropriate load. However, when the main turbine load is lower than the pressure to open the swing valve, the heating steam is not supplied to the 1st stage feed water heater, but it is heated only drain from the steam air heaters. d) a) b) c) Close compressed air root valves 141 / 144VPE. Close compressed air supply valves 025 / 035VPB. Open drain traps and valves - Atomizing steam header drain 022 / 027ZPD. - Drain separator drain 023 / 028ZPD. - Atomizing steam escape valves 026 / 036VPB. Slowly open atomizing steam supply valves 021 / 031VPB.

Controls Following relief valves are provided to protect over pressurization. 1.0MPa steam line 0.24MPa steam line 0.24MPa steam line 0.17MPa steam line : 1.10 Mpa : 0.70 MPa : 0.70 MPa : 0.30 MPa
005VPB 044VPB

The 1st bleed steam is bled from the main turbine at the fifth stage of the HP turbine. The bleed valve 001VPB opens automatically by a signal from the pressure switch located at the bleed off point. The normal bleed steam pressure of 1.62MPa joins the 1.0MPa range supply system also supplied by the boiler internal desuperheaters through 6.0 / 1.0MPa pressure reducing valve 040VPA. The bleed valve opens at a pressure of over 0.87MPa and closes at under 0.85MPa. The 1.0MPa pressure range is supplied to the desuperheated heating steam system through 1.0Mpa external desuperheater. The external desuperheater is provided with a by-pass valve against malfunction of desuperheater so enable to continue the plant operation. (See 3.1.5 1.0MPa Desuperheated Steam System) The 0.24MPa range is fed from two separate sources. These are : 1) 2nd bleed 2) 1.0 / 0.24MPa make-up reducing valve 012VPB The 2nd bleed steam is bled from the HP/LP crossover pipe. The bleed valve 041VPB opens automatically by a signal from the pressure switch located at the bleed off point. The normal bleed steam pressure of 0.65MPa joins the 0.24MPa range supply system. The bleed valve opens at a pressure of over 0.30MPa and closes at under 0.25MPa. The 1.0MPa range steam is supplied through 1.0 / 0.24MPa pressure reducing valve 012VPB when the 2nd bleed steam is not available. The 0.24MPa steam is supplied to main boiler steam air heaters and high pressure 3rd stage feed water heater. The bleed valves can be opened or closed from the ICAS when switched to the REMOTE position. or at local, but automatic operation will normally be selected. All drain traps isolating valves on the system should be opened.

On 3rd feed heater On deaerator

The 1st and 2nd bleed steams are served through electric motor operated check valves 001/ 041VPB. These valves are opened manually with the operators confirmation after open request on ICAS, and are closed automatically. 1st bleed valve Open request Automatic close 2nd bleed valve Open request Automatic close

: Over 0.87MPa of 1st bleed pressure : Under 0.85MPa of 1st bleed pressure : Over 0.30MPa of 2nd bleed pressure : Under 0.25MPa of 2nd bleed pressure

System Starting a) b) Ensure all supply steam lines are drained and warmed. Always use by-pass lines around pressure reducing valves for warming-through purposes. After the line has been warmed sufficiently, open the reducing valve outlet stop valve, slowly open the inlet valve and close the bypass valve. Ensure control air is available.

Alarm Sensor PT PS PT PT Tag No. 504 469 805 830 107 107 223 Function Set point

Main boiler burner atomizing PAL 0.34 MPa steam ESD 0.30 MPa 0.17MPa steam Deaerator shell Main turbine packing steam Generator turbine packing steam PAH 0.27 MPa PAL 0.12 MPa PA H PA L PA L 35 kPa 0 kPa 3 kPa

c)

Boiler Atomizing Medium When the boiler atomizing medium is changed from air to steam, it should be done at boiler stop condition.

PT PT PT

3.1.3a Auxiliary Steam System


SET AT 0.3MPaG
TM SPM

(2) NOTE:

100

S.A.H.

268B

TM SPM

T
056VPB

P
PM 830

250

269B

(2) TO ATMOSPHERE (3) GENE.SERV.AIR (4) TO ATMOS. DRAIN TK (5) TO MAIN CONDR

NO.2 MAIN GEN.TURB.


TO GLAND

PM 223

PAL 223

NO.2 MAIN BLR


SMOTHERING STM
255B 188B

25
410 TO ACC

036VPB

25

DEAERATOR DEAERATOR
(2)
SET AT 0.70MPAG 044VPB

PAL 830

PIC 223

25

F.O.
256B 254B

253B

OIO 428

OIS 428
253B

FROM ACC

255B

F.O.
256B 254B

100
038VPB
339B

037VPB

PM SPM

SET AT 0.70MPAG
P

A
25
063VPB

223

223

(5)

(4)
244B 209B 244B 209B

15
039VPB 035VPB 043VPB

(5)

NO.1 MAIN GEN.TURB.


TO GLAND

OIO 427

OIS 427

FROM ACC

25

(3)
40

(4)
PM 504 PAL 504 G

40
032VPB
226B

200 250

200

3RD STAGE FD.W.HTR


FROM FEED W.PUMP TURB.

PM 223

PAL 223

25

031VPB

PIC 223

PS 469

409

033VPB

40

ESD

25

(4)
TO ACC

PAH 805

P P
PS 469
ESD 409

P
025VPB

PM 805

100

A
40

223

223

(3)

G PM 504

TO ACC FROM ACC

25

062VPB

(5)

PAL 504

25

40

(3)
40

PIC 801

(5)
80
PIC 107
MAKE-UP V.
057VPB

(4)
209B 244B 209B 244B

40
TO ACC OIO 427 OIS 427
022VPB
226B

021VPB

PIC 107

PM 107

PAL 107

PAH 107

(4)
410

023VPB

107

PM 105

3RD BLEED

25

L.P.TURBINE
TO GLAND

T
TM 114
081VPB

100

250

40

P
F.O.
255B 253B 256B 255B 254B 253B

FROM ACC

107

SPILL V.

TR 114

028VPB

339B

027VPB

PACK.STM RESERV. (5) (5)


P
OIS 044 OIO 044 RO 044 AOS 044
M 041VPB

(5)

F.O.
256B 254B

15
OIO 428 OIS 428
029VPB

801

150

054VPB

SMOTHERING STM

(4)
188B

25
026VPB

250
053VPB 052VPB 0.17 MPA P.C.V. 051VPB

100

(4)

150

200

1ST BLEED

NO.1 MAIN BLR


T
268B

PM 104

H.P.TURBINE
P
PM 103

S.A.H.

TM SPM

2ND BLEED
TM 113

TM 112

TM 8062

TIC 807

014VPB 020VPB

807

100

250

269B

TAH 8062

807

1.0 MPA DESUPERHTR


T
401VPB 008VPB

P A
125
011VPB 054VPC 012VPB 1.0/0.3 MPA P.R.V.

PIC 802 802

(5)
(STEAM SIDE)

300

TAL 8062

(4)

TO 1.0 MPA DESUPHTD STM LINE


P

125

125 100

013VPB

PAL PM 8061 SPM

(4)

125

80
042VPA

803

FROM BLR PRESS. DESUPERHTD STM


039VPA

PIC 803

(2)
P
SET AT 1.10 MPA 005VPB

150

051VPC

(4)
803

052VPC 053VPC EXH.STM SPILL V.

TO MAIN OR AUX. CONDR


AOS 043 RO 043 OIO 043 OIS 043
M 001VPB

100

005VPB

A
125
004VPB 003VPB 1.0MPaA P.C.V. 002VPB

150
040VPA 041VPA 6/1.0 MPA P.R.V.

150

(4)

80

009VPB

1ST STAGE FD.W.HTR

3.1.5

1.0MPa Desuperheated Steam System


General Procedure for Putting the Systems into Operation Temperature control valves are provided as follows. 1) Boiler FO heater Master valve 144VPB and slave valve 145VPB for No.1 boiler and 150VPB and 151VPB for No.2 boiler are provided for viscosity/temperature control of boiler FO. The valves are controlled by ICAS. 2) Purifier LO heater The L.O. temperature at purifier suction is controlled to 80 with control valve 105VPB. The valve is controlled by local controller. 3) Hot water heater The water temperature is controlled to 80 by steam heater and/or electric heater. The self contained type temperature control valve is provided for steam heater and the electric heater is operated with thermostat. 4) FO settling tank The FO temperature is controlled to 55 by the self contained type temperature control valve provided for each FO settling tank No.1: 113VPB, No.2: 133VPB. 5) Waste oil settling tank The WO temperature is controlled to 8090 by the self contained type temperature control valve provided for each waste oil settling tank No.1: 162VPB, No.2: 166VPB. 6) Hydrant heater The sea water temperature for hydrant and spray water is controlled to 10 by a control valve 160VPB provided at heating steam. The valve is controlled by local controller 7) Stern tube fresh water heater The cooling fresh water temperature for stern tube LO cooler is controlled to 37 by a control valve 262VPB provided at heating steam. The valve is controlled by local controller It is important when bringing any steam system into service to slowly raise the temperature of the pipes, valves and joints. Heating the various parts of the system too quickly can lead to thermal distortion and damage to joints and packing. The system must be carefully drained of any water during this warming process to prevent steam hammer or water hammer taking place. Mechanical damage can be caused to the surrounding materials. For this reason any water is to be removed from the system before the pressure and temperature are increased. The pressure must be increased gradually to allow expansion of the components to take place at a rate that will not lead to material failure. Any sudden increase in pressure can send shock waves throughout the system which are very likely to cause damage.

1.0MPa External Desuperheater


Maker : No. of sets : Type : Maximum evaporation : Steam condition : Nippon Keystone Corporation 1 set Water Spray Injection 13,000 kg/h 1.0MPaG 300 200

An external desuperheater is provided after the 6.0 / 1.0MPa reducing valve 040VPA where the steam temperature is reduced to 200C before supplying the auxiliary services. Feed water is taken from either the main or auxiliary feed lines, reduced in pressure at valve 054VPF before being passed to the desuperheater. The feed water is injected directly into the steam pipe reducing the temperature of the steam before it is directed to the auxiliary system. The desuperheater system is fitted with a recirculation orifice after the pressure reducing valve 054VPF but before the desuperheater. This ensures that during times of low spray water demand, there is no pressure build up in the pipework after the pressure reducing valve which could damage the equipment. The 1.0MPa desuperheated steam is supplied for the following services. 1) 2) 4) 5) 6) 7) 8) 9)
10)

Deck Service a) b) Open isolating valve after drainage by manual drain valve Before navigation in cold weather, the steam for cold weather is supplied and drainage should be completed. Also, where the steam is not supplied, the steam line exposed to cold weather should be completely drained to prevent freezing.

Oil tank heating and steam trace heating. Fuel oil heaters and purifier L.O. heater. Hot water heater Main boiler burner tip cleaning carrier. Hose connections. Gas compressors, gas heaters and vaporizers in cargo machinery room. Inert gas generator. Main air conditioner and accommodation through 0.3Mpa pressure reducing valve 172VPB. Measures for frigid climate conditions through 0.6Mpa pressure reducing valve 179VPB

Alarms Sensor PT Alarm No 806 Function 1.0MPa desuperheater outlet pressure 1.0MPa desuperheater outlet temperature Set point PAL 0.8 MPa

3) Hydrant heater and stern tube F.W. heater.

TR TR

806 806

TAH 220 TAL 170

3.1.5a

1.0MPa Desuperheated Steam System

WASTE OIL SETT.TK NO.1


15
163VPB

15
164VPB

TO CO2 BOTT.& FORM TK RM TO CABIN USE TO MOORING DECK TO FLYING PASS. 187VPB

80 15 15 100

15

TO UNDER DK PASS.(P)

40

TO IGG DRYER HTG STM SET AT 0.33MPAG 177VPB

189VPB

162VPB

161VPB 168VPB 0.3 MPAG P.R.V. 172VPB 173VPB

65

25

40

NO.2
15
167VPB

15

65

P
15 15 50
171VPB 174VPB

80

(2)

TO AIR CAPSTAN (P)

190VPB

TO AIR CAPSTAN (S)

165VPB 166VPB 170VPB

(4)
100

100

15 25

40

P
25 80
178VPB 181VPB 0.6 MPAG P.R.V. 179VPB 180VPB

SET AT 0.66MPAG 182VPB

(2)
185VPB 184VPB 183VPB

15

(8)

65

188VPB

TO UNDER DK PASS.(S)

I.G.G.GAS OIL TK

D.O.STOR.TK

F.O.SIDE TK F.O.SETT.TK (P)

(INCINE RM) 205VPB

15

80

INCINERATOR D.O.TK
880
148VPB

65 40

198VPB

202VPB

201VPB

150

157VPB

ENG. RM HTR (P)


50
197VPB 176VPB

A
50
150VPB

50

149VPB

BNR TIP CLEAN. CARRIER


50
169VPB

40
175VPB

ENG. RM HTR (S)

(7)

50

(7)
158VPB

(TK TOP-P) 159VPB 140VPB 139VPB 141VPB 138VPB 137VPB 136VPB 135VPB

880

A
151VPB

15

15

40

40

40

NO.4 F.O.HTR
BOILER F.O.

101VPB

150

131VPB

40

132VPB 130VPB 133VPB

134VPB

152VPB

NO.3 F.O.HTR
875
142VPB

NO.1 DO SERV.TK

NO.2 DO SERV.TK

D.O.STOR.TK

25

103VPB

100 125

TO FWD.F.O.TK

A
50
144VPB 123VPB 122VPB 121VPB

124VPB

50

143VPB

TIC G1901

80

102VPB

TO CARGO MACHI.RM

160VPB NOTE: (2) TO ATMOSPHERE (3) TO CLEAN DRAIN TK (6) TO ATMOS DRAIN TK (7) TO DECK HEAT.UNIT (8) TO EMERG. GEN D.O. TANK HEATING

50

25

875

A
145VPB

15

15

40

25

80

SW

HYDRANT HTR

50

147VPB

125VPB

126VPB

(4) TO DRAIN INSPEC.TK 104VPB

150

40

65

NO.2 F.O.HTR
BOILER F.O. 154VPB

TIC 892

25

105VPB 110VPB 111VPB

25
114VPB

146VPB

40

LO

PURIF. LO HTR
(TK TOP-S) 195VPB

TAL 806 TAH 806 TM 806 TIC 807

NO.1 F.O.HTR

FO OVERFLOW TK
15
TO BOILER ATOMIZ.

LO SLUDGE TK
15

109VPB

15

40
112VPB 113VPB

(TK TOP-AFT)

25

40 15

196VPB

15

15

T
150
401VPB 009VPB

020VPB

15

1.0 MPA DESUPERHTR 807 A

40

40

40

40

40

TIC 87A
155VPB

156VPB

15
262VPB 261VPB

15

15

108VPB (PURIF RM)

120VPB

119VPB

118VPB

117VPB

116VPB

40
115VPB

456VPB

15

009VPB

S/T LO FW HTR
P

FW

25

6.0/1.0 MPAG P.R.V.

PIC 803 803

127VPB SET AT 1.10MPAG

128VPB

15

PAL PM 8061 SPM

(6)

100

129VPB

(2)

A
FROM BLR PRESS DESUPERHTD STM 040VPA

G/E LO RENOV.TK AUX. TURBINE LO RENOV.TK


TO 1.0/0.24 P.R.V. FROM 1ST BLEED

LO RENOV.TK F.O.SETT.TK L.O.SUMP TK SEP.BILGE OIL TK F.O.DRAIN TK LOW SULPHUR FO TK F.O.SIDE TK

150
041VPA

40

153VPB

50

40

40

40

40

15

40

HOT WATER HTR

3.1.6

Exhaust and Dump Steam System


Main Feed Water Pump Turbine Exhaust Valve The main feed water pump turbine exhaust valves 041 / 042VPC should be opened after removing drain accumulating in the exhaust pipeline completely by the drain valves 043 / 044VPC. The open signal of main feed water pump turbine exhaust valve 041 / 042VPC is interlocked for main feed water pump starting. (See 3.2.2Boiler Feed Water System) Dump Steam System (See 4.3.4Boiler Control Systems) An automatic steam dumping system is provided to treat the excess steam generated by the main boilers when burning the designed rate boil-off gas. Steam from the boiler internal desuperheaters is dumped to the main condenser under normal conditions, but alternatively it may also be dumped to the auxiliary condenser, by opening valve 038VPC and closing valve 037VPC, should the main condenser be unavailable. Dump piston valve 033VPA and main dump valves 036VPA and 037VPA are controlled by dump order signal from ACC via a Steam Dump Controller. Two identical size main dump valves 036VPA and 037VPA are operated with a split range control system. The valve 036VPA opens first and the valve 037VPA follows when much excess steam is produced. The steam from each main dump valve is led to respective dump steam external desuperheater. The desuperheaters are required to eliminate the effects of superheated steam impinging on either the main condenser or the atmospheric condenser. Desuperheaters operate by injecting spray water directly into the steam flow, reducing the temperature to 150C. The spray water for the desuperheater is supplied from the main condensate pump and/or drain pump discharge. The temperature at the outlet from the desuperheater is measured and a corresponding signal is transmitted to the external desuperheater spray control valve, which alters the water supply accordingly. A further cooling spray is provided at the dump steam inlet to the main condenser to cool the inlet cowl and help prevent mechanical stresses being created in the condenser shell. The spray water to the cowl is served from the condensate system, through an air operating piston valve which is operated automatically in conjunction with the dump system operation. An orifice plate with appropriate size is provided at dump exhaust inlet of auxiliary condenser to maintain similar dump conditions to the main condenser operation. The line between main dump valve 036VPA and stop valve 037VPC is protected against overpressure by relief valves of a half capacity each 033 and 034VPC, set at 0.5 MPa. The stop valves 035VPC and 036VPC fitted at outlet of the respective external desuperheater should be left open normally exception of maintenance of the system. Main and auxiliary condensers can treat the dump steam from main boilers and exhaust steam from generator turbine when burning the designed rate boil-off gas during port hotel load condition. Treated Steam Quantity (See 3.0 Heat Balance for Steam Turbine Plant) Main condenser Auxiliary condenser Treated BOG Quantity BOG quantity on design boil off rate : 3,850 kg/h : 70.0 ton/h : 70.0 ton/h

Exhaust Steam Systems Exhaust steam from the generator turbines is led to the main condenser through the electric motor driven valves 001 / 011VPC. When the main condenser is not available, the exhaust can be led to the auxiliary condenser via valves 021 / 022VPC. Exhaust steam from the main feed pump turbines is led to the 0.17MPa auxiliary steam system. (See 3.1.3 Auxiliary Steam System) In the event of over pressurization, steam is normally dumped to the main condenser through pressure control valve 052VPC and stop valve 055VPC. When the main condenser is not available, the steam can be led to the auxiliary condenser via stop valve 056VPC. CAUTION Do not open both the exhaust to the main condenser and the exhaust to the auxiliary condenser at the same time if the main condenser is under normal vacuum. Doing so will cause a sudden loss of vacuum within the main condenser and subsequent trip of the main turbine. Gland steam, exhausting from the main turbine, generator turbines and main feed pump turbines is led to the gland condenser. The condensate in the gland condenser is then led to the atmospheric drain tank. (See 3.2.5 Clean Drain System) Non-condensable gases from the deaerator are also drawn to the gland condenser. The deaerator vent valve to the gland condenser should remain open whilst the plant is in operation . Generator Turbine Exhaust Valve In case the exhaust valve 001 or 011VPC will be opened after main condenser vacuum-built up, the valves are operated as follows : Ensure the operation and control of gland steam supply for generator turbine. Open the by-pass valve 002 or 012VPC. Open the exhaust valve 001 or 011VPC at local. Close the by-pass valve 002 or 012VPC. When the auxiliary condenser will be operated, water may be supplied to the exhaust valves 001 or 011VPC to protect the seat ring of valve according to following procedure. Supply the water from lower plug. Stop the water supply after confirming the overflow from upper plug.

High Boiler Pressure The main dump valve is controlled from the integrated control and automation system (ICAS). The valve will open when the boiler pressure exceeds its normal set point. It provides stability during periods of fluctuation where the burners are reduced to minimum flow, such as during manoeuvring. The dump will control any excess steam pressure generated during these periods.

High Tank Pressure If the demand of steam is not enough to consume the entire boil-off gas from the cargo tanks, the firing rate of the gas burners will be increased accordingly and any excess steam will be dumped to the main condenser. The amount of steam dumped will depend on the position of the main turbine manoeuvring valves and the cargo tank pressure. The dump signal from the cargo tank pressure is inhibited when burning fuel oil only.

Controls The ICAS will send a Dump Permitted signal to the ACC if the following conditions are fulfilled : Dump steam pressure below 370 10kPa Main condenser vacuum above -73 5Pa (600mmHg Main condenser SW outlet temperature below 452C Dump steam valve 037VPC to main condenser open or valve 038VPC to auxiliary condenser open Auxiliary condenser shell pressure below 150 10kPa

3.1.6

Exhaust and Dump Steam System


FROM M/T RELAY PANEL M/T AHD NOZZLE VALVE LIFT POSITION M/T AST VALVE LIFT POSITION FROM CARGO ICAS NATURAL BOG FLOW DUMP / NON CONTROL FROM LIMIT SWITCH DUMP PISTON VALVE FULL OPEN DUMP PISTON VALVE FULL CLOSED M/T VALVE POSITON "AST. FULL ZONE" M/T REMOTE CONTRO SYSTEM M/T TELEGRAPH POSITON "AST." "STOP" M/T VALVE POSITON "AHD NOR. ZONE" FROM MACINERY ICAS STEAM DUMP AVAILABLE

When all the above conditions are met, the ICAS sends an Excess BOG Dump Order and a Dump Permitted signal to the ACC. The ACC will then output open signal to the dump piston valve 033VPA if either following condition is fulfilled. Boiler steam pressure more than 5.98MPa Cargo tank pressure more than 20kPa The ICAS will receive the control signal sent to the main dump valves 036VPA and 037VPA. This signal is then used to open the external desuperheater spray valves in parallel with the main dump control valves 036VPA and 037VPA. If the temperature after the desuperheater reaches the set point of 150C, the signal from the temperature controller will override the ACC signal and control the desuperheater water spray valves. The water spray piston valve for main condenser dump steam inlet cowl is opened by main dump valve 036VPA open order and the dump steam valve 037VPC open signal. Alarms

M/T TRIP

LIFT

LIFT

STEAM PRESS. SET STEAM DUMP PRESS. SET (BIAS) SET

NOZZLE VALVE

NOZZLE VALVE

BOILER FO FLOW No.1 BLR No.2 BLR

No. OF GAS BNR IN SERVICE

STEAM FLOW No.1 BLR No.2 BLR


OFF DELAY TIMER (900sec) OFF DELAY TIMER (900sec)

STEAM PRESS.

H/S

L/S
SV

L/S
PV

PID

EXCESS BOG DUMP CONTROLLER

SET=0
AT NON DUMP MODE, COMPR STOP OR NON GAS BURNING

STEAM DUMP PRESS. SET (MAX) SET L/S

FO RANGE EVASION CONTROLLER


SV

PID

PV

FO FLOW LOOP BACK SIGNAL

SV

PID

PV

No. OF GAS No.1 BLR No.2 BLR

BOILER FO FLOW No.1 BLR No.2 BLR

L/S H/S H/S


FULL CLOSED BY PISTON VALVE CLOSE

PISTON VALVE CONT. LOGIC

AUTO/MANU STATION
MANU AUTO

AUTO

MANUAL LOADER ICAS MANU. ICAS

AUTO/MANU STATION
MANU AUTO

AUTO

MANUAL LOADER ICAS MANU. ICAS

Sensor PS PT PT PT PT PT PS PS PS PS

Tag No. 070 086 158 813 817 817 215 222 565 575

Function Main condenser vacuum

Set point ESD -67 kPa ASLD -73 kPa PA L - 8 0 k P a Dump stop -73kPa PA H 1 3 0 k P a PA H H 1 5 0 k P a ESD PA H ESD PAH +50 kPa +30 kPa 0.45 MPa 0.27 MPa
FROM ACC2 ACC1 ACC2 COMMON SELECT ACC1 FROM ACC2 ACC2 COMMON SELECT COMMON SELECT AUTO/MANU STATION AUTO
LOCAL ICAS MANU AUTO

ICAS

ICAS

FROM ACC2 ACC1 ACC2 MANUAL LOADER LOCAL MANU. BGB COMMON SELECT

FROM ACC2 ACC1 ACC2 COMMON SELECT

FROM ACC2 ACC1 ACC2 ACC1

FROM ACC2 ACC2 COMMON SELECT

BGB

I/P

I/P ICAS

Auxiliary condenser shell Generator turbine exhaust

033VPA DUMP PISTON VALVE

036VPA MAIN DUMP VALVE

TE
CONDS.W. TO MAIN OR AUX. CONDENSER

STEAM DUMP PRESS. SV TO GAUGE

STEAM DUMP PRESS. PV TO GAUGE

STEAM DUMP CONT. OUTPUT TO GAUGE

TO ACC2
037VPA

Main feed pump turbine exhaust

(Dump steam at main dump valve outlet) PT 816 Pressure PT 816 TR 819 Temperature

PA H 3 3 0 k P a PA H H 3 7 0 k P a TA H 190

3.1.6a
TO ATMOSPHERE
SET AT 0.30 MPA

Exhaust and Dump Steam System


25 350
AOS 048 OIO 048 OIS 048
AUX.STM

65 10
065VPB

PAL 830 PM 830

FROM MAIN CONDS.PUMP

ASD 086 PAL 813 PAL 158 PM 158 DUMP PISTON V. CLOSE M/T TRIP ESD 070

PAHH 816 PAH 816 PM 816


037VPC

DUMP PISTON V. CLOSE

DEAERATOR

NO.2 MAIN TURBO GEN.

10

250

800

900
018VPC

OIO 814

LS

T
350 200

MAIN CONDR
100

P
900
RO 811

PAH 222

ESD 215

TO M/T & T/G GLAND STM

800

T
200

L.P. TURB.
800 25
TM 117

OIS 811

OIO 811
011VPC

OIO 815

LS

65 350
022VPC

TM 819 TAH 819 FROM ACC

TIC 818

200
036VPC

038VPC

TO ATMOSPHERE

035VPC

M
012VPC

033VPC SET AT 0.5MPA

034VPC

H/S
350

200

200

TOP

TOP

DUMP STM EXT. DESUPERHTR


65 10
NA56 NA56

044VPC

043VPC

H.P. TURB.
25 200 50

AUX.STM

OIO 568 LS ESD 565 PAH 575

042VPC

OIO 568 LS ESD 565 PAH 575

041VPC

GLAND LEAK RESERV.

064VPB

057VPC

P
100
ES FIRE SA 652 RM 652 RO 652

NO.1 MAIN TURBO GEN.

350

10

SILENCER

SILENCER

FROM ACC

250

(3)

(3)

GLAND EXH. FAN


15

100

046VPC

045VPC

125

OIS 811

OIO 811
001VPC

RO 811

900

NO.2 MAIN FD.W.PUMP TURB.

NO.1 MAIN FD.W.PUMP TURB.

80

50

007VPC

PAH 222

ESD 215

MAIN DUMP V.

OI 820

RO 820

036VPA

OI 820

RO 820

350
037VPA

FROM MAIN CONDS.PUMP

FROM MAIN CONDS.PUMP

40

40

65 350
021VPC

125

900
PAH 805 PM 805

OIS 812

OIO 812

ACL 812

65

65

GLAND CONDR
65

25

055VPC

002VPC

150

(3)

(3)
056VPC

150 350

FROM BLR STM PRESS.LINE TO ATMOSPHERE


350

033VPA

P
PIC 801 801

DUMP PISTON V. CLOSE

0.27 MPA P.C.V.

FROM 2ND BLEED & 1.0/0.24 MPA P.R.V.

(4)
054VPC

100

AUX. CONDENSER

65

PAHH 817

PAH 817

PM 817

NOTE: (3) TO CLEAN DRAIN TK (4) TO ATMOS.DRAIN TK

125
051VPC 052VPC 053VPC EXH.STM SPILL V.

200

(4)

125

AOS 812

350

3.2.1

Condensate Water System


Teikoku Machinery Works, Ltd. 2 sets Centrifugal vertical 90 m3/h at 85 mth 440V, 45kW, 1,800 rpm Grease Extractor Maker : No. of sets : Type : Flow Capacity : Deaerator Maker : No. of sets : Type : Storage capacity : Main Condensate System Mitsubishi Heavy Industries Ltd. Surface type with dump steam chamber 2,860 m2 11,500 m3/h 5m 19 mm diameter, 0.7 mm thickness The prime function of the main condensate system is the removal of condensate from the main condenser and its delivery to the deaerator, for return to the boilers by the feed pump. The condensate performs other useful functions during this transfer, as detailed below. Two pumps of full capacity are arranged to take suction from the main condenser, one is running and the other for standby. They are designed to auto-cavitate so that if they lose suction, the normal cavitation associated with this takes place away from the impeller. Cavitation can cause damage and erosion in centrifugal pumps particularly to the impeller. By the nature of the conditions under which these pumps operate with no positive head and variable flow rates, cavitation is a real danger. For this reason the pump is designed so that cavitation will not cause damage. The pump delivers the condensate into the main condensate system. It passes through the condensate cooled distilling plant, the gland steam condenser cooling tubes and the low pressure feed heater. These can all be bypassed if necessary. This routing of the condensate serves the dual purpose of condensing or cooling other sources of heat within the plant and heating the condensate. This greatly improves plant efficiency as well as performing cooling functions. Several branches from the main condensate line supply condensate to the following services : Main dump desuperheater spray water Main condenser dump steam chamber spray water Main turbine astern water spray Main Condenser vacuum pump water seal Main feed water pumps mechanical seal Boiler water analysis unit cooling Boiler chemical feed tank filling Takatori Seisakusho Co., Ltd. 1 set Duplex Pylen Filter 120 m3/h A branch situated at the condenser recirculation line, provides cooling spray water to the astern turbine exhaust. Due to the inefficiency of the astern turbine its exhaust still has a high level of enthalpy and temperature. Sustained running of the astern turbine could cause overheating of the condenser shell and tubing and therefore the spray water is applied whilst going astern. This valve operates automatically when an astern movement is detected. The main condensate system joins the auxiliary condensate system and is directed either to the deaerator, or to the distilled water tanks, depending upon the deaerator level at the time. Under steady plant conditions all the condensate will be delivered to the deaerator but at times of plant load change, a situation can occur where there is too much condensate in the system and some will be spilled out to the distilled water tank. Main Condenser Level Control The water level in the hot well is controlled by cavitation control of main condensate pump in principle. A branch from the main condensate line, situated between the gland steam condenser and the first stage feed water heater, returns to the main condenser via a control valve 190VPF. The level of water in the main condenser is maintained in order to prevent the condensate pump from losing suction. This function is controlled by the ICAS system which measures the condenser hot well level. If the level should increase to normal level +450mm, the standby pump will automatically start when the high level switch is activated. The standby pump will stop when the level reaches to normal +300mm and a separate switch at this level is activated. Deaerator Level Control The water level in the deaerator is maintained by the level transmitter which controls two valves, spill valve 132VPF and make-up valve 142VPF, in a split range configuration. The spill valve 132VPF is for dumping water back to the distilled water tanks, in the case of a high level in the deaerator. The makeup valve 142VPF is for filling the deaerator by adding more to the atmospheric drain tank. The level in the drains tank will rise and valve 174VPF will open and supply more water to the system. A level switch is provided to inhibit the automatic starting of main feed water pump in stand-by in the event of extremely low level in deaerator (Normal level - 1240 mm). In this case, the running pump will trip automatically also to prevent possible overspeed.

Main Condensate Pump Maker : No. of sets : Type : Capacity : Rating : Drain Pump Maker : No. of sets : Type : Capacity : Rating : Main Condenser Maker : Type : Cooling surface : Cooling water flow : Tube plates Distance : Tube size : Auxiliary Condenser Maker : Type : Cooling surface : Cooling water flow : Tube plates Distance : Tube size : Gland Steam Condenser Maker : Type : Cooling surface : Cooling water flow : Tube plates Distance : Tube size :

Teikoku Machinery Works, Ltd. 3 sets Centrifugal vertical 45 m3/h at 70 mth 440V, 22kW, 1,800 rpm

DongHwa Entec 1 set Direct contact 22.5 m3

Setouchi Kogyo Co., Ltd. Single pass shell and tube 315 m2 2,600 m3/h 4.4 m 19 mm diameter, 0.7 mm thickness

Mitsubishi Heavy Industries Ltd. Single pass shell and tube 25 m2 102.5m3/h 1.9 m 16 mm diameter, 1.0 mm thickness

1st Stage Feed Water Heater Maker : DongHwa Entec Type : Shell and U-tube Heating surface : 145 m2 Cooling water flow : 94,500 m3/h Tube size : 19 mm diameter, 1.2 mm thickness

A branch from the main condensate line, situated after the gland steam condenser supplies condensate to spray nozzles situated in the dump steam chamber of the main condenser. This provides further cooling of the dump steam whilst reheating the condensate being sprayed.

3.2.1

Condensate Water System


Make-up water to the condensate system during hot plant conditions is led from the distilled water tank(s) through make-up control valve 142VPF to the atmospheric drain tank. The initial filling valves 145VPF fitted at the main condenser hotwell should be closed while normal plant operation. The deaerator is situated at a high point in the engine room to provide a positive suction pressure for the feed pumps greater than the saturation pressure of the water at the pump suction. This prevents the water boiling at the feed pump suction and causing cavitation. The water enters the deaerator through a series of spray nozzles where it meets the heating steam. The steam is supplied from the 0.17 MPa range which is the feed pump exhaust line. Spraying the feed water gives it a large surface area in which to make contact with the steam. This condenses the steam to become one with the feed water and allows oxygen and other non-condensable gases to be liberated. The gases are vented from the top of the deaerator through a vent valve which should always be set for optimum performance. Adjustment of the vent is dependant on the results of the dissolved oxygen tests (See 3.2.1bDeaerator). Preparation of the Main and Auxiliary Condensate Systems The following procedure covers preparation of the systems prior to and during lighting of the boilers. a) b) c) Ensure that the instrument and gauge valves are open and that instrument air is supplied to the control units. Check that all services and bypass valves on the condensate system are shut. Fill the atmospheric drains tank from one of the distilled water tanks. Set the system valves as follows : Description Distilled water tank suction valve Cold start feed water pump suction valve Make-up control valve Make-up valve inlet and outlet valves Make-up bypass valve Make-up valve to the atmospheric drain tank Filling valve to the main condenser Valve
135 or 136VPF 008VPF 142VPF 141 / 143VPF 144VPF 146VPF 145VPF

Auxiliary Condensate System The condensate from the auxiliary steam systems such as fuel and tank heating, feed heating and exhaust steam is eventually fed to the atmospheric drain tank. The auxiliary condensate systems prime function is the return of auxiliary steam system condensate and drains to the deaerator, for return to the boilers by the feed pumps. The condensate performs other useful functions during this transfer, as detailed below. The atmospheric drain tank, capacity 6 m3, receives condensed drain water and condensate from various sources around the steam system including the inspection tank. It acts as a reservoir for the system drains only, with all drains contamination taking place elsewhere in the system (See 3.2.6 "Contaminated Drain System"). The atmospheric drain tank is equipped with three equal capacity drain pumps which are set to starting priority 1st, 2nd and 3rd. The 1st will act as the duty pump with the 2nd pump as standby and the 3rd as standby to the 2nd pump. The pumps are set in duty / priority mode from the ICAS. All three pumps will then be set in automatic mode and priority 1 pump starts as the duty pump. The standby pump will start if there is a failure of the higher priority pump or a low pressure (400 kPa) in the discharge line is detected. The level in the tank is controlled by valve 174VPF, which controls water flow from the drain pump. A valve 165VPF with an orifice which recirculates the water from the pump discharge line back to the tank is provided to maintain the minimum flow of the pump against full close of the level control valve. If the level should increase to activate high level switch (1,450 mm from tank bottom), the standby pump will automatically start. The pump will stop when the level drops and low level switch (800 mm from tank bottom) is activated. A duplex grease extractor unit is fitted in the discharge line to filter out oil and grease. These units operate with one in-line and one off-line. The off-line unit is kept pressurised and ready for immediate use. Once a unit has been taken offline, it should be cleaned immediately and made ready for immediate use. Make-Up Water Supply This vessel has two distilled water storage tanks, any of which can be used to supply the condensate system. Normally one distilled water tank would be set for filling with a different tank in use and the other as a standby tank. Initial filling of water to the systems is performed manually from the distilled water tank to main condenser hotwell via make-up control bypass valve 144VPF with running the main condensate pump In this case, close surely the filling valve 146VPF for atmospheric drain tank, or the water will overflow from the tank. e) Set the system to now fill and maintain the level in the deaerator. Set the system valves as follows : Description Valve 151/152/153VPF Drain pumps suction valves 161/162/163VPF Drain pumps discharge valves 174VPF Drain tank level control valve 176/175VPF Drain tank level control valve inlet and outlet valves 177VPF Drain tank level control bypass valve 165VPF Drain tank recirculating valve
Grease extractor inlet and outlet valves

Position Open Open


Operational

Open Closed Open Set Close Open


Operational

Gland steam condenser bypass valve


Gland steam condenser inlet and outlet valves

185VPF 132VPF 131 / 133VPF 134VPF 119 / 121VPF 120VPF 122VPF 181/182/ 169VPF 186 / 187VPF

Open Close Open Closed Open Open Open f)

Spill control valve Spill valve inlet and outlet valves Spill bypass valve 1st feed heater inlet and outlet valves 1st feed heater bypass valve Deaerator feed inlet valve Feed water pump mechanical seal valves Feed water pump mechanical seal vent valves

Select a DUTY drain pump and place it on AUTOMATIC. Place the other drain pumps on STANDBY.

CAUTION The drain pumps must be operational shortly after the make-up to the atmospheric drain tank has been established. The make-up valve is controlled by the deaerator level controller and takes no account of the level in the drain tank. To Prepare the Main Condenser for Operation g) Establish the main sea water circulating system through the main condenser (See 3.5.1 "Sea Water Circulating System"). h) Close the atmospheric drain tank make-up valve 146VPF. i) Open the main condenser make-up valve 145 VPF.

Position Open Closed


Operational

Open Close Open Close

The atmospheric drain tank will now start to fill and will continue until a level is established in the deaerator. It is therefore important to start the drain pumps as soon as possible.

The level in the main condenser hotwell will start to rise. Open the bypass valve 144VPF around the make-up valve and allow the condenser hotwell to fill to slightly above normal level. (Note : If the make-up bypass valve is used during this operation, it must be closed after use.)

3.2.1

Condensate Water System


Procedure to Shut Down the Main Condenser
(For change main dump steam over to the auxiliary condenser)

Observe the atmospheric drain tank level during this operation and re-open valve 146VPF to allow make-up to take place if necessary. When the condenser hotwell level is satisfactory: j) k) l) Close valve 145VPF and restore the atmospheric drain tank make-up to normal operation by opening valve 146VPF. Check that the condenser recirculation valve 190VPF is operating properly. Set the system valves as follows : Description Main condensate pumps suction valves Main condensate pumps discharge valves Balance line valves Main condensate pumps sealing water valves Suction valve sealing water valves Distilling plant inlet and outlet valves Distilling plant bypass valve Main condenser recirculating inlet and outlet valves Main condenser recirculating bypass valve Valve
101/102VPF 112/114VPF 103/104VPF 106/107VPF 108/109VPF 128/129VPF 130VPF 191/192VPF 193VPF

The auxiliary condenser is not operated normally as long as the main condenser is sound conditions. a) Transfer electrical load on the turbine generator to the diesel generator. b) Start the auxiliary sea water circulating pump and circulate the auxiliary condenser. c) Shut down the off-load turbine generator. d) Change the turbine generator exhaust valve 001 / 011VPC to the main condenser over to the valve 021 / 022VPC to the auxiliary condenser. e) Change the main dump steam valve to the main condenser 037VPC over to the valve 038VPC to the auxiliary condenser. f) Change the 0.17 MPa steam range dump over to the auxiliary condenser by 055VPC and 056VPC. g) Start the turbine generator and transfer the electric load from the diesel generator if required. It is important to confirm the electric demand is less than 2,000kW with normal driving steam conditions (5.88Mpa x 510), because of atmospheric back pressure operation. h) Stop the main turbine, shut the steam stop valves, engage the turning gear and do not put on the main turbine warming through steam. i) Shut down the main turbine gland steam system. j) Slowly reduce the main condenser vacuum to fall off completely. Continuously check the main condenser for hot spots indicative of a steam leak. k) Allow the main turbine and condenser to cool down before stopping the main sea water circulating pump. l) Isolate the condensate recirculation valve 190VPF and the astern cooling spray valve. m) Stop the main sea water circulating pump, jack and lock the main condenser inlet and overboard valves. n) Stop the condensate pump and ensure that the condenser does not start to fill up. o) The sea water side has been completely drained. If checking for leaking tubes, it is possible to leave the vacuum pump operating and use cling film on the tube plate to locate the damaged tube. This check can also be done the conventional way, by filling the condensate side with a water / fluorescence mixture and checking the tube plate with a fluorescent lamp from the sea water side. When using a water / fluorescence mixture, the condenser must be thoroughly rinsed out before returning to service, in order not to contaminate the boilers. (Note : Before entering the sea water side of the condenser, open the doors and use a portable fan to aerate the chamber, leaving the forced ventilation in place during the time that personnel are inside.)

(Note : If the intention is to enter the steam side of the condenser, it must be remembered that in several steam lines to the condenser there is only single valve separation, depending on the method of condenser shut down.)

Alarms Sensor FS LT LT Tag No. 076 089 159 Function Main condenser level (from normal level) Set point ESD + 5 5 0 mm A S L D + 4 5 0 mm L A H + 3 0 0 mm

Position Open Open Open Open Open Open Closed Open Closed

FS FS LT LT LT

735 735 835 835 733/734

Atmos. drain tank level (from tank top) (from tank bottom) Deaerator level (from normal level) Distilled water tank level (from tank bottom) Gland condenser outlet temperature M.F.P.T. seal water differential pressure Main condensate pump discharge salinity Drain pump discharge salinity Aux. condenser outlet salinity

L A H - 3 5 0 mm L A L + 5 0 0 mm L A H + 4 0 0 mm L A L - 4 0 0 mm L A L + 1 5 0 0 mm

m) Start the main condensate pump. The condensate will now recirculate back to the condenser until the level in the condenser rises and the recirculation valve closes in. n) Operate the services to the following items as required by setting the valves as shown below : Position Open
Operational

TR

826

TA H

60

Description Dump steam condenser chamber spray valves


Dump steam condenser chamber spray piston valve

Valve
125/127VPF 172/173VPF

DPS

581

DPAL

20 KPa

Open
Operational

Dump steam desuperheater spray inlet valves


Dump steam desuperheaters Astern turbine cooling spray inlet and outlet valves Astern turbine cooling spray piston valve

SAL

831

4 ppm

Open
Operational

Open Open Open

Feed water pump mechanical seal valve Vacuum pump seal water valves Suction valve sealing water valves

183VPF 178/179VPF 198/199VPF

SAL

832

4 ppm

SAL

834

4 ppm

3.2.1a

Condensate Water System


DEAERATOR
125
(WATER SIDE) DUMP STM EXT. DESUPERHTR

FROM ACC

122VPF

H/S

100
TM 826

120VPF

40

173VPF

TIC 818

100

DUMP STM

TO MAIN OR AUX.CONDR

100

121VPF

125 125

1ST STG FD.W.HTR


119VPF

40
185VPF

172VPF

DPAL 580 DPS

GREASE EXTRACTOR

50

A
836
175VPF 174VPF 176VPF

DUMP STM

LM 835

LAH 835

LAL 835

6 100
167VPC
199VPC

100
179VPF

100

15

LIC 835

NO.2

25 15 15 15 100 25

183VPF

169VPF

MAIN CONDR VACUUM PUMP


AC 617
LAL 734 LM 734

25

25

RO 617

RM 617

SA 617
178VPF

TO DOSING 6 DILLUTION STATION TO FEED W.ANALY.

NO.2 DIST.W.TK
LI

NO.1 DIST.W.TK
LI

LAL 733 LM 733

100
168VPF VACUUM BREAKER

SAH 832

SM 832
170VPF

166VPC 198VPC

NO.1
6

25 125

NO.1 DIST.PLANT
125
129VPF

50

P
25
DPAL 581 DPS
182VPF

FOR SAMPLE

835

SPILL VALVE 133VPF 131VPF 132VPF

125 65 125

25
DPAL 581 DPS
181VPF

25

A
125
139VPF 136VPF 135VPF 138VPF

65

125
128VPF

50 150

P P

DIST.PLANT CIRC.W.TK

186VPF

134VPF

65

65

TO AUX. FEED W. LINE

FD W.SUC.

FD W.SUC.

65
821 190VPF 191VPF

65

141VPF 142VPF 144VPF

143VPF

150

FOR SAMPLE

FOR SAMPLE

125

130VPF

MAKE-UP V.

100 65

NO.2
6
187VPF

NO.1
6
186VPF

FROM FD W.ANALYZER

25 50

50
TAH 826 TM 826

MAIN FD.W. PUMP


50

15
180VPF

A
50 TO COLD START FD.W.PUMP
192VPF

SAH 832

SM 832
170VPF

80
193VPF

AOS 048

OIO 048

OIS 048

AUX.CONDR
80

25

80

100

6 150 25
FOR SAMPLE

PM 832
165VPF 163VPF

25 80

T
6

50
127VPF 125VPF

65

50

109VPF

125

GLAND CONDR

TM 8364

T
C
160VPF 153VPF

65

NOTE: (2) TO CLEAN DRAIN TANK


AST.W. SPRAY SPRAY W. FOR DUMP STM

250

P
25

PM 829 PS
CHANGE OVER

AOS 047

OIO 047

OIS 047

102VPF 104VPF

SAH 834

50

107VPF

200

NO.2

SM 834

NO.3
162VPF

50

CHANGE OVER

FOR SAMPLE

25
113VPF

613

100

80

PS

125
114VPF

ASD 089 LAH 159 LM 159 ESD M/T TRIP 076


FOR ST-BY 613 MAIN CONDS AS PUMP

25

SAH 831 SM 831

146VPF

C
FS

LAH 735
FOR DRAIN PUMP

P
PS 616

100

152VPF

MAIN CONDENSER
LIC 821

TM 825

103VPF

AST FS 616 FS AS 616 LAL 735

NO.2
161VPF

CHANGE OVER

250

101VPF

80

MAIN CONDS.PUMP
ASS 613 AC 613 RO 613 RM 613 SA 613
108VPF

105VPF

110VPF

150

NO.1
C
6

6
106VPF

262VPF

80

FS FS

FS

C
100
TM 844 TAH 844 ASS 616
151VPF

P
PS 616

AST

FLASH CHAMBER

150
FOR SAMPLE

ATMOS.DRAIN TK
381VPD

NO.1
DRAIN PUMP
AC 616 RO 616 RM 616 SA 616

CHANGE OVER

111VPF

125
112VPF

FS 613

145VPF

65

LIC 836

25

(2)

100

PS 616

100

80

177VPF

3.2.1b

Deaerator
To reduce the dissolved oxygen to the necessary low figure, a special direct-contact feed heater designed to meet all the above requirements is included in the feed -heating system. Steam is introduced into the heater shell and the feed water is sprayed into this steam, falling through a series of perforated trays in the opposite direction to the steam flow. Steam condenses in the incoming water spray, giving up its latent heat to the water and raising the temperature of the latter to saturation temperature. To reach the incoming water spray, the steam has to pass upwards through the curtains of falling water, removing the oxygen and driving it towards the vent, and thence to the atmosphere.

De-aeration of boiler feed water


Even in fully closed systems, not open to the atmosphere, there is always the possibility of the feed water being contaminated by dissolved oxygen. This is due to small quantities of air coming over with the steam, and to air leakage into sections of the steam and exhaust and feed systems which work at pressures less than atmospheric pressure. The amount of oxygen which water will hold in solution decreases with increased water temperature, and theoretically becomes zero when the water is at the saturation temperature corresponding to its pressure. Thus any oxygen which is in solution in the feed water will be released at any point or points in the system at which saturation conditions exist. Such conditions exist: (a) in the boiler drum, and (b) in the condenser. Oxygen released in the boiler drum could accumulate and become a potential danger for boiler corrosion, hence means must be provided in the feed-heating system to remove as much dissolved oxygen as possible from the feed water.
To achieve this, there are several requirements : 1. The feed water must be at the saturation temperature corresponding to its pressure. 2. The feed water must be broken up into droplets - the smaller these droplets, then the easier it is for the dissolved oxygen to be released. 3. The water droplets must be in contact with steam in such a manner and for sufficient time to enable the steam to "scrub" the oxygen and other incondensable gas from the water. 4. The oxygen and incondensable gas must be continuously removed. 5. The equipment used for de-aeration should operate at a pressure above atmospheric pressure at all times.

FEED WATER IN. AIR OUT.


SPRAY CHAMBER SPRAY NOZZLE BAFFLE PLATE PRIMARY HEATING CHAMBER FLOW DIRECTION BAFFLE

A deaerator heater of this type in Illustrate will reduce the oxygen content of the STEAM IN. feed water to not more than 0.005cm3/litre, whereas condenser de-aeration could not normally be expected to give less than 0.015-0.02cm3/litre. The condenser can therefore be regarded as the primary stage, and the deaerator heater the final stage of de-aeration. The feed-heating stages are chosen so that the direct-contact deaerator heater can be accommodated high up in the engine-room casing. The deaerator heater is combined with a de-aerated water-storage tank containing about ten minutes' supply of feed water at full power. This stored de-aerated water acts as a "buffer" in the system, to accommodate any transient differences between condensate pump output and boiler feed pump demand during power changes or manoeuvring, without having to spill excess water to, or receive make-up water from, atmospheric drain tank in which the water could absorb oxygen. The deaerator storage tank level can vary over a reasonably wide range, and as this level reflects storage or excess of water in the system, it is used to initiate operation of the deaerator control valves. High deaerator level opens the spill valve to pass excess water to the distilled water tanks, while low deaerator water level opens the make-up valve to pass water into the system via the atmospheric drain tank. As the water in the distilled water tanks is in contact with the atmosphere, it is likely to contain dissolved oxygen.
N.W.L.

CORN PLATE BALANCE PIPE

STEAM CHAMBER

By the nature of its function, the condenser fulfils these requirements to some extent, and gives a reasonable degree of de-aeration. However, unless primarily designed for de-aeration in addition to its other function, the condenser cannot give the low oxygen content necessary for modern high-pressure boilers. Toward the condenser bottom for example, the condensate falling from the tubes is likely to be in large masses rather than droplets; any undercooling of the condensate below the saturation temperature will render it capable of reabsorbing small quantities of oxygen, particularly if there should be any air concentrations in the condenser; air leakage into the condensate pump suction piping or into the pump glands can also cause aeration.

STORAGE TANK

FEED WATER OUT.

3.2.2

Boiler Feed Water System


Operation of Main Feed Pump
The main feed water line is the normal route for the feed flow through to the boiler steam drum. The main feed water line passes to the economiser inlet header through the 3rd stage feed water heater, the feed regulating valve and the motorised feed stop valve. The feed regulating and boiler level control system is described in section 4.3.4 Boiler Control Systems. Each main feed pump is provided with a recirculation line to the deaerator. Recirculation is necessary to prevent overheating of the pumps during low feeding conditions. Recirculation of main feed water pumps is controlled automatically. A small sized cross-connection with an orifice and valves 037 / 038VPF is piped at both main feed pumps discharge to maintain warming condition of the standby pump by the running water. The regulated quantity of feed water gains further heat from the boiler flue gases in the economiser and exits at the economiser outlet header. The boiler main feed stop valve is situated between the economiser and the boiler steam drum. Under normal operating conditions, the main feed pumps are started remotely. For automatic start-up, the switches on the ICAS screen must be in the 'Auto' position. To allow safe remote and standby start, the following are provided : a) Steam traps at upstream of the electric motor driven main steam stop valve, main steam turbine inlet and turbine exhaust casing to remove accumulated condensate. A small sized bypass line with an orifice is fitted around the motor driven main steam stop valve for turbine warming. A small sized cross-connection with an orifice between the discharges of both pumps for warming the standby pump by running one. A common pneumatically operated recirculating valve 033VPF, which is operated automatically to maintain minimum flow and prevents overheating of pumps.

Main Feed Water Pump (See 6.1 Main Feed Water Pump) Maker : Type : Capacity : Shinko Industries Ltd. Multistage horizontal, centrifugal 140 m3/h at 7.84 MPa

Cold Start Feed Water Pump Maker : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. Multistage horizontal, centrifugal 5 m3/h at 2.45 MPa 440V, 22kW, 3,600 rpm

b) c)

3rd Stage Feed Water Heater Sasakura Engineering Co., Ltd Maker : Shell and U-tube Type : 68 m2 Heating surface : 94,040 m3/h Cooling water flow : 19 mm diameter, 2.6 mm thickness Tube size :

d)

Set the valves to allow remote or automatic start-up the main feed pumps as follows : Position Open Open Open Open Open
Operational

Auxiliary Feed System


Main Feed System The Boiler Feed Water System consists of one deaerating feed water heater, two main feed pumps, one cold start feed pump, one high pressure 3rd stage feed water heater and all other necessary piping and fittings necessary to provide feed water to the two main boilers. The main feed system returns the condensate from the steam plant consumers back to the boilers. This involves raising the pressure sufficiently to create flow against the boiler steam drum pressure. This is achieved by turbine feed pumps which are high speed multi-stage centrifugal pumps. Two main feed pumps are supplied, one in use and one on standby. A third electrically driven cold start feed pump is supplied for use during the initial starting phase of the plant warming through procedure. The feed pumps take suction from the deaerator feed outlet which is situated high up in the engine room. This provides a suction pressure at the pump large enough to prevent the feed water from boiling at the pump entry. The location of the deaerator has the added benefit of providing a large reserve of water for the feed pumps in the event of a blackout. All feed pumps can deliver their output into both the main feed water line and the auxiliary feed water line. The auxiliary feed water line is provided for use when a problem develops with the main water line or the feed regulating valve or system. Its most direct route to the boiler bypasses the economizer. The auxiliary feed water valve is hand operated and under steady load conditions it requires little movement to maintain a steady steam drum water level. Spray water for 1.0MPa steam external desuperheater is supplied from either the main or auxiliary feed lines. The water is depressed by a pressure reducing valve 054VPF to 3.0MPa before entering the desuperheater. A recirculation line with double shut valves 057 / 058VPF and an orifice is provided for preventing over pressurizing in the line after the pressure reducing valve 054VPF when the supply of spray water is fully shut down by the control of desuperheater.

Open Open Open Open Open Open

Description Deaerator outlet Steam exhaust Feed water suction Feed water discharge Feed water recirculating Automatic recirculating valve Feed water recirculating on deaerator Turbine warming Pump warming LO cooler cooling water inlet LO cooler cooling water outlet Gland leak off isolating

No.1
041VPC 002VPF 012VPF 031VPF

No.2
042VPC 003VPF 014VPF 032VPF

Common

001VPF

033VPF 036VPF 023VPA 037VPF 065VPG 067VPG 045VPC 024VPA 038VPF 066VPG 068VPG 046VPC

It is recommended that the turbine nozzle hand valve is opened at all times. This will permit operation at any capacity within the capable of the pump. The recirculating feed water valve 036VPF on deaerator should be opened at any time with a lock.

3.2.2

Boiler Feed Water System


Controls
The feed water flow rate to main boilers is controlled by main feed water regulating valve (26B). The feed water regulating valve (26B) of each boiler maintains a water level in the steam drum under varying load conditions. The level can be selected to be either variable or fixed. This is achieved using a control system to monitor steam flow from the boiler for feed forward, feed water flow for feed back and steam drum level. The main feed pumps are controlled to maintain the constant differential pressure between steam drum and feed water common line. The main feed water common pipe pressure is controlled to higher pressure steam drum plus 1.0MPa, but the common pipe pressure is kept in minimum 7.0MPa. The main feed pumps can also be controlled to maintain the constant discharge pressure (7.84MPa) by the local control panel. Auto Start request to the standby pump will be initiated by failure of the running pump sensed by either main feed water low pressure (6.7MPa) or low differential pressure between steam drum and feed water common line (0.2MPa). Auto Start of the standby pump will be inhibited in case of extreme low water level in the deaerator (Normal level minus 1240mm). The recirculation valve is opened automatically by one of following conditions.

Operation of Cold Start Feed Pump


The cold start feed pump is manually started and the suction may be arranged from either the deaerator or the distilled water tanks. Set the valves before starting pump as follows : For Deaerator Suction Position Open Open Open Open Open Close Close Description Deaerator outlet Pump suction Pump discharge Boiler auxiliary feed stop Boiler auxiliary feed stop Economizer bypass valve Boiler main feed stop Valve 001VPF 004VPF 025VPF 11B 12B 13B 4B

Alarms
Sensor SAL PT DPT Alarm No 833 571 572 Function Deaerator outlet salinity Main feed water H PAL DPAL Set point 4 ppm

6.7 MPa 500 KPa

LT LT LT LT LT LT LT LT

463 521 521 464 072 082 083 064

Main boiler drum level (Main boiler)

ESD LAH LAL ESD ESD ASLD ASLD ESD

+240 +130 -130 -240 +220 +200 -200 -240

mm mm mm mm mm mm mm mm

For Distilled Water Tank Suction Position Open Open Open Open Open Close Close Description Distilled water tank suction Pump suction Pump discharge Boiler auxiliary feed stop Boiler auxiliary feed stop Economizer bypass valve Boiler main feed stop Valve 135/136VPF 008VPF 025VPF 11B 12B 13B 4B

(Main turbine)

Plant mode is maneuvering Boiler feed water flow is below 25 m3/h Both feed water pumps are run

The motorized feed stop valve (20B) of each boiler is provided against carry-over the water in the steam drum and it will close automatically by the extremely high water level in the steam drum (Normal level plus 220mm).

3.2.2a

Boiler Feed Water System

SET AT 9.07 MPA 21B

NOTE:
8B 7B 016VPF

TO 1.0 MPA DESUPERHTD STM LINE

64B

(2) TO CLEAN DRAIN TK (3) TO ATMOS DRAIN TK

40

65B

NO.2 MAIN BLR

020VPF 019VPF
TM SPM

TAL 806

TAH 806

TM 806 TIC 807

DEAERATOR
LOCKED OPEN

TRIP & START INTERLOCK FOR ST/BY FD.W.PUMP

100

61B

12B 62B

4B

T
100

ECO.
ABNOR
XA 497 OIS 497 OIO 497 807

T A I/P P
807

FS

551

25

036VPF

6B 5B

100

13B

100
20B

FROM CONDS. PUMP DIS.


PIC 807

1.0 MPA DESUPERHTR

001VPF

"C"
200 50
(2) 203VPF

11B

FROM A.C.C.
ACC 496 PM 571 PAL 571

FOR FD.W. PUMP CONTROL


PIC 553 PM 501 DPI 572 DPL 572

26B 1B 053VPF 054VPF

25 100
055VPF

50

ACL 497

100

(2)

25
056VPF

T
FM 6/0.6 MPA P.R.V.
TM 827

10

TO ANALYZER

FOR FWR
029VPF
407

25
057VPF

058VPF

25

SAH 833

SM 833

P
100

202VPF

10

40

FROM DIST.W.TK
PIC 553

125

200

FM OXYGEN SCAV. CHEMICAL TK

50

50

200

DPI 572 DPL 572 PIC 553 PM 501 ACC 496

S
407

008VPF

004VPF
OIO 567

50

FOR FWR

200

TO DISTILLING PLANT

1B
26B

25

LS

003VPF

033VPF
AOS 569 OIO 569

OIO 567

LS

002VPF

FOR FD.W. PUMP CONTROL


11B

P
ACL 497 OIO 497 OIS 497

P
AC 552 RO 552 RM 552

FROM A.C.C.
13B

20B

AC 552

RO 552

RM 552

SET AT 9.07 MPA 21B 064VPF

100

XA 497

SA 612

RO 612

RM 612

100

P
032VPF 025VPF 031VPF

50

100

100

COLD START FD.W.PUMP

NO.2 MAIN FD.W.PUMP

RO 569

NO.1 MAIN FD.W.PUMP


P

125

7B 8B

ABNOR

50

50

015VPF

125

40

40

019VPF
TM SPM

25
038VPF 037VPF

25

25
61B 62B

100 25
5B 6B 64B 051VPF 65B 052VPF

25

40

12B

4B

ECO.
023VPF 024VPF 013VPF 014VPF

021VPF 022VPF

125

011VPF 012VPF

NO.1 MAIN BLR

SET AT 10.0MPAG (FD.W. SIDE)

TM 828

017VPF

027VPF

(AUX. FEED W. LINE)

100

125

40

100 125

041VPF

3RD STG FD.W.HTR


(2)

042VPF

(MAIN FEED W. LINE)

PROTECT.RING

(3)

80

100

FROM ICAS

3.2.3

Boiler Water Sampling and Treatment System


The main water analyzer unit for the boilers has permanent sample lines fitted. Each sample point is led to a common test equipment which comprises the sample being led through the cooler and then to permanent test meters. The water analyzer unit samples the following points : Port boiler water drum sample : Starboard boiler water drum sample : Feed pump suction sample : Main condensate discharge sample : The amine dosing pump are motor driven diaphragm pumps providing accurate and reliable dosing with no risk of chemical spillage through leaking glands. The pump output is set by adjusting the stroke length.

Sampling, Analysis and Chemical Dosing Unit Maker : Unit type: Dosing Pump type : Tank size : Discharge pressure : Capacity : NALFLEET Nal-Trak3000HP For HP : KM281-2-10021 For LP : KM208-1.0-10361 4 x 25 litres For HP : 10.0Mpa For LP : 1.0 Mpa For HP : 0-2.4 litres/h For LP : 0-1.2 litres/h

pH, Conductivity and Resolved oxygen

Chemical analysis and treatment of feed water is undertaken to prevent corrosion and scale formation in the main boilers and feed system and degradation of the steam quality. Inadequate or incorrect treatment can result in severe damage to the boilers and constant monitoring is necessary to give an early indication of possible contamination of the feed water. Chemical treatment and analytical tests must be undertaken in accordance with the detailed instructions given by the chemical supplier and the water characteristics maintained within the ranges specified. Test results are to be recorded in a form that enables trends and the effect of treatment to be monitored. The dissolved solids in the boiler water are controlled by use of scum lines in the steam drum and/or blow down valves in the water drum, through which these impurities are discharged overboard. These systems are an integral part of the boiler water treatment.

Manual testing should be carried out to test for contaminants not covered by the permanent testing meters. Manual testing should also be made to check calibration of the permanent test meters on a regular basis. Samples are cooled to give a constant temperature for the test equipment. The cooling water is taken from the condensate water system where it is returned to atmospheric drain tank it has passed through the coolers. Sample water from the boilers and the feed system is returned also to the atmospheric drains tank from where it is recycled into the condensate system.

The phosphate and alkalinity chemicals are supplied into the steam drum of main boiler. Each unit consists of a tank into which the chemicals to be dosed are mixed with distillate water supplied from the main condensate system. The units serve the both boilers using high pressure dosing pumps to inject the chemicals into the steam drum, through its chemical injection valves. The chemical dosing line is common and therefore each chemical is dosed sequentially to each steam drum by switching solenoid valves fitted at discharge of each dosing pump. The pump is started locally and will stop automatically The metering pumps are used to apply the alkali and phosphate boiler treatment products. These pumps are capable of generating the high output pressures needed to inject the treatment directly into the boilers. These pumps use a hydraulically actuated diaphragm design to produce the high pressure without danger of leaking seals. A piston pump running in an oil bath drives the diaphragm pump head. The pump stroke is controlled by a sliding vent shield around the piston which allows oil to recirculate for part of the piston stroke.

Chemical Dosing and Dilution Units


There are four separate chemical injection units fitted to supply chemicals to the boilers and feed water system. As these units contain chemicals, they are constructed of chemical resistant materials such as stainless steel throughout. The oxygen scavenging chemical is supplied continuously into the deaerator and the amine chemical is injected into the drop line to the feed water pump suction. Each unit consists of a tank, which is filled with a mixture of distillate water supplied from the main condensate system. They are mixed in the tank and the resulting mix is injected into the deaerator and the feed line through the respective metered pump. The pump for oxygen scavenger is continuously powered and independent of the master pump power switch. This pump has no stroke length adjustment device. Its output is controlled by adjusting the motor speed. In normal operation the pump speed is adjusted according to the dissolved oxygen level by the Nal-Trak 3000HP controller using a 4-20mA control signal. A priming facility is built into the pump electronics and is accessible on the pump control panel.

Water Analysis and Treatment Integration with the ICAS System The ICAS screen displays the continually updated results from various test points around the feed system. It also allows monitor of the dosing pumps. On-line analyzers are fitted to various units in the feed system and constantly monitor the water condition raising an alarm when a specific contamination is detected. They are fitted at the following points : No.1 evaporator distillate : No.2 evaporator distillate : Distilling plant circulating water Auxiliary condenser outlet : Drains pump discharge : Deaerator outlet : Main condensate pump discharge : Salinity Salinity Salinity Salinity Salinity Salinity Salinity

After the treatment mixture has been pumped, the lines should be flushed for a minimum of thirty minutes at maximum stroke to ensure the treatment is displaced to the boiler(s). WARNING Handling chemicals is a hazardous procedure and full protective clothing must be worn at all times whilst handling these substances.

3.2.3
Alarms Sensor

Boiler Water Sampling and Treatment System


Tag No. 838 Function Conductivity (Boiler water) H (Main feed water) H pH (Boiler water) H (Main feed water) L H L 840 Dissolved oxygen (Boiler water) H (Main feed water) H 10.4 9.5 9.2 8.3 Set point 300 S/cm 5 S/cm Control of the feed water pH is necessary to prevent corrosion in the feed water system. Too low a feed water pH will result in corrosion in the feed water system with the corrosion products being carried into the boiler where they form scale and sludge. Too high a pH can result in damage to any copper alloys in the system. Feed water pH is controlled by injecting oxygen scavenger into the system before the feed pump suction. Oxygen scavenger also acts as a oxygen scavenger and acts to eliminate oxygen from the system. Oxygen content in the system will result in pitting which can be both rapid and severe. This undesirable effect is avoided initially by the correct operation of the deaerator and then by use of oxygen scavenger injection. Oxygen scavenger does not function as an oxygen scavenger at temperatures below 130C and decomposes once inside the boilers due to the high temperature. It is therefore pointless to add the chemical to the feed system at too early a stage or to attempt to maintain a oxygen scavenger reserve in the boiler. Sufficient oxygen scavenger should be added to leave a detectable trace at the inlet to the boiler i.e. after the economizer. Excessive hardness in boiler water tends to form scale on the tubes which can result in local overheating and tube failure. Hardness is mostly caused by sea water contamination of the feed water and is controlled by chemical injection, forming a harmless sludge which settles and can be blown out of the boiler. It is therefore advisable to keep the hardness of the feed water to a minimum to reduce chemical and feed water consumption. Should contamination be detected in the system, the source must be identified and eliminated as soon as possible, with increased blow down and chemical treatment simultaneously attempting to maintain the pH and phosphate levels in the boiler water. Silica contamination is unlikely to occur whilst using ships make-up water but may occur when the vessel bunkers distilled water, or is operating in a sandy coastal area. Silica solubility in steam increases as boiler pressure increases. This may result in a hard scale formation on turbine nozzles and blades resulting in a drop in efficiency and mechanical troubles. Silica contamination should therefore be restricted to the 3 ppm limit previously defined. Chloride contamination attacks the protective film that forms on the tube surfaces inside the boiler, promoting corrosion. Chloride contamination is easy to measure and can be used as a guide to the dissolved solids content of the boiler water. Chloride contamination can usually be tracked using the feed system salinometers, but where no particular contamination source has been identified and chloride levels are rising, it can be taken as a measure of main condenser leakage. Chloride contamination cannot be tackled by any other means than blowing down and this should be done in practice to keep the chloride levels as low as possible. 20ppm should be considered a maximum. As chloride levels are kept so low in the boiler, it is considered unnecessary / impractical to measure the levels in the feed water. A high dissolved solids content in boiler water results in increased carryover, which results in deposits in the superheater section of the boiler and in the turbine and also results in increased electrical conductivity, which promotes corrosion. Exact measurement of the dissolved solids content is a long and difficult process, however, electrical conductivity is approximately proportional to the concentration of dissolved solids and this relationship can be used to provide an approximate measurement of the dissolved solids total. This relationship is not exact as many ions are not electrically conductive, so this measurement is only a rough guide to the condition of the boiler water. A more useful and accurate measurement is produced by carrying out the chloride ion test detailed above.

839

0.02ppm 0.02ppm

Water Specification (Boiler Manufacturer Figures)


Boiler Water pH : Conductivity : Total dissolved solids : Chlorides : Phosphates : Silica : Feed Water pH : Total hardness : Dissolved Oxygen : Oxygen scavenger reserve : 8.0 - 9.0 (target 8.7) 0ppm 0.02cc/litre 0.01ppm or above 9.6 - 10.3 less than 400S/mm less than 200ppm less than 20ppm 10 - 20ppm less than 3ppm

Sampling Procedure The following information applies to whichever of the sample units is being used. a) Check that the cooling water lines from the condensate system to the individual analyzer coolers are open. Check that the cooling water flow is correct with the flow meter. Ensure that the cooler outlet valve to the sensing units is closed. Open the inlet valve to and the outlet valve from the cooler, allowing the line to be tested to flow through the cooler. Allow several minutes to pass while the line is drained of any standing water which may be present from previous use. Some of these lines cover large distances and must be allowed time to clear in order to ensure a water sample is taken of the water presently in the system. Check the thermometer in the line to ensure that the sample is at the correct temperature. A sample taken while the temperature is too high may not be tested satisfactorily, as the test chemicals and the test equipment is only rated at certain temperatures. Once the line has cleared and the temperature is correct, the valve to the test analyzer units opened. Manual samples may be taken from the bypass line.

b) c)

d)

(Note : The following information is given for general guidance only. Reference must be made to the specific instructions from the boiler chemical supplier regarding final data for chemical treatment of the boilers and feed water.) Corrosion of steel by high temperature water such as boiler water is minimized at a pH of around 12. However, it has been demonstrated that, as the pressure and load on the boiler increases, a high pH value tends to form local concentrations in hot spots resulting in increased local corrosion. For this reason, the pH is maintained at 9.6-10.3 using phosphate treatments instead of highly concentrated caustic soda. This results in phosphate reserve in the boiler water as defined above.

e) f)

WARNING Boiler water samples are taken from the water drum or the main feed line and are therefore at a high pressure and temperature. Great care should be taken whenever these valves to the sample unit are opened. This must be done slowly.

3.2.3

Boiler Water Sampling and Treatment System


Boiler Compound Injection Unit Boiler Blow Down Procedure
Boiler blow down through the valves on the water drum or steam drum imposes a considerable load on the boiler. When in port, the duty deck officer should be contacted, to ensure that the discharge from the ships side will not be dangerous. The correct amount of blow down is determined from experience and through consistent testing and blowing down procedures. a) Position Open Open Open b) Position Open Open c) Open the following valves fully. Description Ships side blow down valves Boiler primary blow down valve Boiler primary scumming valve Valve 041/042VPF 65B 62B

If any samples are also to be taken from the analyzer unit meters, then clean dry flasks with stoppers are to be used. The flask should be filled to overflowing and sealed to prevent any ingress of oxygen while the flask is standing waiting testing.

Chemicals are injected into the boiler steam drum under its water level. This is done so the natural water circulation system within the boiler will move the chemicals around the boiler and ensure an even distribution. Dosing Procedure a) b) Fill each dosing tank with water from the main condensate discharge, piped to the filling valves. Add the chemicals to be dosed to each tank, based on the results of the boiler tests. Stir the water with a paddle and allow any powdered chemical to dissolve. Open the pumps' discharge valves and the boiler drum chemical injection primary and secondary valves. Ensure that the dosing pump crossover valve and the boiler drum chemical injection primary and secondary valves on the boiler not being dosed are closed. Start the pump motor which drives both pumps simultaneously. Both the pumps can be started locally.

Oxygen Scavenging Chemical Unit


The oxygen scavenging chemical unit should be operated continuously to maintain a constant oxygen scavenger reserve with little fluctuation. The capacity of the tank is such that a full tank will continuously dose the system for approximately three days. The concentration of oxygen scavenger should be varied depending upon the results of the tests.

c) Dosing Procedure a) b) c) Fill the dosing tank with water from the main condensate discharge, piped to the filling valve. Add the oxygen scavenger and amine to be dosed to the tank based on the results of the condensate and boiler tests. Open the tank outlet valve, the pumps discharge valve Open valve 201VPF on the deaerator and 202VPF to the main feed pumps suction line. Start the pump motor. The pump is started initially at local panel and will be automatically started and stopped by local system in accordance with analyzed data. d)

For blow down or scumming, slowly crack open the secondary valve as required, as in the following table. Description Boiler secondary blow down valve Boiler secondary scumming valve Valve 64B 61B

The blow down / scumming line is fitted with an orifice plate which should limit the blow down rate, allowing the secondary valve to be fully opened. This should be done slowly and with due regard to the boiler load. As the blow down progresses, continually monitor the boiler water level and ensure this is being maintained and the feed pump discharge is coping with the extra load. When the blow down is to be stopped, close the secondary and primary blow down valves, then the ships side valve.

The dosing pumps will be stopped by a level switch when the tank is nearly empty. WARNING Handling chemicals is a hazardous procedure and full protective clothing must be worn at all times whilst handling these substances.

d)

d)

e)

The dosing pump will be stopped by a level switch when the tank is nearly empty. WARNING Handling chemicals is a hazardous procedure and full protective clothing must be worn at all times whilst handling these substances.

(Note : Blow down or scumming should always be controlled on the secondary valve to prevent damage to the primary valve.) Blowing of boiler water is usually done by scumming valves on the steam drum. Blow down of the water drum may be done approximately once for every two weeks when the boiler runs under the load of less than 50% of normal rating.

3.2.3a

Boiler Water Sampling and Treatment System

10

244VPF

S 10
201VPF

DEAERATOR

HYDRAZINE

203VPF

10

243VPF

S 10
202VPF

CONDENSATE TREATMENT
68B

67B

10

242VPF

10

10

15B

16B

NO.2 MAIN BLR

NO.2 MAIN FD.W.PUMP

NO.1 MAIN FD.W.PUMP

10 10 10

BOILER PHOSPHATE

SAMPLE COOLER & TRASAR UNIT


10 S
241VPF

10 10

S S 10 10
15B 16B

NO.1 MAIN BLR


S
67B 68B

BOILER ALKALINITY

TS S

XAL 839

XAH 839

XAH 838

XAH 840

PH

CD

OM

10

10 10

S S S

DOSING & DILUTION SECTION

FS NOTE: (3) TO CLEAN DRAIN TK

FS

FS

MONITOR & INJ.PUMP SKID

15

15

15

15

15

10

15

TO ATMOS. DRAIN TK

25 25

10

15

FROM COND. W.

3.2.5

Clean Steam Drain System


Open drains from low points in the main and auxiliary steam piping and the auxiliary exhaust piping, in general, are directed to the clean drain tank so that they can be directed overboard without treatment as bilge water. The gland steam condenser drain is led to the atmospheric drain tank with U seal which compensates the vacuum in the gland condenser. Drains on the HP 1st stage turbine, main turbine stop and astern maneuvering valves and 1st bleeder are led through orifice plates to the main condenser via drains pockets. These drains are controlled by pneumatically operated valves which are controlled via the main turbine control system. Other drains from around the turbines are led directly to the main condenser via orifice plates to provide permanent drainage. The soot blower system line drains are led directly to the bilge but collected into the clean drain tank. This is due to the intermittent and limited nature of the use of this system and the possibility of solid contaminants such as rust or carbon entering the feed system. For To atmos. drain tank (078VPD) : Open Close : At Normal Mode or 3rd bleed steam pressure over minus 35kPa : At Maneuv Mode or 3rd bleed steam pressure under minus 40kPa

Drains which are considered to have no danger of oil contamination are recycled directly to the main feed and condensate systems. They are collected in either the atmospheric drain tank or the main condenser. Collected drains include : All line drains Burner atomizing steam drains Burner purging steam drains Steam air heaters Turbines casing drains Evaporator drains 1st feed water heater Gland condenser Inert gas system Many of the drains (although not all) are fitted with drain traps. In order to obtain maximum benefit from steam as a heating medium it is allowed to condense in the steam service as this recovers the latent heat of evaporation in the steam. Drain traps are fitted at the outlets from such heating coils so that only water is allowed to pass. Some drain traps are fitted with bypass valve to provide continued service should the drain trap malfunction. These services are the high pressure services, where direct supply to the atmospheric drain tank through a bypass is inadvisable, but guaranteed service is essential. Low priority drains where other drain traps are available elsewhere in the line have no bypass at all. After passing the drains trap, the drains from the two steam air heaters and the 3rd feed water heater are both directed to the 1st feed water heater, where they are utilized for heating the feed water. These drains can be bypassed around the 1st feed water heater during periods when the 1st feed heater is not in use. The drain level in the 1st feed water heater is controlled by a pneumatic level control valve (075VPD) and the drain water is directed to either the atmospheric drain tank or the main condenser. The changeover of these valves is made by two pneumatically operated piston valves (078 / 079VPD) depending upon the plant condition. Two further line valves are fitted, one valve 080VPD at the main condenser and one valve 081VPD at the atmospheric drain tank. Valve 081VPD is a non-return valve to prevent air from the atmospheric drain tank being drawn backwards to the main condenser. The drain level in the 3rd feed water heater is controlled by a pneumatic level control valve (042VPD) and the drain water is directed to the deaerator.

Controls
The drain piston valves of main turbine are automatically operated on the following conditions.

Open Close

: At Slow Ahead : At Half Ahead

The destination of drain water in 1st feed water heater (atmospheric drain tank or main condenser) is changed over by two piston valves (078/079VPD) according to plant mode and/or the 3rd bleed steam pressure conditions. The two valves are interlocked by the ICAS to prevent both valves being open at the same time. For To main condenser (079VPD) : Open Close : At Maneuv. Mode or 3rd bleed steam pressure under minus 40kPa : At Normal Mode or 3rd bleed steam pressure over minus 35kPa

3.2.5a

Clean Steam Drain System


15

NOTE: (3) TO CLEAN DRAIN TK

FUNNEL

(5A)

DEAERATOR
LIC 823 TM SPM 823
044VPD

3RD STG FD.W.HTR S.A.H.


40 15 50
294B

40

25 50

GLAND CONDR

T
036ZPD

A
041VPD 042VPD 043VPD

50 40 50

50

50

071VPD

822

026ZPD

1ST STG FD.W.HTR

LIC 822 822

073VPD

A
TM SPM
077VPD

65

0.17 MPA P.C.V.

15

285B 472B

15 15

(3)
SOOT BLOW STM HDR
022VPA

FROM MAIN BLR 021VPA

100 15
035ZPD

LONG

50

074VPD 075VPD

076VPD

(3)

15

028ZPD

15

15

004ZPD

15 15

LP TURBINE
FLUSH CHAMBER

65
TO AST. TURB. AST.GUARD.V.

080VPD

AST.MANEUV.V.

079VPD 078VPD

MAIN STM

PURGE STM HDR

15

15

15

027ZPD

15 25 15

MAIN FD.W.P. TURBINE

15

ATOMIZ.STM

15

029ZPD

15

NO.2

NO.1
25
OIO OIS 0452 0452

AOS 824 RO 824 OIS 824

25
005ZPD

2ND BLEED 034ZPD

15 25

HP 1ST STAGE

15

022ZPD

OIO 824
OIS 0451 OIO 0451 OIS 0454 OIO AOS 0454 0454

15 25

HP TURBINE
15

PURGE STM HDR ATOMIZ.STM

15

024ZPD

15

006ZPD

15

1ST BLEED 033ZPD

MAIN STM

15

023ZPD

15
011VPA 012VPA

(3)

(3)
15

EXH.STM DUMP V.

100

NO.1 MAIN BOILER


285B 472B

FROM MAIN BLR


15 15
011ZPD

15 15

LONG
SOOT BLOW STM HDR

15

031ZPD

031ZPD

15

25

NO.2
021ZPD

15

014ZPD

(3)

15

25

(3)

50

50

MAIN GEN. TURBINE


FROM BLR IDSH

MAIN DUMP V.

S.A.H.

294B

081VPD

(3)
15 15

NO.1
FROM CO2 BOTT.& FORM TK RM FROM INERT GAS DRYER

(3)
15
013ZPD

15 15 15
002ZPD 001ZPD

1.0 MPA DESUPERHTR

15 15

25

037ZPD

15

25

(3)

25

80

ATMOS. DRAIN TK

25

OIO 0453

OIS 0453

GLAND STM MAKE-UP V.

100

15

003ZPD

15

15

NO.2 MAIN BOILER

MAIN CONDR
3RD BLEED

OIO 824

OIS 824

RO 824

AOS 824

3.2.6
Drain Cooler

Contaminated Drains System


Operation Setouchi Kogyo Co., Ltd. 1 Single pass shell and tube 5.0m2 20 m3/h 1.28 m 16 mm diameter, 1.2 mm thickness a) Check that the drain cooler is being circulated by cooling water. b) Open the drain cooler inlet and outlet valves 171VPD and 172VPD. Ensure the drains cooler bypass valve 173VPD is closed. Open the drains cooler vent and drain valves. c) Open Cuno filter inlet and outlet valves 174VPD and 175VPD. Ensure the filter bypass valve 176VPD is closed. Open the filter vent and drain valves. d) Check the contents of the drain inspection tank. If contamination is present, drain the inspection tank through valves 177VPD, 178VPD and 179VPD. Ensure these valves are closed when finished. e) Open all steam trap isolating and by-pass valves for the selected heating tanks and heaters. f) Open all the drain return valves on the selected heating tanks and slowly open the steam inlet to the heating coils, then after initial draining of steam drain lines, close steam trap by-pass valves. The steam trap isolating valves are normally left open. g) Ensure those drains cooler and filter vent and drain valves are closed as clean condensate is observed flowing out of the drain/vent pipes. (Note: Heating steam drains for frigid climate condition are collected directly into the atmospheric drain tank as clean drains without through the drains inspection tank.)

Maker : No. of sets : Type : Cooling surface : Cooling water flow : Tube plates Distance : Tube size :

The low temperature desuperheated steam is supplied to oil heating services, and the condensate drains have potentiality of oil contamination. The contaminated condensate drains are returned to the main feed cycle via atmospheric drain tank after first being decontaminated in the contaminated drains system composed with a drain cooler, filter and drain inspection tank. Once separation has taken place at drain inspection tank. Both the drain cooler and the filter may be bypassed if necessary but the drain inspection tank cannot be bypassed. (Note : When the by-pass operation is requested for the drain cooler and / or filter, the inlet side valve (171/174VPD) should be closed after the by-pass valve (173/176VPD) has been opened to prevent over pressure of the drain cooler and the filter.) The drain inspection tank is divided into two sections. A sight window is provided at the upper part of each section. Water flows from the primary section to the secondary through an access at the bottom of the dividing partition. Any oil floating on the surface of the water will overflow into the drains. A filter with glass fiber elements (Cuno Filter) is provided at the outlet of the drain cooler to capture the oil primarily before drains enter the drain inspection tank. An oil content detector is provided to monitor the presence of oil at the primary section of drain inspection tank.

Controls

The drain level in the hydrant water heater which will be used against frigid climate condition is controlled by a pneumatic level control valve and the drain water is directed to the atmospheric drain tank. Alarms Sensor SAL Tag No. G1907 Function Hydrant heater outlet salinity Oil content H Set point 4 ppm

Drains from gas heaters and vaporizers which have potentiality of cargo gas contamination are led to the gas vent drain tank through the gas heater drain cooler. The drain from the gas vent drain tank which is located in the cargo machinery room is led through a U-tube water seal to the atmospheric drain tank. Any vapor or gas contained in the condensate is released within the gas vent drain tank. Such vapor or gas is monitored by a gas detector provided to the air vent pipe and then vented to atmosphere.

Oil content detector

901

1 5 ppm

3.2.6a
FROM MOORING DK

Contaminated Drains System


181VPD

65

65 25

40 40 65

FROM UNDER DK PASS.(P)

INCINERATOR WASTE OIL SETT.TK DO TK EDG DO TK NO.2


180VPD

FROM AIR COND.& ACCOMMO.

40

25 40 25 25

421ZPD

25 25 25 25

182VPD

NO.1
422ZPD

FROM DECK HTR UNIT (P) FROM DECK HTR UNIT (S)

FROM FLYING PASS.


183VPD

ROOM HTR (P)

25

FROM CARGO MACH. RM

40

40

15

423ZPD

80

15

IGG GAS OIL TK ROOM HTR (S)


LIC G1906

D.O.STOR.TK

F.O. SIDE TK (P)

NO.2 F.O.SETT.TK

40

405ZPD

25

15 15 15 15

25

424ZPD

15 15 15 0.6MPA DOMESTIC STEAM LINE

411ZPD

SAH S I G1907 G1907

136ZPD

40

40

HYDRANT HTR
15 15

195VPD 125VPD

196VPD 121VPD

197VPD 122VPD

198VPD 123VPD

199VPD 124VPD

135ZPD

40 40

134ZPD

40 40 40 40 40

NO.4 BLR FO HTR NO.3 BLR FO HTR NO.2 BLR FO HTR

133ZPD

25

25

40
122ZPD

25

15
124ZPD

15 0.3MPA DOMESTIC STEAM LINE

139ZPD

15

40

40 40

132ZPD

15

131ZPD

NO.1 BLR FO HTR

15

15 25 15

137ZPD

15 25 15

40

138ZPD

HOT W.HTR

40 50 DRAIN HEADER LO SLUDGE TK FO OVERFLOW TK

40

25

40
168VPD

15 FROM FWD F.O.TK 15


104VPD

126ZPD

125ZPD

117ZPD

171VPD

50

50

15 15 15

114ZPD

15

80

PURIF. LO HTR
15 15 40

L.O. SUMP TK

DRAIN COOLER
T
172VPD

115ZPD

173VPD

116ZPD

50 65

176VPD

175VPD XA 901

174VPD

50

15

40

40

25

40

15

15

15

15

15

15

15

15

FILTER

109ZPD

40

102ZPD

25

104ZPD

OIL DETECT.
XA 901

25 25
118ZPD 119ZPD 112ZPD 412ZPD 113ZPD 105ZPD 107ZPD 106ZPD 108VPD

25 25

15

100

DRAIN INSPECTION TK
179VPD 178VPD 177VPD

109VPD 194VPD 189VPD

101VPD 190VPD

102VPD 191VPD

103VPD 192VPD

15

15

15

15

15

15

15

15

193VPD

25

50

25

SEP.BILGE OIL TK 50

F.O.DRAIN TK

ATMOS.DRAIN TK

TO BILGE HOLD TK

G/E L.O. RENOV.TK

A/T L.O. RENOV.TK L.O.RENOV.TK

NO.2

NO.1 D.O.STOR.TK LOW SULPHER F.O.TK F.O. SIDE TK (S) NO.1 F.O.SETT.TK

D.O.SERVICE TK

3.3.1

Compressed Air System


The service air system provides compressed air for the following purposes. Air-operated tools and equipment Air horn and air whistles Pressurizing system for fresh water pressure tanks Operation of fire emergency shut-off system Engine room service Steering gear room service Cargo machinery room service Deck service Bubbling for water ballast tanks in frigid climate Accommodation service The control air system is distributed for the following purposes. Essential control equipment Miscellaneous control equipment N2 generator Cargo machinery room equipment Cargo equipment Air pressurized lighting system ESDS b) d) e) f) Ensure that there is air in the general service air receiver at the desired pressure and that the air compressor is operating. Select LOCAL operation at the compressor control panel, and AUTO position on the ICAS screen. Operate the working air system as required with air being taken from service outlets as needed. When air is not required the valve will be closed. Check the system drain traps are operational. Check that the compressor starts and stops automatically supplying air as required. Ensure that remote service outlets are receiving air. Air valves to service locations should be opened periodically to blow them through in order to remove condensate and prevent seizure.

Air Compressor Maker : No. of sets : Type : Capacity : Rating : Control Air Dryer Maker : No. of sets : Type : Capacity : Nihon Seiki Co., Ltd. 2 sets Duplex, auto-regenerative adsorption 400 m3/h at a dew point minus 40 Tanabe Pneumatic Machinery CO.,Ltd. 3 sets Screw, water cooled, oil injection 550m3/h at a pressure of 0.9 Mpa 440V, 75kW, 1,800 rpm

g) h) i)

Control Air Receiver Maker : No. of sets : Capacity : Safety valve : Henmi Iron Works Co., Ltd. 1 set 5 m3 1.10 Mpa

Procedures for Operating the Control Air System a) Ensure that all instrumentation valves are open and that the instrumentation is functioning correctly. Check that cooling water is being supplied to the service air compressor from the central fresh water cooling system. Set No.1 and No.2 air compressors valves as in the following table. The compressors discharge and line valves will all be open so that the compressors can fill the control air reservoir. The compressors start and stop automatically according to the system pressure. Valve
011 / 012VPE 012VPE 001 / 002VPE 008 / 020VPE 007VPE 021VPE 022 / 023VPE 025 / 027VPE

General Service Air Receiver Maker : No. of sets : Capacity : Safety valve : Henmi Iron Works Co., Ltd. 1 set 5 m3 1.10 Mpa

The compressed air system is divided into four separate parts of general service air, control air, starting air and feed air for N2 generator. Three identical air compressors are provided for general service air and control air systems as common use. Normally, No.1 and No.2 compressors will supply the control air system and No.3 supplies the general service air system. Two vertical cylindrical air receivers are provided to act as buffer storage vessels, one for the service air system, the other for the control air system. Two identical 100% duty (400Nm3/h) air dryers of adsorption type are provided for the control air system. A inter-connection is piped between the control air and general service air for deck uses against frigid climate condition.

The control air for essential equipment is supplied via two separate lines with isolation facilities.

Procedures for Preparing the General Service Air System Operation a) Ensure that all instrumentation valves are open and that the instrumentation is functioning correctly. Check that cooling water is being supplied to the service air compressor (normally No.3) from the central fresh water cooling system. Set No.3 air compressor valves as in the following table. The compressor discharge and line valves will all be open so that the compressor can fill the service air reservoir. Valve
016 / 017VPE 017VPE 003VPE 008 / 020VPE 041VPE

b)

Position Description Open General service air receiver manual drain valve Close Manual drain valve after drainage Open No.3 air compressor discharge valve Close Cross-connection valve between general service and control air system Open General service air receiver outlet valve

Position Description Open Control air receiver manual drain valve Close Manual drain valve after drainage Open No.1 and No.2 air compressors discharge valves Close Cross-connection valve between general service and control air system Open Cross-connection valve Open Control air receiver outlet valve (Locked) Open Either No.1 or No.2 control air dryer inlet valve Open Either No.1 or No.2 control air dryer outlet valve c)

Ensure that there is air in the general service air receiver at the desired pressure and that the air compressor is operating. At the compressor control panel, select both air compressors for REMOTE operation and select AUTO position and select one compressor for LEAD duty and the other for FOLLOW on the IAS screen. Start the duty compressor. Check that the compressor operates correctly.

d) At the compressor control panel, select No.3 air compressor for LOCAL operation and start the compressor. Check that the compressor operates correctly.

3.3.1
e) f) g) h) i)

Compressed Air System


Alarms

Ensure that there is air in the control air receiver at the desired pressure and that the air compressor is operating. Set the control air system valves. The valve for any system will only be open when control air for that system is required. Check the system drain traps are operational. Check that the compressor starts and stops automatically supplying air as required. Manifolds are provided with drain valves and these should be operated daily in order to drain any water which is present in the system. Check the operation of the control air system periodically and ensure that the dryers are working effectively.

Sensor PT PT

Tag No. 751 752

Function Control air receiver General service air receiver Emergency shut-off air receiver Control air main line Boiler trip by low control air pressure

Set point PAL PAL 0.6 MPa 0.6 MPa

PS

755

PAL

0.6 MPa

PT PS

905 465

PAL ESD

0.45 MPa 0.34 MPa

j)

CAUTION The dryer settings must not be changed without good reason and the manufacturers instructions must be consulted before making any change. Defective operation of the dryers can cause moisture to enter the control system and that can damage components and result in defective control of equipment.

Controls
No.1 and No.2 air compressors start and stop in response to pressure changes in the control air receiver. The compressors are operated in a Lead and Follow mode. The operating pressures are as follows : 1) 2) The Lead compressor starts at a falling pressure of 0.7MPa and stops at a rising pressure of 0.9MPa. The Follow compressor starts at a falling pressure of 0.5MPa and stops at a rising pressure of 0.9MPa.

A Lead / Follow changeover can be made on the ICAS. No.3 air compressor starts at a falling pressure of 0.7MPa and stops at rising pressure of 0.9MPa in the service air receiver. When the air receiver pressure has risen to set pressure, the compressors are stopped after unload running (10 min.).

3.3.1a

Compressed Air System

STERN TUBE FW TK

FOR AFT MOORING DK


042VPE

40

40
040VPE

FOR ACCOMM. FOR DK USE (P)


037VPE

FOR AFT BALLAST TK BUBBLING (P) FOR AFT BALLAST TK BUBBLING (S)
045VPE

25

50

25 50

50
036VPE

FOR DK USE (S)

25

25

NO.3 AIR COMPRESSOR


PM 752 ESD 671 ESD 671 PAL 752

FOR COPMPR START/STOP PS P

033VPE

TS

P
003VPE

PS

G.S. AIR RECEIVER


50 50
006VPE 041VPE

032VPE

50
030VPE

50

50
027VPE

50

FOR E/R FOR E/R FOR N2 GENERATOR

ASS 671

SA 671

RO 671

RM 671

XA 671 TROUBLE

50
028VPE

50

016VPE

NO.2 AIR COMPRESSOR

50

50

002ZPE

017VPE

PS P

PS P
XA 904

NO.2 CONT.AIR DRYER

P
PM 905 PAL 905

ESD 671

TS

ESD 671

P
002VPE

008VPE NOR.CLOSE

TO BILGE WELL

020VPE NOR.CLOSE 023VPE

TROUBLE

PS

50

50

50

ASS 671

SA 671

RO 671

RM 671

XA 671 TROUBLE

15

025VPE

50

25

026VPE

007VPE

FOR CARGO MACH. RM

NO.1 AIR COMPRESSOR


PM 751 PAL 751

FOR COPMPR START/STOP PS PS


50

PS P

PS P
XA 904 TROUBLE

15

AIR PRESSURIZED LIGHTING SYSTEM

NO.1 CONT.AIR DRYER

ESD 671

TS

ESD 671

P
001VPE

PS

50

50
005VPE

021VPE LOCKED OPEN

50

50

022VPE

ASS 671

SA 671

RO 671

RM 671

XA 671 TROUBLE

011VPE

CONT.AIR RECEIVER
COOL. W. INLET

ESD 671

P COMPRESSED AIR OUTLET

PS

FS

AIR COOLER

001ZPE

012VPE
COOL. W. OUTLET OIL COOLER

100A TO BILGE WELL

40

AIR INLET

TO BILGE WELL

DPS

SUCTION FILTER
SERVO CYLINDER UNLOADER VALVE

PS

COMPRESSOR OIL SEPARATOR TS T

3.3.2

Starting Air System


Procedures for Preparing the Starting Air System Operation a) b) c) Ensure that all pressure gauge and instrumentation valves are open and that gauges and instruments are reading correctly. Check the oil level in the compressors. Set up valves as in the following table : Valve
408VPE 448VPE 405 / 406VPE 445 / 446VPE 414 / 415VPE 454 / 455VPE 425VPE 423 / 424VPE 432 / 433VPE

D/G Starting Air Compressor Maker : No. of sets : Type : Capacity : Rating : Tanabe Pneumatic Machinery Co.,Ltd 2 sets Reciprocating, air cooled 20m3/h at a pressure of 2.45 MPa 440V, 5.5kW, 1,800 rpm

Operation of Emergency Air Compressor The emergency starting air reservoir is normally maintained at full pressure to allow for emergency starting of the emergency generator engine as required. The emergency compressor is driven by a diesel engine which is hand started. The emergency compressor diesel oil tank level must be checked and replenished as necessary. Normally the emergency starting air receiver is charged from the D/G starting air system but the emergency compressor should be operated regularly to ensure that it is in operational condition. a) b) c) Check the emergency compressor diesel engine and ensure that the fuel oil and lubricating oil levels are correct. Open the compressor discharge line valve and the emergency air receiver filling valves. Start the emergency compressor diesel engine and when running correctly load up the emergency compressor and supply compressed air to the emergency starting air reservoir. Drain water from the emergency starting air reservoir by means of the manual drain valve 424VPE or the automatic drain valve 425VPE. Fill the emergency starting air receiver to the desired pressure and stop the diesel engine driven compressor when the desired pressure is achieved.

E/G Starting Air Compressor Maker : No. of sets : Type : Capacity : Sanwa Iron Works, Co.,Ltd. 1 set Diesel driven, reciprocating, air cooled 5m3/h at a pressure of 2.45 MPa

Position Description Open D/G starting air receiver automatic drain valve Open D/G starting air receiver manual drain valves Open Open Open Open D/G engine inlet drain valves E/G starting air receiver automatic drain valve E/G starting air receiver manual drain valves E/G engine inlet drain valves

D/G Starting Air Receiver Maker : No. of sets : Capacity : Safety valve : Henmi Iron Works Co., Ltd. 2 sets 0.5 m3 2.7 Mpa

Following valves will be opened after completion of drainage. Open D/G starting air compressor discharge valve D/G starting air receiver filling valve D/G starting air receiver outlet valve (Locked) D/G starting air supply valve (Locked) E/G starting air receiver supply valve E/G starting air receiver outlet valve (Locked) E/G starting air supply valve (Locked)
401VPE 441VPE 402VPE 442VPE 410VPE 450VPE 411VPE 451VPE 412VPE 430VPE 431VPE

E/G Starting Air Receiver Maker : No. of sets : Capacity : Safety valve : Henmi Iron Works Co., Ltd. 1 set 0.2 m3 2.7 MPa

Open Open Open Open Open Open )

d)

Each diesel generator engine starting air system is supplied by a dedicated starting air compressor which provides air to the dedicated starting air receiver. The compressed air is used to start the diesel generator engine. It is also supplied to the emergency diesel generator starting air receiver which is located in the emergency generator engine room. Each compressor discharge is cross connected with a stop valve. The compressor supplies air to the starting air receiver and it is provided with an automatic start and stop facility which is activated by the pressure in the starting air receiver. Normally the starting air receiver is open to allow for immediate starting of the diesel generator engine when it is set to standby duty. The starting air receiver also supplies control air to the diesel generator engine. The emergency diesel driven starting air compressor may also be used to replenish the diesel generator starting air receiver in an emergency. The compressors are each fitted with a safety valve, one after the first stage compression and the other after the second stage compression. A pressure switch connected to the automatic control system stops the compressor should the LO pressure fall below a predetermined value.

Controls
The D/G starting air compressor will start and stop automatically in response to pressure changes in air receiver. Start : 2.0 MPa Stop : 2.45 MPa

At the compressor control panel, select LOCAL operation and start the compressor. Check that the compressor operates correctly.

Alarms Sensor PT PS PT Tag No. 753 754 295 Function D/G starting air receiver E/G starting air receiver D/G starting air inlet Set point PAL PAL PAL 1.7 MPa 1.7 MPa 1.47 MPa

3.3.2a

Starting Air System

PAL 754

EMERG.GEN. START.AIR RESERV.


430VPE

EMERGENCY GENE. ROOM


S
AIR MOTOR
START.SOLENOID V.

25

25
432VPE 433VPE

431VPE

421VPE 422VPE 423VPE 425VPE

EMERG.DIESEL GENERATOR ENGINE


PINION RELAY V.

PRESS. REG. V. AIR INLET

25

412VPE

RING GEAR

25
424VPE
EXHAUST

D/G STARTING AIR MOTOR

EMERG.GEN. START.AIR COMP.

25

AUX. DIESEL GEN.ENGINE


PM 295 PAL 295

NO.2
25
454VPE 455VPE 451VPE

MAIN START.V.

AUX. DIESEL GEN.ENGINE


PM 753 PAL 753

D/G START.AIR RECEIVER


P
LOCKED OPEN 450VPE COMP. START/STOP 673 PS

COMP. START/STOP 673

PM 753 PAL 753

D/G START.AIR RECEIVER


P
LOCKED OPEN 410VPE

PM 295

PAL 295

PS

NO.1
25 25
401VPE

25 25
441VPE

25
414VPE 415VPE

411VPE

NO.2

442VPE

NO.1

402VPE

MAIN START.V.

(15A) 445VPE 448VPE

S
405VPE

(15A)

NO.2
D/G START.AIR COMP.
ASS
673 673

408VPE

NO.1
D/G START.AIR COMP.
ASS
673 673

446VPE

406VPE

SA

673

RM

673

RO

SA

673

RM

673

RO

3.4.1

Central Fresh Water Cooling System


Procedures for the Fresh Water Central Cooling System Operation The system supplies cooling water to the following : Main Engine LO coolers Stern tube LO cooler Drain cooler Turbo generator air coolers and LO coolers Main feed water pump LO coolers Air compressors Inert gas generator oil cooler and water cooled condenser Air conditioning plant Provision refrigerating plant Unit coolers Gas compressor LO coolers Gas heater drain cooler The circulating fresh water is chemically treated in order to minimize the risk of corrosion and bacterial infestation in the system. Chemical treatment is added into the chemical dosing tank and injected to the suction main of the cooling fresh water pumps. The regular tests should be carried out as follows to determine level of contamination and level of chemical treatment necessary : Nitrites Chlorides pH P- alkalinity (Note : The above information is given for general guidance only. Reference must be made to the specific instructions from the chemical supplier regarding final data for chemical treatment of the system.) Two identical cooling fresh water pumps are provided for boosting the fresh water pressure to cargo machinery room services. One pump is normally selected as the duty pump and the other pump selected as the standby pump to start automatically should the duty pump fail to maintain the correct water supply pressure. Pumps may be started and stopped locally but are normally set to remote operation for control via the ICAS. The duty pump is started manually at the ICAS mimic diagram for the central cooling system and the other pump is selected for automatic operation to act as the standby pump. Similarly, fresh water for unit coolers in the wheelhouse and the central control room is boosted from the central cooling system by one cooling fresh water boosting pump which is operated at the ICAS mimic diagram for the central cooling system. A fresh water heater supplies hot water to the stern tube L.O. cooler in frigid climate condition. (See 3.1.5 "1.0Mpa Desuperheated Steam
System")

Central Cooling Fresh Water Pumps Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 2 sets Centrifugal, vertical 600m3/h at 22m total head 440V, 55kW, 1,800 rpm

a) Ensure that the fresh water central cooling system is fully charged with chemically treated fresh water and that air is vented from all parts of the system. b) Ensure that the central cooling system expansion tank is at the normal operating level. c) Ensure that the sea water central cooling system is in operation.
(See 3.5.2 "Cooling Sea Water Service System")

Cooling Sea Water Pumps Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 2 sets Centrifugal, vertical 650m3/h at 20m total head 440V, 55kW, 1,800 rpm

d) Open all instrumentation root valves and ensure that the instruments are all working correctly. e) Set the valves as in the following table : Position Open Open Open Open Open Operational Description Either central fresh water cooler inlet valve Either central fresh water cooler outlet valve Expansion tank root valve Both cooling fresh water pumps suction valves Both cooling fresh water pumps discharge valves Three-way temperature controlled valve Valve
005 / 006VPG 007 / 008VPG 095VPG 001 / 002VPG 003 / 004VPG 010VPG

Central Cooling Fresh Water Coolers Maker : No. of sets : Type : Cooling water flow : Fresh water temp. : Hisaka Works Ltd. 2 sets Sea water circulated plate 600 m3/h 37

Central Cooling Fresh Water Expansion Tank Capacity : 1.0 m


3

f) Select one central fresh water cooling pump as the duty pump and start that pump manually and select the other pump as the standby pump. g) Open fresh water cooling inlets and outlets of services, vent as necessary. h) Check that water is circulating to all services and check the system for leaks as the temperature rises when the services are on line.

Fresh water is circulated through the central cooling system by two fresh water circulating pumps. One pump is normally selected as the duty pump and the other pump selected as the standby pump to start automatically should the duty pump fail to maintain the correct water supply pressure. Pumps may be started and stopped locally but are normally set to remote operation for control via the ICAS. The duty pump is started manually at the ICAS mimic diagram for the central cooling system and the other pump is selected for automatic operation to act as the standby pump. Each cooler has sufficient capacity under all plant conditions to cool the fresh water to the designed operating temperature of 37 with sea water at a temperature of 32. The duty central fresh water cooling pump supplies water to the central cooling main from where it is distributed to the various services. Return lines from the various services flow to the return main which returns the water to the pump suction. A three-way air cylinder actuating mixing valve is located at the central fresh water coolers outlet main. The ICAS controls the three-way valve and enables a set temperature of 37 C to be maintained in the central cooling water supply system. Manual valve 009VPG at the fresh water cooling pump discharge main is normally left in the closed position except during the inert gas generator operation.

Controls
1) The central cooling fresh water pump will be automatic changed over by pump discharge low pressure (300kPa). 2) The cargo machinery cooling fresh water pump will be automatic changed over by pump discharge low pressure (340kPa). 3) The cooling fresh water temperature control valve 010VPG maintain the cooling fresh water temperature (37).

Alarms Sensor TR FS TR Tag No. 865 741 239 Function CCS FW cooler outlet CCS FW expansion tank (from tank bottom) T/G gene. air cooler outlet Set point TA H 42

LAL +500 mm TA H 44

3.4.1a

Central Fresh Water Cooling System


TO CARGO MACHINERY RM
NO.2 MCR
099VPG

TO W/H & CCR UNIT CLR


UNIT CLR

40 40

100 80 125

FROM W/H & CCR UNIT CLR FROM CARGO MACH. RM

CCS F.W.EXP.TK
NOTE; (3) TO CLEAN DRAIN TK
100 NO.2 SWBD RM

098VPG

088VPG

40 40

50 125 50

FROM PROV.REF.& AIR COND.UNIT


80

FS

LAL 741

W/H & CCR UNIT CLR C.F.W. BOOST.PUMP


P P
100

UNIT CLR
087VPG

078VPG

TO PROV.REF.& AIR COND.UNIT P


80
028VPG

624

LABORATORY UNIT CLR

PS P
CHANGE OVER 030VPG

090VPG

40 40

PS

25

10

095VPG

072VPG RO 626 RM 626 SA 626

071VPG

(3)

150 40
062VPG

089VPG

ELEC. W/S

038VPG

40 40 80

125

NO.2

80

80

125 125 50 50

068VPG

25 200 25 25 25 40

UNIT CLR
037VPG

P
80
027VPG

P
029VPG

IGG W.COOLED CONDENSER


80

061VPG

NO.2 FD W.P. LO CLR


T

066VPG

064VPG

067VPG

NO.1 MCR UNIT CLR

NO.1 CARGO MACH.COOL. F.W.BOOST PUMP


AC 624 RO 624 RM 624 SA 624

80

036VPG

40 40 125 125 150

IGG LO CLR

063VPG

NO.1 FD W.P. LO CLR NO.3 AIR COMP.


40 150
086VPG

065VPG

035VPG

40

NO.1 SWBD RM UNIT CLR

034VPG

40 40

NO.2 MAIN TURBO GENE. GENE. AIR CLR


TM 239 TAH 239

NO.2 AIR COMP.


40
085VPG

083VPG

L.O.CLR

40 ENG. W/S 50 UNIT CLR

033VPG

50

NO.1 AIR COMP.


40
084VPG

082VPG

032VPG

40 40
047VPG 048VPG

011VPG

25

50

S
865

40

50 200

65

012VPG

010VPG

80

CHEMICAL DOSING TK

A T

081VPG

031VPG 046VPG

TIC 865

65

T
65 65

250 40 40

200
052VPG

150

100

250

CHANGE OVER

40

25

TM 865

TAH 865

C
250
002VPG

P
004VPG

PS PS
250

623

051VPG

DRAIN CLR

NO.1 MAIN TURBO GENE. GENE. AIR CLR


80
TM 239

250

250

250

250

25

NO.2

L.O.CLR
TAH 239

100 25 25
054VPG

005VPG 003VPG

007VPG

006VPG

008VPG

250

001VPG

CCS COOL.F.W.PUMP
AC 623 RO 623 RM 623 SA 623

009VPG

NO.1 CCS F.W.CLR

NO.2 CCS F.W.CLR

053VPG

S/T LO CLR
041VPG

65

NO.1

250

TIC 87A 055VPG

100

STM

042VPG

043VPG

65

S/T LO F.W.HTR
40

T
65 65

250

150

200

200

100

100

3.5.1

Sea Water Circulating System


Two sea chests are provided for the sea water circulating systemone is for low suction, the other is for high suction located on starboard and port sides in engine room respectively. Each sea chest is connected by means of the crossover sea bay which is situated below the double bottom constructed with ship structure. All sea chests are provided with slush ice protection, air vent connection and steam blowing connection. The sea water circulating pumps take suction from the sea bay. Hydraulically operated system valve fitted at each sea chest suction is normally operated remotely from the ICAS mimic display. Normally at sea, the low sea chest will be used for the main sea water circulating pump. However, when operating in shallow waters, the high sea chest will be used in order to prevent the ingress of sand and mud with the sea water. Procedures for Main Circulating System Operation a) Sea chest and sea bay vent valves should normally be left open in order to ensure that the sea chest and sea bay are always completely filled with water. b) The starting and stopping of pumps and the operation of hydraulically actuated valves takes place from the ICAS screen. c) Ensure that all instrumentation root valves are open and that all instruments are operating correctly. d) Ensure that following valves are closed. All drain valves Saw dust injection valve 017VPH Hypochlorite injection valves 043 , 046, 047 VPH Auxiliary condenser vent valves Auxiliary condenser outlet overboard valve 012VPH Auxiliary circulating valves 009 / 011VPH Main condenser back flushing valve 015/020VPH e) Set the valves as in the following table : Position Open Open Open Open Open Description Sea chest suction valve Main condenser outlet overboard valve Main circulating pump suction valve Auxiliary circulating pump suction valve Main condenser water box vent valves Valve
003 or 004VPH 002VPH 005VPH 006VPH

Main Sea Water Circulating Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 1 set Centrifugal, vertical 5,000 / 2,600m3/h at 3 /6 m total head 440V, 80kW, 360 rpm g) Confirm that the scoop system is being AVAILABLE and the control mode is being MANUAL on the ICAS screen. h) Click PUMP mode on the ICAS screen and confirm the start of main circulating pump and the open of discharge valve 007VPH. i) When the system is being circulated by water from the main circulation pump, select AUTO mode. AUTO mode may be selected at any time as the transfer to SCOOP mode will commence provided the conditions are fulfilled. j) The hypochlorite injection valves 043, 045VPH are changed over automatically according to the mode of system and condition of the sea chest. (Note : If required, the auxiliary circulating pump may be used for the main circulating system. The procedure is the same as for operating the main circulating pump.)

Auxiliary Sea Water Circulating Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd.. 1 set Centrifugal, vertical 5,000 / 2,600m3/h at 3 /6 m total head 440V, 80kW, 360 rpm

The seawater circulating system of the main condenser and LO coolers is comprised of an inlet scoop, one main circulating pump, one auxiliary circulating pump, overboard outlet and associated valves and pipework. At sea, under normal operating conditions, sufficient circulating water is supplied by the scoop system without the main circulating pump. The main circulating pump is brought into service when the ship is moving at reduced speeds, astern or during harbor maneuvering. The auxiliary circulating system provides for the auxiliary condenser and circulating sea water is supplied by the auxiliary or main circulating pump. Each circulating pump can supply circulating water to the main condenser or auxiliary condenser and the main LO cooler as required. The chlorinator generates hypochlorite by electrolysis of seawater. Sea water led to the unit from the cooling sea water pump is electrolyzed as it passes between anodes and cathodes in the unit. The hypochlorite is injected to the following points to prevent the adhesion and growth of marine organisms. 1) Sea chests, high and low for general service 2) Scoop inlet A sawdust injection box is connected to the main condenser inlet piping. Sawdust from the box can be injected into the sea water side of the condenser using sea water from the cooling sea water pump as the motive power. This action is performed only in an emergency when condenser tube leakage is suspected in order to prevent contamination by sea water. In order to operate the system the sawdust injector inlet valve 051VPH and outlet valve 017VPH are closed and the injector box is filled with sawdust.

Procedures for Auxiliary Circulating System Operation The auxiliary sea water circulating pump is used to supply the auxiliary condenser when the main sea water circulation system is not operating. There is a cross connection from the main circulating pump, via valve 009VPH, should the auxiliary circulating pump not be available. a) Ensure that all instrumentation root valves are open and that all instruments are operating correctly. b) Ensure that following valves are closed. All drain valves Auxiliary condenser vent valves Auxiliary circulating valves 009 / 011VPH Main condenser back flushing valve 015/020VPH Main circulating valves 007 / 008VPH c) Set the valves as in the following table. It is assumed that the auxiliary system is being started with the auxiliary sea water circulating pump operating. Position Open Open Open Description Sea chest suction valve Auxiliary condenser outlet overboard valve Auxiliary circulating pump suction valve Valve
003 or 004VPH 012VPH 006VPH

d) Start the auxiliary circulating pump. e) As the pump runs up to speed open the discharge in line valve 011VPH and control the pressure to the desired value. f) Open vent valves on auxiliary condenser water box to purge any entrapped air. After confirmed water from vent lines, close them.

f) Select REMOTE control for the scoop inlet valve 001VPH and the main circulating pump discharge valve 007VPH on the ICAS screen.

3.5.1

Sea Water Circulating System


Controls Scoop System
Scoop system is available in following conditions. 1) 2) 3) 4) 5) 6) 7) Sea chest valve 003 or 004VPH is "Open". Main condenser outlet overboard valve 002VPH is "Open". Scoop inlet valve 001VPH control is "REMOTE". Selected circulating pump (main or auxiliary) is "REMOTE". Selected pump discharge valve 007 or 008VPH is "REMOTE". Hot water return valve 015VPH is "Open". Hot water return valve 076 or 077VPH is "Open". Scoop / Pump Changeover When scoop system control mode is in AUTO, automatic changeover is performed by following conditions. Pump to Scoop (at all conditions are established) 1) Shaft revolution : above 52rpm + 10min. Timer 2) Main condenser vacuum : above -80kPa 3) Plant mode : Normal 4) Condenser inlet SW temp. : above Scoop to Pump (at one condition is established) 1) Shaft revolution : below 50rpm 2) Main condenser vacuum : below -80kPa 3) Plant mode : Maneuvering 4) Condenser inlet SW temp. : below Circulation to Re-circulation (at all conditions are established) 1) Sea mode : Cold sea 2) Main condenser vacuum : below -80kPa 3) Condenser inlet SW temp. : below 4) Condenser outlet SW temp. : below Re-circulation to Circulation (at all conditions are established) 1) Sea mode : Normal 2) Main condenser vacuum : above -80kPa 3) Condenser inlet SW temp. : above 4) Condenser outlet SW temp. : above The remote - manual changeover can also be performed by selecting SCOOP or PUMP at the ICAS screen as required. The electric motorized valve 007 / 008VPH fitted on the discharge of each circulating pump is sequentially operated with the operation of respective pump. Chlorinator The High / Low changeover of output electric current is performed by sea water flow of chlorinator inlet. Chlorine injection valve The chlorine injection valves are automatically changed over as follows. 1) Scoop injection valve 043VPH The valve is operated by the main condenser sea water circulating mode changeover sequence. The valve is opened at "SCOOP" mode. Pump mode valve 045VPH The valve is operated by the main condenser sea water circulating mode changeover sequence. The valve is opened at "PUMP" mode. Sea chest injection valves 046 / 047VPH The valves are switched manually at local depending upon the selected sea chest suction valve 003 / 004VPH. Marine Growth Preventing System The scoop overboard valve 002VPH and hot water re-circulating valve 020VPH are sequentially operated with the operation of respective mode. The hot water re-circulating valve 020VPH controls main condenser outlet sea water temperature where Re-circulation operation is activated.

Back Flushing of Main Condenser The cooling tubes of main condenser can be back flushed by utilizing hot cooling sea water out of auxiliary condenser. The cooling water passed through the auxiliary condenser is supplied into outlet water chamber of main condenser and discharged from the inlet scoop passing through the cooling tubes and the inlet water chamber of main condenser. The back flushing is carried out as follows: It is assumed that the auxiliary system is being circulated with the auxiliary sea water circulating pump operating. a) The main condenser should be changed over to auxiliary condenser when the plant is in live condition. (See 3.2.1 "Condensate Water
System ")

b) Ensure that following valves are closed Scoop outlet valve 002VPH Both main and auxiliary circulating pumps discharge valves 007 and
008 VPH

Main LO cooler inlet valves 071 and 072VPH Main condenser back flushing valve 015/020VPH Either overboard valve 076VPH or 077VPH on sea chest Either suction valve 003VPH or 004VPH on sea chest (Note : One of the overboard valves, 076VPH or 077VPH is being opened for operation of auxiliary condenser before back flushing. When the low suction is in use, 077VPH on high sea chest is opened, on the contrary, when the high suction is in use, 076VPH on low sea chest, unless no frigid climate condition.) c) Set the valves as in the following table Open Scoop suction valve 001VPH Open Main condenser back flushing valve 015/020VPH 076/ 077VPH Close Both overboard valve on sea chest The back flushing is now executed with the auxiliary circulating system. For Frigid Climate Condition Where the sea water temperature is extremely low, the main condenser is cooled by one circulating pump even when navigating operation of the vessel for preventing the under-cooling of condensate in the main condenser. The cooling water is re-circulated between sea suction and main condenser to rise the suction sea water temperature when the further severe condition. In this case (Re-circulation mode), the cooling sea water after main condenser is returned into either suction sea chest being used for rising the suction sea water temperature. For the severest case, minus 2 of sea water temperature is considered and the system can maintain the main condenser vacuum 730 to 735mmHg.

2)

3)

Alarms Sensor TR Tag No. 849 Function Main condenser outlet temperature Chlorinator trouble DC over current Thyristor SR high temp Cool. Fan trouble AC over current Set point TA H 45

863

3.5.1a

Sea Water Circulating System

SEA CHEST (HIGH)

004VPH
AOS 852 RO 852 OIS 852 OIO 852

002VPH
AOS 855 RO 855 OI 855

RO 857

OIS 857

OIO 857

077VPH
OIS 859 OIO 859

047VPH

015VPH

082VPH

XA 859

1350

80

020VPH

TAH 849

TM 849

65

100
014VPH

100

TO FIRE & BILGE PUMP

550

AUX. CONDR

550
012VPH

MAIN CONDR
80 (80A) 700
AOS 854 RO 854 OIO 854

65

TO CLEAN DRAIN TK
854

006VPH

TM 848

P
011VPH

1100

700

008VPH M

SEA BAY

700

700

017VPH

AOS 851

RO 851

OIO 851

OIS 851

AUX. CIRC. PUMP


ASS RM
632

1100 40
001VPH
AOS 853 RO 853 OIO 853 OIS 853 OIO 861

SCOOP
005VPH
OIS 861 RO 861 AOS 861

550

632

632

RO

632

SA

632

XA

700
043VPH 009VPH

P
700

400

700

M 007VPH

80

100

SAW DUST INJECTION BOX

850

400

072VPH

MAIN CIRC. PUMP


ASS
631

NO.2 MAIN L.O. CLR


T T

074VPH

400

400

075VPH

RM
631

631

RO

631

SA

631

XA

850

550
XA 858 OIS 858 OIO 858

550

400
051VPH

071VPH

NO.1 MAIN L.O. CLR


80

073VPH

400

863

XA

081VPH

CHLORINATOR
042VPH

TROUBLE

FS

AOS
862

862

RO

OIS
862

OIO
862

RO 856
045VPH

OIS 856

OIO 856

550

80
046VPH

041VPH

044VPH

003VPH

076VPH

COOL. S.W. LINE 40

80
050VPH

FS FS
50

80

FS
052VPH

100

50
048VPH

SEA CHEST (LOW)

3.5.2 Cooling Sea Water Service System


Cooling Sea Water Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd.. 2 sets Centrifugal, vertical 650m3/h at 20m total head 440V, 55kW, 1,800 rpm Procedures for Cooling Sea Water System Operation Pumps may be set for local operation or remote operation via the ICAS display. In remote operation pumps may be started and stopped manually and one pump may be selected for automatic operation to act as the standby pump and start should the duty pump fail to maintain the correct sea water pressure. a) Ensure that the sea bay is flooded as described in Section 3.5.1 Sea Water Circulating System above. b) Ensure that all instrumentation root valves are open and that all instruments are operating correctly. c) Ensure that all drain and vent valves are closed. d) Set the valves as in the following table : Position Open Open Open Open Open Open Open Open Description Both cooling sea water pumps suction valves Both cooling sea water pumps discharge valves Overboard discharge valve Either one central cooler sea water inlet valve Either one central cooler sea water outlet valve Both vacuum pump coolers inlet valves Both vacuum pump coolers outlet valves Chlorinator inlet valve Valve
021/ 022VPH 024/ 026VPH 070VPH 027 or 028VPH 029 or 030VPH 036/ 037VPH 038/ 039VPH 041VPH

Procedures for Distilling Plants Sea Water System Operation The distilling plants are operated as described in section 6.2 Distilling Plant. The description which follows applies only to the setting and operating of the distilling plant sea water systems. a) Ensure that all instrumentation root valves are open and that all instruments are operating correctly. b) Ensure that all drain and vent valves are closed. c) Set the valves as in the following table : Position Open Open Open Open Open Open Description Both cooling sea water pumps suction valves Both cooling sea water pumps discharge valves Isolating valve in crossover line Distilling plant inlet valves Distilling plant outlet valves Overboard discharge valve Valve
061 / 062VPH 063 / 065VPH 067VPH 064 / 066VPH 068 / 069VPH 070VPH

Distilling Plant Cooling Sea Water Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd.. 2 sets Centrifugal, vertical 105m3/h at 50m total head 440V, 30kW, 1,800 rpm

The cooling sea water system comprises two independent cooling systems, one for the central cooling, and the other for the distilling plant cooling. The central cooling system also supplies water to the sawdust injector which is used for injecting sawdust into the main condenser, the main condenser vacuum pump coolers and the chlorinator. The central cooling system is provided with two 100% duty identical cooling water pumps, one acting as the duty pump and the other acting as the standby pump. The pumps take suction from the sea bay. (See: 3.5.1 Sea Water
Circulating System)

d) Start the pump associated to the distilling plant which will be set in service, i.e. No.1 pump for No.1 distilling plant, No.2 pump for No.2 plant. The starter for each pump is incorporated in the local control panel for each distilling plant.

e) Open vent valves on the suction strainers to purge any entrapped air. After confirmed water from vent lines, close them. f) Ensure that the pumps have been primed and start one of pumps and select the other pump for automatic standby. g) Supply chlorine to selected sea chest.

Controls
The cooling sea water pump will be automatic changed over by low pump discharge pressure (120kPa). Alarms Sensor Tag No. 863 Function Chlorinator trouble DC over current Thyristor SR high temp Cool. Fan trouble AC over current Set point

No.2 cooling sea water pump is equipped with a vacuum pump for priming which enables emergency bilge suction in the engine room. The two distilling plant cooling pumps take suction also from the sea bay. These pumps provide sea water feed to the distilling plant for evaporation, cooling water for condensing the vapour and driving water for operating the brine / air ejectors which remove brine from the evaporator shell. Although each distilling plant has its own dedicated pump, these pumps are cross connected by means of valve 067VPH which allows No.1 pump to supply No.1 distilling plant or No.2 pump to supply No.2 distilling plant. The discharge from the eductors is discharged overboard via common valve 070VPH with the central cooling system.

3.5.2a Cooling Sea Water Service System


ABOVE UPP.DK

40

084VPH

SEA CHEST (HIGH)

094VPH

NO.1 DIST. PLANT


T
128VPF

NO.2 DIST. PLANT


125

T
FROM COND.W.

066VPH

125

V
125
129VPF

T P
125
065VPH

634

SA

634

RM

634

RO

65

004VPH
OIO 857 OIS 857 RO 857

077VPH
OIO 859

047VPH

DIST. PLANT COOL.S.W.PUMP


C
062VPH

082VPH

OIS 859 XA 859

FI

FI
067VPH 064VPH 063VPH 083VPH

P
125

C
061VPH

NO.1

125

150 550 550 80 700 700 40

068VPH

069VPH

125

125

FROM MAIN CONDR FROM AUX. CONDR TO AUX. CIRC. PUMP TO MAIN CIRC. PUMP 250 TO E/R BILGE PUMP 250
092VPH

633

SA

633

RM

633

RO

633

AC

150

25
115VPH

FROM FIRE LINE PRESSURISING PUMP

MAIN COOL.S.W.PUMP
P C
022VPH

039VPH

65

037VPH

CLR

65

350

026VPH

025VPH

NO.2

NO.2 VAC. PUMP UNIT


CHANGE OVER TM 848

SEA BAY
PS PS 633
024VPH

P
250
023VPH

C
021VPH

EMERG. BILGE SUC. 250 250

ABOVE UPP.DK

038VPH

65

036VPH

T
250

CLR

65

80

NO.1

300

250

250

070VPH

NO.1 VAC. PUMP UNIT

150

80
078VPH

TO SCOOP
XA

65

80

863 862 862 862 862

250

250

850

250

250

40

034VPH 030VPH

033VPH 028VPH 029VPH

032VPH

031VPH 027VPH 041VPH

042VPH

044VPH

045VPH

XA 858

80

80
050VPH

FS FS
50
071VPH

RO 856 OIS 856 OIO 856

081VPH

OIS 858 OIO 858

DP

DP

T
TO SAW DUST INJECT. BOX 40

80

FS
052VPH

100

50
048VPH

80
046VPH 093VPH

CHLORINATOR

TROUBLE

100

FS

AOS

RO

OIS

OIO

850

NO.2

125

003VPH

076VPH

NO.2 CCS F.W. CLR

NO.1 CCS F.W. CLR

SEA CHEST (LOW)

3.6.1 Fuel Oil Bunkering System


Heavy fuel oil for the boilers is stored in two HFO side tanks located at the engine room, a HFO fore deep tank located forward of the cargo tanks and a low sulphur fuel oil tank also located at the engine room. These bunker tanks are filled from any of the four bunker manifolds. High level alarms are provided and will automatically close the filling valve to the respective tank. Two diesel oil storage tanks and an inert gas generator gas oil tank are located at the engine room. These tanks are filled from any of the four bunker manifolds. All valves in the diesel oil and gas oil bunkering system are manually operated. The heavy fuel oil and low sulphur oil are bunkered using the same 300mm filling line. The line is led through the starboard side under deck passageway and branched to the HFO side tanks which are arranged at port and starboard sides and the low sulphur fuel oil tank which is arranged at starboard side. The diesel oil and gas oil are bunkered using the same 100mm filling line. The line is led through the port side under deck passageway and branched to each diesel oil storage tank and the inert gas generator gas oil tank in engine room. c) Sampling connections are provided at each HFO manifold. Bosses for pressure gauges and air purge connections are fitted to all manifold branches. Over pressurization of bunkering fuel oil is prevented by relief valves set at 0.5MPa, excessive pressure is relieved to a FO overflow tank. Following fixed and portable reducers are provided for the manifold ends. HFO and Low sulphur fuel oil Fixed Piece Portable JIS 5 K - 300ANSI 150 psi - 8" ANSI 150 psi - 8"DIN 10 bar - 6" ANSI 150 psi - 8"DIN 10 bar - 8" 4 pcs 2 pcs 2 pcs f) JIS 5 K - 100ANSI 150 psi - 4" 4 pcs g) e) d) Precautions Prior to and During the Loading of Bunkers The following is only a guide and company procedures should be followed. Before and during bunkering, the following steps should be complied with : a) A pre-bunker conference should be held with all personnel involved with bunkering being present. A bunker plan should be drawn up and all personnel involved in bunkering must be fully aware of the contents of the plan and understand the entire operational procedure. The contents of the plan will include but not be limited to, tanks to be bunkered, start and stop ullages / dips, names of personnel involved and duties assigned. The time that the pre-bunker conference took place should be entered into the vessels log book. All personnel involved should know exactly what role they are to play and what their duties are. Personnel involved should know the location of all valves and gauges and be able to operate the valves both locally and remotely if required. Company rules regarding the taking of bunkers and transferring of fuel oil within the vessel must be understood by all involved in the fuel oil bunkering and transfer procedure. Samples are to be taken using a recognized sampling device that will give a representative sample of the fuel oil bunkered. The sample should be taken at the bunker manifold and on board fuel tests carried out as soon as possible after bunkering. A second sample should be sealed and sent ashore for analysis. As far as possible new bunkers should be segregated from existing bunkers on board. If bunkers being received are to be loaded into the same tanks as existing bunkers on board, great care must be taken to avoid problems of incompatibility. If there is any doubt about the compatibility between the new bunkers and the existing bunkers, the new bunkers should not be loaded on top of the existing bunkers. No internal transferring of bunkers should take place during bunker loading operations, unless permission has been obtained from the Chief Engineer. Bunker tanks should not exceed the maximum volume stated in the company policy. High level alarms are set at approx. 95% on all fuel tanks. Any bunker barges attending the vessel are to be safely moored alongside before any part of the bunker loading operation begins. Frequent checks must be made of the mooring arrangements as the bunker barge draught will change during bunkering. Level alarms fitted the bunker tanks should be tested prior to bunker loading operations. j) k) l) m) n) o) The soundness of all pipework should be verified by a visual inspection. The pre-bunkering check list should be completed prior to starting bunker operations. A watch must be kept at the bunker manifold during loading of bunkers with all personnel involved being in radio contact. Scuppers and save-alls, including those around bunker tank vents, should be effectively plugged. Any Oil Spill Response kit provided by the company must be in place and a pressure gauge must be fitted on the boss of the manifold.. The initial loading rate must be agreed with the barge or shore station and bunkering commenced at an agreed signal. Only upon confirmation of there being no leakages and fuel going into only nominated tanks, should the loading rate be increased to the agreed maximum. Before the tank being filled reaches the maximum volume specified by the company, the rate should be reduced by diverting some of the flow to another bunker tank; if the final tank is being filled the pumping rate must be reduced. When topping off the final tank the filling rate must be reduced at the barge or shore station and not by throttling the filling valve.

b)

p)

CAUTION At least one bunker tank filling valve must be fully open at all times during the bunkering operation. All relevant information regarding the bunkering operation is to be entered in the Oil Record Book on completion of loading. The information required to be entered includes date, time, quantity transferred and tanks used.

DO and Gas oil Fixed Piece

h)

i)

3.6.1 Fuel Oil Bunkering System


Procedure for Loading Fuel Bunkers a) Remove the blank fitted at the bunker connection and connect the bunkering hose ensuring the gasket used is not damaged. The sampling kits and the pressure gauge must be prepared and in place before the bunkering operation begins. Ensure the blanks on the other 3 bunker connections are secure, that the valves are closed and that the drain and sampling valves are closed. The drip tray should be empty with the plugs fitted. Open the correct filling valve for the tank to be bunkered. Open the required valve at the selected bunkering connection as per follows : Description Port forward manifold HFO filling valve Port aft manifold HFO filling valve Starboard forward manifold HFO filling valve Starboard aft manifold HFO filling valve Valve
901VPL 902VPL 903VPL 904VPL

m)

As the level in the first bunker tank approaches the amount stated in the bunker plan, open the filling valve to the second tank and slowly close in the filling valve to the tank being topped off. Fill the remaining tanks in the same way. For the final bunker tank the filling rate must be reduced by slowing the pumping operation and this must be signaled to the barge or shore station. When the final tank is full, the barge or shore station must be signaled to stop pumping unless they have already done so. Ensure that the sample containers are sealed and labeled correctly. When bunkering has finished and the lines have been blown through, close all bunker manifold and tank filling valves. Disconnect the bunker hose and replace the blank.

n)

b)

o) p) q) r)

c) d)

(Note : Fuel oil tanks in engine room can be returned to shore using the HFO or DO transfer pump. Discharge to shore is done through isolating valve 214VPL to the 300mm bunkering line.)

Depending on which HFO bunker tank is to be bunkered determines which HFO line isolation valve will need to be closed. If the aft bunker tanks are to be filled then valve FOV3 will need to be closed isolating the forward HFO deep tank. This valve would need to be opened and valve 905VPL closed if the forward HFO deep tank is to be filled. The isolating valve 214VPL must be closed when bunkering, which is opened for discharge the fuel oil in engine room tanks. e) Establish effective communication between the cargo control room, the engine room, the bunker manifold and the bunker barge or shore station; this communication must remain at all times. Agree filling rates, quantity and specification of the fuel to be supplied and agree on a signaling system with the barge or shore connection. If possible, take meter readings on the barge or shore station supply line prior to commencing bunker transfer. Signal to the shore station or barge to commence bunkering at a slow rate. Check the bunker hose connections and pipeline for any leaks. Check the fuel is flowing into the correct tank and not to any other tank. Increase the bunkering rate to the agreed maximum. Ensure bunker sampling has commenced.

Procedure for Loading Diesel Oil and Gas Oil Bunkers The procedures are the same as heavy fuel oil bunkering except following : a) Open the required valve at the selected bunkering connection as per follows : Description Port forward manifold DO filling valve Port aft manifold DO filling valve Starboard forward manifold DO filling valve Starboard aft manifold DO filling valve b) Valve
911VPL 912VPL 913VPL 914VPL

f) g) h) i) j) k) l)

The DO and gas oil storage tanks filling valves have no remote operating facility. These valves are manually operated in the engine room.

(Note : The bunkering line is to be flushed with compressed air after finishing filling for preventing the mixing of different kinds of oil.)

3.6.1a Fuel Oil Viscosity - Temperature Graph

3.6.1a
Temperature

Fuel Oil Viscosity - Temperature Graph

-10 10,000 5,000 2,000 1,000 500

10

20
Bun ker Fue l Oi

30

40

50 10,000

60

70

80

90

100

110

120

130

140

150

160

170 10,000 5,000

5,000 2,000 1,000 500


V iscosity - Temperature Relationships
Typical Marine Fuels

Pumping Viscosity usually about 1,000 centistokes

2,000 1,000 500

Kinematic Viscosity - Centistokes

100

100
Boiler Atomization Viscosity usually between 10 and 25 cetistokes

100

50
Ma rine

50

50

Die

20 15
Ma rin

sel

Oil

20 15

20 15
IF -7 00

10

eG

as

Oil

10
IF IF IF -6 0 -1 -1

IF

-3

10

80

80

00

5 4

5 4
IF -3 0

5 4

-10

10

20

30

40

50

60

70

80

90

100

110

120

130

140

150

160

170

Temperature

Kinematic Viscosity - Centistokes

3.6.1b Fuel Oil Bunkering System


NOTE DETAIL OF F.O./G.O. SHORE CONN.
AIR TEST & PURGE V. (JIS 5K-25) BOSS & PLUG FOR PRESS.GAUGE (PF1/2) F.O. LINE SAMPLING VALVE AIR TEST & PURGE V. (JIS 5K-25) BOSS & PLUG FOR PRESS.GAUGE (PF1/2) D O. LINE SAMPLING VALVE

1. HYDRAULIC OPERATED VALVES FOR F.O.FILLING CAN BE OPERATED FROM CARGO CONTROL ROOM. EACH VALVE HAS LOCAL MANUAL CONTROL DEVICE FOR EMERGENCY BACK UP OPERATION. 2. SHORE CONN. PIECES ARE SUPPLIED AS FOLLOWS ; APPLICATION FUEL OIL ITEM FIXED PIECE PORTABLE REDUCER GAS OIL FIXED PIECE SIZE JIS 5K-300 ANSI 150PSI-8" ANSI 150PSI-8" DIN 10BAR-8" ANSI 150PSI-8" DIN 10BAR-6" JIS 5K-100 ANSI 150PSI-4" (WITH SLOTS) NO. 4 2 2

I.G.G. G.O.TK

D.O.TK

F.O. SIDE TK UNDER DECK PASS. WAY COFF.


R

DETAIL OF MANIFOLD AREA


100 100

FOV6

300

100

SET AT 0.5 MPa

100

300

902VPL

912VPL

911VPL

901VPL

3. PORTABLE REDUCERS ARE STOWED IN THE CO2 BOTTLE ROOM. 4. FUEL OIL TRANSFER PUMP AND SUCTION VALVE CAN BE OPERATED FROM CARGO CONTROL ROOM.

243VPL

136VPL

100

5. PUMP TABLE
TO F.O. OVERFLOW TK

NAME F.O. TRANSF. PUMP

ITEM
3 50 / 4 BAR DEL.

TYPE E.M.V.G.

ENG. ROOM

200

100

PM

100

300

200
R

FOV2

907VPL

FROM E/R F.O. TRANS. PUMP

214VPL

FOR'D F.O.TK

906VPL
F.O. TRANS. PUMP

100
&S)

FOV1

.T (P

137VPL 904VPL 914VPL 913VPL 903VPL

300

100

100
COFF.
FOV5
R

200
FOV4

905VPL

250

250

100

FOV3

300

200

D.O.TK.

LOW SULPHER F.O.TK.

F.O. SIDE TK.

ACC. TRUNK

NO.4 CARGO TANK

FWD

W.B

FWD PUMP ROOM

100

3.6.2 Heavy Fuel Oil Transfer system


Heavy Fuel Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Diesel Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 1 set Gear, horizontal 10m3/h at 0.294MPa 440V, 3.7kW, 1,200 rpm Taiko Kikai Industries, Ltd. 1 set Gear, vertical 50m3/h at 0.294MPa 440V, 18.5kW, 1,200 rpm Overflow from each side settling tank is led to the FO side tank of same side and the overflow from the side tanks is led to the FO overflow tank through an overflow alarm chamber providing a float switch. The FO overflow tank can be pumped out by the HFO transfer pump via suction valve 206VPL and discharged to FO settling tanks or FO side tanks. A stop valve 207VPL and a spectacle blank are provided at the FO overflow tank suction pipe being the lowest point of the FO transfer pipelines for draining to the FO drain tank in the event that removal of pipe works is required. All fuel tanks are fitted with a quick closing pneumatic outlet valve operated from the fire control station. The valves must be reset locally after being tripped. Each tank is also fitted with a self-closing test cock to test for the presence of water and to drain any water present. The self-closing cock drains are collected into the separated bilge oil tank and pumped to the waste oil settling tanks by the waste oil transfer pump to burn in the incinerator. Save-all from each fuel oil system is collected into the FO drain tank and pumped to the FO settling tanks or waste oil settling tanks by the waste oil transfer pump. The waste oil transfer pump can be automatically stopped depending on the high level of waste oil settling tank being filled. Control selector switch for the automatic stop detector is provided on the ICAS. It is important to ensure the valves are closed on all the other tanks not being filled, especially FOV5 for the low sulphur FO tank and 214VPL for isolation valve. e) f) Start the HFO transfer pump locally. When the desired quantity of fuel has been transferred, stop the pump, close all valves.

Procedure for Transferring from the HFO Side Tanks to Settling Tanks The HFO settling tanks are fitted with level switches and the HFO transfer pump is equipped for automatic stop under the control of these switches. The settling tank in operation must be checked periodically and an estimate made of when a changeover will be needed. If the settling tank in operation is likely to reach its low level during UMS operation the settling tanks should be changed over before that period of UMS operation commences. A low level settling tank should be filled as soon as possible. a) Check the quantity of HFO in the HFO settling tank to be filled and determine how much fuel is to be transferred. Check the quantity of HFO in the side tank from which the fuel is to be transferred and note the temperature. If the quantity of HFO in the side tank is less than the quantity to be pumped be prepared to change over tanks. Ensure the HFO transfer pump filter is clean. Open the quick-closing suction valve 201 or 202VPL on the side tank from which the fuel is to be transferred. Open the HFO transfer pump suction and discharge valves 203VPL and 211VPL ensuring any crossover valves with the DO transfer pump are closed and the blanks fitted. Open the filling valve to the settling tank being filled 212 or 213VPL. Ensure that the isolating valve 214VPL and the waste oil transfer pump discharge valve 326VPL are closed. Start the HFO transfer pump locally. The pump must be selected for automatic cut out when the settling tank level reaches the level switch. Check that the fuel is being transferred from the required side tank to the designated settling tank. When the required amount of oil has been transferred, stop the pump. Alternatively the pump can be allowed to stop automatically when the settling tank level switch is activated.

Forward Fuel Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Waste Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 1 set Snake, horizontal 10m3/h at 0.392MPa 440V, 5.5kW, 1,200 rpm Taiko Kikai Industries, Ltd. 1 set Gear, vertical 50m3/h at 0.4MPa 440V, 18.5kW, 1,200 rpm

b) c) d)

Procedures for Transferring from the HFO Fore Deep Tank The HFO stored in the HFO fore deep tank is transferred to the HFO side tanks in engine room using the forward transfer pump and the bunker filling line. The procedure is as follows : a) Check the quantity of HFO in the side tank to be filled and check the quantity of HFO in the HFO fore deep tank. Ensure the temperature of the HFO in the HFO fore deep tank is sufficient for pumping. (Approx. 40 Ensure the suction filter for the forward HFO transfer pump to be used is clean. Set the valves as in the following table : Description HFO fore deep tank outlet valves Forward HFO transfer pump discharge valve Bunker line isolation valves HFO filling valve for one of side tanks Valve
FOV1 906VPL 905 /FOV3 / 907VPL FOV4 or FOV6

HFO is transferred to the HFO settling tanks from any of the HFO side tanks where it is allowed to settle prior to being used in the boilers. Two HFO settling tanks are provided for this purpose. The HFO transfer pump is used to transfer HFO from the side tanks to the settling tanks. The HFO transfer pump is started and stopped locally or remotely. For local operation, the control selector switch must be set to OFF position on the ICAS before the pump stop. The pump can be stopped from the fire control station in the event of fire in engine room. The HFO transfer pump is automatically stopped depending upon the high level of fuel oil settling tanks. For automatic stop operation, the control selector switch must be set to ON position on the ICAS. The forward HFO system incorporates an HFO fore deep tank located forward of the cargo tanks and above the forward water ballast tank. The forward HFO transfer pump is used to transfer HFO from the HFO fore deep tank to the aft HFO side tanks in engine room as required.

e) f) g) h) i)

b) c) d)

Position Open Open Open Open

The HFO and DO transfer pumps are interconnected allowing any pump to be used with all grades of fuel. It is recommended that the pumps remain isolated by the blanks and the crossover valves 208 / 215VPL closed to ensure no fuel contamination can occur. Only in the event of a pump failure necessitating the use of another pump should the blanks be removed.

3.6.2 Heavy Fuel Oil Transfer system


Procedure for Transferring from the Side Tanks to Fore Deep Tank HFO may be transferred from the aft HFO side tanks to the fore deep tank if required. Open the HFO side tank suction valves and set up the HFO transfer pump as described in transferring HFO to the settling tanks. Instead of opening the settling tank filling valve, open the isolating valve 214VPL. This will direct the fuel to the HFO fore deep tank and bunker manifolds. Open isolation valves 905VPL and FOV3, HFO fore deep tank filling valve FOV2. Prior to starting the pump ensure all bunker manifold valves are closed and the blanks are fitted. Check the quantity in the fore deep tank to ensure there is sufficient space for the fuel to be transferred before starting the transfer operation. Alarms Sensor (Level) *1 *1 LT LT FS Controls All valves in the HFO bunkering and transfer system are manually operated except for the following which are hydraulically and electrically operated : Valve
FOV1 FOV2 FOV3 FOV4 FOV5 FOV6 212VPL 213VPL

Tag No. 711/712 713 716/717 716/717 725

Function FO side tank Low sulphur tank FO settling tank (from tank bottom) FO overflow tank (from tank top) FO drain tank (from tank top) Waste oil settling tank (from tank top)

Set point LAH LAH 90 % 90 %

LAH 13,180 mm LAL 1,760 mm LAH -250 mm

FS

726

LAH

-300 mm

Location HFO fore deep tank suction valve HFO fore deep tank filling valve Isolation valve Starboard HFO side tank filling valve Low sulphur FO tank filling valve Port HFO side tank filling valve Starboard HFO settling tank filling valve Port HFO settling tank filling valve

FS

727

LAH

-150 mm

(Temperature) TR 716/717 TR (Other) FS 727

FO settling tank Waste oil settling tank

TA H TA H

65 11 0

886

FO overflow

FAH

The HFO transfer pump is stopped automatically at the high level of settling tank being filled (with 10 seconds timer) when the control selector switch for the automatic stop detector has been set to ON on the ICAS.

*1 : Resistance tape

3.6.2a Heavy Fuel Oil Transfer System


200
TO & FM FWD F.O.TK

SHORE CONNECTIONS (P) (S)

300

300

40

200 125 125


214VPL

300

200 125
164VPK
FROM L.O.TRANS. PUMP

25

200

100

262VPL

125

25

65

25

25

F.O.ADD.TK

261VPL

150

213VPL

M
PUMP STOP

212VPL

M
PUMP STOP

150

328VPL
LAH 728

65

65
327VPL
LAH 728

25

F.O.SIDE TK(P)
LM 712 LAH 712

NO.2 F.O.SETT.TK
LI E LI E
TAH 717

607

FS
LAH 717 LAL 717 LM 717

LOW SULPHER F.O.TK


LAH 713 LM 713 TAH 713 TM 713

NO.1 F.O.SETT.TK
LI E
TAH 716

607 LAH 716 LAL 716 LM 711 LAH 711

FS

F.O.SIDE TK(S)
LI E 200 65

200

40

NO.2
LI E

40

FS
PUMP STOP

NO.1
LI E

FS
PUMP STOP

PUMP START

PUMP START

643

FS

643

FS

607

FS

607

FS

200

LM 716

200

E
202VPL 101VPL 102VPL

E
204VPL 002VPL 001VPL

125

201VPL

WASTE OIL SETT.TK

150

100

150

100

100

100

072VPL

150

40
FROM G/E D.O.SERV.TK

40

103VPL

103VPL

003VPL

005VPL

65

127VPK
TO NO.1 BOILER FROM ENG.RM BILGE PUMP

40
072VPL

125
D.O. TKS OVERFLOW

200

142VPJ

50
TO D.O.SERV.TKS

225VPL

65

215VPL

65
326VPL

200

P
65
TO NO.2 BOILER

WASTE OIL TRANS.PUMP


FS
252VPL
XA 886 AS 643
FIRE

ES

RO 643

SA 643

RM 643

224VPL

AS 611

RM 611

SA 611

RO ES 611 FIRE

200

D.O.TRANS.PUMP

150

H.F.O.TRANS.PUMP
ASS 607 RM 607 SA 607 RO GSP ES FIRE

25

C
65 65
FROM D.O.STORAGE TK

P
65

65
208VPL

150
203VPL 211VPL
FROM L.O. SUMP TK

125

OVERFLOW

107VPK

200

100

FROM SEPARATED BILGE OIL TK

FS F.O.OVERFLOW TK

50

LAH 725

100

206VPL

207VPL

LAH 726

141VPJ

65
325VPL

FS

F.O.DRAIN TK

3.6.3 Diesel Oil and Gas Oil Transfer System


Heavy Fuel Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Diesel Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Wase Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 1 set Snake, horizontal 10m3/h at 0.392MPa 440V, 5.5kW, 1,200 rpm Taiko Kikai Industries, Ltd. 1 set Gear, horizontal 10m3/h at 0.294MPa 440V, 3.7kW, 1,200 rpm Taiko Kikai Industries, Ltd. 1 set Gear, vertical 50m3/h at 0.294MPa 440V, 18.5kW, 1,200 rpm All DO and GO tanks are fitted with a quick closing pneumatic outlet valve operated from the fire control station. The valves must be reset locally after being tripped. Each tank is also fitted with a self-closing test cock to test for the presence of water and to drain any water present. The self-closing cock drains are collected into the separated bilge oil tank and pumped to the waste oil settling tank by the waste oil transfer pump to burn in the incinerator. The DO transfer pump is started and stopped locally or remotely. For local operation, the control selector switch must be set to OFF position on the ICAS before the pump stop. The pump can be stopped from the fire control station in the event of fire in engine room. The DO transfer pump is automatically stopped depending upon the high level of selected generator engine DO service tank. For automatic stop operation, the control selector switch must be set to ON position on the ICAS. Procedure for the Transfer of Gas Oil Normally the IGG gas oil tank is dedicated to IGG operation. When the transferring from gas oil tank would be needed, it can be shifted to appropriate service tank by operating the DO transfer pump. The procedure for transferring gas oil is the same as the procedure for transferring diesel oil except for the valves. Set up the valves as follows : Position Open Open Open Open Open Description IGG gas oil tank suction valve Isolating valve in line DO transfer pump suction valve DO transfer pump discharge valve Selected service tank filling valve Valve
221VPL 222VPL 224VPL 225VPL

Controls The DO transfer pump is stopped automatically at the high level of generator engine DO service tank or IGG gas oil tank when the control selector switch for the automatic stop detector has been set to ON on the ICAS.

Procedure for the Transfer of Diesel Oil a) Ensure there is sufficient DO in the DO storage tank and that the generator engine DO service tank has sufficient space to take the fuel. Check that all crossover valves connecting the DO transfer pump to the GO are closed. Ensure that the DO transfer pump suction filter is clean. Open the quick-closing suction valve 223 or 231VPL on the DO storage tank from which the fuel is to be transferred. Open the DO transfer pump suction and discharge valves 224VPL and 225VPL ensuring any crossover valve with the HFO transfer pump is closed and the blanks fitted. Open the filling valve to the service tank to be filled 226 / 227VPL on the generator engine DO service tank, 228VPL on the emergency diesel generator engine DO service tank or on the incinerator DO tank 230VPL. Start the DO transfer pump locally and check that diesel oil is being pumped to the selected DO service tank. When the required quantity has been transferred, stop the transfer pump. Alternatively the pump can be allowed to stop automatically when the generator engine service tank level switch is activated.

Alarms Sensor (Level) LT Tag No. 718 Function Set point 3,200 mm

Diesel Oil (DO) and Gas Oil (GO) are bunkered directly to two DO storage tanks and a inert gas generator GO tank located in the engine room. DO is used by the auxiliary diesel generators and emergency diesel generator, and for starting the boilers from cold and starting the waste oil incinerator. GO is used by the inert gas generator. The DO in the DO storage tanks is transferred to the DO service tanks for each consumer by the DO transfer pump. The gas oil in the IGG gas oil tank can be shifted to the DO service tanks as required by the DO transfer pump. Overflow from the generator engine DO service tank is backed to the starboard DO storage tank through overflow pipe fitted at the tank internal. Overflow from the DO storage tanks and the IGG gas oil tank is led to the FO overflow tank connected with the overflow line from the FO tanks. Overflow from the incinerator DO service tank and the emergency generator DO service tank is led to No.2 generator engine DO service tank through a sight glass respectively.

b) c) d) e)

IGG GO tank LAH (from tank bottom) DO storage tank G/E DO service tank (from tank bottom) LAH LAH LAL

*1 LT LT FS

715 721 722 729

95

3,600 mm 1,500 mm 700 mm

f)

E/G eng. GO service tank L A L (from tank bottom) Incinerator DO serv. tank (from tank bottom) LAH LAL

g)

FS FS

723 724

1300 mm 400 mm

*1 : Resistance tape

3.6.3a Diesel Oil and Gas Oil Transfer System

100 100 100 100

100 100

230VPL
LAH 723 LAL 724

INCINERATOR D.O.TK

228VPL

EMERG.GEN.ENG. D.O. SERV.TK


100 100 100

FS
65

50 100

65

FS

LAL 729

FS

50

50

50

100

65

50

227VPL

226VPL

241VPL

242VPL

243VPL

50

244VPL

PUMP STOP

NO.2 G/E D.O.SERV.TK


LAH 721 LAL 721 LM 721

PUMP STOP

NO.1 G/E D.O.SERV.TK

D.O.STOR.TK (S)
LM 715 LAH 715

D.O.STOR.TK (P)
PUMP STOP

IGG GAS OIL TK


611

LAH 722 LAL 722 LM 722

FS

611

611

FS

LM 715

LAH 715

FS

LI

LI

LI

LI

LAH 718 LM 718

LI

50

E
233VPL

E 125 125
232VPL 231VPL
223VPL

E
221VPL

125

65

F.O.TKS OVERFLOW

65

200

50

TO F.O.TKS

65

65

65

125 65 50 65 65
215VPL

225VPL

40

65

25

200

XA 886

OVERFLOW

150

TO MAIN BOILER

P
65

TO I.G. GENERATOR

FS
252VPL

C
203VPL

P
211VPL

D.O.TRANS.PUMP
224VPL
AS 611 RM 611 SA 611 RO 611
FIRE

25

C
ES

200

100

H.F.O.TRANS.PUMP
ASS 607 RM 607 SA 607 RO 607 ES FIRE

200

65

65
LAH 725

208VPL

100
206VPL 207VPL

FS

50

TO F.O.DRAIN TK

F.O.OVERFLOW TK

125

FROM F.O. TKS

125

234VPL

222VPL

3.6.4 Boiler Fuel Oil Service System


Fuel Oil Burning Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 4 sets Screw, horizontal 5m3/h at 2.74MPa 440V, 15kW, 1,800 rpm The heated HFO is delivered to the boiler FO header. Each boiler has supply header and its own oil flow regulating valve 220B, minimum pressure maintaining valve 232B and flow meter 370B which are controlled by the automatic combustion control system. There is FO return line from the pipe rail of each boiler FO supply to the degassing chamber, which a valve 045/145VPL with an orifice. This return line allows proper control of the viscosity meter when the FO flow amount is extremely small. A FO recirculating line is also provided at the end of each boiler fuel header to allow for warming through of the fuel system whenever the fuel oil burners are not fired. When operating boilers on gas, the fuel oil system remains in operation. This will allow boosting fire on fuel oil, should the gas supply fail. For cold starting, the pump takes suction DO from the generator engine DO service tank and discharges to the boiler FO supply system. A non-return valve 071/072VPL is fitted on the DO service tank run-down line to avoid back flow of HFO to the DO service tank from the FO settling tank. Remote stop of those fuel oil pumps and shut-off of quick closing suction valves on tanks is made from the fire control station. A stop valve 014/114VPL and a spectacle blank are provided at the lowest point of the fuel supply line for draining to the FO drain tank in the event that removal of pipe works is required. Procedure for Preparing Cold Start Operation The description assumes that the boiler is being flashed up from cold and that fuel is being taken from the generator engine DO service tank. It is assumed that the boiler has been shut down with DO circulating in the fuel lines to prevent the fuel lines becoming blocked with cold heavy fuel oil. When the steam is available, the HFO is heated in the settling tank and steam is supplied to the heaters. Warm HFO is then circulated through the fuel lines and the heaters and the temperature is gradually raised to 115C. a) b) c) d) Check the quantity of DO in the DO service tank and replenish if necessary. Ensure that all instrument and control valves are open and that instruments are reading correctly. Ensure that there is control air available at all control valves. Ensure that there is general service compressed air available for atomizing the burner. e) Set the manually operated valves in the engine room as in the following table. Description Valve 065/066/165/166VPL FO return valves on FO settling tank 041/141VPL FO flow control inlet valve 042/142VPL FO flow control outlet valve 043/143VPL FO flow control valve bypass valve 021/031VPB Atomizing steam valves 025/035VPB GS air valve to the fuel atomizing system 232/233VPL Generator engine DO service tank suction valve

Boiler Fuel Oil Service Heater Maker : Kajiwara Iron Works CO.,Ltd. No. of sets : 4 sets Type : Steam heating, coil tube, horizontal Capacity : 5m3/h Rating : 55 to 150 The Boiler Fuel System is designed to allow cold starting up using DO, boiler operation using HFO, and gas only firing with HFO as stand-by, or dual fuel firing. The Boiler Fuel Oil Supply System provides fuel oil at suitable pressure and temperature to the burners throughout the operating range of the boilers. Each boiler has a completely independent fuel oil system which comprises of duplicate FO burning pumps, FO heaters and associated control and piping system. HFO is taken from the operating HFO settling tank and flows to the boiler FO burning pump suction via a primary duplex filter and flow meter for each boiler system. There are two boiler FO burning pumps which are on a duty / standby selection. The pumps can be operated locally or from the ICAS system operator station. A pneumatically operated flow meter bypass valve 006/106VPL will open in case of low oil level in degassing chamber. The boiler FO burning pumps take suction from the FO degassing chamber. The pumps operate at a constant pressure discharge using a recirculating valve 025/125VPL to maintain this, the excess FO being returned to the FO degassing chamber and hence back into the pump suction. The boiler FO burning pumps force the HFO through one of the two steam heated FO heaters and a secondary hot duplex discharge filter. A viscometer located after the secondary filter regulates the steam supply to the FO heaters in order to maintain the desired HFO viscosity of 15 cSt or 115approximately through the ICAS. There are two steam valves of different size working in a split range configuration. The temperature or viscosity control is selected by setting the control mode switch on the ICAS.

Position Closed Open Open Closed Closed Open Open f) g)

Turn the fuel oil temperature bypass switch for diesel oil, on the boiler gauge board, to the ON position. Set the manually operated valves in the fuel oil pump rooms as in the following table. Description HFO supply isolating valve DO supply isolating valve Flow meter inlet/outlet valves Flow meter bypass valve FO burning pump suction valve FO burning pump discharge valve Pressure control valve inlet/outlet valves Pressure control valve bypass valve Boiler FO heater inlet valve Boiler FO heater outlet valve Viscometer inlet/outlet valves Viscometer bypass valve Valve
005/105VPL 071/072VPL 007/008/107/108VPL 006/106VPL 011/012/111/112VPL 021/022/121/122VPL 024/026/124/126VPL 027/127VPL 028/029/128/129VPL 031/032/131/132VPL 034/035/134/135VPL 037/137VPL

Position Closed Open Open Close Open Open Open Closed Open Open Open Closed h) i) j)

Set the preliminary FO pressure to about 1.5MPa. Start the FO burning pump. Operation of the burner control system is described in section main Boiler Operation. Manufacturers instructions regarding the procedure for raising steam from cold must be followed precisely. When the boiler has raised steam to sufficient pressure using DO, heating steam will be available for tank heating, trace heating and for the boiler FO heaters. Heavy fuel oil in the settling tank must be heated to the correct temperature to allow for pumping.
4.3.2

WARNING When using diesel oil as the fuel, only compressed air must be used for atomizing.

3.6.4 Boiler Fuel Oil Service System


Procedure for Changeover of Fuel Oils The description assumes that the HFO will be taken from No.1 HFO settling tank. a) b) When the desired boiler pressure has been achieved burning diesel oil, change over to HFO once the DO has been recirculating. Select FO heater control Temperature mode, supply heating steam to FO heater and increase the DO temperature to about 70 gradually at the burner rail and supply trace heating steam for the pipeline. Ensure that the FO settling tank temperature has been reached more than 30. Change the system valves as in the following table. Most valves will remain in the same position as given in the procedure for raising steam from cold and so only the valve changes are listed. Description No.1 HFO settling tank high suction valve Return valve to No.1 HFO settling tank HFO supply isolating valve DO supply isolating valve Valve
001VPL 065/165VPL 005VPL 071VPL

Procedure for Changing from HFO to DO whist the Boilers are still Operating a) Ensure that there is sufficient diesel oil in the DO service tank for the operation of the diesel generator engine and the boiler. If necessary replenish the DO service tank. Change the atomizing system from steam to air by closing valves 021 / 031VPB and opening valves 025 / 035VPB. Open the DO service tank quick-closing valve suction valve
232/233VPL, if it is not already open.

h)

b) c) d) e) f)

Only leave the boiler FO burning pump operating long enough to displace all the HFO from the system to the HFO settling tank. If the pump is left running for a prolonged period, large quantities of diesel oil will be pumped to the HFO settling tank. Stop the pump when all the HFO has been displaced to the HFO settling tank. A reasonable guide to this is when the return pipe to the HFO settling tank fall in temperature. Close all system valves and shut off all power to the pumps etc.

i)

c) d)

Slowly open the boiler system DO supply valve 071/072VPL and immediately close the HFO supply valve 005/105VPL. Gradually shut off steam to the HFO heaters and the trace heating lines. Heavy fuel oil in the boiler burner supply system will gradually be used whilst firing the boilers and this will be replaced by diesel oil. Keep a check on the system temperatures to ensure that the temperature does not fall too quickly whilst there is still HFO in the pipelines. All burners should also be operated to ensure that there is DO in all burner lines. When the HFO has been completely replaced by the DO, the burners may be shut down when the boilers are not required.

j)

Controls The FO burning pumps will be automatically changed over by low pump discharge pressure (800kPa). The flow meter by-pass valve (006/106VPL) is automatically opened by the low level of degassing chamber due to the clogging of flow meter.

Position Open Open Open Close e) f) g)

Set the FO temperature to about 115. When the FO temperature reaches about 110 (more than alarm level of 105), stop the boiler. Change the atomizing fluid to steam from air, set the FO temperature by-pass switch to NORMAL and the preliminary FO pressure to about 2.5MPa. Re-start the boiler. The boiler may be fired up on HFO. Atomizing air must be used initially in order to ensure that all the diesel oil has been burned. The change to atomizing steam can be made when only HFO is observed to have reached the burners. The FO heater control will be changed to Viscosity mode when the viscosity is stabilized at about 15cSt.

g)

Alarms Sensor Tag No. 506 468 513 470 873 873 874 874 881 882 Function BLR FO header pressure Set point PAL 0.15 MPa ESD 0.1 MPa TA L ESD TA H TA L H L 90 80 150 105 25 cSt 10 cSt

Procedure for Changing from HFO to DO after the Boilers have been Shut Down If a boiler has been shut down, the fuel system may be purged of HFO by pumping DO in and forcing the HFO out. Steam should still be available for trace heating and the FO heaters so that the HFO viscosity is low enough to allow for pumping. Ideally the change to DO should be made when a boiler is still operating, but for emergency reasons a change whilst out of service might be required. a) Ensure that there is sufficient diesel oil in the DO service tank for the operation of the diesel generator engine and the boiler. If necessary replenish the DO service tank. Open the DO service tank quick-closing valve 232/233VPL. Open the supply valve 071/072VPL from the DO service tank and close the HFO supply valve 005/105VPL. When the running pump and the inlet and outlet lines are completely filled with DO, stop the pump and start the other pump. Shut off the trace heating and steam supply to the FO heaters and turn off the viscometer. Allow the second pump to operate and pump DO into the system. The DO will displace the HFO which will flow to the in use HFO settling tank.

PT PS TR TS TR TR VS VS DPS DPS

h)

BLR FO header temp.

FO heater outlet temp.

i)

FO heater outlet viscosity

Changing the Boiler Fuel Oil from HFO to DO In the event of the vessel being in port for a prolonged period with the steam system shut down, it is necessary to change the boiler fuel oil system over from HFO operation to DO operation. This is to ensure that all the fuel oil pipes contain DO which can be readily pumped. The procedure for changing essentially means removing all the HFO from the pipework and replacing it with DO. This is better done whilst the boilers are still being fired as then it is a simple case of burning off all the HFO in the lines and replacing it with DO.

b) c) d)

Secondary FO strainer Primary FO strainer

DPAH 200 kPa DPAH 100 kPa

e) g)

3.6.4a No.1 Boiler Fuel Oil Service System

65 65

65

40

066VPL

065VPL

NO.2 F.O.SETT.TK NO.2 GEN.ENG. D.O. SERV.TK NO.1 GEN.ENG. D.O. SERV.TK
W.DETECT.
XA

LOW SULPHER F.O.TK

NO.1 F.O.SETT.TK
W.DETECT.
XA

(HIGH)

(HIGH)

(LOW) 233VPL 232VPL

101VPL 204VPL

(LOW) 001VPL 002VPL

102VPL

80

25

65

65

100

150

105VPL 072VPL

100 150

103VPL

003VPL

100

100

80

25

205VPL 005VPL

PAL 506 G

65

TO H.F.O.TRANS.PUMP

PM 506

ESD 468

TO D.O.TRANS.PUMP ESD 461 RO 462 OIS 422 OIO 422

65
144VPB

40
071VPL

TO ACC

E
232B
TAL 873 TAH 873 421
370B

STM
145VPB
TO NO.2 BOILER FO SYSTEM TM PMS FM 883

65

ICAS

OIS 424 OIO 424

P
E

25

TAL 513 TM 513

ESD 470

TS

FROM ACC

TO ACC

045VPL

189B 221B
OIS 423 OIO 423

421

TM 873

TIC 872

VIC 874

VM 874

VAH 874

VAL 874

F.O.HEADER
223B 225B PURGE STM

50
222B 042VPL 220B

FS

50

035VPL

041VPL

VISCO.METER
034VPL

65 50

008VPL

T
007VPL

FS
65
AOS 884

223B 225B

T
OIS 423 OIO 423

50
043VPL

037VPL

PURGE STM

50

50

NO.1 BLR F.O.HTR


028VPL

FS

LAL 884

006VPL
411

FROM ACC

ATOMIZ.STM

ATOMIZ.STM

40

026VPL 025VPL

024VPL

40

40
031VPL

027VPL

80

50

P
E

DPAH

881

P
E

NO.2 BLR F.O.HTR


029VPL

65

50

65

50
014VPL

NO.2 BURNER

NO.1 BURNER

65

50 50

011VPL 032VPL

AC 606

RO 606

RM 606

SA 606

FIRE

ES

65

012VPL

TO F.O.DRAIN TK

NO.1 MAIN BLR

C NO.2

F.O.BURN.PUMP NO.1

TO ACC
411

010VPL

606

PS PS
E
021VPL

022VPL

50

TO F.O.OVERFLOW TK

50

50

PUMP CHANGE OVER

65

DPAH 882

80

3.6.4b No.2 Boiler Fuel Oil Service System

65 65

65

166VPL

165VPL

40

NO.2 F.O.SETT.TK NO.2 GEN.ENG. D.O. SERV.TK NO.1 GEN.ENG. D.O. SERV.TK
W.DETECT.
XA

LOW SULPHER F.O.TK

NO.1 F.O.SETT.TK
W.DETECT.
XA

(HIGH)

(HIGH)

(LOW)

101VPL 204VPL

(LOW) 001VPL 002VPL

NO.2 MAIN BLR

233VPL

232VPL

102VPL

100

105VPL 072VPL

100 150

103VPL

150

003VPL

100

100

BURNER NO.2

BURNER NO.1

25

65

65

80

80

25

205VPL

65

TO H.F.O.TRANS.PUMP

005VPL

TO D.O.TRANS.PUMP

65
150VPB

40 65
DPAH 882

071VPL

ATOMIZ.STM

ATOMIZ.STM

E
232B
TAL 878 TAH 878 421

STM
TM PMS
TIC 877

PURGE STM
OIS 423 OIO 423
225B 223B

PURGE STM 225B 223B

P
E

P
E

TO NO.1 BOILER FO SYSTEM

25

OIS 423

OIO 423

189B

222B

FROM ACC

TO ACC

145VPL

221B

421

TM 878

VIC 879

VM 879

VAH 879

VAL 879

151VPB

FM 883

F.O.HEADER
OIS 424 OIO 424 TM 513

50
142VPL 220B

370B

FS

50

135VPL

141VPL

VISCO.METER
134VPL

65 50

108VPL

T
107VPL

FS
65
AOS 884

TS
E
ESD 470

OIO 422 OIS 422 RO 462

50
143VPL

137VPL

50

50

TAL 513

NO.3 BLR F.O.HTR


128VPL

FS

LAL 884

106VPL

411

FROM ACC

TO ACC
G

ESD 461

40

126VPL 125VPL

124VPL

40

PM 506 PAL 506

ESD 468

40
131VPL

127VPL

50

P
E

DPAH

80

881

P
E

NO.4 BLR F.O.HTR


129VPL

65

50

65

50
114VPL

65

50 50
132VPL

111VPL

AC 606

RO 606

RM 606

SA 606

FIRE

ES

65

112VPL

TO F.O.DRAIN TK

C NO.4

F.O.BURN.PUMP NO.3

TO ACC
411

E
606

110VPL

PS PS
E
121VPL

122VPL

50

TO F.O.OVERFLOW TK

50

50

PUMP CHANGE OVER

65

ICAS

80

3.6.5 Boiler Fuel Gas Service System


The boil-off gas (BOG) supply system to the engine room is shown on the ICAS Cargo Boil-Off graphic screens. Gas from the tanks has to be compressed and heated before being supplied to the boiler burner system. Two low duty fuel gas (FG) compressors and a low duty FG heater are provided for this purpose. If the gas header pressure is sufficiently high, the gas will flow freely, bypassing the compressor. The BOG is generated by the following three different methods. Natural boil-off during laden and ballast voyage Spraying during cargo tank cool down during ballast voyages Forcing boil-off using a forcing vaporizer in conjunction with either of the above two methods Boil off gas is supplied by a single wall pipe between the cargo machinery room and engine room bulkhead and by double wall pipes between the engine room bulkhead and the boilers. The air between inner pipe and outer pipe of the double wall pipes is being extracted by one of two vent duct exhaust fans and is exhausted to the cargo area. Continuous running of one vent duct exhaust fan is required when the boilers are burning gas. In the event of both vent duct exhaust fans stop, gas firing is tripped. A boiler gas hood is provided at the engine room entrance of BOG, where all fittings for BOG handling in the engine room are located. Gas detecting units are fitted at the boiler gas hood so as to monitor presence of methane in the hood. Before burning the gas, the extraction fan above the gas room must be operating. (Note: The master gas valve will trip if both gas hood fans stop. ) Observe all company regulations regarding operation of the boilers when using boil-off gas. Ensure that the gas is available and check that the gas supply system is operational. For burners to be on fuel gas only, the following conditions must be applied : Main turbine must be in FULL AWAY condition. The steam dump system must be on AUTOMATIC. Request from the gas engineer to go on boil-off gas burning. Dual fuel mode is available. The cargo machinery room is set up by the gas engineer, see the Cargo Manual. Once set up, the compressor can be started from the MCR or CCR ICAS screen if the command is transferred to the engine room. 2) Controls There are two controllers used to control the FG compressor. One is used to control the inlet guide vanes (IGV). This has a set point which will control the IGV opening to attempt to keep the desired opening of gas control valve. The second controller is for tank pressure protection and is set between 107 and 109kPa absolute. If the tank pressure falls to 107kPa the second controller takes control of the FG compressor in a bumpless transfer, matching the first controller. It will then reduce the opening of the IGV to minimum. It will maintain control of the FG compressor until the tank pressure returns to 109kPa, at which point operation of the FG compressor will be transferred back to the first controller. At 107kPa it will also provide a fuel oil back-up signal in the fuel oil burners if the boiler was running on gas only. The burning mode will not change back to gas firing at this point, that would have to be instigated manually. If the Dump mode is engaged for tank pressure control, the excess gas dump control will open the dump valve when the tank pressure rises above the set pressure, in order to increase the boiler load and control the position of the dump valve to maintain the tank pressure. Alarms Sensor (Pressure) PT DPT Tag No. 507 487 488 Function Common line Burner gas header (Differential pressure between gas header and furnace) Burner gas header PAH Set point 150 kPa

ESDH 75 kPa ESDH 0.7 kPa (BLR gas v/v trip PA H PA L 70 kPa 1.0 kPa

PT PT

507 507

(Temperature) TS 481

Common line

E S D 5 (Master gas v/v trip) TAL 15

TR

514

Burner gas header

(Gas leak detect) Gas 479 detector G1206

BOG pipe hood

E S D 6 0 % (Master gas v/v trip) H 3 0 %

Boiler Gas Valve Trip The boiler gas valves 211B are automatically closed by following conditions : Gas header high pressure Gas header low pressure Master gas valve VG900 trip 75kPa 0.7kPa

Nitrogen Purge The fuel gas supply line will be automatically purged by nitrogen when the fuel gas supply is shut down. 1) Burner purge The burner purge is performed automatically by shut-off of the gas burner. When the burner gas valve is closed and there is at least one flame in furnace, the burner N2 purge will be performed. Gas header purge Gas header purge is performed automatically by shut-off of the boiler gas valve 211B. When the boiler gas valve is closed and no burners are firing, the gas header N2 purge will be performed. In case FO burners are firing, the burner gas valve of firing burner will be opened and purged to furnace.

3.6.5a Boiler Fuel Gas Service System

FROM ACC

P H/H P L/L RO 437 OIO 437 OIS 437 ESD 437 ESD 487 ESD 488

BOG PIPE HOOD


250
208B 207B
OIO 443

NO.2 MAIN BOILER


FURNACE

250
211B
OIO 442

15

212B

OIO 439

NO.2 BURNER

NO.1 BURNER

15 150
217B 216B

GAS HEADER

214B

214B

50

TAL 514

TM 514

15
213B
G

15
OIO 454

PAH 507 PAL 507 PM 507

150

25

150

OIO 444

218B
FOR ACC

OIO 439

50
214B 214B

150 15

217B

216B

GAS DETECT.MONITOR
XAH G1026 ESD 479 XM 30% LEL ALARM 60% LEL GAS TRIP

436B

FS

15
213B
OIO 454

XM

042VUN

046VUN

250 250
041VUN 213B

NO.2

200
044VUN

FOR ACC T L/L T ESD 481 OIO 444 OIO 439

OIO 454

200
045VUN

25

TO CARGO AREA

250 15

15 150
217B

NO.1

200
043VUN

TS
50

218B

216B
AC 657

VENT DUCT EXH.FAN


RO 657 RO 657 ES FIRE RM 657 SA 657 ESD 480

214B

214B

ENGINE ROOM

P
PM 507 FOR ACC PAH 507 G

PAH 507

150

GAS HEADER

TAL 514

TM 514

PM 507

50

OIO 454

50

25

PAL 507

150
213B

436B

FS
OIO 442 FOR ACC OIO 443

OIO 439

350

15 150
217B

15
216B

P
25

212B

214B

214B

15
FROM ACC

FM N2 BUFFER TK

15

207B

208B

15

211B

250

250

RO 437

OIO 437

OIS 437

ESD 437

P H/H ESD 487

P L/L ESD 488


MASTER N2 PURGE V.

FURNACE

NO.2 BURNER

NO.1 BURNER

182VUN

NO.1 MAIN BOILER

MASTER GAS V.

VG900
FROM CARGO MACHINERY RM

TO VENT POST

3.6.6 Boil Off Gas System in Cargo Machinery Room


The following equipments are provided in the cargo machinery room to enable the gas to be supplied to the main boilers. Two fuel gas (FG)compressors One FG gas heater One forcing vaporizer The pipe lines from vapor return system are cross-connected with fuel gas system for emergency operation. c) FG Compressors a) Each FG compressor is an electrical motor driven single-stage centrifugal type with axial suction and tangentially mounted discharge nozzle. The shaft sealing system is provided to prevent gas leakage at the penetration part of rotor shaft from casing. Nitrogen is supplied to the shaft sealing system as a sealing medium. The compressor gearbox is a two-shaft, involute helical gear type. One high speed pinion shaft is connected to the compressor impeller and the other drive shaft is coupled with the electric motor via a flexible coupling. The shaft penetration part at bulkhead plate between cargo machinery room and motor room is sealed with LO which is supplied by main or auxiliary LO pump. b) Forcing Vaporizer a) The forcing vaporizer is provided to vaporize LNG supplied from the spray pump system. The forcing vaporizer provides fuel gas in excess of the natural boil-off gas generated during normal operation. The vaporizer is of a stainless steel, horizontal shell and U-tube direct steam heated type, having a design capacity when supplied with steam of 1.0MPa / 200. The forcing vaporizer is provided with two kinds of control valves, one is for LNG flow control VS955, the other is for temperature control VS956 by spraying. Alarms Sensor TR TR TR TR TR TR TR TR Tag No. G612 G632 G712 G715 G715 G702 G705 G705 Function Set point 100 90 100 85 -20 100 85 -20

FG compressor discharge E S D temperature TA H FG heater outlet temperature ESD TA H TA L ESD TA H TA H

Forcing vaporizer outlet temperature

b)

A mist separator of stainless steel is fitted to the gas suction common line of the FG compressors to prevent carry-over of LNG droplets to the FG compressors

Controls Master Gas Valve 1) Master Gas Valve Trip The master gas valve VG900 is automatically closed by following condition : Gas temperature low Both boilers trip Both vent duct exhaust fans trip Both boiler gas valves trip Detection of gas leak 5

c)

d)

FG Heater a) The FG heater is of the horizontal shell and U-tube direct steam heated type, with a design capacity when supplied with steam of 1.0MPa / 200. The heating steam is supplied from the ship service external desuperheater in the engine room. The heater is provided with its own steam condensate drain pot and a steam trap. Condensate from the heater is returned to the atmospheric drain tank in the engine room via gas heater drain cooler and the gas vent drain tank installed in the cargo machinery room. The heater is provided with two temperature control valves VG935 / VG936. VG935 controls the main gas flow and VG936 controls the by-pass gas flow.

60% LEL

Following operations will be executed by the trip of master gas valve. Boiler FO boost-up (Gas to FO) FG compressors stop Master Nitrogen Purge The master N2 purge is performed automatically by the master gas valve VG900 is closed.

b)

2)

c)

Boiler FO Back-up The boiler FO back-up (Gas to Dual) will be performed by following condition. Vapor header low pressure FG heater trip Both FG compressors stop Main turbine telegraph in maneuvering zone 5kPaG

d)

3.6.6a Boil Off Gas System in Cargo Machinery Room


FROM LNG SPRAY LINE TO NO.3 CARGO TK HOT VAPOUR RETURN VAPOUR RETURN

CARGO MACHINERY ROOM

BOG SUC.

MOTOR ROOM

25

RO

OI

VG902

15
G746

LAH

VG996

250

VL950

VG951

250
RO OI

300

G735

TM

G735

TAL

G735

TAH

G736

TIC

MIST SEPARATOR
FC

32

G734

550

FROM H/D GAS COMP.

DIAS

G733

PM

G737

FM

FORCING VAPORIZER
40

P
50
G734

250

G606

I/P

IAS

G606

PM

VG952

T M

700

VS955 F.C.V.

250

VG942

G632

TAH

G632

TM

ESD
G612

G631

TM

T
G601

300

OI

RO

300

RM

RO ESDS G601 G1411

VG994

GEAR NO.2 L/D GAS COMP.

M M

T.C.V. VS956

500

P
700

G703

PM

ESD
G702

G705

TM

G705

TAH

G705

TAL

G622

PM

P
G621

P
PM

G623

PAL

G615

ESD

VG917

FS
VG941

SURGE CONT.

250

G706

TIC

DIAS

VG904

250

300
OI
G605

P
500
VG900
TO E/R

G704

PM

300

WARM UP GAS HTR

125

G610

RO

G610

OIO

G610

OIS

VG916

VG943
OI

VG915

300
ESD 436
OIO 441

VG903

250

VG932

G632

TAH

G632

TM

ESD
G612

G631

TM

T
G601

300

VG914

15

G606

I/P

IAS

RO G606

RM

RO 436

RO ESDS G601 G1411

OIO 436

OIS 436

VG993

P
300

G713

PM

ESD
G712

G715

TM

G715

TAH

G715

TAL

GEAR NO.1 L/D GAS COMP.

182VUN

VG937

150

G716

250

TIC

DIAS

G622

PM

P
G621

P
PM

G623

PAL

G615

ESD

FS
VG931

FUEL GAS HTR

VG936

SURGE CONT.

P
15 250
178VUN VG935

G714

PM

300
VG934
OI
G605

125

G610

RO

G610

OIO

G610

OIS

15

VG933 175VUN 174VUN

P
25

171VUN VN880

FROM N2 LINE

15

15

3.6.7 Diesel Oil and Gas Oil Service System


The diesel oil or gas oil is supplied for following machinery. Auxiliary diesel generator engines Emergency diesel generator engine Incinerator Inert gas generator DO for service is passed bunkered DO from DO storage tanks to DO service tanks by DO transfer pump. The fuel oil system for each auxiliary generator engine is completely separated. The fuel oil for each engine is supplied from designated generator engine DO service tank via a duplex filter and a flow meter. The fuel oil for emergency generator engine is supplied from the emergency generator engine DO service tank via a duplex strainer. The DO for incinerator is supplied from incinerator DO service tank to pilot burner via pilot burner pump, and the DO may also be supplied to waste oil burner via isolating valve 364VPL for assisting the burning of waste oil. The fuel oil for inert gas generator is supplied from IGG gas oil tank via IGG FO pumps, one is for main burner and the other is for pilot burner. DO and gas oil tanks quick closing suction valves are closed from the fire control station. A stop valve 706/716VPL with a spectacle blank is provided at the lowest of the D/G fuel supply header for draining to the FO overflow tank in the event that removal of pipe works is required. DPS G822
Alarms

Sensor DPS

Tag No.

Function D/G inlet filter differential pressure

Set point D PA H 90 kPa

IGG main burner DO P A L pressure

100 kPa

3.6.7a Diesel Oil and Gas Oil Service System

I.G.G. GAS OIL TK


EMERG.GEN.ENG. D.O. SERV.TK INCINERATOR D.O.SERVICETK

25

25

WASTE OIL SETT.TK

366VPL

NO.2

365VPL

NO.1

362VPL

361VPL

221VPL

401VPL

363VPL

25

EMERG.GEN.ENG.
50
G.S.AIR

15

25

50

TO D.O.TRANS.PUMP

S P
PS

15

INJECT.PUMP

F.O. PUMP UNIT


25

M
25

P
25

PAL PM G822 G822

SCRUBBER UNIT

25
F.O.PUMP
364VPL

S S P P
LS PS

25

S S
P

S S
T TS

MAIN
15

P
15

BURNER

402VPL

25
TS
915

XA

PILOT

INCINERATOR

25

NO.2 GEN.ENG. D.O. SERV.TK

NO.1 GEN.ENG. D.O. SERV.TK

25

25

25

NO.2 AUX.DIESEL ENG.

711VPL

081VPL

NO.1 AUX.DIESEL ENG.

733VPL

723VPL

DP
713VPL

40

40

DP
702VPL 703VPL

40

40
716VPL

T P

F.O.PUMP

731VPL

FS
40

712VPL

FS
40

40

40
721VPL 706VPL

F.O.PUMP

DP
DPAH

714VPL

704VPL

DP
DPAH

T P

25

TO F.O.OVERFLOW TK

TO F.O.OVERFLOW TK

25

25

3.7.1

Main Turbine Lubricating Oil System


Procedure for Operating the System The supply to the gravity tank is via a needle valve 014VPK to ensure a continuous top up supply to the tank. The emergency outlet is via a larger bore non-return valve 012VPK. This allows the gravity tank to provide an emergency lubricating oil supply to the oil supply system in the event of complete failure of the pumping system. The emergency supply allows the turbine to be stopped and so helps to prevent damage due to lack of lubricant. The main outlet line from the gravity tank is protected by a quick-closing valve 015VPK which will be operated from the fire control station. The capacity of the LO gravity tank is sufficient to provide adequate lubrication for the longest possible rundown time of the machinery after blackout. The content of the tank ensures a rundown time of approximate 20 minutes. There are two plate type LO coolers which are cooled by fresh water from the central cooling system. (See 3.4.1 Central Fresh Water Cooling System) An auto-backwash main filter is fitted, which has a capacity up to the full rating of the main pump. This filter is automatic in operation and is fitted with a bypass filter for use in emergencies. Drain from the auto-backwash filter is backed to the LO sump tank through a sludge collector. A control oil system is provided at the turbine. This is dependent on the main LO system and is discussed in section 4.2.2 Main Turbine Operation. It is supplied by two control oil pumps. One of these pumps will be selected as the duty pump and the other pump as standby to cut in automatically should the duty pump fail to maintain the control oil supply pressure (0.9Mpa). A dehumidifier is connected to the gearbox and removes moisture from the gearbox atmosphere and hence from the lubricating oil system. The dehumidifier is air reactivated by heating dry air passing over the desiccant dryer. A coalescing water extraction filter is fitted on 5% by-pass system after the main filter, returning to the sump tank. . There are two shell and tube LO coolers which are cooled by sea water from the SW circulating system, (see section 3.5.1) It is assumed that the turbine is stopped but is being prepared for starting. a) Check the level of oil in the main LO sump and replenish if necessary. Clean all the filters.

Main (Direct Driven) Lubricating Oil Pump Maker : No. of sets : Type : Capacity : Mitsubishi Heavy Industries Ltd. 1 set Gear, vertical driven by main turbine 150m3/h at 0.294MPa

Auxiliary (Electric Motor Driven) Lubricating Oil Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 2 sets Centrifugal, vertical, submerged 150m3/h at 0.294MPa 440V, 37kW, 3,600 rpm

b) Ensure that fresh water is circulating through the LO coolers. c) Ensure all pressure gauge and instrumentation valves are open and that instruments are reading correctly.

d) Set up valves as in the following table : Position Open Open Operational Open Open Operational Closed Closed Open Open Open Closed Operational Open Open Open Open Open Open Close Open Open Open e) Description Valve 003VPK No.1 auxiliary LO pump discharge valve 005VPK No.2 auxiliary LO pump discharge valve Pressure regulating valve 016VPK Automatic back wash filter inlet valve 018VPK Automatic back wash filter outlet valve Automatic back wash filter solenoid drain valve 017VPK Bypass filter inlet valve (normally closed) 019VPK Bypass filter outlet valve (normally closed) 006 or 007VPK LO cooler LO inlet valve 008 or 009VPK LO cooler LO outlet valve LO coolers vent valves (normally closed) LO coolers drain valves (normally closed) 001VPK Three-way temperature control valve 081 or 085VPK Line vent valve (normally opened) 034VPK Water extraction filter inlet valve 035VPK Water extraction filter outlet valve 013VPK Gravity tank filling inlet valve Gravity tank filling needle valve (normally opened) 014VPK Gravity tank quick closing valve (normally opened) 015VPK 062VPK Dehumidifier outlet valve 021VPK No.1 intermediate bearing inlet valve (Locked) 022VPK No.2 intermediate bearing inlet valve (Locked) 023VPK No.3 intermediate bearing inlet valve (Locked)

When stationary, the main turbines and gearbox are supplied with lubricating oil from the main LO sump tank by one of two motor driven auxiliary LO pumps. One of these pumps will be selected as the duty pump and the other pump as the standby to cut in automatically should the duty pump fail to maintain the lubricating oil supply pressure. The pumps may be arranged for automatic start, stop and changeover. An emergency start facility is provided in the event of blackout, the power being taken from the emergency switchboard. When running, the lubricating oil is supplied to the system from the main LO pump, which is driven by the HP gearbox pinion. When the main LO pump is producing sufficient pressure (LO pressure above 110kPa), a pressure switch is activated and the ICAS stops the duty electrical LO pump. When the propeller slows and causes the LO pressure to fall below 95kPa, the duty electrical auxiliary LO pump will automatically start to maintain the pressure. The duty LO pump circulates lubricating oil around the gearbox system and turbine bearings. The main LO circulation system also includes the intermediate shaft bearings. The main LO circulation system supplies LO to the system via the LO coolers, a three-way temperature valve 001VPK regulating the flow of oil through the LO coolers in order to maintain the inlet temperature of 40 to 45C to the bearings. A pressure control valve regulates the LO pressure by recirculating excess oil (pressure 0.294MPa) back to the main LO sump tank. A LO gravity tank forms part of the lubricating oil system and this receives a supply of lubricating oil whenever a pump is running. The tank overflows continuously to the main LO sump tank through an observation sight glass.

Select both auxiliary LO pumps for REMOTE operation at the local control selector. At the ICAS screen for the turbine LO system start one of the pumps as the duty pump by selecting MANUAL mode for that pump and then start the pump. At the ICAS screen select the second pump as the standby pump by selecting AUTO mode for that pump.

(Note : If the oil temperature of the oil is lower than 30, steam heating must be applied whilst the oil is circulating in order to raise the temperature to an acceptable level. Also put the LO purifier in use as soon as possible, which will rise the LO temperature.)

3.7.1

Main Turbine Lubricating Oil System


Alarms

f)

Close the gravity LO tank filling valve 013VPK when the overflow has been confirmed in the sight glass.

g) Check the flow of LO throughout the system, ensuring that the flow is adequate to all parts, including the intermediate shaft bearings and that there are no leaks. Utilize LO flow sight glasses on all bearings and gravity tank. Engage and start the turning gear. h) Keep the LO system circulating and allow the temperature of the system to gradually increase to normal operating temperature. (Note : When the turbine is operating at full sea conditions the main LO pump will be supplying LO to the system and the running auxiliary LO pump will be stopped. The standby LO pump remains in standby mode.) (Note : When the main or aux. LO pump is in operation (while at sea and in turning operation), keep switch off the dehumidifier and also keep close the dehumidifier outlet valve 062VPK. When the main or aux. LO pump is out of operation, keep switch on the dehumidifier and also keep open the dehumidifier outlet valve 062VPK.)

In the event of a blackout, the ICAS remembers which pump was running at the time of the blackout, and whether or not the second pump was selected as the standby pump. Provided that the running pump prior to the blackout was selected in REMOTE the ICAS will start the previously running pump as part of the sequential restart system. Should the pump fail to start within a preset time the standby pump will be started, provided that the second pump was selected in AUTO mode. When the main LO pump is operating the standby facility still applies and one of the auxiliary pumps may be selected as the standby pump. This would be done at start-up of the system as one of the auxiliary LO pumps would be started and the other selected as the standby pump. When the turbine is in the at sea condition and the main LO pump takes over, the running auxiliary LO pump will cut out. The auxiliary LO pump selected as the standby pump will remain in that condition and will cut in should the main LO pump fail to maintain the required LO pressure or the main shaft reduce to predetermined revolution. The conditions for automatic changeover between auxiliary and main pumps are as follows : Shaft revolution Auxiliary pump start : Below 64 rpm or Auxiliary pump stop : Above 68 rpm and LO pressure Below 95kPa Above 110kPa

Sensor (Pressure) PT PS PT PS DPT DPT

Tag No. 108 068 108 069 108 893

Function M/T bearing LO inlet M/T control oil

Set point PAL ESD PAL ESD 70 50 1.0 0.5 kPa kPa MPa MPa

Auto back-wash LO filter


Main LO pump suction filter

DPAH 20 kPa DPAH 20 kPa

(Temperature) TR 121

M/T LO inlet

TA H TA L TA H TA H TA H TA H TA H TA H TA H TA H TA H TA H TA H TA H TA L

54 34 80 80 70 80 80 80 70 80 60 60 60 70 20

TR TR TR TR TR TR TR TR

122124 125 / 126 127 / 128 129 / 130 131133 134 / 135 136 / 137 138 / 139 141 / 142 143 145147 700

HP turbine bearing HP 1st pinion bearing HP 1st wheel bearing HP 2nd pinion bearing LP turbine bearing LP 1st pinion bearing LP 1st wheel bearing LP 2nd pinion bearing 2nd wheel Main thrust pad Intermediate shaft bearing M/T LO sump tank

Controls The electrically driven auxiliary LO pumps and control oil pumps are arranged in a duty / standby configuration with one pump started as the duty pump via the ICAS screen and the other selected as the standby pump. The standby pump will start if the duty pump stops or the LO pressure is low. The second pump may be selected for standby (AUTO) mode when the duty pump is running. Selection for standby (AUTO) mode may be made provided that the pump is stopped, is set to remote mode, is not tripped and provided that the other pump is running. In the event of the running pump tripping or producing a low pressure, the ICAS initiates an alarm and when the low-low pressure is reached the standby pump is started. The original running pump is not stopped by the ICAS and must be stopped manually for investigation if it has not already tripped. A manual start is not available for a pump set to standby and if for any reason the operator wishes to start the standby pump then the status of the pump must be changed from standby (AUTO) to MANUAL at the ICAS screen. The auxiliary LO and control oil pumps may be started manually from the ICAS provided that they are set to REMOTE mode at the pump control selector switch. If both pumps are in MANUAL the ICAS cannot start the second pump in the event of a low-low pressure as AUTO mode is not selected for the second pump.

The auxiliary LO pump in standby will start by low LO pressure (70kPa). The control oil pump in standby will start by low LO pressure (0.9MPa).

TR TR TR *1

(Level) *1 FS

700 702

M/T LO sump tank (from normal level) LO gravity tank (from tank bottom)

LAL -200 mm LAL 1,730 mm

*1 : Resistance tape

3.7.1a

Main Turbine Lubricating Oil System


65 150

FUNNEL
80

10

LUB.OIL MIST BOX

L.O.GRAVITY TK

ENG. RM AIR

LAL 702

FS

125

25 100
062VPK

014VPK

013VPK

TO L.O. SLUDGE TK

15 FROM L.O. STOR.TK 80

65 100
012VPK

015VPK

100

DEHUMIDIFIER
100
DPAH

125

100

128VPK

109

DPM 109

TIC 121

121

T.C.V. 001VPK

25 125
TAL 121 TAH 121 TM 121

150

018VPK

016VPK

S T
019VPK 033VPK 017VPK

25

25

25

80

80

80 80 80
LOCKED OPEN 023VPK LOCKED OPEN 022VPK LOCKED OPEN 021VPK
TAH 700 LAL 700 LM 700 TAL 700 TM 700

P
65

081VPK 085VPK

150

80

L.P.TURB.

65

125

TO L.O.DRAIN TK

P
80 150
005VPK 004VPK

NO.2
RM 601 SA 601
FIRE

350

1W

NO.2 L.O.CLR

T T

009VPK

007VPK

125

NO.3

NO.2

NO.1

AC 601

ASS 601

RO 601

ES

AUX.L.O.PUMP P
T T T
150
003VPK 002VPK

THRUST BEARING
350

601 PUMP AUTO CHANGEOVER PS START/STOP

ESD 068

TAH 147 TM 147

TAH 146 TM 146

TAH 145 TM 145

NO.1

PS

CONT. OIL TK
250 200 125 50 DPS 150

STEADY BEARING

L.O.SUMP TK

101VPK

H.P.TURB.
C MAIN L.O.PUMP P

008VPK

C
150
TO L.O.PURIF.

DPAH

893

NO.1 L.O.CLR
T
006VPK

2W
200

1W
WATER EXTRACT. FILTER

125

034VPK

035VPK

65 150

150

PAL 108

PM 108

25

150

150

25

25

3.7.2

Lubricating Oil Purification System


Procedure for Operating the System Mitsubishi Kakoki Kaisha, Ltd. 1 set Centrifugal, total discharge 3.1m3/h 440V, 5.5kW, 1,800 rpm The solid particles suspended in the oil settle on the underside of the discs and slide down into the solid holding space. The smooth disc surfaces allow the solids to slide down and provide self-cleaning of the discs. Each bowl assembly is fitted with a regulating ring, sometimes referred to as a gravity disc. The diameter of the gravity disc is determined by the density of the oil to be purified and will determine the position of the interface between the oil and the sealing water. The position of this interface is critical for the effective separation of the liquid mixture. Being of the self cleaning type, the accumulation of solids within the holding space will be ejected at predetermined intervals depending on the quality of the oil. This is achieved automatically by the control panel and a number of solenoid valves which will bypass the oil supply and open the bowl for a set period of time by the use of high pressure water. The oil feed while the self-cleaning cycle, is returned to the suction of the pump by a three-way piston valve. The purifier will be used for the following purposes : Continuous main system purification Renovating tank purification Stern tube system purification Batch purification of turbo generator, main feed water pump turbine and diesel generator engine. A LO purifier feed pump and a transfer pump are provided for supplying the oil to the purifier, the former is dedicated for turbine LO treatment, and the latter is for generator engine LO. Each supply system is segregated with double shut valves to minimize the contamination of oils of different kind. Normally, the LO in the main turbine sump tank is circulated through the purifier continuously. In the event that big amount water appears in the LO, the LO will be shifted once to LO renovating tank, then the LO will be purified by circulation between LO renovating tank. The LO in small sumps for turbo generator, main feed water pump turbine and generator engine will be purified by circulation between respective renovating tank after shifted once to renovating tank. The LO in the stern tube LO sump tank will be purified by circulation between stern tube LO sump tank. A steam heater is provided for LO purifier system to lower the viscosity of the LO entering to purifier bowl to aid purification. Waste water and sludge is directed to the LO sludge tank for disposal. To purify lubricating oil to and from the main turbine LO sump tank. a) b) c) d) Record the level of oil in all the tanks associated with the system. Open any control air and operating water valves to the purifier. Ensure there is electrical power at the purifier control panel and Multi-monitor. Set the valves as shown in the following list : Description LO sump tank suction valve Purifier feed pump suction valve Recirculation / Purifier return valves Pump discharge valve Purifier discharge valve Purifier discharge isolation valve LO sump tank inlet valve Sludge discharge valve Fresh water supply valve All valves other than the above Valve
101VPK 103VPK 117/118/124VPK 104VPK 110/113/120VPK 106VPK 128VPK 301VPK 131VPG

Lubricating Oil Purifier Maker : No. of sets : Type : Capacity : Rating :

Lubricating Oil Purifier Feed Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 1 set Gear, horizontal 3.1m3/h at 0.294MPa 440V, 0.75kW, 1,200 rpm

Lubricating Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 1 set Gear, horizontal 1.0m3/h at 0.294MPa 440V, 0.75kW, 1,200 rpm

Open Open Open Open Open Open Open Open Open Closed

Purifier Lubricating Oil Heater Maker : No. of sets : Type : Rating : Kajiwara Iron Works Co.,Ltd. 1 set 3.1m3/h 40 to 85

The purifier flow regulating valve 105VPK should be set for the desired discharge pressure and should not be adjusted during normal running conditions. e) f) g) h) Ensure the purifier brake is off and that the purifier is free to rotate. Check the purifier gearbox oil level. Start the purifier feed pump. The three way valve will ensure the oil bypasses the purifier and returns to the pump suction. Set the steam temperature control valve to the required setting (85) taking care not to overheat the oil. Slowly open the steam supply and return on the heater in use. Start the purifier at the control panel and ensure that the bowl is up to speed before continuing. Ensure the operating water opens and closes the bowl. Switch on the control panel. Once the lubricating oil temperature is above the minimum setting, start the program by pressing AUTO.START button on the control panel. This will initiate a start sequence including a sludge and discharge test and operate the purifier in automatic mode. Once the purifier is running and no signs of abnormal vibrations and sound are evident, temperatures, pressures and electric current should be recorded and the levels of the tanks in use checked.

The purpose of the lubricating oil purifier is to remove water and solid particles from the lubricating oil to prevent damage being caused to the machinery the oil is supplying. Liquid mixtures and solid/liquid mixtures can be separated by two means. The gravity field of a renovating (settling) tank or the centrifugal field of a purifier bowl. Both systems rely on the product components having different densities. Since the centrifugal field of a purifier is considerably more effective than the gravity field of a renovating (settling) tank it is usual practice to favor the centrifugal field method. The heated dirty oil enters the purifier and the centrifugal force created by the rotating bowl causes the liquid mixture to separate into its different constituents within the disc stack. The disc stack consists of a large number of conical discs placed one above the other. Each disc is provided with spacers to maintain the precisely determined narrow disc interspaces. These interspaces are critical for the efficiency of the separator.

i) j) k) l)

3.7.2

Lubricating Oil Purification System


Position Open Open Open Description LO renovating tank suction valve Isolating valve from LO renovating tank Purifier feed pump suction valve Valve
125VPK 129VPK 124/103VPK

Procedure to Stop the Purifier a) b) c) d) e) Shut the steam to the heater and allow the oil to cool. Press the AUTO.STOP button. Two total ejections will be triggered and the purifier will stop automatically. The feed pump will need to be stopped if they are running in manual mode. Close the control air and operating water valves to the purifier along with any other valves opened prior to start up. Once the purifier has come to a complete stop the brake can be applied and preparations made for cleaning if required.

MULTI - MONITOR

STARTER

CAUTION Extreme care must be taken when transferring lubricating oil to ensure that oils do not become mixed. The setting of all valves must be checked prior to commencing transfer operations, so that oil will only be pumped from and to the intended destinations.

MITSUBISHI KAKOKI KAISHA, LTD.


Flux (L/Hr) SW Temp. ( C) L. Press. (MPa) Rev. (r/m) W/H Press. (MPa) Error

AUTO. CONT. PANEL


CONT. SOURCE

AUTO. RUNNING
LEAK NO-DIS SV4
S

SV1 SV2 SV3 Water inlet


S S S

FEEDING
Air inlet

ALARM AUTO. START AUTO. STOP DISCHG. TEST

MM ON MM FUNC.

EMERGENCY STOP

LM

MM

Purified oil outlet

DD
Circulation Dirty oil inlet

POWER SOURCE
ALARM RESET

SV1 SV2 SV3 SV4

OPENING CLOSING SEALING / REPLACEMENT FEEDING

CONT. SOURCE
OFF ON

Procedure for Purifying Oil in the Renovating Tank Contaminated oil may be once collected in the renovating tank where the oil is settled. The settled oil in the tank is circulated operating the purifier. The description assumes that the batch purification will be carried out for the contaminated oil in the main sump tank using the renovating tank and that the contaminated oil will be transferred to the renovating tank. a) b) Ensure that the renovating tank has sufficient space to take the LO from main sump tank. (about 15m3) The procedure for starting the purifier is as previously described with the following valve settings :

Controls The control unit is used for the automatic ejection control and condition monitoring of the oil purifier. With the time dependant program cycle, it is important for high clarifying efficiency and to avoid desludging losses that the separable solids content in the product do not fluctuate widely. This system provides two basic monitoring systems. 1) Leakage monitoring system (LM) 2) Discharge detector monitoring system (DD) The illuminated Liquid Emitting Display (LED) provides information about the operating and malfunction condition of the purifier and displays all the relevant process data. The ICAS provides indication for running and oil temperature and alarm for purifier failure.

WATER INLET
131VPG

R4

SV2 SV1 SV3 S S S

SV4 S

CONT. AIR

BOWL OPENING WATER

BOWL CLOSEING WATER

SEALING WATER

V5

Position Description Valve 125VPK Closed LO renovating tank suction valve 431VPK Closed A/T LO renovating tank filling valve 126VPK Closed LO daily tank filling valve 131VPK Open LO renovating tank inlet valve 102VPK Open Isolating valve to LO renovating tank 116VPK Close Isolating valve to LO sump tank c) When the transferring oil in the sump tank would have completed, the new oil will be filled from the storage tank to the sump tank. d) For filling the new oil to the sump by gravity, set the valves as shown in the following list : Description LO storage tank suction valve LO filling line valve LO sump tank inlet valve All valves other than the above Valve
123VPK 127VPK 128VPK

PURIFIED OIL OUTLET

M DD
RETURN DIRTY OIL INLET

WATER DRAIN

SLUDGE

Alarms Sensor TR DPS Tag No. 892 893 Function LO purifier LO inlet Purifier feed pump and LO transfer pump suction filters Oil sludge tank (from tank top) Set point TA H D PA H 90

LM : LEAKAGE MONITOR DD : DISCHARGE MONITOR MM : MULTI-MONITOR

Position Open Open Open Closed e) f) g)

5 0 mm

While the filling of new oil, the purifier operation should be stooped. The valves 123 /128VPK will be closed after completion of the filling. Set the valves as shown in the following list :

FS

707

LAH

2 0 0 mm

HEATER

LM

MM

3.7.2a

Lubricating Oil Purification System

LUB.OIL MIST BOX

40

1.0 MPA AUX.STM

40

40

50

TC 892

114VPK

431VPK

131VPK

50

G/E L.O. RENOV.TK

G/E L.O. STOR.TK

A/T L.O. RENOV.TK

A/T L.O. STOR.TK

L.O.STOR.TK

L.O.RENOV.TK

T
TM 892 TAH 892 TAL 892

40

40

PURIF.L.O.HTR
M01VPK

109VPK

LEAKAGE MONITOR 40
891

165VPK

LM
(2)
110VPK

111VPK

152VPK

153VPK 154VPK

TO W.O. TRANSF.LINE

425VPK

423VPK

123VPK

125VPK

40

40

50

122VPK

80

50

40

166VPK 158VPK

163VPK 119VPK 112VPK 102VPK

301VPK
RM 891 SA 891 ES FIRE

40

162VPK

P
40
SUMP TK
134VPK 168VPK

126VPK

40

40
136VPK

FIRE

ES

RM 603

SA 603

L.O.DAILY TK
116VPK 132VPK 108VPK

C
25

NO.2 AUX.GEN.ENG.

DPS C
40

DPAH

893

40

40
SUMP TK
133VPK

40
106VPK 157VPK 156VPK

100

40
135VPK

40
155VPK

40
196VPK 197VPK

80

L.O.TRANS.PUMP

50

120VPK 113VPK

50

NO.1 AUX.GEN.ENG. NO.2


SUMP TK

LAH 707

FS

25
144VPK

127VPK 117VPK 306VPK 118VPK

80

50

TO SEP.BILGE OIL TK

SUMP TK
136VPK

40

MAIN FD.W.PUMP TURB.

40

TO L.O.DRAIN TK

50
130VPK 128VPK 129VPK

L.O.SLUDGE TK

L.O.PURIF.FD PUMP
RM 604 SA 604
FIRE

ES

NO.2 MAIN T/G

NO.1

SUMP TK

50

25
143VPK

FROM L.O.GRAV.TK SUMP TK


137VPK

TO W.O. TRANSF.PUMP

50

107VPK 124VPK

DPAH

893

DPS

P
104VPK

40

40

139VPK

40

50

50
103VPK

142VPK

80

NO.1 MAIN T/G

25

40

50

101VPK

40

105VPK

STERN TUBE L.O.DRAIN TK

141VPK 201VPK

L.O. SUMP TK

TO S/T L.O.PUMP

L.O.DRAIN TK

40

164VPK LOCKED CLOSE

L.O.PURIF.

3.7.3

Lubricating Oil Filling and Transfer System


Procedure for Filling to Auxiliary Turbines a) Close the following valves : Description A/T LO renovating tank suction valve LO supply in line valves b) c)

Lubricating Oil Transfer Pump Maker : Taiko Kikai Industries, Ltd. No. of sets : 1 set Type : Gear, horizontal Capacity : 3.1m3/h at 0.343MPa Rating : 440V, 0.75kW, 1,200 rpm Lubricating Oil Purifier Feed Pump Maker : Taiko Kikai Industries, Ltd. No. of sets : 1 set Type : Gear, horizontal Capacity : 1.0m3/h at 0.294MPa Rating : 440V, 0.75kW, 1,200 rpm

Valve
425VPK 132/139VPK

The LO storage and LO renovating tanks are fitted with pneumatically operated Each renovating tank is fitted with a steam heating coil which would promote separation of water, oil and sludge in the settling process. quick-closing valves which can be operated from the ships fire control station. After being tripped the valves must be reset locally. Each renovating tank is also fitted with a self-closing sample cock to allow for a sample to be drawn for analysis and to check for the presence of water. All LO tanks have a save-all which will catch and direct any escaped oil to the LO drain tank. The decrepit oil in the sump tanks is discharged either to shore connections or to waste oil settling tank by the transfer pump for engine oil and the waste oil transfer pump for turbine oils. The sludge from purifiers is discharged into the oil sludge tank and collected to the separated bilge oil tank. The contents in the separated bilge oil tank will be pumped to waste oil settling tank or the shore connection by the waste oil transfer pump. Return from Main LO sump Tank to LO Renovating Tank The description assumes that the transfer will be carried outtank using LO purifier feed pump. a) Close the following valves : Description LO renovating tank suction valve Purifier heater inlet valve Pump suction valve from auxiliaries Recirculation / Purifier return valves Engine oil purifier heater inlet valve Purifier discharge valve Isolating valve to auxiliaries Open the following valves : Description LO sump tank suction valve Purifier feed pump suction valve Pump discharge valve Isolating valve in line with pump discharge LO renovating tank inlet valve Start pump at the local starter.

Open the appropriate filling valve on sump tank. On the contrary, Confirm that other valves not to be required to supply LO are closed. Open the following valves : Description Valve 423VPK A/T LO storage tank suction valve 122VPK Turbine LO supply valve in line

Return from Auxiliary Turbine LO Sumps to A/T LO Renovating Tank a) Close the following valves : Description LO sump tank suction valve Recirculation / Purifier return valve Purifier heater inlet valve Engine oil purifier heater inlet valve Purifier discharge valve Isolating valve for A/T LO sump filling LO renovating tank inlet valve Valve
101VPK 105 / 124VPK 109VPK 165VPK 102VPK 132VPK 131VPK

Two LO filling lines, one is for turbines LO, the other is for generator engine LO are provided and each shore filling connection is located at port and starboard on upper deck. The LO transfer system is composed of two transfer / purifier feed pumps, one purifier, storage tanks, renovating tanks and sump tanks of machines. The different kind LO is applied for the main turbine and auxiliary turbines. The generator engine LO system is segragated from the turbine LO system except purifier operation to minimize the mixture of different kind of oils. For this means, double shut valves are provided between for turbine oil and engine oil operation. Each LO sump tank is filled directly from the storage tank and the renovating tank by gravity. The main LO sump tank can be purified or pumped to the renovating tank. This operation would be required if the main sump tank needed cleaning or repairs, or if the oil in use became unfit for further use due to contamination. The sumps for auxiliary turbines and stern tube should be pumped to the A/T renovating tank and renovating tank respectively for the batch purification of them. After completion of the purification, the purified oil in each renovating tank is discharged to respective sump by gravity. The sumps for auxiliary generator engine are pumped to the renovating tank by the LO transfer pump when the batch purification is required. After completion of the purification, the purified oil in the renovating tank is dropped to the sump by gravity.

b) Valve
125VPK 109VPK 139VPK 105 / 124VPK 165VPK 102VPK 132VPK

Open the appropriate suction valve on sump tank. On the contrary, Confirm that other valves not to be required to shift LO are closed. Open the following valves : Description Purifier feed pump suction valve Pump discharge valve Isolating valve in line with pump discharge A/T LO renovating tank inlet valve Start pump at the local starter. Valve
103VPK 104VPK 106/108VPK 431VPK

c)

d)

b)

Valve
101VPK 103VPK 104VPK 106/108VPK 131VPK

Procedure for Filling to Auxiliary Generator Engine LO Sump a) Close the following valves : Description G/E LO renovating tank suction valve G/E LO purified oil in line valve Open the following valves : Description G/E LO storage tank suction valve G/E LO supply in line valve Valve
152VPK 154VPK

c)

b)

Valve
153VPK 158VPK

c)

Open the appropriate filling valve on sump tank. On the contrary, Confirm that other valves not to be required to supply LO are closed.

3.7.3a

Lubricating Oil Filling and Transfer System

LUB.OIL MIST BOX

UPP. DK (P)

UPP.DK (S)

UPP.DK

50 80
(3)

80
191VPK

193VPK

40

40

114VPK

151VPK

431VPK

421VPK

121VPK

50

CLEAN OIL TK
131VPK

G/E L.O. RENOV.TK

G/E L.O. STOR.TK

A/T L.O. RENOV.TK

A/T L.O. STOR.TK

L.O.STOR.TK

L.O.RENOV.TK
M01VPK

40

PURIF.L.O.HTR

109VPK 165VPK

111VPK

40

40

40

80

40

122VPK 166VPK 158VPK 164VPK LOCKED CLOSE 119VPK 112VPK 163VPK

50

154VPK

50

152VPK

153VPK

TO W.O. TRANSF.LINE

425VPK

423VPK

123VPK

125VPK 110VPK

L.O.PURIF.
25
102VPK 120VPK 113VPK

NO.2 AUX.GEN.ENG.

40

162VPK

L.O.TRANS.PUMP
FIRE

168VPK

(3)

SUMP TK

134VPK

ES

40
136VPK

RM 603

SA 603

L.O.DAILY TK
192VPK 132VPK

80

126VPK

116VPK

C
25

DPS C
40

DPAH

893

NO.1 AUX.GEN.ENG.
133VPK

40
108VPK

106VPK

(3)

SUMP TK

40
135VPK

40
155VPK

157VPK 156VPK 196VPK 197VPK

NO.2 NO.2 MAIN T/G


LAL 248 LAL 580
SUMP TK

25
144VPK

127VPK 117VPK

80

118VPK

SUMP TK
136VPK

40

MAIN FD.W.PUMP TURB. NO.1


LAL 580
SUMP TK

40

TO L.O.DRAIN TK
130VPK 129VPK

50

L.O.PURIF.FD PUMP
RM 604 SA 604
FIRE

(3)

ES

50

25
143VPK 128VPK 107VPK

NO.1 MAIN T/G


FROM L.O.GRAV.TK
LAL 248

C
124VPK

DPAH

893

TO W.O. TRANSF.PUMP

50

DPS

P
104VPK

SUMP TK
137VPK

40

40

139VPK

40

50

50
103VPK

(3)

LAH 703

25

40

FS

142VPK

80

50
101VPK

105VPK

NOTE: (3) TO L.O. SLUDGE TK

STERN TUBE L.O.DRAIN TK

141VPK 201VPK

L.O. SUMP TK
NOTE : TO S/T L.O.PUMP (3) TO L.O. SLUDGE TK

L.O.DRAIN TK

3.7.4

Stern Tube Lubricating Oil System


Japan Marine Technologies Ltd. Airguard 3AS the after most. The compressed air is provided in No.1 chamber and the lubricating oil is supplied in No.2 chamber. LO and sea water are completely separated from each other by the air chamber which is provided between #1 and #2 seal rings. In addition, part of the compressed air supplied from the air control unit to the air chamber is guided to the drain collecting unit. In the event that the sea water or oil enters into the air chamber, they are carried to the drain collecting unit by the air flow forcibly and collected inboard without oil leaking outboard or sea water entering into the stern tube. Forward Seal Assembly The forward seal consists of two sealing rings, both facing aft. The chamber between the seals is supplied with oil from a small forward seal circulation tank, of approximately 15 litre capacity, situated on the aft bulkhead so that the normal oil level in the tank is approximately 1,000 mm above the propeller shaft centre line. The circulation tank is fitted with a filling cap, low level alarms. The centre pipe leading down from the circulation tank provides a static head for the seal. The two pipes connected to the sides of the circulation tank form part of the circulating system set up when the shaft is rotating. A circulator is fitted between the two seals and forms a pumping action when the propeller shaft rotates. The two pipes allow for ahead and astern rotation of the shaft. Procedure for the Preparation a) Check the following items. 1) The oil level in the stern tube LO sump tank, the aft seal tank and the forward seal circulation tank and top up as necessary. 2) Presence of sea water and / or LO at the drain collection unit. 3) LO flow (abt 120 L/h) to No.2 chamber with a flow meter. 4) Air flow (abt 35 L/min) to the chamber No.1 with a flow meter. 5) Air pressure at No.1 chamber with a pressure gauge fitted on the control unit outlet b) Clean all the filters c) Ensure that there is control air available for the air control unit. d) Set the valves as shown in the table below. Position Open Closed Open Open Open Closed Open Closed Closed Open Closed Open Open Open Open Closed Description LO sump tank suction valve Cross-connection valve with purifier suction Pumps suction valves Pump discharge valves Cooler inlet and outlet valves Cooler bypass valve Stern tube inlet valves Forward seal circulating tank filling valve Aft seal tank drain valve Aft seal tank inlet valves around sight glass Aft seal tank inlet sight glass bypass valve Aft seal tank outlet valve Aft seal inlet valve Aft seal flow meter inlet / outlet valves Aft seal flow meter bypass valve Sampling and all drain valves Valve
201VPK 141VPK 202 / 203VPK 211 / 212VPK 213 / 214VPK 215VPK 216 / 217VPK 228VPK V19 222 / 223VPK 221VPK 225VPK 210VPK 218 / 219VPK 220VPK

Stern Tube Seal Maker : Type :

Stern Tube Lubricating Oil Pump Maker : Taiko Kikai Industries, Ltd. No. of sets : 1 set Type : Gear, horizontal Capacity : 1m3/h at 0.196MPa Rating : 440V, 0.75kW, 1,200 rpm Stern Tube Lubricating Oil Cooler Maker : Setouchi Kogyo Co.,Ltd. No. of sets : 1 set Type : Shell and tube, horizontal Capacity : 1.0m3/h The function of the stern tube is to act as a seal and bearing support for the propeller shaft. The stern tube assembly is sealed at both ends using lip type seals and is oil lubricated, the lubrication system being totally independent of all other systems. The stern tube passes through a tank filled with water and provides added cooling for the stern tube. There are three lubricating systems for the stern tube, the bearing unit, the aft seal assembly and the forward seal assembly. The bearing and seal assemblies all use the same grade of lubricating oil as main turbine service. Bearing Unit The bearing area is lubricated by means of an aft seal tank system with oil being supplied to the stern tube from one of two stern tube LO pumps. The stern tube LO pumps take suction from the aft seal tank and passes the oil through a cooler and duplex filter before supplying the stern tube bearing. The stern tube LO cooler is supplied from the central fresh water cooling system. The pressure is maintained by the pressure of aft seal tank which is controlled with the compressed air being supplied from the air control unit, and the oil from stern tube is returned to the aft seal tank through a sight glass which enables the operator to positively identify oil return. The pressure distribution in the seal system is automatically adjusted to follow the change of ships draft. The aft seal tank is provided for ingress of sea water by the wear or failure of aft seal for sea water. Aft Seal Assembly The aft seal consists of three major parts, the three lip sealing rings, the metal housing holding the sealing rings, a liner which rotates with the propeller shaft. The seal ring is made from Viton. The aftermost seal ring faces outwards whilst the two forward seal rings face forward. The space created between each seal is called a chamber, there are two chambers at the aft seal assembly, numbered 1and 2, number 1 chamber being

c) Open the cooling water inlet and outlet valves to the stern tube LO cooler and ensure that cooling water is circulating through the cooler. d) Start the duty stern tube LO pump and check that oil is flowing through the bearing system and returning to the Aft seal tank by means of the sight glass. e) Set the other stern tube LO pump to the standby mode. f) During normal operation, regular inspection should be made by oil levels, temperatures and pressure. Oil samples should be tested in accordance with planned maintenance schedule. g) At the dry dock, close the compressed air valves 156 / 228VPE for the air control unit and open blank flange B1. After evacuating air from piping, close air supply valve V19. (Note; Normally, the flushing in air supply line and No.1 aft seal chamber will be executed about once every 6 to 12 months. The flushing work should be made according to the Flushing Procedure for Air Supply and Drain Line of AIRGUARD 3AS attached to the drawing Stern Tube Sealing).

3.7.4
Controls

Stern Tube Lubricating Oil System


Countermeasures in Abnormal Condition In case of substantial amount of oil is collected in the drain collecting unit. #2 seal ring may be damaged. If the unit is frequently discharged i.e. 1 time/10 min. Fully open 216VPK and close 210VPK to operate #3 seal ring. After that, adjust the pressure in the stern tube so it becomes higher, by P2, then supply air pressure by adjusting air-relays in the air control unit. (2) In case of substantial amount of sea water is collected at drain collecting unit, it is possible to reduce the amount of sea water ingress by increasing air supply flow (max. 60L/min.) with adjusting the valve at flow meter outlet in the control air unit. (3) In case of control air failure, a) Supply the air from another source. Change the valve 228VPE over
156.VPE

The stern tube LO pumps may be set for local operation or remote operation via the ICAS display. In remote operation pumps may be started and stopped manually and one pump may be selected for automatic operation to act as the standby pump and start should the duty pump fail to maintain the flow of pump discharge. A stern tube LO fresh water heater supplies the cooling water which the temperature is automatically controlled with a steam valve to maintain the appropriate LO temperature for frigid climate condition

(1)

Alarms Sensor TR Tag No. 148 / 088 Function S/T bearing metal temp. Set point TAH / ASLD (M/T) 5 5

b)

If no air source can be supplied, LO may be filled into the #1 - #2 seal ring chamber (No.1) in accordance with the separate operation instruction Stern Tube Sealing and make close of No.1 chamber.

(Level) FS

703

S/T LO drain tank (from tank bottom) Aft seal tank (from tank bottom) Forward seal circulating tank (from tank bottom) Drain collecting unit

L A L 1 , 7 3 0 mm

FS

704

L A H 1 , 1 0 0 mm L A L 4 3 0 mm LAL 130 mm

FS

705

FS
(Pressure) PS

706

LAH

704 709 893 893

Aft seal tank Seal air Stern tube LO pump suction filter Stern tube LO inlet filter

PS DPS DPS

PA H PA L PA L D PA H D PA H

230kPa 10kPa 10kPa 50kPa 50kPa

3.7.4a

Stern Tube Lubricating Oil System


FOR PIPE FLUSING
140VPG

FM

F.W.

PAL 709 FM

P
228VPE

15
V19

S
B1
FM

CONT. AIR G.S. AIR


156VPE

P
AIR RELAY

LAH 704

PAH 704

PAL 704

AIR CONTROL UNIT

P
50
221VPK

LAL 704

PS

PS

FS AFT SEAL TANK


WEAR DOWN GAUGE

222VPK

223VPK

225VPK
CHECK GAUGE

STERN TUBE COOL.F.W.TK


V19

LAL 705

228VPK
P-RING O-RING #1 #2 #3 #4 #5

FS T FWD SEAL TK
25 50

AFT LINER

FWD LINER

AFT SEAL

FWD SEAL

COOL.F.W.

25

25

25

TIC

25

STM

STERN TUBE L.O.CLR

054VPG

055VPG

25

S/T LO F.W.HTR

T
25
210VPK

T
213VPK

053VPG

25
219VPK

220VPK
DPAH 893

214VPK

217VPK

40
TM 148 TAH 148 ASD 088 TM 149 TAH 149 ASD 088

216VPK

40

605

40

40

25

218VPK

FS

DPS

FS
FOR AUTO CHANGE-OVER

40
215VPK

40 40

40
261VPK

STERN TUBE L.O.PUMP


212VPK
AC 605 RO 605 RM 605 SA 605
FIRE

ES

25

211VPK

P
LAL 703

P NO.1

NO.2
TO L.O.PURIF.FD PUMP

25

40

LS DRAIN COLLECTION UNIT

C C
DPAH 893

C C
DPAH 893

40

DPS

DPS

LAH 708

C
201VPK 141VPK 203VPK

C
202VPK

ALARM CHAMBER

FS

40

40

STERN TUBE L.O.SUMP TK

3.8.1

Engine Room Bilge System


The emergency stop switches for USCG (ESSU) are provided at the places of shore connection (port and starboard) for bilge discharge to stop bilge discharge. The ESSU switches stop the following pumps. Engine room bilge pump Bilge separator service pump Waste oil transfer pump LO transfer pump LO purifier feed pump All bilge wells, the bilge holding tank, separated bilge oil tank, clean drain tank and sunken under the main turbine seating have high level alarms. The emergency bilge suction is provided at the suction of No.2 cooling sea water pump and enables large quantities of bilge water to be pumped overboard in the event of an emergency such as engine room flooding. (See 3.5.2 Cooling Sea Water Service System) Bilges in the steering gear spaces and the emergency fire pump room are drained to aft bilge well through self closing cocks when required. The cocks are normally closing.

Bilge and General Service Pump Maker : No. of sets : Type : Capacity : Rating : Fire and Bilge Pump Maker : No. of sets : Type : Capacity : Rating : Engine Room Bilge Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 1 set Reciprocating piston, vertical 5m3/h at 40m total head 440V, 1.5kW, 1,200 rpm Teikoku Machinery Works, Ltd. 1 set Centrifugal, vertical, self-priming 170/255m3/h at 100/35m total head 440V, 100/30kW, 1,800 /1,200rpm Teikoku Machinery Works, Ltd. 1 set Centrifugal, vertical, self-priming 255m3/h at 35m total head 440V, 45kW, 1,800 rpm The bilge system is composed of the following : Bilge and General Service Pump Fire and Bilge Pump Engine room bilge pump Waste oil transfer pump Bilge separator Clean drain tank Separated bilge oil tank Bilge holding tank Bilge wells

The clean bilge water is discharged to overboard by the fire and bilge pump. In addition, both fire and bilge, and bilge and general service pumps will be used to pump bilge water overboard in the event of an emergency such as the ingress of large quantities of water into the vessel. Bilge wells within the engine room are located as follows : Forward port and starboard Port middle Aft Bilge suctions are provided to following sunken places additionally : Forward port and starboard on 4th deck Under main turbine seating Each bilge suction is connected to a common bilge main line which is taken suction by the engine room bilge pump and the fire, bilge and general service pumps. Bilge wells are normally pumped out using the engine room bilge pump which discharges to the bilge holding tank. The bilge water is settled in the bilge holding tank as pre-treatment of oily bilge and the settled water is directed to the bilge separator to remove the oil so that the oil residues in the treated water do not exceed 15ppm. The separated oil in the bilge holding tank is drained into the separated bilge oil tank. Contents in the separated bilge oil tank is discharged to waste oil settling tank or shore connections as required using the waste oil transfer pump. The engine room bilge pump discharge is also connected to the waste oil transfer pump discharge for discharging the bilge to the shore.

Bilge Separator Service Pump Maker : No. of sets : Type : Capacity : Rating : Waste Oil Transfer Pump Maker : No. of sets : Type : Capacity : Rating : Bilge Separator Maker : No. of sets : Type : Capacity : Taiko Kikai Industries, Ltd. 1 set USH- 50 5m3/h Taiko Kikai Industries, Ltd. 1 set Snake, horizontal 10m3/h at 0. 392MPa 440V, 5.5kW, 1,200 rpm Taiko Kikai Industries, Ltd. 1 set Snake, horizontal 5m3/h at 0.3431MPa 440V, 1.5kW, 1,200 rpm

3.8.1
Controls

Engine Room Bilge System


Notes : 1) 2) All movements of bilge water are to be recorded in the machinery oil record book. Before any bilges are pumped directly overboard, it must be ensured that no local or international anti-pollution regulations MARPOL will be contravened except where safety of the ship or personnel is involved. Bilge water should not discharge directly to sea except in an EMERGENCY. When using the fire and bilge pump for bilge duties it is imperative that the discharge line valve from the pump to the fire main is securely closed in order that no oily water can enter the fire main system which could subsequently be directed onto a fire.

The engine room bilge pump will automatically start and stop according to the level in each bilge well together with an automatically operated valve which will open and close by the level in respective bilge well. The low level switch on the bilge hold tank will stop the bilge separator service pump automatically. The waste oil transfer pump will automatically stop according to the high level in the waste oil settling tank. The select switches for the automatic operation are provided on ICAS.

3) 4)

Alarms Sensor FS Tag No. 742 Function Bilge wells (from tank top) Fwd - P&S Mid - P Aft FS 743 Bilge holding tank (from tank bottom) LAH LAH LAH -400 mm -150 mm -150 mm Set point

LAH 5,550 mm

FS

744

Sunken deck under main turbine LAH seating (from tank top) Separated bilge oil tank (from tank top) Clean drain tank (from tank bottom) E/R bilge pump long running LAH

-150 mm

FS

745

-500 mm

FS

746

LAH 1,900 mm

646

30 min.

3.8.1a

Engine Room Bilge System


XAH 897

FROM CARGO MACHI.RM FROM DRAIN INSPECTION TK UPP. DK UPP. DK TO WASTE OIL SETT. TK

(P)

(S)

TO HOLD BILGE EDUCTOR

UPP. DK

OIL CONTENT MONITOR F.W.


135VPJ

SHORE CONNECTIONS

40
40 40 40
127VPJ

UPP. DK
123VPJ 187VPJ

FROM WASTE OIL TRANS. PUMP 50 25 50


S

40

124VPJ

65

50

65

C
171VPJ 184VPD 126VPJ

100

FOR WASHING

FROM L.O.TRANS. PUMP

200

40

40

40

128VPJ 105VPH 130VPH

P
122VPJ

S.W.

121VPJ

250

BILGE SEP. SERV. PUMP


P
AS 644 SA 644

LAH 743

FS

FIRE & BILGE PUMP


RO
W/H

50

RO
637

112VPJ

TO FIRE MAIN 250

65

LO SLUDGE TK AIR VENT


897

BILGE DEP. SERV. PUMP AUTO STOP 644

40

130VPJ 149VPJ

102VPH

FS
(HIGH)

S.W.
013VPH

25
143VPJ

100
LONG RUN

100 65

088VPH

S.W. 50 50 50

40
133VPJ

40

131VPJ (LOW) 132VPJ

65

ASS 646

RO 646

RM 646

SA 646

XA 646

FROM F.W.TKS

ENG.RM BILGE PUMP


138VPJ 136VPJ 137VPJ 139VPJ

BILGE HOLD TK
40
125VPJ

115VPJ

P
250 250

40

C
100
LAH 745

145VPJ

65
089VPH

154VPJ

155VPJ

FS
S.W.

40
113VPJ

141VPJ

SEPARATED BILGE OIL TK FROM STEER.ENG.RM


50

65
TO W.O.TRANS.PUMP 50 150 50 250 50 50 50

50
250

FROM STEER.ENG.RM FROM EFP RM


FOR E/R BILGE PUMP ASS 646 LAH 742

194VPJ

109VPJ

108VPJ

193VPJ

120VPJ

165VPJ

105VPJ

162VPJ

186VPJ

192VPJ 103VPJ

191VPJ 101VPJ

110VPJ

100

FROM MAIN CONDR

200

FIRE

RO

637

RM

SA
637

111VPH

BILGE & G.S.PUMP


150
RO
637 FIRE

111VPJ

102VPJ

RO

637

RM

SA
637

185VPJ

65

65

50

50

50

50

50

50

ASS FOR E/R 646 BILGE PUMP

100

ASS FOR E/R 646 BILGE PUMP LAH 742

ASS FOR E/R 646 BILGE PUMP LAH 742

50

50

50

65

150

50

FS

B.W. (AFT) VOID SPACE B.W.(P) VOID SPACE SUNKEN CLEAN DRAIN TK B.W.(S) VOID SPACE B.W.(P)
ECO.SOUND/MAGNETIC LOG COMP.

150

(P)

(S)

FS

FS

114VPJ

FS

FS

150

DK SUNKEN

200

FS

LAH 742

LAH 744

LAH 746

VOID SPACE

50

3.8.2

Bilge Separator
Alarms Taiko Kikai Industries, Ltd. 1 set USH- 50 5m3/h The bilge water collected into the bilge holding tank is treated by the bilge separator, and the treated water contained oil at less than 15ppm is discharged to overboard. When the oil content exceeds 15ppm, the discharge water from bilge separator will be returned to the bilge holding tank for reprocessing. The bilge holding tank has primary section where three oil discharge valves at different height are provided. Two different height suctions for bilge separator are provided on the bilge hold tank, and whichever suction is used as required. Heating device is provided for the bilge holding tank. In case the heating device is used as required, take care the water temperature to prevent damage of tank inside painting. Sensor FS
Oil content

Bilge Separator Maker : No. of sets : Type : Capacity :

Tag No. 743 897

Function Bilge holding tank (from tank bottom) Bilge separator outlet oil content

Set point LAH 5,500 mm H 15 ppm

monitor

Bilge Separator Service Pump Maker : No. of sets : Type : Capacity : Rating : Taiko Kikai Industries, Ltd. 1 set Snake, horizontal 5m3/h at 0.3431MPa 440V, 1.5kW, 1,200 rpm

Notes : 1) All movements of bilge water are to be recorded in the machinery oil record book. 2) Before any bilges are pumped directly overboard, it must be ensured that no local or international anti-pollution regulations MARPOL will be contravened. 3) When not in use, the bilge separator is to be filled with water.

Bilge Separator Operation The separator complies with the IMO resolution MEPC 107(49) and is fitted with an oil content meter with an alarm. The purpose of the separator is to separate the oil from the bilge water so that the oil residues in the treated water do not exceed 15ppm before being discharged into the sea. The separating principle of the separator is based on the different specific gravities of oil and water. The rising velocity of oil globules in water is relative to their diameter, i.e. a 60 micron diameter oil globule will rise 195 micron/sec, where a 30 micron of it will rise 50 micron / sec. The separator reduces the shear on the oil particles and enables a plate pack to be used. Oil globules passing through the pack will make contact and coalesce on the oleophilic plates until the globules are large enough to rise up through the pack. The plate pack configuration allows solids drawn in with the liquids to gravitate down through the pack, to collect in the bottom. A service pump supplies the oily water through the separator. Probes fitted into the gravity chamber, monitor the oil and water levels and control pump and solenoid valves to give automatic operation of the unit. When the oil builds up to cover the lower probe in the gravity chamber the pump stops and two solenoid valves open, one connected to a clean water supply and the other on the oil discharge line. The oily water inlet solenoid closes and water pressure forces oil out from the top of the separator until upper probe operates. The oily water inlet solenoid then opens, the pump starts and the clean water inlet and oil outlet solenoids close. If air collects in the top of the separator, it is dealt with in exactly the same manner, since the probes detect a water / air inter face as they would a water / oil interface. The bilge separator service pump will also automatically stop according to the low level in the bilge hold tank. On / Off select switches for the automatic stop detectors are provided on ICAS. a) Ensure that the valves are set as follows. Position Open Open Closed Closed Closed Open Open Open Close Open Closed Description Bilge holding tank suction valve Bilge separator service pump suction valve Bilge separator service pump SW suction valve Bilge separator sampling valves Bilge separator drain valves Bilge separator bilge water inlet valves Bilge separator overboard valves Bilge separator recirculating valve Bilge separator washing water valve Oil content monitor supply valve Oil content monitor flush water valve Valve
131 or 132VPJ 133VPJ 088VPH

SAMPLE WATER

135VPJ 136 / 137VPJ 139VPJ


Operation Status
Standby Auto Test

15ppm BILGE SEPARATOR


Stain Of Detector Memory Status MODEL

Oil Alarm

Detect Alarm

POWER

FOCAS-1800

SAMPLE WATER
OFF ON

FRESH WATER

SOLENOID VALVE

CONTROL AIR

b) Start the bilge separator (Bilge separator service pump). c) Adjust the pressure in chamber by the pressure regulating valve in the discharge line. (The pressure is adjusted to approximately 0.1MPa.)
OIL DETECTOR

P
BILGE INLET

OIL DETECTOR

P
COALESCER FRESH WATER TEST COCK STRAINER

TEST COCK

TO SEPARATED BILGE OILTANK TO BILGE HOLD.TANK TO SEPARATED BILGE OILTANK

3.9.1

Domestic Fresh Water System

Distilling Plant Maker : No of sets : Model : Type : Capacity : Fresh Water Pump Maker : No. of sets : Type : Capacity : Rating : Drinking Water Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 2 sets Centrifugal, vertical 10 m3/h at 65 mth 440V, 11kW, 1,800 rpm Sasakura Engineering Co.,Ltd. 2 sets WX-45M (condensate cooled) EX-45E (sea water cooled) Low pressure, plate type 45 tons/day Water may be taken from a shore supply or a barge by means of water bunkering lines located on the port and starboard sides of the ship at the cargo manifold. Alternatively, the water can be filled directly from the filling cap fitted on top of each tank. Distillate discharged from the evaporator can be transferred to either the fresh water tank or the drinking water tank. Distillate which is to be pumped to the domestic water tanks is first passed through the silver ion sterilizer. Water supplied from ashore does not pass through the silver ion sterilizer and care must be taken to ensure that the water is fit for human consumption. The silver sterilizer destroys bacteria and leaves a residue of silver ions in the stored water thus providing for effective sterilization whilst the water is stored in the tanks. As the water passes between two electrodes in the sterilizing unit, through which a small current is passed, the ions are released and sterilize the water. Sterilization by this method ensures that the water is maintained in a good condition, even when stored in the tanks for a period of time. The silver electrodes should be inspected and changed when all the silver coating has depleted. The dosing of the water is automatic and is set depending on the flow of the water. The domestic fresh water is stored in the fresh water tank and the drinking water tank, which are located in the steering gear room on the starboard side and the levels are monitored by the ICAS. The fresh water hydrophore unit provides the ship with cold fresh water for sanitary water and technical services water. The fresh water hydrophore unit also supplies water to the calorifier and the hot water circulation pumps supply hot water from the calorifier to the accommodation. The drinking water hydrophore unit provides the ship with cold fresh water for drinking Water treatment is made by an ultraviolet sterilizer, and a mineral injection unit. The ultraviolet sterilizer is fitted in the drinking water supply line to the accommodation and domestic fresh water being supplied to end users will normally all flow through the ultraviolet sterilizer. The mineral is injected into the drinking water supply line to the ultraviolet sterilizer as required. Two (2) fresh water pumps, one Lead duty, the other Follow duty take suction from the fresh water tank and discharge to a fresh water pressure tank. Two (2) pressure switches (one for each duty) control the fresh water pump cut-in and cut-out in the automatic mode, to maintain the water level operating band. Initial charge, which sets the position of water level operating band, is supplied from the general service air system. Two (2) hot water circulating pumps and a hot water heater with steam heating, alternatively electric heater are installed in line of the hot water circulation. Top up to the system is from the hydrophore tank. The pumps can be changed over if necessary for maintenance. Pumps are started and stopped locally. Pumps should be changed over periodically in order to avoid one pump having excessive running hours. Caution When the steam heater is in use, the hot water temperature control valve which regulates steam flow to the heater should always be used. The by-pass valve should only be used with an operator in attendance and should be locked closed at all other times. Fresh water can be run down from the fresh water tank to replenish the stern tube cooling water tank as required. A distilled water tank recirculation pump, a fresh water tank recirculation pump and a drinking water tank recirculation pump are provided to prevent from freezing. Pumps are started and stopped locally as required. An interconnection with a spool piece is provided between fresh water tank and drinking water suction lines to secure the drinking water from fresh water tank in event of contamination of the drinking water tank. A fire fighting fresh water hydrophore unit provides the accommodation for first aid purpose. The fire fighting fresh water pump takes suction from the fresh water tank and discharges to a fire fighting fresh water pressure tank. A pressure switch controls the pump operation to keep the water level band. Initial charge air is also supplied from the general service air system.

Teikoku Machinery Works, Ltd. 2 sets Centrifugal, vertical 5 m3/h at 65 mth 440V, 5.5kW, 1,800 rpm

Hot Water Circulating Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 2 sets Centrifugal, horizontal 5 m3/h at 15 mth 440V, 1.5kW, 3,600 rpm

Fire Fighting Fresh Water Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 1 set Centrifugal, horizontal 5 m3/h at 110 mth 440V, 7.5kW, 3,600 rpm

Fresh Water Pressure Tanks Maker : Fresh water : Drinking water Fire Fighting Teikoku Machinery Works, Ltd. 1 m3,1 set 1 m3,1 set 1.5 m3,1 set

3.9.1

Domestic Fresh Water System


Hot Water System This system supplies the hot water to the accommodation for domestic purposes. Water is circulated continuously by one of the two the hot water circulating pump, the water being passed through a hot water heater, which can be either steam or electrically heated to raise the water to the correct temperature. Top up to the system is from the pressure tank. The pumps can be changed over if necessary for maintenance. Pumps are started and stopped locally and monitored on the ICAS. Pumps should be changed over periodically in order to avoid one pump having excessive running hours. The system supplies hot water to the accommodation system, the wash basin in the workshop and the laboratory wash sink in the engine room. Procedure for Operating the Hot Water System a) Operate the FW system as above and set the hot water system valves as follows : Position Open Open Open Open Description Hot water heater supply valve Hot water heater outlet valve Either hot water circulating pump suction valve Either hot water circulating pump discharge Valve
150VPG 166VPG 167 / 170VPG 165 / 169VPG

Procedure for Operating the Fresh Water System a) Check that there is sufficient water in the fresh water tank to meet the immediate demand. Open the fresh water tank suction valve 111VPG (212VPG). b) Check that the fresh water pressure tank outlet valve 121 (179, 127)VPG is closed. c) Vent the fresh water pressure tank and, using one of two FW pumps in local control, fill it until the water level gauge glass is a half full ; stop the pump. Suction valves 113 (118, 115)VPG and 114 (117)VPG for the fresh water pumps must be open together with the pump discharge valves. d) Connect an air hose to the pressure tank air valve to pressurize the hydrophore tank from the ships air supply system. The pressure tank gauge valves must be open. When the pressure tank is at the correct operating pressure close the air valves. e) Open the fresh water pressure tank outlet valve 121 (179, 127)VPG. The fresh water pressure tank is now operational and FW can be supplied to the various users. f) At the local control panel set both fresh water pumps to AUTO. The pump will start and operate in automatic mode with control from the pressure switches stopping and starting the pump as necessary. g) Carry out steps (a) thru (f) for the fire drinking water pumps and pressure tank applying valve numbers in bracket. h) Carry out steps (b) thru (e) for the fire fighting fresh water pump and pressure tank applying valve numbers of red color.

Controls Fresh Water and Drinking Water Pumps The fresh water pumps and drinking water pumps start and stop in response to pressure changes in respective pressure tank. The pumps are operated in a Lead and Follow mode. The operating pressures are as follows : 1) The Lead pump starts at a falling pressure of 550kPa and stops at a rising pressure of 650kPa. 2) The Follow pump starts at a falling pressure of 450kPa and stops at a rising pressure of 650kPa.

Fire Fighting Fresh Water Pump The fire fighting fresh water pump starts and stops in response to pressure changes in the fire fighting fresh water pressure tank. The pump starts at a falling pressure of 980kPa and stops at a rising pressure of 1,100kPa.

Mineral Injection Unit The supply valves are opened manually as required. The supply pumps are automatically started and stopped by the drinking water flow signal at Auto mode.

b) After opening the hot water system supply valve from the cold water system, allow the system to fill from the hydrophore tank. c) Ensure that the hot water circulating pump to be used is primed. d) Start one of the hot water circulating pumps at the local starter panel. e) Open the steam supply or switch on the electrical supply to the hot water heater, and set the system temperature. f) Check that the system is circulating correctly and that the temperature is maintained. g) Open the outlet valves to the hot water systems as required.

Alarms Sensor LT Tag No. 731 Function Fresh water tank level (from tank bottom) Drinking water tank level (from tank bottom) Distilled water tank level (from tank bottom) LAL Set point 1,500 mm

LT

732

LAL

1,500 mm

LT

733/734

LAL

1,500 mm

3.9.1a

Domestic Fresh Water System


40 FOR DK SERVICE 40 40 TO FOAM & CO2 RM TO E/G RM TO GAS BTL RM TO & FROM ACCOMMO.

TO FIRE HOSE REEL SYSTEM 10

65

25

10

10

40
108VPG 107VPG 101VPG 110VPG

25

15

15

40

40
LI
LAL 734 LM 734

65
S

159VPG

162VPG

FOR INCI.

FOR BLR

40
S

GAS SEAL W.POT


15
155VPG

NO.2 DIST.W.TK

NO.1 DIST.W.TK

LI
LAL 733 LM 733 SAH 912

NO.2
FI
104VPG

SAH 912

NO.1

10 15

154VPG

CASING
TO D/G COOL F.W. EXP TK 10

CCS F.W. EXP.TK

FI
184VPG 136VPF 135VPF 183VPG 105VPG

DIST.PLANT
P

DIST.PLANT
P

193VPG

40

65

40 65 65

BASIN(LABO)
40 40 40 40 50

BASIN(W/S)
SHOWER (CHEMICAL STR)

DIST.W. TK RECIRC.PUMP

25 65 CONDS.W.LINE 40
174VPG

DIST.W.PUMP

25

DIST.W.PUMP

65

40
166VPG

TAH 870

40 25

10 15

B.W.

10 15 10

B.W.

40

173VPG

HOT.W.HTR

40 40 40
150VPG

FOUNTAIN
148VPG

172VPG

SILVER ION STERILIZER


65 (2)

40

40

65

40

169VPG

165VPG 170VPG

10
167VPG

153VPG 152VPG 149VPG 146VPG 143VPG 145VPG 143VPG 145VPG

RM 627

2ND DK (P) 2ND DK (S) 3RD DK (P) 3RD DK (S) 4TH DK (P) 4TH DK (S) LOWER FLOOR (P) LOWER FLOOR (S)

NO.2
RM 629

NO.1

40

10 10 10 10

40
207VPG 206VPG

FIRE FIGHT.F.W.PUMP
40
ASS 630 SA 630 RO FIRE RM 630

HOT W.CIRC.PUMP
PS
630

40

SA 629

LI
LAL 731 LM 731

LI

DRINK.W.TK

F.W.TK

C
LAL 731 LM 731

P
119VPG 127VPG

FIRE FIGHT F.W.PRESS.TK


40 (2)

40

115VPG

10 10

40

DIST.W. TK 182VPG RECIRC.PUMP

212VPG

111VPG

181VPG 114VPG

TO LOCAL FIRE EXT.SYS.


627

40

10 40

50 50 65

NO.2
C P

TO I.G.G 10 10 6 TO DIST.PLANT CHEMICAL DOSING UNIT

40

PS PS
113VPG

F.W.PRESS.TK
121VPG

DK SERV. (AFT)
50

25

10

F.W. TK RECIRC.PUMP

65

196VPG
SPOOL PIECE

197VPG

50 40

50

NO.1
SA 627 RM 627 RO 627

STERN TUBE COOL.F.W.TK


116VPG

ASS 627

FRESH W.PUMP
C P

(2)

142VPG

BILGE SEPA. OIL CONT. MONITOR

50 40

118VPG

MINERAL INJECT.UNIT
XA 870

NO.2
MINERAL

187VPG

100

186VPG

MINERAL

PS PS

DRINK.W. PRESS.TK
179VPG

178VPG

40
177VPG 131VPG
S S S

15

176VPG

40
185VPG

117VPG

FS UV STERILIZER
(2)

NO.1 DRINK. W.PUMP

L.O. PURIF.

65

100 TO BILGE & G.S.PUMP

ASS 628

SA 628

RM 628

RO 628

10
FOR D/G

NOTE: (2) TO CLEAN DRAIN TANK

156VPG

157VPG

158VPG

TO BILGE WELL

3.9.2 Sewage Treatment System


Sewage Treatment Plant Maker : No of sets : Model : Type : Capacity : Discharge pump : Aeration blower : Taiko Kikai Industries, Ltd. 1set SBT-40 Biological oxidation 2,400 litres/day 4.0 m3/h at 20 mTH 0.6 m3/min at 20kPa Sewage Treatment Unit The type SBT-40 unit fitted is rated at 40 men / day. Its design complies with USCG Regulation 33 CFR 159 (1975) and has been certified by the UK DOT under IMO Resolution MEPC2 (VI). The unit purifies sewage by the extended aeration activating sludge method, the discharges a sterilized effluent overboard. Effluent has the following qualities : Suspended soils : Coliform bacteria : Biochemical oxygen demand (BOD) : less than 50 mg / liter less than 200 MPN / 100 ml less than 50 mg / liter The vacuum level is controlled by the vacuum switch, which is located on to the manifold of the vacuum piping. The vacuum switch is set to start pump at -35 to -40kPa and stop the pump at -50 to -60kPa. In multiple ejector system, the starting ejector alternates continuously by starting turn of the pump changes. The ejector pump is used for discharging the collecting unit either to sewage treatment unit or overboard. The discharge operation is controlled automatically with level switches. Vacuum Toilet Collecting Unit The vacuum toilet system uses vacuum for sewage transport from toilets to the sewage collecting tank. The vacuum can be created by sewage powered ejectors. The vacuum toilet connected to the piping system use only 0.6 to 1.2 litres of water per flush. Rinse water valve, discharge valve and control mechanism are integrated into toilet bowl.

Vacuum Toilet Collecting Unit Maker : No of sets : Model : Capacity : Discharge pump : EVAC Oy,Finland 1set 0121 EASYFIT 5m3 4.8kW

The sewage from toilets flows into the bio-filter chamber. Foreign objects which could obstruct operation of the device are held from entering the device by a screen. Air from the blower causes circulation of the liquid and brakes up the solids then it also supplies oxygen to the microorganisms attached to the packing media.

Introduction In 1973, the Inter-governmental Maritime Consultative Organization held an international conference from which arose the International Convention for the Prevention of Pollution from Ships. Annex IV of that document dealt with the prevention of pollution by sewage from ships. Sewage is defined as : 1) Drainage and other wastes (black water) from any of toilets, and WC scuppers. 2) Drainage from medical premises (hospital etc.) via wash basins, wash tubs and scuppers located in such premises. 3) Other waste waters (gray water), when mixed with drainages defined above. Normally, sewage may be discharged into the sea only as effluent from the working sewage treatment plant, and then only if the effluent does not produce visible floating solids and does not discolour the water. (Note : When the sewage is mixed with wastes or waste waters having different discharge requirements, the more stringent requirements will apply.) Soil pipes from WCs are gathered into a main line connected to a sewage vacuum toilet collecting tank unit. In the event of plant failure or other emergency, provision is made for discharging the sewage directly overboard or for receiving it to the vacuum tank.

The partially treated sewage in the bio-filter chamber flows into the sterilizing compartment. This liquid is thoroughly disinfected as it washes against the chemical sterilizing tubes in the compartment.
SEWAGE TREATMENT UNIT

The treated water is collected in the sterilizing compartment then discharged overboard by discharge pump automatically with high and low float switches. The high level is alarmed on the ICAS. CAUTION Raw sewage may only be pumped to sea in waters where such discharge is permitted and permission from the bridge must be obtained before the discharge takes place. It should be noted that the sewage treatment plant requires a throughput of raw sewage to keep the bacteria active. If there is no sewage flow for a prolonged period the bacteria will become inactive and operation of the plant subsequently impaired. When raw sewage supply is resumed it may take some days before full bacterial activity is restored and this can result in imperfect treatment and the discharge of untreated sewage. When operating in restricted waters or in harbour, the sewage treatment plant discharge pump must be switched off and the overboard discharge valve 208 / 288VPJ closed. Ensure the shore connection valves 289 / 290 / 271 / 272VPJ from the sewage / vacuum toilet and discharge pumps have been closed firmly. To facilitate maintenance, a connection from the fire main system has been provided to the sewage treatment plant.

SEWAGE

STERILIZER LEVEL PROBE

VENT

OVER FLOW

SCREEN

PACKING MEDIA STERILIZATION COMPARTMENT BIO FILTER TANK DISCHARGE PUMP AERATION BLOWER

OVERBD DISCHARGE AIR SCORE PIPE

CLEANING WATER

3.9.2a Sewage Treatment System


REF.CHAMBER DRAIN

CABIN DRAIN

SOIL

SUEZ WORKER'S RM

COMM. LAV. HWB

CORR. D W F

GARBAGE STR

HOSPITAL & DISP.

F U

W T

W M

W M

F U

F U

F U

F U

F U

80

80

S UPP.DK

50

50

50

50

SOIL

DECK W/S

HOTEL LAUNDRY

OFF'S/CREW'S CHANGE RM

284VPJ

223VPJ

222VPJ

221VPJ

211VPJ

50
272VPJ 271VPJ 290VPJ 289VPJ

50

PS
80

80

65
288VPJ

150

100

80

CABIN DRAIN
100

FUNNEL

DISPOSER

150

65

282VPJ

25 100
287VPJ

50

FS
210VPJ 209VPJ

LAH 747

XA 899 TROUBLE

65

FS

118VPH

80

204VPJ

VACUUM UNIT TK

XA 898 TROUBLE

FS FS FS

LAH 898

ES 898

208VPJ

207VPJ

206VPJ

80
205VPJ

PUMP START 898 PUMP STOP C P

25

50

50

201VPJ

203VPJ

120VPH

80

202VPJ

25 25
119VPH

25
117VPH 285VPJ 286VPJ
ASS 898

150

VACUUM TOILET SYSTEM

FROM FIRE LINE PRESSURIZING PUMP

SEWAGE TREAT.UNIT

SEWAGE DISCH. PUMP

PART 4 : MAIN MACHINERY AND CONTROL


4.1 Control Room
4.1.1 4.1.1a Machinery Control Room Overview Machinery Control Room Console

4.3

Main Boiler
4.3.1 4.3.2 4.3.3 4.3.4 Main Boiler Overview Main Boiler Operation Burner Characteristics Boiler Control Systems Main Boiler Overview Main Boiler Mounting System Combination Burner System Boiler Pressure Rising Charts Combustion Air, Seal Air and Flue Gas System Burner Characteristics Burner Assembly Boiler Gauge Board Automatic Combustion Control (ACC)

Illustrations

4.2

Main Turbine
4.2.1 4.2.2 4.2.3 4.2.4 4.2.1a 4.2.1b 4.2.1c 4.2.2a 4.2.3a 4.2.3b 4.2.4a Main Turbine Overview Main Turbine Operation Main Turbine Control System Main Turbine Warming-up System Main Turbine Overview Main Turbine Overview Main Turbine Gear Arrangement Main Turbine Operation Main Turbine Remote Control System Main Turbine Control System Main Turbine Warming-up System

Illustrations
4.3.1a 4.3.2a 4.3.2b 4.3.2c 4.3.2d 4.3.3a 4.3.3b 4.3.4a 4.3.4b

Illustrations

AUTO. TEL.

I. S. TEL.

OPSM8

OPSM7

OPSM6

OPSM5

M/T REMOTE CONTROL SUB PANEL FOR MCR


PHONTECH
MITSUBISHI HEAVY INDUSTRIES, LTD.
NAGASAKI SHIPYARD & MACHINERY WORKS

M/T CONTROL & TELEGRAPH LEVER

WATCH POSOTION
CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS

WATCH POSOTION
CAS CAS CAS CAS CAS CAS CAS CAS

2 1 12

3 45

11 910

EMERG. TRIP BYPASS

AUTO SLOWDOWN

ASTERN

AHEAD

CONT. METHOD

MATCHING IND.

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

PRE WARNING

EMERG. TRIP

PRE WARNING

ACT

DEC.

INC.

DEC.

INC.

DIRECT

LEVER

MATCHING
(W / H - MCR)

ENG OPE SYS

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

ENG
ON OFF

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

ENG
ON OFF

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

ENG
ON OFF

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

1 4
ON OFF

F P R T

PUSH TO TRIP

REQUEST

BY-PASS DEC INC DEC INC NOR BYP-ASS

MATCHING
(CCR- MCR)

OPE

SYS
TAB DETAIL
CUSTUM GRAPHIC MONITOR MENU CONTROL MENU SYSTEM MENU ALARM SUMMARY EVENT SUMMARY

OPE

SYS
TAB DETAIL
CUSTUM GRAPHIC MONITOR MENU CONTROL MENU SYSTEM MENU ALARM SUMMARY EVENT SUMMARY

OPE

SYS
TAB DETAIL
CUSTUM GRAPHIC MONITOR MENU CONTROL MENU SYSTEM MENU ALARM SUMMARY EVENT SUMMARY

TAB DETAIL SHIFT F1

CUSTUM GRAPHIC

MONITOR MENU

CONTROL MENU

SYSTEM MENU

ALARM SUMMARY

EVENT SUMMARY

IMPOSSIBLE

NOR

BYP-ASS

F2

F3

F4

F5

F6

F7

F8

F9

F10

ACKNOWLEDGE

SHIFT

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

SHIFT

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

ACKNOWLEDGE

SHIFT

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

*
EXEC

TURN TO RESET

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EXEC

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EXEC

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EXEC

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EMERG. TRIP BY-PASS

PROGRAM CONT.

AUTO SPIN

PLANT MODE

1 SELECT

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

7 4 1 0

8 5 2 .

9 6 3

DEL

CANCEL SELECT

7 4 1 0

8 5 2 .

9 6 3

DEL

CANCEL SELECT

7 4 1 0

8 5 2 .

9 6 3

DEL

CANCEL SELECT

7 4 1 0

8 5 2 .

9 6 3

DEL

CANCEL

SOOT BLOWER EMCY RETRACT

2 SELECT

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

BYPASS POSSIBLE

BY-PASS

IN PROGRESS

BY-PASS

START

BY-PASS

MANEUV.

FULL AWAY

BS

SELECT

BS

SELECT

BS

SELECT

BS

O
SWAP Boiler FO FO

P
LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

ALARM ACK

O
SWAP Boiler FO FO

P
LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

ALARM ACK

O
SWAP Boiler FO FO

P
LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

ALARM ACK

O
SWAP Boiler FO FO

P
LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

ALARM ACK

ENT
V
CLOSE Air

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

BUZZER STOP
BZ STOP

ENT
V
CLOSE Air

ENT
V
CLOSE Air

SPACE

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

SPACE

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

BUZZER STOP
BZ STOP

ENT
V
CLOSE Air

NOR

BY-PASS

SAFETY SYSTEM

NOR

BY-PASS

NOR

BY-PASS

RPM CONT.

BZ STOP

SPACE

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

SPACE

BZ STOP

POWER FAIL

SYSTEM FAIL

ON

BY-PASS

NO2 BOILER EMCY TRIP

NO1 BOILER EMCY TRIP

OVER SPEED PREVENTER


OCR

CONT. POSITION

TURNING GEAR

LAMP TEST

ON

MCR

W/H

W/H

CCR

DISENGAGE

ENGAGE

MCR

M/S

NO2 BOILER EMCY TRIP

NO1 BOILER EMCY TRIP

GAS BURN EMCY STOP

MANEUV. TABLE

4.1.1 Engine Control Room Overview

The machinery control room, situated on the 2nd deck, is where the necessary equipment and controls are located which allow the centralized operation and supervision of the engine room machinery, via the Integrated Control and Automation System (ICAS).

4.1.1 MACHINERY CONTROL ROOM OVERVIEW

FIRE SHELTER

UP

UP

72

74

WINDOW

12

1. 2. 3. 5. 7.
Tab Caps Lock Ctrl Esc
| |

ICAS MAIN TURBINE REMOTE CONTROL PANEL ICAS MACHINERY ALARM PRINTER

ICAS NO.2 MACHINERY CABINET

MACHINERY CONTROL CONSOLE ICAS NO.1 MACHINERY CABINET

43

LIFT

42

46

20

8. ICAS MACHINERY LOG PRINTER 9. ICAS COLOR HARD COPIER 11. MACHINERY CONTROL CONSOLE SERVICE TRANSFORMER 12. AC220V FEEDER PANEL 20. VIBRATION MONITOR PANEL

ENGINE CONTROL ROOM LAYOUT

42. 43. 46. 72. 74.

NO.1 BLR FLAME SCANNER AMPLIFIER PANEL NO.2 BLR FLAME SCANNER AMPLIFIER PANEL OIL MIST DETECTION PANEL SMS VDU SMS PRINTER

11

Shift

! 1 Q

A Z S

" 2 W

F1

Alt Alt Gr Ctrl / / End Enter

X E D C F V T G B H N J M K < , O L > . P : ;
|

F2

$
%

4 R 5 6 Y U I
{ [

F3 F4

^
F5 & F6 F7
(

7 8 9 0 -

*
F8
)

F9

@ ' ?
~ # Shift

F10

+
Sys Rq Break

=
} ]

F11

Back space Insert Home Page Up

Enter Delete End Page Down

F12 Print Screen Scroll Lock Pause

Num Lock

Home

Ins Del

Num Lock

2
PgDn

Caps Lock

PgUp

Scrol Lock

4.1.1a

Engine Control Room Console

AUTO. TEL.

I. S. TEL.

OPSM8

OPSM7

OPSM6

OPSM5

M/T REMOTE CONTROL SUB PANEL FOR MCR


PHONTECH
MITSUBISHI HEAVY INDUSTRIES, LTD.
NAGASAKI SHIPYARD & MACHINERY WORKS

M/T CONTROL & TELEGRAPH LEVER

WATCH POSOTION
CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS CAS

WATCH POSOTION
CAS CAS CAS CAS CAS CAS CAS CAS

3 4 5

2 1 12

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

11 10 9

EMERG. TRIP BYPASS

AUTO SLOWDOWN

ASTERN

AHEAD

CONT. METHOD

MATCHING IND.

PRE WARNING

EMERG. TRIP

PRE WARNING

ACT

DEC.

INC.

DEC.

INC.

DIRECT

LEVER

MATCHING
(W / H - MCR)

ENG OPE SYS

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

ENG
ON OFF

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

ENG
ON OFF

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

ENG
ON OFF

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

1 4
ON OFF

F P R T

PUSH TO TRIP

REQUEST

BY-PASS DEC INC DEC INC NOR BYP-ASS

MATCHING
(CCR- MCR)

OPE

SYS
TAB DETAIL
CUSTUM GRAPHIC MONITOR MENU CONTROL MENU SYSTEM MENU ALARM SUMMARY EVENT SUMMARY

OPE

SYS
TAB DETAIL
CUSTUM GRAPHIC MONITOR MENU CONTROL MENU SYSTEM MENU ALARM SUMMARY EVENT SUMMARY

OPE

SYS
TAB DETAIL
CUSTUM GRAPHIC MONITOR MENU CONTROL MENU SYSTEM MENU ALARM SUMMARY EVENT SUMMARY

TAB DETAIL SHIFT F1

CUSTUM GRAPHIC

MONITOR MENU

CONTROL MENU

SYSTEM MENU

ALARM SUMMARY

EVENT SUMMARY

IMPOSSIBLE

F2

F3

F4

F5

F6

F7

F8

F9

F10

ACKNOWLEDGE

SHIFT

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

SHIFT

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

ACKNOWLEDGE

SHIFT

F1

F2

F3

F4

F5

F6

F7

F8

F9

F10

*
EXEC

NOR

BYP-ASS

TURN TO RESET

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EXEC

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EXEC

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EXEC

CSR SET

FOCUS

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

EMERG. TRIP BY-PASS

PROGRAM CONT.

AUTO SPIN

PLANT MODE

1 SELECT

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

7 4 1 0

8 5 2 .

9 6 3

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

DEL

CANCEL SELECT

7 4 1 0

8 5 2 .

9 6 3

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

DEL

CANCEL SELECT

7 4 1 0

8 5 2 .

9 6 3

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

DEL

CANCEL SELECT

7 4 1 0

8 5 2 .

9 6 3

DEL

CANCEL

SOOT BLOWER EMCY RETRACT

2 SELECT

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

BYPASS POSSIBLE

BY-PASS

IN PROGRESS

BY-PASS

START

BY-PASS

MANEUV.

FULL AWAY

BS
ALARM ACK

SELECT

BS
ALARM ACK

SELECT

BS
ALARM ACK

SELECT

BS
ALARM ACK

O
SWAP Boiler FO FO

P
LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

P
FO LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

O
SWAP Boiler FO FO

P
LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

P
FO LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

ENT
V
CLOSE Air

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

BUZZER STOP
BZ STOP

SWAP

Boiler FO

ENT
V
CLOSE Air

ENT BZ STOP
V
CLOSE Air

SPACE

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

SPACE

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

BUZZER STOP
BZ STOP

SWAP

Boiler FO

ENT
V
CLOSE Air

NOR

BY-PASS

SAFETY SYSTEM

NOR

BY-PASS

NOR

BY-PASS

RPM CONT.

SPACE

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

SPACE

BZ STOP

POWER FAIL

SYSTEM FAIL

ON

BY-PASS

NO2 BOILER EMCY TRIP

NO1 BOILER EMCY TRIP

OVER SPEED PREVENTER


OCR

CONT. POSITION

TURNING GEAR

LAMP TEST

ON

MCR

W/H

W/H

CCR

DISENGAGE

ENGAGE

MCR

M/S

NO2 BOILER EMCY TRIP

NO1 BOILER EMCY TRIP

GAS BURN EMCY STOP

MANEUV. TABLE

RPM
OPSM8 OPSM7 OPSM6 OPSM5 COMMON BUZZER MONITORING FUNCTION STATUS

No1. D.W.L.

No2. D.W.L.

50 100 120 ASTERN

50 100 120

SECOND ADJUSTER

min-1
rpm

AHEAD

TEL-TAIL CUT SWITCH

PORTAL MAN ALARM

ENG.CALL
WATCH DUTY POSITION SELECT

SPM IND

RUDDER ANGLE

START

ALARM

KYMA
ENGINEER ALARM SYSTEM SWITCH REPEAT BZ STOP

PERFORMANCE MONITORUNG

ASTERN VALVE

AHEAD VALVE

FIRE ALARM SWITCH

GENERAL ALARM SWITCH

F1

F2

F3

F4

F5

KDU-110

CONSOLE POWER SUPPLIES LAMP/BUZZER TEST

TALK BACK SYS (MACH)

4.2.1 Main Turbine Overview


Specification
Maker : Type : Mitsubishi Heavy Industries Ltd MS36-2A cross-compound, impulse/reaction HP turbine: one two-row Curtis and seven Rateau stages LP turbine: four Rateau stages and four reaction stages Astern turbine: two two-row Curtis stages Output : HP turbine speed : LP turbine speed : Propeller speed : Natural frequency Critical speeds : Overspeed trip : Steam condition : Direction of rotation : Astern maximum continuous speed : Steam bleed off : Maximum Normal - 23,600kW - 23,600kW

Descriptions
Turbines The turbines are the cross-compound, impulse reaction type, consisting of high and low pressure turbines. Steam is supplied from the main boilers at 5.88MPaG at 510 at full away. The steam enters the turbine through the main steam piping, main steam strainer and stop valve. For ahead operation, the steam is supplied to the high pressure (HP) turbine through the nozzle group composed of five nozzle valves which are controlled sequentially for power setting of approximately 100%, 90%, 75%, 50% and 20% . The HP turbine is of the impulse single-flow type. The steam flows across the two-row Curtis stages and eight Rateau stages and then to the exhaust chamber at the aft side of the HP turbine. From the HP turbine the steam flows through the cross-over pipe to the low pressure (LP) turbine. The LP turbine is of the impulse reaction single-flow type in which steam flows towards the forward side through the steam chest, transfers its energy to four Rateau stages and four reaction stages and then exhausts into the main condenser. The astern turbine is of the impulse type, arranged at the forward end of the LP turbine. Steam enters through the astern manoeuvring valve, astern guardian valve, and transfers its energy to two, two-row Curtis stages, towards the aft side, and exhausts into the main condenser. For emergency independent operation of the LP or HP turbine, the flexible coupling should be removed and the cross-over piping changed for the emergency piping (See 9.3 Solo Running of the Main Turbine). The seals are formed by radially slotting sections of labyrinths into the packing rings, which themselves are likewise slotted into the turbine upper and lower casings. The peak and trough edges of these labyrinths are located adjacent to corresponding square radial grooves machined into the rotor shaft. The clearances between the labyrinth edges and the rotor are minimized to reduce steam leakage between the inner (high gland steam pressure) areas and the outer (low gland steam pressure) areas. Adequate axial clearance between the rotor and labyrinths allow for the designed axial movement and expansion between the rotor and the casing. Steam at about 0.02MPaG is supplied to the glands from a gland steam receiver mounted underneath the turbine. Where the internal steam pressure is higher than the pressure in the gland housing, steam will enter the series of diaphragms from the turbine, and is effectively throttled across each stage causing its pressure to drop. The final very low pressure steam is led away to the gland steam condenser. Where the pressure in the gland housing is greater than the internal turbine pressure at the shaft exit point, the steam available from the gland steam receiver will be drawn through the gland, effectively sealing it and preventing the ingress of air. The gland steam receiver releases excess steam through a control valve to the main condenser or receives steam from a make-up controller supplied from the HP exhaust steam range. The need for the steam to make-up or spill changes with the turbine load, i.e. at high load the steam will generally be spilled out of the system and at low loads the packing steam will need to be made up.

5,722rpm at MCR 3,449rpm at MCR 80 rpm at MCR HP turbine: 60.4 rpm, 1st: 21.1 rpm, 110 % MCR ( 88 rpm ) 5.88 MPaG and superheated at 510 Clockwise, looking from aft 56 rpm for a maximum of 2 hours abt. 8,095kW HP : HP turbine 4th stage IP : Crossover pipe LP : LP turbine 3rd stage LP turbine: 52.9 rpm 2nd: 35.0 rpm 3rd: 198.4rpm

Main gearing : Main LO pump : Main condenser :

Double helical, tandem articulated, double reduction gear Main turbine driven, gear type Capacity : 150 m3/h at 0.294 MPaG Single pass reheating surface type Cooling surface: 2,860 m2 Tube size : Diameter 19 mm, thickness 0.7 mm Vacuum : 722 mmHg at NCR with sea temperature of 27 Cooling water flow: 15,820m3/h

Gland Steam Condenser The gland condenser is a horizontal, straight tube type with the gland exhaust fan mounted on top. It has cooling tubes through which the main condensate is passed to act as the cooling medium. Turbine gland leakage steam and air is collected in the gland condenser. Air and non-condensible gases are drawn out and exhausted by the fan. Condensate passes through a loop seal and drains to the atmospheric drains tank.

Vacuum pump :

Water sealed rotary type Suction Vacuum: 722 mmHg Capacity : 4.5 SCFM Gland Steam Labyrinth type seals are used at the both ends of the turbine rotors to prevent the steam in these regions from leaking to atmosphere and more importantly, to prevent air from entering the turbine where the internal pressure is less than atmospheric.

Gland condenser : Gland exhaust fan : Dehumidifier :

Horizontal shell and tube type Cooling surface: 20 m2 Capacity : 7 m /min. at 300mmAq Desiccant type Capacity : 50 m3/h
3

Vacuum Pump The vacuum pump unit consists of a motor driven rotary type vacuum pump, a seal water tank and a seal water cooler. Non-condensed air is extracted from the main condenser by pumping up and exhausted to atmosphere through the seal water tank. Seal water is supplied from the condensate water line and regulated by a float type operating valve integrated in the seal water tank. The seal water is cooled by a shell and tube type cooler with sea water.

4.2.1 Main Turbine Overview


Main Condenser The main condenser is a surface cooled, radial-flow type with a dump steam chamber. It is mounted directly below the LP turbine at right angles to the axis of the turbine and the condenser neck is bolted directly onto the turbine exhaust flange. Thermal expansion of the upper part of the condenser in the longitudinal direction is accommodated by the deflection plate, fitted at the forward side of the condenser. The condenser shell, hotwell, water chambers and dump steam chamber are all fabricated from steel plate and welded together. The internal surfaces of the water chambers are lined with neoprene with sacrificial anodes fitted to help prevent corrosion. The condenser tubes are arranged for radial flow of the steam across them. The air extraction box is positioned at the centre of the tube nest. Steam entering the condenser is guided around the boundary between the tube nest and the shell, and then towards the centre of the tube nest. Condensate flows down into the hotwell at the bottom of the condenser, from where it is pumped out by the main condensate pump. The water level in the hotwell is maintained by recirculating the condensate from gland condenser outlet back into the hotwell. The condenser is of the regenerative type, whereby the steam entering the condenser gives up some of its heat to the condensate. This is achieved by guiding the steam flow as described above. This also has the added advantage of deaerating the condensate. The air and non-condensable gases enter the air extraction box at the centre of the tube nest from where they are removed by the vacuum pump. The dump steam pipe is led into the condenser, the steam being water sprayed on entry in order to cool it, preventing thermal damage to the tubing due to local overheating. Cooling sea water is supplied by a main circulating pump and when at sea and conditions are normal, by a scoop system (See 3.5.1 Sea Water Circulating Systems). Gearing The reduction gearing between the turbine and propeller is a double reduction, tandem articulated type. The reduction gear consists of two first pinions, two first gear wheels, two second pinions and one second gear wheel. Both the HP and LP turbines are connected to the first pinions of the reduction gear by flexible couplings. The pinions drive the first reduction gear wheels. The first reduction gear wheels are connected through flexible shafts fitted with flexible couplings to the second reduction pinions, which drive the second-reduction gear wheel or main gear wheel. The main thrust bearing is located in a separate casing aft of the main reduction gear. An 11kW 1,730 rpm reversible motor driven turning gear of planetary type is provided and mounted at the aft end of the driving shaft, which is connected to the HP first reduction pinion. Safety Device The control oil mechanism will trip the main turbine nozzle valves for ahead or manoeuvring valve for astern under the following conditions :
Tag No. 062 063 064 065 066 067 068 069 070 076 071 072 064 073 074 075

Lubrication The lubricating oil system (See 3.7.1 Main Turbine Lubricating Oil System) consists of one main turbine driven lubricating oil pump, two motor driven auxiliary lubricating oil pumps, a main lubricating oil strainer and bypass filter, a temperature control valve, a pressure regulator, two lubricating oil cooler, an emergency gravity tank and sump tank built into the hull. The main turbine driven LO pump supplies the turbine and gearing with oil when the turbine revolutions are above 68 rpm and the oil pressure is more than 0.11MPa. The motor driven LO pump will start when the revolutions are under 64 rpm, the oil pressure is below 0.095MPa or an abnormality occurs in the operation of the turbine driven pump. This is controlled by the ICAS graphic screen LO Main Turbine. Oil is drawn from the main engine sump tank and discharged to each bearing and to the gear oil sprayers after passing through the main turbine LO filter, the oil cooler and temperature control valve. The oil returns to the hull sump tank. If loss of electrical power occurs the bearings are supplied from the turbine driven pump and the emergency gravity tank. Control oil to actuate the manoeuvring valves is supplied from the control oil pump.

Description Manual trip Overspeed HP turbine rotor excessive vibration LP turbine rotor excessive vibration HP turbine rotor position excessive displacement LP turbine rotor position excessive displacement Lubricating oil pressure low Control oil pressure low Main condenser vacuum low Main condenser hotwell level high Both boilers tripped Boiler steam drum water level high Boiler steam drum water level low Spinning overspeed Turning gear engaged Safety system power failure

Set Point

87.1 88.9 rpm

125 125 0.5 mm 0.5 mm 50 kPa 500 kPa


500 mmHgV

NOR+450 mm +240 mm -240 mm 12 rpm

These safety devices will not reset automatically when the cause of the trip is corrected. The trips are reset by pressing the RESET pushbutton. When the turning gear is engaged, interlocks it will prevent the main turbines steam nozzle valves and astern manoeuvring valve opening. The control oil mechanism will automatically slow down the main turbines under the following conditions :
Tag No. 082 083 084 085 086 087 088 089

Description Boiler steam drum water level high Boiler steam drum water level low Main steam pressure low Main steam temperature high Main condenser vacuum low One boiler tripped Stern tube temperature high Main condenser hotwell high

Set Point

+150 mm -150 mm 5.1 MPa 538


550 mmHgV

55 NOR+450 mm

4.2.1a

Main turbine Overview

MAIN CONDENSER

LP 2ND PINION

LP 1ST WHEEL

ASTERN GUARD. VALVE

ASTERN STEAM INLET

LP TURBINE
THRUST BEARING BLOCK ASTERN MANEUV. VALVE

LOCAL GAUGE BOARD

HP 1ST PINION

HP TURBINE

AHEAD EMERGENCY OPERATION

GLAND EXH. FAN

TURNING GEAR

CONTROL OIL PUMP UNIT GLAND CONDENSER HP TURBINE STEAM INLET

MAIN L.O. PUMP

AHEAD STOP VALVE

HP 2ND PINION

2ND WHEEL

HP 1ST WHEEL

4.2.1b

Main turbine Overview

4.2.1c

Main Turbine Gear Arrangement

SKELETON OF GEAR ARRANGEMENT

LP SIDE
1ST PINION

HP SIDE
1ST PINION FLEXIBLE COUPLING

CONNECT TO LP TURBINE

AHEAD
2ND PINION 2ND PINION

LP 1st FLEXIBLE COUPLING

FORWARD

1ST REDUCTION WHEEL GEAR

2ND REDUCTION WHEEL GEAR

1ST REDUCTION WHEEL GEAR

MAIN THRUST COLLAR

HP 1st FLEXIBLE COUPLING CONNECT TO HP TURBINE FLEXIBLE COUPLING

CONNECT TO MAIN LO PUMP

CONNECT TO TURNING GEAR

LOOKING FORWARD
1ST REDUCTION WHEEL GEAR

2nd FLEXIBLE COUPLING


2ND PINION

MAIN LO PUMP DRIVING GEAR (HP SIDE)

COUPLING SLEEVE

QUILL SHAFT

4.2.2 Main Turbine Operation


Procedure for Start-Up Successful operation of the turbine depends on the manner of the warming through, loading, stopping and cooling down of the turbines. Steam turbines are built and operate with very close tolerances in their structure, and the very nature of the driving medium can lead to problems associated with thermal expansion unless due care is taken. Correct warming through and proper drainage is essential together with careful handling of load changes. The preparation of the turbine for use is the responsibility of the operator. Correct loading up times are programmed into the turbine control system, as are the opening of the drain valves and bleeds. Should any of these functions need to be carried out manually, they should be done in the same manner as the automated function. g) Set up the main turbine lubricating oil system and control oil system, placing the valves as follows : Position Open Open Open Open Open Open Description Auxiliary LO pump discharge valves LO cooler inlet valve LO cooler outlet valve Automatic back flushing inlet and outlet LO coolers cooling water inlet valve LO cooler cooling water outlet valves
Valve

003 / 005VPK 006 or 007VPK 008 or 009VPK 016 / 018VPK 071 or 072VPH 075 and 073 or 074VPH

m) Warm through and drain the main superheated line from the boilers to the main turbine manoeuvring valve by opening the bypasses on the intermediate stop valves and raise the main turbine steam line to approximately 1.4MPa. Warm the line slowly by opening valve 075VPA, whilst continuing to turn the turbine using the turning gear. (See 4.2.4 Main Turbine Warming-up System Systems) n) Drain and warm through the supply steam line to the gland steam make-up system by crack opening the valve 057VPB to the system. Put the controller on automatic. Start the gland exhaust fan. Adjust the gland packing steam pressure so that it is about 0.02MPaG.

h) Vent any air from the LO coolers, then close the vent valves. i) Set the LO temperature controller to 44C from the ICAS graphic screen. Start one of the LO pumps from the same faceplate. j) Stop the gearing dehumidifier. k) Set valves for gravity tank supply and operation. Position Open Throttled Description Gravity tank quick-closing inlet / outlet valve Gravity tank overflow control valve
Valve

CAUTION
The gland packing steam will start to heat the turbine. It is therefore essential to keep the turbine turning gear in use and the LO system running to avoid localised heating. o) Ensure that the vacuum pumps are supplied with sealing and cooling water and start one pump. Observe the vacuum forming in the condenser, checking for leaks should this not take place at the normal rate or fail to achieve the rated vacuum of 720mmHg at a sea temperature of 27C.
015VPK 014VPK

Initial Checks and Preparation a) Start the cooling water systems (See 3.4.1 Central Fresh Water Cooling System) (See 3.5.1 Sea Water Circulating Systems) b) Check the water level in the main condenser hotwell. It should be higher than normal to allow for filling of the recirculating pipework. Top up as necessary from the distilled water tanks through outlet valves 135VPF or 136VPF, make-up valve bypass 144VPF and main condenser filling valve 145VPF. c) Prepare the main condensate system for operation (See 3.2.1 Condensate Water System) Ensure that both pump suction valves are open and that the recirculation system is ready for use. Start one of the condensate pumps with the discharge valve closed, then slowly open the valve. The condensate will be recirculated back into the condenser through the recirculation valve until the condenser receives water from other drains or exhaust. The level control ensures that the level in the hotwell remains constant, and that condensate is pumped up to the deaerator whilst still retaining the correct level. During this initial period of little drainage into the condenser, it is possible for the level to drop due to leakage up to the deaerator. The level in the hotwell will require monitoring and further topping up as necessary. d) Open the gland leak off valve between the main turbine and the gland steam condenser. e) Check and record the axial position of the rotors at the cold condition. f) Check the oil level in the main sump tank and top up as necessary, taking the amount of oil to be placed into circulation into consideration.

p) Open the isolating valves of spray water piston valve for astern operation. Maintain the warming through of the turbine and steam piping for at least one hour, raising the main turbine steam line pressure to full pressure on the bypass valves on the stop valves 001VPA and 002VPA. (Note : The high pressure turbine casing inside temperature should be kept over 200 before try-engine.) q) Start a control oil pump, and place the other on standby.

Check around the LO system for leaks. The level in the LO sump tank will drop as the system charges and may require topping up. A flow of oil should be observed returning from the LO gravity tank and the control oil tank sight glasses. It is good practice to observe gear sprayers and any other oil returns that can be accessed and viewed without loss of oil. The system oil pressures should be as follows : Main LO system : Control oil system : 0.10 - 0.15MPa 1.4 1.5MPa

CAUTION
If the ship is to be moved using tugs or any other means of external propulsion, disengage the turning gear. Failure to do so may damage the turning gear due to the propeller idling whilst under way. Ensure that the LO system is running. If the turbine is hot or gland steam is being supplied, the turbine must not be allowed to remain stationary for longer than 3 minutes, or the risk of the rotors deflecting exists. Ensure that the main turbine manufacturers instructions are followed before any tow is commenced.

l) Engage and start the turning gear. Observe the amps being drawn by the turning gear motor. If these are higher than normal investigate the turbine, gearing and shafting to determine why they are not turning freely.

CAUTION
Before proceeding to the next stage ensure that the main stop valve, the astern guardian valve and the ahead nozzle and astern manoeuvring valves are all CLOSED.

4.2.2 Main Turbine Operation


Testing the Engine Leaving Port Ensure that the cargo manifold pipes are disconnected before testing the engine. Inform the bridge and request confirmation that it is safe to turn the engine on steam. Ensure that the Chief Engineer is aware that the engines are about to be tested. a) Close the isolating valves of warm-up steam PCV (077/071VPA). b) Close the main turbine inlet valve 072VPA. c) Open the main steam stop valves 001/002VPA. d) Close the main steam stop valves bypass 001/002VPA. c) Disengage the turning gear. Run up to Full Speed after Manoeuvring Following manoeuvring, the turbine control system is set to full away on passage. The program controlling the turbine will slowly increase the speed through a pre-programmed ramp. The automatic drain valves will be closed at the beginning of the run up period. The bleed steam valves will open automatically at pre-programmed stages in the ramp allowing bleed steam into the systems they serve. Careful monitoring of the plant is required during this period of instability. The turbine must be observed and, should any vibration be detected, the turbine must be slowed down until they cease and then be investigated. This can be caused by rotor deflection due to poor warming up procedures. A period of running at revolutions below those at which the vibration started can lead to the deflection lessening. After a period of time the revolutions can be increased and the vibration monitored. Should this fail to rectify the situation, then the turbine will need to be stopped and further investigations instigated.

CAUTION
Do not allow the rotors to remain stationary for more than three minutes once the gland packing steam has been admitted. Failure to follow this advice could result in the rotors deflecting. e) In the MCR, reset the turbine trips at the Main Turbine Operation panel on the ECR console. f) Press the WARMING THROUGH pushbutton to restrict the propeller shaft to 12 rpm during turning on the DIRECT switch. g) Turn the main turbine astern and ahead a few times, using the DIRECT switch, to clear the steam lines of any condensation which may be present. The switch is turned in the INC. direction to open the ahead valve and in the DEC. direction to close the ahead valve and open the astern valve. Then in the INC. direction to close the astern valve until the Manoeuvring Valves Closed indicator light is lit. h) Turn the control mode switch to the LEVER position. While the control of this plant is highly automated and of modern design, there can be no substitute for good steam engineering practise. Ensure that the plant is physically checked, listened to and all senses used to detect early signs of problems. i) Upon completion of the tests, place the turbine in AUTOSPIN mode which will automatically turn the engine ahead and astern on steam until it is required.

Settings for the Turbine Automatic Sequence Description Drain piston valves open / close Astern guardian valve open/close 1st bleed valve open / close 2nd bleed valve open / close Astern water spray valve open / close Set Point Slow Ahead / Half Ahead Slow Ahead / Half Ahead 0.87 / 0.85 MPaG 0.30 / 0.25 MPaG While AST governor or maneuvering valve not fully closed

Securing the Turbine a) When finished with engines has been signaled, change over control to the MCR. b) Close the main and intermediate stop valves. Ensure that the manoeuvring and the astern guardian valves are closed. c) Ensure that all the drains have opened. d) Engage the turning gear and start the motor. e) Open the intermediate stop bypass valves to maintain the main steam pipes at the working temperature. Any further shutting down depends on the length of time the turbine is to be unused and any plans for maintenance. In many ports the engine is required to be on ten or thirty minutes notice.

4.2.2a Main Turbine Operation


START UP / SHUT DOWN OPERATIONS
START UP OPERATION
CHECK
STEAM, CONTROL AIR, ELECTRIC SYSTEMS MANOEUVRING, BLEEDER & DRAIN VALVES

4.2.2a

Main Turbine Operation

1
CONDENSATE WATER SYSTEM & SEA WATER CIRCURATING SYSTEM OPEN
SEA WATER INLET & OUTLET VALVES OF MAIN CONDENSER

SHUT DOWN OPERATION 2


LO SYSTEM
SEE 3.7.1

3
WARMING UP CHECK FINISHED ENGINE SLOW DOWN CHECK
BLEEDER VALVE: CLOSE DRAIN & ASTERN GUARDING VALVE: OPEN

CHECK
OIL LEVEL & TEMPERATURE IN LO SUMP TANK

CLOSE : MAIN STEAM STOP VALVE ASTERN MANOEUV. VALVE AHEAD NOZZLE VALVE ASTEAN GUARD. VALVE OPEN : DRAIN VALVES

SET
ASTERN GUARDING, DRAIN, BLEEDER & SPRAY WATER VALVES AUTO

OPEN
WATER BOX AIR VENT VALVE

OPEN
ALL VALVES FOR LO PIPING (EXCLUDING NORMALLY CLOSE

CHECK
MANUAL HANDLE P0SITION OF FOLLOWING VALVES ; OPEN : ASTERN GUARDING VALVE : DRAIN VALVES. : PACKING STEAM : MAKE-UP VALVE LOCKING POSITION: SPRAY WATER VALVES FOR STEAM DUMP AND ASTERN OPERATION

ENGAGE AND START


TURNING GEAR

STOP ENGAGE AND START

START
MAIN CIRCURATING PUMP

VALVES)

CHECK CHECK
CONDENSATE LEVEL IN THE CONDENSER HOT WELL (IF THE LEVEL IS LOW, SUPPLY MAKE-UP WATER) LO TEMPERATURE CONTROL VALVE

START
GLAND EXHAUST VALVE

TURNING GEAR (WITHIN 3 MIN. OF STOP)

CLOSE
DRAIN VALVES OF LO PIPING

OPEN
STOP VALVE FOR PACKING STEAM CONTROL VALVE (SUPPLY PACKING STEAM)

CLOSE
BOILER OUTLET INTERMEDIATE VALVE

START START
LEVEL CONTROLLER OF CONDENSER HOT WELL MOTOR DRIVEN LO PUMP

CHANGEOVER START
TO AUXILIARY CONDENSER FOR EXHAUST STEAM FROM AUXILIARIES GLAND EXHAUST FAN

CHECK
CLOSE : PACKING STEAM SPILL GATE VALVE CONDENSATE WATER SYSTEM & SEA WATER CIRCULATING SYSTEM

OPEN
AIR VENT VALVES OF LO PIPING

OPEN
SUCTION VALVES OF BOTH

START OPEN
COOLING WATER INLET & OUTLET VALVES OF LO COOLER VACUUM PUMP VACUUM PUMP

STOP KEEP
ABOUT 6 HOURS WHEN CONDENSER VACUUM DROPS TD ATMOSPHERIC PRESSURE

1 2

CONDENSATE PUMPS

OPEN L. O. SYSTEM CHECK


MANOEUVRING DEVICE THE VALVES FOR SHAFT & SUCTION VALVE SEAL WATER

6861.3 kPaa DURING WARM-UP

CHECK
LO FLOW TO EACH BEARING AND GEARS WITH SIGHT GLASSES

OPEN
BYPASS VALVE OF BOILER OUTLET INTERMEDIATE VALVE

CLOSE
STOP VALVE FOR PACKING STEAM CONTROL VALVE

START
MAIN CONDENSATE PUMP

CHECK
OIL LEVEL IN LO SUMP TANK

WARMING UP OPEN AUTO. SPINNING OF TRY ENGINE


(WITHIN 3 MIN. OF TURNING OPERATE) DELIVERY VALVES OF BOTH CONDENSATE PUMPS

WARM-UP
MAIN STEAM LINE CONDENSER

CHECK
NO MAKE-UP & SPILL TO MAIN

OVER FLOW FROM GRAVITY TANK DISCHARGE PRESSURE OF LO PUMP MAIN TURBINE INLET OIL PRESSURE

CONTINUE WARM-UP
AT LEAST ONE HOUR

STANDBY OPERATION

STOP
GLAND EXHAUST FAN

CHECK
OVERFLOW FROM CONTROL OIL TANK AND GOVERNOR HEAD TANK

END OF WARM-UP
STOP OPEN
CONDENSATE PUMP VACUUM PUMP SUCTION VALVE

START
CONTROL OIL PUMP

STOP & DISENGAGE CHECK


TURNING GEAR MAIN CONDENSER VACUUM ABOVE 5.07 kPaa

CHECK AGAIN
OVERFLOW FROM CONTROL OIL TANK

STOP
MOTOR DRIVEN LO PUMP

CLOSE
BYPASS VALVE OF BOILER OUTLET INTERMEDIATE VALVE

STOP AND DISENGAGE


TURNING GEAR

SET
MANOEUVRING LEVER POSITION: STOP EMERGENCY HANDLE POSITION: STOP

SLOWLY OPEN
BOILER OUTLET INTERMEDIATE VALVE

4.2.3 Main Turbines Control System 4.2.3 Main Turbine Control System
Maker : Mitsubishi heavy Industries Ltd

System Composition
The main turbine remote operating system has two modes of operation, LEVER and DIRECT. The position of the telegraph lever and a changeover switch determines the mode to be used. The turbine remote control system consists of the following :

Central Control Room (CCR) Main Turbine Control Console


The main turbine manoeuvring control console consists of the following : Telegraph receiver with manoeuvring lever Manoeuvring valve lift indicator Lever position indicator RPM indicator Revolution counter M/T REMOTE CONTROL SUB PANEL FOR CCR Sub panel
MITSUBISHI HEAVY INDUSTRIES, LTD.
NAGASAKI SHIPYARD & MACHINERY WORKS

Introduction
The turbine remote control equipment provides the interface between the operator and the main turbine, carrying out the commands in a preprogrammed sequence from consoles on the bridge (W/H), both wings, central control room (CCR) and the machine control room (MCR). The system is of the electro-hydraulic type which consists of the dual control main computer, electric and electronic circuits, process signal interface units, and the hydraulic servo mechanism of the actuator of the manoeuvring valve. The turbine remote control system is integrated into ICAS.

Main Turbine Remote Control Panel


The Main Turbine Remote Control Panel (MCB3) is housed in the MCR. The panel receives the commands signaled from the telegraphs and houses the components required to control the main turbine in accordance with the telegraph command. It consists of the control computer, mimic panel and miscellaneous electric and electronic signal circuits.

EMERG. TRIP BYPASS

AUTO SLOWDOWN

ASTERN

AHEAD

CONT. METHOD

MATCHING IND.

PRE WARNING

EMERG. TRIP

PRE WARNING

ACT

DEC.

INC.

DEC.

INC.

DIRECT

LEVER

MATCHING
(W / H - MCR)

Control Oil System


A control oil system is provided at the turbine and is independent of the main LO system. It is supplied by one of two pumps, one is duty and the other is standby. Control of the governor motor and solenoids which utilize the control oil to operate the manoeuvring valves, is carried out by the separate turbine management system operated through one of above positions. The turbine remote control system signal is converted to movement of an electric positioning of governor motor. This motor moves a pilot valve assembly which, by covering and uncovering ports, allows a flow of oil to the manoeuvring valves servo piston. The oil acting on the servo piston moves it in the desired direction and consequently moves the manoeuvring valve. The manoeuvring valves admit steam to the turbine at a rate dependant upon their position ahead or astern. Movement of the piston is fed back to the pilot valve assembly and when the piston has traveled the desired amount, the ports in the pilot valve assembly are covered and no further movement takes place.

PUSH TO TRIP

REQUEST

BY-PASS DEC INC DEC INC NOR BYP-ASS

MATCHING
(CCR- MCR)

IMPOSSIBLE

NOR

BYP-ASS

Wheelhouse Main Turbine Remote Control Console


The main turbine remote control console consists of the following : Telegraph transmitter with manoeuvring lever, which is moved to the desired turbine speed setting, ahead or astern, the command being processed and acted upon by the MTRC. Telegraph lever position indicator Telegraph logger RPM indicator Sub panel

TURN TO RESET

EMERG. TRIP BY-PASS

PROGRAM CONT.

AUTO SPIN

PLANT MODE

BYPASS POSSIBLE

BY-PASS

IN PROGRESS

BY-PASS

START

BY-PASS

MANEUV.

FULL AWAY

SAFETY SYSTEM
NOR BY-PASS

NOR

BY-PASS

NOR

BY-PASS

RPM CONT.

POWER FAIL

SYSTEM FAIL

ON

BY-PASS

OVER SPEED PREVENTER

CONT. POSITION

TURNING GEAR

LAMP TEST

ON

W/H

CCR

MCR

M/S

DISENGAGE

ENGAGE

Bridge Wings Main Turbine Control Panel


M/T REMOTE CONTROL SUB PANEL FOR W /H WING CONTROL PANEL
MATCHING IND.

PLANT MODE

MAIN TURBINE REMOTE CONTROL SYSTEM ALARM


WRONG WAY REMO-CON SYSTEM POWER FAIL SAFETY SYSTEM POWER FAIL TELEGRAPH POWER FAIL

AUTO SLOW DOWN


PRE WARNING AUTO SLOWDOWN ACT

EMERG. TRIP
PRE WARNING EMERG. TRIP

M / T CONTROL SYSTEM
MATCHING
(W/H-CCR/MCR)

MANEUV

NORMAL

(SPARE)

AUTO SPIN

SHAFT STOP

AUTO SPIN FAIL

REMO-CON SYSTEM FAIL

(SPARE)

ASTERN GUARD V. ABNR

AUTO SLOWDOWN REQUEST

AUTO SLOWDOWN BYPASS

PUSH TO TRIP

IMPOSSIBLE

HAND TRIP TRIP RESET

PUSH TO TRIP

FULL HALF SLOW

Main Turbine Remote Control (MTRC) Equipment


The control levers are combined with the engine telegraph and signal the turbine command to the computer. The computer carries out the command for desired a change in turbine speed or direction through consistent, stepped procedures. The logic is designed to carry out the most suitable turbine and boiler operating procedures considering best practice and their limitations.

START

BY-PASS

NOR

BYP-ASS

NOR

BYP-ASS

PROG. CONT.
IN PROGRESS

TURN TO RESET

D/S
TURN TO RESET

BYPASS

STOP

EMERG. TRIP BYPASS

LAMP TEST

D/S SLOW

CONT. POSITION
NOR RPM CONT ON RPM CONT BYPASS BYP-ASS W/H CCR CENTER

BYPASS POSSIBLE

BYPASS

HALF

ACKNOWL.

FULL

Please change the control location after matching the order of WING LEVER and W / H CENTER LEVER. In the lever of "Telegraph power failure" Bridge wing control not available.

TURN GEAR DISENG.

TURN GEAR ENGAGE

NOR MCR M/S PORT STBD

BY-PASS
BEFORE ACCEPTANCE CONTROL ENSURE LEVER POSITION MATCHES W/H CONTROL POSITION

CONTROL LOCATION
LAMP TEST
DIMMER FOR INDICATOR

LOCATION ACK.

PORT

CENTER

STBD

DIMMER FOR MATCHING

PORT

CENTER

STBD

(SPARE)

LEVER CONT. (SPARE) IMPOSS.

CAUTION
CONTACT CHIEF ENGINEERWHENEVER YOU OPERATE TRIP BYPASS SWTCH, EXCEPT WHEN SHIP HERSELF IS IN EMERGENCY SITUATION

MITSUBISHI HEAVY INDUSTRIES, LTD.


NAGASAKI SHIPYARD & MACHINERY WORKS

IND. LT

INDICATOR

TELEGRAPH DIAL

4.2.3 Main Turbine Control System


Machinery Control Room (MCR) Main Turbine Control Console
The main turbine manoeuvring control console consists of the following : Telegraph receiver with manoeuvring lever Manoeuvring valve lift indicator Lever position indicator RPM indicator Revolution counter Sub panel M/T REMOTE CONTROL SUB PANEL FOR MCR
MITSUBISHI HEAVY INDUSTRIES, LTD.
NAGASAKI SHIPYARD & MACHINERY WORKS

System Functions
The turbine remote control system can perform the following functions : The automatic slowdown will be performed by three procedures as follows : 1. Where the abnormality of above Tag Nos. 082 or 083 occurs, the manoeuvring valve lift is lowered with a ratio of 100% per 40 seconds until it reaches at a preset valve lift and when the condition is recovered to a normal, lowering of the valve lift is stopped. The valve lift will return to the lever position being put with the time schedule after recovering the boiler water level. 2. When the abnormality of above Tag Nos. 084 occurs, the manoeuvring valve lift is lowered with a ratio of 100% per 0.7MPa until it reaches at a preset pressure and when the condition is recovered to a normal, lowering of the valve lift is stopped. The valve lift will return to the lever position being put with the time schedule after recovering the boiler water level. When the lever or valve position is in Ahead Normal zone, if the abnormality of the above other than Tag Nos. 082083, and 084 occurs, the turbine revolution will lower to the bottom of Normal zone (border between Navigation Full and Harbor Full). The reset is made by putting the lever to telegraph pointer of Ahead Full.

Auto Spinning
It is intended to prevent any sagging of the hot turbine rotors whilst they are stationary by turning the engine frequently in both directions but not for warming the turbines. The turbines should be started carefully as the conditions when they are started from cold state. When the engine is stopped between movements during manoeuvring and the following conditions apply, the automatic spin function will operate : The CONTROL MODE switch on the console is turned to the LEVER position The telegraph lever is set at the STOP position The AUTO SPINNING switch on the console is turned to the NOR position The turning gear disengaged. The propeller shaft is in stop (0.1 rpm+15sec.) If the propeller shaft revolutions are less than preset revolution rpm for 20 seconds, the automatic spinning system opens the ahead steam manoeuvring valve to a preset limit to turn the propeller shaft at 3 rpm and then close. Once the propeller shaft has stopped the automatic spinning system opens the astern steam manoeuvring valve to turn the propeller shaft at 3 rpm and then close. To stop the automatic spin function from taking place change the Auto Spinning from NOR to BYPASS. If the telegraph lever is placed on some position while the auto spinning, the auto spinning is by-passed immediately and the manoeuvring valve will be operated with the lever position. The turbine will trip if the auto spinning revolution reaches 10rpm.

EMERG. TRIP BYPASS

AUTO SLOWDOWN

ASTERN

AHEAD

CONT. METHOD

MATCHING IND.

PRE WARNING

EMERG. TRIP

PRE WARNING

ACT

DEC.

INC.

DEC.

INC.

DIRECT

LEVER

MATCHING
(W / H - MCR)

PUSH TO TRIP

REQUEST

BY-PASS DEC INC DEC INC NOR BYP-ASS

MATCHING
(CCR- MCR)

3.

IMPOSSIBLE

NOR

BYP-ASS

TURN TO RESET

EMERG. TRIP BY-PASS

PROGRAM CONT.

AUTO SPIN

PLANT MODE

BYPASS POSSIBLE

BY-PASS

IN PROGRESS

BY-PASS

START

BY-PASS

MANEUV.

FULL AWAY

NOR

BY-PASS

SAFETY SYSTEM

NOR

BY-PASS

NOR

BY-PASS

RPM CONT.

POWER FAIL

SYSTEM FAIL

ON

BY-PASS

Transfer of Control Location The following conditions need to apply : Telegraph lever position matches, otherwise the HANDLE MATCHING indicator light will flicker until the positions match. The telegraph lever or the direct manoeuvring methods match, otherwise the LEVER or DIRECT indicator light will flicker until the positions match.

OVER SPEED PREVENTER


OCR

CONT. POSITION

TURNING GEAR

LAMP TEST

ON

MCR

W/H

W/H

CCR

DISENGAGE

ENGAGE

MCR

M/S

Local / Emergency Control Panel at the Main Turbine Side (MS)


(Note : When changing from neutral position to either Ahead or Astern, the governor oil pressure is dumped.)

Operation of the Main Turbine Control System


Preparation for Lever Control Prepare the main turbine for use as described in Section 4.2.2 Main Turbine Operation. a) Set the control location to MCR. The location is displayed by an indicator lamp on all the consoles. b) The control lever in all locations should be at the STOP position. c) Select the control mode as LEVER then toggle switch. Engine control positions may be selected as W/H, CCR or MCR. The turbine can now be controlled from the telegraph lever which initiates the control ramps and carries out all functions automatically. Use of the toggle switches on the machinery control room console, to raise or lower turbine speed, bypasses the computer control system and actuates the governor servomotor directly when direct control is selected.

Automatic Slowdown
The main turbine is automatically slowed down when one of the following conditions occur :
TELEGRAPH RECEIVER SHAFT REV. IND. CONT LOCATION

M/S

REMOTE

EMERG. TRIP

F/E S/B R/U SUB-TEREGRAPH

50 100 120 ASTERN

50
M/S REMOTE

M/T EMERG. TRIP


PUSH TO TRIP

A H E A D A S T E R N

N A V. FULL FULL HALF SLOW DEAD SLOW STOP DEAD SLOW SLOW HALF FULL FULL

100 120

min-1
RPM

AHEAD

TURN TO RESET TURN GEAR


TRIP RESET

E M E R G.

EMERGENCY GAUGE BOARD

ENGAGED

DISENGAGED

LAMP TEST

SPEED TABLE

Tag No. Description 082 Boiler steam drum water level high 083 Boiler steam drum water level low 084 Main steam pressure low 085 Main steam temperature high 086 Main condenser vacuum low 087 One boiler tripped 088 Stern tube temperature high 089 Main condenser hot well high Over torque due to ice shock

Set Point +180 mm 180mm 5.15 MPa 538 550 mmHgV 55 +450 mm

EMERGENCY GAUGE BOARD

(Note : The auto slowdown function can be cancelled by turning the AUTO SLOWDOWN switch to BYPASS on the console.)

4.2.3 Main Turbine Control System


Transfer of Control from the Engine to the Bridge M/T REMOTE CONTROLTo Change from Remote to Local Turbine Control SUB PANEL FOR MCR
In bridge control the wheelhouse telegraph lever signals the MTRP directly. The telegraph levers in the engine control room do not need to be moved. The indicator built into the telegraph lever will show the position in which the bridge telegraph lever has been placed. a) Telephone contact between the bridge and engine room establishes the need to transfer control. b) The telegraph levers in all locations must be in the same positions. This can be checked by observing the pointers indicating the current telegraph position and the remote telegraph position When the levers are all correctly positioned the HANDLE MATCHING lamp is lit. c) The machinery control room control location switch is moved from MCR / CCR to WHEELHOUSE.

Alarms and Trips


The main turbine is protected by alarms and trips which can be viewed through the ICAS system. These are listed as follows : Alarms Tag No.
101 107 107 108 108 108 110 111 111 115 118 121 121 122~139 141/142 143 151/152 153/154 155/156 157 158 159

In the event of the turbine remote control system failing, control can be taken from the machinery side (MS).
a) Ensure that the telegraph lever is in the STOP position and matches the bridge level. b) Ensure that the Manoeuvring Valve Closed indicator light is lit to confirm that the manoeuvring valves are closed. c) Turn the control mode switch from LEVER to DIRECT control. d) Operate the Control Mode switch at the emergency panel near the main turbine to the M/S position. The main turbine may now be operated turning the local DIRECT switch to either the INC. or DEC. position or using the manoeuvring wheel as described below. e) Pull out the lock pin on the manoeuvring wheel, which will trip the control oil system. f) Turn the manoeuvring wheel in the direction required to operate the main turbines in the ahead or astern direction, as required by the telegraph. g) Observe the position indicator below the wheel which will confirm the direction the manoeuvring wheel is being turned. The telegraph signal is acknowledged by turning the pointer switch to the flashing light at the speed required by the bridge. Then the manoeuvring wheel is turned

The WHEELHOUSE CONTROL indicator lamp begins to flicker and the buzzer sounds. Until this is acknowledged the wheelhouse telegraph lever is inoperative. ) The bridge operator acknowledges the change of control location by moving the wheelhouse console location switch from ECR / CCR to WHEELHOUSE and pressing the ACKNOWLEDGE button. The WHEELHOUSE CONTROL indicator lamp stops flickering and becomes steady. The main turbine can now be controlled from the bridge.

Description Inlet steam low pressure Gland steam high pressure Gland steam low pressure Low LO pressure Control oil low pressure LO filter high differential pressure Warming-up steam high pressure Main steam Inlet high temperature Main steam Inlet low temperature Astern steam high temperature (leakage) Astern steam drain low temperature Bearing LO high temperature Bearing LO low temperature HP / LP turbine thrust and bearing temperature Main gear bearing Main thrust pad HP / LP turbine vibration HP / LP turbine thrust bearing axial displacement Main reduction gearing vibration Main thrust bearing axial displacement Main condenser low vacuum Main condenser high level alarm

Set Point 5.2 Mpa 35 kPa 0 kPa 70 kPa 1.0MPa 70 kPa 1.15MPa 520 C 490 C 350 C 300 C 54 C 34 C 70-80 C 60 C 60 C 75 m 0.5 mm 250 m 1.3 mm -80 kPa +300 mm

Transfer of Control from the Bridge to the MCR or CCR a) Telephone contact between the bridge and engine control room establishes the need to transfer control. b) The telegraph levers in all locations must be in the same positions. This can be checked by observing the pointers indicating the current telegraph position and the remote telegraph position. When the levers are all correctly positioned the MATCHING lamp is lit. c) The engine control room (or CCR) control location switch is moved from WHEELHOUSE to ECR (or CCR). The WHEELHOUSE CONTROL indicator lamp begins to flicker and the buzzer sounds. The main turbine can now be controlled from the engine control room (or CCR). d) The bridge operator acknowledges the change of control location by moving the wheelhouse console location switch from WHEELHOUSE to ECR (or CCR) and pressing the ACKNOWLEDGE pushbutton. The WHEELHOUSE CONTROL indicator lamp stops flickering and is extinguished. The ECR indicating lamp is lit.

Description Set Point 062 Manual emergency trip 063 Overspeed 87.1 rpm 064/065 HP / LP turbine rotor excessive vibration 125 066/067 HP / LP turbine rotor position excessive displacement 1.0 mm 068 Lubricating oil pressure low 50 kPa 069 Control oil pressure low 500 kPa 070 Main condenser vacuum low -67 kPa 071 Both boilers tripped 072 Boiler steam drum water level high +240 mm 073 Spinning overspeed 10 rpm 074 Turning gear engaged 075 Safety system power failure 076 Main condenser hot well level high +450 mm 110 Warming-up steam pressure high 1.25MPa (Note : The colored TRIP function can be cancelled by turning the TRIP BYPASS switch to BYPASS on the wheelhouse, CCR or ECR console.)

Trips Tag No.

4.2.3a Main Turbine Remote Control System

4.2.3a

Main Turbine Remote Control System

W/H TELEGRAPH LEVER

PCS
FG1 V GOV. LIFT SV1 RG1 GOV. LIFT SV1' PI CONTROLLER + + + PI PV2 (AHEAD) FG2 SV2 RG2 RPM SV2' PI CONTROLLER MVH PV1 PWM (AHEAD) SOLID STATE RELAY GOVERNOR MOTOR GOV. MTR. POTENTIO METER POT ELECTRICAL POSITIONING CONTROLLER ASR ASL PI PV2 (ASTERN) B C MVS PV1 PWM (ASTERN) ASB POTENTIO METER POT SOLID STATE RELAY B GOVERNOR MOTOR GOV. MTR. ASTERN MANEUVERING VALVE AHEAD NOZZLE VALVE

POTENTIO METER CCR / MCR TELEGRAPH LEVER

ELECTRICAL POSITIONING CONTROLLER AHR AHL AHB

TURBINE

PROPELLER

V GOV. LIFT

POTENTIO METER

TG

TACHO GENERATOR

MITSUBISHI HEAVY INDUSTRIES, LTD


NAGASAKI SHIPYARD & MACHINERY WORKS

Main Turbine Remote Control System Control Diagram

4.2.3b Main Turbine Control System

ROTOR AXIAL DISPLACEMENT ALARM & TRIP DEVICE AHEAD NOZZLE VALVE VALVE POSITION TRANSMITTER HP: LP: FWD 0.5mm ALARM AFT 0.5mm ALARM &TRIP FWD 0.5mm ALARM &TRIP AFT 0.5mm ALARM

ROTOR VIBRATION INDICATOR ALARM & TRIP DEVICE (ALARM:75m, TRIP:125m)


066 067 064 065

EMERGENCY TRIP DEVICE


DESCRIPTION
063

AHEAD

ASTERN

HAND OVER SPEED L.O. LOW PRESS. MAIN CONDENSER LOW VAC. MAIN CONDENSER LEVEL HIGH

MAIN STEAM
STRAINER

* * * * * *

GOVERNOR MOTOR

H.P.TURBINE

HP & LP THRUST EMERGENCY ROTOR REVOLUTION DETECTOR TURBINE OVERSPEED TRIP DEVICE (TRIP: 110 }1%MCR SPEED) HP LP ROTOR VIBRATION CONTROL OIL LOW PRESS BOILER H-H LEVEL BOTH BOILER TRIP AUTO SPINNING OVER SPEED * : WITH BYPASS SWITCH

P P
ELECTRIC POSITIONER WITH LIMIT SWITCH
PI

PS

068

NO.4 AHEAD STOP VALVE

NO.2

NO.1

NO.3

NO.5

L.O.LINE

40

H.P. TURBINE
SOLENOID VALVE (AHEAD TRIP)

15

15

L.P.TURBINE

PRESS SWITCH (LO.LOW PRESS. TRIP:0.05MPa)

15

3
P

070

PS
PRESS SWITCH (COND.LOW VAC. TRIP:-6.7kPa / 500mmHgV)
062

EMERGENCY TRIP SWITCH

15

40

MAIN CONDENSER

*1
25 25

DUPLEX STRAINER (200 MESH)

15
EMERGENCY HANDWHEEL VALVE POSITION TRANSMITTER STRAINER LIMIT SWITCH (VALVE OPEN)

PRESS.SWITCH

PS

15

(CONTROL OIL LOW PRESS. TRIP: 0.5MPa)

069

PS PS
602

PI 108

25
RELIEF VALVE (SET 1.5MPa) CONTROL OIL PUMP

MAIN STEAM
GOVERNOR MOTOR

2.5

AUTO START (9bar) CONTROL OIL LOW PRESS.ALARM (1.0MPa) SOLENOID VALVE (AST.GUARD V.)

25
25

2.5

25

FROM L.O.LINE

*3

40

CONTROL OIL PUMP 40 50 CONTROL OIL TANK 25 SIGHT GLASS

P
ASTERN MANEUVERING VALVE

S
15

*1

ELECTRIC POSITIONER WITH LIMIT SWITCH

3 15
40

TO ASTERN TURBINE
SUCTION STRAINER (100 MESH)

*2 *2

15

15 25

TO R.G.OIL PAN

3
SOLENOID VALVE (ASTERN TRIP) 40

*2

ASTERN GUARD VALVE

*3

TO L.O. DRAIN LINE

65

25

4.2.4 Main Turbine Warming-up System


4.2.4 Warming-up Procedure
The main turbine is in need of keeping in the temperature which is more than 200at H.P. turbine casing inside. The turbine is to be ready for start-up at all times during the vessel's mooring or anchoring periods.

(1) Warm-up procedure for main steam piping


a) Confirm that the maneuvering valve is in trip condition and the main steam stop valves 001VPA and 002VPA are being closed. b) Confirm the bypass valves of main steam stop valves 001VPA and 002VPA are being closed. c) Confirm the root valves 071VPA and 077VPA of pressure reducing line are being closed. d) Confirm the warm-up steam valves 072VPA and 073VPA are being closed. e) Confirm that the main steam temperature at the main boiler outlet is over abt. 350 and set the pressure of pressure reducing valve 074VPA at 1.0MPaG. f) Open the drain valve 075VPA.

EFFECT OF TURBINE WARMING-UP SYSTEM AT PORT CONDITION


Warming-Up Condition of Main Turbine at Port(For Reference)
500 450 400 350 Temperature ( ) 300 250 200 150 100 50 0 0:00:00 12:00:00 24:00:00 36:00:00 48:00:00 60:00:00 Passage Time after Turbine Stop (hh:mm:ss) Valve Opening of Warming-Up Line HP Casing Temp. In: 173.2 /Out: 171.4 Main Steam Press./Temp. Press.: 1.5MPaG/Temp.: 315 Turbine Stop Turbine Warming-Up HP Casing Temp. In: 243.0 /Out: 242.1 Main Steam Press./Temp. Press.: 1.4MPaG/Temp.: 301 HP Turbine Casing Inside ( ) HP Turbine Casing Outside ( ) Main Steam Temperature ( )

L.P.TURBINE
S

ICAS

g) Open the bypass valves of main steam stop valves 001VPA and 002VPA. h) Fully open the root valve 077VPA valve and open slowly the valve 071VPA. i) Close the drain valve 075VPA. (The warm-up of the main steam pipe starts)

(2) Warm-up procedure for main main turbine


a) Confirm that the maneuvering valve is in trip condition. b) Confirm that the warm-up valve 073VPA is in auto mode and opened. c) Open the warm-up valve 072VPA slowly up to the full opening. (The warming-up of the turbine starts) d) Confirm the the H.P. turbine casing inside temperature is being kept over about 200. 1) In case that the H.P. turbine casing inside temperature is descended down during warming-up, stop warm-up operation and check the cause. 2) In case that the H.P. turbine casing inside temperature is descended below about 200, the superheated steam temperature of main boiler shall be increased until the H.P. turbine casing inside temperature rises up to 200.

(3) Warm-up finish


When the stand-by for departure is close at hand, the following operation is carried out. a) Close the root valves 071VPA and 077VPA.

TM
116 2

Caution
If any abnormal noise and vibration is noticed, stop opening of warm-up valve 072VPA and check the cause carefully. If following abnormal is found, Stop the turning motor and Disengage the clutch of tursning gear. - Electric current of the motor is shown extremely low and high Then check if the propeller is being turned by tide. Never stop the turbine longer than three minutes at ht condition.

TM
116 1 OUT

b) Close the warm-up valve 072VPA. c) Open the main steam stop valves 001VPA and 002VPA. e) Prior to the try-engine, the following conditions are to be confirmed. 1) The H.P. turbine inlet steam temperature is more than 300. 2) The H.P. turbine casing inside temperature is more than 200.

MANEUV. V.
IN

OIS 050

H.P.TURBINE

OIO 050

TRIP PS

PAH 110 PM 110 PIC 110 PIC 110


001VPA 002VPA

FROM No.1 BLR


AHEAD V.
076VPA

FROM No.2 BLR

AHD NOZZLE VALVES

072VPA

TRIP
LS

074VPA 071VPA 077VPA

WARMIMG-UP STEAM INLET (STEAM PRESS. : 1.0MPa)

073VPA 075VPA
WARMIMG-UP STEAM CASING INSIDE (STEAM PRESS. : abt 650mmHgV)

TO FLUSH CHAMBER
HP 1ST NOZZLE GROUPS

TO ATMOS.DRAIN TK

4.3.1 Main Boiler Overview


Maker : Mitsubishi No. of sets : Mode l : Type : Maximum evaporation : Normal evaporation : Steam condition : Fuel oil consumption : Gas consumption : No. of burners : Safety Valve Settings Drum high set : Drum low set : Superheater : Economizer : 7.65 MPa 7.60 MPa 6.40 MPa 9.07 MPa 2 sets Mitsubishi MB-3E Two drum, water tube, roof fired 55,000kg/h 46,200kg/h 6.03 MPa x 515C at superheated steam 3,322 kg/h at normal evaporation 2,726 kg/h at normal evaporation 2 combined oil/gas Alarms and Trips
Tag No. 072 082 083 463 464 465 466 467 468 469 470 471 474 479 479 481 487 492 497 502 502 504 506 507 507 507 511 511 512 513 514 518 521 521 521

General Construction
Set Point

Operating Parameters at Normal evaporation Drum pressure : FO burner header press : BOG header pressure : Atom. steam pressure : FD fan outlet pressure : Economiser inlet temp : FO burner heater temp : BOG heater temp : Air heater inlet temp : Air heater outlet temp : Economiser gas temp : O2 content : 6.58 MPa 1.30 MPa 32.5 kPa 0.79 MPa 3.50 kPa 145 C 120 C 30 C 38 C 130 C 179 C 1.90 %

Description High level (main turbine trips) : High level (main engine slowdown) : Low level (main turbine slowdown) : High level (boiler trips) : Low level (boiler trips) : Control air pressure low trip : FD fan stop (boiler trips) : Superheater outlet temperature high trip : FO pressure low trip : Atomizing steam pressure low trip : FO temperature low trip : All burners failure (boiler trips) : FO burning pump stop (boiler trips) : FG leak content high trip : FG leak content high alarm : FG temperature low trip : FG header pressure high trip : FG header pressure low trip : Feed water motor valve closes : Superheater outlet pressure high alarm : Superheater outlet pressure low alarm : Atomizing steam pressure low alarm : FO header pressure low alarm : FG header pressure high alarm : FG header pressure low alarm : FG Common line pressure high alarm : Superheater outlet temperature high alarm : Superheater outlet temperature low alarm : Desuperheater outlet temperature high alarm : FO temperature low alarm : FG temperature low alarm : Exh. gas eco. flue gas outlet temp. high alarm: Low level alarm : High level alarm : Smoke density :

+240mm +180mm -180mm +240mm -240mm 0.34 MPa 530C 0.1 MPa 0.3 MPa 80 C

+ 5 sec. +12 sec. +12 sec. + 0 sec. + 0 sec.

Each boiler is of the two drum type construction, with one steam drum and one water drum and mainly consists of the boiler proper, boiler casing, superheater, economiser, air heater, fuel and gas firing equipment, mountings, fittings and other accessories. The unit is composed of a steam drum and a water drum connected by a bank of inclined generating tubes. Other water side components include : Front screen tubes shielding the superheater elements from the direct radiant heat of the furnace Side and roof water wall Front and rear water wall tubes Downcomers Bottom headers Roof and bottom front wall headers Roof and bottom rear wall headers Front and rear wall riser pipes The tubes in the furnace floor, sides and roof, front and rear walls are of membrane wall construction. Each tube has two fins welded to it, opposite each other, and running the length of the tube. The fins of the adjacent tubes are welded together to form the membrane wall. The furnace is enveloped on three sides, the roof and the floor, by the membrane construction. This forms a gas tight envelope around three sides of the furnace and prevents gas leaking into the casing. The remaining principal components of construction are a superheater, an internal desuperheater in the steam drum, a superheat temperature control desuperheater in the water drum, the economiser, steam air heater and the casing. The combination burners are roof mounted and therefore the gas flow is evenly distributed across the front bank, superheater and generating bank tubes, before discharging through the economiser and into the flue.

60%LEL 30 % LEL 5C 75 kPa 0.7 kPa +220mm 6.2 MPa 5.2 MPa 0.35 MPa 0.15 MPa 70 kPa 1.0 kPa 150 kPa 525C 480C 400C 90 C 15C 235C -130mm +130mm Ringelman

+10 sec.

+7 sec. +7 sec. 4

4.3.1 Main Boiler Overview


Drum Internals The steam drum internals consist of the desuperheater, surface blow line, internal feed pipe, chemical feed line, baffles and dry box. Steam generated in the boiler tubes enters the steam drum where it is forced to enter a baffle located at the normal water level, before entering the upper part of the steam drum. The baffle is intended to reduce the surging of the water level due to hard steaming, sudden load changes and any vessel movement. Before leaving the boiler through the steam outlet nozzle, the steam must pass through the dry box located at the top of the steam drum. The dry box separates larger water particles from the steam and helps to prevent or reduce carry over of water with the steam. A submerged tube desuperheater is located in the steam drum below the normal water level. Superheated steam is fed through the tubes, giving up most of its degree of superheat to the water within the drum and emerging as reduced heat auxiliary steam. Desuperheated steam is supplied in this way to ensure that there is always a flow of steam through the superheater even when the demand for superheated steam is low. This ensures that the superheat tubes are not damaged by overheating during low steam flow conditions. The water drum located at the bottom of the boiler, houses a submerged tube desuperheater, through which some of the superheated steam is diverted to control the final superheat outlet temperature. Both steam and water drums are fitted with swinging manhole covers to allow entry and inspection. Furnace As previously described, the furnace walls are of the membrane construction. The tubes forming the furnace sides, floor and roof are of 63.5mm diameter, whilst the tubes forming the front and rear walls are of 50.8mm diameter. External downcomer tubes are placed outside of the boiler casing and provide ample circulation of the water from the steam drum to the water drum, bottom header and the front and rear water wall headers. The water cooled furnace floor tubes leave the bottom header to transverse the floor before bending upwards to form the furnace side and roof. They terminate in the steam drum. The furnace front and rear tubes are arranged from the lower to upper water wall headers. The upper water wall headers are connected to the steam drum by riser pipes. Where openings in the furnace walls are required for burners, access doors and sootblowers, the water wall tubes are bent around them and then back to their original plane. The furnace water wall tubes are backed up with insulation and supporting back stays that allow for expansion. The outer casing is corrugated steel plate coated with heat resistant paint. Superheater The superheater is of the vertical, interbank, convection type and arranged for multipass steam flow. The superheater elements are arranged in groups of six concentric hairpin loop elements, the ends of which are welded into inlet-outlet headers and intermediate headers. The arrangement of the elements is such that the superheater tubes are parallel to the boiler generating tubes. Guide castings are welded to the superheater elements and to the generating tubes. These sliding supports help to maintain the alignment of the superheater elements. The superheater inlet, outlet and intermediate headers run parallel to the water drum. Each header is separated internally by welded steel diaphragms to direct the steam flow through five passes between the headers. Drainage is through small openings in the lower edge of the diaphragms.

Economizer An extended surface type economiser is placed above the boiler tube bank. The economiser is made up of closely spaced, continuous loop elements, welded to the terminal headers at each end. Each element tube is 50.8mm diameter carbon steel with a spiral steel fin, connected by U-bends to form an integral loop. All the elements are supported at the front and rear side by tube plates. The outside of the terminal headers are provided with hand holes to allow access. The economiser is insulated and surrounded by a steel casing with large removable access panels. Feed water enters the inlet header at the top and flows through the elements to the bottom header and from there to the boiler steam drum. This is counter to the gas flow which passes upwards over the elements.

Saddles Saddles are provided under the water drum and the front and rear water wall headers to support the boiler. The rear saddle under the water drum is fixed and the front saddle has slotted bolt holes, grooves and grease fittings to allow for easy movement and lubrication. Grease fittings are provided on the front and rear saddles of the water wall header. The grooved saddles are free to move to allow for expansion of the boiler as it warms up. (Note : The boiler sliding feet should be inspected and cleaned as frequently as possible and should be greased at least every 600 hours. Failure to do this could result in the sliding feet seizing and subsequent damage to the boiler as it expands.)

4.3.1 Main Boiler Overview


Forced Draft Fans Maker : Air flow : Drive : Osaka Blower 950 / 1,110 / 1,900 m3/min. 900 / 1,200 rpm and 130 / 300 kW The decreasing of burner numbers, however, can not be performed automatically. No.2 burner on each boiler should be stopped manually at ICAS screen or local. Flame Eye Seal Air Fan Maker : Air flow : Drive : Onishi Electric Industry Co. Ltd 4 m3/min. 3,600 rpm and 3.7 kW

Two fans are situated on the upper deck and are controlled by adjustable vanes, automatically positioned by the combustion control equipment. The outboard fans are arranged to supply their respective boilers. The ICAS displays the following : Winding temperatures Single phase failure Vibration alarms Running high speed Running low speed Failure alarm Local or remote control Position of the crossover damper Control of the fans is from the Automatic Boiler Control system incorporated with the ICAS. The fans are started and stopped from the ICAS and high / low speed is changed by automatic combustion control signal automatically. Seal air from the FD fan ducting provides sealing air to the furnace peepholes, sootblower gas seals and the sealing connection for the superheater header casing.

Two seal air fans are supplied, one is running, the other is stand-by. The seal air fan provides cooling and sealing air to the burner flame eyes and smoke indicators.

Steam Air Heater The boiler has a steam air heater to heat the combustion air before entry to the wind box and the furnace. The steam is supplied from the main turbine 1st bleeder, 2nd bleeder or make-up steam up from the 0.24MPa depending upon the plant conditions. Each air heater has inlet steam isolating valve 268B. The air temperatures can be monitored on the ICAS BOILERS AIR SUPPLY graphic screen.

Combined Oil and Gas Burners The boiler is fitted with two combination fuel oil and gas burners mounted in the furnace roof wall. The fuel oil burner is a steam assisted pressure jet type consisting of atomizer gun, forced draft air register and a fuel oil shut off valve. The fuel is distributed to the burners from a burner manifold and branch connection pipe. The operation of increasing the number of burners is automatically operated by the automatic combustion control signal, and remotely operated by pushbutton when necessary.

4.3.1a Main Boiler Overview

PERFORMANCE DATA FLUE GAS OUTLET


EVAPORATION kg/h NORMAL MAXIMUM

MB-3E
55,000 46,200 76.5 6.03 515 145 38 88.5 10

SOOT BLOWER

FEED W. INLET HEADER

MANHOLE ECONOMIZER INSPECTION HOLE

STEAM PRESSURE MPa DESIGN SUPERHEATER OUTLET WORKING TEMPERATURE AT NORMAL F.O.MODE, SUPERHEATER OUTLET FEED WATER ECON. INLET AIR AT F.D.F. OUTLET MISCELLANEOUS DESIGN DATA AT NORMAL F.O.MODE, % BOILER EFFICIENCY EXCESS AIR

AIR INLET
FEED W. OUTLET HEADER SATURATED STEAM PIPE

SUPERHEATER INLET & OUTLET HEADER

MANHOLE FRONT STEAM DRUM N.W.L. MANHOLE FRONT RISER PIPE ROOF HEADER MANHOLE DOWNCOMER

BOTTOM HEADER INTERMEDIATE HEADER

DOWNCOMER

DOWNCOMER

DESUPERHTR INLET PIPE

SUPERHEATER SUPPORT TUBE

SUPERHEATER TUBE

REAR BANK TUBE

DOWNCOMER

DOWNCOMER

FRONT BANK TUBE

ROTARY SOOT BLOWER

WATER WALL SIDE & ROOF TUBE

OBSERVATION HOLE

OBSERVATION HOLE

LONG RETRACTABLE SOOT BLOWER

DOWNCOMER

OBSERVATION HOLE FRONT

OBSERVATION HOLE

OBSERVATION HOLE

ROTARY SOOT BLOWER

MANHOLE FRONT

MANHOLE FRONT

DOWNCOMER MANHOLE WATER DRUM WATER DRUM MANHOLE FRONT


BOTTOM HEADER BOTTOM HEADER
(FRONT & REAR)

DOWNCOMER

DOWNCOMER

MANHOLE

BOILER FRONT

SUPERHEATER HEADER

4.3.2 Main Boiler Operation


Preparation of the Boiler for Firing from Cold Preliminary Checks a) All internal parts of the boiler and tubing should be free of debris, clean of oil and combustible materials and the refractory checked to be in good condition. b) The furnace gas passages and air passages should be clear. c) Check dampers for operation and indication. d) Close the drain valves of the level gauges. e) Check the operation of the safety valves easing gear, ensuring that the gags have been removed. f) Check that the drum manholes and header hand holes are properly closed. All casings are to be secured in position. g) Check that the boiler access doors, air duct and gas duct access doors and header casing doors are properly closed. h) Open the superheat header drains 72B, 76B, 77B, 78B. i) Check that all water wall header drains and blow down valves are shut. j) Open the superheater starting vent (cold start) valve 73B, 74B and the superheater primary stop valves 134B, 135B and 136B. k) Open the saturated steam pipe vent valves 49B, 50B. l) Open superheater starting vent valve outlet drain valve 148VPC. m) Open control desuperheater drain valve 137B, 138B. n) Open steam temperature control valve 130B. o) Check that all the level gauge and instrumentation root valves are open and that their drains are closed. CAUTION The superheater starting vent valves 73B and 74B must be open while the boiler is being fired under no normal steam flow condition. Procedure for Filling the Port Boiler and Establishing the Correct Water Level Initial filling of the boiler with distilled water can be achieved by pumping distilled water either from the atmospheric drain tank or directly from the distilled water storage tanks, as follows. Using the cold start feed pump, which takes suction from the distilled water storage tanks via pump suction valve 008VPF. In the case of one boiler and the plant operating normally, the auxiliary condensate system will be running and no further preparation of it is necessary. When the plant is being started from cold the auxiliary condensate system will need to be prepared (See 3.2.1 Condensate Water System and 3.2.2 Boiler Feed Water System). Prior to filling the boiler the feed treatment chemical manufacturers recommended initial dose should be applied. This can be mixed into a solution and poured through the steam drum door prior to closing up or, pumped into the steam drum using the chemical injection equipment (See 3.2.3 Boiler Water Sampling and Treatment System). a) Set up the valves as follows for using the cold start feed pump, with due consideration for the effects of water hammer and mechanical shocking. All feed valves are considered initially closed. Position Description Valve 008VPF Open Cold start feed pump suction from distilled tank 135 or 136VPF Open Distilled water tank suction 025VPF Open Cold start feed pump discharge 11B Open Auxiliary feed line valve 12B Open Auxiliary feed line valve 7 & 8B Open Economiser header vent valves 019 & 020VPF Open Feed line high point vents 4B Open Main feed check valve b) Fill the boiler through this system and vent all air from the economiser and feed water lines. Close the vents when all air has been expelled and water issues from them. c) Fill the boiler to about 100 mm below the normal level in the gauge glass. Then bring up to the normal water level via the main feed line. Position Open Regulate Open Close Description Main feed control valve inlet and outlet Main feed control valve 1.0MPa desuperheater cooling root valves Auxiliary feed line valve Valve
1 & 20B 26B 051 & 052VPF 11B

d) Briefly open the water level gauge drain valves and ensure that they are clear and that the level in the gauge reacts. This is to initially prove that they are operating and not blocked.

Preparation of the Fuel Oil System and Initial Firing In this case the initial firing of the boiler is carried out at the boiler gauge board BGB using the base burner. The process is manually operated. a) With reference to section 3.6.4 Boiler Fuel Oil Service Systems, set up the boiler fuel system with diesel oil as the fuel supplied and recirculating at the burner header rail. Set up the valves to supply atomising air to the burner. At the group starter panel in the main switchboard room b) Start the FD fan. c) Start the fuel oil burning pump. At the boiler gauge board d) Turn the EMERGENCY Mode switch from NOR to the PURGE position. e) Using the MANUAL pushbutton on the Boiler Gauge Board, open fully the FD fan inlet vanes to conduct a furnace purge. f) When the Purge Finish light is lit turn the EMERGENCY Mode switch to the BURN position. g) Turn the FO Shut Off Valve switch from the CLOSE position to the OPEN position. h) Turn the base Burner Igniter switch from the OFF position to the ON position. i) Adjust the furnace air pressure to 150 mmAq on the wind box gauge. j) Turn the base Burner FO switch from the CLOSE position to the OPEN position. This commences the lighting up sequence. Observe the process from the furnace top and ensure that there are no leaks of fuel or air, that the fire is clean and sitting correctly in relation to the quall, and that the flame eyes are reading the flame. k) If the burner does not ignite, turn the FO switch to the CLOSE (within 10 seconds after switching to the OPEN on the step j), repeat the steps from e).

Stop the cold start feed pump once the required water level has been achieved. The valves may remain open as they are non-return. (Note : It is unwise to rely upon the remote level gauging at this stage. It can take some time to stabilise after the boiler has been in use and the static heads establish.)

4.3.2 Main Boiler Operation


(Note : It would be prudent, particularly where refractory repairs have taken place, to pull the fire out after about five minutes. This allows the heat generated to even out and prevent thermal shocking due to uneven expansion.) m) Maintain the fuel pressure at 0.35MPa, adjusting the fuel air ratio as necessary to optimize combustion. When the steam pressure reaches 0.1MPa and steam is issuing from the drum vent, close the vent. The superheater and desuperheater header drains should remain open until drained completely. They can be throttled in on the secondary valves in case the steam severely spurts. CAUTION When controlling steam flow through any of the boiler and steam line drains, always use the secondary of the two valves, leaving the primary valve fully open. This is done to protect the primary valve seat from damage due to cutting and erosion by the steam. n) With reference to the steam raising graph, continue to raise steam over the time period specified. When the drum pressure reaches 0.2MPa, start warming through the desuperheated steam system (See 3.1.2 Steam Systems). Start to warm the heavy fuel oil in the settling tanks and prepare the fuel oil heaters for operation (See 3.6.4 Boiler Fuel Oil Service Systems). During this operation and whilst the steam drum pressure is still less than 0.5MPa, it will be possible to maintain the water level using the auxiliary condensate system. Expansion of the boiler contents will cause the level to rise initially and may preclude the need to add any water before a feed pump can be brought into operation. o) Secure the burner in operation. Recirculate fuel oil until the fuel temperature has reached about 120C at the burner rail. Relight the boiler using fuel oil at 0.35MPa and atomizing steam and continue to raise the steam pressure with 0.6Mpa fuel oil pressure in accordance with the steam raising graph. p) Start to warm through the main superheat lines to the feed pumps. Prepare the main feed system for operation. Line up the valves as follows : Position Open Open Open Open Open Description Deaerator outlet valve Feed pump suction valves Feed pump recirculating valves Feed pump recirculating line to deaerator valve Feed pump main feed discharge valves Valve
001VPF 002, 003VPF 031, 032VPF 036VPF 012, 014VPF

(Note : By using the steam tables, the degree of superheat being achieved at the superheated steam outlet can be determined. In addition to monitoring the rate of increase in the steam pressure compared to the graph, the rate of increase in the superheat temperature should also be observed.) r) With reference to the Feed Water Supply screen, line up the main feed to the boiler by clicking on and opening the motor driven valve 20B. Clicking on the feed regulating valve 26B faceplate allows it to be opened and manual control to be taken. Until the automatic level control has stabilized, control the feed to the boiler with the valve set to manual. It may now be possible to shut the superheater vent as sufficient steam is being consumed in the auxiliaries to maintain a safe flow through the superheater. Carefully monitor the conditions and adjust the vent and drains accordingly. s) Warm through and drain the superheated steam lines to the turbine generators. Prepare one of the turbine generators for service as described in Section 5.1 Turbo Generators. When the boiler pressure reaches about 2.0MPa, start the turbine generator, synchronise and apply load. Leave the diesel generator on load until the boiler has stabilised on full automatic control. The boiler safety valves should be carefully tested, when the pressure is about 0.3 to 0.4MPa below full pressure, by using the easing gear to lift the disc well clear of the seat. A short strong blow of steam should be released before letting the valve disc reseat sharply. When the boiler has reached the operating pressure and combustion control is being regulated in automatic by the ICAS, place the water level control to automatic, if not already established. Ensure that all systems previously in manual control have been placed to AUTOMATIC, including the local control panel, to the REMOTE position. All safety overrides must be restored to normal. t) Close all the drain valves.

Preliminary Checks a) All internal parts of the boiler and tubing should be free of debris, clean of oil and combustible materials and refractory checked to be in good condition. b) The furnace gas passages and air passages should be clear. c) Check dampers for operation and indication. d) Close the drain valves of the level gauges. e) Check the operation of the safety valves easing gear ensuring that the gags have been removed. f) Check that the drum manholes and header hand holes are properly closed. All casings to be secured in position.

g) Check that the boiler access doors, air duct and gas duct access doors and header casing doors are properly closed. h) Open the superheater header drains. i) j) Check that all water wall header drains and blow down valves are shut. Open the superheater vent and the superheat primary stop valves.

k) Open the drum vent valves if not already open. l) Check that all the level gauge and instrumentation root valves are open and that their drains are closed.

Procedure to Fill the Second Boiler with Water There are two options available : 1) Using the cold start feed pump via the auxiliary feed line, with suction from the deaerator. 2) Using the cold start feed pump via the auxiliary feed line, with suction from the distilled tank. The best solution is to fill the second boiler whilst raising steam in the first boiler, using the condensate system. This is not possible if the boiler has been shut down and drained for repairs with the plant running on the other boiler, without shutting down the auxiliary feed system. This still leaves the problem of maintaining the level during the early stages of raising pressure. This will be achieved by option 2, using the cold start feed pump, fed from the distilled tank, with due consideration for the effect of throttling across the auxiliary feed valve 11B.

Procedure to Fire a Boiler with the Other Boiler in Operation With one boiler in use and the plant operating normally the second boiler can only be fired on fuel oil, not diesel oil.

q) When the steam pressure reaches about 1.5MPa, start one of the main feed water pumps. The feed pump can be left running; its output will be limited by the available steam pressure. It may now be necessary to throttle in the superheater vent in order to raise steam pressure at the rate shown on the graph.

4.3.2 Main Boiler Operation


Procedure to Fill the Boiler from the Condensate System Where one boiler is already in use and the plant operating normally, it will be necessary to isolate the auxiliary feed line from the feed pumps. Prior to filling the boiler the feed treatment chemical manufacturers recommended initial dose should be applied. a) Set up the valves as follows with due consideration for the effects of water hammer and mechanical shocking. All feed valves are considered to be initially closed. Position Open Open Open Open Description Economiser header vent valves Feed line high point vents Cold start feed pump suction from distilled tank Cold start feed pump discharge valve Valve
7, 8 019, 020VPF 008VPF 025VPF

e) Once the purge is complete the following sequence occurs : The FO recirculating valve FO REC V/V lamp goes out as the valve closes. The FO CONT V/V, IGN RATE and IGN AIR lamps flicker on as the base burner ignition signal is established. The second burner AIR REG. lamps go out as the air registers close. The base burner FO CONT V/V, IGN RATE and IGN AIR lamps go on as the ignition signal is confirmed. The FO BNR V/V (downstream) lamp goes on as the base burner FO valve (downstream) opens. IGNIT lamp flickers as the igniter is inserted. The IGNIT lamp goes on as the igniter position is confirmed. The igniter sparks. The FO BNR V/V (up stream) lamp goes on as the base burner FO valve (up stream) opens. If the flame eye detects a flame within 10 seconds of the burner FO valve opening the IGNIT lamp goes on and the igniter is retracted. The base burner FO CONT V/V, IGN RATE and IGN AIR lamps go off. Observe the process from the furnace top and ensure that there are no leaks of fuel or air, that the fire is clean and sitting correctly in relation to the quall, and that the flame eyes are reading the flame. (Note : It would be prudent, particularly where refractory repairs have taken place, to pull the fire out after about five minutes. This allows the heat generated to even out and prevent thermal shocking due to uneven expansion.) f) Maintain the fuel pressure at 0.6MPa, adjusting the fuel / air ratio as necessary to optimise combustion. When the steam pressure reaches 0.1MPa and steam is issuing from the drum vent, close the vent. The superheater and desuperheater header drains should remain open during the steam raising process to remove any water. They can be throttled in on the secondary valves as the pressure increases. CAUTION When controlling steam flow through any of the boiler and steam line drains, always use the secondary of the two valves, leaving the primary valve fully open. This is done to protect the primary valve from damage due to cutting and erosion by the steam.

g) With reference to the steam raising graph, continue to raise steam over the time period specified. Expansion of the boiler contents will cause the level to rise initially. h) The water level can now be maintained using the auxiliary feed system. Open the auxiliary feed valves from the feed pumps as shown below. Regulate the boiler water level using the auxiliary feed valve 11B, feeding through the auxiliary feed line. Position Open Description Feed pump auxiliary feed discharge valves Valve
11B, 12B

b) Fill the boiler through this system and vent all air from the economiser and feed water lines. Close the vents when all air has been expelled and water issues from them. c) Fill the boiler to about 100mm below the normal level in the gauge glass. This is to allow room for expansion during the first firing and steam raising phase. (Note : It is unwise to rely upon the remote level gauging at this stage. It can take some time to stabilise after the boiler has been in use and the static heads establish.) d) Briefly open the water level gauge drain valves and ensure that they are clear and that the level in the gauge reacts. This is to initially prove that they are operating and not blocked.

(Note : By using the steam tables, the degree of superheat being achieved at the superheater steam outlet can be determined. In addition to monitoring the rate of increase in the steam pressure compared to the graph, the rate of increase in the superheat temperature should also be observed.) i) Line up the main feed to the boiler by opening the motor driven valve 20B at local or group starter panel. With reference to the Feed Water Supply screen, clicking on the feed regulating valve 26B faceplate allows it to be opened and manual control to be taken. Until the automatic level control has stabilized, control the feed to the boiler with the valve set to manual. The boiler can be placed in automatic combustion control from the ICAS faceplate. The ICAS applies a fixed fuel and air signal until the pressure has nearly reached the set point. j) Continue to raise steam pressure and temperature in accordance with the graphs. Commence warming through the superheat and desuperheat lines and draining as necessary. The superheat and desuperheat main stops have warming through valves fitted around them with drains located between the main and primary stops. k) When the boiler pressure reaches about 5.0MPa, the desuperheat primary and main stops can be opened, assuming that warming through and draining has been satisfactory. Close the warming through valve but continue to drain the line. The boiler safety valves should be carefully tested when the pressure is about 0.3 to 0.4MPa below full pressure, by using the easing gear to lift the disc well clear of the seat. A short strong blow of steam should be released before letting the valve disc reseat sharply. l) As the boiler desuperheated steam pressure reaches the same pressure as the output from the on line boiler, it will begin to overcome the check valve and feed into the desuperheated steam system. The superheat main stop is left closed and the superheat vent left open at this time. This method is known as floating the boiler on line.

Preparation of the Fuel Oil System and Lighting Up a) With reference to Section 3.6.4 Boiler Fuel Oil Service Systems, circulate fuel oil until the temperature has reached a minimum of about 120C at the burner rail. Warm through the atomising steam system, and the system is drained and ready for use. b) Start the forced draft fan with the vanes closed from the local control panel or from the forced draught fans and air heaters faceplate. c) Using either the ICAS screen, Boiler Air Supply, set the air flow to about 25%. The fuel pressure should rise accordingly, dependant upon the fuel/air ratio setting on the same faceplate. The fuel pressure at the fuel rail should be 0.6MPa, if necessary, adjust the air flow to achieve this figure. d) At the local boiler control panel press the base FO burner ON pushbutton. The base burner ON lamp will light and the furnace purge sequence will start. The FURNACE PURGE lamp and the AIR REG. lamp will light as the burner air registers fully open. Once the purge condition is established the FURNACE PURGE lamp will light. The purge sequence takes approximately one minute.

4.3.2 Main Boiler Operation


Taking the Boiler Out of Service When the boiler has reached the operating pressure and combustion control is being regulated in automatic by the ICAS, place the water level control to AUTOMATIC, if not already established. Ensure that all systems previously in manual control have been placed to automatic, including the local control panel to the REMOTE position. All safety overrides must be restored to normal. Place the burner control to AUTO on the screens. This allows the ICAS to put the second burner into operation as required. This will be necessary with the plant operating on one boiler. m) Stabilise the boiler and the automatic controls. Observe the superheat temperature as it increases due to the load now on the boiler. Prepare to bring the superheater steam onto line by opening drains on the superheater pipelines, the feed pumps, the turbine generators and the main engine steam chest. This is a precaution should any water still remain in the superheater or pipelines and is carried into the system during coupling. n) Slowly open the superheater main stop valve and bring the superheated steam onto line. CAUTION During the coupling operations of the desuperheated and superheated steam systems, observe the combustion conditions on the other boiler. The effect of the coupling is to reduce the load of the on line boiler and, its reaction should be checked as satisfactory. o) Close all the drain and the superheat vent valves. a) Operate the soot blowers. b) Change from heavy oil to diesel oil before stopping the boiler. c) Stop the boiler using the manual trip. Stop the FD fan. d) The furnace post purge should be carried out twice by using the furnace pre-purge sequence. Purge the furnace by pressing REQUEST in the Furnace Purge section of the panel. Allow the furnace purge to complete as indicated when the FINISH lamp lights. e) Close the main steam stop valve gradually, to avoid a sudden pressure drop in the pipeline. f) Open the superheater vent valve and open the superheater drain valves a quarter of a turn. g) Change the automatic combustion control system to MANUAL operation. h) Close the fuel oil valves and atomising steam valves. i) Remove the burner.
Steam Drum Pressure (MPa)
4.5

The rate of reduction in the steam drum pressure should be executed in accordance with the following graph.

Reduction of Pressure in Steam Drum


6.5

5.5

j) Maintain the normal water level, which will drop as the boiler cools down. k) When the boiler pressure drops to about 0.1MPa fully open the superheater drain valves and desuperheater drain valves. CAUTION To avoid uneven expansion and damage to the pressure parts and refractory, do not open the furnace access door until the furnace cools. Do not cool the boiler by blowing down and filling with cold feed water. l) Allow a minimum of 4 hours to cool down a boiler. Regular checks of the casing and flues should be made to ensure that no fires have developed within the boiler. Check the furnace using the peepholes provided. Observe the funnel from outside to ensure that no smoke, indicating fire, is being emitted. Observe the superheater outlet temperature. This should be dropping rapidly down to saturation temperature. Failure to drop to saturation temperature could indicate a fire somewhere, giving the steam a degree of superheat.

Normal Case

3.5

2.5

1.5

Emergency Case

0.5

m) Close all the main and auxiliary feed valves.

50

100

150

200

250

300

350

Time after Stop of Boiler (minute)

4.3.2a

4.3.2a Main Boiler Mounting System


PAL 571 020VPF 019VPF 8B 7B 20B 26B 1B 083VPF PM 571

MAIN FEED LINE 082VPF PIC 553 FOR FD.W. PUMP CONT. 1B 26B 20B

M
TO No.2 BOILER

SET AT 9.07 MPA 21B

ECONOMIZER

DPI 572 DPL 572

081VPF

DPI 572

FOR F.W.R.

FOR F.W.R.

DPL 572

FROM No.2 BOILER

TM SPM

5B

T
4B 12B

6B 11B 11B TO No.2 BOILER PM 501 PIC 553 PM 503

P
TM 512 AUXILIARY FEED LINE TAH 512 031VPA TO AUX. STEAM LINE 048VPA 049VPA

TO ATMOS.

TO ATMOS. 38B 38B


G

FOR FD.W. PUMP CONTROL


50B 49B

T
145B

P
CHEMICAL FEED
148VPC 148VPC

15B

48B 16B 62B

STEAM DRUM

61B SURFACE BLOW OFF 141B

FS

ESD 463 ESD 072

74B 73B

INTERNAL DESUPERHEATER
FS
142B 143B ESD 464

H ASD 082 L ASD

LI

083

LAH 521 LAL 521

FOR ACC MASTER


165B 123B 165B

144B

STM FLOW
134B

STM FLOW

FOR F.W.R.

LM 521

123B

136B

135B 132B

167B

167B

166B

157B

TO ATMOS. 37B

124B 125B

124B 125B
H

79B

FOR STC
77B

T
ESD TS 467 78B

122B

122B

INLET & OUTLET HEADER


121B

T
TM 511 130B
G

FOR STC
76B 67B 68B 72B

#6

#5

#4

#3

#2

#1

TO MAIN TURBINE

INTERMEDIATE HEADER
TO AUX. TURBINES TO AUX. TURBINES

P
PM 502 PAH 502 PAL 502

TAL 511 TAH 511

WATER DRUM CONTROL DESUPERHEATER


131B

TO SAMPLE CLR

138B

137B

BOTTOM BLOW OFF

64B

65B

66B

BOTTOM WATER WALL HEADER


69B

NO.1 MAIN BLR


71B

69B

011VPA

012VPA

71B FROM No.2 BOILER

80B 81B (3) (3)

083VPA 084VPA 001VPA 002VPA

Feed Water & Main Steam

4.3.2b Conbination Burner System

GENERAL SERVICE AIR 026VPB TO 2ND BLEED LINE 021VPB 1.0 MPa AUX. STEAM 023VPB 025VPB 226B 022VPB

FROM ACC
426 212B FROM N2 BUFFER TK 213B FOR ACC FOR ACC 207B TO VENT POST

DRAIN SEPARATOR

TO ACC
OIO 428 254B 253B OIS 428 255B 214B 214B 216B 217B 211B

FROM ACC
208B
436B

T
238B

ESD 481

T L/L

FROM ACC
339B 027VPB 028VPB 429

TS

240B

FS
232B

FROM CARGO MACH.RM

E
256B 029VPB TO F.O. DRAIN TK 244B 209B OIO 427 OIS 427 OIO 423 OIS 423 225B 222B

P
PM 507 FOR ACC PAH 507

FROM ACC
OIO 422 OIS 422 042VPL 220B
370B

230B

NO.1

BURNER

223B

TO ACC
041VPL FROM F.O. HEATER 043VPL

FS
ESD 475 FFA 435 FFA 456 ESD 475

FLAME EYE

FLAME EYE

T
TO ATMOS DRAIN TK ESD 469 PAL 504 PM 504 G TM 514 TAL 514

GAS HEADER

P H/H P L/L ESD 487 ESD 488

FOR ACC

TAL 514

TM 514

F.O. HEADER

ESD 474

PAH 507 PAL 507 PM 507

FURNACE

213B

OIO 428 253B

OIS 428

214B 216B 217B 214B ESD 472

218B TO VENT POST

254B 255B 254B 255B

256B

E
TO F.O. DRAIN TK 244B 209B TO ATMOS DRAIN TK ESD 475 TO ATMOS DRAIN TK FFA 435 FFA 435 ESD 475 221B OIO 427 OIS 427 OIO 423 OIS 423 225B

PM 506

PAL 506

P E
FOR ACC

NO.2

BURNER

223B

FLAME EYE

FLAME EYE
OIO 424

189B TO AIR SEPARATOR OIS 424

Fuel Oil & Auxiliary Steam

4.3.2c Boiler Pressure Rising Charts

Boiler Pressure Rising Time for 1st Boiler Cold Initial Start
Note : Combustion rate should be used as a guide for startup and should be controlled appropriately so as to follow the pressure rising curve. 7.0 7.0

Boiler Pressure Rising Time for 1st Boiler Hot Start


Note : Combustion rate should be used as a guide for startup and should be controlled appropriately so as to follow the pressure rising curve.

6.0

6.0

5.0

5.0

4.0

4.0

DRUM PRESSURE (MPag)

3.0

DRUM PRESSURE (MPag)

3.0

2.0

Start the main condenser. Change from diesel oil to heavy fuel oil. Rise fuel oil pressure to 0.6MPa. Start the main feed water pump turbine. Close the starting valves 77B and 79B.

2.0

Start the turbo generator.

1.0

Open superheater inlet pipe vent valves 49B and 50B. Open superheater header drain valves 72B, 76B and 78B. Opeb starting valves 77B and 79B. Open control desuperheater drain valves 137B and 138B. Use normal atomizer at pressure of 0.4MPa. Use diesel oil and air atomizing.

Rise fuel oil pressure to 0.6 MPa. Start the main feed water pump and Close the starting valve. Supply the steam to fuel oil heating

1.0

Close superheater inlet pipe vent valves 49B and 50B. Crack open the superheater header drain valves 76B and 78B and control desuperheater drain valves 138B. When drained completely, Close the superheater drain valves and control desuperheater drain valves.

Close drum air vent valve. Open following valves. Superheater header drain valve, starting valve, starting line drain valve, control desuperheater drain valve and steam temperature control valve. Supply steam to fuel oil heater. Light off the burner using normal atomizer at pressure of 0.4 MPa. Use heavy fuel oil . When drained completely, Close all drain valves.

0 0 20 40 60 80 100 120 140 160 180 200 220 240

0 0 10 20 30 40 50 60 70 80 90 100 110 120

OPERATING TIME AFTER LIGHT OFF (minute)

OPERATING TIME AFTER LIGHT OFF (minute)

4.3.2d Combustion air, Seal Air and Flue Gas System

RO 651

RM 651

SA 651

ES FIRE

PM 508

PM 508

NO.2 F.D.FAN

B
OIO 495

RO 651

RM 651

SA 651

ES FIRE

NO.1 F.D.FAN

ACC

FOR ACC

FOR ACC

ACC

INLET VANE

INLET VANE

405

FLUE GAS AIR

AC 656

RO 656

RM 656

SA 656

ES FIRE

405

FLUE GAS AIR P


TM 519

BLR FLAME EYE SEAL AIR FAN


TM 519 TM 517

NO.2
333VPE

NO.1
331VPE 332VPE

TM 517

ECONOMIZER

334VPE

ECONOMIZER

G XI

SMOKE XAH 523 XM 523

NO.2 STM AIR HTR


TM 516 351VPE TM SPM CONT. AIR WIND BOX FURNACE 341VPE TM 516

NO.1 STM AIR HTR

SMOKE XM 523 XAH 523

G XI

SMOKE INDICATOR
G XI XM 522

SMOKE INDICATOR
TM SPM CONT. AIR XM 522 G XI

OXYGEN

PM 509

PM 509

OXYGEN

P P
PM 510

G G

G G

P P
PM 510

WIND BOX FURNACE

MH

MH

MH

MH

MH

MH

OBSERVATION HOLE

OBSERVATION HOLE

NO.2 MAIN BLR

SH HDR CASING

SH HDR CASING

NO.1 MAIN BLR

Draft Air & Seal Air System

4.3.3 Burner Characteristics


Maker: Hamworthy Combustion Engineering No. of sets : Model : Type : Maximum fuel oil flow : Fuel oil pressure at burner : Burner turndown on oil : Maximum fuel gas flow : Fuel gas pressure at burner : Burner turndown on gas : 2 sets per Boiler Hamworthy HXG 550 Oil / Gas combination burning type 2,275kg/h per burner 1.97MPa at burner maximum 15 : 1 (152kg/h per burner) 1,868kg/h per burner 59.4kPa at burner maximum 7 : 1 (267kg/h per burner) Fitted to the front plate of the air registers are mountings for two main flame and ignition flame detector heads. These are each fitted with a swivel mount. This is adjusted during commissioning to ensure that the maximum signal is optimized. Through the center of the burner register is located the oil sprayer down which the atomizing medium and fuel oil are passed. Captive in the end of the sprayer by means of a cap nut is the atomizing nozzle. The other end of the sprayer attaches to the external carrier tube assembly. The external carrier tube assembly supports the sprayer on the outside of the front plate and attached to this is the valve block assembly. This has a dual function of securing the sprayer in position and providing isolation of the oil and steam valves. Also fitted to the burner front plate is a connection for either a portable or fixed igniter which is used to ignite the main flame. The igniter protrudes through the air register locating just in front of the primary air swirler. This position is fixed to ensure correct ignition. The gas burner section is fitted internal to the air register and consists of manifold with a signal flanged inlet supply connection. The manifold will have 7 off pipe stub connections onto which the gas spuds are mounted. The individual gas spuds are fitted into the register and set in relationship to the primary swirler. They have been designed to be removable if necessary. The end nozzles of each spud will be manufactured in stainless steel and drilled to suit the type of gas fuel and operating conditions.

Description The burner consists of an air register for controlling the flow of combustion air, fuel injectors for controlling the flow of liquid and gaseous fuels. The burner has to meet these requirements for flow metering, whilst producing the necessary aerodynamic patterns for flame shape and stability in conjunction with the spatial distribution of finely atomized fuel oil to meet the specified combustion performance. The burner register is based on an air venturi and where the combustion air is divided into two individual streams, the primary and the secondary. The primary air flow is through a center section, discharging through an axial flow stabilizer (primary swirler). The secondary air passes through an annular section, produced by the outer wall of the primary section and the inner wall of the register casing, then through fixed angle swirl blades to be discharged through a divergent throat or venturi. The design concept is that the primary / secondary is of a fixed design, set at the design stage to produce the flame shape and performance required. The register draught loss (RDL) is kept to a value commensurate with the specified combustion performance. Fuel is normally introduced to the air stream by : 1) Oil, atomized through a central sprayer assembly and atomizer. 2) Gas through seven separate spuds / nozzles. A damper is included to permit a flow of combustion air through the register when firing to shut it off when not in use. When shut, a maximum of 2% air leakage is present. The damper is operated by two double acting pneumatic cylinders modulating motor opens or closes the damper blades to control the amount of combustion air depending on the firing rate. The damper is fitted with limit switches proving to the burner management control either open or close position.

4.3.3a Burner Characteristics

Characteristics of Oil Burner


60

Characteristics of Gas Burner


121

2.0 1.9

55 1.8 1.7 1.6 1.5 1.4 1.3 119 120 50

Steam Flow
118

45

40

Steam Flow (kg/h)

1.2 1.1 1.0 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0.0
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200

117

Fuel gas Pressure(kPa)

F.O. Pressure (MPa)

35

116

30

25

115

Oil Press.
114

20

15 113 10

112

111
2400

0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700 1800 1900

F.O. Flow (kg/h)

Fuel Gas Flow (kg/h/Burner)

4.3.3b Burner Assembly

Operating the Valves (Starting)

BURNER ASSEMBLY

As soon as the sprayer is secured, open the steam valve by raising the right hand (red) lever fully up. When the sprayer has been secured and its steam valve opened, the manual steam valve in the boiler front pipework should be re-opened to supply cooling steam to the atomiser.

SLIDE DAMPER AIR CYLINDER FIXED IGNITER


OPEN

RETAINING BOLT
CLOSE

FIXED IGNITER FLAME SCANNER SPARE

SLIDE DAMPER AIR CYLINDER

It is not necessary to re-open the oil valve until shortly before re-lighting the burner. At this time the oil valve in the block can be opened by raising the left hand (black) lever fully up.

FLAME TRAP

OIL AND STEAM INLET

FLAME SCANNER

SIGHT GLASS

Operating the Valves (Stopping)


To close the oil valve on the burner lower the left hand (black) lever to the bottom of its travel.

FRONT PLATE

To close teh steam valve lower the right hand (red) lever to the bottom of its travel. This action will also close the oil lever if this has not already been done.
OIL INLET AIR SLIDE DAMPER GUIDE BAR STEAM INLET

AIR SLIDE DAMPER

VENTURI THROAT SECONDARY SWIRLER

GAS FUEL INLET

PRIMARY SWIRLER GAS MANIFOLD GAS MANIFOLD GAS SPUD

VENTURI THROAT

SECONDARY SWIRLER GAS FUEL INLET

PRIMARY SWIRLER

BURNER TIP

GAS SPUD

4.3.4 Boiler Control Systems


Description
The boiler control systems are a computerized sub-system which is interfaced with ICAS. It uses Central Processor Units (CPU) for control the sequencing of the dual fuel burners and automatic combustion, and also provides a manual control capability from a dedicated boiler operation panel in the ICAS. An emergency manual control is also available at local (Boiler Gauge Board) in the Manual Local mode or the Boiler Emergency mode. The control systems consist of the following : Burner management system BMS - Each burner is controlled automatically or manually with a safety system incorporated to protect the boiler. Automatic combustion control ACC - The combustion control system regulates the fuel and air to the boiler, in the correct ratio for the conditions, to maintain the superheated steam pressure at the outlet within predetermined limits. Steam dump control SDC - Excess steam generated is automatically dumped to the main or atmospheric condensers to maintain the boiler steam pressure within the normal operating parameters. Steam temperature control STC - The superheated steam outlet temperature is automatically controlled by recirculating steam through the water drum desuperheater. This is achieved by the control of an attemperation valve 130B fitted in between the fourth and fifth pass of the superheater. Some of the steam is diverted via this valve into the desuperheater within the water drum. The steam passing through the desuperheater has the temperature reduced before it passes out and into the superheater at the fifth pass. Regulating the quantity of steam passing through the desuperheater controls the final superheat temperature of the steam. Feed water control FWR - The water level in the steam drum is automatically maintained at the normal working level by the controlling the feed control valves 26B. The system primarily matches the feed water flow to the steam flow and senses the boiler water level to ensure that it remains at the correct level. In the event of control air failure the valve will lock in the current position. Fuel oil pump discharge pressure control - The fuel oil pressure is maintained by controlling the fuel oil recirculating valve 025VPL on the pump discharge line. Atomizing steam pressure control - The atomizing steam pressure is controlled by controlling the control valve 226B so as to harmonize with burner fuel oil pressure. Purge steam pressure control The purge steam is maintained to preset pressure by the control valve 399B to minimize smoke emission.

Automatic Combustion Control (ACC)


The system consists of one Boiler Gauge Board (BGB), boiler control cabinets, sensors, transmitters and actuators. The summary of the function to gain a proper condition of combustion of the boiler is as follows ; 1) 2) 3) 4) The sensors and transmitters detect the state under the present situation. At the BGB or ACC A/M station, the demand conditions are set. The ACC cabinets calculate in accordance with the processing method previously programmed. The calculated outputs are transmitted to actuators.

Function 1) The control system controls one boiler separately or both boilers together. 2) Operation for cold starting of boiler is made from BGB at local side but once boiler achieves a certain pressure, operation of boiler may be changed over to remote control from the ICAS. 3) The fuel burning system is designed for burning fuel oil only, dual fuel or boil-off gas only. 4) All FO burners can be operated automatically and remotely. 5) Burner number control of No.2 (2nd) burner is made automatically according to the boiler load signal either at FO or at Dual fuel mode. 6) An automatic steam dump control system is provided to dispose steam generated by excess boil-off gas. 7) The gas compressor is controlled in accordance with the demands from ACC.

This system is classified as follows from its functional viewpoint. 1) 2) 3) 4) 5) 6) 7) 8) 9) Master control system Fuel control system Combustion air control system Steam dump control system Superheater outlet temperature control system Feed water control system Atomizing steam pressure control system Purge steam pressure control system FO burning pump discharge pressure control system

Master Control The master control consists of master controller and the steaming up controller. 1) Master controller The fuel demand signal is controlled by the steam flow signal (feed forward control) and by the steam pressure control signal (feed back control). 2) Steaming up controller The steaming up controller controls the hot re-start of the boiler to follow the steaming up schedule after ignition of base FO burner within maximum boiler load at steaming up. The hot start valve will open automatically, provided that either the steam flow of the boiler is low at steaming up period or the steam pressure is high during boiler stop condition.

Each boiler control cabinet has an independent control system which is composed of duplicate CPUs. These CPUs have the same function and the same system design is such that both run all the time, with the designated "master" CPU constantly updating the standby unit. This ensures that any failure of the master controller is immediately recovered by the standby unit, which will instantaneously assume control without any interruption to the process. In the event of failure, the failed CPU will be inhibited from operation until inspection and repair have been effected.

Operation panel on Boiler Gauge Board (BGB) This panel is installed on the BGB and has valve position gauges, manual loaders and changeover switches. In the event of total failure of ICAS, it can be used for BGB operation. Selecting manual switch, manipulation of the associated control valve is carried out by use of relevant Increase / Decrease buttons.

4.3.4 Boiler Control Systems


Fuel Control System The fuel control consists of the total fuel flow controller, overload controller, FO boost controller, preset FO flow controller and preset gas flow controller. 1) Total fuel flow controller The total fuel flow controller controls the combined fuel flow of FO and gas so as to match the Fuel Demand signal from the Master controller. The FO flow control valve and gas flow control valve are controlled with a split range control according to the total fuel flow control signal. Overload controller The overload controller prevents boiler overload by limiting fuel flow to the burners. The set point of this controller is automatically set by number of burners in use. FO boost controller The FO boost controller is provided to prevent loss of flame when burning dual fuel, by increasing FO flow in the event of loss of gas flow due to closure of Master gas valve. Preset FO flow controller The preset FO flow controller has the following functions. Minimum FO flow to the FO burners when burning fuel oil only or dual fuel. Recirculating FO flow control when boiler is not burning FO. FO flow control at burner ignition. FO flow control according to the fuel demand signal. FO boosting when gas only burning. If gas is lost due to closure of Master gas valve, thus ensuring that flameout does not occur. Preset gas flow controller The preset gas flow controller has following functions. Minimum gas flow to the gas burners. Gas flow control at gas burner ignition. Gas flow control according to the fuel demand signal. (2) Air flow controller The air flow controller controls the air flow to match the total fuel flow from the fuel control block. In addition, the following functions are also carried out ; Automatic control of excess air ratio by boiler load. Automatic increase of air flow during soot blowing. Automatic air flow control during the one forced draft fan and both boilers operation (1 fan 2 boiler). Air rich circuit to prevent black smoke generation. Purge air flow control when furnace purge. Air flow control at FO burner ignition. Feed Water Control System (FWR) The boiler feed water controller is of the three elements type, sensing steam flow drum level and feed water flow. The level controller has the following two set points and these set points can be selected by manual operation from the ICAS or the operation panel on BGB. 1) 2) Fixed set point. Variable set point which depends on the steam flow.

2)

Atomizing Steam Pressure Control

The atomizing steam pressure controller controls the steam pressure to match the burner FO pressure.
Purge Steam Pressure Control

3)

Steam Dump Control System (SDC) The steam dump system consists of the steam dump controller and excess BOG dump controller. 1) Steam dump controller The steam dump controller will open the steam dump valve at high superheated steam pressure. Excess BOG dump controller The excess BOG dump controller will dump the steam generated by excess boil-off gas from LNG cargo tanks when Dump mode is selected on ICAS.

The purge steam pressure controller controls the steam pressure to preset pressure.
Control of FO Burning Pump Recirculating Valve

4)

2)

The position of the FO burning pump recirculating valve is controlled by "P" controller according to the FO flow control valve position and by "PID" controller for FO burning pump discharge pressure and differential pressure between FO burning pump discharge and FO burner header.
Sequence Control for Burner Management System

The boiler ACC assists the BMS by providing the following control functions ; Superheater Outlet Temperature Control System (STC) The superheater steam temperature control system is comprised of the superheater, a control desuperheater of submerged type located in the water drum and pneumatically control attemperation valve. The steam temperature is controlled by controlling the steam flow to the control desuperheater. And this controller is of the two elements type, sensing primary and secondary superheated steam temperature. 1) 2) 3) 4) 5) Judgment of fuel condition to change the fuel mode. Control for burner ignition. Ordering No.2 burner ignition. Control of FO boosting. Control of boiler hot re-start.

5)

Air Control System The air control system consists of the oxygen trim controller and air flow controller. 1) Oxygen trim controller The oxygen trim controller controls the excess air ratio to optimize oxygen content in the boiler exhaust gas and have automatic start / stop control function by the soot blower control signal and boiler load changing signal

Operation The following systems can be operated from either ICAS or the operation panel on BGB. The control mode of Manual (M) or Automatic (A) for each system is selected independently. Master control system Steam dump control system Feed water control system Superheater outlet steam temperature control system Atomizing steam pressure control system Combustion air control system Fuel gas control system Fuel oil control system Fuel oil burning pump delivery pressure control system

BOILER AUTOMATIC COMBUSTION CONTROL SYSTEM

NO.1 B O I L E R A C C
STM PRESS PV CONT. LOCATION
LOCAL ICAS

STM DUMP SP PV

COMMON
COMMON PART CONT. LOCATION BGB ICAS

MASTER SP PV STM PRESS PV

NO.2 B O I L E R A C C

STEAM UP
STM UP FINISH

COMMON PART CPU SELECT PCSB1 PCSB2

STEAM UP STM UP FINISH

CONT. LOCATION LOCAL ICAS

DRUM LEVEL SET POINT


VAR FIX

STM DUMP PISTON V.

DRUM LEVEL SET POINT

OPEN

VAR

FIX

DRUM LEVEL SP PV

STEAM TEMP SP PV

ATOMIZ STEAM PRESS SP PV

AIR FLOW SP PV

GAS FLOW SP PV

FO FLOW SP PV

FO DELIV PRESS SP PV

FO DELIV PRESS SP PV

FO FLOW SP PV

GAS FLOW SP PV

AIR FLOW SP PV

ATOMIZ STEAM PRESS SP PV

STEAM TEMP SP PV

DRUM LEVEL SP PV

4.3.4 Boiler Control Systems


Burner Management System (BMS) The BMS is composed of ICAS cabinets and Boiler Gauge Board (BGB). The ICAS cabinets are located in the Machinery Control Room (MCR).The panel contains the burner sequence controllers, various relay units and system power supply unit, required for the automatic operation of boiler burners. Each cabinet is deviled into three (3) sections, one for common system, another No.1 Boiler ACC and BMS and the other No.2 Boiler. Each ICAS cabinet has an independent control system which is composed of duplicate CPUs. These CPUs have the same function and the same system design is such that both run all the time, with the designated "master" CPU constantly updating the standby unit. This ensures that any failure of the master controller is immediately recovered by the standby unit, which will instantaneously assume control without any interruption to the process. In the event of failure, the failed CPU will be inhibited from operation until inspection and repair have been effected. The exchanges of necessary information between the BMS and ACC systems are made by digital signals. The boiler gauge board is located on the burner platform for local operation. The BGB contains the relays and displays the monitoring gauges, the Burner Operation Graphic panel and ACC Operation panel and the associated Emergency Burner Operation panels. BGB can allow the following operations. Manual burner operation FO shut off valve Open / Close Master gas valve Open / Close Boiler gas valves Open / Close Master and header N2 purge Start Changeover of operation site Emergency manual trip ACC emergency operation BMS emergency operation Operation Mode Control Position 1) The control position of BGB or ICAS can be selected by depressing Control Position push button on the BGB. 2) Local operation can be done at BGB. When BGB is selected, the burner control mode is changed to Manual automatically. Control priority is afforded to the BGB position. 3) ICAS operation can be done at the central control room or the machinery control room where the ICAS is provided. Fuel Mode 1) Manual operation mode The fuel mode (FO / DUAL / GAS) is selected on ICAS only when the control position is set to ICAS. When the burner control is in AUTO mode, the burner is operated automatically under selected fuel mode. On the other hand, when the control mode is set to MANU, the burners can be operated under any fuel mode regardless of the position of fuel mode switch provided that the operation conditions are established by the ACC. 2) FO mode a) When the following events occur, the fuel mode is shifted automatically to FO mode. All burners are extinguished. Master gas valve trip at Dual mode or Gas mode (for boost up order) b) The first ignition and automatic steaming up can be made only at
FO mode.

Burner Control Mode 1) Manual operation mode a) Manual operation mode is selected on ICAS only when the control position is set to ICAS at BGB. b) When the following events occur, the burner control mode is automatically shifted to manual operation. Boiler trip at any fuel mode Burner trip Selection of BGB When FO Temp. Bypass mode or Emergency operation mode is carried out, the burner control can not be changed to AUTO, because of BGB operation only. 2) Automatic operation mode Automatic operation mode can only be selected on ICAS after the operating site has been set to ICAS at BGB.

The mode change from Dual to FO requires that "Gas Burner Extinguish" signal from ACC is established. 3) Dual mode When the following events occur, the fuel mode is shifted automatically to Dual mode. FO back up order at Gas mode The mode change from FO to Dual requires that "Gas Ignition Condition" signal from ACC is established with master gas valve and boiler gas valve Open and with "Gas Ignition Rate" lamp ON. The change from Gas to Dual requires that "HFO Ignition OK" signal from ACC is established. 4) Gas mode Gas mode can be selected only when all burners are in combustion at Dual mode. The mode change from Dual to Gas requires that "HFO Burner Extinguish" signal from ACC is established.

4.3.4 Boiler Control Systems


Operation of Burner Ignition of Oil Burner 1) Initial ignition at FO mode is carried out by lighting any burner at BGB mode. 2) The restart of the burners can be carried out remotely on ICAS after the control position has been transferred to ICAS. 3) By pressing the push button of FO ON for selected burner, the ignition of the burner progresses sequentially and automatically. Ignition of Gas Burner 1) The ignition of gas burner is made with a flame of own oil burner, thus at least, the ignition of one oil burner must have been completed before the ignition of gas burner.. 2) The master gas valve and respective boiler gas valve should be opened from BGB or ICAS. 3) The ignition of gas burner at local is made by pressing the push button of GAS ON on the BGB. 4) The ignition from ICAS can be performed by setting to DUAL in the Fuel Mode provided that the burner control is in "AUTO" mode and the conditions from ACC have been established. Burner Number Control (Cascade control) In the AUTO mode, the second burner is ignited automatically in accordance with the instruction from ACC. The increase of burner number is made automatically in any fuel mode, the extinguishment of second burner, however, can be executed by manual only. When ACC requires increasing the fuel quantity exceeding the maximum gas flow of the burner being attended, the following FO Back up or FO boost up control will function. The BMS remotely operates the two LNG / FO combination burners situated in the boiler roof. A dual programmable controller, used in the control section of the BMS, enables a sequential operation of the LNG / FO combination burner and piston valves. These are interlocked with the boiler protection system and the ACC. The ICAS displays the flow of the sequence and the operation of the interlock on a graphic operating panel. FO Boost up Control In Gas or Dual mode operation under "AUTO" mode, when the master gas valve closes due to trip cause, the FO burner will start immediately and the fuel mode is transferred to the FO mode automatically. Master N2 Purge On initiation, the line from the master gas valve outlet to each of the boiler gas valve inlets is purged with N2. There are following two modes available (selected at the ICAS). (1) Auto - in which an automatic N2 purge is carried out after the master gas valve has closed, or (2) Manual - in which a manually initiated N2 purge is carried out by depressing the master N2 purge switch either on the ICAS or on the BGB. Gas Header N2 Purge On initiation, the line from each boiler gas valve outlet to each burner is purged with N2. There are following two modes available. (1) Auto - in which an automatic N2 purge is carried out after the boiler gas valve has closed, or (2) Manual - in which a manually initiated N2 purge is carried out by depressing the relevant header N2 purge switch either on the ICAS or the BGB. (NOTE : If the forced draft fan stopped when a header N2 purge is initiated, each burner gas valve is closed, the header vent valve is opened and only the gas header is purged with N2.) Gas Burner N2 Purge (1) On initiation, the line from each burner gas valve outlet to each gas burner is purged with N2. This purge will be carried out automatically when the gas burner valve has closed. (2) It should be noted that the gas burner N2 purge will not be carried out when ; Boiler shutdown has occurred, or All burners have stopped. In either case, only the Gas Header N2 purge will take place. Emergency Trip Boiler Shut off During normal operation, the following events will shut off the fuels to the boilers and initiate alarms at the BGB and ICAS. Tag No.
462 463 464 465 466 467 471 472 473

Description Manual Trip Steam Drum Level High / High Steam Drum Level Low / Low Control Air Pressure Low / Low Forced Draft Fan Stop SH Steam Temp High / High All Burners Flame Failure Black-out Both CPUs Failure

Set Point Nor +240 mm Nor -240 mm 0.34 MPa 530

Boiler Fuel Oil Shut off During normal operation, the following events will shut off the fuel oil to the boilers and initiate alarms at the BGB and ECC. Tag No.
461 468 469 470 474

Description Boiler Shut Off Conditions FO Pressure Low / Low Atomizing Steam Pressure Low / Low FO Temperature Low / Low FO Burning Pump Stop

Set Point 0.1 MPa 0.3 MPa 80

Master Gas Valve Shut off During normal operation, the following events will shut off the gas to the boilers and initiate alarms at the BGB and ECC. Tag No.
477 478 479 485 481

Description Manual Trip Both Boilers Trip Gas Leak Detection High / High Both Gas Duct Exhaust Fan Stop Gas Temperature Low / Low

Set Point

60 % LEL 5

Boiler Gas Valve Shut off During normal operation, the following events will shut off the gas to the boilers and initiate alarms at the BGB and ECC. Tag No.
487 488 489 490

FO Back up Control In Gas mode operation under "AUTO" mode, when the following events occur, the FO back up is carried out according to the demand from ACC and the fuel mode is transferred to Dual mode automatically. Operation in manoeuvring zone FO back up order from ACC FO back up order from ICAS

Description Gas Pressure High / High


Gas Pressure Low / Low

Set Point 75 kPa 0.7 kPa

Boiler Trip Master Gas Valve Trip

4.3.4a Boiler Gauge Board


BOILER GAUGE BOARD

ATOMIZING PRESS.

FO PRESS.

SH STM PRESS.

STM DRUM PRESS.

FW PRESS.

STM DRUM PRESS.

SH STM PRESS.

FO PRESS.

ATOMIZING PRESS.

N2 PURGE PRESS.

FD FAN OUTLET

WIND BOX

FURNACE

F.G. PRESS

D.W.L.
CPU(A) RUN CPU(B) RUN NO1 BLR AC100V SOURCE NO1 BLR DC24V SOURCE EMERG MODE COMMON AC100V SOURCE COMMON DC24V SOURCE FO BACK-UP V. DUCT EXH FAN BOTH STOP

BMS OPERATION PANEL


MASTER GAS TRIP CONDITION GAS LEAK DETC GAS TEMP L/L BOTH BLR TRIP MANU TRIP MASTER GAS V/V ABNOR LDC1 MAST GAS AUX MACH LDC2 1 V. DUCT EXH. FAN 2 V. DUCT EXH. FAN EMERG MODE NO2 BLR DC24V SOURCE NO2 BLR AC100V SOURCE CPU(B) RUN CPU(A) RUN

D.W.L.

F.G. PRESS

FURNACE

WIND BOX

FD FAN OUTLET

NO.1 BOILER
GAS P H/H L/L

HDR N2

MASTER VENT

MASTER VENT GAS CONT V/V BLR GAS V/V BLR GAS V/V

HDR N2

BLR GAS TRIP


BLR GAS V/V

GAS CONT V/V

BLR GAS TRIP


BLR GAS V/V GAS P L/L H/H

NO.2 BOILER

HDR VENT V/V

HDR VENT V/V

IGN RATE BNR N2 GAS BNR V/V BNR N2 GAS BNR V/V BNR N2 GAS BNR V/V BNR N2 GAS BNR V/V

MASTER N2

AIR REG

IGNIT

AIR REG

IGNIT

MASTER GAS V/V

AIR REG

IGNIT

AIR REG

IGNIT

NO.1 BNR
ATM STM V/V
FL1 FAIL BNR FAIL

F.O.BNR V/V ATM STM V/V

NO.2 BNR
BNR FAIL

F.O.BNR V/V

MASTR GAS TRIP


GAS SUPPLY ATM STM V/V ATM CONT V/V

NO.2 BNR
BNR FAIL

F.O.BNR V/V ATM STM V/V

NO.1 BNR
BNR FAIL

F.O.BNR V/V

FL2 FAIL

BNR PURGE V/V

FL1 FAIL

FL2 FAIL

BNR PURGE V/V

BNR STM SUPPLY ATM CONT V/V

FL1 FAIL

FL2 FAIL

BNR PURGE V/V

FL1 FAIL

FL2 FAIL

BNR PURGE V/V

FL1 BY-PASS

FL2 BY-PASS

FL1 BY-PASS

FL2 BY-PASS

FL1 BY-PASS

FL2 BY-PASS

FL1 BY-PASS

FL2 BY-PASS

L-L F.O. REC. V/V F.O. CONT V/V BLR F.O. SHUT V/V

L-L F.O. REC. V/V F.O. CONT V/V BLR F.O. SHUT V/V

BLR TRIP

FDF TRIP

DWL L/L

DWL H/H

SH-T H/H

F/E ABNOR

MANU TRIP

FO TRIP

V & REG ABNOR

C-AIR TRIP

F.O.P. L/L F.O.T. L/L

F.O.P. L/L F.O.T. L/L

RUN

C-AIR V & REG ABNOR TRIP

FO TRIP

MANU TRIP

F/E ABNOR

SH-T H/H

DWL H/H

DWL L/L

FDF TRIP

BLR TRIP

NO.1 BNR

NO.2 BNR

FDF H-RUN FDF L-RUN

FURN PURGE IGN AIR

1 FAN 2 BLR MODE

COMMON DMPR OPEN

HOT START V/V

BY - P

IGN RATE

TRIP F.O. PUMP

IGN RATE

BY - P

HOT START V/V

COMMON DMPR OPEN

1 FAN 2 BLR MODE

FURN PURGE IGN AIR

FDF H-RUN FDF L-RUN

NO.2 BNR

NO.1 BNR

NO.1 BOILER
MANU TRIP

NO.1 BNR F.O. ON OFF

NO.2 BNR F.O. ON OFF

MANU TRIP

NO.2 BNR F.O. ON OFF

NO.1 BNR F.O. ON OFF NO.2 BOILER


MANU TRIP

O2 IND

SMOKE IND

SH STM TEMP

GAS ON OFF

GAS ON OFF

MASTER GAS V/V

GAS ON OFF

GAS ON OFF

SH STM TEMP

SMOKE IND

O2 IND

OPEN

CLOSE

FO SHUT V/V OPEN CLOSE F.O.

FUEL MODE DUAL GAS

BLR GAS V/V OPEN CLOSE

MASTER N2 PURGE

BLR GAS V/V OPEN CLOSE F.O.

FUEL MODE DUAL GAS

FO SHUT V/V OPEN CLOSE

ON

OFF

BLR CONT POSITION BGB ICAS

CASCADE CONTROL AUTO MANU

HDR N2 PURGE ON OFF

MASTER GAS CONTROL POSITION

HDR N2 PURGE ON OFF

CASCADE CONTROL AUTO MANU

BLR CONT POSITION BGB ICAS

BGB

DCS

EMERG OPERATION
PURGE FINISH
EMERG MODE PURGE NOR BURN

FL SW

TEST

ACKNOW - LEDGE

CAUTION
WHEN BOILER IN SERVICE WITH "FO TEMP BY - PASS" ON "FO TEMP L - L ", DO NOT SELECT SWITCH TO "OFF" AS THIS WILL CAUSE BOILER TRIP.

FO TEMP BYPASS

1FAN 2BLR MODE

EMERG OPERATION
NO.1 BURNER
IGNITER

NO.2 BURNER
IGNITER

NO.1 BURNER
IGNITER

NO.2 BURNER
IGNITER
EMERG MODE PURGE NOR BURN

PURGE FINISH

OFF

ON

OFF

ON

OFF

ON

OFF

ON

BOILER AUTOMATIC COMBUSTION CONTROL SYSTEM

NO.1 B O I L E R A C C
BLR FO SHUT V/V
CLOSE OPEN

STM DUMP SP PV STM PRESS PV

COMMON
COMMON PART CONT. LOCATION BGB ICAS

MASTER SP PV STM PRESS PV

NO.2 B O I L E R A C C
FO V/V
CLOSE OPEN STEAM UP STM UP FINISH CONT. LOCATION LOCAL ICAS

FO V/V
CLOSE OPEN

FO V/V
CLOSE OPEN CONT. LOCATION
LOCAL ICAS

FO V/V
CLOSE OPEN

BLR FO SHUT V/V


CLOSE OPEN

STEAM UP
STM UP FINISH

COMMON PART CPU SELECT PCSB1 PCSB2

DRUM LEVEL SET POINT


VAR FIX

STM DUMP PISTON V.

DRUM LEVEL SET POINT

OPEN

VAR

FIX

DRUM LEVEL SP PV

STEAM TEMP SP PV

ATOMIZ STEAM PRESS SP PV

AIR FLOW SP PV

GAS FLOW SP PV

FO FLOW SP PV

FO DELIV PRESS SP PV

FO DELIV PRESS SP PV

FO FLOW SP PV

GAS FLOW SP PV

AIR FLOW SP PV

ATOMIZ STEAM PRESS SP PV

STEAM TEMP SP PV

DRUM LEVEL SP PV

EMERGENCY MODE
RESORT TO EMERGENCY OPERATION MODE START-UP ONKY WHEN BOTH CPU(A) AND CPU(B) ARE OUT OF ORDER, IN THE FOLLOWING MANNER. 1. START F. D. FAN AND F. D. BURN. PUMP. 2. CHANGE EMERGENCY MODE SELECT SWITCH FROM "NOR" TO "PURGE". 3. FULL OPEN F. D. FAN INLET VANE TO CONDUCT FURNACE PURGE. 4. WHEN PURGE FINISH LAMP "ON", CHANGE THE EMERGENCY MODE SELECT SWITCH TO "BURN". 5. CHANGE BLR FO SHUT V / V SWITCH FROM "CLOSE" TO "OPEN". 6. CHANGE IGNITER SWITCH FROM "OFF" TO "ON", AND FO V / V SWITCH FROM "CLOSE" TO "OPEN". KEEP THE FO V / V OPEN NOT MORE THAN OF 10SEC. NAX. 7. IF HFO BUNER DOSE NOT IGNITE BY THE ABOVE PROCESS, REPEAT THE OPERATION FROM 3. NOTE : FURNACE PURGE SHOULD BE SUFFICIENTLY CONDUCTED, IF BURNER FAILS TO LIGHT-OFF, FURNACE MUST BE REPURGED PRIOR TOREPEATING IGNITION SEQUENCE.

EMERGENCY MODE
RESORT TO EMERGENCY OPERATION MODE START-UP ONKY WHEN BOTH CPU(A) AND CPU(B) ARE OUT OF ORDER, IN THE FOLLOWING MANNER. 1. START F. D. FAN AND F. D. BURN. PUMP. 2. CHANGE EMERGENCY MODE SELECT SWITCH FROM "NOR" TO "PURGE". 3. FULL OPEN F. D. FAN INLET VANE TO CONDUCT FURNACE PURGE. 4. WHEN PURGE FINISH LAMP "ON", CHANGE THE EMERGENCY MODE SELECT SWITCH TO "BURN". 5. CHANGE BLR FO SHUT V / V SWITCH FROM "CLOSE" TO "OPEN". 6. CHANGE IGNITER SWITCH FROM "OFF" TO "ON", AND FO V / V SWITCH FROM "CLOSE" TO "OPEN". KEEP THE FO V / V OPEN NOT MORE THAN OF 10SEC. NAX. 7. IF HFO BUNER DOSE NOT IGNITE BY THE ABOVE PROCESS, REPEAT THE OPERATION FROM 3. NOTE : FURNACE PURGE SHOULD BE SUFFICIENTLY CONDUCTED, IF BURNER FAILS TO LIGHT-OFF, FURNACE MUST BE REPURGED PRIOR TOREPEATING IGNITION SEQUENCE.

MITSUBISHI HEAVY INDUSTRIES, LTD.


NAGASAKI SHIPYARD & MACHINERY WORKS

4.3.4b Automatic Combustion Control (ACC)


FROM UPS1 AC100V FROM UPS2 AC100V FROM UPS1 FROM UPS2 FROM UPS1 AC100V FROM UPS2 AC100V
UN(M) P-LINE UN(M) Q-LINE

AC100V

No.1 BOILER ACC PANEL

COMMON PANEL

No.2 BOILER ACC PANEL

MCB21
TO OTHER SYSTEMS

MCB21
SELECTOR

MCB22
AUTO CHANGEOVER CIRCUIT

No.1 No.2

A/D

A/D

A/D

EATR

EATR

A/D

A/D

A/D

A/D

A/D

A/D

EATR

EATR

A/D

A/D

A/D

A/D

A/D

SEPARATED CABLE ROUTES

PCS

IOS
TO RELAY CIRCUIT TO LAMP CIRCUIT

PCS

IOS

SIGNAL CONDITIONER
TO RELAY CIRCUIT TO LAMP CIRCUIT

SIGNAL CONDITIONER
TO RELAY CIRCUIT TO LAMP CIRCUIT

ANALOG BACK UP UNIT

SIGNAL DISTRIBUTOR SIGNAL CONDITIONER

ANALOG BACK UP UNIT

AI

AI

AO

AO

DI

DO

DO

AO

AI

AO

DO

AO

AI

AI

AO

AO

DI

DO

DO

MCR MACHINERY CONTROL CONSOLE

No.1 BOILER SENSOR


SUPHTER OUTLET FEED W. FLOW GAS FLOW VENTURI PRIM. SUPHTR STEAM TEMP BOILER EXH. GAS O2 CONTENT GAS FLOW TRANS. (DUAL) AIR FLOW TRANS. SUPHTR STEAM TEMP (DUAL)

STEAM DRUM

CONDENSER

SUPHTER STEAM FLOW

F.O. FLOW

CONDENSER F.O. BURN. PUMP DIS. PRESS TRANS. F.O. FLOW TRANS. (DUAL) STEAM FLOW TRANS.

(DUAL) STEAM PRESS TRANS. CONDENSER FEED W. FLOW TRANS.

ATOMIZ. STEAM PRESS TRANS.

PURGE STEAM PRESS TRANS.

BURNER HDR F.O. PRESS TRANS.

BGB

ACC CONTROL PANEL

DRUM LEVEL TRANS.

COMMON SENSOR
GAS PRESS TRANS. GAS TEMP

16 CONTRO LOOPS

CCR

INTEGRATED AUTOMATION SYSTEM (IAS) MACHINERY CONTROL CONSOLE

No.2 BOILER SENSOR


SUPHTER OUTLET FEED W. FLOW GAS FLOW VENTURI PRIM. SUPHTR STEAM TEMP BOILER EXH. GAS O2 CONTENT GAS FLOW TRANS. AIR FLOW TRANS. SUPHTR STEAM TEMP (DUAL)

STEAM DRUM

CONDENSER

SUPHTER STEAM FLOW

F.O. FLOW

CARGO CONTROL CONSOLE

CONDENSER F.O. BURN. PUMP DIS. PRESS TRANS. F.O. FLOW TRANS.

STEAM PRESS TRANS. CONDENSER FEED W. FLOW TRANS.

ATOMIZ. STEAM PRESS TRANS.

PURGE STEAM PRESS TRANS.

BURNER HDR F.O. PRESS TRANS.

DRUM LEVEL TRANS.

STEAM FLOW TRANS.

OPERATOR STATION

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

I/P CONVERTER

FEED WATER CONTROL VALVE


AIRLESS OPEN

STEAM TEMP CONTROL VALVE


AIRLESS OPEN

ATOM. STEAM PRESS CONTROL VALVE


AIRLESS CLOSE

PURGE STEAM PRESS CONTROL VALVE


AIRLESS CLOSE

F.D. FAN VANE DRIVE

AIRLESS OPEN

GAS FLOW CONTROL VALVE


AIRLESS CLOSE

F.O. FLOW CONTROL VALVE


AIRLESS CLOSE

F.O. RECIRC. CONTROL VALVE


AIRLESS CLOSE

STEAM DUMP CONTROL VALVE


AIRLESS CLOSE

STEAM DUMP CONTROL VALVE


AIRLESS CLOSE

F.O. RECIRC. CONTROL VALVE


AIRLESS CLOSE

F.O. FLOW CONTROL VALVE


AIRLESS CLOSE

GAS FLOW CONTROL VALVE


AIRLESS CLOSE

F.D. FAN VANE DRIVE

AIRLESS OPEN

PURGE STEAM PRESS CONTROL VALVE


AIRLESS CLOSE

ATOM. STEAM PRESS CONTROL VALVE


AIRLESS CLOSE

STEAM TEMP CONTROL VALVE


AIRLESS OPEN

AIRLESS OPEN

FEED WATER CONTROL VALVE

AUTOMATIC COMBUSTION CONTROL SYSTEM DIAGRAM

No.1 BOILER CONTROL VALVES

COMMON

No.2 BOILER CONTROL VALVES

PART 5: ELECTRIC POWER GENERATING SYSTEM

5.1 5.2 5.3 5.4


5.4.1 5.4.2 5.4.3 5.4.4 5.4.5 5.4.6 5.4.7

Turbo Generator Diesel Generator Emergency Diesel Generator Power Distribution System
Electrical Equipment Main Switchboard and Generator Operation Shore Power Main Alternators Emergency Alternator Preferential Tripping and Sequential Restarting 24 Volt Battery and Uninterruptible Power Supply

Illustrations
5.1a 5.1b 5.1c 5.1d 5.2a 5.2b 5.3a 5.3b 5.3c 5.4a 5.4.7a Turbo Generator Overview Turbo Generator Alternator Turbo Generator Steam and Exhaust Systems Turbo Generator Lubrication and Control Oil Systems Diesel Generator Alternator Diesel Generator Piping Systems Emergency Diesel Generator Overview Emergency Diesel Generator Alternator Emergency Diesel Generator Piping Systems

Power Distribution System


24 Volt Battery and Uninterruptible Power Supply

5.1

Turbo Generator
Alarms and Trips
Mitsubishi Heavy Industries Ltd AT42CT-B Single cylinder, impulse, multistage, condensing 2 sets 3.200kW (2,000kW at atmospheric back pressure) 5.88 MPaG 510C 710mmHg 10,045 / 1,800 rpm UG-8D Clockwise viewed from generator end 6 Ratio Single reduction, single helical Taiyo Electric Co.,Ltd. HPW 65B-4 6,600V, 3ph, 60Hz, 4,000 kVA, 0.8pf Steam is supplied to the glands from a gland steam receiver mounted adjacent to the turbine. Where the turbine internal steam pressure is higher than the pressure in the gland housing, steam will enter the series of diaphragms from the turbine, as well as supplying the gland steam receiver and is effectively throttled across each stage causing its pressure to drop. The gland steam receiver is connected to the inner sections of the glands so that the steam supplied will pass outwards and is led away from the outer glands to the packing steam receiver and from there it is dumped to the main condenser by the system controller. Where the pressure in the gland housing is greater than the internal turbine pressure at the shaft exit point, the steam available from the gland steam receiver will be drawn through the gland, effectively sealing it and preventing the ingress of air. The need for the steam to make-up or spill changes with the turbine load, i.e. at high load the steam will generally be spilt out of the system and at low loads the packing steam will need to be made up. Steam from the outer stages of the labyrinth is led to the main gland steam condenser. Due to the make-up and spill operation of the controller on the inner glands, the pressure of the steam at the leak off point is always positive. The reduction gear is of the single reduction, single helical type, the turbine pinion is solid and its one end is connected to turbine shaft. One end of gear wheel drives the main LO pump and governor gear, and the other end is connected to the alternator with diaphragm coupling. The gearing is supported by four oil lubricated bearings. The LO system is supplied from a motor driven priming pump when the turbine is stopped or starting up. The priming pump starts when the LO pressure falls to 60kPa and cuts out when the turbine reaches 85kPa. A gear-driven main LO pump supplies the system when the turbine is running normally. The pressure is regulated to the bearings and gears by a regulating valve, full delivery oil pressure is supplied to the trip valve. The governing system consists of a Woodward UG-8D governor, actuator, hydraulic servomotor and turbine nozzle valve. The governor has a very fast response to load change and is designed to prevent the turbine over speeding even in the event of the generator circuit breaker tripping. The governor reacts to changes in speed by moving a linkage to the hydraulic servomotor which in turn opens or closes the steam inlet to the turbine nozzles. Cooling of the LO and the generator windings is supplied from the central fresh water cooling system. In an emergency the generator windings can be cooled by opening the covers and allowing air to pass through, drawn in by the fan mounted on the generator rotor shaft. The trip valve protects the turbine in the event of a serious problem by closing and immediately shutting off the steam to the turbine. The trip valve is held open mechanically by a tripping mechanism. The tripping mechanism is activated by hydraulically operated tripping cylinder In the event of a trip condition occurring, the oil supply to the tripping cylinder is cut off, moving an internal piston which is directly connected via a mechanical linkage to the tripping mechanism on the stop valve. This action trips the stop valve. The following table details the protective alarm and trip and set points : Tag No.
214 222 223 225 231 248 213/224 215/222 216/246 217/247 232-237

Specification
Turbine : Maker : Type : Number of units : Rated output : Main steam pressure : Main steam temperature : Exhaust vacuum : Revolutions : Governor : Direction of rotation : Number of stages : Gearing : Alternator : Maker : Type : Capacity :

Description Overspeed Sentinel valve Gland steam pressure Low LO strainer differential High LO inlet temperature High LO sump level Low LO pressure Low Exhaust pressure High Rotor vibration High Rotor axial movement High Bearings temperature High

Alarm 30 kPa 3 kPa 50 kPa 55C -150mm 70 kPa 30 kPa 50 m 0.55 mm 75C

Trip 1,962 rpm

40 kPa 50 kPa 80 m 0.7 mm

Descriptions
The Mitsubishi AT42CT-B turbine generator consists of the steam turbine, reduction gear, alternating current generator and auxiliaries mounted on a common bedplate. The bedplate incorporates the lubricating oil (LO) sump tank. The steam turbine is of the six stage impulse type with a hydraulic constant speed governor controlling steam flow. The steam passes through a trip valve, designed to shut off the steam instantly should a trip condition occur and then through the nozzle control valves. The turbines normally exhaust to the main condenser under vacuum conditions but can be set to exhaust to the auxiliary condenser. Labyrinth type seals are used at the end of the turbine rotors to prevent the steam in these regions from leaking to atmosphere and, more importantly, to prevent air from entering the turbine where its internal pressure is less than atmospheric. The seals are formed by radially slotting sections of labyrinth into the packing rings, which themselves are likewise slotted radially into the turbine upper and lower casings. The peak and trough edges of these labyrinths are located adjacent to corresponding square radial grooves machined into the rotor shaft. The clearances between the labyrinth edges and the rotor are minimized to reduce steam leakage between the inner (high gland steam pressure) areas and the outer (low gland steam pressure) areas. Adjacent axial clearance between the rotor and the labyrinths allow for the designed relative axial movement and expansion between the rotor and the casing.

5.1
Operation

Turbo Generator
Using No.1 Turbine Generator h) Stop turning and Disengage the electrically operated turning gear. i) Set the emergency trip device. The emergency trip device should be set by raising the reset lever for over speed emergency trip device. j) Open the governor valve with starting lever and Slightly Open the main stop valve. Allow the turbine to start and bring the speed up to 100rpm generator speed. Maintain this speed for approximately 5 minutes for warming. Check the running sound and Observe that the lubricating oil pressures remain constant, with a flow passing through the turbine and generator bearing sight glasses. k) Rise revolution to about 500rpm by gradually opening the main stop valve, maintain this revolution for about 5min. Ascertain whether the governor valve and the main stop valve would close momentarily by pushing the emergency button. Then Confirm that there is no rubbing noise or no abnormal sound inside the turbine as soon as turbine has tripped. l) Provided that the conditions are satisfactory, Reset the trip lever and Open the stop valve gradually and Increase the speed to the rated speed in 10 minutes. Since the critical speed of the turbine equates to approximately 810rpm generator speed, Pass through this speed range as quickly as possible. m) Check that all temperatures and pressures are reaching to normal level and Confirm that the priming LO pump stops automatically. (set 85 kPa) n) Confirming that the Woodward governor takes control, Fully Open the main stop valve and Return the main stop valve handle by a half turn forwards the original position from full opening. o) Electrically Load the generator and monitor on the ICAS. Connect the generator to the main switchboard by clicking on the TG icon on the ICAS screen to call up the menu. Click on the CONNECT icon on the menu and the generator will automatically parallel with the main switchboard.

Procedure for Manual Generator Connection


The generator can also be connected manually at the 6.6kV main switchboard panel by using the following procedure : a) Turn the Remote / Manual switch to the Local Manual position. b) Lower or raise the generator speed until the synchroniser light slowly revolves in the clockwise direction. c) Turn the breaker trip/close switch to the CLOSE position to connect the generator to the 6.6kV main switchboard when the synchroniser light passes the top position. d) Turn the Remote / Auto switch to RA (Remote / Auto) position to allow the ICAS to control the generator and balance the load with the No.2 turbine generator.

Preparation
a) Ensure that the lubricating oil level in the sump tank is correct, with no water content. When water is detected, change the oil by shifting it to the lubricating oil renovating tank for processing, using the lubricating oil purifier feed pump. Replenish the turbine sump tank from the turbine lubricating oil storage tank. b) Check that the circuit breaker is Open. c) Ensure that main steam stop valve, exhaust valve and packing steam valve are Closed. d) Check that the electrical supply is available to the priming LO pump motor. e) Check that control air is being supplied to the gland sealing steam controller. f) Ensure that cooling fresh water is available for the coolers from the Main Central Cooling System (CCS). g) Check that the gland condenser is operating with cooling condensate passing through it and that the gland exhaust fan is operating. h) Ensure that the turbine is free to turn.

Stopping
a) Transfer the electrical load and Confirm that the main air circuit breaker is Open. b) Close or Trip the main steam stop valve. c) Open all drain valves. (main stop valve casing and turbine casing) d) Engage the electrically operated turning gear immediately when the turbine is shut down and Rotate the turbine rotor for 10 hours to ensure uniform cooling. e) Ensure that the electric driven priming LO pump is started automatically when the lubricating oil pressure drops to 60kPa or the main steam stop valve is closed. Keep the priming LO pump running during motor turning operation. f) Close main steam supply valve 014VPA and open the drain valve fitted on main stop valve. g) Close the turbine exhaust valve. h) Shut down the gland packing steam. i) Close drain valves, cooling water supply and return valves for LO cooler and generator air cooler.

Starting
a) Start the priming LO pump at the local panel and Confirm that the bearing oil pressure is above 60kPa. b) Ensure the power source is on for emergency trip device. c) Warm up the main steam supply line. After confirming that the main stop valve for turbine is definitely closed, Open the drain valves fitted on main stop valve casing and Slightly Open the main steam supply valve 014VPA. When sufficiently warmed, Close the drain valves, Open the main steam supply valve gradually. d) Engage the electrically operated turning gear and Start turning the turbine and gearing, and Maintain for approximately ten minutes checking for abnormal sounds from the turbine. e) Ensure that the gland steam leak-off valve 008VPC is Open. f) Open the gland steam supply valve 062VPB from 0.17 MPa steam range and Provide steam to gland steam regulating control valve. Regulate the controller to maintain the sealing steam pressure between 10 and 20 kPa, keeping spill and leakage to a minimum (set point 20 kPa). g) When the turbine casing has warmed sufficiently, Open the turbine exhaust valve bypass 002VPC to build up the vacuum gradually in the turbine. When balanced, Open the exhaust valve 001VPC.

5.1a

Turbo Generator Overview

SPILL VALVE

PARTICULAR OF STEAM TURBINE RATED OUTPUT RATED SPEED (TURBINE) RATED SPEED (GENERATOR) MAIN STEAM PRESSURE MAIN STEAM TEMPERATURE EXHAUST PRESSURE : 3,200 kW : 10,045 rpm : 1,800 rpm : 5.88 MPaG : 510 : 6.7 kPaA (710mmHgV)

RECEIVER

MAKE-UP VALVE

L.O HAND PUMP

L.O.TEMP.CONT. VALVE PRIMING L.O.PUMP LO COOLER COOL. W.

L.O FILTER TURNING MOTOR

GENERATOR

LEVEL SEITCH

L.O.PRESS.REG. VALVE

MAIN STEAM INLET

GOVERNOR MAIN STOP VALVE STEAM TURBINE

GENERATOR

REDUCTION GEAR

TURNING MOTOR

SPILL VALVE

TURBINE EXHAUST

5.1b

Turbo Generator Alternator

7
6

9 10

20
19

21 22

23 24 25 26 27 28

29 30
31

5
4

11

18
17
12 16

Air

Air

32
33

Air

Air

34
r

13

35

3
2

14

36
38 37

1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
INSULATION LINER

15

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Ex. ARMATURE COIL

31 32 33 34 35 36 37 38

INSULATION LINER

OIL SIGHT
CT BOX

Ex. ARMATURE CORE


Ex. FIELD CORE

FAN FAN BOSS


THERMO METER

TACHOMETER

Ex. FIELD COIL

PEDESTAL
RESISTANCE BULB

ROTATING RECTIFIER

SHAFT OIL INLET PIPE


FRAME

ROTOR COIL
ROTOR CORE STATOR CORE

Ex. FRAME

4000kVA 6600V 60Hz 4P 1800min-1 0.8PF BRUSHLESS AC GENERATOR

COVER

SPACE HEATER

STATIC EXCITER
CABLE GLAND

DUCT PIECE
COOLER AIR DUCT

DAMPER BAR

BEARING CASE
SLEEVE BEARING

STATOR CLAMPER
DAMPER PLATE
ROTOR CLAMPER
STATOR COIL

TACHO GENERATOR COVER

5.1c

Turbo Generator Steam and Exhaust Systems


STEAM SUPPLY, EXHAUST AND GLAND SEALING SYSTEM
NOTE : Tag numbers for No.1 Turbo Generator are shown in this drawing. Tag numbers for others are referred to Section 3 Piping System in this Manual.
PIC

SPILL V.

PI 223

PAH 223

PAL 223

MAKE UP V.
062VPB

RECEIVER

0.27MPa STEAM

064VPB

TO GLAND CONDENSER
008VPC

MAIN STEAM

014VPA

GEAR BOX

TURBINE
EXHAUST ESD 215 PS PAH 222 PS P

1ST STAGE

PM 221

1ST STAGE

OIO 821

OIS 821
001VPC

RO 821

021VPC

TO MAIN CONDENSER

TO AUX. CONDENSER

002VPC

5.1d 5.1d Turbo Generator Lubrication and Control Oil Systems Turbo Generator Lubrication and Control Oil Systems
MAIN STEAM

MAIN STOP VALVE

TRIP COIL

GOVERNOR MOTOR

LUBRICATING AND CONTROL OIL SYSTEM

TRIP SOLENOID

S
TRIP OIL CYLINDER
ESD 216 ESD 214 XAH 246 T TM 232 TAH 232

WOODWARD GOVERNOR
P

POWER CYLINDER

TM 234

TAH 234 T

TM 235

TAH 235 T T

TAH 233

TM 233

TURNIG MOTOR

LS

TURNING MOTOR
XAH ESD 247 217

TURNING MOTOR

M
ESD 213 ASTP 203

TURBINE RED. GEAR

SSS CLUTCH
(Synchro-Self-Shifting)

PS TM 236 TAH 236 T T TAH 237 TM 237 TM 241 TAH 241 T T TAH 242 TM 242

PS

FOR PRIMING L.O. PUMP P PAL 224 PI 224

GENERATOR

TM 231 TAH 231 T

COALESCIMG FILTER

DPAH 225

DP

T.C.V. P.R.V. T

LAL 248 FS

MAIN L.O.PUMP HAND PUMP

L.O.PRIMING PUMP

093VPG

COOL. F.W.

L.O.COOLER

L.O.SUMP TK

5.2 Diesel Generator


Specification Engine : Maker : Type : Number of units : Number of cylinders : Cylinder bore : Piston stroke : Engine speed : Rated output : Alternator : Maker : Type : Capacity : Yanmar Co.,Ltd. 6EY26L Four cycle single acting, turbo-charged, trunk piston 2 sets 6 cylinders 260 mm 385 mm 720 rpm 1,730 kW Taiyo Electric Co.,Ltd. HPW 558C-10 6,600V, 3ph, 60Hz, 2,000kVA(1,600kW),0.8pf

Descriptions
There are two diesel generators, operating in the medium speed range, which supplies electrical power for the ship. The engine is of the unidirectional trunk piston type, has six in-line cylinders, is turbocharged, operates on the four stroke cycle and is normally powered by marine diesel oil. The diesel generators are used as required and are on automatic standby, which are set to starting priority 1st and 2nd, when stopped. Under normal circumstances the turbine generators supply electrical power and the diesel generators are set to cut in should the turbine generators fail to meet the electrical demand, or is started if the turbine generators are shut down for any reason. The engine driven jacket (high temperature) cooling water pump discharges engine jacket and cylinder head cooling water spaces. At the outlet from the engine the water flows to a pneumatically operated valve which maintains the HT cooling circuit at the correct temperature. If the cooling water temperature of the engine outlet is below the normal operating temperature, the cooling water back to the high temp. FW pump suction. When the cooling water outlet temperature reaches the operating temperature, the cooling water will back to the fresh water cooler via cooling FW pump, thus maintaining a constant temperature. The ICAS controls the three-way valve and enables a set temperature to be maintained in the cooling water supply system.

Starting Air System The engine is started by means of air motor starter located at the driving end. A blocking valve prevents the air start system from operating when the turning gear is engaged. The master starting air solenoid is activated when the start signal is sent by the power management system for an automatic start or a manual start is initiated. The master solenoid valve directs to the air motor starter. The main starting valve may be operated by the pushbutton at the local starting position or pneumatically by a solenoid valve when starting the engine remotely or automatically. The engine cannot be started whilst the turning gear is engaged CAUTION This starting air valve solenoid pushbutton must not be operated whilst the engine is running.

D/G Cooling Fresh Water Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 1 set / engine Centrifugal, vertical 90m3/h at 20m total head 440V, 7.5kW, 1,800 rpm

The low temperature fresh water is supplied to the charge air cooler, lubricating oil cooler and alternator air cooler. The fresh water temperature supplied is controlled by a three-way air actuating mixing valve is located at the fresh water cooler outlet. The ICAS controls the three-way valve and enables a set temperature of 37 C to be maintained in the cooling water supply system. Both fresh water coolers are cooled by two 100% identical sea water pumps. One pump is normally selected as the duty pump and the other pump selected as the standby pump to start automatically should the duty pump fail to maintain the correct water supply pressure. Pumps may be started and stopped locally but are normally set to remote operation for control via the ICAS. The duty pump is started manually at the ICAS mimic diagram for the D/G cooling system and the other pump is selected for automatic operation to act as the standby pump.

D/G Cooling Sea Water Pump Maker : No. of sets : Type : Capacity : Rating : Teikoku Machinery Works, Ltd. 2 sets Centrifugal, vertical 200m3/h at 25m total head 440V, 22kW, 1,800 rpm

Fuel System Turbocharger System The engine is fitted with an exhaust gas driven turbocharger. The turbocharger draws air from the engine room via a suction filter and passes it through a charge air cooler, before supplying the individual cylinders via the air box. The engine fuel oil supply rail is supplied from the generator engine fuel oil preparation and supply system. The generator engine is supplied with marine diesel oil (MDO) from the segregated fuel system. The fuel oil feed pump of each engine takes suction from the respective generator engine DO service tank via a set of filters, flow meter. Each cylinder has an injection pump which delivers the fuel oil under high pressure through the injection pipe to its associated injection valve. Cams on the camshaft operate the injection pumps.

D/G Cooling Fresh Water Cooler Maker : No. of sets : Type : Cooling water flow : Fresh water temp. : Hisaka Works Ltd. 1 set / engine Sea water circulated plate 200 m3/h 37

Cooling Water System All cooling water requirements for the generator engine are provided by water from the low temperature fresh water cooling system. Each engine is cooled by a dedicated closed circuit fresh water cooling system composed of a cooling fresh water pump and a plate type fresh water cooler independent from the ships central fresh water cooling system. The generator engines cooling system is divided into high temperature (HT) and low temperature (LT) circuits.

D/G Cooling Fresh Water Expansion Tank Capacity : 1.0 m3

Lubricating Oil System All running gear of the engine is force lubricated by the engine driven gear type pump. The pistons are also supplied by oil as a cooling medium. A priming pump which is run continually whilst the engine is stopped supplies oil to the bearings and other running gear. This reduces wear on the engine in the period between the engine starting and the engine driven pump building up lubricating oil pressure. The priming pump is normally switched to automatic mode when the engine is selected for standby. The priming pump stops automatically when the engine is running and the main lubrication pump is delivering oil.

5.2 Diesel Generator


The engine driven pump and the electrically driven priming pump both take suction from the engine sump and discharge through a cooler, an automatic filter set to the engine oil supply rail. The temperature is controlled by a three-way thermostatic control valve, which regulates how much of the oil passes through the cooler. Procedure to Start the Diesel Generator Engine Locally a) Ensure that the engine is ready for starting by completing the procedure above. b) At the local control panel turn the selector switch from REMOTE to LOCAL and manually start the engine by pressing the pushbutton on the main starting valve. Allow it to run up to normal speed. (Note : A pneumatically operated start fuel limiter optimises fuel injection during the acceleration period; the speed of the engine controls the start fuel limiter.) c) Make a thorough check of the engine to ensure that there are no leaks and the engine is running smoothly and firing on all cylinders. d) Check that the LO pressures and temperatures are normal. e) Check that the pressure drop across the filters is normal. f) Check that the FO pressure is normal. g) Connect the generator engine to the switchboard. h) Ensure that the engine temperatures and pressures remain within normal limits as the load is applied to the engine and the engine heats up. i) Check the exhaust gas temperatures for deviation from normal. j) Check the exhaust gas for smoke. k) Keep the charge air temperature under control. Engine Control Procedure to Manually Stop the Diesel Generator Engine a) Before stopping, run the engine off load for a few minutes for cooling down purposes. b) Actuate the local stop device. Under normal circumstances the engines should be set to AUTO operation so that they may be started and stopped by the power management system (PMS) to allow for automatic operation of the electrical power supply. The diesel generator starting and stopping is normally controlled by the power management system (See 5.4.1 Electrical Equipment). Alarms Sensor PT DPS PS PT PT PS PS TR TR TS TR Tag No. 291 293 294 295 296 297 298 301 302 303 304 Function Set point

Procedure to Prepare the Diesel Generator Engine for Starting a) Set the engine to LOCAL control. b) Set up the fuel oil service system. Both fuel systems are to be set normally. c) Set up the cooling water system. The cooling systems for both engines are to be set normally. d) Check the level of oil in the sump and top up as necessary with the correct grade of oil. e) Switch the generator engine priming LO pump to AUTOMATIC operation and check that the lubricating oil pressure builds up. The engine should be prelubricated at least 2 minutes prior to start. f) Check the pressure before and after the filters. g) Check the governor oil level. h) Check the air pressure in the starting air reservoir. i) Turn the engine at least one complete revolution using the turning gear with the cylinder indicator cocks open. Remove the turning gear. j) Vent the jacket cooling water space. If any part of the engine has been drained for overhaul or maintenance, check the level in the fresh water cooling expansion tank and refill with fresh water if necessary. k) Open the vent on the cooling water outlet line on the generator air cooler, and close it again when all air has been expelled. If maintenance work has been carried out on the engine, start the engine locally as below, prior to switching the engine to automatic operation. l) Check that all fuel pump indexes are at index 0, when the regulating shaft is in the STOP position. m) Check that all fuel pump control linkages are free to move full distance and return to their original stop positions when released. n) Switch the engine to AUTOMATIC operation.

Engine inlet LO low PA L 400kPa pressure LO filter high differential D P A H 9 0 k P a pressure Priming LO low pressure PA L 20kPa Starting air inlet low pressure Jacket cooling water inlet low pressure Control air low pressure LT cooling water inlet low pressure Engine inlet LO high temperature Jacket cooling water outlet high temperature Jacket cooling water pre-heater over heat T/C exh. gas high temperature PA L 1 . 4 7 M P a PA L PA L PA L TA H TA H TA H TAH 0.13MPa 0.65MPa 0.13MPa 65 95 60 630

Emergency Stops Tag No.


278 279 280

Description Overspeed Lubricating oil low pressure Cooling water outlet high temperature

Set Point 806 - 828 rpm 350 kPa 100C

5.2a

Diesel Generator Alternator

5
4

7
8
9

17

18 19 20 21

22 23 24 25 26
27
Air

16
15
10 14

28
29

13
Air ir

Air

30

31

2
1

11

32 33

12

34
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
INSULATION LINER OIL SIGHT

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Ex. FIELD COIL

31 32 33 34 35

RESISTANCE BULB

ROTATING RECTIFIER
ROTOR COIL

SHAFT
OIL INLET PIPE

35
2000kVA 6600V 60Hz -1 10P 720min 0.8PF BRUSHLESS AC GENERATOR

PEDESTAL
THERMO METER

ROTOR CORE

FRAME

Ex. FRAME

STATOR CORE

SPACE HEATER

COVER
STATIC EXCITER

DUCT PIECE
COOLER

CABLE GLAND
DAMPER BAR BEARING CASE

AIR DUCT
STATOR CLAMPER

STATOR COIL

SLEEVE BEARING
COVER Ex. ARMATURE COIL Ex. ARMATURE CORE
Ex. FIELD CORE

DAMPER PLATE
FAN ROTOR CLAMPER
END COVER

FAN BOSS

5.2b

Diesel Generator Piping Systems


PIPING SYSTEM
(FOR NO.1 DIESEL GENERATOR)
COOL. S.W. H.T. COOL. F.W. L.T. COOL. F.W. LUB. OIL
744VPG

LAL 741

COOL. F.W. EXP. TK

TO FUNNEL

GEN. ENG. D.O. SERVICE TK 50

600

AIR SEPARATOR

25
ACCUMULATOR

723VPL

LAH 306

EXH. GAS FUEL OIL

701VPL

ACCUMULATOR

15

TO F.O.DRAIN TK
DPAH

40

DP
702VPL 703VPL

F.O.FEED PUMP 40 40
704VPL 721VPL

DP
(42)

FS
004JPL (60 MESH)

40
OUT IN

T
P
G

F.O.LEAK TK
TO F.O.DRAIN TK

EXH.GAS

600
G

TM 304 TAH 304

T
LAL 302

INJECTION PUMP GENERATOR


PM 296 G TM 302 TM 311 TAH 311

T
T/C
RO SA FIRE 284 RM ASS 284 284

CENT.FILTER

L.O.SUMP TK

PAL 296

STATOR COIL

TM 313 TM 314

TAH 313 U TAH 314 V TAH 315 W TM 316 TAH 316 TAH 312 TM 312

867

TAH 302 TAL 867 TIC 867

T T

ESD 280

F.W. LEAK

XA 307

TM 315

L.O.PUMP

L.O PRIM.PUMP M

AIR CLR F.W.PUMP


TM 317
725VPG

TAH 317

CAM SHAFT

CAM SHAFT

BEARING

TAH 866

TM 866

TIC 866

125

A
866

BEARING

721VPG

65

704VPG

PAL 298

FOR PRIMING ESD PS 279

PAL 291

PM 291

65

AIR CLR

100

100

SA 639

RM 639

RO 639

AST 639

AC 639

100
TM 301 TAH 301 DPAH 293
713VPH 707VPH

D/G COOL.S.W. PUMP

P
150 125
701VPG 708VPH 727VPG 711VPH

C
NO.2
703VPH

DP

125

705VPH

125

100

FROM NO.2 D/G F.W. CLR

CHANGEOVER

P
706VPH 704VPH

C
NO.1
702VPH

100

D/G COOL.F.W.CLR
RO 625 RM 625 SA 625

T
L.O. CLR

C
722VPG

DP 125

100

125
725VPG

TO NO.2 D/G F.W. CLR

SEA BAY

150

D/G COOL.F.W. PUMP

125

AUTO FILTER

PS PS 639

5.3

Emergency Diesel Generator


An electric starter motor is also provided. The power is supplied by batteries which are on constant charge while the ship is in service. The emergency generator control panel provides monitoring information of the emergency generator. The local panel has a number of lamps which illuminate to indicate the status of various operating parameters. The emergency generator control panel allows for selection of the operating mode and for local starting of the emergency generator. Normally the emergency generator will be selected for automatic starting so that it operates automatically in the event of the failure of the main electrical supply system. The engine should be started once a week and run up to full load monthly. Whenever the engine has been started, the fuel oil tank must be checked and refilled if the level has dropped to or below the 18 hour operation level. The gas oil tank has a capacity to allow the generator to run for 18 hours on full load. The tank has level monitoring which generates Low level alarm. The tank is larger than the SOLAS requirement so that the generator can run for longer periods before the tank requires replenishing.

Specification Engine : Maker : Type : Number of units : Number of cylinders : Cylinder bore : Piston stroke : Engine speed : Rated output : Alternator : Maker : Type : Capacity : STX Engine Co.,Ltd. KTA38DMGE Four cycle, turbocharged, direct injection 1 set 12 159 mm 159mm 1,800 rpm 768kW

Procedure to Manually Start the Emergency Diesel Engine (Using the Air Starter)
a) Ensure that the engine AUTO / MAN switch is turned to the MAN position at the control panel. b) Check the LO, cooling water and fuel as in the procedure for automatic start. c) Ensure that the air receiver is fully charged and that the air hose to the air starter is secure. d) Press the START button on the alarm control panel, the engine will now run up to speed. e) Check that the engine is running smoothly. Check the engine oil pressure, cooling water pressure and rpm, investigate any abnormalities. f) Close E /G ACB if required. g) After the run period, press the STOP button on the alarm control panel, the engine will now shut down. h) When the engine has stopped, turn the control switch to the AUTO position to restore the engine to automatic standby.

Taiyo Electric Co.,Ltd FBT 45DL-4 450V, 3ph, 60Hz, 787.5 kVA(630kW), 0.8pf

Descriptions
The emergency diesel generator is a self-contained diesel engine located in the emergency generator engine room located on the starboard side of the engine room casing, A deck. The generator set will start automatically on power failure from the main electrical supply system and couple to the emergency switchboard to maintain an electrical supply to essential services. The generator set will also be used to get the ship under power from dead ship condition. It will enable power to be supplied to essential services selectively without the need for external services such as starting air, fuel oil supply and cooling water. The engine is a 12 cylinder V-type turbocharged engine with a self-contained cooling water system. The cooling water is radiator cooled and circulated by an engine driven pump. A thermostat maintains the correct water outlet temperature from the engine. Air is drawn across the radiator by an engine driven fan. The cooling water is circulated by an engine driven pump, which also supplies cooling fresh water to the lubricating oil cooler. The engine running gear is force lubricated, an engine driven gear pump drawing oil from the integral sump and pumping it through the cooler, then through a filter before being supplied to the lubricating oil rail. The engine is normally started by air. A starting air reservoir supplies air to the starting air motor which drives the toothed rim of the flywheel by means of a pinion.

Procedure to Prepare the Emergency Diesel Engine for Automatic Starting a) Ensure that there is power at the emergency generator control panel by checking that the POWER ON light is illuminated. b) The engine AUTO/MAN switch is turned to the MAN position to prevent starting of the engine whilst checking is taking place. c) Check the level of LO in the engine sump and top up as necessary with the correct grade of oil. d) Check the level of water in the radiator and top up as necessary with clean water. e) Check the level of DO in the emergency generator DO service tank and top up as required. f) Ensure the fuel oil supply valve to the diesel engine is open. This valve is normally left open when the engine is stopped. g) Ensure that the starting battery is fully charged. h) Turn the operation switch on the emergency generator local panel to the AUTO position, this will allow for emergency starting should the main electrical power system fail. When normal electrical power is restored the emergency generator will be stopped by ships staff. i) Check the alarm panel on the control panel to ensure that there are no alarm conditions. Press the TEST and RESET buttons on the alarm control panel.

Procedure to Manually Start the Emergency Diesel Engine (Using the Electric Starter)
a) Ensure that the AUTO / MAN engine selector switch is turned to the OFF position at the control panel. b) Unbolt the air starter from its housing and replace it with the electric unit. Ensure the electric starter is secure in the housing. c) Observe all the checks as for automatic start. d) Put and hold the START-OFF toggle switch on START position at the instrument panel. e) Put the crank toggle switch to ON at the instrument panel.. f) Put the START-OFF toggle switch on START position at the instrument panel. g) Close E / G ACB if required. h) After the run period, put the STOP START-OFF toggle switch on the instrument panel, the engine will now shut down. i) Restore the air starter and set the engine to AUTO operation with the air starter.

5.3a

Emergency Diesel Generator Overview

5
6
7
8
1. Aftercooler Housing 2. Aftercooler Core 3. Aftercooler Coolant Supply
4. Aftercooler Coolant Return 5. Coolant Return to Radiator 6. Coolant Transfer Tube (Head to Head)

7. Thermostat

8. Coolant Filters 9. Oil Cooler

10. Water Pump


11. Coolant Supply from Radiator 12. By-Pass Tube 13. Coolant in Block "V"
14. Cylinder Liner

15
14

15. Cylinder Head

13

12

11

10

5.3b

Emergency Diesel Generator Alternator

10
1
24

11

12

13

14

15

16

17
18
Air

9 8
7
6
Air Air

19
20
21

23

5
4

22

1 2 3 4 5 6 7 8 9 10

AIR COOLER

11 12 13 14 15 16 17 18 19 20

TERMINAL BOX
DAMPER BAR
ROTATING RECTIFIER

FRAME STATOR CORE

21 22 23 24 25 26 27

FAN BOSS

SHAFT END BRACKET(BEARING SHIELD)


SEARCH COIL

DUCT PIECE
ROTOR CORE

BALL BEARING
Ex. ARMATURE COIL

DAMPER PLATE
STATOR CLAMPER

787.5kVA 450V 60Hz -1 4P 1800min 0.8PF BRUSHLESS AC GENERATOR

Ex. FIELD COIL


Ex. ARMATURE CORE
Ex. FRAME Ex. FIELD CORE

STATOR COIL
ROTOR COIL

ROTOR CLAMPER FAN

5.3c Emergency Diesel Generator Piping Systems 5.3c EMERGENCY DIESEL GENERATOR PIPING SYSTEM

EMERGENCY GENERATOR ROOM

SILENCER

EMERG.GEN. D.O.SERV.TK
203VPG
EMERGENCY GENERATOR SET AUTO START CONTROL PANEL
SOURCE

AUTO START RUNNING STAND-BY L.O. LOW PRESS. ALARM

START FAIL L.O. HIGH TEMP. ALARM

OVERSPEED TRIP BATTERY CHARGER FAIL

L.O. LOW PRESS. TRIP C.F.W. LOW PRESS. ALARM

C.F.W. HIGH C.F.W. HIGH TEMP. TEMP. TRIP ALARM

228VPL
LAMP & BELL TEST

"AFTER ENGINE OVERSPEED LOCAL ENGINE PANEL SWITCH (OFF-RUN-START) MUST BE PUT TO OFF AND THEN BACK TO RUN POSITION TO RESET"

START

STOP

RESET

ENSURE SWITCHES ARE RETURNED TO "AUTO" AFTER TESTING

T
LAL 729

BELL STOP

POWER SOURCE
ON OFF

MANUAL - AUTO
MAN AUTO

E/G Mode - Test Mode

E/G

TEST

210VPB

EM'CY TRIP
(PUSH LOCK TURN RESET)

FS

202VPG

EMERG. GENE. ENG.


AIR CLR F.W.HTR
T
PISTON CLG

211ZPD

T/C

401VPL

RADIATOR

CORROSION RESISTOR

PAL 358

PAL 364

START AIR RESERVOIR

CT

MAIN BRG

DU

ESD TAH 358 363


T

PISTON CLG

AIR CLR

T/C

PAL 754

EX

H.

F.W.HTR
CORROSION RESISTOR

OIL PAN
TAH 366

S
L.O.CLR AIR MOTOR

431VPE

L.O.PUMP INJECT. PUMP

432VPE 433VPE

F.W.PUMP F.O.PUMP

PAL 363

423VPE 201VPG 424VPE 402VPL 425VPE

149VPE

412VPE

START.AIR COMPRESSOR

302VPL

COFFERDUM

CONTAMI. DRAIN F.W. SERV. TO OVERFLOW TK G.S. AIR D/G START AIR 1.0MPA STM

TO G/E D.O. SERV. TK FROM D.O. TRANS. PUMP

5.4a

Power Distribution System


EG

Restrictions on the circuit braker operation


(1) Up to three (3) of CM1, CM2, BTC1 and BTC2 are permitted to close in order to prevent "Loop" distribution system. (2) Only one (1) of closing condition, EG, SC, BT-LE1 AND BT-LE2 are permitted to prevent parallel running with Ship's service generators and shore generators. (3) SC is not permitted to close during Ship's generator running. When the vessel supplies the power to another vessel, this interlock must be released by selecting "Ship to ship from SWBD" mode at shore connection panel of ESB. (4) Up to three (3) of TM1, TM2, BT-LM1 and BT-LM2 are permitted to close in case of one (1) or both of BT1 and BT2 open condition. All of TM1, TM2, BT-LM1 and BT-LM2 are permitted to close allow supply changeover without a blackout of LVMSB in case of both of BT1and BT2 closed condition. If the ring main condition (all of TM1,TM2, BT-LM1 and BT-LM2 are closed) continuous for one (1) minute, an alarm activates on the ICAS as a cution for the operator. (5) The ICAS does not allow to operate T/G1, T/G2, E/G, BT1, BT2, BT-EL1, BT-EL2, EG and SC.

EM'CY SWBD ESB

EG

450V
BT-EL2 BT-EL1

SC

D/G2
SCB
Shore Connection Box

T/G2

T/G1

D/G1

LE2

NO.2 440V SWBD LVMSB2 450V


BT-LM2 TM2

NO.2 6600V SWBD HVMSB2 6600V


TRM2

DG2

TG2 BT2 BT1

TG1

DG1

NO.1 6600V SWBD HVMSB1 6600V

NO.1 440V SWBD LVMSB1 450V


TM1 BT-LM1

LE1

MC2

MC1

TRM1

EM'CY 220V FEEDER


ST ST Starter ST ST

T31HV2

WSP
Water Spray pump

BP No.2

Ballast Pump

Ballast Pump

BP No.1

BP No.3

T31HV1

Galley & Laundry Equipment NO.2 GSP

Galley Equipment NO.2 CARGO SWBD HVCSB2 6600V NO.1 CARGO SWBD HVCSB1 6600V
ST ST

NO.2 GSP

CM2 BTC2

CM1 BTC1

ST

ST

ST

ST

ST

ST

Cargo Pumps 4 sets

CP

VRC No.2 Vapour Return


Compressor

No.1 Vapour Return Compressor

VRC

CP

Cargo Pumps 4 sets

No.2 CARGO GSP

No.1 CARGO GSP

NO.4 GSP

NO.3 GSP

5.4.1

Electrical Equipment
6.6 kV Main Switchboards The 6.6 kV main system consists of two switchboards, connected by two transfer breakers. The 6.6 kV main switchboard is arranged in two interconnected sections. To enhance the security of supplies, each section is located in a separate switchboard room in the engine room. Each section consists of a bus-tie panel, diesel generator panel, turbo generator panel, synchro. panel, feeder panel and transf. panel. The 6.6 kV main turbine generator panels and 6.6 kV diesel generator panels are equipped with an ammeter, voltmeter, active power meter (kW), reactive power meter (kVAR) and power factor meter. Each feeder panel can supply electrical power to the cargo and 440V switchboards, and starters for motor drives of the ballast pumps and water spray pump as shown on diagram. These feeder circuits are sized to accept the full load requirements of the respective switchboards, and so provide total redundancy should any one feeder panel be unavailable due to a fault. Off-load disconnecting switches are provided between each generator section. 440V Main Switchboards The 440V main switchboard is arranged in two interconnected sections. To enhance the security of supplies, each section is located separately from the 6.6 kV main switchboard partitioned with wire net wall in the switchboard room. The port and starboard 440V main switchboards feed the emergency switchboard and also the accommodation and engine 230V feeder panel via 450 / 240V transformers. Each 440V and 230V distribution circuit is protected against over current and short circuit by a molded case circuit breaker. These are fitted on the switchboard or panel board with inverse time over current and instantaneous short circuit trip units enclosed within the casing. Group starter and distribution boards are provided in suitable locations to supply the various powers, heating, lighting, communication and navigation equipment throughout the vessel. It is possible to perform a cold start of the vessel, that is, from total blackout, by back feeding from the emergency switchboard to the main 440V switchboard. This will provide sufficient power to start the necessary equipment to enable running of the turbine generator. (See 5.4.2 Main Switchboard and Generator Operation).

Generating Plant The electrical power generating plant consists of the following : Main Steam Turbine Generator No. of units : 2 sets Rating : 6,600V, 3ph, 60Hz, 4,000 kVA, 0.8pf Main Diesel Generator No. of units : 2 sets Rating : 6,600V, 3ph, 60Hz, 2,000 kVA, 0.8pf Emergency Diesel Generator No. of units : 1 sets Rating : 450V, 3ph, 60Hz, 787.5 kVA, 0.8pf Only one steam turbine generator is used during normal sea going conditions. Two generators are required when manoeuvring, using the vapour return compressors and unloading cargo. Power Distribution System

The power distribution network consists of two 6.6 kV switchboards, two 6.6 kV / 450V cargo switchboards, two 440V switchboards, the 440V emergency switchboard, one engine room 230V feeder, one accommodation 230V feeder and one 230V emergency feeder.
The normal operating condition of the network is as follows :

The load sharing of the both turbine generators is controlled from the Integrated Control and Automation System (ICAS). The ICAS is fed from its own dedicated Uninterruptible Power Supplies (UPS), which are in turn fed from the main and emergency 230V networks.
The main control voltage for the operation of the 6.6kV main switchboards is 230V AC and 110V DC supplied from a separate freestanding 110V DC UPS with battery banks.

Emergency Switchboard The emergency switchboard is located in the emergency switchboard room. The switchboard is normally fed from one section of each 440V main switchboard and with facility to supply the power from emergency generator.

The port and starboard 6.6kV main switchboards will be linked, i.e. the bus-tie breakers will be closed effectively forming one 6.6kV main switchboard. One or both of the turbine generators and/or the diesel generator can feed the network. The port and starboard 6.6 kV cargo switchboards are fed from the breakers on the port and starboard 6.6 kV main switchboards. The 450V feeder for cargo auxiliaries are fed via the port and starboard High Voltage (HV) 6,600 / 450V cargo service transformers. The port and starboard 440V main switchboards are fed via the port and starboard High Voltage (HV) 6,600 / 450V engine service transformers respectively. The engine room and the accommodation 230V feeders can both be fed via Low Voltage (LV) 440 / 230V transformers from the port and starboard 440V main switchboards. Control of the safety interlocks is provided by the Power Management System (PMS) to prevent an undesirable closed loop in the network on the primary side of the main transformers. If in local control, the breakers are interlocked to prevent this situation.

Cargo Switchboards The 6.6 kV and 440V cargo switchboard is arranged in two interconnected sections. To enhance the security of supplies, each section is located in a separate room on the upper deck in the accommodation. Each 6.6 kV cargo switchboard section consists of a bus-tie panel, 6,600V feeder panel. Each 440V cargo switchboard section consists of feeder panel.
Each 6,600V feeder panel supplies the power to starters for motor drives of the cargo pumps and high duty gas compressors and 450V cargo switchboard for low duty gas compressors and cargo auxiliaries services via 6,600 / 450V transformers.

Large Motor Starters In the port and starboard 6.6kV main switchboards, all incomers and feeder breakers/vacuum contactors are equipped with an earthing switch on the field side for maintenance purposes. The earthing switch is mechanically and electrically interlocked with the breaker, preventing the breaker from being closed if the earthing switch is connected and vice versa. The 6.6kV bow thruster motor is started and stopped using an auto-transformer starter. The 6.6kV cargo pumps have starting and bypass contact systems as well as a soft starter group start.

The tie lines provide both redundancy and supply continuity in the event of any system failures.

5.4.1

Electrical Equipment
Power Management System (PMS) The PMS controls the load sharing of the turbine generators and the starting, connecting and load sharing of the diesel generator. In the event of a blackout the diesel generator will start automatically if set in standby operation, and feed the main switchboard. If both diesel generators fail, the emergency generator will start automatically and feed the emergency switchboard. The PMS can start and stop the main diesel generator to provide extra generating capacity as required. The steam turbine generators cannot be started and stopped automatically due to the nature of their local starting and stopping procedures.

Standard Motors The 440V motors are generally of the squirrel cage induction type with a standard frame designed for AC 440V three phase 60Hz supply. The exceptions are the motors for domestic services and small capacity motors of 0.4kW or less. Where continuously rated motors are used, the overload setting ensures the motor trips at 110% of its full load current by an ambient-compensated over current relay of thermal type with three current elements. The motors in the engine room are of the totally enclosed fan cooled type.

440V Starters The 440V starters are generally of across-the-line type. All the group starter panels are situated in the main switchboard rooms, with the exception of the deck group starter panels.

The PMS performs the following main control functions :


1) 2) 3) 4) 5) 6) Generator control and monitoring Load dependent start Blackout restart Load sharing/net frequency control Start blocking of heavy consumers Preferential trip

Sequential Restarting Essential service motors, which were in service before a blackout, are started automatically on recovery of the main bus voltage or emergency bus bar voltage. They will start according to the predetermined restarting sequence. Motors that were selected for duty before the blackout are automatically returned to duty after the blackout. Similarly, motors selected for standby are automatically returned to standby. (See 5.4.6 Preferential Tripping and Sequential Restarting)

The generator PMS has the following facilities : 1) Short circuit, over current, overload and reverse power tripping protection for the generators and network via operation of the circuit breaker, circuit breaker under voltage trip or network preferential trips 2) Power, voltage, frequency and current measurement (local and remote) of the generators and main bus / network

Preference Tripping
Non-essential loads are interrupted automatically in the case of an over current on any one of the main generators. This provides continuity of supply to the essential consumers. (See 5.4.6 Preferential Tripping and Sequential Restarting)

3) Earth monitoring 4) Control of the number of running generators in accordance with the ships power demand 5) Automatic blackout restart and connection of generators 6) Adjustment and storage of operational values, settings and alarms via panel display and keypads 7) The blocking of large motors until the number of running generators is sufficient to supply the motor start current and ships power demand. In this case, the standby diesel generator is started and synchronized automatically and shut down once the low demand is re-established. 8) Frequency, automatic control ensures the supply frequency remains at 60Hz independent of the load.

5.4.2

Main Switchboard and Generator Operation


Transfer Circuit Breakers The transfer breakers can be operated from the switchboard (local control) and from the ICAS (remote control). Local and remote selection is done via separate buttons on the switchboard front panel. The bus-tie breakers will operate in pairs. Check synchronizers are provided for synchronizing the breakers when voltage is present on both sides of the breakers. Upon a close command from the operator station, the ICAS will activate the synchronizing unit which will perform engine speed adjustment and carry out volt / frequency / phase check before closing the breaker. If one or both sides of the bus-tie breaker are without voltage when the close command is given, the check synchronizer is bypassed and the breaker is closed immediately. The bus-tie breakers work as a pair, so if one breaker trips, the other one in the pair will be opened. In the event that both the 440V main switchboards are being fed from both the 6.6kV main switchboards, the 440V supply breakers are allowed to close. Start Blocking of Heavy Consumers When an electric motor start request is made from the ICAS, the PMS will check whether the available power is sufficient to allow a start of the electric motor. If not, a standby generator start request is given. When the capacity of the power plant is sufficient and other start conditions are fulfilled, an electric start order is given. If sufficient capacity is not reached within the time-out specified time, the motor start order is timed-out and the start has failed. The system will prevent more than one heavy consumer starting at a time. To prevent overloading the power generation plant, the PMS will start block the following consumers : 6.6kV Cargo Switchboard, Starboard Side Description Cargo pump 1, tank 1 Cargo pump 1, tank 2 Cargo pump 1, tank 3 Cargo pump 1, tank 4 HD compressor No.1 Blocking Limit 730kW 730kW 730kW 730kW 960kW
No. of Generators 2 2 2 2 2

The Electric Power Plant The electric power plant consists of two turbine generators, two diesel generators and one emergency diesel generator. These generators are controlled from the Integrated Automation System (ICAS). The two turbine generators cannot be set in standby mode and it is not possible to start them from the ICAS.

Generator Breaker Control When a generator is started and the alternator voltage is established, the alternator can be connected to the switchboard. When receiving a CONNECT command from the operator station, the Power Management System (PMS) will activate the synchronizing unit which will perform the turbine speed adjustment and volt / frequency / phase check before closing the circuit breaker. When closing the circuit breaker onto a dead bus the synchronising unit is bypassed by internal HV switchboard logic. A synchronising time-out alarm is given if the breaker is not closed within 30 seconds or 2 seconds during a blackout. In the event of an automatic start request, from the PMS or the diesel engine safety system, the synchronizing unit will be activated automatically and the generator will connect without operator intervention.

Time-Out 60 sec 60 sec 60 sec 60 sec 60 sec

Load Dependent Start / Stop The ICAS power management system will always ensure that the correct number of generators is connected, in accordance with the actual electrical power consumption. To enable the load dependent start / stop system, the load dependent start and the load dependent stop functions must be switched on and the diesel generator set to STANDBY. The load dependent start / stop function is based on the % load (kW) of the connected generator(s). The table below shows the initial parameters for the load dependent start / stop function for the diesel generator. No. of Generators Connected 1 (turbine generator) 2 (turbine generator) 3 (diesel generator) 4 (diesel generator) Start limit 1 84% 86% Delay Start time limit 2 30 sec 90% 30 sec 91% Delay time 10 sec 10 sec Stop limit Delay time

6.6kV Cargo Switchboard, Port Side Description Cargo pump 2, tank 1 Cargo pump 2, tank 2 Cargo pump 2, tank 3 Cargo pump 2, tank 4 HD compressor No.2 Blocking Limit 440kW 440kW 440kW 440kW 730kW
No. of Generators 1 1 1 1 1

Breaker Disconnection for the Diesel Generator A DISCONNECT command given by the operator will cause an automatic load reduction of the generator, provided the load sharing mode is either SYMMETRIC or ASYMMETRIC. When the generator load is less than 10% the PMS will give a signal to the switchboard to trip the generator circuit breaker. If the generator stops due to an automatic stop request, such as a low load, the generator downloading and breaker trip will be performed automatically, without operator intervention.

Time-Out 120 sec 120 sec 120 sec 120 sec 120 sec

The heavy consumers start block function can be switched on or off from an operator station. This is done separately for each switchboard. (Note : If the heavy consumers start block is switched off, the consumer will be started without checking the power available.)

Interlock of a Generator Breaker Operation The generator breaker will be blocked from closing by the PMS if any of the following conditions apply : 1) 2) 3) 4) Generator speed control in manual mode Busbar earth knife closed Generator breaker not ready Generator breaker tripped and blocked (start block must be manually reset)

65% 15 min 60% 15 min 55% 15 min

5.4.2

Main Switchboard and Generator Operation


Load Sharing e) Run the boiler until sufficient pressure is achieved. f) Start the turbine feed water pump : Start the auxiliary circulating pump Start the main lubricating oil pump Start the main feed turbine pump panel Start the drain pump Start the main condensate pump g) Start the turbine generator : Start the UPS for 6.6kV main switchboard Start the auxiliary lubricating oil pump h) Couple the turbine generator with the emergency switchboard for load transfer, couple the secondary (440V) transformer : Switch the relay synchronizing switch to position 2 Select the breaker control for the secondary transformer supply to position 2 (local) Adjust the turbine generator frequency to match the emergency generator frequency When the green light in the synchronizing relay is lit, press the button to connect the transformer secondary supply in parallel with the emergency generator supply Disconnect the interconnection switch between the main switchboard and the emergency switchboard Change the position of the key from position 2 to position 1 at the emergency switchboard Connect the interconnection switch between the main switchboard and the emergency switchboard i) Disconnect the emergency generator : Change over of power at the emergency switchboard from the emergency generator to the turbine generator will occur automatically upon detection of normal ships supply. After 5 minutes cooling down time, the emergency generator will stop automatically. j) Normal operation with the turbine generator running: Close all consumer breakers at the main and emergency switchboards. The load sharing mode can be selected individually for each generator and is based on active power (kW) measurements. Speed increase/decrease signals are sent to the speed governor during load sharing and net frequency control. The ICAS Power Management System allows the following load sharing options : 1 Symmetrical Load Sharing In this mode, the load of the generators running in parallel will be equal with a small (1%) dead band of rated power. 2) Manual Load Sharing When the diesel generator is selected for manual load sharing, the operator can give speed increase/decrease signals to the speed governor directly from the generator operation menu on an operator station. In this mode the PMS is not performing active load sharing of the generators. Manual load sharing cannot be selected when the generator is in standby mode.

Blackout Restart In the event of a blackout on the 6.6kV switchboard, the PMS will immediately give a start order to the diesel generator, if set in the standby condition. It will be connected to the dead busbar because the synchronizing unit is bypassed by the DIRECT CLOSE signal from the PMS. If there is a blackout on the port and starboard switchboards, the PMS will connect the diesel generator to the starboard switchboard. All circuit breakers are equipped with undervoltage relays and the PMS will reconnect the breakers after the diesel generator has started.

Cold Start of the Vessel from the Emergency Switchboard It is possible to perform a cold start of the vessel, that is from total blackout, by back feeding from the emergency switchboard to the main 440V switchboard. This will provide sufficient power to start the necessary equipment to enable running of the turbine generator.

Load Shedding Load shedding is not part of the ICAS and will be done by the switchboard logic. An alarm will be activated in the ICAS when the load is increased to above 90%.

Procedure a) Start the emergency generator set. It should automatically start as a result of a blackout. b) Connect the emergency generator to the emergency switchboard. It should automatically connect. c) Feed the main switchboard from the emergency switchboard : Change the position of the key from position 1 (Normal) to position 2 (Feedback) at the emergency switchboard. Automatic loading of the spring on the breaker for interconnection with the main switchboard in the emergency switchboard panel. Automatic connection of the interconnection breaker to the main switchboard located in the emergency switchboard panel

Turbine Generator Power Management System


Turbine Generator Control and Alarm Monitoring Unlike the diesel engine, the turbines must be started locally. The control from the ICAS is similar for both turbine generators and consists of the following main control functions : 1) Boiler Interaction When the boiler steam pressure drops to below 4.9 MPa, stem drum level rises to 150mm from normal or both boilers trip, an alarm will be activated and the diesel generator standby start will be initiated. 2) Monitoring of the Turbine and Generator The monitoring includes : LO temperatures and pressures of the turbine, gearing and generator bearings Generator winding temperatures 3) Turbine Stop A normal stop sequence of the turbine can be caused by : A stop request from the ICAS operator station after the generator has been downloaded to 10% load and the breaker has been disconnected The safety system of the generator is activated

WARNING
Before feeding the main switchboard from the emergency switchboard, all consumer breakers from the main switchboard and emergency switchboard must be open. d) Start one boiler : Start the control air compressor Start the cold start feed water pump Start the forced draft fan at low speed Start the FO burning pump Start the boiler gauge board Start the seal air fan Start the CCS fresh water pump Start the sea water cooling pump

5.4.2

Main Switchboard and Generator Operation


Disconnect by the ICAS The breaker disconnect can be initiated when the following apply : Disconnect request from an operator station Load dependent stop (if the generator is in standby mode.) Safety system of the connected generator activated (if the generator is in standby mode.) The breaker will be prevented from disconnecting when the following apply : Breaker in local control Internal blocking (e.g. not reset after downloading time-out.) Disconnect interlocked The opening of the generator breaker is possible when : Generator load <10% of generator nominal load No interlock active Two types of load reduction can be defined for the turbine generators : 1. Ramp down (%/second) and disconnect when the generator load is <10% of the nominal load. The ramp setting is set to 2%/second ( % of nominal load). 2. Reduce the load as fast as possible and disconnect when the generator load is <10% of the nominal load. A disconnection failure alarm is given if the Circuit Breaker Opened feedback is not confirmed within 5 seconds after open command. Low steam pressure at turbine generator (will start and connect to the busbar and share the load with the running turbine generator.) High exhaust back pressure at turbine generator (will start and connect to the busbar and share the load with the running turbine generator.) High boiler water level (will start and connect to the bus bar after the generator breaker in service has tripped..) Low voltage on main bus bar (will start and connect to the bus bar after the generator breaker in service has tripped..) High voltage on main bus bar (will start and connect to the bus bar after the generator breaker in service has tripped.) Low frequency on main bus bar (will start and connect to the bus bar and share the load with the running turbine generator.) Circuit breaker abnormal on running generator (will start and connect to the bus bar and shore the load with the running turbine generator.) Over current on running generator (will start and connect to the bus bar and share the load with the running turbine generator.) In order to start the diesel engine, the ICAS gives a start signal of 10 seconds. If the engine does not start in this time, a waiting time of 60 seconds is activated before another start is attempted. If the engine fails to start, a START FAILURE alarm is sounded and the start failure must be reset before a new start can be performed. The ICAS will fail to start the engine due to start blocking if : The safety system has caused a shutdown (pre-lubrication oil pressure is low). The turning gear is engaged. Bus bar earth knife closed Safety system of the diesel generator activated Once the generator starts the voltage will normally rise to 6,600V before the generator is available to connect to the busbar. The generator will be downloaded either automatically or manually from an operator station, to 10% of the nominal load before the breaker disconnects and the stop signal is given. If a load dependent stop is initiated, a cooling down period will be activated between the breaker disconnecting and the engine stop signal. The ICAS blocks the engine from stopping if the engine is in local control or not reset from a previously corrected alarm. A normal stop sequence of the engine can be caused by : Stop request from an operator station. Load dependent stop from the PMS if the generator is in standby mode.

Alarm Monitoring The following alarms are generated : A Disconnect Failure is given if the circuit breaker opened feedback is not confirmed within 5 seconds after the open command. An RPM Failure alarm is given if the running indication disappears while the generator voltage is normal or the generator breaker is closed. An Inconsistency alarm sounds if the circuit breaker is closed and the turbine generator is stopped. An Error alarm sounds if the turbine generator is started / stopped in remote mode without the corresponding command, or the circuit breaker position is changed without command. A Synchronizing Time-out alarm will be given if the synchronizing time exceeds 30 seconds. Upon successful start, the generator voltage would normally rise to the rated voltage. If the rated voltage is not established within the Volt / Frequency OK time-out values (10 seconds) after engine start a Voltage Not Established alarm will be given.

Turbine Generator Breaker Connect / Disconnect


Connect by the ICAS The generator breaker connect can be initiated when a connect request is sent from an operator station. The breaker must be ready before it can be closed. A Circuit Breaker Ready signal is sent to the ICAS. The generator breaker can be closed when all the following conditions apply : Turbine is running Circuit breaker in inserted position Voltage established Breaker not tripped or blocked from protection relay Earth switch open Breaker in remote control No synchronization block signal Enable restart from protective devices

Diesel Generator Power Management System


Diesel Engine Control and Monitoring The diesel generator PMS consists of four main control functions : Diesel engine start / stop on request or automatically from the PMS Diesel engine safety system Control and auxiliary systems Alarm and monitoring of the diesel engine

1) Engine start and stop, on request or automatically from the PMS. The engine start sequence can be activated if it is in the standby mode and as a result of the following conditions : Start request from operator station (will start and connect to the bus bar.) Bus bar blackout (will start and connect to the Busbar.) Load dependent start (will start and connect to the busbar and share the load with the running turbine generator.) Start request from heavy consumers (will start and connect to the busbar and share the load with the running turbine generator.)

5.4.2

Main Switchboard and Generator Operation


Generator Breaker Disconnect by the ICAS A generator breaker disconnect can be initiated as a result of the following conditions : A disconnect request from the operator station A load dependent stop (if the generator is in standby mode.) The safety system is activated (if the generator is in standby mode.) The breaker will be prevented from disconnecting when the following apply : Breaker in local control Internal blocking (e.g. not reset after downloading time-out) Disconnect interlocked Generator load >10% of the nominal load

Diesel Generator Breaker Connect/Disconnect


Connect by the ICAS The generator breaker connect can be initiated if the generator is in the standby mode and as a result of the following : When a connect request is sent from an operator station Load dependent start Start request from heavy consumer Busbar blackout Safety system of a turbine generator is activated Alarm start of any connected generator Both boilers trip

4) Alarm and monitoring of the engine.


The software generated alarms are as follows : RPM FAILURE alarm is given if the Engine Run indication disappears while the generator voltage is normal and the generator breaker is closed. START FAILURE alarm is given when the Engine Run feedback signal is not confirmed 10 seconds after the start command. DISCONNECTION FAILURE alarm is given when the Circuit Breaker Open feedback signal is not confirmed within 5 seconds after the open command. STOP FAILURE alarm is given when the Engine Run feedback signal is not lost within 60 seconds after the open command. INCONSISTENCY ALARM is sounded if the circuit breaker is closed and the engine is stopped. ERROR alarm sounds when it is in remote mode and it is started or stopped without the corresponding command, or the circuit breaker position is changed without the corresponding command. VOLTAGE NOT ESTABLISHED alarm will sound if, after a successful engine start, the voltage does not rise to 6,600V within 10 seconds. SYNCHRONIZED TIME-OUT alarm will sound if the synchronizing time exceeds 30 seconds.

The generator breaker will be prevented from closing, if a Connect Blocking signal has been activated. It can be caused by the following : Generator breaker not ready Generator breaker tripped and blocked Busbar earth knife closed Generator speed control in manual

The opening of the generator breaker is possible when : Generator load <10% of generator nominal load No interlock active Two types of load reduction can be defined for the diesel generator : Ramp down (%/second) and disconnect when the generator load <10% of the nominal load. The ramp setting is set to 2% / second (% of nominal load). Reduce the load as fast as possible and disconnect when the generator load <10% of the nominal load. A disconnection failure alarm is given if the Circuit Breaker Opened feedback is not confirmed within 5 seconds after the open command.

(Note : Circuit breaker tripped and blocked must be manually reset on 6.6 kV main switchboard before Close operation from the ICAS if possible.) The breaker can be closed when : Engine is running Circuit breaker in inserted position Voltage established Breaker not tripped or blocked from protection relay Earth switch open Breaker in remote control No synchronization block signal Enable restart from protective devices

2) The diesel engine safety system, which when activated will result in the following immediate actions : A stop command signal to the engine Emergency stop command to the engine Open command to the circuit breaker When the shutdown system has been activated, a reset command from the operator station keyboard is required before any new start of the engine can be performed.

Dead Bus Operation In the event that a blackout on the 6.6 kV switchboard is detected, the PMS will immediately give a start order to the diesel generator if set in standby mode, blackout detection units in the 6.6kV switchboard will bypass the synchronizing unit and it will be connected to the dead busbar. In the event of blackout on both the port and starboard 6.6kV switchboards, the PMS will default connect the diesel generator to the starboard side. A synchronizing time-out alarm will be given if the synchronizing time exceeds 30 seconds.

3) Control of auxiliary systems includes the starting and stopping of the prelubrication oil pump in response to the Engine Run feedback signal.

5.4.2

Main Switchboard and Generator Operation


Procedure to Disconnect the Diesel or Turbine Generator from the Main Switchboard and Stop the Diesel Engine from the ICAS a) Click on the DG or TG icon to reveal a menu list. b) On the menu list click on the DISCONNECT button to disconnect the generator from the main switchboard. (Note : The following procedure is for the diesel generator only.) c) Before stopping, allow the engine to run for a few minutes for cooling down purposes, e.g. the exhaust gas temperatures. d) Finally, click on the DG icon to display the menu and click on STOP on the menu to stop the engine. d) Ensure that the LO pump starts when the engine stops. Transformer Feeder Functions Transformer feeders in the engine room are feeding the port and starboard main 440V switchboards via two 2,500kVA, 6,600 / 450V transformers and transformer feeder in the cargo switchboard room feeds the 440V section of the cargo switchboards via a 1,000 kVA 6,600 / 450V transformer. Two interlocks are provided on the 450V side of the transformer. The 450V incoming breaker cannot be closed before the transformer 6,600V feeder breaker is closed and if the 6,600V feeder breaker opens, the 450V incoming breaker will open. Due to the limited short circuit rating of the 440V switchboards and to prevent load transfer between the port and starboard 6,600V switchboards via the 440V switchboards there is an interlocking system between the two 6,600V transformer feeders and the 440V transfer breaker whereby only two of the three can be closed at the same time. If the two transformer feeders are closed, the transfer breaker will be open. The transfer breaker can be closed if only one transformer feeder is closed. To change the set up of the breakers, short time parallelling is allowed. The breaker to close gets a close signal and closes. If this breaker does not receive a signal that one of the other two breakers has opened within 40 seconds, it will trip. In addition to this, the 6,600V and the 440V transfer breakers are interlocked whereby, if the 6,600V transfer breakers are not closed, the 440V transfer breakers cannot close except when only one transformer feeder is closed and one open.

Procedure to Start the Diesel Generator Engine and Parallel with the Main Switchboard from the ICAS The following procedure describes how to put the diesel generator into symmetric mode, manually start it and then connect it to the 6.6 kV main switchboard. a) Ensure that the engine is ready for starting. b) At the local control panel, ensure that the selector switch is in the REMOTE position. c) At the ICAS in the MCR, select the Power Management screen and click on the DG icon to reveal a menu list. d) On the menu list click on SYMMETRIC. e) On the menu list click on START to start the diesel generator engine. f) Once the diesel generator engine has started, return to the diesel generator to ensure that the engine is running satisfactorily and without any leaks or excessive noise. g) Allow the engine to run for 10 minutes before deciding to parallel the generator with the main switchboard. h) To parallel the diesel or turbine generator, select the PMS screen and click on the DG or TG icon to reveal a menu list. i) On the menu list click on the CONNECT button to parallel the generator with the main switchboard. If on test, allow the diesel generator to be paralleled for at least 30 minutes.

Procedure to Manually Connect the Diesel or Turbine Generator to the Main Switchboard a) At the main 6,600V switchboard power management panel, turn the Remote/Auto switch to the Local/Manual position. The synchroscope lights will turn on to indicate if the generator is turning too fast + or too slow -. b) Raise or lower the speed of the generator, using the Lower / Raise switch until the synchroscope light revolves slowly in a clockwise + direction. c) Turn the CB Trip / Close switch to the CLOSE position and the generator will connect to the main switchboard when the revolving light reaches the top position on the synchroscope. d) Turn the Remote / Auto switch to the Remote / Auto position. The synchroscope lights will turn off and the power management system will control the generator to remain in parallel with the main switchboard. (Note : The selector switch Local / Auto position is similar to Remote / Auto position. After putting the switch to the Local / Auto position, the close switch must be operated to start the synchronizer. The synchronizing function (lower / raise and comparison of voltage) is still carried out by the synchronizer.)

5.4.3

Shore Power
Procedure for the Operation of Shore Power Reception The vessel is being supplied by the diesel generator. a) Isolate all non-essential services, including the sequential start system. Reduce the load at the 440V main switchboards to the absolute minimum. Set the PMS to MANUAL to ensure that the diesel generator does not start when the vessel blacks out. b) Isolate the emergency generator to ensure that it does not start. c) At the shore connection box turn the shore power switch on. d) At the both 6,600V main switchboards open breaker. Stop the diesel generator. e) At the 440V main switchboards close breaker to feed the port and starboard main switchboards. f) Proceed to supply essential services such as fire detection, lighting, etc. g) The shore supply should be closely monitored to ensure the 1,000A current is not exceeded. Procedure for the Transfer from Shore Power to Diesel Generator a) Isolate the emergency generator to ensure that it does not start. b) Isolate all non-essential services, including the sequential start system. Reduce the load at the main 440V switchboards to the absolute minimum. Set the PMS to MANUAL to ensure that the diesel generator does not start when the vessel blacks out. c) Run up the diesel generator on local control. d) At the power management panel turn the Remote / Auto switch to the Local / Manual position. e) Lower or raise the generator speed until the synchronizer light slowly revolves in the + direction. f) Turn the breaker Trip / Close switch to the CLOSE position to connect the generator to the main switchboard when the synchronizer light passes the top position. g) At the 440V main switchboards open the breaker to black out. h) At the 440V main switchboards close breaker to feed the switchboards from the main transformers. i) At the 6,600V switchboards close breaker to feed the 440V switchboards via the main transformers. j) Supply consumers as required and return the switchboards and generators to automatic operation, if conditions allow. WARNING Do not attempt to close the circuit breaker for the shore power source while the main transformers or the diesel generator are supplying power to the main switchboards. Do not attempt to close the circuit breaker for the main transformers or the diesel generator while the shore power is supplying power to the main switchboards.

A shore power connection box of 440V is included in the emergency switchboard. It is used during dry docks and refits to provide the vessel with power from ashore when the vessels normal power generator facilities are unavailable. The maximum current rating for each shore connection is 1,000A. When the bus tie breaks control switch is selected feed back mode on emergency switchboard, power to shore connection box can supply both the 440V main switchboards. A phase sequence monitoring system is fitted on the shore supply connection box. The phase sequence should be checked before connecting shore power to the main switchboard. If the phase sequence is correct, the bright light will be lit. If the phase sequence is incorrect, the dark light will be lit. In this situation, the shore supply must be isolated and two supply phases changed over. The supply should then be re-connected and the phase sequence checked once again. When shore power is connected and operational, the 6.6kV / 450V transformer breakers will always be open. If a diesel generator starts and one of the transformer breakers close, the secondary side of 6.6kV / 450V transformer breaker cannot close.

5.4.4

Main Alternators
Bearings ICAS Alarms Turbine Driven Alternator Tag No. Description 241 Bearing turbine side 242 Bearing free end 243 Winding U 244 Winding V 245 Winding W 249 Air cooler FW leak 259 Load current Diesel Driven Alternator Tag No. Description 311 Bearing turbine side 312 Bearing free end 313 Winding U 314 Winding V 315 Winding W 316 Air cooler outlet air 317 Air cooler outlet FW 307 Air cooler FW leak 329 Load current

Steam Turbine Driven Alternators Maker : Taiyo Electric Co.,Ltd. Type : HPW 65B-4 Capacity/rating : 6,600V, 3ph, 60Hz, 4,000 kVA, 350A, 0.8pf, IP44 Speed : 1,800 rpm Weight : 13,900kg Heating : 220V, 726W

The main bearings are of the self-lubricating sleeve type using oil ISO VG68 for turbine generator and SAE #40 for diesel generator. The bearings also have PT100 temperature sensors which can be monitored from the ICAS screen mimic and will raise alarms when the temperature set points are exceeded. One bearing is of insulated type to prevent harmful circulating current.

High 85C 85C 125C 125C 125C 297A

Diesel Driven Alternator Maker : Type : Capacity/rating : Speed : Weight : Heating :

Taiyo Electric Co.,Ltd. HPW 558C-10 6,600V, 3ph, 60Hz, 2,000 kVA, 175A, 0.8pf, IP44 720 rpm 10,000kg 220V, 726W

Electrical

The alternator output voltage is kept constant by a microprocessor based automatic voltage regulator (AVR). The alternators employ the Automatic Voltage Regulator which precisely controls the output voltage of the alternators by controlling the amount of current supplied to the exciter field. One turbine alternator will provide electrical power under normal conditions at sea and in port, with the diesel alternators on standby. During standbys, manoeuvring or cargo operations, two turbine alternators will be on load supplemented by the diesel alternator if necessary.

Description

Two main steam turbine generators and two diesel generator are fitted. They are all of the totally enclosed, cylindrical rotor, self-excited, brushless type fitted with an integral air to fresh water cooler. Generator cooling is provided by passing air over the integral fresh water cooler, using a closed circuit air supply. The cooler is constructed of double tubes, the outer tube has internal grooves. The grooves drain any leakage water from the primary tubes, which is drained out via a clearance between the primary and secondary tube plate to the leakage detector, which will raise an alarm via the ICAS alarm system. Space heaters are fitted which are energised when the generator vacuum circuit breakers are open. These protect against internal condensation during shutdown periods. Nine PT100 sensors are embedded in the stator to monitor the temperature in each phase winding, six are active and three are spare. These temperatures can be monitored from the Integrated Control and Automation System (ICAS) screen mimics and will raise alarms when the temperature set points are exceeded.

High 85C 85C 125C 125C 125C 49C 43C 148A

Emergency Cooling

If the cooling system fails, the alternator may still be run on reduced load the emergency ventilation in place, as follows ; a) Open all side cover plates on both sides of the alternator b) Remove the plates but do not remove the nets behind them. c) Close the emergency cooling plate on the top of the generator to block the top module air flow. During emergency cooling the alternator protection is lowered to IP 21, therefore the ingress of dirt must be kept to a minimum. The winding temperatures must be closely monitored when operating in this condition.

5.4.5

Emergency Alternator
Taiyo Electric Co., Ltd. FBT 45DL-4 450V, 3 phase, 60Hz, 787.5kVA, 1010A, 0.8pf, IP44 1,800 rpm 4,780kg 220V, 645W Manual Operation: Generator Start and Connection onto Dead Bus a) The emergency generator interlocks are normal, the engine is ready to start. b) The emergency generator operation switch is set to MAN at the generator engine control panel. c) Put and hold the START-OFF toggle switch on START position at the instrument panel for 3 to 10 seconds and put the crank toggle switch to ON. d) When the emergency generator speed reaches approximately 350 rpm, the electric starter will disengage automatically. The engine controller will stop further start attempts. e) Select CLOSE of ACB control switch on emergency switchboard. f) The emergency generator will now supply the emergency switchboard 440V busbar. Manual Stop of the Emergency Diesel Engine a) Normal ships power has been restored and the emergency switchboard is being supplied from either the port or starboard 440V main switchboard. The operator selector switch is in the MAN position. b) At the Selco M2000 control panel (or the remote stop pushbutton), press the START / STOP pushbutton until 'INOPERATION' starts flashing slowly. c) When 'INOPERATION' starts to flash slowly, the stop solenoid will remain energized for approximately a further 50 seconds. The diesel engine cannot be restarted while the stop solenoid is energized. d) When the stop solenoid is de-energized after approximately 50 seconds, 'INOPERATION' will stop flashing and the engine is available for restart. Automatic Stop of the Emergency Diesel Engine a) Normal ships power has been restored and the emergency switchboard is being supplied from either the port or starboard 440V main switchboard. The operator selector switch is in the AUTO position. b) As soon as a stop signal is received, 'IN OPERATION' on the Selco panel will start to flash slowly to indicate acceptance of the stop signal but the engine will continue to run for approximately 2 minutes to cool down. c) After cooling down, the engine speed will be decreased to approximately 450rpm and the stop solenoid will be energized for approximately 50 seconds. d) At the end of 50 seconds, the stop solenoid will be de-energised and 'IN OPERATION' will stop flashing and the engine will be available for restart. Emergency Generator Testing Emergency generator sequence test button is provided in the emergency switchboard. Following emergency generator start sequence can be confirmed by pushing of the test button. a) Trip bus tie breaker for LV main switchboard, and initiate black out. b) Start emergency generator. c) Close E / G ACB after 30sec. from bus tie breaker trip. d) Emergency generator is unload running, in case the bus tie breaker is recovered within 30 sec. by ships staff. Back-Feeding from the Emergency Switchboard to the 440V Main Switchboard It is possible to perform a cold start of the vessel from total blackout by back feeding from the emergency switchboard to the 440V main switchboard. This will provide sufficient power to start the necessary equipment to enable running of the turbine generator.

Maker : Type : Capacity/rating : Speed : Weight : Heating : Description

A self-contained emergency diesel generator, rated at 630kW, is installed in the emergency generator room for use in an emergency or during refit. The generator is of the self-excited, brushless type and can be set for manual or automatic operation. Automatic mode will be normally selected, with the manual setting being used for testing the generator and emergency operation of the generator in the event of automatic start failure. The emergency switchboard is normally supplied from either of the 440V main switchboards. When automatic mode is selected, the emergency generator is started automatically by detecting zero volts on the emergency switchboard bus bars. The emergency generator circuit breaker will connect automatically to the emergency switchboard after confirming the continuation of no-voltage. The bus tie breakers on the emergency switchboard, which connect to the 440V main switchboards, are opened automatically when zero volts is detected on the emergency switchboard. The emergency generator will supply the emergency switchboard 30 seconds from zero volts being detected at the emergency switchboard. The alternators automatic voltage regulator is located within the emergency switchboard. There is a potentiometer at the generator cubicle to enable the voltage to be manually adjusted. The generator is fitted with a space heater to prevent condensation when the generator is stationary or idling. The heater is interlocked with the generator circuit breaker. The generator has sufficient capacity to enable the starting of the required machinery to power up the vessel from a dead condition.

Emergency Generator Automatic Start and Automatic Breaker Closure onto Dead Bus a) The emergency generator interlocks are normal, the engine is ready to start. b) The emergency generator operation switch is set to AUTO at the generator engine control panel. c) The Emergency switchboard bus-tie breaker opens due to a zero volt situation (440V switchboard blackout). d) The emergency switchboard bus voltage drops to zero, the emergency generator receives a start command. e) The generator starts via its air starter and 'RUNNING' on the generator engine control panel. will flash. f) When the emergency generator speed reaches approximately 550 rpm, the air starter will disengage automatically and ' RUNNING ' will be lit constantly.

g) If the emergency switchboard bus voltage is still zero, the emergency generator breaker closes. The emergency generator now feeds the emergency switchboard. Emergency Generator Failure to Start in AUTO Should the diesel engine fail to reach 350 rpm within 25 seconds from the time of the first start, a second automatic start attempt will be made. Should the engine not start, a third attempt is made. At the third failed start, 'START FAIL' on the generator engine control panel will be lit and any further attempt to start the engine is blocked. To restart again with 3 start attempts press the RESET pushbutton twice. Main Switchboard Power Restoration Upon restoration of normal power, changeover from emergency power to normal power will occur automatically. The emergency generator will then continue to run unloaded for a cooling down period of approximately 2 minutes before stopping automatically.

5.4.6

Preferential Tripping and Sequential Restarting

Preferential Tripping The power management system matches the generator capacity to the power requirements of the vessel. However, should a main generator or main transformer be overloaded for a set period of time, certain service groups will be disconnected. If the overload occurs in the 440V services (main transformers), the disconnection is detected by an overload relay in the following sequence : 1) 2) If the main transformers experience a 105% overload for a period of 30 seconds (high winding temperature), Case-A will be initiated. If the running generator. experience a 105% overload (over current), Case-B will be initiated. POS.OF STOP
HVCSB1 HVCSB1 HVCSB1 HVCSB1 HVCSB1 HVCSB2 HVCSB2 HVCSB2 HVCSB2 HVCSB2 LVMSB1 LVMSB1 LVMSB1 LVMSB1 LVMSB1 LVMSB1 LVMSB2 LVMSB2 LVMSB2 LVMSB1 LVMSB1 LVMSB1 NO.1 C.TANK NO.1 CARGO PUMP NO.2 C.TANK NO.1 CARGO PUMP NO.3 C.TANK NO.1 CARGO PUMP NO.4 C.TANK NO.1 CARGO PUMP NO.1 VAPOUR RETURN COMPRESSOR NO.1 C.TANK NO.2 CARGO PUMP NO.2 C.TANK NO.2 CARGO PUMP NO.3 C.TANK NO.2 CARGO PUMP NO.4 C.TANK NO.2 CARGO PUMP NO.2 VAPOUR RETURN COMPRESSOR NO.1 STEER ENG. RM ROOM HEATER NO.1 AIR COND.UNIT NO.1 SW.BD RM PACK.AIR COND. NO.6 DECK MACHINE NO.9 DECK MACHINE NO.2 STEER ENG. RM ROOM HEATER NO.2 AIR COND.UNIT NO.2 SW.BD RM PACK.AIR COND. ELEC. & INST.WORK SHOP PACK. AIR COND. NO.7 DECK MACHINE NO.8 DECK MACHINE NO.10 DECK MACHINE

Case-A

Case-B

Case-C

POS.OF STOP
GSP3 GSP3 FWDDA FWDDA FWDDA FWDDB FWDDB WRKDB WRKDB WRKDB WRKDB WRKDB WRKDB WRKDB WRKDB WRKDB WRKDB WRKDB PP42 PP42 PP42
NO.1 SANITARY SPACE EXH.FAN NO.2 SANITARY SPACE EXH.FAN

Case-A

Case-B

Case-C

If the overload occurs in the 6.6 kV services, the disconnection is detected by the power management system with the following sequence : 3) If the overload (over current) is maintained on the running main generator after Case-B activation, Case-C will be initiated.

NO.1 DECK MACHINE NO.4 DECK MACHINE NO.1 FWD STORE RM HEATER NO.5 FWD STORE RM HEATER NO.2 FWD STORE RM HEATER ELECT.ARC WELDER LATHE PEDESTAL GRINDER PEDESTAL DRILL MACHINE COMB.BORING / MILLING MACHINE. W / SHOP WELDING SPACE EXH.FAN ENG.WORK SHOP PACK.AIR COND. LABORATORY PACK.AIR COND. TEST PANEL ELECTRIC HOIST PLASMA CUTTER NO.1 EL.EQUIP RM PACK.AIR COND. NO.1 CSB RM PACK.AIR COND. NO.2 CSB RM PACK.AIR COND.

5.4.6

Preferential Tripping and Sequential Restarting


Blackout Restart (UVR Auxiliaries) The following auxiliaries will restart automatically according to the table below. These auxiliaries are arranged for step wise sequential restart for avoiding the disconnection of generator breaker due to the rush current at start. (UVR : when the switch of auto start / stop is set at Auto position) Time Delay A. 0 sec. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Lighting Radio. Navigation & I.C. equipment Instrumentation Miscellaneous Steering gear Lift Control oil pump Stern tube L.O. pump T/G L.O. priming pump D/G L.O. priming pump Main feed water pump aux. L.O. pump Cargo & ballast V. control hyd. oil pump Engine room bilge pump Hot water circulation pump Gland exhaust fan Boiler flame eye seal air fan Comp. motor room supply fan W/H & CCR unit cooler fresh water pump Electric heat trace & room heaters Package air conditioners kW 161 1 2 3 4 Time Delay C. 10 sec. Aux. L.O. pump Main cooling sea water pump Vapour return comp. L.O. priming pump Fuel gas comp. L.O. priming pump Time Delay D. 15 sec. Fresh water pump Drink water pump No.1 & 2 E/R supply fans Drain pump Vacuum pump Vent duct exhaust fan Time Delay E. 20 sec. No.3 & 4 E/R supply fans Time Delay F. 25 sec. No.1 Forced draft fan Time Delay G. 50 sec. No.2 Forced draft fan Time Delay H. 75 sec. No.1 main air compressor Time Delay I. 80 sec. No.2 main air compressor Time Delay J. 85 sec. No.3 main air compressor kW 37 55 2.5 2.5 kW 11 5.5 30 22 22 3.7 kW 30 kW 130 kW 130 kW 75 kW 75 kW 75 Time Delay M. 110 sec. F.O. pump room exhaust. fan F.O. heating room exhaust. fan Emergency. fire pump room supply fan Steering engine room supply fan CO2 bottle room exhaust. fan (cargo mach room) Under deck pass. supply fan Cargo machinery cooling fresh water boost pump kW 1.5 1.5 0.4 7.5 0.4 5.5 5.5 Time Delay K. 90 sec. Main or aux. circulating pump D/G starting air compressor kW 80 5.5

Sequential Restarting Blackout reconnection of breakers will only be necessary for the transformer supply breakers and the 440V switchboard incoming breakers. The transformer breakers will be reconnected immediately after voltage is restored to the 6.6 kV switchboard, the 440V incoming breakers will be delayed .(Note : The reconnection will be timed out if voltage is not established on the main bus within 120 seconds.)

1 2

90 15 2.2 0.75 3.7 2.2 1 5.5 1.5 1.5 1.5 3.7 5.5 5.5 230 19.1

1 2 3 4 5 6

1 2 3 4 5

Time Delay L. 95sec. F.O. burning pump Fire fight fresh water pump Fire line press. pump Engine room exhaust fan Cargo machine room exh. fan

kW 15 7.5 11 18.5 11

1 2 3 4 5 6 7

1 2 3 4

Time Delay B. 5 sec. Main condensate pump Central cooling fresh water pump D/G cooling fresh water pump D/G cooling sea water pump

kW 45 55 7.5 22

5.4.7

24 Volt Battery and Uninterruptible Power Supply


ICAS UPS Units The output from the UPS is fed to Power Distribution Units (PDU). The power distribution units in turn supply the process control stations and the operator stations of the ICAS. A manual bypass switch in the UPS allows the user the opportunity to isolate the UPS from the load. This is achieved by first putting the UPS in static bypass by entering the configuration mode using the front panel and scrolling down to the Manual Bypass option. Refer to the UPS operational manual for further information. To operate the manual bypass switch : a) Make sure that the load is being fed by the mains input of the UPS and not the batteries. b) Verify that there is now no AC input into the cabinet. c) Turn the manual switch to the Bypass position. This will cause a short break in the output feed. To reinstate the UPS : a) If maintenance has been carried out on the UPS or batteries, ensure that all connections have been carried out correctly. b) Turn the manual bypass switch to the UPS position. This will once again result in a short break in the output feed. c) Confirm that output voltage is present on the load circuit breakers. WARNING The manual bypass switch should only be operated by qualified and trained personnel. Incorrect procedure may result in a breakdown of the load feed. The front of the UPS unit contains an LCD panel, three buttons and four LEDs. The three buttons are : UP / DOWN SCROLL button ON / OFF button ENTER button The four LEDs are : UPS ON ON BATTERY ON BYPASS ALARM (green) (yellow) (yellow) (red) By use of the LCD panel, the UPS settings and current state of the batteries can be viewed. Use the UP / DOWN SCROLL button to scroll through the settings : O/P VOLT = xxx.xV : O/P Cur = x.xA : O/P Power = xkW : O/P FREQ = xx.xHz : BYPASS VOLT = xxx.xV : I/P VOLT = xxx.xV : BAT VOLT = xx.xV : BAT Cur = x.xA : INT TEMP = xx.x Back Up Time = xxxxM : Output voltage Output current Output power Output frequency Bypass voltage Input voltage Battery voltage Battery current Interval temperature Battery backup time

The ships battery / Uninterruptible Power Supply (UPS) systems are as follows : 1) General 24V DC power is supplied from 24V DC Battery and the emergency switchboard 440V section. 2) The radio / GMDSS equipment has its own 24V battery back-up system. 3) The ICAS is fed from two UPS units of 100V AC. No.1 is fed from 204V DC battery, No.1 low voltage main switchboard 440V section or the emergency switchboard 440V section and No.2 is fed from 204V DC battery, No.2 low voltage main switchboard 440V section or the emergency switchboard 440V section 4) General 220V AC UPS unit is supplied from two 204V DC Battery and each battery is connected with No.2 low voltage main switchboard 440V section and the emergency switchboard 440V section. 5) Four 110V DC Battery chargers are installed for control of the 6.6kV high voltage main switchboards breakers. Two of them are fed from 110V DC Battery and No.1 and No.2 low voltage main switchboard 440V section respectively and the remains are fed from 110V Battery and the emergency switchboard 440V section, as back-up system for the formers. 5) The emergency generator starter has its own 24V battery back-up system for the emergency generator starting arrangements. The batteries are normally on a floating charge with the rectifier supplying the load. The batteries are maintained by the charger in a fully charged state. The charging panel contains three meters, one voltmeter measuring output voltage, one output ammeter which measures the current that the load is consuming and one insulation level meter. There is also a DC insulation measuring relay mounted on the front of the rectifier. This measures the insulation with respect to ground of both the positive and negative legs. When one of these legs falls below the limit set by controls on the front of the unit an alarm is activated. Activation of any of these alarms will generate an alarm in the control room.

The UPS uses an Advanced Battery Management (ABM) technology which doubles the life of the batteries compared with normal trickle charge systems. ABM uses a three stage charging technique which not only doubles battery life but also optimises battery recharge time. Batteries can be replaced without powering down the UPS. Emergency Generator Batteries Two battery units, one for electric starter, the other for black start control, are charged from each bulkhead-mounted battery charger located in the emergency generator room. The charging power is supplied from AC 220V emergency feeder panel (EF220). The charger is fitted with an ammeter and voltmeter to monitor the charging supply. The boards and chargers are designed for continuous operation and are practically maintenance free. However, the units should be kept clean and dry and a visual inspection of connection integrity, cable condition etc, made once a year. At this time the charging voltages should be checked using a high quality digital voltmeter. All batteries should be kept clean and dry. The battery poles and connections must be kept covered with acid free vase line. The cell voltages should be checked and logged once a month and the connection terminals checked for tightness once a year.

The UPS has an audible alarm feature to warn of potential power problems. When the alarm is activated, the UPS beeps in different intervals according to a particular condition. Refer to the operational manual for a full list of the fault conditions. To silence the alarm press, one of the front panel buttons. The alarm cannot be silenced for a low battery alarm.

5.4.7a

24 Volt Battery and Uninterruptible Power Supply


ESB EM'CY SWBD

EG
ACO

CHE

BATTERY CHA. & DISCH. PANEL FOR GENERAL USE

W/H GROUP PANEL


AC 440V 1200AH DC 24V

INTERNAL COMMUNICATION etc. AUTOMATION INSTRUMENT DC110C No.3 DC 110V BATTERY CHARGER

1200AH

DC 110V

No.1 HVCSB BREAKER CONTROL No.1 HVMSB BREAKER CONTROL

RTMC

GMDSS RADIO STATION

LVMSB1 NO.1 440V SWBD

FROM EF220
DC 24V

GMDSS No.4 DC 110V BATTERY CHARGER

200AH AC 440V

DC110D

AC6600/450V DC 110V 3300kVA

LVMSB2 NO.2 440V SWBD

AC450/105V AC 100V

UPS-1

No.1 UPS FOR ICAS

No.2 HVCSB BREAKER CONTROL No.2 HVMSB BREAKER CONTROL

300AH AC 440V DC 204V

ICAS EQUIPMENT DC110A

No.1 DC 110V BATTERY CHARGER

AC6600/450V DC 110V 3300kVA

AC450/105V AC 100V

UPS-2

No.2 UPS FOR ICAS

No.1 HVCSB BREAKER CONTROL No.1 HVMSB BREAKER CONTROL

HVMSB1 NO.1 6600V SWBD

300AH AC 6600V

ICAS EQUIPMENT
DC 204V

T/G1 D/G1

DC110B

No.2 DC 110V BATTERY CHARGER

DC 110V

UPSG

UPS FOR GENERAL USE

No.2 HVCSB BREAKER CONTROL No.2 HVMSB BREAKER CONTROL

HVMSB2 NO.2 6600V SWBD

150AH DC 204V

AC 6600V

T/G2 D/G2

DC 204V

AC 220V

150AH

COS FROM AC220V ACCOMMO. FEEDER PANEL FOR MAINTENANCE

GAS ALARM ESDS GYRO COMPASS INMARSAT etc.

PART 6: AUXILIARY MACHINERY

6.1 6.2 6.3 6.4 6.5


6.1a 6.1b 6.1c 6.2c 6.3a 6.4a 6.5a

Main Feed Water Pump Distilling Plant Incinerator Nitrogen Generator System Inert Gas Generator System
Main Feed Water Pump Sectional View Main Feed Water Pump Turbine Sectional View Main Feed Water Pump Trip System Distilling Plant Systems Incinerator Nitrogen Generator System Inert Gas Generator System

Illustrations

6.1

Main Feed Water Pump


Shinko Industries Ltd. DMG100-3 3-stage horizontal, centrifugal Single stage velocity compound impulse DE 510kW 2 sets 5.88 MPa at 510C 0.17 MPa 140 m3/h at 7.84 MPa D.P. 6,600 rpm 7,3907590 rpm 7,2607460 rpm 0.40 MPa 0.27 MPa 0.32 MPa 0.100.15MPa 0.06 MPa 0.05 MPa 53C 80m 140m 0.5mm 0.7mm Woodward UG-10DM There are two shafts, one for the turbine end and one for the pump end, joined together with a gear coupling which is spray lubricated from the turbine LO system. The turbine shaft has two split white metal force lubricated bearings, one at each end with the governor end bearing incorporating a thrust bearing which allows the turbine to expand freely towards the pump end. The pump shaft is supported in a similar fashion with the thrust bearing provided in the non-drive bearing and white metal bearings which are also force lubricated from the turbine LO system. The turbine shaft is fitted with a bearing casing at both ends. In addition to the bearing support duty, the governor end bearing housing has the governor/trip casing fitted on top of it with the main oil pump fitted below the bearing casing. The bearing casing additionally serves as an oil reservoir. The oil temperature throughout the LO system is controlled by a shell and tube type oil cooler, installed independently of the feed pump. The main turbine shaft serves the additional purpose of providing power to the governor drive shaft through a worm gear. This vertical shaft is connected to a further vertical shaft through a spline coupling to drive the gear type main oil pump mounted below the turbine. The main turbine shaft further drives the eccentric ring mechanical overspeed trip at the free end of the governor side of the shaft. The turbine shaft is sealed using labyrinth packing and a gland leak-off arrangement which prevents steam leakage to atmosphere under the normal backpressure conditions experienced whilst the pump is running. The pump shaft is sealed using a floating sealing ring inside a stuffing box. This arrangement uses injected condensate to effect a seal at both ends of the pump shaft. The sealing ring arrangement allows a portion of the feed water to pass out of the pump where it mixes with the condensate sealing water before being led to the atmospheric drains tank. Small clearances reduce the amount of leakage. The sealing water also serves to cool the sealing arrangement. Sealing water passes through a water jacket prior to injection into the seal ring unit to further cool the stuffing box. Control of the feed pump is provided by a Woodward UG-10DM hydraulic governor mounted on top of the turbine drive end bearing casing. It is driven by a vertical shaft through a worm gear at about 1,000 rpm. The governor unit consists of two parts, a lower and an upper part which forms the speed detection / constant speed and speed setting mechanisms respectively. For full operating description of the governor, refer to the manufacturers manual. The output shaft of the governor is connected to the governor valve through a mechanical linkage lever which in turn regulates the steam flow to the turbine. The governor unit acts to keep the speed of the pump constant against changes in load and steam condition. The governor unit is rated to a speed fluctuation of 9% from full to no load, with the speed settling within 1% of the original speed. It can also be used to set the pump speed at any desired setting, from the local or remote positions. The governor valve also operates as the emergency stop valve though use of a hydraulic servomotor. This hydraulic servomotor holds the governor valve open through the same mechanical lever as the governor, by hydraulic pressure from the LO system against a closing spring. Should the hydraulic pressure be lost for any reason, the spring will act on the servomotor piston, closing the governor valve. The oil pressure in the servomotor can be released through either the action of the mechanical trip lever or by an electrically operated solenoid valve which vents the oil pressure back to the sump. There are several ways to activate both of these mechanisms, which include the following : The Mechanical Overspeed Trip Should turbine revolutions exceed 115% of the rated speed (at approximately 7,590 rpm), the mechanical overspeed device will operate and close the governor valve, bringing the turbine to a standstill. The mechanism comprises a spring loaded eccentric weight which is thrown outwards under centrifugal force as the turbine speed rises. The weight eventually comes into contact with a spring loaded trip lever which loses support and moves under the compression of a spring. The trip lever drops, activating a limit switch which, in turn, operates the tripping solenoid valve, venting the servomotor. This trips the pump and avoids excessive rotor stresses. The Electrical Overspeed Trip An electrical overspeed trip is fitted which detects the turbine speed from the turbine tachometer and activates the tripping solenoid when the turbine revolutions exceed 113% of the rated value (at approximately 7,460 rpm). The solenoid vents the closing servomotor, the governor valve and brings the turbine to a standstill. The High Exhaust Back Pressure Trip If the exhaust pressure should rise, the high pressure alarm will initially activate .Should the pressure rise further, a pressure switch will activate the tripping solenoid and thus stop the turbine. The trip is set at 0.32 MPa. The sentinel valve will finally activate a whistle giving warning of the pressure rise. Loss of Lubricating Oil Pressure Loss of LO oil pressure causes the same action as the high exhaust back pressure mechanical trip. This trip is set at 0.05MPa.

Specifications Maker : Pump model : Pump type : Turbine model : Turbine type : Power : Number of units : Steam conditions : Exhaust pressure : Capacity : Operating speed : Overspeed trip, mech : Overspeed trip, elec : Sentinel valve : Back pressure alarm : Back pressure trip : Operating oil pressure : Low oil pressure alarm : Low oil pressure trip : High oil temp. alarm : Vibration alarm : Vibration trip : Axial disp. Alarm : Axial disp. Trip : Governor :

Description The turbine feed pump consists of two main sections : Turbine assembly Pump assembly The turbine is a single stage velocity compound impulse type mounted on a single shaft which is directly coupled to the single pump shaft through a gear coupling. Speed control and hence differential pressure control is effected by a Woodward UG-10DM governor in combination with an integral pressure control unit. The driving steam enters the axial flow turbine through the top of the unit by way of the combined governor valve/emergency stop valve. It then passes through the steam chest and is guided to the nozzle block by way of the steam chest manifold. After expanding through the turbine wheel, the steam exhausts from the lower portion of the turbine casing directly adjacent to the nozzle block.

6.1

Main Feed Water Pump


Turbine Extra Nozzle One turbine extra nozzle is provided to permit more efficient operation of the turbine at loads other than the normal design rated load. This nozzle is operated by a hand wheel positioned at the bottom of the unit. As mechanical wear takes place in the feed pump between rebuilds, its efficiency drops. The extra nozzle is provided to allow additional steam to be supplied to bring the pump up to rated output. It is also used when the steam inlet pressure drops or the exhaust pressure rises, bringing the pump back to its rated capacity. It is important that this valve is closed when normal operating conditions have been re-established to prevent overstressing of components. The feed pumps supply feed water to the boilers. One feed pump is sufficient to supply both boilers and the pumps are arranged as duty and standby units. At ICAS control, the feed pumps are controlled on the basis of the differential pressure between the feed pump discharge pressure and the steam pressure in the boiler steam drum. The feed pump discharge pressure is controlled to higher pressure of boiler steam drum + 1.0MPa, but the control pressure is kept minimum 7.2MPa. Failure of the feed pump recognized by low pump discharge pressure or low differential pressure case, providing the transfer conditions are met, the standby pump will automatically start. Inhibition of automatic starting is provided in the event of deaerator low-low level and by the occurrence of a blackout. Once steam is available and one of the pumps is running, it is then possible to start and stop automatically the feed pumps from ICAS.

Manual Trip The manual trip mechanism is located adjacent to the mechanical overspeed trip and uses the same tripping lever. The tripping lever is moved by the action of a separate hand tripping lever mounted adjacent to the overspeed tripping lever. This hand tripping lever is fitted with a spring operated stopper unit which prevents inadvertent operation. To activate the manual trip, the stopper mechanism is first disengaged by pulling the hand tripping lever upwards. The spring loaded stopper unit will disengage and move out of the way, allowing the hand tripping lever to be fully pushed down. This action moves the tripping lever in a similar fashion to the overspeed weight, producing the same results.

Pump assembly The pump assembly is of the three stage double volute centrifugal type, with a horizontally split casing for easy handling/maintenance. The first stage impeller is of the double suction type with the remaining two stages being only single suction. The double suction first stage allows the pump to operate with a small NSPH at very high revolutions. The double volute arrangement reduces any radial thrust load to a minimum and the whole unit is fixed at the suction end to allow expansion towards the discharge end. The mouth rings at the inlets to the impellers have double step labyrinth seals, improving volumetric efficiency. A balance piston is fitted after the final stage impeller to provide hydrodynamic balance. Any leakage water passing the lengthened seal on the balance piston is returned to the suction side via the balance pipes. This arrangement has the added benefit of reducing the pressure on the discharge side stuffing box to the suction pressure. Lubricating Oil System The main LO pump for each unit is a double helical gear arrangement, driven from the main shaft through the same worm gear arrangement which drives the governor drive shaft. The oil delivered from the main LO pump has its pressure adjusted by the regulating valve before being filtered and then cooled by the external oil cooler. The oil is then delivered to each bearing and gear meshing section where it is sprayed onto the mesh. During the start-up and standby periods, LO is supplied to the LO system by an electrically driven priming pump. This centrifugal pump is submerged in the sump and is operated by pressure switches from the priming pump starter which normally operate the pump automatically. The priming pump cuts-in at 45 kPa as the feed pump slows down, then stops at 95 kPa as the feed pump speeds up. The emergency stop hydraulic servomotor operates on main LO pressure. This has the added benefit of preventing the start of the feed pump without LO pressure. Operation of the Main Feed Water System from the Integrated Control and Automation System (ICAS) The FEED WATER SUPPLY graphic screen is used by the ICAS to control the main feed water system. Three feed water pumps are fitted, two steam driven main feed pump, and one electric motor driven cold start feed pump for initial priming of the boiler during the warming through period. The electric feed pump can be started and stopped from the ICAS but does not have any form of output control from the ICAS. Each of the two main feed pumps is fitted with a governor device which receives a 4-20mA signal from the ICAS which operates to increase or decrease the discharge pressure as required. This is achieved by regulating the steam supply to the feed pump though a governor valve fitted in the main steam supply lines, as previously described.

Manual Operation of the Main Feed Water Pumps The feed pumps can also be operated from an independent control system panel, which is installed locally by the machines. This panel automatically performs the correct start-up and stop sequences for both main feed pumps and also provide the facilities for the automatic changeover of the pumps in the event of trouble with the duty pump and control of recirculation valve. These panels will be used when the pumps are at the warmed through stage. Therefore any cold start of the pumps must be operated locally. To prepare for automatic starting, a number of manual steps must first be taken. These are as follows : a) Ensure that the instrument and gauge valves are open and that instrument air is supplied to the control units. b) Set the valves / components as per the following table. Valve
002/003VPF 012/014VPF 037/038VPF

Turbine Assembly The turbine casing is also split horizontally with the sentinel valve mounted on the upper casing. The rotor disc has two rows of moving blades attached to the periphery and has four balance holes to reduce axial thrust. The nozzle plates and stationary blades are attached to the inside face of the casing. Baffle plates are provided around the ends of the moving blades to reduce agitation losses. The blades themselves are made from stainless steel and are buffed smooth to reduce friction losses. Moving blades have an I-shaped root fixing for maximum strength and are fitted with a caulked stainless steel shroud to provide strength and impart anti-vibration characteristics. The governor valve itself is a double seated valve to eliminate any unbalanced steam forces produced by the steam flow. The wearing components are stellite coated to increase service life. A strainer is fitted at the inlet to the governor valve to protect the unit from small solid particles which become entrapped in the steam flow.

041/042VPC

Description Pump suction valve Pump discharge valve Pump warming through valve Pump sealing water supply Pump air vent Turbine line drains Turbine exhaust valve Turbine warming through valve Trip cause Governor LO cooler

Position
Open Open Open Operational Closed Open Open Open Reset Set to minimum Operational

6.1

Main Feed Water Pump


The recirculation valve 033VPF is automatically opened by the following condition at AUTO mode. (1) (2) Plant mode is maneuvering. Both main feed pumps are run. It is assumed the one boiler is now producing sufficient steam to operate the feed pump. c) Prepare the pump side of the feed pump for use as follows and refer to the valve table on the previous page as necessary : 1) Procedure to Prepare the Feed Water System for Use and to Start a Turbine Feed Water Pump a) Start to warm through the main superheater lines to the main feed pumps. Prepare the main and auxiliary feed systems for operations including the electrical and cold start feed pump. Line up the valves as follows : Valve
001VPF 002/003VPF 031/032VPF 033VPF 036VPF 037/038VPF 025VPF 012/014VPF 051VPF 052VPF 053/055VPF 054VPF 056VPF 057/058VPF

c) Check the LO levels in the governor and the sump. d) Set the selector switch for the LO priming pump to AUTO. e) Set the selector switch for the recirculating valve to AUTO. f) Check that power is available at the local control panel and press the TRIP RESET button. All trip lights should extinguish. g) Place the local control panel position selector switch in the desired position. The control position selector switch has three positions. These are : (1) (2) (3)
MANUAL : This position is selected if it is intended to start the machine manually from the machine side. LOCAL : When this position is selected, it is possible to start and stop the feed pump using the START and STOP pushbuttons on the local panel. REMOTE : When this position is selected, control is passed to the ICAS

Ensure that the instrument and gauge valves are open and that instrument air is supplied to the control units. Check the LO levels in the pump bearings by viewing the level through the oil sight glass at the bottom of the bearing housing. Open the sealing water inlet valve so that condensate can be supplied to the pump stuffing box and check the differential pressure is more than 0.05MPa. Close the pump casing drain valve. Open fully the pump suction valve and ensure that there is sufficient suction pressure on the pressure gauge. Open the pump casing vent valve and close it when water begins to come out. Ensure that the automatic recirculation valve is fully open. Open the pump discharge valve approximately 25% to avoid a sudden load on the pump and turbine during starting. Open the pump warming through valve 037 and 038VPF.

2) 3)

screen. The ICAS screen has a selector switch which provides two starting options. These are : (1) (2)
MANUAL : This position provides manual start and stop of the feed pumps using START and STOP icons on the screen. AUTO : In this position, the feed pump is placed on standby and will start

automatically should there be an abnormal drop off in the discharge pressure of the running pump. There are several start interlocks provided for the feed pumps. If these conditions are not met, the controller will prevent the start-up sequence for the feed pump. These are as follows : Valve
002/003VPF 033VPF 041/042VPC

Description Pump suction valve Pump recirculation valve Turbine exhaust valve Trip Cause Priming LO pump

Position
Open Auto Open Reset Auto

Description Position Open Deaerator feed outlet valve Open Feed pump suction valves Open Feed pump recirculating valves Auto Feed pump recirculating control valve Open Feed pump recirculating line to deaerator Open Feed pump warming through valves Open Cold start feed pump line discharge valve Open Feed pump main feed discharge valves Open Main feed spray water to desuperheater Open Auxiliary feed spray water to desuperheater Open Desuperheater spray water control valve inlet and outlet valves Operational Desuperheater spray water control valve Close Desuperheater spray water control valve bypass Open Desuperheater spray water recirculating valves

4) 5) 6) 7) 8) 9)

d) Prepare the turbine side of the feed pump for use as follows and refer to the valve table on the previous page as necessary : 1) 2) 3) Check the feed pump lubricating oil (LO) sump for water and drain as necessary through the sump drain valve. Check the LO level on the dipstick and in the governor and top up as necessary. Open the cooling water inlet and outlet valves to the LO cooler. Start the LO priming pump in AUTO mode and confirm that the LO pressure is above 0.03 MPa. Turn the LO strainer handle several times to clean the screen. Open the drain valves on the main steam line. Open main line valves 011and 012VPA. Open the turbine casing drain valves. Open the turbine exhaust valve very slowly and carefully monitor the turbine casing pressure. When open, allow the turbine and casing temperature to rise to that of the exhaust steam temperature over a period of 30 minutes.

b) Arrange the boiler feed inlet valves as required (See 4.3.2 Main Boiler Operation). For initial filling and firing, the cold start feed pump can be used. This low duty pump is only designed to provide feed water at low pressures. It has an extra suction valve 008VPF which draws water from the distilled water tanks. This allows water to be supplied to the boilers when the condensate system is unavailable. It is important to start operation of both the deaerator and condensate systems as soon as possible to provide as much feed heating as possible to the cold system. For operating procedures for the deaerator and the condensate system, See 3.2.1Condensate Water System.

4) 5) 6) 7) 8) 9)

When all of the above conditions are met, the STANDBY indication lamp on the local control panel will light and READY and STANDBY indicators on the ICAS screen will show that the pump is available for automatic start. Automatic start is only available when the REMOTE position is selected at the local panel. The automatic sequence is controlled by the governor and involves slowly ramping up or down the speed setting. Once running, all start interlocks are disabled except trips. Once stopped, the governor speed setting is set to minimum and the STANDBY lamp ignites.

6.1

Main Feed Water Pump


Procedure to Place the Feed Water Pump Ready for Use 10) Reset the turbine trip lever and ensure that the governor steam valve is in the CLOSED position. 11) Check that the local control panel is on MANUAL control and reset any TRIP alarms. 12) Crack open the bypass valve on the main steam supply valve. 13) Once the warming through steam has been applied for a minimum period of 15 minutes, the feed pump may now be started. 14) Open the manual steam valve gradually and run the pump up at approximately 500 rpm, ensure that water is being delivered through the recirculating line. Check for any abnormal noise or vibration in the turbine and pump. 15) Close the turbine and steam line drain valves. 16) After sufficient warming through open the manual steam valve, bringing the speed up to 70% over a period of 10 minutes, using feed water discharge pressure controller on the local panel in MANUAL mode. Press the INCREASE pushbutton to raise PV reading to equal the SV set point. 17) Ensure that the priming LO pump stops automatically. 18) Ensure that the governor has control of the turbine speed. 19) If the pump is performing satisfactorily, open the main steam inlet valve slowly until it is fully open. 20) Increase the set point on the controller to bring the discharge pressure up to the preset value (7.8 MPa). 21) Place the running pump on REMOTE control. Stopping a Feed Pump Stopping of a feed pump is normally carried out from the ICAS panel by selecting MANUAL and then pressing STOP. It is good practice to stop a running pump by using or simulating one of the trip devices, which has the advantage of testing the trip and testing the automatic start of the standby pump. After the pump has stopped, check for water leakage from the mechanical seals, this commonly occurs when the pump is stopped and takes up with the pump running. Reset the trip device and place the pump in AUTO mode as previously described. A trip of the feed pump may be caused by : (1) (2) (3) (4) Local trip i.e. high back pressure, overspeed, manual trip Excessive vibration Excessive axial displacement Low-low lubricating oil pressure With the system now operating normally it is important to make regular checks of the feed pumps paying particular attention to the following : (1) (2) (3) (4) LO level and drainage of water from the sump Leakage from the mechanical seals Correct flow of cooling water to the mechanical seals Offline feed pump is warmed-up. For the pump to be in standby the following conditions need to apply : a) b) c) d) e) f) g) h) i) j) k) All trips are reset The pump suction and discharge valves are open The recirculating line valves are open and the control valve switch is in the
AUTO position

The sealing water valves are open and sealing water is flowing All vent valves are closed All drain trap inlet and outlet valves are open and bypasses are closed Fresh water cooling valves are open to the LO cooler The LO pump is on AUTO and running Turbine warming through valve is open and turbine is turning at 700 rpm The local panel selection switch is in the REMOTE position The 24V DC supply on the control panel is set to the ON position

At the ICAS screen in the MCR : (1) (2) Move the cursor to the Change Over Mode area and click on the MANUAL / AUTO icon and ensure it is showing AUTO. The standby pump icon indicates READY To START.

Procedure for Starting a Feed Pump via the ICAS When all the above conditions are met, the operator may request to start of standby pump from graphic screen FEED WATER PUMPS.

In the event that a trip condition has existed, the operator must reset the system before a start may be attempted. Reset is not possible if the condition still exists.

Once one feed pump is running, the other feed pump can be set to standby once the feed pressure is above the automatic cut-in pressure. The procedure for placing the stopped pump on standby is described earlier in this section. It should be noted that the level in the deaerator must be maintained as both feed pumps will trip if the level reaches the low-low alarm level. The standby pump must be run at about 500rpm for warming. The driving steam is supplied through the bypass valve on main steam supply valve. Once the feed system is running, the feed water treatment system should be started at the earliest opportunity. For the procedure to operate this system, See 3.2.3 Boiler Water Sampling and Treatment System. If the running pump trips for any reason, or if the differential between the feed pump discharge pressure and the boiler drum pressure becomes too low and providing that there is no deaerator low-low level, then a standby start command is issued. The same start sequence occurs as for the operator initiated start.

6.1a

Main Feed Water Pump Sectional View


FROM CONDENSATE PUMP DIRECT TYPE PRESS. CONTROL VALVE

PART NO. NAME OF PART


1 2 3A 3B 7-1 7-2 8-1 8-2 9 10 16 17-1 17-2 18 19-1 19-2 20 21-1 21-2 21-3 21-4 22 24 27-1 27-2 27-3 38-1 38-2 38-3 39 42 46-1 46-2 46-3 46-4 46-5 46-6 47 48 49 70 73 74 77 78 79 102 103 104 110 111 112-1 112-2 113 114 120 121 372

TO SUC. PRESS.

70

20

8-1

42

77

78

47

49

22

16

24

112-1

79

21-1 27-2 19-2 17-1 112-2 38-3

17-2 21-3 27-3 21-2 46-6 46-4 46-3

49

47

102

78

8-2

77

110 21-4

10

VOLUTE CASING VOLUTE COVER PEDESTAL PEDESTAL BEARING HOUSING BEARING HOUSING BEARING CAP BEARING CAP BEARING COVER BEARING COVER PLUG IMPELLER IMPELLER IMPELLER IMPELLER SHAFT IMPELLER KEY IMPELLER KEY COUPLING KEY STAGE SLEEVE KEY SLEEVE KEY BALANCE PISTON KEY THRUST COLLAR KEY SLEEVE STAGE SLEEVE SPLIT RING SPLIT RING SPLIT RING MOUTH RING MOUTH RING MOUTH RING BALANCE PISTON BEARING METAL HOLDER HOLDER COVER SEAL RING SPRING LANTERN RING SEAL RING RETAINER GLAND BUSH FLINGER
VENT CAP

74

73

7-1

102

48

3B

46-2 372

121 46-1 46-3 46-4 46-5 46-6 21-2 38-1 19-1 38-2 27-1

18

38-3

113

39

22

46-5 46-1 372

46-2

48

7-2

42

3A

114

103 111 104 120

TO ATMOS. DRAIN TANK

COUPLING SLEEVE GEAR HUB COUPLING BOLT THERMOMETER VENT PLUG VENT VALVE OIL GUARD CARRIER RING THRUST PAD ADJUSTING RING THRUST COLLAR STAGE PIECE STAGE PIECE BALANCE BUSH OIL SEAL RING THRUST NUT PIN O-RING

6.1b

Main Feed Water Pump, Tuebine Sectinal View

6.1c

Main Feed Water Pump Trip System

Running Condition
Speed Setting Motor

Trip Condition
Speed Setting Motor

- +

Manual Adjust DC24V Source

Turbine Starter

Manual Adjust DC24V Source

Turbine Starter

Reset Button (Push Before Starting) AC440V Source AC440V Source

Reset Button (Push Before Starting)

From Main Steam Line Governor and Emergency Stop Valve

From Main Steam Line Governor and Emergency Stop Valve

+ To Turbine Nozzle

Press Switch For High Back Pressure Trip

Close

Press Switch For High Back Pressure Trip

Governor Lever

Trip Servomotor Lubricating Oil Pressure Above 0.3kg/cm2 Hand Trip Knob (Pull Before Starting) Reset Knob (Pull Before Starting)

Press Switch For Low Lubricating Oil Pressure Trip Lubricating Oil Pressure Below 0.3kg/cm2

Governor Lever

Trip Servomotor

Press Switch For Low Lubricating Oil Pressure Trip

(Pull and Push at Tripping)

Limit Switch

Limit Switch

Plug

Plug

Solenoid Valve 15% Of Rated Speed

Solenoid Valve

To Lubricating Oil Tank Overspeed Trip Orifice Overspeed Trip Orifice

Pressure Oil From Main Lubricating Oil Line (1.0 - 1.5kg/cm2)

Transmitter For Tachometer

Pressure Oil From Main Lubricating Oil Line (1.0 - 1.5kg/cm2)

Transmitter For Tachometer

6.2

Distilling Plant
Distilling Plant Cooling Sea Water Pumps Distillate from the plant is discharged to the domestic fresh water and distilled water tanks. Water from the distilling plant flows directly to the distilled water tanks and flows to the domestic fresh water tanks (fresh water tank and drinking water tank) connecting to the deck filling pipe rail via silver ion sterilizer. The distilling plant cooling sea water pumps are single-stage centrifugal type. The pump dedicated to No.2 sea water cooled distilling plant supplies the sea water for its condenser, drive water for the brine ejector system and feed water for evaporation. Because the No.1 distilling plant produces condensate from the main steam system in its condenser, the sea water pump only supplies the drive water for the brine ejector and feed water for evaporation. Distillate Pump The distillate pump is a single-stage centrifugal type that extracts the fresh water produced from the condenser and discharges it to the distilled and fresh water tanks. Salinometer The salinometer continuously checks the salinity of the produced water and the circulating water for heating. If the salinity of the fresh water produced is found to be outside the set limits, the controller will dump the out of tolerance fresh water back to the evaporator by a solenoid valve. The salinometer for the circulating water is fitted on the overflow from the circulating water tank and monitored on the ICAS. Control Panel A salinity panel is located on the evaporator vessel of the distillation plant with LCD indicators ranging from 0.5 - 20 ppm. The panel also contains a 5 ppm test function and control buttons to set the alarm point. Alarms Tag No. 912 912 837 837 Description Distilled water salinity high Circulating water salinity high Heater outlet heating water temperature high Heater outlet heating water temperature low Set point 4.0 ppm 4.0 ppm 110C 75C

Specifications Maker : Type : Model : Capacity : Number of units : Sasakura Engineering Co.,Ltd. Plate type EX-45E (condensate cooled) EX-45E (sea water cooled) 45 tons / day Each 1 set

Main Components A distilling plant consists of the following components :

Description There are two fresh water distillation plants installed and these operate at low pressure using boiler feed in the deaerator as the heat source. No.1 distillation plant is condensate cooled and No.2 distillation plant is sea water cooled. Each plant is self-contained with its own combined brine / air ejector and distillate pump. The combined brine / air ejector is driven by the distillation plant cooling SW pump (See 3.5.2Cooling Sea Water Service System) which creates a vacuum in the system in order to lower the evaporation temperature of the feed water. The feed water is introduced into the heater section through a spring operated regulating valve and is distributed into every second plate channel via the evaporation channels. The heating water which the temperature is controlled by mixing boiler feed water from the deaerator and re-circulating water is distributed into the remaining channels, thus transferring its heat to the feed water in the evaporation channels. Having reached boiling temperature, which is lower than at atmospheric pressure, the feed water undergoes a partial evaporation and the mixture of generated vapour and brine enters the separator vessel (evaporator). Here the brine is separated from the vapour and extracted by the combined brine/air ejector. After passing through a demister the vapour enters every second plate channel in the condenser section. The sea water supplied by the distilling plant cooling SW pump distributes itself into the remaining channels, thus absorbing the heat being transferred from the condensing vapour in the No.2 SW cooled distilling plant. This heat transfer is between the generated vapour and main condensate for No.1 condensate cooled distilling plant. The produced fresh water is extracted by the distillate pump and discharged through a salinometer which monitors the salinity of the water. Should the salinity rise above a preset value an alarm is sounded and the condensate is discharged back to the evaporator. Heater Section The heater section consists of a plate heat exchanger that is enclosed in the bottom section of the distilling plant. It is in this section that the sea water is fed. It passes through the heat exchanger where it is heated by hot water such that the sea water separates into water vapour and brine. The water vapour leaves the heater and enters the evaporator. The hot water used as heating source is cooled in the heater and returned to the circulating water tank. The water in the circulating water tank is pumped by a dedicated circulating pump into the heater again after mixing with the boiler feed water from the deaerator. An additional water amount which is supplied from the deaerator for heating overflows to the atmospheric drain tank and it is returned to the steam plant system by the drain pump. Evaporator The evaporator incorporates a filter type demister that separates any residual brine from the water vapour as it rises to pass to the condensing section. Condenser Section The condenser section consists of a plate heat exchanger enclosed in the upper section of the unit. In this section the fresh water vapour is condensed so that it can be pumped by the distillate pump to the fresh water tanks or distilled water tanks. Condensate water from the main condenser pumped by the main condensate pump is supplied for cooling this section of No.1 plant. This heat transfer recovers heat loss due to the production of distilled water. Combined Brine/Air Ejector The ejector extracts brine and incondensable gases from the evaporator vessel and the condenser. The ejector is supplied with driving water from the distilling plant cooling S.W. pumps that take suction from the sea bay.

6.2

Distilling Plant
Evaporation

Operating Procedure Condensate Cooled Distilling Plant Starting Procedures The following procedure is for the operation of the condensate cooled distilling plant. a) b) Ensure that all pressure and temperature gauge root valves are open. Set the condensate cooled distilling plant cooling S.W. pump valves as described in section 3.5.2Cooling Sea Water Service System ensuring that the overboard discharge valve 070VPH is open. Close the vacuum release valve on the evaporator vessel. Open the heater and condenser ejector air suction valves. Start the No.1 cooling S.W. pump for the distilling plant locally to create a vacuum of -85kPa. k) l) m) n) o) p) q) r) j) When there is -85kPa vacuum (after a maximum of 10 minutes). f) g) h) Adjust the feed water regulating valve with a flow meter. (Rated flow 8.5 to 9.4 m3/h) Open valve for the feed water treatment. Ensure that the chemical dosing tank is full. Open the condensate cooling valves to the evaporator, 128VPF and 129VPF and close the bypass valve 130VPF, it is assumed that the gland condenser is already in operation with inlet and outlet valves open. Open the heater condensate outlet drain valve 123VPF to the circulating water tank. Open the control air supply to the deaerator water cut off valve 085VPF and temperature control valve 086VPF and check the cut off valve 085VPF is open. Ensure that the circulating water tank. is filled with condensate from the drain pump. The filling valve 186VPF leaves open. Open the No.1 circulating water pump suction and discharge valves 115VPF and 116VPF. Start the circulating water pump. Open the temperature control valve 086VPF by adjusting the temperature controller until the desired water temperature is reached (maximum 85C). Press Power Switch on the salinity panel. Open the supply valves to the distilled water tanks or fresh water tanks as required. Once the flow of produced water is confirmed at the sight glass, start the distilled water pump at local starter. Open the distillate water pump discharge valve and confirm that the sight is not filled up. Normally a pressure regulating valve controls the discharge pressure so that the produced water flow can meet this indication.

i)

c) d) e)

The pressure at the combined brine/air ejector inlet should be a minimum of 0.4 MPa. The back pressure at the combined brine/air ejector outlet should be no more than 0.06 MPa.

(Note : Avoid the sight glass being filled up with the water absolutely.)

6.2a

Distilling Plant

NO.2 DIST W. TK

NO.1 DIST W. TK
066VPH

TO CONDENSATE LINE

125
130VPF

125

125

FROM CONDENSATE LINE

T
125
128VPF

108VPG

107VPG

EVAPORATOR

FROM DIST.PLANT EJECT.W.PUMP

125

EVAPORATOR CODENSER CODENSER


T V
125
129VPF

T
40 40

NO.2 S.W.C. DIST. PLANT NO.1 C.C. DIST. PLANT


T FI

HEATER
FI

HEATER

S
069VPH 124VPF

S
068VPH 123VPF

125

064VPH

WATER EJECTOR
40 150

WATER EJECTOR
150

FI
125
104VPG

CHEMICAL INJECTION UNIT


125
TAL 837 TAH 837

FI
105VPG

125

SM 921

SAH 921

SM 912

SAH 912

CHEMICAL INJECTION UNIT


TAL 837 FROM DIST.PLANT EJECT.W.PUMP TIC 837 TAH 837

837

TIC 837

25

DIST.PUMP

I/P

DIST.PUMP

A
FROM DEAERATOR

837

109VPG

I/P

40

25 80 S 65
088VPF 087VPF

150

S 65
085VPF 086VPF

TO OVERBOARD

DIST.PLANT CIRC.W.TK
186VPF

40

TO F.W. TANKS

25

FROM DRAIN PUMP

150

150
TAH 736 TM 736

150
PUMP START INTERLOCK

150

P
118VPF

FS

P
116VPF

NO.2

150
117VPF 381VPF 190VPF 115VPF

NO.1

150

DIST.PLANT CIRC.W.PUMP
RM 619 RO 619 SA 619

15
SM 912 SAH 912

DIST.PLANT CIRC.W.PUMP
RM 619 RO 619 SA 619

TO CLEAN DRAIN TK

25

TO ATMOS DRAIN TK

150

6.3

Incinerator
Operation Volcano Co., Ltd VIM - 50 581 kW 58 kg/h at 8,600 kcal/kg calorific value 30 kg/h 1 set Waste oil atomizing burning Induced draft Diesel oil pressure jet direct ignition Diluting air cooling type JHM-SM-215SN High press. air jet PBL-VIM-2 Electric ignition Trochoid type, 230 kg/h x 0.19 MPa D.P. Solenoid type, 12 kg/h x 0.69 MPa D.P. Centrifugal type, 265 m3/min x 0.88 kPa Photo-conductive cell type 2 x 1 m3 1 x 1 m3 The combustion system is designed so that the incinerator can be operated for the following conditions : Maximum furnace temperature 1,200 Minimum furnace temperature 850 Maximum exhaust temperature 350 Normal exhaust temperature 200 The furnace internal pressure is maintained in the negative with the induced fan and the exhaust temperature from the furnace is maintained less than 1000 with the combustion air damper and diluting air damper. The incinerator can be started and stopped automatically and sequentially by 'Auto start / Auto stop' of the switch. Preparation a) b) c) d) Ensure that the temperature of waste oil settling tank is controlled about 90 through a steam control valve. Drain the water in the waste oil settling tank. Ensure that the compressed air is available for burner atomizing. Solid wastes may be charged through the single door before running of incinerator. After charging, Close the door securely.

Specifications Maker : Type : Capacity : Disposal quantity : Solid disposal quantity : Number of units : Combustion system : Draft system : Ignition system : Exhaust gas cooling system : Waste oil sprayer : Pilot burner : Waste oil pump : Pilot burner pump : Induced fan : Flame eye : Waste oil settling tank capacity : Diesel oil service tank capacity :

Warming up a) Set the following switches on the control panel. "FUEL FO MAIN BNR" to "DO SUBSTITUTION" "PILOT BNR ASSIST" to NOR "ALL MANUAL OPERATION SWITCH" to "AUTO" Close furnace air damper to reduce the air into combustion chamber. Ensure that the waste oil settling tank suction valve 361/362VPL Close. Open the diesel oil tank suction valve 363VPL, diesel oil supply non-return valve to the main burner 364VPL. Set the three-way valve for changeover of burner return oil to waste oil pump suction side. The return oil should not be returned to the waste oil settling tank. Select Auto start. The incinerator will warmed up automatically with DO by sequential control of the ignition burner and the main burner.

Incineration When the incinerator receives a start signal, the waste oil pump and induced fan will start for waste oil circulation and furnace purge respectively. Prepurge takes place for a period of 10 seconds, followed by start-up of cam timer, and 20 seconds after the start-up, pilot burner will start. When the flame eye detects the flame of pilot burner, combustion indicator lamp will light up and, 7 seconds after the ignition of pilot burner, waste oil shut-off valve will open to start on continuous combustion by waste oil burner. The pilot burner is automatically extinguished 60 seconds after ignition. Subsequently, cooling valve will open 30 seconds after extinction, so that cooling air is supplied to the atomizer of pilot burner. When the furnace temperature has increased up to the OFF set point (1,000) of waste oil burner ON / OFF temperature controller, the waste oil shut-off valve will close, so that waste oil burner goes out automatically. When the furnace temperature has decreased to the ON set point (900) of waste oil burner, the waste oil burner will start on combustion automatically in the same way as in the foregoing (2). Unless the flame eye detects combustion during the period of 10 seconds after the ignition of pilot burner, the pilot burner and waste oil burner are shut off forthwith, and ignition failure indicator lamp comes on to give an alarm. Subsequently, the furnace after-purge takes place for a period of 90 seconds and induced fan comes to a stop in the case of the furnace temperature below 50 or, alternatively, the induced fan keeps running in the case of the furnace temperature above 50 and then comes to a stop when the furnace temperature has dropped to 50 and less. Since restarting is prevented as long as the ignition failure indicator lamp is lighting up, investigate into the cause and reset the trouble, followed by restarting the operation. (Note : In the case of burner cut affected by interlock, the incinerator will automatically restart simultaneously with resetting after the cause has been removed to restore the normal state.) b) c) d) e)

Description An incinerator and associated tanks are situated in the incinerator room at the upper deck starboard side in the engine casing. A garbage store is located next door to this room in accommodation area. Contain in the separated bilge oil tank is discharged to the waste oil settling tank or shore connections as required through the waste oil transfer pump which will stop automatically by a high level of either waste oil settling tank which will be selected for transfer. Contain in the waste oil tank is settled and heated up with steam and discharged to the incinerator through the waste oil pump in the unit. A dedicated diesel oil tank is provided. The diesel oil is supplied to the pilot burner through the solenoid pump and for warming up and pipe cleaning of the main burner. The incinerator has a cylindrical steel frame with air cooled jacket between the inner and the outer plating and the furnace is lined internally with castable heat-resistant material. A solid waste inlet port of bucket type double door and an ash removal port are fitted at the side of incinerator. The atomizing of waste oil combustion is performed by a high pressure air jet burner. The pilot burner of diesel oil burning can assist the combustion when the high water content (more than 40%) in the waste oil.

f)

Waste oil burning a) b) c) d) e) f) Provided that the temperature in combustion chamber is higher than preset lower limit (850), the waste may be burned in the incinerator. Close diesel oil supply non-return valve 364VPL and Open waste oil settling tank suction valve 361/362VPL. Change over the three-way for valve burner return oil to waste oil settling tank. Set "FUEL FOR MAIN BNR" switch to "NOR". Set PILOT BNR ASIST to ASSIST RUN in case high water content waste oil is burned. Adjust the burner air damper depending on the burning rate of waste oil after the chamber has warmed, and when solid wastes will be burned, Adjust the furnace air damper depending upon the conditions of solids.

6.3

Incinerator
2. Other 1) In the event of followings, the fuels will be shut off and indication lamp will illuminate. Flame fault Exh. gas temp. high : Comb. chamber temp. high W.O. press low : IDF / WO pump trip : W.O. temp. low : Ignition press. Low : Furnace press. high : Atomize air press. low : 350 1200 0.019 MPa 60 390 - 0.049 190 kPa kPa kPa

Waste oil pipe cleaning a) b) c) d) Set "FUEL FOR MAIN BNR" switch to "DO SUBSTITUTION". Close the waste oil settling tank suction valve 361/362VPL. Open the diesel oil tank suction valve 363VPL, diesel oil supply non-return valve to the main burner 364VPL. The three-way valve for burner return oil is kept as it is (to waste oil settling tank). Long time cleaning causes loss of diesel oil. It is recommended to complete the cleaning as short time as possible. Select Auto start .

e)

Control 1. A thermocouple is provided to control the temperature in the furnace. 1) Upper set point : 1,000 In the event of temperature rising to the upper set point, the fuels will be shut off. 2) Lower set point : 900 When the temperature lowers into the lower set point, the ignition will restart. 3) Low limit point : 850 When the temperature lowers into the low limit point after the chamber has once been heated up, "COMBUSTION CHAMBER TEMP LOW" lamp will illuminates. This informs completion of warming up. 4) Overheat point : 1,200 In the event of temperature reaching the overheat point, the fuels will be shut off and "COMBUSTION CHAMBER TEMP HIGH" lamp will illuminate. 5) Finish point : 50 When the chamber is cooled down to the finish point in the shutting down process, the induced fan will stop.

2) In the event of W.O. temperature rising above 95. W.O. Temp. High lamp will illuminate. 3. The level of waste oil settling tank will stop automatically. 1) the waste oil transfer pump by high level 2) the incinerator by low level

Igniting
Main Switch ON Emergency Stop Auto.Start SW. ON Not Flame Detecting Not Flame Fault Ash Outlet Port Shut Strating Condition I.D. Fan Running W.O. Pump Running Not Flame Detecting Ignition Sparking Stop Pilot Burner Pump ON Not Furnace Temp. High Solid Inlet Port Shut Not W.O. Level Low Not Atomize. Air Press. Low Not W.O. Temp. Low Not Furnace Press. High Not Exh. Gas Temp. High Not Ignition Press. Low Not W.O. Press. Low Not I.D. Fan & W.O. Pump Trip

900 ON

Furnace Temp. Controller

Pilot Burner Firing

Flame Detecting

Ignition Sparking Stop Flame Fault Alarm Nozzle Cooling Valve Open

T
10 sec

Not Flame Detecting W.O. Solenoid Valve Open D.O. Pump Stop

T
30 sec Temp. Controller OB/OFF Cycle

T
7 sec

Flame Detecting

W.O. Firing

Pilot Burner SW. NOR

T
80 sec

Pilot Burner Stop

T
30 sec

Extinguishing

1000 ON

Furnace Temp. Controller Furnace Temp. Low


50

W.O. Solenoid Valve Close Auto.Stop SW. ON W.O. Pump Stop Nozzle Cooling Valve Close

I.D. Fan Stop

- W.O. Temp. Low - Flame Fault - Exh. Gas Temp. High - I.D. Fan Trip - W.O. Pump Trip - W.O. Press. Low - Furnace Temp. High - Furnace Press. High - Atomiz. Air Press. High

W.O. Solenoid Valve Close W.O. Pump Stop Nozzle Cooling Valve Close

Furnace Temp. Low


50

I.D. Fan Stop W.O. Solenoid Valve Close Nozzle Cooling Valve Close

Low Voltage 85V

6.3a

Incinerator
FUNNEL

TO SHORE CONNECTION

EXHAUST FAN
100

100

INCINERATOR CONTROL PANEL


SOURCE
FLAME PRESENT FLAME FAULT EXH. GAS TEMP HIGH W. OIL PRESS LOW

50 65 25
328VPL 366VPL

FROM E/R BILGE PUMP

127VPJ

IDF/W.O.PUMP TRIP

W. OIL TEMP LOW

W. OIL TEMP HIGH

COMB. CHAMB. TEMP HIGH

COMB. CHAMB. TEMP LOW

65 25

IGNITION PRESS LOW

FURNACE PRESS HIGH

ATOMIZ AIR PRESS LOW

EXH. GAS TEMP

COMB. CHAMB. TEMP HIGH

COMB. CHAMB. TEMP LOW

I.D. FAN

100

A ~

365VPL

327VPL

INCINERATOR DIESEL OIL TK


FS

AS
643

LAH FS 728
PUMP STOP

168VPB

AS 643

FS

NO.2 WASTE OIL SETT. TK


TAH 727

NO.1 WASTE OIL SETT. TK


TAH 727

LAH 728 AS 643


PUMP STOP

LAH FS 723 LAL 724 1.0MPA STM


FS

WASTE OIL TRANS. PUMP


P
142VPJ

65

FIRE

ES

643

RO

643

SA

643

RM

AUTO START

BUZZER STOP

NOR

D.O. CHANGE

TEST
BUZZER - NOR - LAMP

AUTO STOP

RESET

PILOT BURNER
NOR ASSIST RUN

FS

164VPB

SOURCE
W.O. PUMP I.D. FAN MANU. ON PILOT BNR MANU. ON W.O. BNR MANU. ON

1.0MPA STM

165VPB 166VPB

167VPB

LI

163VPB

161VPB 162VPB

205VPB

LI

326VPL
STOP

MANU. ON

STOP

STOP

STOP

TO F.O. TRANS. SYSTEM

AUTO

AUTO

AUTO

AUTO

TO DRAIN CLR
136ZPD 135ZPD 405ZPD

TO DRAIN CLR
362VPL 361VPL 363VPL

25

50

50

50

25

25

65

107VPK

FROM LO SUMP TK

65 25

65
141VPJ

364VPL

325VPL

EXH. GAS
25
900

EXH. GAS

25

TS

25

SEP. BILGE OIL TK W.O. INLET

F.O. DRAIN TK

RETURN
INDUCE FAN

900

PS S S

INDUCE FAN

DILUTION DAMPER AIR


900

DILUTION

TS

CHAMBER DILUTION DAMPER CHARGING DOOR

D.O. PUMP

PS

900

S S
PILOT BURNER

TS TS

W.O. PUMP

MAIN BURNER FLAME EYE


900

FURNACE

ASH DOOR

BURNER
LS 900

FE

ASH DOOR
XA 900
900 LS

FURNACE AIR DAMPER


AIR

WALL COOLING AIR DAMPER

WALL COOLING AIR DAMPER

FURNACE AIR DAMPER

6.4 Nitrogen Generator System


Specifications Maker : Type : Model : Capacity : Discharge pressure : Typical gas composition (on dry basis) Oxygen : Carbon dioxide : Nitrogen : Temperature : Dew point : Air Products AS Hollow-fiber membranes permeation type 60 Nm3/h 2 0.6 MPa less than 3 vol.% less than 30 ppm balance max. 60 N2 -65 at atmospheric pressure Process description Compressed air is directed to a filter package to protect the membranes from any harmful particles, oil and water condensate, then it is heated by an electric small heater to rise the temperature to approximate 50 deg.C from minimum 8 deg.C, which is the optimal temperature to reach the design capacity. The compressed air is filtered by a prefilter and microfilter. Contaminations and water are now separated. Further, oil vapour is reduced by means of a carbon bed filter and dust is separated by an after filter. To prevent a pressure shock in the filter line and membrane at start-up, valve should be opened slowly. Each membrane unit consists of one module. Separation of nitrogen and oxygen occurs in the membrane module, where the compressed air flows into the hollow fibers. The compressed, cooled, cleaned and heated air (oxygen, water, carbon-dioxide) permeate through the fiber walls. Nitrogen is separated from the air and leaves the membrane at essentially the same pressure as the entering air. The oxygen-enriched flow is directed to permeate discharge and is to be vented to a safe area (open-air). The capacity of the module is adjusted by the oxygen control valve, membrane inlet pressure and inlet temperature. Adjustment is done in such a way that the total nitrogen outlet capacity and oxygen content of the membrane system complies with the requirements. By means of the O2 analyzer it is possible to deliver nitrogen with pre-adjusted constant oxygen content. The control valve is led up to regulate the pressure in the membranes. If, on account of malfunctioning of the nitrogen generator, the oxygen level in the nitrogen outlet exceeds the alarm setting of the oxygen analyzer, the delivery and dump valves will switch in blow-off position. The delivery and dump valves shall automatically switch to delivery when the maximum admissible O2-quality is measured. The sample line to the O2 analyzer goes via a pressure-reducing valve to a ventilated area. For calibration of the analyzer, a calibration line can be connected. It is also possible to connect a test gas to the analyzer. If, due to malfunctioning of the compressor, dryer or heater, the compressed air temperature fed to the membranes exceeds the set point, the nitrogen generator will be switched-off giving an alarm. For visual indication of temperature and pressure, some pressure indicators and temperature indicators are installed. Both generators are provided with a dew point meter. Compressed air for the nitrogen generator is supplied from the control air system in engine room The nitrogen produced is stored in a 10 m3 buffer tank, where high and low service pressure set points actuate the start and stopping of the generators as demand from the system is activated. In case of a problem with one of both units, it is possible to run in cross-operation. For this purpose manual valves are installed at the inlet of each unit. Both units will be started / stopped from the local panel. Except local start-up / stop the units also can be started / stopped by using pressure signals from the buffer tank. At automatic operation on external start / stop contacts the units will operate in lead and follow principle. Leader will be selected on the local panel. To prevent ingress of the water in the ambient air into the nitrogen system during shutdown periods, dew point preservation back purge lines are installed between the nitrogen system and the buffer tank. Electrical Equipment Local control panels Each skid has its own control panel, which contains the equipment like relays, fuses, lamps, terminal strips etc. for : Automatic starting Operation Autonomous safeguarding A fixed O2 content analyzer and a fixed dew point analyzer are installed on the package unit and they are connected before the remotely operated outlet and vent valve. The system conditions are also monitored by the ICAS. Plant Safety Interlocks The following circumstances with cause an alarm and subsequent shutdown of the system : Sensor DPS TR TR TR TR PT Analyzer Analyzer Analyzer Shut Down Level SD1 SD1 SD1 SD1 SD1 Function Feed air filter diff. pressure Feed air temperature Heater rise temperature Heater overheat Separator feed temperature Separator feed pressure Dew point Oxygen content Oxygen content Set point PAH TAH TAL TAH TAH PAL XAH XAH XAH 60kPa 50 5 350 70 400kPa -60 3.5 % 4.0 %

Description Two nitrogen generators, installed in the engine room upper deck port, produce gaseous nitrogen which is used fro the pressurization of the barrier insulation spaces, as shaft seal gas for the vapour return and fuel gas compressors, fire extinguishing in the vent mast risers and for purging various parts of the cargo piping and BOG system. The two high capacity units (60 m /h each), are able to produce almost pure nitrogen, which is mainly required for the topping up of the barrier insulation space during loading, cooling down and other services, such as compressor sealing, BOG line and system sealing etc. Both generators will be operated in parallel to supply maximum demand during cooling down such as post docking. This double unit nitrogen system uses hollow-fiber membranes to separate air into nitrogen and oxygen. The principle of separation is based on the selective permeation of nitrogen and oxygen. Each gas has a characteristic permeation rate. Nitrogen permeates slowly, oxygen, CO2 and water rapidly, through the membrane. This allows nitrogen to be separated from oxygen. Membrane modules consist of a bundle of numerous hollow fibers. Compressed air connected to a bundle of membranes will leave this bundle as pure nitrogen, while oxygen enriched air will be vented. Continuous monitoring of the gas ensures that it is always of the correct purity.
3

SD2

SD1 Shutdown of complete system SD2 Shutdown of N2 delivery valve

6.4a Nitrogen Generator System


TO E/R BOG LINE N2 PURGE SYSTEM TO GAS COMPR SEAL SYSTEM TO CARGO PART N2 SYSTEM TO N2 CHARGE SYSTEM

G902 G902

PAL

PM

G903 G903

PAL

PM

G901 G901 G901

PAH

PAL

PM

P
G921

UA XA XA

SD

CONTROL PANEL

SD

G928 SD SD SD SD

G917

AY

G917

AIC

G917

AAH

AAAH
G929

SD

G917

AT

MAH
G918

G916

FIC

G923

TAH

PDAH
G933

TDAL
G926

G924

TAH

T
G934

G922

PAL

G917

FI

G918

MM

G916

FY

TM

N2 CHARGE COMPR
P G931
PM

T G932

TM

PDSH

G927

TAH

G934

TIC

P G935

PM

G918

MT

G936

PM

FT

TS
S

DPI

DPI

G925
S S S

LA

SD

ELECT. HTR.

MENBRANE SEPARATORS

FE

0.4 MPA PRESS. RED. V.

NO.2 N2 GENERATOR UNIT

CONTROL AIR LINE


CONTROL PANEL

G921

UA XA XA

SD

SD

G928 SD SD SD SD

G917

AY

G917

AIC

G917

AAH

AAAH
G929

SD

G917

AT

MAH
G918

G916

FIC

FAH 915 FM 915


G914

G923

TAH

PDAH
G933

TDAL
G926

G924

TAH

T
G934

G922

PAL

G917

FI

G918

MM

G916

FY

PAL PM

TM

P
PM
G918

G914

G911

AST PS

G911

AST PS

G911

ASP PS

T G932

TI

PDSH

G927

TAH

G934

TIC

P G935

MT

G936

PM

FT

P G931
SET AT 1.1 MPA

PM

TS
S

DPI

DPI

G925
S S S

LA

SD

ELECT. HTR.

N2 BUFF. TANK

MENBRANE SEPARATORS

FE

NO.1 N2 GENERATOR UNIT

6.5

Inert Gas Generator System


Description for Generator Air Products AS 1 set 11,000 Nm3/h 25 kPa Rotary silica gel R-404A, 222kW at 1,200 rpm 3 sets, 155kW at 3,600 rpm 2 m3/h, 2.5 kW x 1,800 rpm 11kW at 3,600 rpm 9kW at 1.800 rpm 1,000 m3/h at 40mTH, 185 kW x 1,800 rpm The generator is manually started from the control panels mounted locally. The inert gas generator contains an O2 analyzer for the indication of oxygen content in the inert gas. The analyzer is fitted with maximum and minimum setting alarms (1.5% and 0.1%). The gas is led to the deck main via pressure control valve and delivery valve depending on the gas analysis. The valve is normally controlled by the O2 and dew point analyzers and the gas is led to the deck line only when the gas analysis meets with the set requirements. High O2 levels result in the delivery valve closing and purge valve opening to vent the IG to atmosphere at the funnel. The generator consists of the following items ; Combustion air blower Burner unit Scrubber unit Cooler & dryer unit Refrigeration compressor Mist filters Wet gas blower Dry gas blower Combustion Air Blowers Working Principle An electrical motor driven blower, of the single stage centrifugal type, supplies the combustion air to the inert gas generator via flexible bellows connection and regulating valve. A Stand-by blower can also be operated either as a combustion air blower or as a dry gas blower. The blower motors are fitted with standstill heating elements. The heating is automatically switched on as soon as the motor is stopped. The pressure of the air into the combustion chamber is regulated with a blow-off valve situated just above the front of the generator. This valve will contribute to a soft start during ignition of main burner by going into a preset start-up value. The valve will be completely shut after start-up and with inert gas to the dryer / cooler unit.

Specifications Maker : Number of units : Capacity : Discharge pressure : Absorption dryers : Refrigeration plant : IGG air blower : Fuel oil pump : Wet gas blower : Chilled water pump : IGG cooling SW pump (Scrubber pump)

Inert Gas Composition Oxygen : Carbon dioxide : Carbon monoxide : Sulphur oxides : Nitrogen oxides : Nitrogen : Dew point 1.0 vol % maximum 15 vol % maximum 100 ppm maximum 10 ppm maximum 100 ppm maximum Remainder -45 @ atmospheric pressure

Inert gas produced by the combustion of gas oil supplied by the fuel oil pump with air provided by the blower, in the combustion chambers of the inert gas generator. Good combustion is essential for the production of a good quality, soot free, low oxygen inert gas. The products of the combustion are mainly CO2, water and small quantities of oxygen, carbon monoxide, sulphur oxides and hydrogen. The nitrogen content is generally unchanged during the combustion process and the inert gas produced consists mainly of 85% nitrogen and 15% CO2. Initially, the hot combustion gases produced are cooled indirectly in the combustion chamber by a sea water jacket. Thereafter cooling of the gases mainly occurs at the scrubber section in the cooing tower where the sulphur oxides are washed out. A pressure control valve located at the dryer outlet maintains a constant pressure throughout the system, thus ensuring a stable flame at the combustion chamber.

Description The inert gas system is used for the inerting and freeing of cargo tanks, cargo pipes and void spaces when required. The inert gas is produced by a combustion process, which takes place in a combustion chamber where gas oil is used as the fuel. The inert gas contains approximately 85% N2, 15% CO2 and about 0.5% O2 and is at a temperature approximately 5 above the sea water temperature. After combustion, the inert gas has a level of corrosive sulphur oxides from the combustion process which have to be removed. The inert gas enters a sea water cooling tower and water separator where the gas is scrubbed and cooled with a sea water spray. The inert gas is then dehumidified to a dew point of about +5 in the inert gas cooler where glycol water (chilled water) is used as the cooling medium. The chilled water is cooled in the chiller from a separate R-404A refrigerating system and circulates in a closed loop. The gas is further dried to a dew point of about -45 in a dryer unit which consists of inlet filter, rotor unit of silica gel absorbent, regeneration gas steam heater, wet gas blower, and dry gas blower.

Burner Unit The burner unit comprises of a main burner, a pilot burner and a combustion chamber. Pilot Burner The fuel oil burner is ignited by a long flame from the pilot burner which is fitted alongside. The unit consists of an oil atomizing nozzle and electrical spark plug which operates from a 115V AC. which is activated before the pilot burner fuel oil valve is opened to admit fuel oil to the burner. Main Fuel Oil Burner The fuel oil burner is of the vortex turbulent type. The fuel oil is directed to the burner tip. The oil is sprayed into combustion air of vortex flow which is formed in the combustion chamber inlet by the turbulator. The main flame is monitored by a photoelectric cell connected to an electric flame relay. This relay will shut down the main burner, via the main programming unit, if the flame is too weak or has failed to ignite. Flame sensors and gauge glasses of the burner unit are protected by a separate air-cooling system, branched off from the combustion air supply line. The main burner initially receives the total air quantity from the blower. If this quantity is more than required, the front of the generator has a separate atmosphere outlet where the surplus air is ventilated to atmosphere.

Dry-Air Production The generator can produce dry-air at the same rate. For the production of dry air there is no combustion, no oxygen content measurement and the oxygen signal is overridden when the mode selector is get to dry-air (compressor only) production. As long as the dew point is correct after the processes of cooling and drying, the dry-air is supplied to the cargo system.

6.5

Inert Gas Generator System


Refrigeration is the transfer of heat from the substance to be cooled to some other substance. During the refrigeration process, the refrigerant undergoes a number of changes in state or condition, and various terms are used to indicate when and how these are achieved. Mist Filter Saturated Inert gas from the cooler passed through a filter to eliminate any mist due to gas saturation before this gas is passing the dryer. Filter elements are installed in cassettes that have easy access for replacement and maintenance. Dry Gas Blower The dry inert gas system is fitted with one blower, designed to carry 100% of the dry inert gas capacity. The design is identical to the combustion air blower. The blower provides a sufficient supply of dry inert gas to consumers at the necessary flow rate and pressure. Back up Blower The system is also fitted with one back up blower, with identical design as combustion air blower designed to carry 100% of the capacity either as a Dry Gas Blower or as a combustion air blower. Wet Gas Blower The inert gas system is fitted with one wet gas blower, designed to carry 100% of the required inert gas capacity for regeneration of dryer rotor. The blower is driven by an electric motor. Blower and motor are mounted on a joint framework. The units are equipped with flexible connections. The wet gas blower provides regeneration loop of the metal silicate by transporting dry inert gas via a steam heater through a quarter of the dryer rotor back to the cooler inlet The speed of the wet gas blower is controlled by a frequency converter. A software controller receives input from a flow transmitter installed down stream of the blower. An output signal (4mA 20mA) to the frequency converter is determining the speed of blower. Parameters are set in the operator terminal The blower motors are fitted with standstill heating elements. The heating is automatically switched on as soon as the motor is stopped. Dryer Unit The main parts of the dryer are the adsorption rotor, casing for regeneration gas with regeneration heater and wet gas outlet. The inert gas is dehumidified in the rotating adsorption dryer. This is a rotating, heat regenerated, dryer where the drying is performed by a metal silicate rotor with high adsorption capacity. Rotation speed of the dryer is controlled by a frequency converter.
Heated Inert Gas for Regeneration

Combustion Chamber The combustion chamber is an open vessel where the combustion is performed. The heat of combustion is removed by the seawater flowing in the cooling jacket outside of the combustion chamber. The combustion takes place in the combustion chamber. The chamber is water-cooled and requires a steady sea water supply throughout the inerting process and the following cooling period after shutdown.

Fuel Oil System The generator requires Marine Diesel Oil for the pilot burner and the main burner. The fuel pump needs positive pressure to the fuel pumps suction side (maximum 0.3MPa). From the main fuel pump the fuel is delivered to the main burner. The pump motor speed and the fuel rate / pressure are controlled by the flow rate of the inert gas leaving the generator. A differential pressure transmitter gives the input signal, which is measured across the flow venturi by the flow transmitter. The pilot fuel pump regulates the pilot fuel oil pressure. The pilot burner is activated during the start-up sequence only. The fuel pumps are fitted with their own fuel safety re-circulation arrangement. Cooling Water System The sea water is supplied by the eductor driving and IGG cooling sea water pump and is mainly used for cleaning the inert gas in the scrubbing tower. It is also used to cool the cooling jacket of combustion chamber. The seawater flowing in the cooling jacket is ejected into the lower part of the scrubber tower through small holes situated around the outside of the burner outlet into the cooling chamber. No.3 ballast pump can supply the cooling water alternatively if the IGG cooling sea water pump is not available. The cooling F.W. from CCS is supplied to refrigerant condenser and oil cooler. Drain System

Scrubber Unit The scrubber unit comprises a: Scrubber tower Sea water spray nozzles Demister Inspection hatch Level switch The lower part of the scrubber tower receives the hot flue gases from the combustion chamber. The scrubber cools and cleans the combustion gas through direct contact with sea water sprayed from nozzles in the top of chamber. The gas then flows upwards through water droplets generated by spray nozzles. The droplets clean the inert gas before it passes through a stainless steel demister at the top of the tower, which prevents any water droplets being carried away from the tower. The gas leaves the unit via the inert gas outlet at the top of the scrubber unit, and it now forms a humid inert gas with dew point in the range of +35-40C. Cooling Unit The cooler unit is served by a refrigeration compressor operating a chilled water loop. The cooler is of the finned type and designed to reduce the humidity to +5C dew point before the inert gas is led into the dryer. The cooling effect in the cooler is provided through a glycol / water based system from the separate refrigeration plant. The Chilled water pump circulates a mixture of glycol and water in a loop between the cooler and the separate refrigeration plant. This glycol / water mixture will cool down the inert gas while it passes the cooler finned surface. Water vapour is condensed on the surface into water drops that leaves the cooler unit via the bottom drain line.

Return Gas to Cooler Inlet

Wet Inert Gas from Cooler for Regeneration

Dry Inert Gas, -45

Wet Inert Gas from Cooler

The sea water effluent from the scrubber is controlled by a regulating valve so as not to allow any inert gas to flow overboard. This is achieved by a differential pressure control system which controls a water column level in the effluent pipeline, by measuring the pressures in the effluent pipeline and the inert gas outlet pipeline. The discharge valve 090VPH is controlled to maintain the water column level.

6.5

Inert Gas Generator System


Shutdown Level Inert Gas System SD1 Shutdown of scrubber outlet valve Shutdown of fuel supply and combustion Shutdown of dry air blower Shutdown of scrubber pump SD2 Shutdown of scrubber outlet valve Shutdown of fuel supply and combustion Shutdown of dry air blower SD3 Shutdown of scrubber outlet valve Shutdown of fuel supply and combustion SD4 Shutdown of delivery to deck Dry Air System SD5 Shutdown of scrubber outlet valve Shutdown of regeneration heater Shutdown of dryer unit and dry gas blower SD6 Shutdown of scrubber outlet valve Shutdown of regeneration heater SD7 Shutdown of scrubber outlet valve SD8 Warning Control Panel The control panel contains the programmable controller which takes care of the starting, stopping alarm / trip functions and the running mode of the plant. On the front of the panel the IG plant is in the form of a mimic diagram with motor running lights and automatic valve open / closed indicating lights. All alarm initiators are displayed on the mimic diagram with normal operation. Operation Pressing the MAIN MENU membrane key will display the current status on display. Further operating instructions including calibration are displayed on the front of the unit.

The overboard valve 091VPH is operated remotely and has a limit switch that prevents operation of the plant while the valve is closed. During flame failure, the discharge valve 090VPH will close and the discharge to bilge valve 095VPH will open to prevent the discharge overboard of un-burnt fuel.

Monitoring The ICAS monitors the IG system with facility to start and stop the IG generator via Soft keys. IGG cooling sea water pump will start automatically when the ICAS receives an Auto Start signal from the IG control panel. The pump automatically stops when it receives an Auto Stop signal. An oxygen analyzer is installed and monitors the gas after the water separator.

Checks before starting at local control panel Ensure that there at least two main electric generators connected to the main switchboard. Ensure that the control panel is energized at all time, because alarms and trace heating need to be operative even if the plant is shut down. Ensure that the control air supply is on and that the R404A compressor crankcase heater is operational. Check that there is no alarm condition and reset any alarms by pressing the ALARM RESET pushbutton on the control panel. Check the oxygen analyzer for correct calibration and ensure that the tower rinsing valves 151VPG and 152VPG are closed. Open the scrubber tower overboard discharge valve 091VPH. The valve 091VPH is interlocked with the scrubber water pump and No.3 ballast pump starters.

Plant Safety Interlocks The following circumstances with cause an alarm and subsequent shutdown of the inert gas generator : Sensor Pressure PT PT PT PT PT PT PT PT PS Temperature TR TR TR TR TR Level FS Others UV Analyzer Analyzer Analyzer Shut Down Level SD2 SD2 SD1 SD4 SD4 SD5 SD4 SD3 SD2 Function Set point

Combustion air Cooling sea water Cooling sea water Dryer outlet gas Dryer outlet gas Dryer outlet gas Inert gas discharge Fuel oil Control air

PAL 400mmWG PAL 100 kPa PAH 350 kPa PAL 500mmWG PAH 3,000mmWG PAH 3,500mmWG PAL 50mmWG PAL 100 kPa PAL 450 kPa

In the event of a flame failure in port, the system rinses the furnace with water and changes over the scrubber tower discharge to drain to bilge. The bilge drain valve switch, situated inside the IG generator cabinet, must be turned to the AUTOMATIC position before stating the plant in port. Operation Mode Following three modes are provided for operation of the plant. 1. Generator Mode This mode of operation is used for inerting the cargo tanks. In this mode air is blown into the combustion chamber where it is mixed with fuel and burned to give an inert gas of certain oxygen content. This hot gas is then cooled and washed in the scrubber tower of the generator before the humid inert gas is delivered to a cooler and dryer unit. In the cooler the humidity is reduced to a +5C dew point. Finally the dryer reduces the gas humidity by adsorption to between 45C and 65C

SD2 SD2 SD8 SD6 SD5

IG cooling jacket Inert gas Regeneration gas Regeneration gas Dry Inert gas

TAH TAH TAH TAH TAH

60 65 150 165 65

SD1

Scrubber water

LAH
A - Main Menu: Return to main menu. B - ENTER: Activates changes in parameters to the PLC. C - Arrow keys: Used to move cursor up/down and left/right. D - Alarm List: Move to alarm list. E - NUM key: Used for entering new set points/alarm limits etc. F - Function keys: Function changing between different views. G - Global function keys: Fixed function in all views.

SD3 SD7 SD7 SD7

Burner flame failure Oxygen content Oxygen content Dry IG dew point

XAH XAH XAH

1.5 % 0.1 % -45

2. Generator Reduced 50% Mode This mode of operation is identical to Generator mode, used for inerting the cargo tanks at reduced capacity and with less fuel consumption. 3. Fresh Air Mode Fresh air mode of operation applies when all tanks are to be gas-freed by diluting with dry fresh air. The scrubber and inert gas generator is then shut down and the dry gas blower simply supplies air to deck (or to atmosphere when desired) through the dryer & cooler unit.

6.5

Inert Gas Generator System


m) Set up the fuel oil system by opening the following valves : Procedure for Stopping of the Plant a) b) On completion of inertingpress the DELIVER TO ATM button. The delivery valve will close and the purge valve will open. Pressing the STOP SYSTEM will extinguish the burner and stop the fuel pump, but the blowers will keep running. After approximately three minutes, the furnace purge will be complete and the blowers will stop automatically. The two systems will then shut down in parallel in a safe manner which will ensure all heated components are cooled down safely before they are stopped together with the refrigeration plant. During the system stop operation the LED attached to the stop button will be flashing in order to indicate the operation in action. The scrubber pump is then automatically stopped after some time (when the system has been properly cooled) Stop the refrigerator compressor with chill water pump. (as described in the vendor manual) Check that the motor heaters of blower and scrubber pump have been switched on.

Starting Procedure for the Plant in Generator Mode This start procedure is to be used when testing the plant after inspection or maintenance work and if the automatic controls are not functioning. It is assumed that the sea water crossover is fully operational. a) b) Ensure that all pressure gauge and instrumentation valves / cocks are open and that the instruments are reading correctly. Set the water valves as shown in the following table : Position
Open Open Close Close Open Open Open Open Operational Operational Open

Valve Description 041VPJ IGG cooling SW pump suction valve 046VPJ IGG cooling SW pump discharge valve to IGG 042VPJ IGG cooling SW pump discharge valve for eductor 045VPJ No.3 ballast pump discharge valve 061VPG R404A condenser cooling FW inlet valve 062VPG R404A condenser cooling FW outlet valve 063VPG Ref. compressor oil cooler cooling FW inlet valve
064VPG 095VPH 090VPH 091VPH Ref. compressor oil cooler cooling FW outlet valve

Valve Description Position Open IGG gas oil tank quick-closing valve Open Main fuel oil pump suction and delivery valves Open Pilot oil pump suction and delivery valves Operational Burners solenoid valves n) At the fuel oil pump starter panel, turn the main switch on the pump panel to the position 1 to ensure that the pump will start when the IG generator is started.
221VPL

o) p) q) r)

Arrange the deck distribution and ventilation system according to the cargo handling operation instructions. Ensure the stationary oxygen analyzer power is activated. Select GENERATOR mode and the equipment to be started as shown in the description of the operator terminals. Start the system by pressing the Start System button on the front of the terminal.

c) d) e) f)

c) d)

Tower outlet drain to bilge valve Tower level control valve Overboard valve Turn seawater manual control valve to a nearly closed position.

(Note: More than three consecutive starts within one hour causes overheat the blower motors.) s) t) u) Check the blower and motor for vibrations Check sample flow to the stationary oxygen analyser. Adjust sample flow if necessary by means of the sample flow meter. When the oxygen content is below the alarm limit and the system is stable the IG READY LED on the top of the terminal will be lit, and the system is ready for delivering inert gas Cooler/dryer. Press IG TO DRYER for delivering inert gas to the dryer Check that the plant temperatures and pressures are normal. If the inert gas is required to the cargo tanks, turn the gas flow to deck by pressing DELIVER TO DECK function key. If so desired, the gas flow can be returned to atmosphere by pressing DELIVER TO ATM function key. All gas will be supplied to deck as long as the deck pressure is significantly below the set point. When the deck pressure approaches the controller set point, more and more of the gas will flow to atmosphere via the atmosphere control valve. If the plant is not stopped, all gas will finally be led to atmosphere.

Start the scrubber pump either locally at the pump starter using the START / STOP pushbuttons if the seawater line has been drained or remotely from ICAS. If started locally, the pump should be changed to remote control once satisfied that it is operating correctly. Adjust the seawater manual control valve slowly until the water supply pressure to the generator unit has the value given in the performance test. After checking the oil level in the refrigeration compressor crankcase and the oil separator, open all valves on the refrigeration compressor. Prior to start up make sure that compressor oil heater has been turned on for last 12 hours Open cooler chill water loop inlet and outlet valves. Check the chill water loop is filled with water and glycol (25%) Start the chill water pump at starter panel. Check the expansion tank has been filled with 0.1MPa air pressure. Verify pressure on chill water loop to be the same as air pressure at expansion tank inlet. Start the refrigeration compressor at local start panel.

(Note : Do not switch off the electrical supply to the main panel, as this will render the system alarms inoperative. g) h) Drain the sea water pipe by use of the DRAIN switch inside the panel. Once drained, close this valve 095VPH and shut the overboard 091VPH. Shut the fuel and instrument air supply valves to the unit.

e) f) g) h) i) j) k)

Pilot Burner Test Switch (In Generator Mode) While the blower is running in generator mode, and there is no combustion going on, it is possible to test the operation of the pilot burner. For this purpose the generator is equipped with a test switch mounted on the generator itself. The switch is key operated, 3 position. The switch stays at position 1 and 2 and has a spring return from position 3 to position 2. Position 1 Position 2 Position 3 Off Pilot pump on Ignition transformer on

v) w) x)

l)

Once the acceptable O2 content, dew point and IG outlet temperature has been achieved, the inert gas supply main valve M12VUJ will be opened, the vent valve M13VUJ will close and gas will be supplied to the deck. (Note : The main IG supply valve M12VUJ is controlled by the O2 content and dew point. If the O2 content is too high or too low and the dew point is too high, the valve will not open. If either the O2 content, the dryer or the refrigeration plant should reach alarm limits during normal operation the vent valve M13VUJ will open and the supply valve M12VUJ will close.)

When keeping the key operated switches in position 3 the operators can easily do adjustments of the fuel air ratio for the pilot burner if the flame is not operating properly. Warning: Do not leave key switch in position 2 for a long time, because this will keep the pilot pump operating in re-circulation mode, which is in effect a closed loop. When operating like this heat will be accumulated in the pump and there is risk of the fluid boiling if the pump runs for a long time.

6.5

Inert Gas Generator System

Starting Procedure for the Plant in Reduced 50% Mode Follow the start up procedure for Generator mode. The Operator must also in addition to select Generator mode also select Reduced 50% Mode as shown in the description of the operator terminals. This mode can also be selected when system is running in Generator mode (100%) without stopping the system by following the order bellow: 1. Deliver dry inert gas to atmos. 2. Deliver inert gas to atmos. 3. Select reduced 50% mode. 4. Deliver Inert gas to dryer. 5. Deliver inert gas to deck. Procedure for Stopping of the Plant Follow the shut down procedure for Generator mode Starting Procedure for the Plant in Fresh Air Mode 1. Arrange the deck distribution and ventilation system as described in the cargo handling manual. 2. Ensure that controllers are in auto mode and pre set with the correct set point. 3. Select Fresh Air mode on the terminal. 4. Check that there are no active shutdown alarms. 5. Start the refrigeration compressor with the chill water pump as described in the vendor manual. 6. Press the System Start button. 7. Press Delivery to Deck and the dry air is then automatically delivered to deck. Warning: The safety procedures must be strictly observed during tank entry. Procedure for Stopping of the Plant 1. On completion of gas freeing the system can be stopped by pressing the Stop System button and this will stop the inert gas blower and close the delivery valve. 2. Check that the blower motor heating is switched on.

6.5a

Inert Gas Generator System


I.G.G. GAS OIL TK
TO ATMOS.DRAIN TK FROM 1.0 MPA STM 15 40
158VPB 157VPB

15 15 15 40 40 40 400 400
090ZPD 089ZPD 088ZPD

FUNNEL

TO I.G.MAIN TO GAS DETECTOR

M12VUJ

400
G817-1

221VPL
G884 G884 G884

SD SD

M13VUJ

XM

XAL

XAH

FRESH AIR INTAKE

TAHH
G817

G890 G890

TAH TM

G891 G807

FIC

G817-2

P 50 TO D.O.TRANS.PUMP

O2 ANALYZER
10
M07VUJ

G837 G817-3

TM

G889

TM

250

400

350

F.O. PUMP UNIT


25

WET GAS BLOWER


TM
G886

M
TO COMBUSTION AIR BLOWER 400 FI
MAH MM

G816-4

SD

G885

FM

250

M
25

G813-6

SD

P 25

40 FROM F.W.SERV.LINE
G812-4

40

151VPG

G836 G836

TAH TM

G835 G835

PAL SD PM

G815-3

PIC FIC PM

P 400

G888

COOLER

DPI

G882 G882

TAH

TM

B 600

G883 G883

SD PAH

152VPG

MAIN
15

G814-2

SD

P
PM

G813-4

G832

SD PAL

G822 G822

PAL

P
M03VUJ

G832 G832

PM

G887

TM

15

40

UPP.DK

TO ATM.

ROTOR DRYER EXP. TK


PAH PAL

G816-2 G816-2 G806-2

SA

G816-1 G816-1 G806-1

SA

ESD RM

ESD RM

PILOT
S S
P

G813-3

200

S S

G833 G833

TAH TM

SD

G815 G815

SCRUBBER UNIT
P PS

P T 200

PIC PIC

TM

DRY INERT GAS BLOWER

NO.2

NO.1

G812-3

FROM NO.2 DRY I.G. FAN


G813 G812 G806-3

BURNER
G825

SD
G838

200
023VUJ

021VUJ

LAH

50

50

50

SA

ESD

RM

PM

FS

WATER CHILLER
PS P

COMBUSTION AIR BLOWER


400

400

PIC

G825 G813-2

PAL

SD

400
M01VUJ

S
700

G841-4

TO BALLAST STRIP.EDUCTOR C
G812 G809

PS P

ESD

RM

042VPJ

P 400
046VPJ

REF.COMPR
350
G838 G811

ECONOMIZER
G841-7

400

50

RM

G837

TAH

G816-3

SD PAH

G881 G881

PM

PIC

LM

TS

LIC

P
G841-5 G841-6

EDUCTOR DRIV.& IGG COOL.S.W.PUMP


TO BALLAST LINE C P
047VPJ

400

G811

PIC

PS

TO & FROM CCS 125 125

PS
045VPJ G810 G810 G810

RO

OIO

OIS

G811

860

RO

OIO
860

OIS
860

OIL SEPARATOR
50

062VPG

125 125
061VPG

NO.3
150

350
095VPH 090VPH 091VPH 064VPG

CONDENSER
S

BALLAST PUMP
TO BALLAST LINE

OIL COOLER
063VPG

TO BILGE WELL

50

PART 7: ENGINE ROOM BALLAST SYSTEM

7.1 7.2 7.1a 7.2a

Engine Room Ballast System Ballast and Fuel Oil Valves Control System Engine Room Ballast System Ballast and Fuel Oil Valves Control System

Illustrations

7.1 Engine Room Ballast System


Specifications Water ballast pump Maker : Capacity : Water spray pump Maker : Capacity : Teikoku Machinery Works. Ltd. 1 1,050 m3/h 100 mTH 420 kW 1,800 rpm Teikoku Machinery Works. Ltd. 3 2,800 m3/h 35 mTH 375 kW 1,200 rpm The valves marked with R can be controlled remotely at voluntary opening position and the valves marked with "R" are operated at either full open or full close position. Discharge of ballast can be accomplished in three steps. 1) Discharge by gravity 2) Deballasting by use of the ballast pump 3) Stripping by use of the ballast stripping eductor The pumps take their suction from the sea bay, with a high and low sea suction being available at both port and starboard sides. The ballast water is discharged through the dedicated overboard discharge valve 036VPJ. No.3 ballast pump is used also for inert gas generator cooling water supply. Niikura Low pressure type 1 350 m3/h A draft gauge sensor for aft of the ship is provided at 3rd deck in the engine room. Following gauges are monitored on the ICAS. Description The purpose of the Ballast System is to provide the distribution of sea water ballast throughout the ship under varying load conditions. The load varying of the hull and trim of the ship are affected by cargo loading and unloading, bunkering, fuel oil transfer and fuel consumption. The ballast system is used to compensate for all of these operating conditions. Three vertical centrifugal ballast pumps are provided in engine room for operating the ballast water. The pumps can be operated either in parallel or in single as required. A ballast stripping eductor is provided to strip the ballast tanks. The driving water for eductor is supplied from either the eductor drive and IGG cooling sea water pump or No.3 ballast pump. A vertical centrifugal pump is provided to supply sea water to water spray system and a steam heating shell and tube type heater is arranged for heating the sea water in winter condition. The bilge in the double bottom pipe passage is discharged with a dedicated bilge eductor which is situated in the passage. The driving water for eductor is supplied from the bilge and G.S. pump. The valves in the ballast system are hydraulically operated with open / close or valve position indications from the ballast control console in cargo control room. Ballast main pressure Ballast pump suction and discharge pressures Ballast stripping eductor driving water inlet pressure Ballast stripping eductor suction pressure Aft water ballast tanks level

Eductor Drive & IGG Cool. Sea Water pump Maker : Capacity : Ballast stripping eductor Maker : Type : Capacity : Teikoku Machinery Works. Ltd. 1 1,000 m3/h 40 mTH 185 kW 1,800 rpm

The ballast pumps are started and stopped using the ICAS screen, provided that the switches on the main switchboard group starter panel are set to remote. The pumps have an automatic stop sequence control for tank level status. When on local control, the pumps can be started and stopped from the local panel, and can be stopped from this panel regardless of the position of the local / remote switch. The local panels always take priority and can take control from cargo control room at any time. The ICAS has to send a Power Available signal to the switchboard prior to the start signal. When starting in local mode a Power Request signal is sent from the switchboard to the PMS in ICAS. All hydraulically operated valves in the system are also operated the on screen menu / keyboard in conjunction with the ICAS Ballast screen.

7.1a Engine Room Ballast System


SEA CHEST (HIGH)
OIS
G1316

OIO
G1316 R

RO
G1316

053VPJ

650
036VPJ
LAH
G1331

150

40

LAL
G1331 R R

LM

250

550
013VPJ 003VPJ

550

G1331

125
051VPJ
R

D.B.PIPE PASSAGE

AFT W.B.TK (P)


400

550

010VPJ

C
PM
G1304

BALLAST PUMP
ASP 641 SA 641 RO 641 RM 641

250

NO.3
PM
G1305

FOR PORTABLE VENT.FAN

500
029VPJ

550
WATER DETECTOR

550

(300A)

027VPJ

P
R

007VPJ

500
028VPJ
R R

500

450
037VPJ
R

G1301

PM

005VPJ

550
012VPJ 002VPJ

550
008VPJ

300

C
550 650
PM
G1304

BALLAST STRIP. EDUCTOR


400
047VPJ
R

SEA BAY
BALLAST PUMP
SA 641 RO 641 RM 641

550

P
PM
G1302

NO.2
PM
G1305

026VPJ
R R

SA 642

RO 642

RM 642

400

024VPJ

P
500
025VPJ

004VPJ

500

EDUCTOR DRIVING & IGG COOL.S.W. PUMP


P
041VPJ

400 TO IGG COOL.W.


046VPJ
R

400 MOORING DK
LM
G1337 R R

042VPJ

300
R

500

045VPJ

300
WATER DETECTOR
006VPJ

TO CCR

550
011VPJ 001VPJ

550

550

550 (300A)
FOR PORTABLE VENT.FAN

550

PM
G1304

DRAFT GAUGE

BALLAST PUMP
2ND FLAT
SA 641 RO 641 RM 641

NO.1
PM
G1305

250 500
023VPJ
LAH
R G1331

25

AFT W.B.TK (S)

009VPJ

021VPJ

P
150 250 500 500
022VPJ

LAL
G1331

LM
G1331

061VPJ

65

SEA CHEST (LOW)

REMOTE CONTROL VALVE WITH OPEN/SHUT IND.

40

150

REMOTE CONTROL VALVE WITH POSI.IND.

7.2 Ballast and Fuel Oil Valves Control System


Specifications Maker : Type : Main pump capacity : Small pump capacity : Accumulator : Working pressure : Pressure switches : Nakakita Seisakusho Co., Ltd NS 4 x 25.0 litres/min x 5.5 kW x 1,200 rpm 2 x 14.3 litres/min x 3.7 kW x 1,200 rpm 4 x 60 litres preloaded to 7.0 MPa 11.5 Mpa normal, 13.7 MPa maximum Main pump : Loading : 10.5 MPa Unloading : 12.5 MPa 13.7 MPa 950 litres Hydraulic Power Packs The units consist of a 950 litre oil tank, with the two main pumps and a small pump for sea going situated on top of the tank. The lead pump has a delivery rate of 25.0 litres / min at the working pressure of between 10.5 MPa and 12.5 MPa. There is a bank of four accumulators of 60 litre capacity, capable of restoring 20 litres of oil between the working pressures, under low pressure demand conditions. The system is protected by a safety relief valve set at 13.7 MPa, which returns to the tank via the main return line. The starter panel consists of the following : Changeover switch to select either automatic or emergency use Changeover switch to select either duty or standby pump Pushbuttons for: Pump start and stop Acknowledging and canceling audible alarms Lamp test Indicator lamps for: Electrical power available Pump running Pump stopped Pump failure due to high temperature Alarms due to low oil level and high and low oil pressures 2.0 cc / cycle 11.5 MPa 0.7 litre The system has the following alarms Capacity tank low level at 312mm from tank top Oil pressure low-low at 9.0 MPa Oil pressure low at 9.5 MPa Oil pressure high at 13.0 MPa The main pumps are each capable of: Operate three of the 700mm valves in 60 seconds Operate two 300mm - 400mm globe valves in 98 seconds Operate all the manifold valves in 30 seconds Operate three 1000mm - 1,400mm butterfly valves in 30 seconds An electric heater is provided in the oil tank, which starts at 0 and stops at 10 by a thermostat. j) k) Emergency Shutdown System The ESD system is supplied by two accumulators, each fitted with a rupture disc, safety sequence valve, power supply, non-return valve and isolating valve. The accumulators operate the manifold ESD valves in an emergency situation and are capable of two closing operations within 30 seconds.

Procedure for Operating the Remote Valve Operating System a) b) c) d) e) f) g) h) i) Ensure that the oil system is fully charged and that there are no leaks evident. Turn the Automatic / Manual select switch to the control required. Turn the pump select switch to either PUMP 1 or to PUMP 2 position. Turn the power switch to the 1 (ON) position and ensure that the power light illuminates. Press the start button on the selected operating pump and ensure that the RUNNING light illuminates when the pump is running. Check the pressure rise on the pressure gauge and check that the pump cuts out at the pressure of 12.5 MPa. Check that the second pump unit is operational. The system is now ready for operation. Press the OPEN or CLOSE buttons for the selected valves on the mimic panels in order to open or close the selected valves when setting the pipeline system. When the pipeline is set, start the selected pump and check that the system is pumping as intended. Each day press the LAMP TEST button in order to check that the lamps are illuminating.

Relief valve setting : Oil tank capacity : Pump Shutdown Level-low low : Press.-low low :

412mm from top of tank 8.5 MPa

Emergency Hand Pump For cargo and deck part (3sets) Stroke : Pressure : Oil tank volume : For engine room (1set) Stroke : Pressure : Oil tank volume : 33.0 cc / cycle 11.5 MPa 6.5 litre

General Description All the valves necessary for the operation of the cargo, engine room and emergency shutdown system are hydraulically operated by a hydraulic power pack, which can be cross-connected to the cargo hydraulic power pack in an emergency. The power packs are situated in the hydraulic pump unit room on the port side of upper deck and the solenoid valve boards and boxes are distributed and arranged in several places. The power pack is started locally and valve operation is from the ICAS graphic screens in the central control room, situated on G Deck. Emergency operation is carried out by using one of the three for deck and cargo part and one for engine room portable manually operated pumps and by manually operating the solenoid valves. The solenoid valves operate at 230V.

7.2a Ballast and Fuel Oil Valves Control System


NOR. PRESSURE MAX. PRESSURE FIRE EQUIP. ROOM ( "F" - DECK ) CENTRAL CONTROL ROOM ( "G" - DECK ) ELECT. EQUIP. ROOM ( "E" - DECK ) : 10.5 ~ 12.5 MPa : 13.7 MPa

HAND PUMP
ICAS

VDU
I.S. TYPE BARRIER UNIT ( FOR DOL. V. )

I.S. TYPE BARRIER UNIT WITH SIGNAL CONVERTER

SIGNAL CONVERTER

HYD. PUMP ROOM

POWER UNIT FOR BALLAST LINE


STARTER STARTER

POWER UNIT FOR CARGO LINE

FOR CARGO & HULL PART

P
P P P P

TM G1110

LI

TM G1110

LI

P
ACCUMULATOR UNIT

P R

P R

P R

R P P R P
No.9 BALLAST VALVE SOL. V. BOARD ( 7SETS ) No.8 BALLAST & F.O. VALVE SOL. V. BOARD ( 28 SETS )

D.B. PIPE PASSAGE

R
JUNC. BOX JUNC. BOX JUNC. BOX JUNC. BOX

HAND PUMP
S S O S S O S S O S S O S S S O S O

B.T.F.V. 10 SETS ( OPEN - SHUT ) 036VPJ 001VPH 002VPH 003VPH 004VPH 091VPH

B.T.F.V. 1 SET ( OPENNING ) 020VPH

ENGINE ROOM

B.T.F.V. 14 SETS ( OPENING ) 001VPJ 002VPJ 003VPJ 022VPJ 023VPJ 025VPJ 026VPJ 028VPJ 029VPJ 042VPJ 047VPJ FOV04 FOV05 FOV06

B.T.F.V. 10 SETS ( OPEN - SHUT ) 004VPJ 005VPJ 006VPJ 007VPJ 011VPJ 012VPJ 013VPJ 031VPJ 033VPJ 037VPJ

B.T.F.V. 2 SETS ( OPENING ) 009VPJ 010VPJ B.T.F.V. 2 SETS ( OPENING ) 718VPJ 728VPJ

PART 8: INTEGRATED CONTROL AND AUTOMATION SYSTEM

8.1 8.2 8.3

ICAS Overview ICAS Operator Station Operations Graphic Displays Integrated Control and Automation System Overview

Illustrations
8.1a

ICAS Graphic Displays


8.3a Custum Graphic Main Menu
1. Macinery Overview 2. Main Turbine 3. Main Turbine L.O. System 4. Main Turbine Bearings 5. Main Condenser 6. Main Turbine Trip & Auto Slow Down 7. Main Turbine Remote Control Monitoring 8. Boiler Sub Menu 9. FD Fans and Air Heaters 10. Soot Blower 11. BMS Overview 12. No.1 Boiler BMS Overview 13. No.2 Boiler BMS Overview 14. Boiler Trip and BMS Fatal Condition 15. ACC Overview 16. Boiler Condition Overview 17. No.1 Boiler ACC Overview 1/2 18. No.2 Boiler ACC Overview 2/2 19. No.2 Boiler ACC Overview 1/2 20. No.2 Boiler ACC Overview 2/2 21. ACC Signal Monitor 22. Superheated Steam 23. Auxiliary Steam 24. 1.0MPa Auxiliary Steam 25. Steam Dump 26. Exhaust and Gland Exhaust Steam 27. HP Feed System 28. LP Feed System 29. Sea Water Circulation System 30. Sea Water Sevice 31. Ship Side Valve 32. CCS Fresh Water Service 33.D/G Cooling Line 34.Distilled Water Plant 35.Domestic Water Service 36.Bilge / Waste Oil and Sewage 37.Fire Fighting Sea Water 38.No.1 Boiler F.O. Supply 39.No.2 Boiler F.O. Supply 40.F.O. Filling and Transfer 41.L.O. Purifier and Transfer 42.Stern Tube L.O. System 43.E/R Gas and Fire Fighting 44.Fire Detector 45.E/R Vent Fan 46. Ventilation 47.Compressed Air System 48. Refr1gerator and Air Conditioner 49.Steering Gear and Miscellaneous 50. Motor List

8.3b Power Management System Screen


1. Electric Distribution (High Volt) 2. Generator Control 3. Frequency Control Sensor Select 4. No.1 Turbine Generator 5. No.2 Turbine Generator 6. No.1 Diesel Generator 7. No.2 Diesel Generator 8. Emergency Generator 9. Insulation and UPS Status 10. Blackout Recovery

8.3c Gas Handling Screen


1. Fuel Gas Compressor

8.1 ICAS Overview


Maker : Model : Mitsubishi Heavy Industries, Ltd. MCS-6100A Control Stations The control stations are interface and processing units. They are related to particular pieces of equipment, or plant, and provide the interface between the ICAS system and the actual plant or equipment. Process stations also contain the operating software for the associated equipment. The ICAS system on board is called a distributed processing system, because the process control functions are defined locally in the process stations and not in the operator stations. The operator stations function independently, so they can be located at the ship control centres. This also means that each station is capable of controlling any process, provided it has control of the appropriate command group and the user is logged on with the correct access code. Each station computer has a hard disk containing the software files for the fitted equipment. Process values to be displayed at the operator stations are generated in the control stations and transferred to each station as required. The Operator Interface The graphic displays are shown on the monitor of the operator stations. These displays show all or part of a system or process using standard symbols to represent the actual plant / equipment (valves, motors etc). Events (alarms and messages) are also shown on the displays. The operator panel is used to interact with the display and control the process. This is achieved by the use of the trackball and buttons to point and click on symbols and menus. Displays and Views The system is made up of the following types of views : Process Flow Event Trends Equipment The Display and Control of System Processes The number of views in a system depends upon the equipment under system control. The operator can select views with varying levels of detail. When a view is selected showing an overall process, there may not be enough room to display all the detail on a single view. To account for this, the system will therefore have number of views, accessed from the main view, that show these details. System Peripheral Equipment Printers Certain operator stations are connected directly to a dedicated printer for printing out events and may be interfaced to one or more network printers for event and report printing. An operator station may also have the facility to print to the network colour printer, providing colour screen dumps. Monitoring and Control Monitoring and control is performed by software modules. The basic modules are : Buttons Analogue measurement modules Digital measurement modules Pulse measurement modules Motor / pump control modules Valve control modules PID controller modules All display views are made up from a set of standard modules. The symbols on the screen are the symbols associated with these modules, valves, motors, measurements etc. Symbols The symbols indicate the operational mode and status of the represented equipment (motor / pump etc) by means of tag mark characters and changes in colour and appearance.

The ICAS system is a machinery monitoring and control system which covers all the important plant on board the vessel, such as propulsion, power generation, boilers, auxiliary machinery and cargo / ballast systems etc. The basic functions include : Process and system monitoring Event logging and monitoring Control functions (motor control, valve control and PIDs) The main applications to which these functions are applied are : Power management Propulsion plant control Gas handling Cargo and ballast control Watch call system Main Components The ICAS system is made up of operator, data server, control and input / output stations connected by a dual bus to the network units. Operator Stations The operator stations are the main interface between the operator and the processes under the operators control. The operator station has a colour monitor, an operator panel with buttons and trackball and a controller computer (EWS). These are installed in the central control room, the bridge and the machinery control room. Data Server Station A data server station is installed in the cargo control console and engine control consol respectively in the central control room. They are a specific computer on the network which runs the operator station software. It also contains the historical database, storing an historical (time / date) series of process (samples). These series are used to produce trends and reports at the operator and history stations. Communication Network The network used is a dual Local Area Network (LAN) connecting the operator, data server and control stations. All the communication between the operator and the controlled / monitored equipment takes place on this network. Network Systems The Network System composes of Unit Network and Local BUS Network. The unit network is an upper side network system which connects the operator, data server, control stations and gateway controller. The local BUS network is a field side network which connects the control station and I/O station.

8.1a Integrated Control and Automation System Overview


Central Control Room No.1 Electric Equipment Room

UPS

UPS

UPS

UPS

LC D2 0

LC D2 0

LC D2 0

LC D2 0

OP EP

OP EP

OP EP

OP EP

EW

EW

EW

EW

CC
DS S

B1S

CC

CC
HDC1

B21

B11

CC

CC

B12

B22

CC

B13

ALMPRM1

LOGPRM1

C/E Office
U PS

HUB3P

HUB3Q

HUBMPR1

LC D2 0

EW

Machinery Control Room


U PS UPS UPS UPS

MAIN BOILER CONTROL


LC D2 0 LC D2 0 LC D2 0 LC D2 0

OP EP

OP EP

OP EP

OP EP

EW

EW

EW

EW

MC
DS S

B13

MC MC B12 MC

B22

MAIN TURBINE CONTROL

MC

B23

HDC2

B11

MC

B21

MC

B3

ALMPRM1

LOGPRM1

HUB4P

HUB4Q

HUBMPR1

8.2 ICAS Operator Station Operations


Operation Panel The systems operator / user interface is the monitor screen, operation panel and alphanumeric keyboard or mouse device. The screen displays the system views and the operation panel is used to interact with those views. The alphanumeric keyboard or a mouse device is used for set-up and maintenance purposes. The operation panel is used to interact with the views on the screen, display a new view or to act upon an element within a view. The layout of the pushbuttons, lamps and controls on the operation panel are divided into functional groups, as shown in Illustration ICAS Operator Station Panel. 9
CAS CAS CAS CAS CAS CAS CAS CAS

OPE (Operation) mode This mode covers normal operation of the plant monitoring and control. ENG (Engineering) mode This mode covers OPE mode operation and engineering operation such as parameter and engineering function setting. SYS (System) mode This mode covers all system functions such as hardware setting, system maintenance. Alphabet / Display Select Keys Group The buttons of the views group select and display the views representing the various process areas. The most important and commonly used views are assigned to these buttons so that they are instantly accessible from the operation panel. Each button is labeled with the name of the view. To display the views assigned to these buttons, the user should press the appropriate button.

Control Menu This function button opens the menu for plant control operation. System Menu This function button opens the menu for system utility and engineering function. Alarm Summary This function button calls ALARM SUMMARY on the alarm function window. Event Summary This function button calls EVENT SUMMARY on the alarm function window.. Control Key Group The buttons of this group are used to enter values into control panel and monitoring panel on the Graphic display, when setting parameters or required levels. Alphanumeric Keyboard The alphanumeric keyboard is a standard, QWERTY keyboard that is located in a compartment under the operation panel. A keyboard selection switch is fitted to select the keyboard. When the keyboard is selected, the buttons of the keypad group are disabled. For a desktop operator station, the keyboard selection switch is a toggle switch located on the back of the operation panel.

A/M

A/M

A/M

A/M

A/M

A/M

A/M

A/M

ENG OPE SYS

PANEL CLOSE

PANEL SELECT

SHIFT

SV

REF

V. SLOW

SLOW

FAST

PANEL CLOSE

10
ON OFF

TAB DETAIL

CUSTUM GRAPHIC

MONITOR MENU

CONTROL MENU

SYSTEM MENU

ALARM SUMMARY

EVENT SUMMARY

1
F8 F9 F10

2
CSR SET
FOCUS 1 SELECT

SHIFT

F1

F2

F3

F4

F5

F6

F7

ALPHA

GAPS

Main Turbine

M/T Remocon

Elect Dist (HV)

Elect Dist (LV)

Gen Control

Overview

System Status

4
9 6 3
ENT DEL BS

EXEC

5 6 7 8

A
FD Fans

B
BMS Overview

C
ACC Overview

D
SH Steam

E
Aux Steam

F
Steam Dump

G
Exh Steam

7 4 1 0

8 5 2 .

CANCEL

2 SELECT

H
Boiler Level HP Feed

J
LP Feed SW Circ

K
CCS FW

M
Dist Plant

N
Fire Fight

O
SWAP Boiler FO FO

P
LO

Q
Gas

R
Fire

S
E/R Fan

U
Vent

ALARM ACK

V
CLOSE Air

W
Refrig

X
Miscellaneous

Y
Motor List

Z
Control Overview

SPACE

3 11

BZ STOP

14 13

12

ICAS Operator Station Panel 1. 2. 3. 4. 5. 6. 7. 8. OPS Power Key Switch Operator Mode Key Switch Track Ball Cursor Click Key Execute Key Cancel Key Alarm Acknowledge Key Buzzer Stop Key 9. 10. 11. 12. 13. 14. Control Key Function Key Ten Key Alphabet/Display Select Key Custom Graphic Window Control Key Cursor Key

Above each button is a red status LED, which will flash when any unacknowledged alarms are active in the view assigned to that button. When all the active alarms in the view are acknowledged, the LED illuminates steadily. If there are no active alarms in the view, the LED will be off. There are several different ways to navigate through the views of the ICAS system : Using the views buttons on the operation panel Using the previous view and next view buttons on the tool bar Using the history function which records the last 20 screens viewed Using the navigator Using the context menu of a module Function Key Group This group contains FUNCTION and SUB FUNCTION buttons. The function buttons (F1 to F10) are user-definable. The sub function buttons provide the following display operation. Tag Detail This function button is active by selecting the monitoring or control point on the main display area of custom graphic. CHANNEL DETAIL or CONTROL PARAMETER TUNING display is called on the system display window. Custom Graphic This function button is active by selecting the monitoring or control point on the main display area of custom graphic. The custom graphic display associated with the selected point is called on the custom graphic display area. Monitoring Menu This function button opens the menu for monitoring point management.

System Functions The functions composing the system are arranged on the hierarchical structure configurations and they are concentrated on the system display for human-machine interface for monitoring and operation of a target plant. Top Menu / Main Menu All operator stations have plant monitoring function for the cargo and machinery parts, and the monitoring system of each part is selected on TOP MENU. The custom graphic display functions are assigned effectively for operation and those screens are called on Main Menu screen by click of button.

Track Ball Operation The trackball is used to position the cursor on the screen and the command that the cursor is placed in the view is executed by pressing the cursor click key put at the upper side of track ball.. Operation Mode Control Operation mode of the system privilege is selected by the operation mode key switch or the user ID with password protection. The key switch allows the user to select following three modes and the system privilege control.

8.2 ICAS Operator Station Operations


Basic Display Format The basic display consists of five areas and each area has the following function.
3. ALARM WINDOW AREA 5. SUB FUNCTION BUTTON AREA 2. TITLE AREA

5. Sub Function Button Area In addition to the function buttons, this area displays the buttons of eleven menus, of which seven have context sensitive commands and five have fixed commands.
SUB FUNCTION
TAG CUSTOM GRAPHIC MONITORING MENU CONTROL MENU SYSTEM MENU ALARM SUMMARY EVENT SUMMARY AUTO ALARM DISPLAY TEST WINDOW RESET HARD COPY

System Display Operation All system functions are integrated in the system display. The display selection is executed with the following operation. 1) Custom Graphic Window Operation The custom graphic window is controlled by five custom graphic window control keys on the operation panel.
HELP

1. MAIN DISPLAY AREA

DETAIL

a) Window Open A new custom graphic window and the graphic being requested are displayed by pressing either No.1 or No.2 window select button before change of display on the main display area. b) Window Close The selected custom graphic window is closed by pressing the window close button. c) Focus All system operations on the display are effective for focused display including the main display area. The focus condition of the main display area and the custom graphic window varies by the focus button. d) Display Swap The displayed custom graphic sheet and the selected custom graphic window are swapped by the swap button after selection of the custom graphic window. 2) Alarm / System Function Window Operation The alarm and the system function windows are controlled by he following operation. a) Window Open

Window Display Function


4. FUNCTION BUTTON AREA

The following window display functions are provided in addition to the above basic display. 1. Custom Graphic Window The custom graphic window is opened for custom graphic display and the same display function as the main display area is provided without control operation. Maximum two windows are available for the custom graphic window at a time. 2. Alarm Function Window The alarm function window is opened for ALARM SUMMARY and EVENT SUMMARY functions. One window display is available for the alarm function window.

1. Main Display Area An individual custom graphic for the monitoring and control operation is displayed and the plant monitoring and control are performed in this area. 2. Title Area The title area displays the status of current screen being displayed as follows:
TITLE BAR
REPOSE STATUS MARK UNACKNOWLEDGED ALARM STATUS MARK INHIBIT STATUS MARK SCAN STOP STATUS MARK

POP-UP

DISPLAY TITLE

LMT : 2008/11/06 14:15 UTC : 2008/11/06 05:15


ALARM STATUS (self-diagnosis) (Flicker : OPS normal, Stop/No mark : OPS trouble) CURRENT MONITORING PART (C : Cargo, M : Machinery) OPS NODE NAME

M M1

3. System Function Window The system functions except the above functions are displayed on the system function window. One window display is available for the system function window.

3. Alarm Window Area The latest two alarm message lines of ALARM SUMMARY are displayed in this area. 4. Function Button Area This area displays 10 function buttons for basic display operation. The contents of function buttons are arranged automatically in accordance with the type of current focused display window..
FOCUS 1 SELECT 2 SELECT

WINDOW FOCUS BUTTON

The alarm / system function window is opened by the sub function key of the monitoring, control or system menu on the operation panel, or the button on the custom graphic display. b) Window Close The window is closed by the close function button or close icon which is provided on all alarm / system function window. c) Focus

No.1 WINDOW SELECT BUTTON

No.2 WINDOW SELECT BUTTON

DISPLAY SWAP BUTTON

FUNCTION
f1

SWAP

TOP MENU

f2

HISTORY

f3

RETURN

LAST SHEET UPPER SHEET PRE SHEET NEXT SHEET

f4

f5

f6

f7

f8

DISPLAY SELECT

f9

CANCEL

f10

All system operations on the display are effective for focused display including the main display area. The focus condition varies by access to the displaying area of alarm / system function window. d) Minimize The minimize icon button is provided on all alarm / system function windows. It minimizes the window to the window title bar.

EXECUTE

WINDOW CLOSE BUTTON


CLOSE

8.2 ICAS Operator Station Operations


3) Display Select All CUSTOM GRAPHIC DISPLAY sheets are selected by the basic function of the display selection. Both monitoring parts for Cargo and Machinery have independent system function structure. a) Selection by Basic Function and Function Buttons The system display is selected by the track ball operation to control the cursor pointer or the basic system function keys on the operation panel. The system display is called by access to the touch target (sheet jump button) with the track ball. The system display selection is available with the following functions. TOP MENU
TOP MENU of the system is called directly from MAIN MENU screen of the custom graphic display. TOP MENU button is displayed only on the function button area in the main menu screen. TOP MENU selects the

b) Pop Up Menu The pop up menu is displayed by the POP UP button on the title area bar. Five buttons are arranged for calling the associated custom graphic sheet. c) Display ID Input The display ID input window is displayed by the DISPLAY SELECT function on the displayed screen. The associated display is called directly for input of display ID or tag number in the display ID input window. d) Display ID Input The display ID input window is displayed by the DISPLAY SELECT function on the displayed screen. The associated display is called directly for input of display ID or tag number in the display ID input window. e) Operation Panel The display can be called from ALPHABET/DISPLAY SELECT key on the operation panel as well. Alarm Management Function The alarm management function is composed of the following basic functions. a) Alarm detecting function for analogue and digital monitoring. b) Alarm suppress and scan stop functions Alarm Repose: The repose function suppresses the alarm of monitoring points registered in the same repose group except range and I/O error detection. Alarm Repose: The alarm inhibit function suppresses the alarm of each monitoring point individually by user except range and I/O error detection. Scan Stop: The scan stop function suppresses all alarms and hold process data updating of each monitoring point individually. c) Alarm buzzer and acknowledge control d) Extension alarm control Alarm Summary ALARM SUMMARY gives user the current abnormal plant condition and displays the alarm point on the alarm summary list in time sequence. The alarm message line is inserted at the top of the alarm summary in alarm condition and it is erased automatically if the plant recovers in the normal condition. Maximum 500 message lines are displayed (25 alarms per page). The display filtering function for GROUP ALARM SUMMARY sorts the alarm messages based on the selected monitoring group.

The following items are displayed for an alarm message on the alarm summary. Date and time at detection of the alarm Tag number (touch target) Service name (touch target) Monitoring group number (touch target) Status of alarm Current process value and status Unit for analogue monitoring The associated custom graphic, channel detail and group alarm summary are displayed on the alarm summary by the display call function. The alarm summary is opened automatically if a new alarm is detected when AUTO ALARM MODE is set on the sub function button area. Alarm Window The latest two alarm messages of the selected monitoring part are displayed on ALARM WINDOW area on the top of screen. Event Summary The events of alarming and recovering are listed on EVENT SUMMARY with colours (red for alarm, white for recovery). Maximum 500 records are displayed (25 alarms per page) in turn from the latest. . The layout of EVENT SUMMARY is the same as ALARM SUMMARY. Alarm / Recovery Log The messages of alarm events are printed out by the alarm printer. The alarm message is printed out with an alarm mark and under line, and the recovery message is with RECOVERY message. Alarm Demand Log The contents of the current alarm summary are printed out as ALARM DEMAND LOG from the alarm printer. The command for printing out is executed on Printer Function Control Display by the user. Event Trace Display The predetermined event messages are listed on EVENT TRACE DISPLAY. The event massage data are stored in Data Server Station (DSS). The maximum 2500 events x 100 files are available for the event trace display function. Display Control Function The following event record sorting functions are provided for the event trace display.

monitoring part either Cargo or Machinery. MAIN MENU


MAIN MENU of the current monitoring custom graphic display is called

directly. HISTORY The last twenty displays which have been selected can be called again on the history list by HISTORY button. RETURN The display sheet which called the present display sheet in the same window is recalled. LAST SHEET Each custom graphic and main menu window has the independent history storage function. The last ten displays selected on the same window can be recalled and the history of the window is erased when the system window has closed. UPPER SHEET The display allocated to the upper stream in the hierarchical structure is recalled. PRE SHEET The previous display in the same display group is recalled in turn. NEXT SHEET The next display in the same display group is recalled. PAGE UP The data on the displays of list style system such as ALARM SUMMARY, EVENT SUMMARY and TAG LIST are shifted one page upward. PAGE DOWN The data on the displays of list style system are shifted one page downward.

8.2 ICAS Operator Station Operations


a) Message Type Selection The messages are sorted out by the selection button on the system window. b) Tug Number Selection There are following two styles to select the tag number. Setting the tag number Setting the wild card c) Even Message Line Search The event message lines are searched by means of a keyword. Monitoring Point Management Function This function consists of the following three basic displays which are displayed hierarchically. Monitoring Group List Monitoring Group Display Channel Detail Display a) Monitoring Group List All monitoring points are classified as the several groups. Information of the monitoring group is summarized on the monitoring group list and the details are displayed by clicking of the group name. b) Monitoring Group Display The information of monitoring which is necessary for the normal operation is displayed on this sheet and the details are called by clicking the service name. c) Channel Detail Display The information of monitoring point is detailed on this display. Two display types are provided, one for analogue monitoring point and the other for digital. The change or adjustment of alarm management parameter can be done on these displays. d) Free Monitoring Group Display User can make arbitrary monitoring groups on the display with the same display format and function as Monitoring Group Display. The free monitoring group display function provides ten display sheets (20 lines x 10 pages) and the tag number for them is set from each operator station. e) Repose Set and Status Display The current conditions of repose groups are shown by the following two categories. Auto repose by external signal condition Manual repose by manual set on operator station Graphic Display Function The system gives human interface for monitoring and control by the following graphic display function. Custom Graphic Display Bar Graph Display Analogue Meter Display a) Custom Graphic Display The custom graphic display can be designed arbitrarily by combination of the basic display elements. b) Bar Graph Display The current process values are indicated on the bar graph display with bar graph elements. The user can make arbitrary bar graph groups by Bar Graph Display Function. The function provides maximum twenty bar graph groups, in which maximum ten analogue monitoring tags are registered. .The setting of bar graph group is available on each operator panel individually. c) Analogue Meter Display The current process values are indicated on the analogue meter display with analogue meter elements in the system window. The user can make arbitrary analogue meter groups by Analogue Meter Display Function. The function provides maximum twenty bar graph groups, in which maximum eight analogue monitoring tags are registered. .The setting of bar graph group is available on each operator panel individually Trend Graph Function The system gives two trend graph function types, one is the real time trend graph and the other is long time trend graph. a) Trend Group List All trend groups are listed as the display selection menu of the trend graph display. The trend graph is called from the list. b) Trend Graph Display The trend graph display indicates process data of analogue monitoring with plotted graph. c) Trend Graph Set Display The user can layout arbitrary trend groups on the trend group set display of each operator station b) Control Panel There are two types of the control panel, one is for digital control and the other is for analogue. Digital Control Panel The digital control panel is used for the control, such as Start / Stop and Auto / Manual mode selection of auxiliary machinery. The digital control panel is composed of maximum ten elements as shown in the figure below. The buttons on the panel are operated by the track ball or the control key on the operation panel. Analogue Control Panel The analogue control panel is used for analogue control loop such as temperature, pressure and level control. The analogue control panel is composed of maximum ten elements as shown in the figure below. The panel is operated by the control key on the operation panel. Control Function The operator station (OPS) makes it for the user to control the machinery and tune the parameters of control processing through VDU operation, and the human-machine interface gives effective circumstance for the plant control operation. a) Monitoring Panel The plant condition is normally monitored by CUSTOM GRAPHIC DISPLY. The monitoring panel is called from the custom graphic display when the details for monitoring point are requested, and the monitoring panel calls CHANNEL DETAIL DISPLAY for alarm parameter setting operation. Two panel types are provided, one is for digital monitoring and the other is for analogue.
M034VPA
EDSHTR DUMP STM IN VV
ALM RPS INH S/S

MTIST621B
2B SHTR

SERVICE NAME & MONITORING TAG NO. STATUS MARK (alarm, repose, inhibit, scan stop) ALARM STATUS PROCESS STATUS (signal status)
600C

OUT TEMP.
ALM RPS INH S/S

SERVICE NAME & MONITORING TAG NO. STATUS MARK (alarm, repose, inhibit, scan stop) PROCESS VALUE ALARM STATUS
100%

PROCESS VALUE

NORMAL OPEN
I/O ERR

400 LOW

OPEN CLOSE INTERMED INTERMED

ASSOCIATED SIGNAL STATUS I NDICATOR (individual signal condition indication)

PROCESS VALUE & ALARM SET POINT (bar graph indication)

MONITOR GROUP

0C

0%

M44
I/O CHANNEL

MONITORING GROUP NO. I/O CHANNEL ASSIGNMENT

MONITOR GROUP

M41
I/O CHANNEL

MONITORING GROUP NO. I/O CHANNEL ASSIGNMENT CHANNEL DETAIL DISPLAY CALL BUTTON

M21-01-07
CHANNELDETAIL

CHANNELDETAIL

CHANNEL DETAIL DISPLAY CALL BUTTON

DIGITAL MONITORING PANEL

ANALOGUE MONITORING PANEL

8.2 ICAS Operator Station Operations


f) Control Parameter Tuning Display
MEISB321C_C1 T1 ACB CONTROL
OPE PV SV MV
260.0

b) Tag List Display All tags being registered in the system are displayed on the tag list display and related channel detail display for the monitoring tags and control parameter tuning display for control tags are called from this display directly. The following functions are provided for the tag number selection. Tag type selection (monitoring and control) Tag number set (tag number input) Wild card set (tag number input with wild card) Keyword search c) System Clock Adjustment Display Two system clocks of UTC and LMT for system function are managed on the system clock adjusting display. d) Printer Function Display The system provides the following printer functions and they are managed on the printer function control display. Logging Function 1) Noon Report Log The predetermined process data are collected at 16:00, 20:00, 0:00, 4:00, 8:00 and 12:00 everyday based on LMT. All collected data are automatically printed out at 12:00 on the format with the logging printer. 2) Noon Report Log of the Last Data The last days noon report log data are stored in the system and they can be printed out again on the same format of Noon Report Log. 3) Demand Log The instantaneous data at the demand requested time and the latest 5 samples of noon report log data are printed out on the format from the logging printer. 4) Periodical Report Log 5) Alarm Parameter List 6) Control Parameter List Printer Control The printer management functions are provided on the printer function control display for control of the above printer operations. The following displays and functions are provided for the system utility and engineering function besides the above. a) b) c) d) Parameter Management Display Program Management Display Logic Program Monitoring Display System Maintenance Function

MLCW811_C1 1ST FW HTR LEVEL CONT


OPE

CONTROL TAG NO. CONTROL SERVICE NAME PROCESS VALUE SET VALUE MANIPULATE VALUE

-50 -25 68.5


100.0

mm mm %

The details of information in the control loop are shown on the control parameter tuning display in the system window. Additionally, the change or adjustment of control parameters of each loop is available on the display. The following items are displayed. Tag number and service name Trend graph for SV, PV and MV Current value for SV, PV and MV Attribute data of control program Control parameters (indication and setting) g) Control Parameter List The control parameter list is provided in addition to the channel detail display and the control parameter tuning display which access to the system parameters for monitoring and control function. The control parameters are listed on the display and they can be accessed from this display exclusively. h) Control Overview Display The summarized information of analogue control panel and monitoring panel is displayed on the control overview display. The relevant control group display, control panel and monitoring panel can be called from this display. System Utility and Engineering Function The System Utility and Engineering Function is called on the system window and the custom graphic display This function allows the user to carry out the system operation such as system maintenance through VDU. a) System Status Display The system is composed of various kinds of system components being connected by the network system. All system components are monitored by means of the system diagnosis function. The current system conditions are displayed on the system status display and the user can get the information at the system abnormal condition. The system provides the following status monitoring function. OPS status (overview) OPS status (details) Printer status PCS status Network status (Unit network) Network status (Local bus network) IOS status I/O board status GWC status GWC communication status DSS status System power source status Console and system cabinet status

DISCORD ALARM

NORMAL NOT AVAIL CLOSE INTERMED OPEN CONT OFF


06

0.0

50.0

DATA INDICATOR

-200.0

08

-300.0 mm

0.0 %

CASCADE
AUTO MANUSL
RTN PRE NEXT CH DTL RTN PRE NEXT CH DTL PRE TUNE PRE TUNE

CONTROL STATUS INDICATION CASCADE MODE SELECT BUTTON AUTO/MANUAL MODE SELECT BUTTON DISPLAY CONTROL FUNCTION BUTTON

DIGITAL CONTROL PANEL

ANALOGUE CONTROL PANEL

c) Control Display The plant control operation is done by the monitoring / control panel. The maximum two panels can be displayed simultaneously on the control display, monitoring panel is at the left and the control panel is the right side. The monitoring panel is called on the main display area by clicking the process data indicator on the custom graphic display. The control panel is called on the main display area by clicking the control panel calling box which is assigned on the target equipment such as auxiliary machinery and control valve on the control display on the main display area. The monitoring / control panel call function is not provided is called on the main display area by clicking the process data indicator on the custom graphic display. d) Control Group Display (8 Loop Control Display) The control group display is a specialized display for the plant control purpose. The maximum eight control panels and monitoring panels are distributed on one control group display. The display makes it possible to start or stop the auxiliary machinery or to control the valve by the track ball or the operation panel keys. e) Free Control Group Display The user can make arbitrary control group with the free control group function. This function has maximum 50 free groups, in which the maximum 8 control panels and monitoring panels can be registered. The free control group is set on each operation station.

8.3 Graphic Displays


The following custom graphics are available.

Custom Graphic Main Menu


Machinery Overview Main Turbine
1. Main Turbine L.O. System 2. Main Turbine Bearings 3. Main Condenser 4. Main Turbine Trip & Auto Slow Down 5. Main Turbine Remote Control Overview 6. Main Turbine Remote Control Monitoring

Steam Piping System


1. Superheated Steam 2. Auxiliary Steam 3. 1.0MPa Auxiliary Steam 4. Steam Dump 5. Exhaust and Gland Exhaust Steam

Boiler F.O. Supply Piping System


1. No.1 Boiler F.O. Supply 2. No.2 Boiler F.O. Supply

Power Management System


1. Electric Distribution (High Volt) 2. Electric Distribution (Low Volt) 3. Generator Control

F.O. & L.O. Piping System


1. F.O. Filling and Transfer 2. L.O. Purifier and Transfer 3. Stern Tube L.O. System

4. Frequency Control Sensor Select 5. No.1 Turbine Generator 6. No.2 Turbine Generator 7. No.1 Diesel Generator 8. No.2 Diesel Generator

Main Boiler
1. Boiler Sub Menu 2. FD Fans and Air Heaters 3. Soot Blower 4. BMS Overview 5. No.1 Boiler BMS Overview 6. No.2 Boiler BMS Overview 7. Boiler Trip and BMS Fatal Condition 8. ACC Overview 9. Boiler Condition Overview 10. No.1 Boiler ACC Overview 1/2 11. No.1 Boiler ACC Overview 2/2 12. No.2 Boiler ACC Overview 1/2 13. No.2 Boiler ACC Overview 2/2 14. ACC Signal Monitor

Boiler Feed Piping System


1. Boiler Level 2. HP Feed System 3. LP Feed System

Fire Fighting System


1. E/R Gas and Fire Fighting 2. Fire Detector

9. Emergency Generator 10. Insulation and UPS Status 11. Blackout Recovery

Sea & Fresh Water Piping System


1. Sea Water Circulation System 2. Sea Water Service 3. Ship Side Valve 4. CCS Fresh Water Service 5. D/G Cooling Line 6. Distilled Water Plant 7. Domestic Water Service 8. Bilge / Waste Oil and Sewage 9. Fire Fighting Sea Water

Miscellaneous
1. E/R Vent Fan 2. Ventilation 3. Compressed Air System 4. Refr1gerator and Air Conditioner 5. Steering Gear and Miscellaneous

Motor List
1. Motor List

Custom Graphic Main Menu


1 MACHINERY

02

OVERVIEW

11 9 21 20 ELECTRIC BLR SUB MENU DIST(HV) 3 12 10 22 21 31 23 33 M/T LO FD FAN & BMS ELECTRIC SYSTEM AIR HTR OVERVIEW DIST(LV) 4 13 11 23 22 32 24 34 M/T GENERATOR NO1 SOOT BLOWER BEARING CONTROL BLR BMS 5 12 25 14 24 35 FREQ CONT MAIN NO2 CONDENSER BLR BMS SENSOR SEL 6 26 15 13 25 36 NO1 BLR TRIP M/T TRIP & T/G &BMS COND SLOW DOWN 7 16 14 26 NO2 M/T T/G REM-CONT 8 17 15 27 REM-CONT NO1 SYS D/G MONITOR MAIN TURBINE
16

30

34

41 39 SH STEAM BLR LEVEL

27

28 NO2 D/G

3A 35 42 40 AUXILIARY HP FEED STEAM SYSTEM 28 3B 36 43 41 BLR COND LP FEED 1.0MPaG OVERVIEW SYSTEM AUX STEAM 29 37 3C 44 NO1 BLR STEAM DUMP ACC(1/2) 30 3D 38 45 EXH & NO1 BLR GLAND EXH ACC(2/2) STEAM 31 3E NO2 BLR ACC(1/2) 32 3F NO2 BLR ACC(2/2) 33 3G ACC OVERVIEW
ACC SIGNAL MONITOR

51 42 61 SEA WATER CIRC SYS 52 43 62 SEA WATER SERVICE 53 44 63 SHIP'S SIDE VV 45 64 CCS FW SERVICE 46 65 D/G COOL LINE 47 66
DIST WATER PLANT

71 53 81 56 91 58 A1 E/R GAS & FO FILL & E/R VENT FIRE FIGHT FAN TRANSFER 52 72 54 82 57 92 59 A2 NO2 BLR LO PURIF& FIRE VENTILATION DETECT FO SUPPLY TRANSFER 55 60 83 A3 S/T LO COMPRESSED AIR SYSTEM SYSTEM 61 A4 REF & AIR COND A5 62 STEERING GEAR&MISC
51

66

M1

NO1 BLR FO SUPPLY

MOTOR LIST(1/15)
67

M2

MOTOR LIST(2/15)
68

M3

MOTOR LIST(3/15)
69

M4 M5

MOTOR LIST(4/15)
70

MOTOR LIST(5/15)
71

M6

MOTOR LIST(6/15)
72

67 DOMESTIC WATER SERV 49 68 BILGE/WO & SEWAGE


50 69 FIRE FIGHT SEA WATER

48

M7

MOTOR LIST(7/15)
73

M8

MOTOR LIST(8/15)
74

17

29 E/G

M9

MOTOR LIST(9/15)
75

18

2A 2B

MA MB MC MD

INS & UPS STATUS


19

MOTOR LIST(10/15)
76

BLACK OUT RECOVERY

MOTOR LIST(11/15)
77

MOTOR LIST(12/15)
78

MOTOR LIST(13/15)
79

ME MF

MOTOR LIST(14/15)
80

MOTOR LIST(15/15)

MAIN TURBINE
81

ELECTRIC
82 83

BOILER
84

STEAM
85

FEED SYSTEM
86

WATER SYSTEM

FO & GAS SYSTEM


87

FO GO & LO SYSTEM
88

SAFETY SYSTEM
89

MISCELLA -NEOUS
90 91

MOTOR LIST

GM01 CUSTOM GRAPHIC MAIN MENU

4-2-1

Machinery Overview
208 ELECTRIC

PORT

STBD
29

No2 T/G

No2 D/G

(GM21)

No1 D/G
9

No1 T/G

No2

No1 FG
38

0 kW 30 0A 0 0
ACC Master
26

25

0 kW 21 0A
HVMSB2

20

0 kW
18 14

0A
MSB1

10

0 kW 2 0A

0
41

(kg/h) ACC Master

0.0 % 0.0 MPa


No2 BLR Trip
49 43 48

47

0
42

FO
39

19

15

0.0 % 0.0 MPa


35 34 17 16

33

212 BOILER

0C

(GM30)

No1 BLR Trip Boiler Deaerator


27 209 HP FEED SYSTEM

37

0 C

12

1
FDW PP
6

Steam
44 MAIN TURBINE 213 SH STEAM 211

0 mm

22

(GM52)

0.0 knot 0 kW 0 rpm


46 45

(GM11)

(GM41)

L/P
32 31

R/G H/P
36

Conds PP

Main Condenser

210

LP FEED SYSTEM

13

11

2 0.0
MPa

1
28

0 kPa 0 mm
24

23

(GM53)

Drain PP

40 201 WATER SYSTEM FO & GAS SYSTEM 202 FO GO & LO SYSTEM

M/T Trip
203 SAFETY SYSTEM 204 MISCELLA -NEOUS 205 MOTOR LIST1 206

ATMOS DRAIN TK

0 mm
207 CONT OVERVIEW

GM02 MACHINERY OVERVIEW

4-2-2

S2229/30

Main Turbine
217

(GM53)

0 C

67

55

0 C
56

1st FDW HTR

0.00 MPa
LP T VIB & POS Pos 83 PosH 3rd Bleed VV

68

0.0 MPa
50

AST Guard VV
42

* Gov A
41

AST M VV
35

General M a i n T u r b i n e R u n h o u r

0.0 mm

0 %
29

28

Stop

1 2

* A
45

0 h
3

0.00 mm
Vib
84

72

LP FEED SYSTEM

211

Ship' Speed Shaft Power Torque Shaft Revolution Rev Counter Scoop System

0 knt
4

LP Turbine

VAH

AST T

AST Water Spray VV * M a r k e d


REM-CONT

(GM53) V V
215 37

0 kW
5

73

A Water Spray VV

36

0 kNm 0 rpm
7 6

0 m 0.00 MPa 0.00 MPa


64 51 63 57

( G M 1 6 )
46

0 Rev
SCOOP SYSTEM

x10

M
47

0 % 0 %

43

212 AUX STEAM

44

M HP T VIB & POS Pos 88 PosH HP Turbine Out In


78 94 216 65 66

(GM42)

30

104

0
C
26

Off

14

(GM61) No2 Main Conds Pump No1 12 22 15 D D R


23

208

0.00 mm
Vib
89

77

0 C 0 C

MCGP1 HP 1st STG Drain VV

52

31 48

53

VAH

0 m
102

Main Condenser 38 0 kPa


39

AST Manoeuv Drain VV

209 LP FEED SYSTEM

0 C

32

R
16

(GM53)

A
59

93

LO System LO Filter Diff Press

0.00 kPa
9

0.00 MPa
103

1st Stage STM

0 C
99

0.0 MPa
98

58

0 % AHD NZ VV 0.0 mm Gov *


* 54 A
49 61 60 213

0 mm
MAIN CONDENSER

40

LO In Temp LO In Press
33

0.0 C 0.00 MPa


17 11 10

82 69

Emerg Shut
100

(GM14)

2nd Bleed VV
218 AUX STEAM 71

0.00 MPa 0 C
70

0.0 MPa
101 96

0.0 MPa AHD Stop 0 C


95 205 62

M/C SW In Temp M/C SW Out Temp


214 SH STEAM

0.0 C 0.0 C

Control Oil Cont Oil Press DPAH 24 18 No1 13 27 No2 D D R


25

Drain VV

34

0.0 MPa
210 REM-CONT CONTROL

0.0 MPa
A
97

1st Bleed VV
M/T LO SYSTEM 201 M/T BEARING 202 MAIN CONDENSER 203 M/T TRIP & SLOW DOWN 204

0.0 %
206

(GM41)

R
19

(GM16)
207 CONT OVERVIEW

M/T REM-CONT

REM-CONT SYS MONITOR

GM11 MAIN TURBINE

4-2-3

S2229/30

Main Turbine L.O. System


E/R Oil Mist Detect System

LO GRAVITY TK
23 37

LAL

Normal

36

High

Auto Back-Wash Filter

0.00 kPa
C 0.0 19

11

1 5 3

0.0 C

0.0 %

0.00 kPa 18
15

LO CLR No2

PAL

Steady BRG 3 2 1

LP Turbine Astern Turbine HP Turbine No1

0.0
31

0.0
C
30

0.0
C
29

R/G C

Main LO PP

Filter
32

DPAH Lock

No2
35

Aux LO PP
26 24 20 17

No1 34 Lock

PP No 13

ASS Function ASS Mode Set ASS Status 9 6 ASS by

ACO Function ACO Mode Set 4 ACO Status

Shaft Rev

D R
28 33 25

D R
21

2 1

No2 PP ASS No1 PP ASS

No2 ASS-Off No1 ASS-Off

0 rpm
LO P Low

ACO

ACO-Off

14

10

0 C 0 mm
27

Off

LO SUMP TK
201 MAIN TURBINE M/T BEARING 202 MAIN CONDENSER 203 M/T TRIP & SLOW DOWN

208 LO PURIF SYSTEM 205 M/T REM-CONT REM-CONT SYS MONITOR 206 CONT OVERVIEW

(GM82)
207

204

GM12 M/T LO SYSTEM

4-2-4

S2229/30

Main Turbine Bearing


0.0 C
20 18 14 8

A B C D

HP Turbine Thrust Bearing HP Turbine Forward Bearing HP Turbine Aft Bearing LP Turbine Thrust Bearing LP Turbine Forward Bearing LP Turbine Aft Bearing HP 1st Pinion Forward Bearing HP 1st Pinion Aft Bearing HP 1st Wheel Forward Bearing HP 1st Wheel Aft Bearing HP 2nd Pinion Forward Bearing HP 2nd Pinion Aft Bearing LP 1st Pinion Forward Bearing LP 1st Pinion Aft Bearing LP 1st Wheel Forward Bearing LP 1st Wheel Aft Bearing LP 2nd Pinion Forward Bearing LP 2nd Pinion Aft Bearing 2nd Wheel Forward Bearing 2nd Wheel Aft Bearing Main Turbine Thrust Bearing
207 CONT OVERVIEW

0.0 C
R/G Vib

0.0 C

0.0 C

0 m
28

VAH
23

Q P

O
9 1

0.0 C
N
15

0.0 C
LP Turbine
6

F G

D
10

H I

Main Thrust Bearing


30

0.0 C
Reduction Gear
13

0.0 C 0.0 C

0.0 C

PosH

Astern Turbine

J K

Pos
31

0.00 mm

S
16

L M N O

0.0 C
27 21

0.0
C H

0.0 C

0.0 C
G
11

0.0 C
B A
3

HP Turbine

R/G Vib

0.0 C
VAH
25

0.0 C

P Q

0 m
29

R S

0.0 C
22 19

0.0 C 0.0 C
17

0.0 C
12

T U

201 MAIN TURBINE M/T LO SYSTEM

202 MAIN CONDENSER

203 M/T TRIP & SLOW DOWN

204 M/T REM-CONT

205 REM-CONT SYS MONITOR

206

GM13 M/T BEARING

4-2-5

S2229/30

Main Condenser
S T M D u m p V V
212 33 STEAM DUMP 29 11 25 209 M/T REM-CONT LP FEED SYSTEM 208

0.0 %

(GM16) M F Water Spray VV


16 3

(GM53)

(GM44) Aux Condenser

EXH STM

31 34 32

0.00 MPa

0.0 %
213 EXH STEAM DUMP

B
210 AUX CONDENSER

(GM42)

Main Condenser

A/S G

12

0 kPa
(GM45) 26 C
211 24 23 21

22

0 C

19

C D G E

M/C Level Control VV

214 NO2 T/G EXH

(GM26)
AUX CONDENSER

0
mm

0
mm

20

Dump STM Box

Main Conds PP 5 No2 D R H


13 7 6 1 2

F A PAL PAL

D (GM45)
27

215 NO1 T/G EXH

C H

(GM25)

R No115 Main Conds Vac PP 35 9 D No2 Lock


39 37

43 44 38

PAL PAL

ATMOS DRAIN TK
216 1ST FDW HTR

36

30 28

M/C SW In Temp D M/C SW Out Temp

0.0 C 0.0 C

17

ACO E No1 Lock 42

ACO-Off
10 40

18

D R

(GM53)
201 MAIN TURBINE M/T LO SYSTEM 202 M/T BEARING 203 M/T TRIP & SLOW DOWN 204 M/T REM-CONT 205 REM-CONT SYS MONITOR 206

41 207 CONT OVERVIEW

GM14 MAIN CONDENSER

4-2-6

S2229/30

Main Turbine Trip & Slow Down

12 13 14 15

EMCY TRIP Manual Trip Over Speed

11

PRE-WARNING

2 3 4 5 6 7 8 9 10

SLOW DOWN

PRE-WARNING

BLR Steam Drum Level H BLR Steam Drum Level L Main Steam Press L Main Steam Temp H Main Condenser Vacuum L S/T BRG Temp H One BLR Trip Main Condenser Level H SLOW DOWN REQUEST

HP Rotor Excess Vib LP Rotor Excess Vib HP Rotor Axis Excess Pos LP Rotor Axis Excess Pos LO Press LL Cont Oil Press LL Main Condenser Vacuum LL Both BLR Trip BLR Steam Drum Level HH Main Condenser Level HH Auto Spin Over Speed Turning Gear Not Disengage Safety System Power Failure

LP Turbine

16 17

Reduction Gear

Astern Turbine

18 19 20 22

HP Turbine

23 24 25 26 27 28

31

Main Condenser Level H (Astern)

Trip Bypass
30

Auto Slow Down Bypass


29

Normal

Normal

201 MAIN TURBINE M/T LO SYSTEM

202 M/T BEARING

203 MAIN CONDENSER

204 M/T REM-CONT

205 REM-CONT SYS MONITOR

206 CONT OVERVIEW

207

GM15 M/T TRIP & AUTO SLOW DOWN

4-2-7

S2229/30

Main Turbine Remo-Con Overview


PROPULSION CONTROL SEQUENCE Telegraph
NAV FULL A H E A D FULL HALF SLOW DEAD SLOW STOP DEAD SLOW A S T E R N SLOW HALF FULL CRASH ASTERN
64 65 66 67 68 69 70 71 72 73 74 63 84 56

CONTROL CONDITION 0.0 rpm


24

Control

Cont Pos

Lever Pos Shaft Rev

Governor/VV Lift and Control Mode No1 Rev Raise No2 Rev
31

0.0 rpm
82 83

Plant Mode Program Control

Maneuv Off Off

Not W/H Cont W/H


57 51

0.0 rpm
Nozzle VV

AHD

AHD Gov

30

Over Speed Preventer

0.0 mm
32

26

0.0 % 23
CPU(A)
21

CPU STATUS
PCST1ASER
8 PCST1 208

62

Lever
58

Stop
52

45

RPM Control RPM Cont By-Pass


42 43

Lower 28
29

AHD Gov Upper LMT AHD Gov Lower LMT

Rem-Cont Trouble CPU(B) PCST1BSER


9

CCR

Off
46

Lower

(GMS4)

33 27

M/T PLANT CONDITION 0.0 %


Manoeuvre VV
25

Direct Control

MCR

53

Gov
35

0.0 mm
34

M/T Inlet STM Press Temp

AST

AST
47 48

Guard VV

0.0 MPa 0 C
12 11

10

SUB TELG
76 59

Guard VV Abnormal Water Spray VV Open

Raise
36 37

AST Gov Lower LMT AST Gov Upper LMT

M/S

CONTROL OIL
Cont Oil Press DPAH

0.0 MPa
6 14 1

AUTO SPINNING
AHD Raise
60 49

M/T TRIP & S/DOWN


22

No2

19

Cont Oil PP
15

No1

AHD Lower Turning


54

38

M/T Trip M/T Trip By-Pass M/T Auto Slow Down M/T Auto Slow Down By-Pass
209 18 M/T TRIP & SLOW DOWN

D R 20 Lock
79

D R 7
78

ACO
16 17

ACO-Off PAL PAL

Bypass
77

Start
75

Shaft Stop
44

39 40 41

Lock

Auto Spin Fail


61

TURNING GEAR Engaged

Raise AST
201 MAIN TURBINE M/T LO SYSTEM 202 M/T BEARING 203 MAIN CONDENSER

55

50

Lower AST
205 M/T TRIP & SLOW DOWN REM-CONT SYS MONITOR 206

(GM15)
204

Lock 81 80 Turning Gear Motor


207 CONT OVERVIEW

GM16 REM-CONT SYSTEM OVERVIEW

4-2-8

S2229/30

Main Turbine Remo-Con System Monitor


MAIN TURBINE REMOTE CONTROL SYSTEM MONITORING System Status & Abnormal
36 55

Power Source Diagram in MCB3 Incom UPS1 (AC100V) UPS2


19 9 208 PCST1

M/T Rem-Cont Trouble


54

Lever Cont A B No1 No2 No3 No4 No5

Direct Cont
24 37 38 25 26 27

50

Safety System

AC/DC AC/DC
20

CPU

PCST1ASER PCST1BSER DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF)

W/H Lever (Digital) W/H Lever (Analog) CCR Lever (Digital) CCR Lever (Analog)

AC/DC AC/DC
10 1

(GMS4)

Signal Converter
11 12 2

39 40 41

51 52

Control Lever Off


13 4 56 57 5 3

MCR Lever (Digital) MCR Lever (Analog)

Fan,etc Gov Motor Control VV Cont Location Unit Direct Control Cont Location Safety System Miscellaneous (Switch Signal,etc) Lamps

28 29 30 31 32 53

42

AHD VV Position AST VV Position Shaft RPM Signal Main Steam Signal AST Water Spray VV Cont Location Unit Fail
17

43 44 45 46 47

I/O No6 SLOT No7 No8 No9 No10 No11 No12 No13 No14
201 MAIN TURBINE

DI(ON/OFF) DO(RY) DO(RY) AI(4-20) AI(RTD-N) AO(4-20)

Others
33

AC/DC AC/DC AC/DC AC/DC

58

48 49

Over Speed Preventer Unit Fail Shaft Stop too Long M/T Wrong Way
23

18

6 7

34 35

M/T REM-CONT ALARM RESET


Reset

Incom IBSST (AC100V)


205 206 M/T REM-CONT

Telegraph

202 M/T LO SYSTEM M/T BEARING

203 MAIN CONDENSER

204 M/T TRIP & SLOW DOWN

207 CONT OVERVIEW

GM17 M/T REMOTE CONTROL SYS MONITORING

4-2-9

S2229/30

HV Power Distribution
NO2 T/G
103

Auto Run

84

NO2 D/G
79

NO1 D/G

39

Auto Run

NO1 T/G

0 kW
104

95

0 kW
85

63

0 kW 0 A
53 40

52

46

0 kW 0 A 0.00 PF
41 42 29 28 27 18

26

21

D
105

0 A 0.00 PF
106 97

96

D
80

0 A 0.00 PF
66 81 65

64

0.00 PF Off STBY


DG1
55

54

D
47

D
22

Off STBY
DG2
67

48

0 V

115 116

107 108

TG2
90

86 87

TG1

23 19 20

Total Black Out


68

0 V
8

0.00 Hz

D
109

COS-G

ICAS
123 98

82

BT2
77 69 70

BT1

D
56

49

COS-G

ICAS
4

24

0.00 Hz

HVMSB2
117 135 120 124

HVMSB1
33 30

No Volt TRM2 R
111 112

93

Short Cir MC2 R


91

83

0 A

Short Cir Ring Main

0 A

50

43

Short Cir MC1 R


37

No Volt TRM1
14

9 128

133 99

129

0 A

34

0 A

15

10

U V W

0 C 0 C 0 C

U
94 134 100

0 C 0 C 0 C
PT100 Fail
3 2

125 126

CM2 R
92 38 137 132

CM1 R
136

35 130

V
36

W
5

PT100 Fail

121

0 A

BTC2 71

57 BTC1

0 A
131 25 51 44 45

TM2 R
122 113 118

HVCSB2 110 Pref Trip-B 88 Pref Trip-C 89

0 A

78 75

R
72

R
61

D
58

0 A
59

HVCSB1 Pref Trip-B Pref Trip-C

TM1
16

11

R D
12

BT-LM2
73 119

BT-LM1
6

0 V
201 ELECTRIC DIST(LV) GENERATOR CONTROL 202

LVMSB2 No Volt 102


203

127

LVMSB1
32

76 204 NO1 T/G NO2 T/G 205 NO1 D/G

D
206

R
74

R
62 207

No Volt
210

60 208 E/G INS & UPS STATUS 209 BLACK OUT RECOVERY

0 V
211 CONT OVERVIEW

13

FREQ CONTROL SENSOR SELECT

NO2 D/G

GM21 ELECTRIC DISTRIBUTION(HIGH VOLT)

4-2-10

S2229/30

LV Power Distribution
0 A BT2
59 47 36 30

BT1

0 A
25 1

23

HVMSB2 No Volt

64

HVMSB1 14 No Volt TRM1


8

74 62

TRM2 R
57 48

31 32

Total Black Out Ring Main

13

D
70

D
10

U V W PT100 Fail

0 C 0 C 0 C
73 63

0 A

0 A

U V W

0 C

66 67

71

0 C 0 C
69 68

72

TM2 D
60

TM1
58 9

PT100 Fail

BT-LM2
33 61 50 51 52

BT-LM1
26 4

0 V

LVMSB2 65 No Volt Pref Trip-A Pref Trip-B


40

LVMSB1
15 16

35 39

R
34

R
28

27

LE2 R
37

LE1 R
24

21

17

No Volt Pref Trip-A Pref Trip-B

0 V

20

E/G
45 54 55

41

Auto Run

76

75

0 kW Off
EG
46 43

42

SC
77

0 A
Ship to Ship

12

BT-EL2 DISCONN ESB


44 56 78 205 NO2 T/G NO1 D/G 29 22

BT-EL1

SC
19

38

ESB Pref Trip


206 NO2 D/G 207 E/G 208 INS & UPS STATUS 209 BLACK OUT RECOVERY 210 CONT OVERVIEW 211

No Volt
204

201 ELECTRIC DIST(HV) GENERATOR CONTROL

202 FREQ CONTROL SENSOR SELECT

203 NO1 T/G

GM22 ELECTRIC DISTRIBUTION(LOW VOLT)

4-2-11

S2229/30

Generator Control
NO2 T/G
76

Auto Run
63 51

62

NO2 D/G
56

44

NO1 D/G
38

21 22

Auto Run
39

NO1 T/G
5 10

STBY

Off
57

STBY-SEL
45

STBY
27

Off
Full Auto
23 28

Trip
89 85

Full Auto
64

2-1
46

Trip
2

D
86 87

58

Pref Trip
47

D
29

D
6 7 24 25

59

On
DG2 DG1
48

90 91

TG2 D
88 74

65 66

TG1
11

3 4

COS-G HVMSB2
92 77

ICAS

D
60

BT2
52 53 49

Total Black Out BT1


41

D
30

COS-G
1

ICAS
HVMSB1
12

D
8

No Volt

Short Cir

Short Cir

40

Short Cir

No Volt Load Share Fail

NO2 T/G
78

NO2 D/G
67

NO1 D/G HVMSB2


54

NO1 T/G
14

0 Load(%) 0 kW 0.0 Hz 0 V 0 A 0.00 PF


84 75

0 Load(%) 0 kW 0.0 Hz 0 V 0 A 0.00 PF


73 61

HVMSB1
42

31

0 Load(%) 0 kW 0.0 Hz 0 V 0 A 0.00 PF


37 26

0 Load(%) 0 kW 0.0 Hz 0 V 0 A 0.00 PF


20 13

79

68

0 kW 0.0 Hz 0 V

0 kW 0.0 Hz 0 V

32

15

80

69

55

43

33

16

81

70

94

93

34

17

82

71

TOTAL LOAD 0 kW
50

35

18

83

72

36

19

AFC
201 ELECTRIC DIST(HV) ELECTRIC DIST(LV) 202

ALC
203

AFC
204 NO1 T/G

ALC
205 NO2 T/G NO1 D/G

PMS FUNCTION
206 NO2 D/G 207 E/G 208

AFC
209 INS & UPS STATUS

ALC
210 BLACK OUT RECOVERY

AFC

ALC
211 CONT OVERVIEW

FREQ CONTROL SENSOR SELECT

GM23 GENERATOR CONTROL

4-2-12

S2229/30

Frequency Control Sensor Selection

48

40

23

TG2 AFC NO2 T/G

DG2 AFC NO2 D/G

DG1 AFC NO1 D/G

TG1 AFC NO1 T/G

49

41

24 14

3 1 4

0.0 Hz

53

50

0.0 Hz

47

42

25

0.0 Hz

0.0 Hz

HVMSB2
51

HVMSB1
35 26 5

0.0 Hz
BUS TIE CONDITION GEN NO1 T/G
52 43

0.0 Hz

MODE SELECT

HVMSB2 (Hz)
27 28 29 30 31 32 33 34

HVMSB1 (Hz)
15 16 17 18 19 20 21 22

GEN (Hz)
6 7 8 9 10 11 12 13

SET SET SET SET


205

36

Auto Auto Auto Auto


206

0.0 0.0 0.0 0.0


208 E/G

0.0 0.0 0.0 0.0


209

0.0 0.0 0.0 0.0


210

Close

NO1 D/G NO2 D/G NO2 T/G

44

37

45

38

46

39

201 ELECTRIC DIST(HV) ELECTRIC DIST(LV)

202 GENERATOR CONTROL

203 NO1 T/G

204 NO2 T/G

207 NO2 D/G

: Selected
CONT OVERVIEW

211

NO1 D/G

INS & UPS STATUS

BLACK OUT RECOVERY

GM24 FREQ CONTROL SENSOR SELECT

4-2-13

S2229/30

No.1 Turbine Generator


214 SH STEAM 29 30 31 51 26

EMCY TRIP
213 20 21 22 23 ALARM REPOSE

NO1 T/G
4

Hand Trip LO In Press LL Over Speed Exh STM Press HH


27

(GM41) VAH Vib


43

Rotor Axis Excess Pos Rotor Excess Vib Gen Trouble Cont Power Fail
24

Off
5

Stop

0 m 0.00 mm

0 hour

32

0 kW

52

PosH Pos
44 45

0 C
1st Stage

42

PAL

0 C
P

0 C

0 C

19

Air CLR
8

(GM64)

212

0.00 MPa
36 46

Air
9

0.0 C
FW Leak

0 C

CCS FW COOLING

0 kPa
34

0 C
PAH

33

0 C

28

25

Stator Coil

0 C
W

0 C

18

7 10

U V W

0 C
11

0 C

216

47

0.00 kPa 0.00 kPa


38

37

MCGP3-1

0 C
12

0 C
3

DPAH

0.0 %
217 AUX STEAM LINE 50

48

0.0 %
40

39 35

49

M Spill Lock No1 T/G Main LO PP P Lock


56

Receiver Make Up
41 57 218

(GM42)

No1 T/G LO Prim PP

16

14

D R
17 15

LO CLR ASS ASS-Off A S S S 55 n s o r S t a t 53 s e u

EXH STEAM

(GM45)

NO1 T/G LO SUMP TK


201 ELECTRIC DIST(HV) ELECTRIC DIST(LV) 202 GENERATOR CONTROL 203 FREQ CONTROL SENSOR SELECT 204 NO2 T/G 205 NO1 D/G 206 NO2 D/G 207 E/G 208 INS & UPS STATUS 209

LAL
210 BLACK OUT RECOVERY

Off

54

211 CONT OVERVIEW

GM25 NO1 TURBINE GENERATOR

4-2-14

S2229/30

No.2 Turbine Generator


214 SH STEAM 29 30 31 51 26

EMCY TRIP
213 20 21 22 23 ALARM REPOSE

NO2 T/G
4

Hand Trip LO In Press LL Over Speed Exh STM Press HH


27

(GM41) VAH Vib


43

Rotor Axis Excess Pos Rotor Excess Vib Gen Trouble Cont Power Fail
24

Off
5

Stop

0 m 0.00 mm

0 hour

32

0 kW

52

PosH Pos
44 45

0 C
1st Stage

42

PAL

0 C
P

0 C

0 C

19

Air CLR
8

(GM64)

212

0.00 MPa
36 46

Air
9

0.0 C
FW Leak

0 C

CCS FW COOLING

0 kPa
34

0 C
PAH

33

0 C

28

25

Stator Coil

0 C
W

0 C

18

7 10

U V W

0 C
11

0 C

216

47

0.00 kPa 0.00 kPa


38

37

MCGP3-2

0 C
12

0 C
3

DPAH

0.0 %
217 AUX STEAM LINE 50

48

0.0 %
40

39 35

49

M Spill Lock No2 T/G Main LO PP P Lock


56

Receiver Make Up
41 57 218

(GM42)

No2 T/G LO Prim PP

16

14

D R
17 15

LO CLR ASS ASS-Off A S S S 55 n s o r S t a t 53 s e u

EXH STEAM

(GM45)

NO2 T/G LO SUMP TK


201 ELECTRIC DIST(HV) ELECTRIC DIST(LV) 202 GENERATOR CONTROL 203 FREQ CONTROL SENSOR SELECT 204 NO1 T/G 205 NO1 D/G 206 NO2 D/G 207 E/G 208 INS & UPS STATUS 209

LAL
210 BLACK OUT RECOVERY

Off

54

211 CONT OVERVIEW

GM26 NO2 TURBINE GENERATOR

4-2-15

S2229/30

No.1 Diesel Generator


38 39 41 40

EMCY Trip
42

OPERATION Gen Trouble GOS-G Local


18

ALARM REPOSE

211

STBY
12

LOCAL Handle SW Turn Gear


47

LO In Press LL Over Speed CFW Temp HH

0 kW
19

16

ALARM REPOSE

Off Engaged
Auto Run

Stop
43

0 hour
COMPRESSED AIR SYSTEM 213

17

Off
(GMA3)

13

Off

0 C
T/C
214 D/G COOL SYSTEM 44

PAL

23

0.00 MPa
Gen Air CLR Air

45

PAL

0 C 0 C
3 7 5

Air CLR

20 21 22

Start Fail Stop Sol VV Fail Cont Power Fail


11

(GM65)

Water
6

FW Leak

0 C

U V W

0 C
8

0 C

0 C
9

0 C

28 0.00 MPa Pre Heater

0 C

27

15

Off

24

D/G FO LEAK TK
14 10

LAH

PAL

LO CLR
35 33

26 29

DPAH

0 C
A S S S e n s o r S t a t u s
30

25

0.00 MPa

P Lock
46

D LO Prim PP R
34

ASS

31

ASS-Off

Off

36

P
212 G/E DO SERV TANK

D/G LO SUMP TK
201 ELECTRIC DIST(HV) ELECTRIC DIST(LV) 202 GENERATOR CONTROL 203 FREQ CONTROL SENSOR SELECT 204 NO1 T/G 205 NO2 T/G 206 NO2 D/G 207 E/G 215 INS & UPS STATUS 208 BLACKOUT RECOVERY 209

(GM81)
210 CONT OVERVIEW

GM27 NO1 DIESEL GENERATOR

4-2-16

S2229/30

No.2 Diesel Generator


38 39 41 40

EMCY Trip
42

OPERATION Gen Trouble GOS-G Local


18

ALARM REPOSE

211

STBY
12

LOCAL Handle SW Turn Gear


47

LO In Press LL Over Speed CFW Temp HH

0 kW
19

16

ALARM REPOSE

Off Engaged
Auto Run

Stop
43

0 hour
COMPRESSED AIR SYSTEM 213

17

Off
(GMA3)

13

Off

0 C
T/C
214 D/G COOL SYSTEM 44

PAL

23

0.00 MPa
Gen Air CLR Air

45

PAL

0 C 0 C
3 7 5

Air CLR

20 21 22

Start Fail Stop Sol VV Fail Cont Power Fail


11

(GM65)

Water
6

FW Leak

0 C

U V W

0 C
8

0 C

0 C
9

0 C

28 0.00 MPa Pre Heater

0 C

27

15

Off

24

D/G FO LEAK TK
14 10

LAH

PAL

LO CLR
35 33

26 29

DPAH

0 C
A S S S e n s o r S t a t u s
30

25

0.00 MPa

P Lock
46

D LO Prim PP R
34

ASS

31

ASS-Off

Off

36

P
212 G/E DO SERV TANK

D/G LO SUMP TK
201 ELECTRIC DIST(HV) ELECTRIC DIST(LV) 202 GENERATOR CONTROL 203 FREQ CONTROL SENSOR SELECT 204 NO1 T/G 205 NO2 T/G 206 NO1 D/G 207 E/G 215 INS & UPS STATUS 208 BLACKOUT RECOVERY 209

(GM81)
210 CONT OVERVIEW

GM28 NO2 DIESEL GENERATOR

4-2-17

S2229/30

Emergency Generator
7 8 9 10

EMCY Trip

CONDITON

ALARM REPOSE
5 ALARM REPOSE 212

STBY
15

LO In Press LL Over Speed CFW Temp HH

Stop
6

0 kW 0 hour
20

Off

Off

11

Auto Run

Stator Coil

12 13 14 16 18

Start Fail Cont Power Fail Emerg Trip Cancel E/G ENG Fail E/G Gen Fail

U V W

0 C 0 C 0 C
3 2

PAL
COMPRESSED AIR SYSTEM

17 213

(GMA2)

P OIL PAN
201 ELECTRIC DIST(HV) ELECTRIC DIST(LV) 202 GENERATOR CONTROL 203 FREQ CONTROL SENSOR SELECT 204 NO1 T/G 205 NO2 T/G 206 NO1 D/G

P
E/G DO SERV TANK

214

LAL (GM81)
19 208 NO2 D/G INS & UPS STATUS 209 BLACKOUT RECOVERY 210 CONT OVERVIEW 211

207

GM29 EMERGENCY GENERATOR

4-2-18

S2229/30

Insulation & UPS Status

46 47 48 50 51

HVMSB1
No1 T/G No1 D/G HVCSB1 No1 HV TRANS
40 37 38

Galley
AC440V AC220V
25 26

MCC
MSB(AC100V) ESB(AC100V)
12 13 14

GENERAL UPS
Insulation Inv-1 MJR TRBL Inv-1 MNR TRBL Inv-2 MJR TRBL Inv-2 MNR TRBL

1 2 3

Heat PPH1
Insulation-1 Insulation-2

MAIN 220V
E/R Serv Accom Serv Heater Serv FWD LT Serv
29 27 28

ECC
MSB(AC100V) ESB(AC100V)

15 16

4 5 6

Heat PPHP
Insulation-1 Insulation-2

52 53 54 56 57

HVMSB2
No2 T/G No2 D/G HVCSB2 No2 HV TRANS

43 41 42

DC110V UPS CCC


MSB(AC100V) ESB(AC100V)
17 18 19 20

No1 Insulation No1 TRBL No2 Insulation No2 TRBL No3 Insulation No3 TRBL No4 Insulation No4 TRBL

7 8 9

Heat PPHS
Insulation-1 Insulation-2

DC24V Batt CH
44

30

Insulation TRBL
31 32 33

MAIN 440V
58 59

45

ICAS UPS1
Insulation MJR TRBL MNR TRBL

21 22 23 24

10

Heat PPPB

LVMSB1 LVMSB2

11

Heat PPSB

ESB
61 39

49

AC440V AC220V
34 35 36

Spare MTR Space HTR

ICAS UPS2
Insulation MJR TRBL MNR TRBL
207 NO1 D/G NO2 D/G 208 E/G 209 BLACK OUT RECOVERY 210 CONT OVERVIEW 211

201 ELECTRIC DIST(HV) ELECTRIC DIST(LV)

202 GENERATOR CONTROL

203 FREQ CONTROL SENSOR SELECT

204 NO1 T/G

205 NO2 T/G

206

GM2A INSULATION & UPS STATUS

4-2-19

S2229/30

Blackout Recovery
1

Blackout SEQUENTIAL START AFTER BLACKOUT TIME 3 4 1 2 W/H & CCR Unit CFW Boost PP MFDWPT Prim LO PP D/G CFW PP D/G CSW PP
53 54 55

TIME
2

1
3

2
Steering Gear Motor
(LVMSB2)
5

TIME

4
Drain PP

TIME

(ESB)
4

0 26 sec (LVMSB2)
27 28

Cont Oil PP Gland Exh Fan


8

15 (LVMSB1) (LVMSB2) (LVMSB1) sec


56 57

(LVMSB1) (LVMSB2)
6

(LVMSB1) (LVMSB2)
29 30

(ESB)

(LVMSB2)
58 59

(LVMSB2)
7

(LVMSB1) (LVMSB2)

20 sec 25 60 sec (LVMSB1) 50 sec 75 sec 80 sec 85 sec


65 62 61

E/R Supply Fan

76 E/R 75 Exhaust Fan 95 (LVMSB1) (LVMSB2) sec Cargo Mach RM 78 77 Exhaust Fan

(LVMSB1/LVMSB2)
79 80

(LVMSB1) (LVMSB2)

(LVMSB1) (LVMSB2)
81 82

Cargo Mach CFW Boost PP FO Pump RM Exhaust Fan FO Heat RM Exhaust Fan

S/T LO PP T/G LO Prim PP D/G LO Prim PP Hot W Circ PP

31

32

(LVMSB1) (LVMSB2)
9 10

5 (LVMSB1) (LVMSB2) sec 33 34 CCS CFW PP


(LVMSB1) (LVMSB2)
35 36

FD Fan
(LVMSB2)

(LVMSB1) (LVMSB2)
83 84

(LVMSB1) (LVMSB2)
11 12

(LVMSB1) (LVMSB2)

M/C Conds PP Aux LO PP Main CSW PP

(LVMSB1) (LVMSB2)
13 14

(LVMSB1) (LVMSB2)
37 38

(LVMSB1)
63

0 (LVMSB1) (LVMSB2) sec 15 Cargo Mach Motor 16 RM Supply Fan


(LVMSB1/LVMSB2)
17 18

Air Comp
64

(LVMSB1) (LVMSB2)
39 40

(LVMSB2)

Und DK Pass 86 110 85 sec (LVMSB1/LVMSB2) Supply Fan Steering Gear RM 87 Supply Fan
(ESB)
88

(LVMSB1) (LVMSB2)
19

BLR F/E Seal Air Fan E/R Bilge PP

10 (LVMSB1) (LVMSB2) sec 41 V/R Comp 42 Aux LO PP


(LVMSB1/LVMSB2)
44 43

(LVMSB1)

(ESB)

EMCY Fire PP RM Supply Fan

Main Circ PP Aux Circ PP


68

(LVMSB1)

(LVMSB1)
20 21

(LVMSB1/LVMSB2)

F/G Comp Aux LO PP FW PP Drink W PP

90 sec

66

(LVMSB2)
67

(ESB)
22

(LVMSB2)

Cargo VV Hyd Oil PP

45

46

(LVMSB1) (LVMSB2)
47 48

(LVMSB1)
69 70

(ESB)
71 72

D/G Start Air Comp FO Burn PP Fire Fight FW PP Fire Line Press PP
208 209 E/G INS & UPS STATUS 210 CONT OVERVIEW 211

(LVMSB2)
23 24

Small Cargo VV Hyd Oil PP Ballast VV Hyd Oil PP Small Ballast VV Hyd Oil PP
202 ELECTRIC DIST(LV) GENERATOR CONTROL 203

(ESB)
25

(LVMSB2)

15 (LVMSB1) (LVMSB2) sec 49 Main Conds 50 Vac PP


(LVMSB1) (LVMSB2)
51 52

(LVMSB1) (LVMSB2) (LVMSB1) (LVMSB2)

95 73 sec (LVMSB1)
74

(LVMSB2)
201 ELECTRIC DIST(HV)

(LVMSB1) (LVMSB2)
204 NO1 T/G

Vent Duct Exhaust Fan


205 NO2 T/G 206 NO1 D/G

(LVMSB2)
207 NO2 D/G

FREQ CONTROL SENSOR SELECT

GM2B BLACK OUT RECOVERY

4-2-20

S2229/30

Main Boiler Sub Menu


206

GM31

205

GM33

Air

Air

No2 BLR

No1 BLR

FD FAN / AIR HEATER & SOOT BLOWER


207

BLR BMS OVERVIEW


GM3A

PV

A/S PID

SV

H/S PID

BLR ACC OVERVIEW


201 FD FAN & AIR HEATER BLR BMS OVERVIEW 202 BLR ACC OVERVIEW 203 CONT OVERVIEW 203

GM30 BLR SUB MENU

4-2-21

S2229/30

FD Fan & Air Heater

Funnel

26

No2 FD Fan
45

Stop
47 46 44 48 50

Lock D

58 28

VENT DUCT EXH FAN 21 No1 D D No2 ACO-Off R ACO R Common Damper
29 25 23 22 20

No1 FD Fan
57

Lock

1 5 4

Stop
3

Air Lock Low Ins Low Current VAH


63 64 52

27

Air
2

0.0
kPa

0.0
kPa

D
7

Lock
61 62 9

49 51

36 AUX STEAM 205

Vib
53

0 micr 0 C
ECO

(GM42)
39 43

38

BLR F/E SEAL AIR FAN 31 No1 D D No2 ACO-Off R ACO R


37 35 33

R
8

AUX STEAM 204

Vib

0 micr 0 C
10

Low Ins Low Current VAH

Lock

60

32 30 59 Lock

(GM42)

54

Smoke

0 C
STM Air HTR

0 C

0 C

15

14

0 C

ECO

Smoke

11

0.00 deg
02 Content
55

STM Air HTR

0.00 deg
02 Content 12

0.0 %
56

0 C
40 16

0 C

0.0 % 0 C
17 13

0 C
41

Wind Box No2 BLR Furnace

0.0
kPa
42

0.0
kPa
18

Wind Box No1 BLR Furnace

0.00
kPa

0.00
kPa

201 BOILER SUB MENU SOOT BLOWER

202 CONT OVERVIEW

203

GM31 FD FANS & AIR HEATERS

4-2-22

S2229/30

Soot Blower
206 DESUPER HTD LINE 35 36

NO2 SOOT BLOWER


Power Source AC440V Power Failure AC100V Power Failure DC24V Power Failure Alarm SB Abnormal Motor Over Load L-SB Time Exceed R-SB Time Exceed EMERG Retract
51 52 54 55 56 48 49 50

(GM42)

PAL
37

0.0 MPa
Warming Blowing

M02VPA
34

M01VPA
16

15

0.0 MPa
Warming Blowing

14

PAL
17 1 2 3

NO1 SOOT BLOWER


Power Source AC440V Power Failure AC100V Power Failure DC24V Power Failure Alarm
4

38 41

18

10

R6
42

SOOT BLOWER CONTROL


64

R6
11

SB Abnormal Motor Over Load L-SB Time Exceed R-SB Time Exceed EMERG Retract

Eco

R5
43

1B Cont
65

Status
32

Seq

Mode
31

Cont Pos
30

R5
29 12

Eco

5 7 8 9

R4
44

2B Cont

Stop

Off

Off

Local

R4
13

R3

R3

R1
46

Funnel
67 45

Funnel
19 66 21

R1 L1
20

No2 BLR
47

R2 Boiler

L1

R2 Boiler

No1 BLR

Super Heater
40 39

Super Heater

Bypass R6
63 201 BOILER SUB MENU FD FANS & AIR HEATER

207

Bypass R1
58

204

R5
62

R4
61 202

R3
60

R2
59

L1
57

Drain

Drain

L1
28

R1
27

R2
26

R3
25

R4
24

R5
23

R6
22 203 CONT OVERVIEW

GM32 SOOT BLOWER

4-2-23

S2229/30

BMS Overview
HDR Vent HDR N2
101

Purge ABN

99

98

Master Vent IGN Gas Rate 53 N2


83

51 52

50 49

Master Vent IGN 48 Gas Rate


29

27

26

Purge ABN

HDR N2
1

HDR Vent

102

N2
104 103

NO2 BLR
BLR Trip
100

BLR Gas VV Trip


61

55

54

85

84

Mast Gas VV Trip FO 106 ABN IGN 108


109 111 115 113 110 92 112 96 94 105

60

59

BLR Gas VV Trip 57 56 N2 Mast N2 PUR ABN 58

N2

NO1 BLR
28

N2
3

BLR Trip
4

31 30

Gas ABN Air 107 REG

FO ABN IGN 89

87

86

Gas ABN Air 88 REG


91

F/G Comp COMMON CONDITION Common Damper 62 Open


63

Gas 33 ABN Air 35 REG


36 38

32

FO ABN 34 IGN
37

Gas ABN Air 8 REG


11

FO ABN 7 IGN
10

90

No2 F/E Fail

No1 F/E Fail

No2 F/E Fail

No1 F/E Fail

FO Boost Up
207 ATOMIZ STM

93

GM42)

No1 43 F/E Fail

No2 F/E Fail

41 42

39

16

No1 F/E Fail

No2 F/E Fail

14

12

116

114

No2 BNR

97

95

No1 BNR

No1 BNR

40

No2 BNR

15

13

65

64

Recirc

FO Back Up

46 17

117

Recirc

BLR FO Trip Hot Start VV Open IGNITION SEQUENCE


118 124 68

66 67 209 208 FO PUMP FO PUMP 47

45

BLR FO Trip
44

FO Temp Bypass

FO Temp Bypass

Hot Start VV Open IGNITION SEQUENCE IGN Ready


18

IGN Ready

GM72)
119

GM71)
25

IGN Gas Rate 120 Gas STBY


121

125

122 123 201 BOILER SUB MENU

IGN Air Rate IGN FO Furn Finish Rate Furn Establish Furn Purge

No2 BLR BMS Cont Pos Fuel Mode


81

BURNER CONTROL Common Gas Cont Pos


75

No1 BLR Fuel Mode BLR Cont Pos

Local Off
204

79

Off
BMS Mode

Local
77 78

74

73

Off Manual

71

69

Local Off
70

HDR N2 Purge
82 203

Mast N2 Purge
80

BMS Mode
72

HDR N2 Purge

IGN Air Rate IGN FO Furn Rate Finish Furn Establish Furn Purge

21

22

23

IGN Gas Rate Gas STBY

19

20

Manual

Off

76

202 NO2 BLR BMS

24 CONT OVERVIEW

205

NO1 BLR BMS

BLR TRIP & BMS COND

GM33 BMS OVERVIEW

4-2-24

S2229/30

No1 Boiler BMS


*ACC 73 Master Vent
90 91 72 71

IGN Gas Rate

33 34

Purge ABN N2
35 32 37 36

HDR N2
1

75

0 x10kg 0 kg/h 0 kPa


92 208 NO2 BLR 82 81

77 79

0.0 %
N2

76

78

BLR Gas VV Trip Mast N2 PUR ABN

0 C
67 68

66

0 kPa
65

NO1 BLR
BLR Trip
2

N2

HDR Vent

PALL PAHH Gas 39 ABN Air 41 REG


42

80

38

F/G Comp Mast Gas VV Trip COMMON CONDITION Common Damper 83 Open 84 FO Boost Up

FO ABN 40 IGN

Gas ABN Air 8 REG

FO ABN 7 IGN No2 F/E Fail F/E


17

(GM35)

209 AUX STEAM

52

No1 BNR Fail No2 F/E F/E Fail 45 44 43 Fail No1 F/E No2 F/E
51

48

46

19

No1 BNR Fail F/E Fail 12 11 10 No1 F/E No2


18

15

13

(GM42)

0.00

0.00

50

0.00

0.00

NO1 BNR
*ACC
210 NO2 BLR 89 87 86

49

47

NO2 BNR
53 20

16

14

0.0 %
85

0.00 MPa 0 C
54 69 70

PALL
21 22

0.00 MPa
23

(GM35)
211 FO PUMP

*ACC

0.0 %
88

FO Back Up BLR FO Trip


56

55 TALL

PALL IGNITION SEQUENCE IGN Ready


26

Recirc

IGN FO Rate

(GM71) NO1 BOILER CONDITION Steam-up Finish


100 99 96 97

FO Temp Bypass

93

0
hour

NO1 BOILER BURNER CONTROL Common No1 BLR Gas Cont Pos Fuel Mode BLR Cont Pos

Hot Start VV Open

EMERGENCY MODE
201 BOILER SUB MENU

95 FD Stop Fan 98 1Fan 2BLR Mode

Local
Mast N2 Purge
64

62

61

Off
BMS Mode

59

57

Local Off
58

O2

0.0
94

HDR N2 Purge
60

IGN Air Rate IGN FO Furn Rate Finish Furn Establish


31

27

28

IGN Gas Rate Gas STBY

24

25

29

101 202 203 NO2 BLR BMS BLR TRIP & BMS COND 204

Off

63

Manual

Furn Purge

30 206 CONT OVERVIEW

BMS OVERVIEW

GM34 NO1 BLR BMS

4-2-25

S2229/30

No.2 Boiler BMS


44

HDR N2 HDR Vent


71

Purge ABN N2
67 51 50

43

IGN Gas Rate

*ACC

6 1

Master Vent N2
74 73 72

NO2 BLR
BLR Trip

49

0 kPa
46

0 C
47 48

45

PALL PAHH

BLR Gas VV Trip Mast N2 PUR ABN

10 12

0.0 %
11 3

0 x10kg 0 kg/h 0 kPa


13 4 207 NO1 BLR 15

N2

FO ABN IGN 78

76

75

Gas ABN Air 77 REG


83 65 63

FO ABN IGN 55

53

52

Gas ABN Air 54 REG


60

14

F/G Comp (GM72) Mast Gas VV Trip COMMON CONDITION Common Damper 16 Open FO Boost Up 17

79 88 86 89 87 85

56

No2 BNR Fail No1 F/E F/E Fail 82 81 80 Fail No2 F/E No1 F/E

No2 BNR Fail No1 F/E F/E Fail 59 58 57 Fail No2 F/E No1 F/E

(GM34)
209 AUX STEAM

0.00

0.00
84

66

0.00
64 62

0.00
61

(GM42)

NO2 BNR

NO1 BNR 0.0 %


19 18 22 21 210 20 NO1 BLR

PALL

90

0.00 MPa 0 C 69
TALL
70

68

*ACC

93

0.00 MPa
PALL
92

91

FO Back Up IGN FO Rate


25

23 24

0.0 %

*ACC

(GM34)
211 FO PUMP

IGNITION SEQUENCE
94

BLR FO Trip

IGN Ready IGN Air Rate


95

(GM72) NO2 BOILER BURNER CONTROL No2 BLR Common Gas Cont Pos BLR Cont Pos Fuel Mode NO2 BOILER CONDITION
33 26 27

100

101

IGN Gas Rate Gas STBY

96

97

98

IGN FO Furn Finish Rate Furn Establish Furn Purge


202 203 NO1 BLR BMS

0
hour
34

FO Temp Bypass FD Fan 1Fan 2BLR Mode


Stop
32

29 30 31

Steam-up Finish Hot Start VV Open


28

Local
HDR N2 Purge
42 BLR TRIP & BMS COND

41

39

Off
BMS Mode

35 36

Local Off
37

Mast N2 Purge
40 38

99 201 BOILER SUB MENU BMS OVERVIEW

Off
204

Manual

O2

0.0
%

EMERGENCY MODE MODE


206 CONT OVERVIEW

GM35 NO2 BLR BMS

4-2-26

S2229/30

BLR Trip & BMS Faital Condition


BOILER TRIP AND BMS FATAL CONDITION
37

Both Boiler Trip NO1 BOILER No1 FO Cut OFF Valve Trip Atomize Steam Press LL FO Temp LL FO Press LL Both FO Pump Stop No1 FO Pump Run No2 FO Pump Run Gas Valve Trip Gas Press HH Gas Press LL Boiler Trip Master Gas Trip Master Gas Valve Trip Master Gas Valve Trip Both Boiler Trip Both Boiler Gas Trip Both Vent Duct Exh Fan Stop 1 Vent Duct Exh Fan Run 2 Vent Duct Exh Fan Run Gas Leak Detect Gas Temp LL

NO2 BOILER Gas Valve Trip Gas Press HH Gas Press LL Boiler Trip Master Gas Trip Master Gas Valve Trip Master Gas Valve Trip Both Boiler Trip Both Boiler Gas Trip Both Vent Duct Exh Fan Stop 1 Vent Duct Exh Fan Run 2 Vent Duct Exh Fan Run Gas Leak Detect Gas Temp LL
59 60 61 62 63

No2 FO Cut OFF Valve Trip Atomize Steam Press LL FO Temp LL FO Press LL Both FO Pump Stop No3 FO Pump Run No4 FO Pump Run No2 Boiler Trip Manual Trip SH Steam Temp HH Drum Level DWL HH(FS) DWL LL(FS) DWL LL (RWLI) FD Fan Trip All F/E Fail BMS Both CPU Stop or I/O Card Fail CPU(A) PCSB2ASER CPU(B) PCSB2BSER
208 PCSB2 56 57 43 44

38 39 40 41 42

17 18 19 20 21

1 2 3 4 5

64 65 66 67 68 69 70 71 73

22 23 45 46 48 24 25 27 28 29 30 31 33

6 7 8 9 10

No1 Boiler Trip Manual Trip SH Steam Temp HH DWL HH(FS) DWL LL(FS)
16

49 50 51 52 54

Drum Level

11 12

0 mm
58

0 mm

DWL LL (RWLI) FD Fan Trip All F/E Fail BMS Both CPU Stop or I/O Card Fail PCSB1ASER PCSB1BSER
35 CPU(A) 36

13 15

55

34

CPU(B)
207

PCSB1

(GMS4)

(GMS4)

201 BOILER SUB MENU BMS OVERVIEW

202 NO1 BLR BMS

203 NO2 BLR BMS

204 CONT OVERVIEW

206

GM36 BLR TRIP & BMS FATAL COND

4-2-27

S2229/30

ACC Overview
MCB22(NO2 ACC) NO2 BOILER
Total Fuel
109

COMMON
0.0

COMMON
52

MCB21(NO1 ACC) NO1 BOILER


30

FO Press %
0.00

0.0

94

STM Flow
81

MPa

t/h Steam Up
Stop
72

62

- - -

- - -

STM Flow 0.0 t/h Feed W

FO Press
15

Total Fuel MPa


1

0.00

0.0

O2 Cont Status PV SV MV Auto/Man Air Status PV SV MV Auto/Man


115 116 117 110 111 112 113

Level
Var
95

Feed W

Master

Master

Steam Up
43

Level
16

O2 Cont
2

Stop 0.0 0.0 0.00

Stop 0.0 0.0 0.0

Var 0 0 0.0

Stop 0.0 0.0 0.00

% %

96 97 98

0 0 0.0

mm mm %

82 83 84

0.00 0.00 0.0

t/h t/h %
85

73 74 75

0.0 0.0 0.0

MPa MPa %

63 64 65

0.0 0.0 0.0

MPa MPa %

53 54 55 56

0.0 0.0 0.0 Manual

MPa MPa %

44 45 46

MPa MPa %

31 32 33

0.00 0.00 0.0 Manual

t/h t/h %
34

17 18 19

mm mm %

3 4 5

% %

Manual

66 Manual

FO
114

Gas
100

FO Deliv
86 76 77 78 79

STM Dump
67 Intermed 57

STM Dump
Intermed
58 59 60

FO Deliv
47

Gas
0
35

FO
0
22 23 24 21 6 7 8 9

Air
Stop 0.0 0.0 0.0 Manual

Stop 0.0 0.0 0.0 Manual

0
101 102

0
87 88 89

Stop 0.0 0.0 0.0

Stop 0.0 0.0 0.0 Manual

% % %
118

0 0 0.0

kg/h kg/h
103

0 0 0.0

kg/h kg/h %
90

MPa MPa %
80

68 69 70

0.0 0.0 0.0

MPa MPa %

0.0 0.0 0.0 Manual

MPa MPa %

48 49 50 51

MPa MPa %

36 37 38 39

0 0 0.0 Manual

kg/h kg/h %

0 0 0.0

kg/h kg/h %

% % %

Manual

104

Manual

Manual

71 Manual

61

25 Manual

10

Atomiz Status PV SV MV Auto/Man


119 120 121

Purge

STM Temp

STM Temp

Purge

Atomiz

0.0 0.0 0.0

MPa MPa %
122

105 106 107

0.0 0.0 0.0

MPa MPa %
108

91 92 93

0.0 0.0 0.0 Manual

C C %
99 211 210 209

40 41 42 20

0.0 0.0 0.0 Manual

C C %

26 27 28 29

0.00 0.00 0.0 Manual

MPa MPa %

11 12 13 14

0.00 0.00 0.0 Manual

MPa MPa %

Manual

Manual

GAS SUPPLY SYSTEM 201 BOILER SUB MENU BLR COND OVERVIEW 202 NO1 BLR ACC (1/2) 203 NO1 BLR ACC (2/2) 204 NO2 BLR ACC (1/2) 205 NO2 BLR ACC (2/2)

(GC22)
206

BMS OVERVIEW 207

(GM33)

FO SUPPLY SYSTEM

(GM71)
208 CONT OVERVIEW

ACC SIGNAL MONITOR

GM3A ACC OVERVIEW

4-2-28

S2229/30

Boiler Condition Overview


Air
77

Common Damper
Stop
76 78 55 54

1 2

No2 FD Fan
79

Off
211 1.0MPa AUX STM 57

Stop
4 3

No1 FD Fan kPa


209 6

Air

Air Flow Cont No3


82

No2
75

No1

0.0

%
214 FO BURN PUMP

0.0

kPa

74

F/G Compressor

( G M 4 3 )

0.0

0.0

Air Flow Cont No1


5

No4
81

(GM72)
0.0
83

0.0
80

64 63

62

21

0.0

0.0

20

19

0.0

18

FO BURN PUMP

No2

%
65

kg/h
0.0
61

MPa
0
58

MPa
0
24

kg/h
23 22

(GM71)
8 7

0.0

FO SUPPLY SYSTEM
85

0.0

FWR

84

67

%
0.00
66 59

kg/h
0.0

kg/h
26

% % MPa
0.00 0

FO SUPPLY SYSTEM
25 10

0.0

% Drum Level
87 86

kPa
0

MPa
60

56

34 33

0.0

MPa

kPa STM PV Air HTR Eco O2


0.0
13

0.0

FWR

%
11

Eco O2
0.0

0.0

MPa ACC Common Cont Pos


Local - - - - -

35

0.0

mm
88

STM PV Air HTR %


40

mm %
210

Drum Level
0.0

0.0

t/h

NO2 BLR Cont Pos


Local

71 215 HP FEED SYSTEM

70

69

68

88 38

36

NO1 BLR Cont Pos


Local
37 30 29 28 27

12

t/h

2 1 No2 Boiler
Stop
73 72

(GM52)
0.0

Master Cont 1B 41 0.0 % 39 2B


0.0 0.0

Master Cont
0.0

2 1 No1 Boiler
Stop
31 32

% MPa
42

HP FEED SYSTEM

(GM52)
0.0

t/h
89

MPa
46 44

45

0.0 0.0

H/S

MPa STEAM DUMP


213 STEAM DUMP 51

0.0

43

t/h
14

( G M 4 4 )
49

0.0

92

0.0
91

90

C
53

0.0

16

15

C
17

0.0

No2
52

0.0

%
0 0
50

47 48

kPa mm Hot Start VV


208 CONT OVERVIEW

Hot Start VV
201 BOILER SUB MENU ACC OVERVIEW 202 NO1 BLR ACC (1/2) 203 NO1 BLR ACC (2/2) 204 NO2 BLR ACC (1/2)

M033VPA
205 NO2 BLR ACC (2/2)

No1
0.0
206 ACC SIGNAL MONITOR 207

GM3B BLR COND OVERVIEW

4-2-29

S2229/30

No.1 Boiler ACC (1/2)


AIR FLOW Low Span
81 80 79

O2 High Span
78

GAS FLOW Vortex


68 67

FO FLOW Flow Meter 55


54

SHTD STM PRESS No1 BLR (1)


34

SHTD STM PRESS No2 BLR (1)


11

Contnt
77 76

Diff Pressure
66 65

FO HDR Pressure 53
52

35

33

No1 BLR (2)


32

12

10

No2 BLR (2)


9

STEAM FLOW High Selected


8 7

VPR HDR PRESS


2 1

0.0

kPa kg/h %
3

NBO
0.0 0
4

0.0

0.0

0.0

0.000

0.000

0.000

0.000

%
82

kg/h

kg/h
69

kg/h
56

kg/h Steam Up Schedule P T


0.0

MPa
38

MPa Dev Press H/S


37

MPa
0.00

MPa
14

t/h MPa
13

0.0

Dev Press
0.0
91

A/S
83

A/S
70

A/S
57

MPa

36

H/S
15

0.0 0.0
94

MPa

92

0.0

%
71

kg/h +

kg/h +

0.0

MPa

+ +

41

MV

PV
0.00 84

212

MPa SV

SV

0.0

PID
72

Excess Air Set


0.000

58

PID PV 211 + PID


42

210

MPa

SV M +
40

39

0.0

MPa
6

Forcing VPR Gas Flow 5 0 kg/h


0.0

SV PV PID

0 0.0

kg/h
59

43

0.0

0.0
44

NO2 BLR ACC(1/2)

209

PV SV PID

85

0.0

% +

% Normal

SV PV PID
48 46 47

Steam Up
0 0.0

(GM3E)

Purge IGN
86

Min Gas SV 0 kg/h


60 61

kg/h %
0.0

45

16 17

0 0.0

kg/h %

0.0
87

+ -

0.0

Min FO SV 0 kg/h From Steam up cont MV


19 26

93

PV 213 SV PID %
0.0

18

0.0

MPa

88

M
89

NO1 CONT STATUS COMMON Cont Pos Common Cont Pos


75

63

62

50

49

30

29

27

24

23

21

20

FD Fan Vane Drive


90

Local

74

Off

73

Local

Gas Flow Control VV


64

0.0
201

%
202 ACC OVERVIEW BLR COND OVERVIEW 203 NO1 BLR ACC (2/2) 204

0.0
205

%
NO2 BLR ACC (2/2)

FO Flow Control VV 51 0.0 %


206 ACC SIGNAL MONITOR 207

31

Hot Start Piston VV

28 Piston

Steam Dump VV

Intermed

Intermed

Steam Dump Control VV1 25 0.0 %

Steam Dump Control VV2 22 0.0 %


208 CONT OVERVIEW

BOILER SUB MENU

NO2 BLR ACC (1/2)

GM3C NO1 BLR ACC (1/2)

4-2-30

S2229/30

No.1 Boiler ACC (2/2)


FO BURN PP DISCHARGE PRESS
66 65

FO BURNER HEADER PRESS


72 71

PRIMARY SHTR OUTLET TEMP


64 63

SH STM TEMP
(2)
50 49 51 48

BLR STM FLOW


(2)
40 41

DRUM LEVEL
FWR
24 38 23

(1)

(1)
39

Monitor
22 21

FEED WATER FLOW


13 12

ATOMIZ PRESS
7 6

PURGE STEAM PRESS


2 1

0.0

0.0

0.0

0.0

0.0

0.0

0.0
44

0.0

0.0

0.0

MPa +
73

MPa -

C Dev Temp
53 54

C
52

C H/S

t/h

t/h Dev Flow


0.0
43

mm
42 25

mm

t/h

MPa

MPa

0.0

H/S
45 55

t/h

A/S

0.0

H
57

H
26

MPa SV
79 213

0.0

PV

212

PV

SV
0.0

67

0.0

PID
78

PID

SV

0.0

C +

PV PID +

0.0

t/h

mm

MPa
74

MPa
0.0

%
76

0.0

Var SV Fix SV

46

mm
47

Var

27

mm SV
210

PV M
28

17

H/S

PID Fix
29

0.0

t/h
209

75

mm

PID

14

0.0

0.0

NO2 BLR STM FLOW


58

20

0.0

16

SV 8 PV PV 0.0 PID PID MPa MPa


15

56

(2)
32 33

(1)
31 30

Override

Normal

68 69

Steam Temp Cont VV


59

0.0

0.0

9 18 10

3 4

0.0

t/h Dev Flow


0.0
37 36 35

t/h H/S
34

FD Burn PP Discharge Press Cont VV 70 0.0 %

NO1 CONT STATUS COMMON Cont Pos Common Cont Pos


62

t/h

Feed Water Cont VV


19

Atomiz Cont VV
11

Purge Stm Cont VV %


5

Local

61

Off

60

Local

H (GM3C)
NO1 BLR ACC(1/2)

0.0
211

t/h

0.0

0.0

0.0

201 BOILER SUB MENU ACC OVERVIEW

202 BLR COND OVERVIEW

203 NO1 BLR ACC (1/2)

204 NO2 BLR ACC (1/2)

205 NO2 BLR ACC (2/2)

206 ACC SIGNAL MONITOR

207 CONT OVERVIEW

208

GM3D NO1 BLR ACC (2/2)

4-2-31

S2229/30

No.2 Boiler ACC (1/2)


AIR FLOW Low Span
81 80 79

O2 High Span
78

GAS FLOW Vortex


68 67

FO FLOW Flow Meter 55


54

SHTD STM PRESS No2 BLR (1)


34

SHTD STM PRESS No1 BLR (1)


11

Contnt
77 76

Diff Pressure
66 65

FO HDR Pressure 53
52

35

33

No2 BLR (2)


32

12

10

No1 BLR (2)


9

STEAM FLOW High Selected


8 7

VPR HDR PRESS


2 1

0.0

kPa kg/h %
3

NBO
0.0 0
4

0.0

0.0

0.0

0.000

0.000

0.000

0.000

%
82

kg/h

kg/h
69

kg/h
56

kg/h Steam Up Schedule P T


0.0

MPa
38

MPa Dev Press H/S


37

MPa
0.00

MPa
14

t/h MPa
13

0.0

Dev Press
0.0
91

A/S
83

A/S
70

A/S
57

MPa

36

H/S
15

0.0 0.0
94

MPa

92

0.0

%
71

kg/h +

kg/h +

0.0

MPa

+ +

41

MV

PV
0.00 84

212

MPa SV

SV

0.0

PID
72

Excess Air Set


0.000

58

PID PV 211 + PID


42

210

MPa

SV M +
40

39

0.0

MPa
6

Forcing VPR Gas Flow 5 0 kg/h


0.0

SV PV PID

0 0.0

kg/h
59

43

0.0

0.0
44

NO1 BLR ACC(1/2)

209

PV SV PID

85

0.0

% +

% Normal

SV PV PID
48 46 47

Steam Up
0 0.0

(GM3C)

Purge IGN
86

Min Gas SV 0 kg/h


60 61

kg/h %
0.0

45

16 17

0 0.0

kg/h %

0.0
87

+ -

0.0

Min FO SV 0 kg/h From Steam up cont MV


19 26

93

PV 213 SV PID %
0.0

18

0.0

MPa

88

M
89

NO2 CONT STATUS COMMON Cont Pos Common Cont Pos


75

63

62

50

49

30

29

27

24

23

21

20

FD Fan Vane Drive


90

Local

74

Off

73

Local

Gas Flow Control VV


64

0.0
201

%
202 ACC OVERVIEW BLR COND OVERVIEW 203 NO1 BLR ACC (1/2) 204

0.0
205

%
NO2 BLR ACC (2/2)

FO Flow Control VV 51 0.0 %


206 ACC SIGNAL MONITOR 207

31

Hot Start Piston VV

28 Piston

Steam Dump VV

Intermed

Intermed

Steam Dump Control VV1 25 0.0 %

Steam Dump Control VV2 22 0.0 %


208 CONT OVERVIEW

BOILER SUB MENU

NO1 BLR ACC (2/2)

GM3E NO2 BLR ACC (1/2)

4-2-32

S2229/30

No.2 Boiler ACC (2/2)


FO BURN PP DISCHARGE PRESS
66 65

FO BURNER HEADER PRESS


72 71

PRIMARY SHTR OUTLET TEMP


64 63

SH STM TEMP
(2)
50 49 51 48

BLR STM FLOW


(2)
40 41

DRUM LEVEL
FWR
24 38 23

(1)

(1)
39

Monitor
22 21

FEED WATER FLOW


13 12

ATOMIZ PRESS
7 6

PURGE STEAM PRESS


2 1

0.0

0.0

0.0

0.0

0.0

0.0

0.0
44

0.0

0.0

0.0

MPa +
73

MPa -

C Dev Temp
53 54

C
52

C H/S

t/h

t/h Dev Flow


0.0
43

mm
42 25

mm

t/h

MPa

MPa

0.0

H/S
45 55

t/h

A/S

0.0

H
57

H
26

MPa SV
79 213

0.0

PV

212

PV

SV
0.0

67

0.0

PID
78

PID

SV

0.0

C +

PV PID +

0.0

t/h

mm

MPa
74

MPa
0.0

%
76

0.0

Var SV Fix SV

46

mm
47

Var

27

mm SV
210

PV M
28

17

H/S

PID Fix
29

0.0

t/h
209

75

mm

PID

14

0.0

0.0

NO1 BLR STM FLOW


58

20

0.0

16

SV 8 PV PV 0.0 PID PID MPa MPa


15

56

(2)
32 33

(1)
31 30

Override

Normal

68 69

Steam Temp Cont VV


59

0.0

0.0

9 18 10

3 4

0.0

t/h Dev Flow


0.0
37 36 35

t/h H/S
34

FD Burn PP Discharge Press Cont VV 70 0.0 %

NO2 CONT STATUS COMMON Cont Pos Common Cont Pos


62

t/h

Feed Water Cont VV


19

Atomiz Cont VV
11

Purge Stm Cont VV %


5

Local

61

Off

60

Local

H (GM3E)
NO2 BLR ACC(1/2)

0.0
211

t/h

0.0

0.0

0.0

201 BOILER SUB MENU ACC OVERVIEW

202 BLR COND OVERVIEW

203 NO1 BLR ACC (1/2)

204 NO1 BLR ACC (2/2)

205 NO2 BLR ACC (1/2)

206 ACC SIGNAL MONITOR

207 CONT OVERVIEW

208

GM3F NO2 BLR ACC (2/2)

4-2-33

S2229/30

ACC Signal Monitor


ACC SENSOR INPUT SIGNAL BOILER BLOCK PCS PCSB1 PCSB2 PCS PCSB1 PCSB2 PCS PCSB1 PCSB2 PCS PCSB1 PCSB2 PCS
1B Steam Pressure(1) 1B Steam Pressure(2) 2B Steam Pressure(1) 2B Steam Pressure(2) FO Header Pressure FO Flow

CONTROL OUTPUT & LOOP BACK SIGNAL BOILER BLOCK PCS PCSB1
Out put Loop Back FO Flow Control 0.0 0.0 0.0 0.0
37 38 39 40

Gas Flow Control

Air Flow Control

Atom Control

FWR Control

STM Temp Control

165B-1S MPa 165B-1S


0.0 0.0
112 111

165B-2S MPa 165B-2S


0.0 0.0
102 101

165B-1P MPa 165B-1P


0.0 1B Steam Flow(1)
92

165B-2P MPa 165B-2P


0.00
84 83

231B-S MPa 231B-P


0.00
76

370B-S kg/h 370B-P


0 0
68 67

0.0

91

0.00

75

% % % %

0.0 0.0 0.0 0.0

29 30 31 32

% % % %

0.0 0.0 0.0 0.0

25 26 27 28

% % % %

0.0 0.0 0.0 0.0

17 18 19 20

% % % %

0.0 0.0 0.0 0.0

9 10 11 12

% % % %

0.0 0.0 0.0 0.0

1 2 3 4

% % % %

MPa

MPa

MPa

0.00

MPa

MPa

kg/h PCSB2

Out put Loop Back

Drum Level (FWR)

Drum Level (Monitor)

1B Steam Flow(2)

2B Steam Flow(1)

2B Steam Flow(2)

166B-S
0
113

157B-S mm 157B-P
0 0
104 103

167B-1S t/h 167B-1S


0.0 0.0
94 93

167B-2S t/h 167B-2S


0.0 0.0
86 85

167B-1P t/h 167B-1P


0.0 0.0
78 77

167B-2P t/h 167B-2P


0.0 0.0
70 69

BOILER BLOCK PCS PCSB1


Out put Loop Back Out put Loop Back 0.0
43

COMMON BLOCK
Master Control STM Dump Control 1 STM Dump Control 2

mm mm

166B-P
0
114

Purge STM Control 0.0


41

FO Deliv Control

mm

t/h

t/h

t/h

t/h

0.0 0.0

33 34 35 36

% % % %

0.0 0.0 0.0 0.0

21 22 23 24

% % % %

0.0 0.0 0.0 0.0

13 14 15 16

% % % %

0.0 0.0 0.0 0.0

5 6 7 8

% % % %

Air Flow

1B Air Flow (High Span)

2B Air Flow (High Span)

O2 Content

Gas Flow

Fuel Gas Diff Press

247B-S kPa 247B-P


0.00 Steam Temp(1) 0.00
115

475B-S kPa 475B-S


0.00 Steam Temp(2) 0.00
105

475B-P
0.00
95

MA1011S kPa kPa


96

436B-S m3/h 436B-P


0.00
80

205B-S
0
71

0.0

87

0.00

79

kPa
72

PCSB2

0.0 0.0

475B-P
0.00 Primary STM Temp

MA1011P
0.0
88

205B-P
0

kPa

116

kPa

106

m3/h

kPa

Atomiz Pressure

Purge STM Pressure

Feed Flow

129B-1S
0.0
117

129B-2S C C C 129B-2P
0.0 0.0
107

119B-S
0.0
97

242B-S C C MPa 242B-P


0.0 0.0
90 89

362B-S
0.0
81

30B-S
0.0
73

MPa MPa

t/h t/h

CONTROL MODE SELECT NO1 BOILER NO2 BOILER Emergency Normal Emergency Normal Drum Level 3 Element 2 Element 2 Element 3 Element Control Control Control Control Control 55 50 60 45
61

129B-1P
0.0
118

119B-P
0.0
98

362B-P
0.0
82

30B-P
0.0
74

Drum Level (FWR) FO Flow Meter Gas Flow Vortex

Drum Level (Monitor) FO HDR Pressure Fuel Gas Pressure

108

56

MPa

COMMON BLOCK
FO Pump Deliv Press
119

62

57

Drum Level Sensor FO Flow Sensor Gas Flow Sensor Air Flow Sensor

Drum Level (Monitor) FO HDR Pressure Fuel Gas Pressure

51

46

Drum Level (FWR) FO Flow Meter Gas Flow Vortex

52

47 48

Gas Temp

Gas Pressure

No1 L/D Surge VV

No2 L/D Surge VV

Other Gas Flow VV

63

58

53

238B PCSB1 PCSB2


201 BOILER SUB MENU ACC OVERVIEW

230B
109

VG933
99

VG943 % %
205

0.0

MPa MPa
202 120

0.0

C C

kPa
100

0.0

125

0.0

123

% %
206

0.0

121

% %
207

64

Air Flow (Low Span)

Air Flow (High Span)

59

Air Flow (High Span)

54

49

Air Flow (Low Span)

238B
0.0 0.0
110

230B
0
203

VG933 kPa
204

VG943
0.0
124

COMMON CONTROL SELECT


PCSB2
66 65 208 CONT OVERVIEW

0.0
126

0.0
122

PCSB1

BLR COND OVERVIEW

NO1 BLR ACC (1/2)

NO1 BLR ACC (2/2)

NO2 BLR ACC (1/2)

NO2 BLR ACC (2/2)

GM3G ACC SIGNAL MONITOR

4-2-34

S2229/30

Superheated Steam
215 NO2 BLR ACC 212 TO AUX STM 2 DESUP HTR (DUMP) 207 206 NO1 BLR ACC

(GM3B)

(GM42)

(GM44)

(GM3A)

Steam Drum

Steam Drum

12

0.0
t/h

No2 Boiler

210

No1 Boiler
BLR LEVEL

0.0
t/h

0 C
8

0 C
6

(GM51)

0.0
MPa Water Drum

0.0
MPa Water Drum

0 C

15

0 C 0.0
MPa

13

16

14

0.0 0.0
NO2 MFDWPT 214 10

MPa
MAIN TURBINE

0.0 MPa
211

213

0.0
MPa

3 208 NO1 MFDWPT 209

MPa

(GM11)

(GM52)
NO2 T/G

(GM52)
NO1 T/G

(GM26)
201 AUXILIARY STEAM 1.0MPaG AUX STEAM 202 STEAM DUMP 203 EXH & GLAND EXH STEAM 204

(GM25)
205 CONT OVERVIEW

GM41 SUPERHEATED STEAM

4-2-35

S2229/30

Auxiliary Steam
0 C
214 MAIN TURBINE 3 8

Deaerator
2

(GM11)
NO1 T/G

0.00
215 MFDWPT EXH STM 216 210

MPa
1

(GM25)
NO2 T/G

(GM52)

0.00 0.00

11

0
mm Exh STM Dump V
4 5

MPa (GM26)
217 DESUPERHEATED STEAM 18 12

MPa

M
218 213

0.0 %
MAIN OR AUX COND

206

(GM41)
SOOT BLOWER

(GM45)
13

MCGP4
219 NO2 STM AIR HTR 211

(GM32)
BLR ATOM STM

30

31

(GM31)
209 NO1 STM AIR HTR 212

0.0 %
0.5/0.17MPaG PRV

A R
36

32 20 33

0.0 MPa 0 C
10 2ND BLEED

(GM3B)
1.0MPaG AUX STEAM

207

(GM31)
16

(GM43)

M 1.0/0.24MPaG PRV
23

17

0.00

14

38

Lock VV ABN

(GM11)

MPa
15

0.0 %
A M
29 19 34 27 35

24

0.0 MPa
22

21

R
28 37 39

0.0 MPa 0 C
26 1ST BLEED

25

220

0.0 %
6.0/1.0MPaG PRV
201 SH STEAM 1.0MPaG AUX STEAM 202 STEAM DUMP 203 EXH & GLAND EXH STEAM 204

0.0 %
1.0MPaG PCV

Lock VV ABN

(GM11)
205 CONT OVERVIEW

GM42 AUXILIARY STEAM

4-2-36

S2229/30

1.0MPaG Auxiliary Steam


NO1 WASTE OIL SETT TK
3

TAH
#2 BLR FO SUPPLY

DO STOR TK (P)
206

FO SETT TK(P)
1

NO2 WASTE OIL SETT TK


4

TAH

TAH

(GM72)
#1 BLR FO SUPPLY

210

IGG GAS OIL TK

INCINE DO TANK G/E LO RENOV TK A/T LO RENOV TK LO RENOV TK NO1 DO SERV TK NO2 DO SERV TK DO STOR TK
37 36 26

FO SIDE TK(P)

(GM71)
HYDRANT HTR

211

(GM69)
207 LO PURIFIER

FWD FO TK CARGO MACH ROOM

(GM82)

0.0 MPa 0 C
28 27

0 C

FO OVERFLOW TK LO SLUDGE TK

29

LO SUMP TK
30 31

LOW SULPHUR FO TK
38

208 HP FEED WATER 209 (GM52) AUX STEAM

0.0 MPa
34

33

1.0MPaG Ext Desup HTR

SEP BILGE OIL TK FO DRAIN TK

TAH

FO SIDE TK(S) FO SETT TK(S)


2

0.0 %

32

0.0 %

TAH
205 CONT OVERVIEW

(GM42)
SH STEAM

201 AUXILIARY STEAM

202 STEAM DUMP

203 EXH & GLAND EXH STEAM

204

GM43 1.0MPaG AUX STEAM

4-2-37

S2229/30

Steam Dump
207

MCGT5

8 6 7

A/S

0.0 % 11
M
20 16

14

0
9

206 LP FEED SYSTEM

M
18

(GM53) NO2 Dump STM Ext Desup HTR


3 15 1

Dump Piston VV
208 DESUPERHEATED STEAM 23

22

0.0 %

0.0 % 12
M
21 17

0
10

0
C

GM41)
209 ACC

0.00 MPa
NO1 Dump STM Ext Desup HTR
13

M
19

(GM3B)

0.0 %

Main Condenser

0 kPa

31

0 C

30

33 32

Dump STM Box

24 25 26 28

Dump Available Dump Steam Press H Main Condenser Vacuum L Main Condenser Sea Water Temp H Aux Condenser Press H

0 mm
210

0 kPa
Aux Condenser

29 MAIN CANDENSER

(GM14)
201 SH STEAM AUXILIARY STEAM 202 1.0MPaG AUX STEAM 203 EXH & GLAND EXH STEAM 204 CONT OVERVIEW 205

GM44 STEAM DUMP

4-2-38

S2229/30

Exh. & Gland leak Steam


TURBO GENERATOR
NO2 T/G NO1 T/G
13 10

FEED WATER PUMP


NO2 NO1

0 kW
12 208 207 No1 T/G 11

0 kW
9 8 4 206 FEED WTR PUMP 1

GM26)

No2 T/G

GM25)

0.0
%

0.0
GM52) %

MAIN TURBINE 0 kW 0 RPM


30 31 15 14

0.00 MPa 27

25 EXH STM DUMP 26

LP
209 MAIN TURBINE

211

Gland Exh Fan


5 2

0 %

GM42) Lock VV ABN


20

HP

GM11) Lock
29

D R
3

MAIN CONDENSER
17 16

Gland Condenser

21

kPa
32 33 28

Lock VV ABN
210

19 18

mm

22

LAH LAL

7 6

0 kPa
Aux Condenser
201 SH STEAM AUXILIARY STEAM 202 1.0MPaG AUX STEAM 203 STEAM DUMP 204

MAIN CONDENSER

23

0 mm
205 CONT OVERVIEW

(GM14)

ATMOS DRAIN TK

GM45 EXH & GLAND EXH STEAM

4-2-39

S2229/30

Boiler Level

208 ACC

204

(GM3A)

31 209

No.2 BOILER
22

No.1 BOILER
6 21

ACC 1

SUPERHEATED STEAM

0. 0 t/h

0. 0 t/h
No.2 No.1
9

(GM3A)

205

(GM41)

0. 0 MPa
23

0. 0 0
7

MPa mm mm
2 34

SUPERHEATED STEAM

(GM41)

0 mm
35 24

8 17 12

ECO

0
Diff.
27

0 mm

0 0. 0 Diff.
MPa

ECO

206

0. 0
MPa
28 18

ACC

(GM3A) FWR
25

0. 0
MPa

13

0. 0
MPa

FWR

10

VV ABN Lock

29 33

0. 0

26 % HP FEED SYSTEM 207

0. 0
(GM52) No.1
14

11 5 % 32

VV ABN Lock

FDWPT

No.2

19

16

20 201
HP FEED SYSTEM LP FEED SYSTEM

0. 0

Recirc

0. 0

15 % 203
CONT OVERVIEW

202

GM51 BLR LEVEL

S2229 / 30

HP Feed System
s/cm No1 BLR No1 BLR M FDW
129 Inj PP TRBL 122 123 124

pH
0.0
117

ppm
0.00 0.00 0.00
87 125 126 127

No2 Boiler A/S


52

0 0 0

MCGP8-2 A

SV DP DP

213

15

66

13

0.0
118

PV
ECO

0.00 0.00 MPa 95


104 96

0.00
MPa A No2 3

0.0
119

114

0.00 MPa 31
94

MPa A
63 103

No2 FWR

0
mm
99 1 204

0.0
%

128 Chemical PP TRBL

0 C
86

0.00 MPa

64

0.00 MPa
L/S

53

107

A/S A
106

33

H/S A H/S
16

A M

BLR LEVEL

102 14

0.00 MPa
3rd STG FDW HTR

0.00 MPa
65

0.00 MPa
54 55

L/S
ECO

(GM51)
4 2

A/S A
115

A/S

105 30

DP PV
216

0.00 MPaDP

32

0.00 MPa

97

0
100

0.0
FWR No1
208

0 mm 0 C A93
89 90

88

0.00
SV MPa

0.00
MPa

No1 mm

MCGP8-1

0 %

91

Cold Start FDW PP


Lock 116
69

No1 Boiler D R
67 68 34

DEARATOR

(GM53)

NO2 MFDWP TURBINE


TRIP
76 109 77 78 79 80 85 98 81 82 83 112 113 1.0 MPaG AUX STEAM 70

0 C
40 56 47

0.0 ppm
206

101 SAH

MODE

AUX STEAM

211

Manual Trip Over Speep Trip LO Press LL EXH Steam Press HH Rotor Vib HH Rotor Axial HH Deaerator LVL LL Trip SV ABN Seal W DPL
23 LO PAL 24 LO TAH

Recirc 43 VV
48

NO1 MFDWP TURBINE


MODE
5

41 42

35

AUX STEAM

TRIP

Ready
ACO
72 71

(GM42) 57 A
58 59

No2

A
Start Fail
49

No1

36 26

(GM42)

Ready
ACO

108 Manual Trip 17

Auto STBY

0.0
%

Start Fail
44

0.0
% 27

25

Auto STBY

0.00
MPa
VV ABN 61 Lock 121

50

0.0
mm/s
60 VAH 51

STBY Select
45

0.0
mm/s
38 VAH

37

0.00
R
39 29

PRIM LO PP
No2
74

MPa

Over Speep Trip LO Press LL 8 EXH Steam Press HH 18 9 Rotor Vib HH 84 Rotor Axial HH 19 92 Deaerator LVL LL
6 7

62

Press
MCGP9

PRIM LO PP
28 VV ABN 120 Lock

LO Tk LAL Rotor Axial H Power Fail

46 Mode Change

No1

21

212

209

(GM41)
SH STEAM 207

LO PAL 22 Trip SV ABN LO TAH 20 Seal W DPL 12 LO Tk LAL 110 Rotor Axial H 111 Power Fail
10 11

(GM43)

201 BLR LEVEL LP FEED SYSTEM

202 CONT OVERVIEW

203

GM52 HP FEED SYSTEM

4-2-41

S2229/30

LP Feed System
82

Deaerator

0 kPa
84 83

0
LALL

85

0
mm
3RD BREED

SAH
209

mm
107

0 C

46

45

NO2 DIST W TK

NO1 DIST W TK
205

PP No

ASS Mode Set 28 29

Drain PP ASS Function ASS Status

Drain TK Level 3 4 5

3 2

No3 PP ASS No2 PP ASS

No3 ASS-Off No2 ASS-Off No1 ASS-Off

31 DIST WATER PLANT

Level High
1

106 LALL

(GM11)
55

MCGL2 1st STG FDW HTR


97

206

(GM65)
42

30

Level Low
2

No1 PP ASS

209

Spill A
43 44

88

(GM52) No2 FDW PP No1


86 87

MFWPT

0
mm

0
C
52 51

0.0 %

ACO Function ACO ACO Status Mode Set 20 27

ACO

ACO-Off

0 C
A
50

47

89

0.0 %

0.0 %
57

0.0 %
A
56

Gland Condenser
48

49

M/T REM-CONT

212

W Spray VV

59

58 60 208

Aux Condenser
M/T AST WATER SPRAY

(GM16)
90 62

A
PP No

0.0 %

0.00
54

40

41

Make Up A
32 34

0.0 %
Grease Extractor 9 DPAH
10 22

A
7

0.0
C

61

GM11
M/C LVL 65

SAH

ppm

53 ASS Mode Set 67 ASS Function ASS Status

0.0
35

SAH

0.00
ppm Drain PP 100 PAL 23 PAL D 24 R
105 25 104 19 99 16

0.0
PAL PAL D 17 R
18 15

11

MPaG
98 12

2 1 Main Condenser

No2 PP ASS No1 PP ASS


75

No2 ASS-Off No1 ASS-Off Lock

High
63

207 DIST WATER PLANT

68

66

Low
64

PAL PAL D 13 R
14

(GM65)

26

0.00 kPa94
96

95

92

0 C
93

No2

77

101 76

0
mm
MAIN CONDENSER 211

0
mm
91

R M/C Conds PP
81 79

ACO Function ACO ACO Status Mode Set 70 69

Lock No2

Lock No1

103

Lock

ACO

ACO-Off
38 71

LAH

No3
37 36

D R

102 80

Lock

72

PAL
74 33

PAL

(GM14)
201 BLR LEVEL HP FEED SYSTEM

0 C
202

No1

0.00 ppm

SAH

0.00 MPa (GM44)

73

DUMP STM EXT DESUP HTR

204

ATMOS DRAIN TK
39

0
mm
21

LAL

0 C
CONT OVERVIEW

203

GM53 LP FEED SYSTEM

4-2-42

S2229/30

Sea Water Circ. System


44

002VPH

0 C

43 10 39

Sea Water Circulation System Condition and Mode Set Condition 1 (Ready) Mode Set Cooling System Available Selected Circ Pump Avail Scoop In VV Avail
40 11 210 8

MCGO3

0 kPa
Main Condenser
41

0 C

38

Selected Disch VV Avail Main Condr Out VV Avail


51

Cooling System
9

Normal Auto Cold Sea Aux PP Off Off Off 0.0 knot
7

50

Control Mode Sea Mode Pump Select Scoop


13

49

0 mm
211 MAIN CONDENSER

12

HSC or LSC VV Open


52

Plant Signal Avail

46

(GM14)
59

Pump Re-circ Available Condition 2 (Transfer) SET PV

0 C

42

020VPH

0.0 %
008VPH Lock VV ABN
25 54 58 23 56

Shaft RPM
19

0 rpm
17

16

Pump Circ Pump Re-circ Ships Speed (Reference)

0 rpm
14

007VPH
53 57 55

Vacuum Lock VV ABN Telegraph

0 kPa Maneuv

0 kPa
15

22

20

10% Aux Condenser

10%
18

012VPH
33 31 28 27

Aux Circ Pump Lock 34


35 37 48

D R ACO
32

D R29
30

Main Circ Pump 26 Lock


36

001VPH

ACO-Off

Low Sea Chest 003VPH


202 203 CCS FW SERVICE D/G COOL LINE 204

Sea Bay 004VPH


205 DIST WATER PLANT DOMESTIC WATER SERV 206 BILGE/WO & SEWAGE 207

High Sea Chest


208 FIRE FIGHT SEA WATER

47

076VPH
201 SEA WATER SERVICE SHIP'S SIDE VALVE

077VPH

Scoop Inlet
209 CONT OVERVIEW

GM61 SEA WATER CIRC SYSTEM

4-2-43

S2229/30

Sea Water Service System


High Sea Chest
22

004VPH
212 DIST WATER PLANT

Main CSW PP No2 D Lock


25 13 11

No2 VACUUM PP
9 10 12 3 2

PAL PAL

0 C

(GM66) S e a B a y
FIRE FIGHT SEA WATER

No1 VACUUM PP

213

R ACO

ACO-Off D
14 15

(GM69)

Lock
21

26

045VPH
20

No1

16

210

MCGO4
19

A
23

18

043VPH CHLORINATOR

003VPH
SCOOP SYSTEM

211

Normal Stop
Cooling Line

8 6

No2 CCS FW CLR

No1 CCS FW CLR

Low Sea Chest

(GM61)

Off
202 203 CCS FW SERVICE D/G COOL LINE 204 DIST WATER PLANT 205 DOMESTIC WATER SERV

17

Auto High Set

7 24 209 CONT OVERVIEW

201 SEA WATER CIRC SYSTEM SHIP'S SIDE VALVE

206 BILGE/WO & SEWAGE

207 FIRE FIGHT SEA WATER

208

GM62 SEA WATER SERVICE

4-2-44

S2229/30

Ship Side Valve


24

002VPH
20

0 kPa
22 23 21

19

0 C
High Sea Chest 077VPH
7 16

Main Condenser

004VPH
6

036VPJ
5

091VPH
4

020VPH
25

0 mm
210 MAIN CONDENSER

0.0 %
(GM14)

12

IGG
1

007VPH Aux Condenser

Main Circ Pump Sea Bay

No3 W.B TK
2

No2
17 15 3

W.B TK 076VPH
9

008VPH 001VPH
18

Aux Circ Pump

003VPH
8

No1

Low Sea Chest Scoop Inlet


201 SEA WATER CIRC SYSTEM SEA WATER SERVICE 202 CCS FW SERVICE 203 D/G COOL LINE 204 DIST WATER PLANT 205 DOMESTIC WATER SERV 206 BILGE/WO & SEWAGE 207 FIRE FIGHT SEA WATER 208 CONT OVERVIEW 209

GM63 SHIP'S SIDE VALVE

4-2-45

S2229/30

CCS FW Service
CCS FW EXP TK
31

LAL

Laboratory

S/T LO FW CLR S/T LO CLR

210

(GM83) No2 Mach Cont RM No2 SWBD RM


IGG Chiller Water Cooler

No2 MFDWP LO CLR No1 MFDWP LO CLR

Air Cond Unit Prov Ref Unit

Air CLR
NO2 T/G

211

Elect&lnst W/S No1 Mach Cont RM No1 SWBD RM ENG W/S

No3 Air Comp No2 Air Comp No1 Air Comp Drain CLR

(GM25) LO CLR Air CLR


NO1 T/G 212

IGG LO CLR

(GM24) LO CLR

CCS CFW PP 22 No2 D Lock


36 26 24 25

40

23 20 21

No2 CCS FW CLR PAL PAL No1 CCS FW CLR


35

Cargo Mach CFW Boost PP No2 6 4 D Lock


15 16 32 8

R
7

0.0 %
M
18

17

0 C

0 C

ACO No1 Lock


33

ACO-Off
12

2 3

PAL PAL

ACO

ACO-Off
28

D R

10

Cargo Mach RM

D Lock
37

11

No1

30

29

13

D R

38

Lock

34

39

W/H & CCR Unit CLR

201 SEA WATER CIRC SYSTEM SEA WATER SERVICE

202 SHIP'S SIDE VALVE

203 D/G COOL LINE

204 DIST WATER PLANT

205 DOMESTIC WATER SERV

206 BILGE/WO & SEWAGE

207 FIRE FIGHT SEA WATER

208

W/H & CCR Unit CLR CFW Boost Pump


CONT OVERVIEW

209

GM64 CCS FW SERVICE

4-2-46

S2229/30

D/G Cooling System


0 C
28 24

0 C
M
22 3

26

29 PAL Jacket 211 NO2 D/G

0 C 0.0 %
46

0 C 0.0 %
30

27 PAL Jacket 210 NO1 D/G

(GM28) Air & LO

(GM27) Air & LO

0.0 %
47 25 12

0 C 0 C
11 10 48

0 C
D/G COOL FW EXP TK
37

0.0 %
1 31

No2 D/G COOL FW CLR


Lock
50

23

LAL D
33

0 C
6

No1 D/G COOL FW CLR

R49

R34

32

Lock

No2 D/G CFW PP

No1 D/G CFW PP

D/G CSW PP No2 Lock


PP No ASS Mode Set 44 51 15

D R

13 14 ACO Function ACO ACO Status Mode Set 35 39

ASS Function ASS Status

D/G Run 42

Sea Bay

2 1

No2 PP ASS No1 PP ASS

No2 ASS-Off No1 ASS-Off No1

No2
40

PAL PAL

45

43

No1
41 19 20

ACO

38

ACO-Off

36

D
21 206

Lock
201 SEA WATER CIRC SYSTEM SEA WATER SERVICE 202 SHIP'S SIDE VALVE 203 CCS FW SERVICE 204 DIST WATER PLANT 205

52

207 BILGE/WO & SEWAGE FIRE FIGHT SEA WATER

208 CONT OVERVIEW

209

DOMESTIC WATER SERV

GM65 D/G COOL LINE

4-2-47

S2229/30

Distilling Plant
211 LP FEED SYSTEM

NO2 DIST W TK
(GM53) No2 CC Dist Plant
29 4 2

No1 SWC Dist Plant

0.0 m3
3

No2

0.00 m
D
40

S e a B a y

Lock

42

R41

NO1 DIST W TK
9

Dist Plant CSW PP


30

0.0 m3
D
43 8

0.00 m
27

33 58

SAH Lock D
55

45

No1 No1
Dist Plant Distil PP

R44

SAH D
52 51

R56 Lock
57

No2

R53 54 Lock

Silver Ion Sterilizer

11

ABN

DRINK W TK
15

0.0 m3 0 C
34

47 31

Dist Plant Circ W Tank

0 C
28

22

13 14

0.00 m FW TK
20

46 Lock R48 No2 Dist Plant Circ W PP

0 C

37

10

0.0 %
36 201 SEA WATER CIRC SYSTEM SEA WATER SERVICE

50

085 VPF

0.0 ppm
32

38

Lock 21 R16 No1 Dist Plant Circ W PP 087 VPF


210 5

0.0 m3 0.00 m 0.0 %


18 19

To Atmos Drain TK
204 CCS FW SERVICE D/G COOL LINE

SAH
DEARATOR

A
202

35

49 203 205 DOMESTIC WATER SERV 206

(GM42)
207 BILGE/WO & SEWAGE

39 208 FIRE FIGHT SEA WATER

24

23 209 CONT OVERVIEW

SHIP'S SIDE VALVE

GM66 DIST WATER PLANT

4-2-48

S2229/30

Domestic Water Service


NO2 DIST W TK
41

NO1 DIST W TK
35 33

Deck Serv

Form & CO2 RM

Gas Bottle RM

Accom

Accom

Accom

Accom

0.0
m3
42

40

0.0
m3
34

0.00
m

0.00
m

To FW Tank Fire Fight FW PP A 59 Lock

10

M
5

FIRE FIGHT FW PRESS TK

Hot Water Heater

UV Sterilizer

No2 Drink W PP Lock


6

17

D R

15 16 1 ASS Sensor Status 20 1ST Auto Sensor 18

ASS Mode Set 22

ASS Function ASS Status

TAH

DRINK W PRESS TK
No2 Hot W Circ PP
4

S/T CFW TK
210 FIRE/BILGE & PP

No2 PP ASS No1 PP ASS

No2 ASS-Off No1 ASS-Off


36

Mineral Injection

Off Off

23

21

2ND Auto Sensor 19

No1 Drink W PP Lock


8

D R

28

Lock
30 43

ABN

(GM69)

DRINK W TK
55 57

FW TK
52 54

No2 FW PP Lock
9

44

D R

38 58

0.0
m3

0.0
m3

Lock
ASS Sensor Status 47 1ST Auto Sensor 45

0.00 m

56

0.00 m
49 50

53

ASS Mode Set

ASS Function ASS Status

No2 PP ASS No1 PP ASS

No2 ASS-Off No1 ASS-Off


27

Off Off

FW PRESS TK

No1 Hot W Circ PP

48

2ND Auto Sensor 46

211 DIST WTR PLANT

32

ABN A
204 CCS FW SERVICE D/G COOL LINE 205 DIST WATER PLANT

No1 FW PP Lock
206 BILGE/WO & SEWAGE 11

D R
207

25 26 208 FIRE FIGHT SEA WATER CONT OVERVIEW 209

(GM66)
201 SEA WATER CIRC SYSTEM SEA WATER SERVICE 202

Silver Ion Sterilizer


203 SHIP'S SIDE VALVE

GM67 DOMESTIC WATER SERVICE

4-2-49

S2229/30

Bilge/Waste oil and Sewage


13

Bilge Separator Separator

OIL CONTENT MONITOR 15 ppm Alarm 51 High 52 Monitor TRBL

Waste Oil Trans PP


31

NO1 LAH 12 TAH WASTE OIL SETT TK LAH 14 TAH WASTE OIL SETT TK NO2

INCINERATOR DO SERV TK
INCINERATOR
1

15

Lock

32

Normal

Bilge Sep Serv PP Lock 54


55 211 LP FEED SYSTEM 56

53

Fire & Bilge PP


34

(GM69)
FIRE FIGHT SEA WATER

210

LAH

33

LAH

Stop
25

24 23 4

Bilge & GS PP
2

#2 TK Oil Cont High #1 TK Oil Cont High

(GM53)

DRAIN INSPECTION TK

E/R Bilge PP Lock 47 Long Run


43

46

44

SEPARATED BILGE OIL TK

FO DRAIN TK

D R
26 22

D Lock Lock
5 3

D
45

R
36 35

ASS

ASS-Off

194 VPJ
59

58

193 VPJ
38

37 17

192 VPJ P S
30 40

16 7

191 VPJ A

A VACUUM TOILET LAH BILGE WELL AFT


60 48 61 57

A
39

A LAH LAH BILGE WELL STBD FWD


18

Eco Sound Del Comp


8

VOID

Trouble

LAH

LC Auto Off

Auto Start Auto Stop


201 SEA WATER CIRC SYSTEM

62 63 202 SEA WATER SERVICE

BILGE HOLD TK
203 SHIP'S SIDE VALVE CCS FW SERVICE 204

SEWAGE Treatment Unit 49 Trouble 50 High Level


205 D/G COOL LINE DIST WATER PLANT 206

LAH BILGE WELL MID


LC Auto Off

LAH

29

SUNKEN
41 42 208

CLEAN DRAIN TK

19

LAH BILGE WELL PORT FWD


LC Auto Off

LC Auto Off

Auto Start Auto Stop


207 BILGE/WO & SEWAGE

Auto Start Auto Stop

20 21

Auto Start Auto Stop

10 11 209 CONT OVERVIEW

FIRE FIGHT SEA WATER

GM68 BILGE/WASTE OIL AND SEWAGE

4-2-50

S2229/30

Fire Fighting Sea Water


Fire Line Press PP
4

Lock To Water Spray Line

9 3

0 C
HYD HTR

25

High Sea Chest

0.0 ppm
27 SAH To Atmos Drain TK

26

From Water Spray Line


8 6 7

Fire Pump D R

004VPH

29

Lock

10

0.0 C
A
5

23

30

Fire & Bilge PP HYV02

Stop
To Hull HYD Line

Fire Station A
31 32

S e a B a y

A HYV03 Main Line From Hull HYD Line


12 17 15

D Lock
11

0.00 MPa
21

16

Bilge & GS PP EMCY Fire PP Lock


13 2

Valve Control
28

Ready
20

Auto

18

003VPH

H Y V 0 1 22

H Y V 0 4
19

210 BILGE SYSTEM

LAL Sea Chest


201 SEA WATER CIRC SYSTEM SEA WATER SERVICE

To Hold Eductor

(GM68)

Low Sea Chest

Fresh Water Tank


202 SHIP'S SIDE VALVE 203 CCS FW SERVICE 204 D/G COOL LINE 205 DIST WATER PLANT 206 DOMESTIC WATER SERV 207 BILGE/WO & SEWAGE 208 CONT OVERVIEW 209

GM69 FIRE FIGHTING SEA WATER

4-2-51

S2229/30

No.1 Boiler FO Supply


42

A
206 FO FILL & TRANSFER

20

(GM81)

28

DPH

0.0 m3
41 23 22

21

No1 BNR FS LAL NO1 BLR


203 BURNER 6

FO Burn PP
33 31

Lock

44

No2
36

D R
32

29

25

ACO

ACO-Off

D R
24

Lock No1
43

(GM33)
16

0.0 MPa

34 35

PAL PAL

(*ACC)

17

M No2 BLR FO HTR


18

No2 BNR

0.0 %
ACC

204

0.0
%

(GM3A)
A
207 1.0MPaG AUX STEAM 38

0
kg/h FO CONTROL MODE
5 4

0.0 %
37

26 205

Large
13

MCGT7-1

Temp

(GM43)
A Small
40 39

0.0 %

27

14

0.0 cst
VISCO

0.0 C

15

12

0.0 C

No1 BLR FO HTR


19 201 NO2 BLR FO SUPPLY

DPH
202 CONT OVERVIEW

GM71 NO1 BLR FO SUPPLY

4-2-52

S2229/30

No.2 Boiler FO Supply


42

A
206 FO FILL & TRANSFER

20

(GM81)

28

DPH

0.0 m3
41 23 22

21

No1 BNR FS LAL NO2 BLR


203 BURNER 6

FO Burn PP
33 31

Lock

44

No4
36

D R
32

29

25

ACO

ACO-Off

D R
24

Lock No3
43

(GM33)
16

0.0 MPa

34 35

PAL PAL

(*ACC)

17

M No4 BLR FO HTR


18

No2 BNR

0.0 %
ACC

204

0.0
%

(GM3A)
A
207 1.0MPaG AUX STEAM 38

0
kg/h FO CONTROL MODE
5 4

0.0 %
37

26 205

Large
13

MCGT7-2

Temp

(GM43)
A Small
40 39

0.0 %

27

14

0.0 cst
VISCO

0.0 C

15

12

0.0 C

No3 BLR FO HTR


19 201 NO1 BLR FO SUPPLY

DPH
202 CONT OVERVIEW

GM72 NO2 BLR FO SUPPLY

4-2-53

S2229/30

FO Filling &Transfer
INCINERAT DO SERV TK
81 82

EMERG GEN DO SERV TK


73

SHORE CONN

F0V2
39 29 100

FWD FO TK
27

LAH LAL

0 0.0
99

m3
28

FWD FO F0V1 Transfer PP


11 8

LAL

0
30

m
98

D R9
103

0.00

MPa

F0V3 213VPL
102 Lock 46

LAH 212VPL
0.0
31

0.0

10

Lock

F0V6
41

F0V5
0.0
40 32

101 Lock 12

F0V4
3

R96
105 ABN 44

%
42

IGG GAS OIL TK


89

DO STOR TK (P)
85

76

NO2 GEN DO SERV TK


0
74

NO1 GEN DO SERV TK


68

DO STOR TK (S)
59

FO SETT TK(P) 50 47 WDH


48

FO SIDE TK (P)
0

87

m3
88

83

m3
84

m3
75

66

m3
67

57

m3
58

m3
49

m3
43

% 104 ABN LOW SULPH TK FO SETT TK(S) 13 WDH 35 16 33 14 0 m3 0 m3


34

R93

0.0
2

% FO SIDE TK (S) 6
4

0 0
7

m3
5

0
90 91

0
86

0.00
79 80

0.00
71 72

0
60

0.00 LC Auto Off


53 LAH 52 TAH 54 LAL

51 45

m
36

0.00 LC Auto Off

15

17

LAH LAL

LAH

LAH LAL

LAH LAL

LAH

LAH

LAH
0
37

LAH

Auto Start Auto Stop (GM72)


205 NO2 BLR FO

55 56

19 LAH 18 TAH

Auto Start Auto Stop

20 LAL

21 22

DO Trans PP Lock
97 63

HFO Trans PP 24 D Lock


95 94 23 26

25

(GM71)
204 NO1 BLR FO 203 CONT OVERVIEW

92 201 LO PURIF & TRANSFER

FO OVER FLOW
202

65

LAH

FO OVERFLOW TK

ASS

ASS-Off

STERN TUBE LO SYSTEM

GM81 FO FILLING & TRANSFER

4-2-54

S2229/30

LO Purifier & Transfer


PORT STBD
20

Water Extract Filter Drain LH

204

G/E LO RENOV TK

G/E LO STOR TK

LO STOR TK

LO RENOV TK

A/T LO A/T LO STOR TK RENOV TK

A/S

1.0MPaG AUX STEAM

(GM43)
9

0.0 C

Heater

LO Purif Lock 14
13

LO Trans PP Lock
21

LO DAILY TK
22

19

LAH

TRBL

LO DRAIN TK
15

DPAH

LO Purif Feed PP 6 DPAH


16

S/T LO PUMP

206

Lock
205

(GM12)
M/T LO SYSTEM

(GM83)

LO SLUDGE TK
17

LAH

NO1 AUX G/E LO SUMP TK


201 FO FILLING & TRANSFER

NO2 AUX G/E LO SUMP TK


STERN TUBE LO SYSTEM

NO1 FDWPT LO SUMP TK


202

NO2 FDWPT LO SUMP TK

NO1 T/G NO2 T/G LO SUMP LO SUMP TK TK

S/T LO DRAIN TK

LO SUMP TK
203 CONT OVERVIEW

GM82 LO PURIFIER & TRANSFER

4-2-55

S2229/30

Stern Tube LO System


PAL
1

S/T LO AFT SEAL TK


4 5

PAH 2 PAL
3

Air Control Unit

LAH LAL

AFT BRG AFT S AFT P

S/T LO FWD SEAL TK


16 20

0.0 C

LAL

24

DPAH

S/T LO Cooler

0.0 C

21

204 CCS FW SERVICE

(GM64)

15

13

S/T LO PP
10

No2 Lock
25

D R
14

ACO
11

ACO-Off

D R
8 22

No1 Lock DPAH

FAL

26

DPAH

23

Drain Collection Unit


19

S/T LO DRAIN TK
27

205 LO PURIF & TRANSFER

LAH

LAH

(GM82)
201 FO FILLING & TRANSFER LO PURIF & TRANSFER 202 CONT OVERVIEW 203

GM83 STERN TUBE LO SYSTEM

4-2-56

S2229/30

E/R Gas and Fire Fighting


GAS DETECTION SYSTEM
Gas Detection System
35 36 24

FIRE FIGHTING SYSTEM

Normal

Local Fire Fight(Water Fog) Release Alarm


3 4

Normal

Engine Room 2nd Deck E/R Vent Fan Room Boiler Space (30%) Boiler Space (60%)

No1 BLR Top No2 BLR Top NO1 D/G NO2 D/G IGG Room Incinerator FO Pump Room (STBD) FO Pump Room (PORT) No1 FO Heat Room No2 FO Heat Room Common FW TK Level
2

5 6 7 8 9

37 38

FIRE FIGHTING SYSTEM


CO2 Fire Extinguish System M a i n E M C Y P o w e r P o w e r

10

Normal Normal

25

11 12

26

Pre Release Alarm

27 28 29 30 31 32 33 34

Main SWBD Room Paint Store E/G & ESB Room Cargo Mach Room HV Trans Room Mach Cont Room Cargo Motor Room Instru & W/Shop

Pre Release Alarm

13 14

High Exp Foam Discharge Alarm


15 16 17 18 19 20 21 22 23

Normal

Engine Room Steer Eng Room IGG Room FO Pump Room (STBD) Incinerator NO1 D/G NO2 D/G No1 FO Heat Room No2 FO Heat Room
202 CONT OVERVIEW

201 FIRE DETECT

GM91 E/R GAS AND FIRE FIGHT

4-2-57

S2229/30

Fire Detecting

NAV DK
1

G DK F DK E DK D DK C DK B DK A DK Upp DK 2nd DK 3rd DK


20

Normal
2

Fire Detection System Engine Room Accommodation Space

8 18

E/R Casing

10

11

Cargo Mach RM
21

12

Cargo MTR RM
19

13

Forward STR

17

Steer Eng RM

14

15

4TH DK Tank Top

16

201 E/R GAS & FIRE FIGHT CONT OVERVIEW

202

GM92 FIRE DETECT

4-2-58

S2229/30

Engine Room Vent Fan


FWD

17

18

D Lock
26

D Engine Room Temp


20

R
19

R
3

21

Lock

No2 E/R Supply Fan

0 C

No1 E/R Supply Fan (Reversible)


4

Stop

14

15

11

12

D Lock
25

D Lock
24

D R
10 23

D Lock R
7 22

R
16

R
13

Lock

No4 E/R Supply Fan

No2 E/R Exhaust Fan

No1 E/R Exhaust Fan

No3 E/R Supply Fan

201 VENTILATION COMPRESSED AIR SYSTEM

202 REF & AIR COND

203 STEER GEAR & MISC

204 CONT OVERVIEW

205

GMA1 E/R VENT FAN

4-2-59

S2229/30

Ventilation System
Bridge Deck G Deck F Deck E Deck D Deck Waste Oil Sett TK Exh Fan
20

Upper Deck

FWD Store Exh Fan


1

Lock 1 Tank

28

C Deck

Lock

35

FWD EL RM Sup Fan


2

B Deck A Deck No2 Vent Duct Exh Fan


21 11 16

Lock

29

D R

ACO
12

No1 Vent Duct Exh Fan D R


8 7 4

Upper Deck Lock FWD Store Flat

Steer Gear RM Sup Fan


26

EMCY Fire PP RM Sup Fan


27

Lock

36

ACO-Off No1 FO Heat RM Exh Fan D R


14 13

17

31

No2 FO Heat RM Exh Fan


25

Work Shop Exh Fan


5

D R

22

2nd Deck FWD PP RM Exh Fan


3

Lock

40

Lock

39

Lock

37

23

15

34

Lock No1 FO PP RM Exh Fan D R


9 6

Steering Gear RM Lock

No2 FO PP RM Exh Fan 18 24 D


38

19

10

33

Lock

3rd Deck

Lock

30

Engine RM
201 E/R VENT COMPRESSED AIR SYSTEM 202 REF & AIR COND 203 STEER GEAR & MISC 204 CONT OVERVIEW 205

GMA2 VENTILATION

4-2-60

S2229/30

Compressed Air System


COMPRESSED AIR
53 29

Fail D R26
25 15

Fire Station E/R GS Air Line


5

No3 Air Comp Lock 57


56

0.00
MPa
General Service Air Receiver
Off

ASS

ASS-Off Fail
30

ASS Sensor Status GS Receiv 55 54

Air PAL Receiver

Deck Use Accom

0.00 MPa
E/R Cont Air Line N2 Generator

11

62

Cont Use

31

No2 Air Comp Lock 58


CP No 46 ASS Function ASS Mode Set ASS Status

D R

27

28

Cargo Mach RM Control Air Dryer


19 14 20 12

32

2 1

No2 CP ASS
47

No2 ASS-Off
33

ASS Sensor Status Cont Receiv 1ST AUTO 2ND AUTO

Air Pressurized Lights Normal 1 6 PAL PAL EMCY 1 8 PAL


7 9

Off Off

No1 CP ASS

No1 ASS-Off
36

Control Air Receiver


16

Fail

Fail

Main Second

Normal 2 1 PAL PAL EMCY 2 3 PAL


2 4

No1 Air Comp Lock 59


37

D R Fail
38

34

0.00
35

No2

No1

Main Second
52

MPa

PAL

PAL

START AIR
No2 D/G Start Air Comp Lock 60
48

40

D R
ASS Sensor Status 39 No2 D/G Receiv 41 23

17

0.00 MPa
No2 D/G

206

0.00
MPa
No2 D/G Start Air Receiver E/G Start Air Comp
13

(GM28)
207

ASS

ASS-Off

Off

PAL
10

E/G

49

ASS
45

ASS-Off

42

No1 D/G Start Air Comp Lock 61


201 E/R VENT VENTILATION 202 REF & AIR COND

D R
203

24 ASS Sensor Status 43 No1 D/G Receiv

Off

No1 D/G Start Air Receiver


18

(GM29) E/G Start Air Receiver

0.00 MPa
No1 D/G

208

0.00
44 204 STEER GEAR & MISC

MPa

(GM27)
205 CONT OVERVIEW

GMA3 COMPRESSED AIR SYSTEM

4-2-61

S2229/30

Refrigirator & Air Conditioner

REFRIGERATOR
Vegetable Room
27

AIR CONDITIONER
No2 Air Conditioner
1 10 7

Lock In Alarm

Defrost

Off
Fish Room Defrost
23

Gas Leak High TAH TAL

Chiler Unit

Lobby Defrost
14

8 9

No1 Air Conditioner


2

Off

21

Gas Leak High


22

Off
15 16

Chiler Unit

TAH

Gas Leak High TAH Air Conditioner Expansion TK


3

LAL

Meat Room Defrost A Lock


28

Off

26 24

Gas Leak High


25

Dairy Room Defrost


17 18

13

31

TAH

Off

Gas Leak High TAH TAL

No2 Prov Ref Comp


12

RETRIGERANT GAS LEAK Air Cond Room 1 Air Cond Room 2 Air Cond Room 3
4

A
32

11

High High High

19 20

Lock

No1 Prov Ref Comp

201 E/R VENT VENTILATION

202 COMPRESSED AIR SYSTEM

203 STEER GEAR & MISC

204 CONT OVERVIEW

206

GMA4 REFRIGERATOR & AIR CONDITIONER

4-2-62

Steering Gear and Miscellaneous

STEERING GEAR
Over Load No Volt Phase Fail
13 14 22 15 12 5 6 7

Over Load No Volt Phase Fail

Lock

Lock

21

No1 Steering Gear Motor

No2 Steering Gear Motor Cont Motor

Normal
Auto lsolation System
11

16

Normal

Hydraulic Oil Tank Level No1 No2


19 20

Auto Pilot System No1 No2


17 18

LAL LAL

Power Fail Power Fail

Normal

LIFT
Lift Alarm

GENERAL ALARM Off


1

CO2 CONCENTRATE
2

System Power

Normal

Cabin Public Space

3 4

High High

PATROLMAN ALARM
System Condition System Power Patrolman Alarm

EXTENSION ALARM Off


24 25 26 23

Normal Normal

System Power

Normal

201 E/R VENT VENTILATION

202 COMPRESSED AIR SYSTEM

203 REF & AIR COND

204 CONT OVERVIEW

205

GMA5 STEERING GEAR & MISCELLANEOUS

4-2-63

S2229/30

Motor List - Main Turbine


MAIN TURBINE DESCRIPTION
1 2 42 GSP1 EMCY Stop PWR Source Fail 43 GSP2 EMCY Stop PWR Source Fail 44 FWD DB EMCY Stop PWR Source Fail

MOTOR STATUS
D R 3
5 6 4

RUN HOUR (h)


37

STATOR COIL(C)

MAIN GRAPHIC

No1 Cont Oil PP

Lock

19

Stop

24 20

PAL PAL

ACO Mode Set ACO


26

ACO Status ACO-Off


27

0
216 GM16

No2 Cont Oil PP


9

D R 7

Lock
Stop

25

38

Turning Gear
11 12

10

Lock
Stop

21

39

0 ASS Mode Set No1 PP ASS ASS Mode Set No2 PP ASS
35 28

No1 Aux LO PP

D R
13

14

Lock
Stop

22

ASS Status No1 ASS-Off ASS Status No2 ASS-Off


29

30

Shaft Rev 0

ACO Status 32

40

ACO-Off ACO

0
GM12 41

ACO Mode Set 33

217

15 16

No2 Aux LO PP

D R17

18

Lock
Stop

23

36

LO P Low
31

Off

34

PAL

202 MOTOR LIST2 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

201

GMM1 MOTOR LIST(1/15)

4-2-64

S2229/30

Motor List - Electrical Generator


ELECTRICAL DESCRIPTION
1

MOTOR STATUS
D R
5 2 4 3

RUN HOUR (h) ASS Status 22 ASS-Off ASS Senser Status 23 Off ASS Senser Status 26 Off ASS No1 D/G Run
29 33

STATOR COIL(C)

MAIN GRAPHIC
216 GM25

No1 T/G LO Prim PP No2 T/G LO Prim PP


9

Lock

17

Stop
18

ASS Mode Set 21 ASS ASS Mode Set 24 ASS ASS Mode Set 27 ASS ASS Mode Set 30 ASS

0
34

D R D R

6 7

Lock
Stop

ASS Status 25 ASS-Off ASS Status 28 ASS-Off ASS Status 31 ASS-Off

217 GM26

10 11

No1 D/G LO Prim PP


13

12

Lock
Stop

19

35

218 GM27

0
36

No2 D/G LO Prim PP

D R

14 15

16

Lock
Stop

20

No2 D/G Run


32

219 GM28

201 MOTOR LIST1 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

202

GMM2 MOTOR LIST(2/15)

4-2-65

S2229/30

Motor List - Boiler & Steam


BOILER DESCRIPTION
1

MOTOR STATUS
D R
6 2 3 7 8 12 4

RUN HOUR (h)


25

STATOR COIL(C)

U
29

V
30

W
31

MAIN GRAPHIC

No1 FD Fan

Lock
5

19

Stop

A
9

No2 FD Fan
11

D R D R

Lock
10

Stop

20

26

32

33

34

A
14

0
27

216 GM31

No1 BLR F/E Seal Air Fan


15

Lock
Stop

21

13 16 17

ACO Mode Set ACO


22

23

ACO Status ACO-Off


24

0
28

No2 BLR F/E Seal Air Fan

D R

18

Lock
Stop

STEAM DESCRIPTION
35

MOTOR STATUS
D R
36 37 38

RUN HOUR (h)


40

STATOR COIL(C)

MAIN GRAPHIC
217 GM45

Gland Exh Fan

Lock

39

Stop

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

203

GMM3 MOTOR LIST(3/15)

4-2-66

S2229/30

Motor List - Feed & Condensate


FEED SYSTEM 1 DESCRIPTION
1

MOTOR STATUS
39

RUN HOUR (h)

STATOR COIL(C)

MAIN GRAPHIC

No1 MFDWPT
2

Stop

29

Ready
44

ACO

Auto STBY

68 40 41 45 46 70 216 GM52 43

STBY Select
42

0
69

Press
Mode Change

ACO

Auto STBY

No2 MFDWPT
3

Stop
4 5

Ready
30 31

Cold Start FDW PP


7

D R

Lock
Stop

0
71

No1 MFDWPT Prim LO PP


8

Stop

32

0
72

No2 MFDWPT Prim LO PP


9

Stop
10 11

33 34

0 ASS Mode Set No1 PP ASS


47

No1 M/C Conds PP


13

D R D R

12

Lock
Stop

ASS Status No1 ASS-Off ASS Status No2 ASS-Off ASS Status
57 48

Cond LV Level High


49

ACO Status 51

73

ACO-Off ACO

0
74

ACO Mode Set 52 53 54

14 15

16

Lock
Stop

35

ASS Mode Set 55 No2 PP ASS ASS Mode Set No1 PP ASS

56

No2 M/C Conds PP


17

Level Low
50

PAL PAL
61

0
75

No1 Drain PP
21

D R D R

18 19

20

Lock
Stop

36

No1 ASS-Off ASS Status No2 ASS-Off

58

Drain TK Level Level High


59

ACO Status ACO-Off ACO Mode Set 62 ACO


63 64 65

217 GM53

22

24

Lock
Stop

37

ASS Mode Set No2 PP ASS

78

79

76

No2 Drain PP
25

23 26 27

0
77

No3 Drain PP

D R

28

Lock
Stop

38

ASS Mode Set No3 PP ASS

66

ASS Status 67 No3 ASS-Off

Level Low
60

No1 PAL No2 PAL No3 PAL

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

204

GMM4 MOTOR LIST(4/15)

4-2-67

S2229/30

Motor List - Vacuum Pump


FEED SYSTEM 2 DESCRIPTION
1

MOTOR STATUS
D R
5 2 3 4

RUN HOUR (h)


15

STATOR COIL(C)

MAIN GRAPHIC
216 GM14

No1 Main Conds Vac PP No2 Main Conds Vac PP

Lock

Stop

11

PAL

ACO Mode Set ACO

0 ACO Status ACO-Off


14 16

13

D R

6 7

Lock
Stop

10 12

PAL

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

205

GMM5 MOTOR LIST(5/15)

4-2-68

S2229/30

Motor List - Cooling Water System


WATER SYSTEM 1 DESCRIPTION
1

MOTOR STATUS MOTOR STATUS


D R
5 2 3 4

RUN HOUR (h)


63

STATOR COIL(C)

MAIN GRAPHIC
216 GM61

Main Circ PP

Lock

Stop

37

ACO Mode Set ACO


47

ACO Status ACO-Off


48

0
64

Aux Circ PP
9

D R D R

6 7

Lock
Stop
38 39

0
65 49

10 11

12

No1 Main CSW PP


13

Lock
Stop

PAL

ACO Mode Set ACO

51

ACO Status ACO-Off


52

0
66 217 GM62

No2 Main CSW PP

D R

14 15

16

Lock
Stop

40 50

PAL
Normal Auto
54 53

41

67

Chlorinator
17

Stop
18 19 42

0
68

No1 CCS CFW PP


21

D R D R

20

Lock
Stop

55

PAL

ACO Mode Set ACO

0 ACO Status ACO-Off


58 69

57

22 23

24

Lock
Stop

43 56 44

No2 CCS CFW PP


25

PAL PAL

0
70 218 GM64

No1 Cargo Mach CFW Boost PP


29

D R D R

26 27

28

Lock
Stop

59

ACO Mode Set ACO

0 ACO Status ACO-Off


62 71

61

30 31

No2 Cargo Mach CFW Boost PP


33

32

Lock
Stop

45 60

PAL

0
72

W/H & CCR Unit CLR CFW Boost PP

D R

34 35

36

Lock
Stop

46

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

206

GMM6 MOTOR LIST(6/15)

4-2-69

S2229/30

Motor List - Cooling Water System


WATER SYSTEM 2 DESCRIPTION
1

MOTOR STATUS
D R
5 2 3 4

RUN HOUR (h)


61

STATOR COIL(C)

MAIN GRAPHIC

No1 D/G CFW PP

Lock

Stop

41

0
62

No2 D/G CFW PP


9

D R D R

6 7

Lock
Stop

42

0 ASS Mode Set ASS Status


51

216 GM65

10 11

12

No1 D/G CSW PP


13

Lock
Stop

43

No1 PP ASS ASS Mode Set

No1 ASS-Off ASS Status

52

D/G Run No1


53

ACO Status 55

63

ACO-Off ACO

0
64

ACO Mode Set 56 57 58

No2 D/G CSW PP


17

D R D R

14 15

16

Lock
Stop

44

No2 PP ASS

59

60

No2 ASS-Off

No2
54

PAL PAL

0
65

18. 19

No1 Dist Plant Circ W PP


21

20

Lock
Stop

45

0
66

No2 Dist Plant Circ W PP


25

D R D R

22 23

24

Lock
Stop

46

0
67

No1 Dist Plant Distil PP


29

26 27

28

Lock
Stop

47

0
GM66 68

217

No2 Dist Plant Distil PP


33

D R D R

30 31

32

Lock
Stop

48

0
69

34 35

No1 Dist Plant CSW PP


37

36

Lock
Stop

49

0
70

No2 Dist Plant CSW PP

D R

38 39

40

Lock
Stop

50

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

207

GMM7 MOTOR LIST(7/15)

4-2-70

Motor List - Fresh Water System


WATER SYSTEM 3 DESCRIPTION
1

MOTOR STATUS
D R
5 2 3 4

RUN HOUR (h) ASS Status No1 ASS-Off ASS Status No2 ASS-Off ASS Status No1 ASS-Off ASS Status 1ST Auto Senser
33 43

STATOR COIL(C)

MAIN GRAPHIC

Lock
Stop

No1 FW PP

24

ASS Mode Set No1 PP ASS ASS Mode Set No2 PP ASS

31

32

Off

No2 FW PP
9

D R

6 7

Lock
Stop

25

35

36

2ND Auto Senser


34

44

Off

No1 Drink W PP
13

D R D R

10 11

12

Lock
Stop

26

ASS Mode Set No1 PP ASS

37

38

1ST Auto Senser


39

45

Off

0
46 216 GM67

14 15

16

No2 Drink W PP
17

Lock
Stop

27

ASS Mode Set No2 PP ASS


41

42

2ND Auto Senser


40

No2 ASS-Off

Off

18

Lock
19

Fire Fight FW PP
20

Stop

28

47

A
21

No1 Hot W Circ PP


22 23

Lock

Stop

29

48

0
49

Lock

No2 Hot W Circ PP

Stop

30

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

208

GMM8 MOTOR LIST(8/15)

4-2-71

S2229/30

Motor List - Fire & Bilge System


WATER SYSTEM 4 DESCRIPTION
1 2

MOTOR STATUS
Lock
Stop
3 4 5 22

RUN HOUR (h)


31

STATOR COIL(C)

MAIN GRAPHIC

Bilge Sep Serv PP D R


8 6 7 9

0
23

E/R Bilge PP

Lock Long Run Lock

Stop

ASS Mode Set 29 ASS

32

ASS Status ASS-Off


30

0
33 216 GM68

24

Waste Oil Trans PP


10

Stop
11 12 15 16

0
34

Fire & Bilge PP


14

D R D R

13

Lock
Stop

25

0
26 35

17

Bilge & GS PP
18

Lock
Stop

0
27 36

19

Fire Line Press PP


20 21

Lock
Stop

0
37 GM69 38 39 40

217

Lock
Stop

28

EMCY Fire PP

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

209

GMM9 MOTOR LIST(9/15)

4-2-72

S2229/30

Motor List - F.O. System


FO SYSTEM DESCRIPTION
1

MOTOR STATUS
D R
5 2 3 4

RUN HOUR (h)


29

STATOR COIL(C)

MAIN GRAPHIC
216 GM71

Lock
Stop

17

No1 FO Burn PP

21

PAL

ACO Mode Set ACO


23

0 ACO Status ACO-Off


24 30

No2 FO Burn PP
9

D R

6 7

Lock
Stop

18 22

PAL PAL
31

No3 FO Burn PP
13

D R D R

10 11

12

Lock
Stop

19

25

ACO Mode Set ACO


27

0 ACO Status ACO-Off


28 32 GM72 217

14 15

16

No4 FO Burn PP

Lock
Stop

20 26

PAL

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

210

GMMA MOTOR LIST(10/15)

4-2-73

S2229/30

Motor List - F.O, D.O. & L.O. System


FO,DO & LO SYSTEM DESCRIPTION
1

MOTOR STATUS
D R
5 2 3 4

RUN HOUR (h)


39

STATOR COIL(C)

MAIN GRAPHIC

Lock
Stop

25

FWD FO Trans PP

0
26

HFO Trans PP
9

D R

6 7

Lock
Stop

ASS Mode Set 33 ASS

ASS Status ASS-Off


34

40

216 GM81

0
41

10

Lock
Stop

27

DO Trans PP
11 12

Lock
Stop

28

LO Purif
13 14

Normal

35

42

0
43 217 GM82

LO Purif Feed PP
15 16

Lock
Stop

29

LO Trans PP
17

Lock
Stop

30

44

0
31 45

No1 S/T LO PP
21

D R D R

18 19 22 23

20

Lock
Stop

ACO Mode Set


36

ACO Status ACO-Off


38

0
GM83 46

24

Lock
Stop

FAL

ACO

37

218

32

No2 S/T LO PP

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

211

GMMB MOTOR LIST(11/15)

4-2-74

S2229/30

Motor List - Vent Fans


MISCELLANEOUS 1 DESCRIPTION
1

MOTOR STATUS
D R
5 2 3 4

RUN HOUR (h)


53

STATOR COIL(C)

MAIN GRAPHIC

No1 E/R Supply Fan (Rev) No2 E/R Supply Fan


9

Lock

41

Stop

0
42 54

D R D R

6 7

Lock
Stop

0
43

10 11

12

No3 E/R Supply Fan


13

Lock
Stop

55

0
44 56

216 GMA1

No4 E/R Supply Fan


17

D R D R

14 15

16

Lock
Stop

0
45 57

18 19

20

No1 E/R Exhaust Fan


21

Lock
Stop

0
58

No2 E/R Exhaust Fan


25

D R

22 23

24

Lock
Stop

46

0
47 59

No1 Vent Duct Exhaust Fan


29

D R D R

26 27

28

Lock

Stop

ACO Mode Set


48

0 ACO Status ACO-Off


52 60

217 GM31

30 31

No2 Vent Duct Exhaust Fan


33

32

Lock
Stop

ACO

51

0
49 61

No1 FO Pump RM Exhaust Fan


37

D R D R

34 35

36

Lock
Stop

0
50 62

218 GMA2

38 39

No2 FO Pump RM Exhaust Fan

40

Lock
Stop

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST13

213 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

212

GMMC MOTOR LIST(12/15)

4-2-75

S2229/30

Motor List - Compressor & Vent Fan


MISCELLANEOUS 2 DESCRIPTION
1

MOTOR STATUS
D R
6 2 3 4 5

RUN HOUR (h) ASS Status No1 ASS-Off ASS Status No2 ASS-Off ASS Status ASS-Off ASS Status ASS-Off ASS Status ASS-Off
57 54 51 45

STATOR COIL(C)

MAIN GRAPHIC

No1 Air Comp

Lock Fail Lock Fail Lock Fail Lock

Stop

34

ASS Mode Set No1 CP ASS

44

ASS Sensor Status Cont Receiv 1ST Auto


46

59

0
60

No2 Air Comp


11

D R D R

7 8

Off Off 0
216 GMA3

9 10

Stop

35

ASS Mode Set 48 No2 CP ASS ASS Mode Set 50 ASS ASS Mode Set 53 ASS ASS Mode Set 56 ASS

49

2ND Auto
47

12 13

14 15

No3 Air Comp


16

Stop

36

ASS Sensor Status GS Receiv


52

61

0
62

Off

No1 D/G Start Air Comp


20

D R D R

17 18

19

ASS Sensor Status


55

Stop

37

Off

0
63

21 22

No2 D/G Start Air Comp FWD EL RM Supply Fan FWD PP RM Exhaust Fan FWD Store Exhaust Fan Work Shop Exhaust Fan
32 24

23

Lock
Stop

38

ASS Sensor Status


58

Off

0
64

25

Lock
Stop

39

0
65

26

27

Lock
Stop

40

0
217 GMA2

28

29

Lock
Stop

41

66

30

67

Stop

42

Waste Oil SETT TK Exhaust Fan

33

Lock

Stop

43

68

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST14

214 MOTOR LIST15

215 CONT OVERVIEW

213

GMMD MOTOR LIST(13/15)

4-2-76

S2229/30

Motor List - Room Fans


MISCELLANEOUS 3 DESCRIPTION
1

MOTOR STATUS
D R
5 2 3 6 7 4

RUN HOUR (h)


17

STATOR COIL(C)

MAIN GRAPHIC

No1 FO Heat RM Exhaust Fan No2 FO Heat RM Exhaust Fan


9

Lock
Stop

13

0
14

D R

Lock
Stop

18

0
216 GMA2

Steering Gear RM Supply Fan


11

10

Lock

Stop

15

19

0
20

EMCY Fire PP RM Supply Fan

12

Lock

Stop

16

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST15

215 CONT OVERVIEW

214

GMME MOTOR LIST(14/15)

4-2-77

S2229/30

Motor List - Ref. & Air conditioner


MISCELLANEOUS 4 DESCRIPTION
1

MOTOR STATUS
2

RUN HOUR (h)


25

STATOR COIL(C)

MAIN GRAPHIC
216 GMA4

No1 Prov Ref Compressor


4

Lock
3

Stop

13

A
5

No2 Prov Ref Compressor


7

Lock
6

Stop

14

0
19 20 21

26

A
8

No1 Steering Gear Motor


9

Lock
Stop

15

No2 Steering Gear Motor


11

10

Lock
Stop

16

22 23 24

Over Load No Volt Phase Fail Over Load No Volt Phase Fail

27 217 GMA5

0 28

No1 Air Conditioner


12

Stop

17

0 29
GMA4

218

No2 Air Conditioner

Stop

18

0 30

201 MOTOR LIST1 MOTOR LIST2

202 MOTOR LIST3

203 MOTOR LIST4

204 MOTOR LIST5

205 MOTOR LIST6

206 MOTOR LIST7

207 MOTOR LIST8

208 MOTOR LIST9

209 MOTOR LIST10

210 MOTOR LIST11

211 MOTOR LIST12

212 MOTOR LIST13

213 MOTOR LIST14

214 CONT OVERVIEW

215

GMMF MOTOR LIST(15/15)

4-2-78

S2229/30

Fuel Gas Compressor (Reference)


LO NO2 F/G IGV Seal N2 Press L LO Sump TK Temp L LO Sump TK Temp H LO Sump TK Level L BHD Seal LO Press L VG942
BLR GAS FLOW CONT VV

In DP R No2 F/G

0 kPa 0 kPa 0 C 0 C 0 C 0 m 0 C 0 C

NO2 F/G COMP


Common Trip Manual Trip Disch Gas Temp HH Rotor Vib HH Bearing Temp HH BHD Seal LO Press LL Seal N2 Press LL BHD Seal Temp HH LO In Press LL ESD / TK Protect Common Alarm

0.0 %
Start POS

0 C 0 C 0.0 %
VG943 Surge VV Full Open

0 kPa

0 A Remote No2 Aux LO PP


D

In D BHD BRG

Reset

Not Ready

Not Ready

0.0 % 0.0 %
BLR Gas Flow
FUEL GAS HEATER

0 C 0 kPa
CCGO1 VG941 Mist Separator

Vib

VPR HDR Press LAH

0 x10kg

0.0 %
VG952

0.0

GAS BURN EMCY STOP

kPa

VG931 VG934 VG951 VG950

Stop
EMCY STOP

(GC24)

0.0 kPa 0 C
Forcing VPR

V/R COMP

VG933 VG903

(GC21)

Full Open Surge VV

0 kPa 0 C
Not Ready Not Ready

0.0 % 0 C

Master Gas VV Trip

Vib BRG

0 m 0 C 0 C 0 C 0 kPa 0 kPa
LO

BHD Seal LO Press L LO Sump TK Level L LO Sump TK Temp H LO Sump TK Temp L Seal N2 Press L

No1 F/G VG932

0 C 0 C

0 C

0 kPa
Start POS C R

D BHD No1 Aux LO PP In DP In

0 A Remote

0.0 %

NO1 F/G IGV

Common Alarm ESD / TK Protect LO In Press LL BHD Seal Temp HH Seal N2 Press LL BHD Seal LO Press LL Bearing Temp HH Rotor Vib HH Disch Gas Temp HH Manual Trip Common Trip

Reset

NO1 F/G COMP


CONT OVERVIEW

V/R COMP

VAPORIZER

GAS HEATER

CARGO MACH ROOM

BOG CONTROL (1/2)

BOG CONTROL (2/2)

ESD Act

GC22 FUEL GAS COMPRESSSOR

4-2-13

S2229/30

PCS Status (Reference)

PCS STATUS A-CPU PCS CPU STATUS UNIT NETWORK P-LINE Q-LINE P-LINE SEND Q-LINE SEND COM CONTROL P-LINE RECEIVE Q-LINE RECEIVE SOFTWARE OPERATION PROGRAM DATA LOGIC DATA BACKUP MEMORY STATUS PARAMETER SAVE PARAMETER LOAD

MCB12 PCSM2 B-CPU


PCSM2BSER PCSM2BETHP PCSM2BETHQ PCSM2BSNDP PCSM2BSNDQ PCSM2BRCVP PCSM2BRCVQ PCSM2BSW PCSM2BLPDT PCSM2BCF1 PCSM2BCF2 PCSM2BCF3 PCSM2BCF4 PCSM2BTRER PCSM2BTRSD PCSM2BTRRV PCSM2LBSB PCSM2ASER PCSM2AETHP PCSM2AETHQ PCSM2ASNDP PCSM2ASNDQ PCSM2ARCVP PCSM2ARCVQ PCSM2ASW PCSM2ALPDT PCSM2ACF1 PCSM2ACF2 PCSM2ACF3 PCSM2ACF4 PCSM2ATRER PCSM2ATRSD PCSM2ATRRV PCSM2LBSA

MCB12 IOS & I/O STATUS IOS STATUS IOC-A STATUS IOC-B STATUS NO1 NO2 NO3 NO4 NO5 NO6 NO7 NO8 NO9 NO10 NO11 NO12 NO13 NO14
AI(4-20) AI(4-20) AI(RTD-N) AI(RTD-N) AI(RTD-W) AO(4-20) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DO(RY) DO(RY)

PCSM2

IOSM21
IOSM21SER IOSM21ASER IOSM21BSER AI(4-20) AI(4-20) AI(4-20) AI(RTD-N) AI(RTD-W) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DO(RY) DO(RY)

IOSM22
IOSM22SER IOSM22ASER IOSM22BSER DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DO(RY) DO(RY) DO(RY) DO(RY) DO(RY)

IOSM23
IOSM23SER IOSM23ASER IOSM23BSER DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DO(RY) DO(RY) DO(RY) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF) DI(ON/OFF)

I/O SLOT

STATUS CPU TRACKING SEND STATUS RECEIVE STATUS LBS NETWORK CONTROL

GMS4 PCSM2/IOSM21/IOSM22/IOSM23

2-8-3-4

S2229/30

PART 9: EMERGENCY PROCEDURES

9.1 9.2 9.3 9.4 9.5 9.6 9.3a

Flooding in the Engine Room Steaming on One Boiler Solo Running of the Main Turbine Steaming with One Forced Draft Fan Emergency Steering Fire in the Engine Room Emergency Operation of Main Turbines

Illustrations

9.1 Flooding in the Engine Room


Flooding in the engine room may occur due to a defect in the hull structure, possibly due to grounding, berthing or collision damage, or, more likely, due to a defect in the sea water pipeline system. Pumps Available for Bilge Pumping Duties Engine Room Bilge Pump (Reciprocating) Can take suction from : Bilge main

Measures to Prevent or Alleviate Flooding Maintain pipelines externally, tighten slack supports and replace broken U bolts on pipe brackets to minimize fretting in way of supports. Operate all ships side valves regularly, so that they can be operated easily when required. Valves such as fire pump suction valves, which are normally open, should be closed and reopened regularly to prevent a build up of marine growth. Before opening sea water filters for cleaning, make sure the shut off valves are tight by opening the vent in the cover. In any case, break the cover joint before removing all cover bolts. The same applies when opening coolers and pipelines anywhere in the system. Care must always be taken when removing covers or opening any part of the sea water pipe system as valves which are indicated as being closed may not be fully closed. Personnel should be familiar with the position of bilge suctions and the pumps that can be utilized for bilge pumping duties. They should also be familiar with the position of main sea suction and overboard valves and know which main suction is currently in use. The emergency bilge suction valve should be operated on a regular basis. Double bottom sounding pipe cocks and caps should be secured after use.

Fire, Bilge & General Service Pump (Centrifugal) Can take suction from : Bilge main Bilge wells Main condenser

No.2 Cooling Sea Water Pump (Centrifugal) No.2 Cooling SW pump is provided with a direct bilge suction via valve 099VPH with the operating handwheel 450mm above the lower platform.

Bilge Suction Strainers Bilge suction strainers should be checked and cleaned whenever the opportunity arises. Frequent checking and cleaning will reduce the risk of a strainer becoming blocked and difficult to clear due to subsequent flooding.

9.2 Steaming on One Boiler


Description If a boiler is shut down due to a failure in any of its systems, then the main turbines can still be operated but at a much reduced power. It may not be possible to use all the cargo normal boil-off gas (BOG) in the remaining boiler and facilities for incineration will be limited by the maximum steaming rate of the online boiler. After a period of time under these conditions it might be necessary to vent the excess BOG gas to maintain tank pressures within the designated limits. Normal evaporation for each boiler is approximately 47,200 kg/h for 100% MCR. Individual circumstances will dictate where the steam produced is used, and selected non-essential services should be shut down as required, depending upon prevailing circumstances. It may be necessary to shut down the turbine generator and use the diesel generator. Shut down non-essential heating and evaporators if conditions permit and reduce the electrical loading where possible. The steam consumption of the main turbines at MCR includes bleed steam which may well have to be isolated due to reduced steaming conditions. Basically, the circumstances encountered in each particular case will dictate the steam usage with priority being given to essential services such as gland steam, feed pump, turbine generator and boil-off / warm-up heaters. In the event of a boiler shut down, planned or otherwise, the bridge must be informed immediately. The main turbine must be slowed down sufficiently to enable the remaining boiler to be maintained within its operating parameters. Control of the boiler coming out of service will be generally under manual operation and particular care must be taken to ensure the remaining boiler controls and associated systems function to compensate accordingly. The steaming rate of the remaining boiler must be maintained below the design maximum. During transition periods vigilance is necessary to ensure the safe operation of the plant, particularly with reference to water level control and firing rate. When conditions have settled down, the faulty boiler can be shut down and isolated. Depending on the type of fault and when the correct temperature is reached, the boiler should then be either filled with water or emptied and dried. As conditions stabilize, if required, a progressive increase of steam supply to the main turbine may be possible until the maximum steaming rate is achieved. When a Boiler has to be Shut Down a) b) Inform the bridge of the problem and reduce the engine speed to a rate which maintains steerage way but does not overload the remaining boiler. Change over the control system to manual on the boiler to be shut down and decrease its steaming rate, ensuring that the remaining boiler is on automatic and takes up the load. When the conditions have stabilized and the faulty boiler is on its minimum firing rate, shut it down and isolate it completely, including the air heater. Closely monitor the supply of the boil-off gas and the condition of the remaining boiler. Shut down as much steam using equipment or systems as operationally possible. Reduce the electrical loading. Keep the forced draft fan running on the faulty boiler to cool it down or allow it to cool down naturally. Bear in mind the possibility of economizer fires. Either fill the boiler to the top of the gauge glass or empty it out when cool. When conditions have stabilized increase the main turbine steam supply as required, loading the boiler up to but not exceeding the maximum firing rate.
3

Operating Procedures Boiler Trips a) Inform the bridge of the problem and reduce the engine speed to a rate which maintains steerage way but does not overload the remaining boiler. This should be done swiftly, but not so swiftly that the boiler pressure rises in an uncontrolled manner and lifts the safety valves. Isolate the faulty boiler completely including the air heater.
Fuel Flow (kg/h) 4,500 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500 0 0 10 20 30 Evaporation (ton/hr) 40 50 60 Evaporation Vs Fuel Flow / Pressure

F.O.

b) c) d) e)

Keep a check on the gas boil-off situation as well as the condition of the remaining boiler. Shut down as much steam using equipment or systems as possible. Reduce the electrical loading. Reduce the cargo compressor load and open the mast vents if necessary.

F.G.

(Note : This will not be possible in port due to local restrictions.) f) Keep the forced draft fan running on the faulty boiler to cool it down, or allow it to cool down naturally. Bear in mind the possibility of economizer fires. Either fill the boiler to the top of the gauge glass or empty it out when cool. When conditions have stabilized, increase the engine speed as required up to the maximum firing rate on the remaining boiler.

g)

Evaporation Vs Fuel Pressure


60

2.5

F.G.

50

c) d) e) f)

F.O. Pressure (MPa)

1.5

30

F.O.
1 20

0.5

10

0 0 10 20 30 40 50 60 70 Evaporation (ton/hr)

g)

F.G. Pressure (kPa)

40

9.3 Solo Running of the Main Turbine


If failure occurs in the HP or LP turbines or associated gearing, the pipelines can be altered to allow either turbine to be operated singly at reduced power. Some additional piping will have to be added in and some will have to be blanked off. When the damage has been to the LP turbine and the ship is to be operated on the HP turbine only, then no astern power will be available. Desuperheated steam only is used for the emergency operation. It is supplied via portable pipe work fitted between valve (034VPA) and the main turbine superheated steam inlet Operating with the Low Pressure Turbine Only a) To avoid turning the HP turbine, disconnect the coupling between the HP turbine and the first pinion by removing the reamer bolts from the flange of the claw coupling. Remove the crossover pipe and expansion joint at HP exhaust. Disconnect gland steam leak-off and pressure gauge pipe works on the ahead stop valve Disconnect and Turn the ahead stop valve and fit the support (fixing device) G on the ahead nozzle valve steam inlet flange. Connect gland steam leak-off and pressure gauge pipes supplied for emergency use on the ahead stop valve Fit a blank flange D on HP turbine exhaust Install emergency operating pipes A and B with an orifice plate C and diffuser E between the ahead stop valve and LP turbine. Ahead running can be carried out by opening the emergency steaming desuperheated steam stop valve 034VPA on the 3rd deck level and controlling the turbine speed directly from the ahead stop valve. Astern running will be carried out by opening the astern manoeuvring valve at the engine side. Should a failure occur, it would be most likely that the ship would be at sea. The turbines will therefore be hot and will need to be cooled for some time before any work can be carried out. Unless internal mechanical damage prevents it, the main turbine should be cooled down with the turning gear in use prior to opening up for internal inspection work. If it is impossible to cool the engine using the turning gear, care must be taken when starting the usable turbine. It should be run at low revolutions for several hours in order to straighten out any bowing of the rotor which may have occurred during cool down whilst stationary. If vibrations occur when increasing speed, decrease the speed until the vibrations stop and allow the temperature of the rotor to stabilize. Speed can then be increased slowly to the maximum permitted value.

b) c) d) e) f) g) h)

Failure of Bridge/Remote Control If a failure occurs with the bridge control, central control room, machinery control room control or the hydraulic servomotor system for the manoeuvring valves, then these can be put into manual operation and controlled locally.
NOTE : The following is offered for general information only. Before

emergency operation is contemplated, the manufacturer's operating manual is to be closely studied.

Operating with the High Pressure Turbine Only


See 9.3aEmergency Operation of Main Turbine

a)

To avoid turning the LP turbine, disconnect the coupling between the LP turbine and the first pinion by removing the reamer bolts from the flange of the claw coupling (flexible coupling). Remove the crossover pipe and expansion joint at HP exhaust. Fit blank flange B on LP steam inlet instead. Remove the blank flange D on emergency exhaust inlet to the LP turbine exhaust casing. Connect the HP turbine exhaust directly to the LP turbine exhaust casing using the emergency piping A. Insert an orifice C between the HP exhaust and the expansion joint. Manually close the astern guard valve.

CAUTION
1. The steam chest pressure of the LP turbine must not exceed 0.3MPa. 2. All pipe works for the turbine warm-up system provided for HP turbine must be removed and proper blanks are to be inserted in the LP turbine solo operation. Maximum output is limited due to the following : To protect the reduction gearing teeth from overload Turbine capacity Heat balance flow The following conditions will apply as limit powerduring emergency running. Steam conditions : Output : Rpm : Remarks : Maximum power in HP turbine solo operation is estimated approx. 7,750 kW x 56 rpm based on following steam conditions:. Desuperheated steam : 4.7MPa x 336 x approx. 76 ton/h at the turbine inlet. HP Turbine in Use 3.8 MPa at 510C 8,090kW 56 LP Turbine in Use 0.30 MPa at 265C 8,090kW 56

b) c) d) e) f) g)

CAUTION
The astern turbine cannot be used so an astern movement is not possible. h) Manually open the ahead stop valve to operate the turbine.

(Note : Turn the LP turbine rotor 180 once every 6 hours using the flexible coupling flange to prevent any deflection. Use the water spray in the astern turbine exhaust chamber to prevent any overheating of the exhaust casing.)

9.3a Emergency Opration of Main Turbine

H. P. TURBINE SOLO

L. P. TURBINE SOLO

L. P. TURBINE

L. P. TURBINE

B
PUT ON BLANK FLANGE PUT ON BEND PIECE

DIFFUSER

ORIFICE

A C
TAKE OUT BLANK FLANGE

TAKE OUT CROSSUNDER PIPE & EXPANSION JOINT AND PUT IN BLANK FLANGE

ORIFICE

D B
PUT ON EMERGENCY PORTABLE PIPES 100

H. P. TURBINE

H. P. TURBINE G
NOZZLE VALVE

SUPPORT NOZZLE VALVE

SUPERHEATED STEAM LINE


150

200

SUPERHEATED STEAM LINE


150

200

AHEAD STOP VALVE TURN THE VALVE AND FIT SUPPORT

AHEAD STOP VALVE

PUT ON PORTABLE PIPE

PUT ON PORTABLE PIPE

034VPA

034VPA

150

DESUPERHEAD STEAM LINE

DESUPERHEAD STEAM LINE

150

9.4 Steaming with One Forced Draft Fan


Forced Draft Fans Maker : Type : Air flow : Pressure : Speed : Power : Osaka Blower Mfg. Co., Ltd. Horizontal Centrifugal 950/1,110/1,900m3/min 500/650/500mmAq 900 / 1,200 / 1,200 rpm 130/300/300kW Procedure for One Fan - Two Boilers Operation Assuming the failure of the starboard (No.1) FD fan, the starboard boiler trips.
See 4.3.2dCombustion Air, Seal Air and Fuel Gas System.

a) b) c) d) e)

Close the damper A on the starboard (No.1) FD fan outlet. Open the crossover duct damper C leading from the port FD fan to the starboard boiler. Put (No.2) F.D. fan to high speed mode. The fuel oil emergency shut-off valve 222B for the shutting down boiler is now ready to open. Switch ACC from Auto to Manual mode. Fuel oil and F.D .fan Auto / Manual switches are to be put in Manual mode for both boilers. Open the air slide of the base burner of the shut-down boiler, and purge for at least 5 minutes with the burner wind box air pressure at about 20 mm Aq. Pay attention to air flow adjustment so that the boiler in normal is not short of air. Fully open the superheater starting valve 74B of shutting boiler. Open the fuel oil emergency shut-off valve 222B. Relight the shutting boiler. After lighting up, adjust oil pressure to about 0.4 MPa and raise steam pressure at the same combustion rate until the pressure reaches the same pressure as the other boiler. When the boiler pressure has reached the same pressure as the other boiler, start two-boiler operation and close the superheater starting valve. Balance the load between the two boilers. Make the number of burners and burner oil pressure the same for both boilers and adjust the air damper to make air distribution to both boilers the same. Put the fuel Auto / Manual switch in Auto position for both boilers. Switching must be made after boiler load has become steady. Keep the F.D. fan Auto / Manual switch in Manual position. After boiler load has been steady and air distribution to both boilers has been stabilized, adjust air flow manually to match the boiler load by manual loader for the F.D. fan. Increase the main turbine load gradually.

Two fans are situated on the upper deck level and are controlled by adjustable vanes, automatically positioned by the combustion control system. Each fan is arranged to supply their respective boilers. If either the port or starboard FD fans fail, the boiler on the same ship side is shut down by the fuel oil emergency shut-off equipment. On the other hand, the boiler in normal receives ACC signals so to take over the load of the shutting down boiler. Therefore, whenever the fan failure alarm occurs, the main turbine load should be lowered immediately. (In normal, the main turbine will be slowed down automatically.) If the steaming by two boilers with one FD fan is necessary as the result of investigation of the cause, the operation will be performed in accordance with the following procedure.

f) g) h)

i) j)

k) l)

m)

9.5 Emergency Steering


If failure occurs in the remote operating system from the wheelhouse, the steering can be operated from the steering gear room. Should there be a failure of the bridge steering system, the steering gear can be operated locally from within the steering gear compartment. Both the steering gear pumps must be switched to the LOCAL control position on the starter panels. (Note : Only one hydraulic pump should be operated when on local emergency control.) Steering instructions will be sent to the steering gear compartment through the sound powered telephone and the steering gear controlled locally using the manual controls on the manoeuvring solenoid valves. The emergency controls are actuated by pressing the pushbutton at the end of the solenoid valves, so directing oil from the pump to the rudder actuator. Pressing the solenoid on the other side of the valve will reverse the direction of the rudder. A read out of the rudder angle can be obtained by viewing the mechanical rudder angle indicator bolted to the top of the actuator. Procedure for the Steering Gear Emergency Operation on Loss of Remote Bridge Control a) On loss of steering gear control from the bridge, establish communication with the bridge via the telephone system. A telephone is located on the steering gear compartment platform.

Indication of the rudder angle and a compass repeater are provided for manual control of the steering gear. b) c) Stop the faulty pump. At the control panel for the other steering gear turn the Remote / Local switch to the LOCAL CONTROL position. When operating the steering gear from the local position Follow the instructions from the bridge. Operate the steering gear in response to requests from the bridge by operating the solenoid valves of the running pump using the Port / Starboard pushbuttons.

d) e)

Description The steering gear, in accordance with IMO regulations the pumps, hydraulic power circuits and rams can operate as two isolated systems. The steering gear is fitted with an automatic isolation system. This system is used to divide the hydraulic power circuits in the event of a hydraulic oil loss from the oil tanks. In accordance with IMO regulations the hydraulic pumps used in the steering gear are supplied with power from two independent sources. In the event of power failure from the main switchboard, one pump can be supplied from the emergency switchboard.

9.6 Fire in the Engine Room


The risk of a fire outbreak can be minimized by ensuring that all personnel understand the risks and by ensuring that the engine room is maintained in a clean condition and that any oil leaks are dealt with immediately. Oily rags and waste must be disposed of in a safe manner using metal containers. Empty plastic containers must never be left around the engine room spaces, and they should never be used as waste bins for oily rags and similar combustible material. There must always be an awareness of potential fire ignition sources such as leaking oil pipes or insecure electrical contacts. High temperature points such as exhaust manifolds or boiler furnace casings should always be lagged effectively and lagging must always be repaired or replaced when damaged or after overhaul. Combustible materials such as rags, oily waste and plastic containers must never be placed close to exhaust manifolds whether lagged or not. All personnel having anything to do with the engine room spaces must know the locations of the different types of fire extinguisher available in the engine room and must know which type is suitable for the different types of fire which can occur. The location of fire hoses and hydrants must also be known. A fire in a particular location may prevent the use of the hose and hydrant at that location so it is essential that the location of alternative fire fighting equipment is known and the best route for running hoses is understood. General 1) 2) 3) Sound the fire alarm and inform the Chief Engineer and the bridge. Do not attempt to tackle the fire alone without informing others of the situation. If personnel are missing, consider the possibility of searching in the fire area. Determine the location of the fire, what is burning, the direction of spread and the possibility of controlling the fire. Determine if oil or other materials are feeding the fire and take steps to cut off the supply of combustible material, e.g. operate quick-closing or other accessible valves to shut off oil supply to the fire. If the fire is in an isolated compartment close the doors to the compartment and shut off ventilation. If necessary, start the emergency generator in order to ensure continuity of electrical supply. Have the fire team organised to tackle the outbreak with maximum speed. The situation must be thoroughly assessed before any personnel are directed to the fire. The means of tackling the fire and the means by which the fire party can retreat from the outbreak area if necessary must be understood by all involved. If there is the least doubt whether the fire can be controlled by ships crew, the safety team must inform the Master so that other ships can be informed on the distress frequencies. Depending upon the fire and the availability of fire fighting capacity, give priority to fire limitation until the situation is clarified. Where appropriate, use portable fire extinguishers on small fires when safe to do so. In Port 1) 2) 3) 4) 5) 6) Activate the emergency shutdown system in agreement with the gas terminal duty personnel and prepare to vacate the berth if required. Conduct a crew check and organise crew for fighting the fire. Inform the local fire brigade even though the fire appears to be under control. If personnel are missing, consider the possibility of searching in the fire area. Close all accessible openings and hatches to prevent the fire spreading. If there is a danger of the release of poisonous gases or of explosion consider part or total ship abandonment. Ship drawings, cargo plans etc. should be taken ashore. A crew check is to be carried out. Consider using the fixed extinguishing systems, depending on extent of fire. On arrival of the fire brigade inform the Chief Fire Officer of: Any personnel missing Assumed location of fire What is assumed to be burning Any conditions that may constitute a hazard Assist the Chief Fire Officer with information and orientation, by means of drawings and plans.

4) 5) 6)

7) 8)

7)

9)

8) 9)

Battening Down of the Engine Room a) b) c) d) e) f) g) h) Stop the main engine and shut down the boilers. Sound the evacuation alarm. Stop all the ventilation fans. Start the emergency generator and put on load. Trip the quick-closing valves and the engine room auxiliary machinery and close all fire flaps and funnel doors. Count all personnel and ensure that none are in the engine room. Start the emergency fire pump and pressurise the fire main. Prepare to operate the Hot Foam fire fighting system if necessary, depending on the extent of the fire. The procedure for this is described in
Section 10.3.3Engine Room Hot Foam Fire Extinguishing System.

10) If substances which are on fire, or close to a fire, may emit poisonous gases or explode, direct the crew to a safe position before actions are organised. 11) Effective communication must always exist between the fire fighters and the ships control centre. The control centre must maintain an open communication with the bridge. 12) If any person is seriously injured, request assistance from the nearest rescue centre. 13) Prepare to operate the Hot Foam fire fighting system if necessary, depending on the extent of the fire. The procedure for this is described in Section 10.3.3Engine Room Hot Foam Fire Extinguishing System. If the High Expansion Foam system does not extinguish the fire, operate the CO2 system. See 10.3.2 Engine Room CO2 Fire Extinguishing System.

Part 10: FIRE FIGHTING SYSTEMS

10.1 10.2 10.3 10.3.1 10.3.2 10.3.3 10.3.4 10.3.5

Fire Fighting Systems Fire Detection System Engine Room Fire Fighting Systems Engine Room Fire Main System Engine Room CO2 Fire Extinguishing System Engine Room Hot Foam Fire Extinguishing System Engine Room Local Fire Extinguishing System Quick-Closing Valves and Fire Dampers System Engine Room Fire Main System Engine Room CO2 Fire Extinguishing System Engine Room Hot Foam Fire Extinguishing System Engine Room Local Fire Extinguishing System Quick-Closing Valves and Fire Dampers System

Illustrations
10.3.1a 10.3.2a 10.3.3a 10.3.4a 10.3.5a

10.1 Fire Fighting Systems


Description The vessels fire fighting capacity is enhanced by the inclusion of systems that can detect and fight the types of fires which might occur due to the ignition of fuel oil, lubricating oil and cargo. The choice of fire fighting system to use will depend on the location and nature of the fire. Initially any fire is attacked using portable extinguishers and if that method fails the following systems are considered. Dangers in Use Do not use on fires where there is live electricity in the vicinity.

Operating Procedure a) Remove the safety pin. b) Press the operating handle.

Portable Fire Extinguishers There are three types on board : 1. Carbon Dioxide - CO2 Suitable for class A and B fires and for class C fires when in a liquid state, such as liquid gas leak. Safe for use in fighting electrical fires. May not be effective when used outside, especially in a breeze.

c) Squeeze the trigger. d) Point the spray at the base of the fire.

3. Dry Powder Suitable for use on fires involving liquids and liquefied solids. Suitable for use, with the correct technique, on extinguishing a high pressure gas flame (Class C Fires). Suitable for use against carbonaceous fires (Class A fires).

Dangers in Use Hold only the insulated parts of the discharge hose and horn. With the expansion and evaporation of the CO2 there are cooling processes and a danger of frost burn if the discharge horn comes into contact with the skin. Do not use without a discharge horn as the discharge will then entrain air and cause an increase in the intensity of the fire. Do not remain in the area after the discharge as CO2 is asphyxiating. Operating Procedure a) Remove the safety pin. b) Direct the horn at the base of the fire. c) Press the lever down fully. d) Direct the CO2 at the base of the fire.

Dry powder gives a fast flame knock-down and may be used on fires involving live electrical equipment.

Dangers in Use May not be effective against a deep seated fire. Avoid inhalation of the powder.

Operating Procedure a) Remove the safety pin. b) Press the operating handle. c) Squeeze the trigger. d) Point the spray at the base of the fire.

2. Foam Suitable for use on liquid spills and contained liquid fire of oils, paints, cleaning fluids and fires involving liquefied solids such as fats and waxes (Class B fires).

10.1 Fire Fighting Systems


Fire Fighting Systems Fire Main System (See 10.3.1Engine Room Fire Main System) The fire pump together with the fire and bilge pump are normally kept ready for use on the fire main. In addition to these pumps the emergency fire pump can all be lined up and used on the fire main system. The accommodation is covered by first aid hoses located on each deck. The hose reels are supplied via freshwater pressure tank and pump installed in engine room, taking suction from the fresh water tank. CO2 Flooding System (See 10.3.2Engine Room CO2 Fire Extinguishing System) The Unitor CO2 system installed in the CO2 bottle room on the starboard side of the Upper Deck and CO2 bottle / foam tank room on the port side of the A-Deck protects the following spaces ; Cargo machinery room Cargo compressor motor room Machinery control room Switchboard rooms Transformer rooms Emergency generator room Paint store Elect. & instrument workshop The central bank CO2 system consists of 19 x 45.4 kg CO2 cylinders for the engine room and 21 x 45.4kg cylinders for the cargo machinery and motor rooms. Foam System for the Engine Room (See 10.3.3Engine Room Hot Foam Fire Extinguishing System) The Yamato High Expansion Foam fire fighting system provides a local fire extinguishing capability to each of the following areas : Engine room Engine room casing Engine room store Engine room workshop BOG pipe hood Laboratory Chemical store Inert gas room F.O. heating rooms F.O. pump rooms Incinerator room Diesel generator rooms Steering gear room Stairway The system supplies high expansion foam making chemical and salt water to the spaces listed above through dedicated lines that are each controlled by electric motor operated butterfly valves. The foam concentrate tank is fitted inside the CO2 bottle and foam tank room which is located on the port side of the A-Deck. Each protected space is provided with High Expansion foam generators designed to produce the required quantity and concentration of foam to meet SOLAS requirements. The operating / control panel provides for control of the entire fire alarm system and consists of a text display, indicator lamps, operating buttons and an element keypad.

Quick-Closing Valve System (See 10.3.5Quick-Closing Valves and Fire Dampers System) All the outlet valves from the fuel oil and lubricating oil tanks, from which oil could flow to feed a fire, are equipped with air operated quick-closing valves, which are controlled from the fire control station. They are supplied from an air receiver situated in the quick-closing valve bottle cabinet, also located in the fire control station. The reservoir is supplied, at a pressure of 0.9 MPa, directly from the service air main system. The inlet valve 161VPE to the quick-closing valve air receiver is locked open. The quick-closing valve air receiver is fitted with a low pressure alarm transmitter. The oil tanks are grouped into four systems, with one three-way cock operating each system. In normal operation the supply line to each group of tank valves is vented to atmosphere, but when the cock is turned, air is supplied to pistons, which collapse the bridge of each valve in that group, thus causing the valve to close. The valves are reset by venting the air supply and operating the valve hand wheel in a closed direction to reset the bridge mechanism and then opening the valve in the normal way. The quick closing valve fitted on the emergency generator diesel oil tank and the generator engine diesel oil service tanks is operated by a directly so as to enable to feed the fuel to emergency diesel generator or main diesel generators in the event of a fire. Fire dampers with an air cylinder are closed by this system as well. The fire dampers are grouped into 6 lines with a three-way solenoid valve and manual cock. The solenoids are operated automatically in conjunction with the operation of CO2 or hot foam system. Emergency Escape Breathing Devices (EEBD) Emergency breathing devices are provided so that, in the event of a fire or other emergency, they are readily available, near the escape routes, to aid escape. There are 18 sets on board : 16 sets for the engine room Two sets for accommodation space

Water Fog System for the Engine Room (See 10.3.4Engine Room Water Fog Fire Extinguishing System) High pressure water forced through atomizer heads will break down into very fine droplets. These droplets have a very effective extinguishing effect on fires, even oil fires. The fine droplets remain suspended in the air and so they do not disturb the oil surface nor do they settle to form a water layer on which burning oil could float. Fine water droplets present a large surface area to the fire and so they exert a cooling effect as the droplets rapidly evaporate. The large droplet concentration and the evaporation have the effect of reducing the local oxygen level. The cooling effect and the reduced local oxygen concentration result in the fire being extinguished. The fresh water fog fire extinguishing system relies upon the delivery of high pressure water to nozzle heads located at sites of fire risk. Ten areas are protected by the water fog system, these are : No.1 main boiler burners platform No.2 main boiler burners platform No.1 diesel generator engine top No.2 diesel generator engine top I.G.G. burner zone Incinerator burner zone Port F.O. pump room Starboard F.O. pump room Port F.O. heating room Starboard F.O. heating room Each protected space can be released locally either by pushbutton located near each protected area inside engine room or remotely on the control panel in fire control station.

Fire Detection System (See 10.2Fire Detection System) The Autronica BS-320 Fire Detection system is a computerized, fully addressable analogue fire alarm system with analogue detectors. The operating panel, control unit and power supply are contained in a central cabinet in the wheelhouse. There are also a full fire alarm panels located in the central control room and a repeater panel in the fire control station in the accommodation cross alleyway on the main deck.

10.2 Fire Detection System


Maker : Model : Autronica AS BS-320 Function Disabled This yellow indicator is illuminated when any part of the system is disabled. Mains This green indicator lamp is illuminated when the power supply is on. Text Display The two line text display provides information about the alarms and the system. It also displays the operating menu. Procedure in the Event of a Prewarning

CAUTION
Always treat a prewarning condition as if it is a fire alarm. a) Determine the location of the activated prewarning detector and check this location for fire conditions, observing all safety precautions. Deal with the situation as necessary in order to remove the danger of fire. b) Open the control panel door and press the SOUNDER SILENCE pushbutton. The prewarning indicator lamp will now change to a steady condition. c) Press the RESET pushbutton. The following text will appear on the display RESET PROCEDURE IN PROGRESS WAIT..... The text will remain for 60 seconds and the reset procedure will be executed in that period. d) If everything is in a normal condition the text display will indicate RESET OK NORMAL CONDITION. e) Close the panel door. After the door is closed only the mains power indicator lamp should be illuminated.

Description
The BS-320 Fire Detection system is a computerized, fully addressable analogue fire alarm system with analogue detectors. The main operating panel, control unit and power supply are contained in a central cabinet in the wheelhouse. There are also a repeater panels located in the engine control room, the fire control station and the cargo control room. The system comprises a wide range of detectors and sensors to suit different needs and conditions. It includes detectors for different alarm parameters, such as smoke, heat and flames. Manual call points, short circuit isolators and timers are connected to the detector loops where required. A fault in the system or a false alarm is detected immediately since the function of the detectors and other installed loop units are automatically and continuously tested. The system will also provide a prewarning when a hazard exists but is not yet serious enough to initiate a full alarm.

Operating Buttons
More Alarms This black pushbutton allows the second line of the text display to be scrolled enabling additional alarms to be revealed. Sounder Silence

The Operating / Control Panel


The operating / control panel provides for indication of alarm conditions and allows the operator to communicate with the system.

This red pushbutton is pressed and mutes all alarm devices and the control panel internal buzzer. It is located behind the panel door. Reset This green pushbutton is pressed in order to reset all system events.

Fire Alarm In the event of one or more detectors detecting a fire, the fire alarm will be activated. The red Fire indicator will flash and the internal buzzer is activated and all audible horns connected to the fire alarm system are activated. If the address of the fire alarm had previously issued a prewarning the prewarning lamp will flash. The text display indicates the address of the detector which registered an alarm condition first. Possible disablements are indicated in the lower line of the display. The printer will operate to register the alarm information. In the event of an alarm condition the following functions are activated : Alarm message to the fire fighters. (BMA) General control output. (AUX) Control output for fire door holders. (Door Hold Magnets)

Indication Devices
Fire The red Fire indicator is illuminated when there is a fire alarm condition. The indicator flashes upon activation of an alarm and will emit a steady light when the SOUNDER SILENCE pushbutton is pressed. More Alarms The red More Alarms indicator will be illuminated when there is more than one fire alarm active. Device Still in Alarm Condition This yellow indicator is illuminated when a detector is automatically disabled. Prewarning This yellow indicator flashes when a prewarning is activated. Press the
SOUNDER SILENCE pushbutton to mute the alarm and the yellow light

System Operation
Prewarning A prewarning will occur when a detector is activated in the event that a fire is likely. A prewarning should always be treated as if there is an actual fire alarm. The yellow Prewarning lamp flashes and the internal buzzer is activated. The text display indicates the location of the detector(s) in the prewarning condition. If more than one prewarning is present the text display will indicate this. The active prewarnings may be seen by calling up the menu function Show Status, Prewarnings. The menu is accessed by pressing the ENTER key and the arrow keys are used until the desired menu function is displayed and pointed to by the cursor; the ENTER key is pressed in order to display the prewarnings.

becomes steady. Fault This yellow indicator flashes when a fault has occurred. Press the SOUNDER SILENCE pushbutton to mute the alarm and the yellow light becomes steady.

10.2 Fire Detection System


Procedure in the Event of a Fire Alarm a) Carry out fire checks and corrective action as necessary for extinguishing the fire, observing all safety precautions. When the scene of the fire has been investigated and the necessary actions taken the audible horns may be switched off. b) Open the control panel door and press the SOUNDER SILENCE pushbutton; all alarm devices including the internal buzzer will be muted. The red FIRE indicator lamp will change to a steady light. All alarm outputs from the control panel are turned off when the SOUNDER SILENCE pushbutton is pressed but the alarm message to the fire fighters remains. c) Press the RESET pushbutton. The following text will appear on the display RESET PROCEDURE IN PROGRESS WAIT.....The text will remain for 60 seconds and the reset procedure will be executed in that period. d) If everything is in normal condition the text display will indicate RESET OK NORMAL CONDITION. This text will remain for 15 seconds and then the menu selection will appear. (Note : After resetting an address may still be in alarm condition. This may be due to mechanical damage, water damage, an electrical fault or the presence of smoke within the compartment. The address still in alarm condition will automatically be disabled and the yellow DEVICES STILL IN ALARM CONDITION indicator lamp will be illuminated. Text indicating the alarm address disabled will be shown in the text display. Technical personnel must be contacted in order to have the damage rectified.) 5) Close the panel door. After the door is closed only the mains power indicator lamp should be illuminated unless there is an address still in alarm condition. Fault Indication The FAULT indicator is flashing and the internal buzzer is activated; the common fault warning output is activated. The text display indicates the nature of the fault: FA means a loop / detector fault and SF means a system fault. If there is more than one fault the text display indicates how many FA and SF faults are present. The nature of each fault may be determined via the menu which is accessed by pressing the ENTER key. Disabling an Address An address is a detector, manual call point or interface unit. When an address is disabled it is isolated and will not generate an alarm, prewarning or fault. 1) In the menu select OUT / IN CONTROL, then DISABLE, then ADDRESS. The text display will show SELECT ADDRESS 0000 and the up and down arrow keys are used to scroll through the 0000 part in order to select the number of the address to be disabled.

Action to be Taken in the Event of a Fault 1) Press the SOUNDER SILENCE pushbutton to mute the internal buzzer : the yellow FAULT indicator lamp becomes a steady light. 2) Note the fault information indicated on the text display and obtain a printout 3) Contact the technical service department in order to have the fault rectified.

2) When the desired address number has been selected press the ENTER key. If further addresses are to be disabled at the same time the up and down arrow keys are used to select further addresses, each one being selected by pressing the ENTER key. 3) When the ENTER key is pressed the text display will change showing the address and time. When all addresses to be disabled have been selected the cursor is moved to TIME and the ENTER key pressed. The display changes indicating a disablement duration of 02 hours which is the initial default. The time may be increased or reduced using the up and down arrow keys then the ENTER key is pressed to select the time.

Disabling or Disconnecting Different parts of the fire alarm system can be disabled. For instance, sections, detectors, manual call points, section units, alarm devices, external control devices and loops. This can be useful when there is welding in a particular section or removal of detectors is required due to structural shipboard work etc. The disabling and restoring are carried out from the Out / In Control part of the main menu. When disabling parts of the system the yellow FUNCTION DISABLED lamp on the front of the control panel will be illuminated for the period the disablement lasts. All disablements must be allocated a time period. By selecting the manually disable time of 99 hours the function will be disabled until restored. The maximum automatic disablement time is 24 hours. When the disable time expires the function will be automatically restored.

Disabling a Zone It is only possible to disable a zone if the zones have been programmed in custom data. The menu will not allow access to the zone area unless this is the case. When a zone is disabled the address is isolated and this will not generate an alarm, a prewarning or a fault. The total number of possible zones is 240 and these have addresses 1-240. 1) In the menu select OUT / IN CONTROL, then DISABLE, then ZONE. The text display will show DISABLE ZONE 001 and the up and down arrow keys are used to scroll through the zone number in order to select the number of the zone to be disabled. It is also possible to select Next or Previous in the display to select a zone. 2) When the desired zone number has been selected press the ENTER key. The text display changes and duration time may be changed by means of the up and down arrow keys. When the duration time has been changed the ENTER key is pressed to disable the zone. 3) The text changes giving the option of selecting more zones. If more zones are required for disabling the YES item is selected and ENTER pressed to repeat the disabling procedure. If NO is selected the disabling zone procedure is closed.

More Alarms If more than one fire alarm is active the MORE ALARMS indicator lamp will be illuminated. The system will operate as for the fire alarm above but the text display will indicate the addresses of all devices in alarm. The printer will operate to register all of the alarm information. Action to be taken in the event of activation of the MORE ALARMS indicator lamp is similar to the procedure for a single alarm. Upon opening the panel door the MORE ALARMS pushbutton must be pressed and the second alarm will be indicated on the second line of the display. Subsequent pressing of the MORE ALARMS pushbutton will bring up each alarm in the queue. Operation of the SOUNDER SILENCE and RESET pushbuttons is the same as for the single alarm; the silent alarm situation applies to each alarm in the queue. With multiple alarms some may remain in the alarm condition for the reasons mentioned above and the DEVICES STILL IN ALARM CONDITION lamp may remain illuminated.

Procedure for Disabling a Function a) At the main menu select OUT / IN CONTROL and then DISABLE. The text display will indicate options for address, zone, controls, sounders and fire brigade. b) Use of the left and right arrow keys (and the down arrow key for the fire brigade option) allows the operator to select the function to be disabled.

10.2 Fire Detection System


Disabling Controls Disabling control is password protected at operator level. The procedure is similar to disabling addresses and zones as above except that Controls is selected after Disable from the main menu. If BT-outputs are disabled the Door Hold Magnet and AUX (control-/alarm outputs) will not function at alarm. Restoring a Zone 1) In the menu select OUT / IN CONTROL, then RESTORE, then ZONE. The zone to be restored is selected using the arrow keys and the ENTER key pressed. The display changes and YYY is selected and ENTER pressed to restore the zone. 2) If more zones are to be restored YES is selected and ENTER pressed and the procedure repeated for other zones. If no more zones are to be restored NO is selected and the ENTER key is pressed to exit the restore zones menu. Restore Controls, Restore Sounders and Restore Fire Brigade operate in the same way as the Restore Address and Restore Zone functions.

Disabling Sounders The disable sounders procedure is similar to disabling addresses and zones as above except that Sounders is selected after Disable from the main menu.

Disabling the Fire Brigade Function The disable fire brigade (BMA) procedure is similar to disabling addresses and zones as above except that Fire Brigade is selected after Disable from the main menu. The fire brigade output, prewarning and fault outputs are disabled.

ALARM

19:23

Restoring Any address, zone or function which has been disabled may be restored. The restoration procedure is similar to the disabling procedure. The FUNCTION DISABLED lamp will be extinguished when all functions have been restored.

AUTROSAFE
SelfVerify

Fault Function Disabled Mute Panel Function Delayed Fire Brig. Signalled Power
More Events

Silence Alarms Reset

Procedure for Restoring a Function a) At the main menu select OUT / IN CONTROL and then RESTORE. The text display will indicate options for address, zone, controls, sounders and fire brigade. b) Use of the left and right arrow keys (and the down arrow key for the fire brigade option) allows the operator to select the function to be restored.

Testing Fire Brig. Disabled Fire Brig. Fault System Fault Alarms Disabled Alarms Fault

1 4 7 C

2 5 8 0

3 6 9

Restoring an Address 1) In the menu selected OUT / IN CONTROL, then RESTORE, then ADDRESS. The text display will show SELECT ADDRESS 0000 and the up and down arrow keys are used to scroll through the 0000 part in order to select the address number to be restored. 2) When the desired address number has been selected press the ENTER key to restore the address. The next address will appear automatically, select that or another address and press ENTER, Selecting MM returns the operator to the main menu.
ALARM

Main Panel

INFORMASJONSPANEL
AUTROSAFE
SelfVerify

Fault Function Disabled Mute Panel Function Delayed Test Power More Events Next Window Lamp Test

Sub Panel

10.3.1 Engine Room Fire Main System


Fire and Bilge Pump Maker : Type : No. of sets : Capacity : Motor : Fire Pump Maker : Type : No. of sets : Capacity : Motor :

Description
Teikoku Machinery Works. Ltd. Vertical centrifugal pump, self-priming 1 170/255 m3/h at 100/35 mTH 100 kW x 1,800 rpm The fire main system supplies sea water to the following locations : Fire hydrants in the engine room Fire hydrants on deck Fire hydrants in the accommodation block Fire hydrants in forward stores Anchor chain hawser pipes Water curtain header Helicopter deck foam system All of the pumps listed in the equipment specifications at the beginning of this section can have their suction and discharge valves configured to supply the engine room fire main although the primary pump for this purpose is the dedicated fire pump. The fire pump together with the fire and bilge pump are normally kept ready for use on the fire main. In addition to these pumps the emergency fire pump, the water spray pump and the fire line pressurizing pump can all be lined up and used on the fire main system. The pumps can be started from the following locations : Fire, and bilge pump - locally, fire control station, bridge ICAS for cargo system, and the ICAS Firefighting screen Fire pump - locally, fire control station and bridge emergency panel. Emergency fire pump - locally, fire control station bridge emergency panel and the ICAS Firefighting screen Pressurizing pump locally, fire control station and the ICAS Firefighting screen Fire fighting FW pump - locally and from the ICAS Firefighting screen The pump suction valves from the sea suction main and the discharge valves to the fire main outlet are normally left open. The fire and bilge pump can take its suction from the sea or the engine room bilge system but is normally left set up for sea suction. The sea suction is from the sea bay in the engine room. This sea bay has connections to the high sea chest and low sea chest. The fire line pressurizing pump is used to maintain a constant pressure in the fire main when the vessel is in port, but because of its low capacity it needs to be supplemented by an additional pump if the fire hydrant is opened. In the cold weather condition, the hydrant sea water heater will be operated and the sea water will be circulated from the end of the fire main into the sea bay to prevent freezing in the fire main line. In this case, the pressurizing pump will be stopped. The seawater temperature at heater outlet is maintained to 10 when seawater temperature is minus 2 by a control valve which regulates steam flow. The spray water is supplied to the system passing the heater whenever the spray water pump is operated regardless of the season. The fire line pressurizing pump discharge has an overboard pipe with an orifice to protect overheat of the pump when all services are not required in operation of the pump. The pump also provides sea water for washing the sewage treatment unit and vacuum unit tank. The fire fighting fresh water hydrophore unit provides the accommodation for first aid purpose. The fire fighting fresh water pump takes suction from the fresh water tank and discharges to a fire fighting fresh water pressure tank. A pressure switch controls the pump operation to keep the water level band. Initial charge air is supplied from the general service air system. The fire fighting fresh water hydrophore unit also provides the fire main and water spray lines for rinsing out seawater. The spraying water pump is normally set for the water spray system but it can be used to direct water to the fire main if required by opening the crossover valve in fire station. Ordinarily this valve would be used to allow the fire pump or the fire and bilge pump to supply water to the water spray system should the spraying water pump be unable to perform that function.

Teikoku Machinery Works. Ltd. Vertical centrifugal pump 1 170 m3/h at 100 mTH 100 kW x 1,800 rpm

Fire Line Pressurizing Pump Maker : Teikoku Machinery Works. Ltd. Type : Horizontal centrifugal pump No. of sets : 1 Capacity : 13 m3/h at 100 mTH Motor : 11 kW x 3,600 rpm Fire Fighting Fresh Water Pump Maker : Teikoku Machinery Works. Ltd. Type : Horizontal centrifugal pump No. of sets : 1 Capacity : 5 m3/h at 110 mTH Motor : 7.5 kW x 3,600 rpm Water Spray Pump Maker : Type : No. of sets : Capacity : Motor : Emergency Fire Pump Maker : Type : No. of sets : Capacity : Motor :

Teikoku Machinery Works. Ltd. Vertical centrifugal pump 1 1,050 m3/h at 100 mTH 420 kW x 1,800 rpm

Teikoku Machinery Works. Ltd. Vertical centrifugal pump 1 630 m3/h at 105 mTH 340 kW x 1,800 rpm

Hydrant Sea Water Heater Maker : DongHwa Entec Type : Shell and tube Heating surface : 19.7 m2 Sea water flow : 200 m3/h Tube size : 16 mm diameter, 1.2 mm thickness

10.3.1 Engine Room Fire Main System


Preparation for the Operation of the Fire Hydrant System To prepare the system for use in the engine room or on the fire and deck wash system, the following procedure needs to be followed : a) All intermediate isolating valves along the fire main on the upper deck must be open. b) All hydrant outlet valves must be closed. It is assumed that the sea water main suction valves at the sea chests are open to provide suction. Valve Description 116VPH Pressurizing pump discharge valve to sewage system 104VPH Pressurizing pump suction valve 113VPH Pressurizing pump discharge valve 115VPH Pressurizing pump overboard valve 103VPH Fire pump suction valve 112VPH Fire pump discharge valve 102VPH Fire and bilge pump SW suction valve 111VPH Fire and bilge pump fire main discharge valve 114VPH Hydrant seawater heater bypass valve 131/136VPH Hydrant seawater heater inlet and outlet valves 031VPJ Water spray pump suction valve 033VPJ Water spray pump discharge valve 112VPJ Fire and bilge pump bilge main suction valve 122VPJ Fire and bilge pump discharge valve Cross connection valve fire main/water spray system c) Start Pressurizing pump at local or fire control station. d) If additional water is required at the fire main, start the fire and bilge pump depending upon circumstances. e) Open the desired hydrant valve on the fire main after connecting the fire hose to the hydrant. (Note : Whenever the fire pump is operating, at least one fire hydrant valve, in the engine room or on deck, must be open to ensure a flow of water through the pump to prevent overheating.) Position
Closed Open Open Open Open Open Open Open Open Closed Closed Closed Closed Closed Closed

Emergency Fire Pump The emergency fire pump is installed in the emergency fire pump room in the compartment aft side of engine room. The pump draws water from a sea chest positioned in the aft peak. The pump is independent of the engine room pumps and can be used to supply water to the fire main in situations when the engine room pumps are not available because of an engine room fire or collision damage etc. The pump is driven by an electric motor and is fed from the emergency switchboard 440V feeder panel located in the emergency generator room. Starting and stopping of the pump can take place from locations : Locally at the pump starter panel in the emergency fire pump room Remotely from the fire control station Remotely from the bridge at the emergency control console The emergency fire pump together with its suction and discharge valves should be tested weekly to ensure correct operation and that full system pressure can be achieved. The suction and discharge valves should always be left open so that the pump is available for immediate operation. Fire Hydrants The fire main has hydrants in the engine room, the accommodation block and on the forward and aft decks. Located adjacent to each hydrant is a hose box containing a fire hose and nozzle. All of the hydrant valves should be operated at frequent intervals to ensure satisfactory operation in the event of an emergency. Intermediate valves in the fire main along the deck should be kept open at all times to ensure that water will be available to all of the deck hydrants whenever required. (Note : After use, the hose and nozzle unit must be properly stowed back in the hose box. Any defects in the hose, nozzle, valve or system must be reported immediately and rectified as soon as possible. Hose boxes must never be left with components which are defective.)

10.3.1a Engine Room Fire Main System


HYDRANT RETURN LINE TO FIRE HOSE REEL SYSTEM
TO W.SPRAY SYSTEM

TO FIRE MAIN

F.W. TK

200

ENG.CASING

129VPH

65

65

128VPH

TO F.W. RECIRC.PUMP
182VPG 111VPG

FIRE FIGHT F.W.PRESS.TK


COMP. AIR

350

40

127VPH

FIRE FIGHT.F.W.PUMP
ASS 630 SA 630 RO FIRE RO 630

PS

40

115VPG

127VPG 034VPJ

65

119VPG

65

PAL 906

200

50

630

2ND DECK

TO FRESH W. PUMP
RO W/H RO FIRE RO 636 RM 636 SA 636

200 350

65

126VPH

WATER SPRAY PUMP

C
R

P
R 032VPJ

STM
132VPH 133VPH

TIC 908

135VPH

350
033VPJ

200

TO OVERBOARD
25

031VPJ

HYDRANT HTR
131VPH 136VPH

65

125VPH

3RD DECK
200
116VPH

25

TO SEWAGE TREAT.UNIT
113VPH 114VPH 114VPH

200

80

115VPH

200

200

65

124VPH

350

150

150

40

112VPH

111VPH

122VPJ

121VPJ

100

65

123VPH

4TH DECK
P
AST 635

119VPJ

FIRE PUMP
RO W/H RO FIRE RM 635 SA 635 RO 635

FIRE &BILGE PUMP


RO W/H RO FIRE RO 637 RM 637 SA 637

BILGE & G.S. PUMP


RO 637 RM 637 SA 637

100

65

122VPH

104VPH

FIRE LINE PRESSURISING PUMP


RO FIRE RO 638 RM 638 SA 638
103VPH

C
112VPJ

C
65

SEA BAY
BILGE SUC. BILGE SUC.

BILGE SUC. FROM MAIN CONDR


102VPH

123VPJ 105VPH

TO HOLD EDUCTOR
150 150 100 40

100

121VPH

65 200

150

200

LOWER FLOOR

10.3.2 Engine Room CO2 Fire Extinguishing System


Maker : Type : Capacity : Unitor High pressure 19 cylinders each containing 45.4 kg

Central Bank CO2 System The central bank CO2 system for engine room consists of 19 x 45.4kg CO2 cylinders located in the CO2 bottle and foam tank room, which is situated on the port side of the A-Deck. Cylinders are grouped together according to the space they protect. These cylinders are connected to discharge nozzles within the protected spaces via cylinder manifolds and distribution pipe work. A pressure gauge and relief are fitted to the main CO2 manifold. The system is designed to discharge the required number of cylinders into each space protected as follows : CO2 Requirements 'The amount of CO2 required to be carried on board the vessel depends upon the volume of the largest protected compartment. This is the switchboard rooms which requires 19 cylinders each containing 45.4kg. The vessel carries 19 cylinders of CO2 to provide protection for the spaces indicated above. If the release of CO2 is authorized, all 19 cylinders are released into the switchboard rooms; the other protected spaces have fewer cylinders released as indicated above. It should be realized that if any cylinders are released into the smaller spaces then there will be insufficient cylinders for the switchboard rooms. It is essential that, in the event of any CO2 release, used cylinders are replenished at the next port of call. The pilot CO2 line to the main cylinder actuation system passes through a time delay device which delays the passage of the CO2 for a preset period of time before the main CO2 charge is released into the compartment. A pressure gauge is fitted to the pilot CO2 pipeline to indicate pilot CO2 pressure.

Description
Dependent upon the application, CO2 is normally employed at levels of between 35% and 50% by volume to produce an oxygen deficiency and thus extinguish a fire. This level of oxygen reduction is also capable of causing asphyxiation. Fixed systems are therefore designed to include safeguards which prevent the automatic release of the CO2 whilst the protected area is occupied. The use of portable extinguishers should ensure that there is sufficient air to breathe normally. CO2 is not generally regarded as having a high intrinsic toxicity and is not normally considered to produce decomposition products in a fire situation. The CO2 cylinders are fitted with safety devices to relieve excess pressure caused by high temperatures. To avoid these operating, it is recommended that cylinders are located in areas where the ambient temperature will not exceed 60C. Cylinders must not be stored in direct sunlight. Certain gaseous extinguishing agents may cause low temperature burns when in contact with the skin. In such cases the affected area should be thoroughly irrigated with clean water and afterwards dressed by a trained person.

Operating Instructions a) On discovering a fire, shutdown machinery, fuel supplies and ventilation systems as appropriate. Close all door ventilators and other openings, having first ensured that all personnel have been evacuated.

b) Check that all personnel have been evacuated from the protected space. c) Go to the release cabinet for the protected space in which the fire has occurred.

d) Open the release cabinet door. This will cause the alarms to sound in the protected space and stop the ventilation fans if not already done so. e) f) Open both isolation valves by pulling valve handles downwards. Release pilot CO2 by opening the screw down valve on one of the pilot cylinders only.

WARNING DANGER OF ASPHYXIATION


Re-entry to a CO2 flooded area should not be made until the area has been thoroughly ventilated.

g) Extinguishing CO2 gas will be released from the main cylinder bank for the protected space after the time delay period. The main valve will be opened and CO2 will be discharged from the nozzles into the protected space. h) After 10 minutes close the pilot cylinder hand wheel valve. i) When the pilot pressure gauge within the control box is zero close both pilot isolation valves.

System Description Areas Protected The CO2 system installed in the ship protects the following spaces ; Cargo machinery room Cargo compressor motor room Machinery control room Switchboard rooms Transformer rooms Emergency generator room Paint store Elect. & instrument workshop 21 cylinders 8 cylinders 8 cylinders 19 cylinders 4 cylinders 6 cylinders 2 cylinders 3 cylinders

Release Cabinets The system is operated by a supply of CO2 separate from the main fire extinguishing CO2. Pilot CO2 cylinders are used for activating the release of the main CO2 cylinders. Two pilot cylinders are located in the supply cabinet installed in the fire station space, one cylinder acts as a standby cylinder. Only one pilot CO2 cylinder would be opened at any time to release the CO2. The release cabinets are all situated in the fire station space. The pilot cylinders connect to the main pilot system pipe work via two isolation valves installed within the release cabinet. One isolation valve is connected via small bore pilot gas pipework to the cylinder bank to open the required number of cylinders, the other is connected via a separate pilot gas line to actuate the power cylinder to open the main valve which directs the released CO2 to the protected space. The isolation valves are positioned so that the control box door cannot be closed with the valves in the open position. It is also arranged that the control box door will operate a switch, when it is in the open position, to initiate audible and visual alarms.

The number of cylinders required to afford complete protection of any protected compartment depends upon the volume of that compartment. The total 40 cylinders are supplied, which are the total numbers of the largest volume for cargo compressor room (21) and that for switchboard room (19).

10.3.2 Engine Room CO2 Fire Extinguishing System


After Release of CO2 Following the release of CO2 the following procedure must be undertaken. a) Allow enough time for the CO2 to extinguish the fire. b) Do not open the compartment until it is evident that the fire is completely extinguished. The protected compartment must be completely ventilated before the door to the space is opened. c) Entry into the protected compartment must only be made by personnel wearing breathing apparatus and with fire extinguishing equipment. Entry by personnel not wearing breathing apparatus must be prohibited until a test confirms that the atmosphere in the compartment contains at least 21% oxygen. Cargo Compressor Room a) Open the main line valve (E) leading to the cargo compressor room. The CO2 alarm will sound and the ventilation fans will stop. b) Remove the manual release handle from its mounting position near the cylinders. c) Insert the end of the handle into the hole in the release lever and open one or two of the CO2 cylinders in the CO2 bank. d) The remaining necessary CO2 cylinders will automatically and the CO2 will be discharged into the space.

WARNING
Do not enter CO2 flooded space without using breathing apparatus. In the unlikely event of pilot gas release failure the second pilot cylinder valve must be opened in order to release CO2 from that cylinder.

Manual Operation Should the pilot CO2 cylinders fail to open the main CO2 cylinders for the protected compartment then these must be opened manually. The main line valve to the protected compartment must also be operated manually. The CO2 cylinders for each protected compartment are grouped together and so it is easy to recognize which cylinders must be manually opened for any protected compartment. The procedure for opening the main cylinders is as below; these should be opened by operation of the manual release lever on top of each CO2 cylinder as follows : a) Open the main line valve (E) leading to the protected space. The CO2 alarm will sound and the ventilation fans will stop. b) Remove the manual release handle from its mounting position near the cylinders. c) Insert the end of the handle into the hole in the release lever. Pull the handle as far as possible in order to operate the release mechanism for the cylinder. d) Repeat these procedures for each cylinder until the specified number have been discharged. All cylinders can be individually manually discharged into any of the protected cargo compartments as and when they are required.

10.3.2a Engine Room CO2 Fire Extinguishing System

10.3.2a

Engine Room CO2 Fire Extinguishing System

SUPPLY CABINET

FIRE STATION
PAINT STORE ELEC. & INST. WORK SHOP EM'CY GEN. RM & SWBD RM HIGH VOLT TRANS. SPACE MACH. CONT. RM SWBD RM MOTOR RM CARGO MACH. RM

CO2 RELEASE ALARM RELAY BOX

MAIN SOURCE

EM'CY SOURCE

ALARM TEST

SUPPLY CABINET

FIRE STATION
PAINT STORE ELEC. & INST. WORK SHOP EM'CY GEN. RM & SWBD RM HIGH VOLT TRANS. SPACE MACH. CONT. RM SWBD RM MOTOR RM CARGO MACH. RM

CO2 RELEASE ALARM RELAY BOX

TIME DELAY UNIT

TO ATMOS.

SHORE / AIR CONNECTION

TO ATMOS.

SHORE / AIR CONNECTION

LS

LS

LS

LS

LS

LS

LS

LS

C01
HANDLES FOR CYLINDER VALVES

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01
HANDLES FOR CYLINDER VALVES

CO2 & FOAM TANK RM

CO2 BOTTLE RM

MAIN SOURCE

EM'CY SOURCE

ALARM TEST

SWBD RM MACHINERY CONT. RM GENERAL DESCRIOTION OF THE SYSTEM


A TOTAL - FLOODING CO2 FIREFIGHTING SYSTEM IS INSTALLED IN THIS SHIP TO COVER THE ROOMS AND STORES. CO2 GAS IS STORED IN 40 CO2 CYLINDERS. 19 CO2 CYLINDERS ARE IN THE CO2 & FORM TANK ROOM (A-DECK). 21 CO2 CYLINDERS ARE IN THE CO2 BOTTLE ROOM (UPP.DECK, S-SIDE). THE CO2 CYLINDERS ARE ARRANAGED FOR QUICK (PNEUMATIC) RELEASE. FOR THIS PURPOSE, THE REMOTE RELEASE CABINETS ARE LOCATED IN THE FIRE STATION. ALARMS ARE PROVIDED IN ALL THESE ROOMS TO GIVE ADVANCE WARNING WARNING OF DISCHARGE OF CO2. MOTOR SIRENS AND ROTATING LAMPS ARE PROVIDED IN MACHI. CONT. RM, SWITCHBOARD ROOM, HIGH VOLT. TRANSFORMER SPACE, EM'CY GENERATOR RM & EM'CY SWITCHBOARD RM, ELECTRIC 6 INSTRUMENT WORKSHOP. AN EEX-SIGNAL HORN IS PROVIDED IN PAINT STORE. AIR HORNS AND EX-PROOF ROTATING LAMPS ARE PROVIDED IN CARGO MACHINERY ROOM AND MOTOR ROOM. WHEN THESE ALARMS ARE ACTIVATED, ALL PERSONNEL MUST LEAVE THE ROOM IMMEDIATELY. NOTE CO2 FIREFIGHTING SYSTEM TO BE USED ONLY FOR FIRE EXTINGUISHING AND NOT INERTING PURPOSE.
PROTECTED SPACES
SWITCHBOARD ROOM (2ND DK) MACHINERY CONT. ROOM (2ND DK) HIGH VOLT TRANS. SPACE (3RD DK) PAINT STORE (UPP. DK) EMERGENCY GENERATOR ROOM & EMERGENCY SWITCHBOARD ROOM (A - DK) ELECTRIC & INSTRUMENT WORK SHOP CARGO MACHINERY ROOM CARGO MOTOR ROOM NO. OF CO2 CYLS TO BE DISCHARGED

MOTOR RM

HIGH VOLT TRANS. SPACE EM'CY GEN. RM & SWBD RM


CO2 CYLINDERS IN CO2 BOTTLE & FOAM TANK ROOM

CARGO MACHINE RM

19 8 4 2 6 3 21 8
TOTAL : 40 CYLS CO2 CYLINDERS IN CO2 BOTTLE ROOM

ELEC. & INST. WORK SHOP PAINT STORE

AFTER A FIRE
GO TO THE CO2 BOTTLE ROOM, CHECK THAT CONTROL (SELECTOR) VALVE FOR THE ROOM ON FIRE HAS OPENED AND THAT THE CORRECT NUMBER OF CO2 CYLINDERS HAVE BEEN DISCHARGED. IF NOT, OPEN BY HAND. SEE SKETCH SHOWING MANUAL RELEASE METHOD FOR PRESSURE OPERATED CYLINDER VALVES. THE NECESSARY HANDLES ARE LOCATED ON THE RED PLATE MARKED "HANDLES FOR CO2 CYLINDER VALVES" 1. TAKE ALL REASONABLE PRECAUTIONS TO ASCERTAIN THAT THE FIRE IS EXTINGUISHED BEFORE OPENING THE ROOM WHICH WAS ON FIRE. 2. BEFORE RE-OPENING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED, IT MUST BE THOROUGHLY VENTILATED. 3. PERSONS ENTERING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED MIST WEAR BREATHING APPARATUS UNTIL IT HAS BEEN VERIFIED THAT THE OXYGEN CONTENT IS BACK TO NORMAL.

OPERATION OF THE SYSTEM


IF A FIRE OCCURS IN ONE OF THE CO2-PROTECTED ROOMS, WHICH CANNOT BE PUT OUT BY PORTABLE FIREFIGHTING EQUIPMENT. 1. GO TO THE FIRE STATION AND OPEN THE DOOR OF THE VALVE RELEASE CABINET FOR THE ROOM ON FIRE. THIS WILL CAUSE THE DISCHARGE ALARMS TO OPERATE. 2. SHUT DOWN ALL MACHINERY IN THE ROOM ON FIRE. 3. CLOSE ALL DOORS, VENTILATORS, AND OTHER OPENINGS TO THE ROOM ON FIRE. 4. MAKE SURE ALL PERSONNEL ARE EVACUATED FROM THE ROOM ON FIRE. 5. IN THE VALVE RELEASE CABINET, OPEN THE BALL VALVES (PUT DOWN THE HANDLE). 6. TAKE THE KEY FROM THE INSIDE OF THE VALVE RELEASE CABINET DOOR. OPEN THE DOOR OF SUPPLY CABINET AND OPEN ONE OF TOP VALVE ON THE PILOT CYLINDER. (THE CONTROL VALVE FOR THE ROMM ON FIRE WILL BE OPEN AND THE VENTILATION FANS TO BE STOPPED) 7. AFTER A TIME LAPSE OF APPROXIMATE 30 SECONDS FROM OPENING THE PILOT CYLINDER TOP VALVE, CO2 GAS WILL BE DISCHARGED INTO THE ROOM ON FIRE.

1. OPEN CONTROL VALVE FOR THE ROOM ON FIRE 2. TAKE MANUAL HANDLE(S) FROM THE RED PLATE SO MARKED AND OPEN REQUIRED NUMBER OF CO2 CYLINDERS BY HAND. (SEE SKETCH) CO2 WILL NOW BE RELEASED INTO THE ROOM ON FIRE.
1. INSERT HANDLE (FROM RED PLATE) INTO TOP OF VALVE 2. PULL BACK

MANUAL RELEASE FOR THE ROOM ON FIRE

10.3.2a

Engine Room CO2 Fire Extinguishing System

SUPPLY CABINET

FIRE STATION
PAINT STORE ELEC. & INST. WORK SHOP EM'CY GEN. RM & SWBD RM HIGH VOLT TRANS. SPACE MACH. CONT. RM SWBD RM MOTOR RM CARGO MACH. RM

CO2 RELEASE ALARM RELAY BOX

TIME DELAY UNIT

TO ATMOS.

MAIN SOURCE

EM'CY SOURCE

ALARM TEST

SHORE / AIR CONNECTION

TO ATMOS.

SHORE / AIR CONNECTION

10.3.2a

Engine Room CO2 Fire Extinguishing System

SUPPLY CABINET

FIRE STATION
PAINT STORE ELEC. & INST. WORK SHOP EM'CY GEN. RM & SWBD RM HIGH VOLT TRANS. SPACE MACH. CONT. RM SWBD RM MOTOR RM CARGO MACH. RM

CO2 RELEASE ALARM RELAY BOX

MAIN SOURCE

EM'CY SOURCE

ALARM TEST

TIME DELAY UNIT

TO ATMOS.

SHORE / AIR CONNECTION

TO ATMOS.

SHORE / AIR CONNECTION

P
LS LS

P
C01 C01
HANDLES FOR CYLINDER VALVES

TIME DELAY UNIT

TO ATMOS.

SHORE / AIR CONNECTION

TO ATMOS.

SHORE / AIR CONNECTION

LS

LS

LS

LS

LS

LS

LS

LS

LS

LS

LS

LS

LS

LS

C01
HANDLES FOR CYLINDER VALVES

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01
HANDLES FOR CYLINDER VALVES

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01
HANDLES FOR CYLINDER VALVES

CO2 & FOAM TANK RM

CO2 BOTTLE RM

CO2 & FOAM TANK RM

CO2 BOTTLE RM

SWBD RM MACHINERY CONT. RM GENERAL DESCRIOTION OF THE SYSTEM


A TOTAL - FLOODING CO2 FIREFIGHTING SYSTEM IS INSTALLED IN THIS SHIP TO COVER THE ROOMS AND STORES. CO2 GAS IS STORED IN 40 CO2 CYLINDERS. 19 CO2 CYLINDERS ARE IN THE CO2 & FORM TANK ROOM (A-DECK). 21 CO2 CYLINDERS ARE IN THE CO2 BOTTLE ROOM (UPP.DECK, S-SIDE). THE CO2 CYLINDERS ARE ARRANAGED FOR QUICK (PNEUMATIC) RELEASE. FOR THIS PURPOSE, THE REMOTE RELEASE CABINETS ARE LOCATED IN THE FIRE STATION. ALARMS ARE PROVIDED IN ALL THESE ROOMS TO GIVE ADVANCE WARNING WARNING OF DISCHARGE OF CO2. MOTOR SIRENS AND ROTATING LAMPS ARE PROVIDED IN MACHI. CONT. RM, SWITCHBOARD ROOM, HIGH VOLT. TRANSFORMER SPACE, EM'CY GENERATOR RM & EM'CY SWITCHBOARD RM, ELECTRIC 6 INSTRUMENT WORKSHOP. AN EEX-SIGNAL HORN IS PROVIDED IN PAINT STORE. AIR HORNS AND EX-PROOF ROTATING LAMPS ARE PROVIDED IN CARGO MACHINERY ROOM AND MOTOR ROOM. WHEN THESE ALARMS ARE ACTIVATED, ALL PERSONNEL MUST LEAVE THE ROOM IMMEDIATELY. NOTE CO2 FIREFIGHTING SYSTEM TO BE USED ONLY FOR FIRE EXTINGUISHING AND NOT INERTING PURPOSE.
PROTECTED SPACES
SWITCHBOARD ROOM (2ND DK) MACHINERY CONT. ROOM (2ND DK) HIGH VOLT TRANS. SPACE (3RD DK) PAINT STORE (UPP. DK) EMERGENCY GENERATOR ROOM & EMERGENCY SWITCHBOARD ROOM (A - DK) ELECTRIC & INSTRUMENT WORK SHOP CARGO MACHINERY ROOM CARGO MOTOR ROOM NO. OF CO2 CYLS TO BE DISCHARGED

MOTOR RM

SWBD RM MACHINERY CONT. RM

MOTOR RM

HIGH VOLT TRANS. SPACE EM'CY GEN. RM & SWBD RM


CO2 CYLINDERS IN CO2 BOTTLE & FOAM TANK ROOM

CARGO MACHINE RM

GENERAL DESCRIOTION OF THE SYSTEM


A TOTAL - FLOODING CO2 FIREFIGHTING SYSTEM IS INSTALLED IN THIS SHIP TO COVER THE ROOMS AND STORES. CO2 GAS IS STORED IN 40 CO2 CYLINDERS. 19 CO2 CYLINDERS ARE IN THE CO2 & FORM TANK ROOM (A-DECK). 21 CO2 CYLINDERS ARE IN THE CO2 BOTTLE ROOM (UPP.DECK, S-SIDE). THE CO2 CYLINDERS ARE ARRANAGED FOR QUICK (PNEUMATIC) RELEASE. FOR THIS PURPOSE, THE REMOTE RELEASE CABINETS ARE LOCATED IN THE FIRE STATION.
PROTECTED SPACES
SWITCHBOARD ROOM (2ND DK) MACHINERY CONT. ROOM (2ND DK) HIGH VOLT TRANS. SPACE (3RD DK) PAINT STORE (UPP. DK) EMERGENCY GENERATOR ROOM & EMERGENCY SWITCHBOARD ROOM (A - DK) ELECTRIC & INSTRUMENT WORK SHOP CARGO MACHINERY ROOM CARGO MOTOR ROOM NO. OF CO2 CYLS TO BE DISCHARGED

HIGH VOLT TRANS. SPACE EM'CY GEN. RM & SWBD RM


CO2 CYLINDERS IN CO2 BOTTLE & FOAM TANK ROOM

CARGO MACHINE RM

19 8 4 2 6 3 21 8
TOTAL : 40 CYLS CO2 CYLINDERS IN CO2 BOTTLE ROOM

ELEC. & INST. WORK SHOP PAINT STORE

19 8 4 2 6 3 21 8
TOTAL : 40 CYLS CO2 CYLINDERS IN CO2 BOTTLE ROOM

ELEC. & INST. WORK SHOP PAINT STORE

AFTER A FIRE
GO TO THE CO2 BOTTLE ROOM, CHECK THAT CONTROL (SELECTOR) VALVE FOR THE ROOM ON FIRE HAS OPENED AND THAT THE CORRECT NUMBER OF CO2 CYLINDERS HAVE BEEN DISCHARGED. IF NOT, OPEN BY HAND. SEE SKETCH SHOWING MANUAL RELEASE METHOD FOR PRESSURE OPERATED CYLINDER VALVES. THE NECESSARY HANDLES ARE LOCATED ON THE RED PLATE MARKED "HANDLES FOR CO2 CYLINDER VALVES" 1. TAKE ALL REASONABLE PRECAUTIONS TO ASCERTAIN THAT THE FIRE IS EXTINGUISHED BEFORE OPENING THE ROOM WHICH WAS ON FIRE. 2. BEFORE RE-OPENING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED, IT MUST BE THOROUGHLY VENTILATED. 3. PERSONS ENTERING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED MIST WEAR BREATHING APPARATUS UNTIL IT HAS BEEN VERIFIED THAT THE OXYGEN CONTENT IS BACK TO NORMAL.

ALARMS ARE PROVIDED IN ALL THESE ROOMS TO GIVE ADVANCE WARNING WARNING OF DISCHARGE OF CO2. MOTOR SIRENS AND ROTATING LAMPS ARE PROVIDED IN MACHI. CONT. RM, SWITCHBOARD ROOM, HIGH VOLT. TRANSFORMER SPACE, EM'CY GENERATOR RM & EM'CY SWITCHBOARD RM, ELECTRIC 6 INSTRUMENT WORKSHOP. AN EEX-SIGNAL HORN IS PROVIDED IN PAINT STORE. AIR HORNS AND EX-PROOF ROTATING LAMPS ARE PROVIDED IN CARGO MACHINERY ROOM AND MOTOR ROOM. WHEN THESE ALARMS ARE ACTIVATED, ALL PERSONNEL MUST LEAVE THE ROOM IMMEDIATELY.

AFTER A FIRE
GO TO THE CO2 BOTTLE ROOM, CHECK THAT CONTROL (SELECTOR) VALVE FOR THE ROOM ON FIRE HAS OPENED AND THAT THE CORRECT NUMBER OF CO2 CYLINDERS HAVE BEEN DISCHARGED. IF NOT, OPEN BY HAND. SEE SKETCH SHOWING MANUAL RELEASE METHOD FOR PRESSURE OPERATED CYLINDER VALVES. THE NECESSARY HANDLES ARE LOCATED ON THE RED PLATE MARKED "HANDLES FOR CO2 CYLINDER VALVES" 1. TAKE ALL REASONABLE PRECAUTIONS TO ASCERTAIN THAT THE FIRE IS EXTINGUISHED BEFORE OPENING THE ROOM WHICH WAS ON FIRE. 2. BEFORE RE-OPENING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED, IT MUST BE THOROUGHLY VENTILATED. 3. PERSONS ENTERING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED MIST WEAR BREATHING APPARATUS UNTIL IT HAS BEEN VERIFIED THAT THE OXYGEN CONTENT IS BACK TO NORMAL.

OPERATION OF THE SYSTEM


IF A FIRE OCCURS IN ONE OF THE CO2-PROTECTED ROOMS, WHICH CANNOT BE PUT OUT BY PORTABLE FIREFIGHTING EQUIPMENT. 1. GO TO THE FIRE STATION AND OPEN THE DOOR OF THE VALVE RELEASE CABINET FOR THE ROOM ON FIRE. THIS WILL CAUSE THE DISCHARGE ALARMS TO OPERATE. 2. SHUT DOWN ALL MACHINERY IN THE ROOM ON FIRE. 3. CLOSE ALL DOORS, VENTILATORS, AND OTHER OPENINGS TO THE ROOM ON FIRE. 4. MAKE SURE ALL PERSONNEL ARE EVACUATED FROM THE ROOM ON FIRE. 5. IN THE VALVE RELEASE CABINET, OPEN THE BALL VALVES (PUT DOWN THE HANDLE). 6. TAKE THE KEY FROM THE INSIDE OF THE VALVE RELEASE CABINET DOOR. OPEN THE DOOR OF SUPPLY CABINET AND OPEN ONE OF TOP VALVE ON THE PILOT CYLINDER. (THE CONTROL VALVE FOR THE ROMM ON FIRE WILL BE OPEN AND THE VENTILATION FANS TO BE STOPPED) 7. AFTER A TIME LAPSE OF APPROXIMATE 30 SECONDS FROM OPENING THE PILOT CYLINDER TOP VALVE, CO2 GAS WILL BE DISCHARGED INTO THE ROOM ON FIRE.

OPERATION OF THE SYSTEM


IF A FIRE OCCURS IN ONE OF THE CO2-PROTECTED ROOMS, WHICH CANNOT BE PUT OUT BY PORTABLE FIREFIGHTING EQUIPMENT. 1. GO TO THE FIRE STATION AND OPEN THE DOOR OF THE VALVE RELEASE CABINET FOR THE ROOM ON FIRE. THIS WILL CAUSE THE DISCHARGE ALARMS TO OPERATE. 2. SHUT DOWN ALL MACHINERY IN THE ROOM ON FIRE. 3. CLOSE ALL DOORS, VENTILATORS, AND OTHER OPENINGS TO THE ROOM ON FIRE. 4. MAKE SURE ALL PERSONNEL ARE EVACUATED FROM THE ROOM ON FIRE. 5. IN THE VALVE RELEASE CABINET, OPEN THE BALL VALVES (PUT DOWN THE HANDLE). 6. TAKE THE KEY FROM THE INSIDE OF THE VALVE RELEASE CABINET DOOR. OPEN THE DOOR OF SUPPLY CABINET AND OPEN ONE OF TOP VALVE ON THE PILOT CYLINDER. (THE CONTROL VALVE FOR THE ROMM ON FIRE WILL BE OPEN AND THE VENTILATION FANS TO BE STOPPED) 7. AFTER A TIME LAPSE OF APPROXIMATE 30 SECONDS FROM OPENING THE PILOT CYLINDER TOP VALVE, CO2 GAS WILL BE DISCHARGED INTO THE ROOM ON FIRE.

1. OPEN CONTROL VALVE FOR THE ROOM ON FIRE 2. TAKE MANUAL HANDLE(S) FROM THE RED PLATE SO MARKED AND OPEN REQUIRED NUMBER OF CO2 CYLINDERS BY HAND. (SEE SKETCH) CO2 WILL NOW BE RELEASED INTO THE ROOM ON FIRE.
1. INSERT HANDLE (FROM RED PLATE) INTO TOP OF VALVE 2. PULL BACK

MANUAL RELEASE FOR THE ROOM ON FIRE

LS

LS

LS

LS

LS

LS

LS

LS

NOTE CO2 FIREFIGHTING SYSTEM TO BE USED ONLY FOR FIRE EXTINGUISHING AND NOT INERTING PURPOSE.

1. OPEN CONTROL VALVE FOR THE ROOM ON FIRE 2. TAKE MANUAL HANDLE(S) FROM THE RED PLATE SO MARKED AND OPEN REQUIRED NUMBER OF CO2 CYLINDERS BY HAND. (SEE SKETCH) CO2 WILL NOW BE RELEASED INTO THE ROOM ON FIRE.
1. INSERT HANDLE (FROM RED PLATE) INTO TOP OF VALVE 2. PULL BACK

MANUAL RELEASE FOR THE ROOM ON FIRE

C01
HANDLES FOR CYLINDER VALVES

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01

C01
HANDLES FOR CYLINDER VALVES

CO2 & FOAM TANK RM

CO2 BOTTLE RM

SWBD RM MACHINERY CONT. RM GENERAL DESCRIOTION OF THE SYSTEM


A TOTAL - FLOODING CO2 FIREFIGHTING SYSTEM IS INSTALLED IN THIS SHIP TO COVER THE ROOMS AND STORES. CO2 GAS IS STORED IN 40 CO2 CYLINDERS. 19 CO2 CYLINDERS ARE IN THE CO2 & FORM TANK ROOM (A-DECK). 21 CO2 CYLINDERS ARE IN THE CO2 BOTTLE ROOM (UPP.DECK, S-SIDE). THE CO2 CYLINDERS ARE ARRANAGED FOR QUICK (PNEUMATIC) RELEASE. FOR THIS PURPOSE, THE REMOTE RELEASE CABINETS ARE LOCATED IN THE FIRE STATION. ALARMS ARE PROVIDED IN ALL THESE ROOMS TO GIVE ADVANCE WARNING WARNING OF DISCHARGE OF CO2. MOTOR SIRENS AND ROTATING LAMPS ARE PROVIDED IN MACHI. CONT. RM, SWITCHBOARD ROOM, HIGH VOLT. TRANSFORMER SPACE, EM'CY GENERATOR RM & EM'CY SWITCHBOARD RM, ELECTRIC 6 INSTRUMENT WORKSHOP. AN EEX-SIGNAL HORN IS PROVIDED IN PAINT STORE. AIR HORNS AND EX-PROOF ROTATING LAMPS ARE PROVIDED IN CARGO MACHINERY ROOM AND MOTOR ROOM. WHEN THESE ALARMS ARE ACTIVATED, ALL PERSONNEL MUST LEAVE THE ROOM IMMEDIATELY. NOTE CO2 FIREFIGHTING SYSTEM TO BE USED ONLY FOR FIRE EXTINGUISHING AND NOT INERTING PURPOSE.
PROTECTED SPACES
SWITCHBOARD ROOM (2ND DK) MACHINERY CONT. ROOM (2ND DK) HIGH VOLT TRANS. SPACE (3RD DK) PAINT STORE (UPP. DK) EMERGENCY GENERATOR ROOM & EMERGENCY SWITCHBOARD ROOM (A - DK) ELECTRIC & INSTRUMENT WORK SHOP CARGO MACHINERY ROOM CARGO MOTOR ROOM NO. OF CO2 CYLS TO BE DISCHARGED

MOTOR RM

HIGH VOLT TRANS. SPACE EM'CY GEN. RM & SWBD RM


CO2 CYLINDERS IN CO2 BOTTLE & FOAM TANK ROOM

CARGO MACHINE RM

19 8 4 2 6 3 21 8
TOTAL : 40 CYLS CO2 CYLINDERS IN CO2 BOTTLE ROOM

ELEC. & INST. WORK SHOP PAINT STORE

AFTER A FIRE
GO TO THE CO2 BOTTLE ROOM, CHECK THAT CONTROL (SELECTOR) VALVE FOR THE ROOM ON FIRE HAS OPENED AND THAT THE CORRECT NUMBER OF CO2 CYLINDERS HAVE BEEN DISCHARGED. IF NOT, OPEN BY HAND. SEE SKETCH SHOWING MANUAL RELEASE METHOD FOR PRESSURE OPERATED CYLINDER VALVES. THE NECESSARY HANDLES ARE LOCATED ON THE RED PLATE MARKED "HANDLES FOR CO2 CYLINDER VALVES" 1. TAKE ALL REASONABLE PRECAUTIONS TO ASCERTAIN THAT THE FIRE IS EXTINGUISHED BEFORE OPENING THE ROOM WHICH WAS ON FIRE. 2. BEFORE RE-OPENING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED, IT MUST BE THOROUGHLY VENTILATED. 3. PERSONS ENTERING ANY ROOM INTO WHICH CO2 HAS BEEN DISCHARGED MIST WEAR BREATHING APPARATUS UNTIL IT HAS BEEN VERIFIED THAT THE OXYGEN CONTENT IS BACK TO NORMAL.

OPERATION OF THE SYSTEM


IF A FIRE OCCURS IN ONE OF THE CO2-PROTECTED ROOMS, WHICH CANNOT BE PUT OUT BY PORTABLE FIREFIGHTING EQUIPMENT. 1. GO TO THE FIRE STATION AND OPEN THE DOOR OF THE VALVE RELEASE CABINET FOR THE ROOM ON FIRE. THIS WILL CAUSE THE DISCHARGE ALARMS TO OPERATE. 2. SHUT DOWN ALL MACHINERY IN THE ROOM ON FIRE. 3. CLOSE ALL DOORS, VENTILATORS, AND OTHER OPENINGS TO THE ROOM ON FIRE. 4. MAKE SURE ALL PERSONNEL ARE EVACUATED FROM THE ROOM ON FIRE. 5. IN THE VALVE RELEASE CABINET, OPEN THE BALL VALVES (PUT DOWN THE HANDLE). 6. TAKE THE KEY FROM THE INSIDE OF THE VALVE RELEASE CABINET DOOR. OPEN THE DOOR OF SUPPLY CABINET AND OPEN ONE OF TOP VALVE ON THE PILOT CYLINDER. (THE CONTROL VALVE FOR THE ROMM ON FIRE WILL BE OPEN AND THE VENTILATION FANS TO BE STOPPED) 7. AFTER A TIME LAPSE OF APPROXIMATE 30 SECONDS FROM OPENING THE PILOT CYLINDER TOP VALVE, CO2 GAS WILL BE DISCHARGED INTO THE ROOM ON FIRE.

1. OPEN CONTROL VALVE FOR THE ROOM ON FIRE 2. TAKE MANUAL HANDLE(S) FROM THE RED PLATE SO MARKED AND OPEN REQUIRED NUMBER OF CO2 CYLINDERS BY HAND. (SEE SKETCH) CO2 WILL NOW BE RELEASED INTO THE ROOM ON FIRE.
1. INSERT HANDLE (FROM RED PLATE) INTO TOP OF VALVE 2. PULL BACK

MANUAL RELEASE FOR THE ROOM ON FIRE

10.3.3 Engine Room Hot Foam Fire Extinguishing System


Foam System Maker : No. of sets : Tank capacity : Generator inlet pressure : Emergency Fire Pump No. of sets : Type : Capacity : Motor : Form Concentrate Pump No. of sets : Type : Capacity : Motor: Yamato Protec Corporation 1 8,000 litres 0.4 MPa 1 Vertical centrifugal 630 m3/h at 105 mTH 340 kW x 1,800 rpm 1 Horizontal gear 15 m3/h x 1.30 MPa 18.5 kW x 1,200 rpm There are three concentrate / water mixing units, one has big capacity and the others are small of the same capacity. The combinations of the units are controlled automatically by the main control panel depending upon the protected spaces to be extinguished. The foam is generated by mixing the foam making chemical with sea water at a rate of 2% chemical solution to 98% sea water. The foam chemical mixes with sea water in the proportioner and the combined liquid is pumped to the protected spaces through a 300mm supply line. The generators utilized are designated as YHE-15, YHE-30 and YHE-60, and these have a foam production capability of 16m3/min, 32m3/min and 65m3/min respectively. A total of 131 generators are used with the numbers in each location being as follows : Engine room Engine room casing Engine room store Engine room workshop BOG pipe hood Laboratory Chemical store Inert gas room F.O. heating rooms F.O. pump rooms Incinerator room Diesel generator rooms Steering gear room Stairway 52 generators 12 generators 9 generators 7 generators 2 generators 2 generators 2 generators 9 generators 4 generators 6 generators 4 generators 6 generators 14 generators 2 generators System Operation The system operation is controlled automatically by the programmed logic circuit (PLC) in the control cabinet. In the event of failure of the control system the hot foam system may be controlled manually as described later. The test (maintenance) mode is normally used for testing and maintenance the system by utilizing switches located at the inside of the control cabinet. The hot foam system may be operated from the control panel in the foam tank room or from individual sub panel situated in the fire station. Procedure for Making the Foam System Operational a) Check the foam concentrate tank visually for any damage or leakage. b) Ensure there is sufficient foam chemical in the foam tank. c) Check that the emergency fire pump sea water supply valves are all open. These valves should remain open during normal service.

d) If the weather is cold, the pump and system heaters must be left on.

Description
The Yamato High Expansion Foam fire fighting system provides a local fire extinguishing capability to each of the following areas: Engine room Engine room casing Engine room store Engine room workshop BOG pipe hood Laboratory Chemical store Inert gas room F.O. heating rooms F.O. pump rooms Incinerator room Diesel generator rooms Steering gear room Stairway The system supplies high expansion foam making chemical and salt water or fresh water to the spaces listed above through dedicated lines that are each controlled by electric motor operated butterfly valves. The system is manually operated and can be released from the main control cabinet in the CO2 bottle and foam tank room or the sub control panel in the fire control station. The foam concentrate tank is fitted inside the CO2 bottle and foam tank room which is located on the port side of the A-Deck. The tank is a standard 8,000 litre unit made of steel and has a full charge when it has 7,289 litres of foam making chemical inside. The capacity of the system is designed to be able to supply foam to all of the protected spaces simultaneously.

WARNING
Before activating the hot foam system in any protected compartment, it is essential to ensure that all personnel have been evacuated .Procedure for Operating the System from the Foam Tank Room The following description and valve numbers refer to Illustration 10.3.3aEngine Room Hot Foam Fire Extinguishing System. When the system is not in use valves AV2-4 and AV3-1~AV13 must all be closed. If it is necessary to operate the system in the case of a fire then the following procedure needs to be followed : a) b) c) d) e) f) g) h) i) Ensure that power is available to the control panel and pumps. Ensure that the valves MV1~MV4.are open. Ensure that all personnel are evacuated from the space into which the foam is to be injected and close all doors and openings to that space. Press the PREPARATION button on the control panel. Alarm sounds in engine room. Confirm that the emergency fire pump is running. Press START push button of the area to be flooded after the PREPARATION lamp has been continuous lighting from flickering. Confirm that the foam concentrate pump is running. When the fire is extinguished the system must be manually switched off by pressing the SYSTEM STOP pushbutton. When the fire has been extinguished and the space has cooled down the foam must be cleared from the room before personnel may enter. Precautions must be observed regarding breathable atmosphere and the risk of a further fire outbreak if the seat of the fire has not cooled down completely.

The generators are designed as an integral part of the High Expansion foam system. The generators are constructed from stainless steel and are built as one unit with no moving parts. They each have one discharge nozzle. The water / foam mix enters the generator housing at a pressure of between 0.6 and 0.7 MPa and with the speed at which it passes through the housing it creates a negative pressure. This pressure reduction causes air and smoke to be drawn into the housing so mixing with the foam / water solution to create a high expansion foam. It is important to note that to ensure correct operation of this system only the manufacturers approved foam making chemicals should be used. Electrical power for the pumps and control panels is supplied from the main switchboard distribution system, however back-up power from the emergency switchboard has been provided for. Alarms are provided in the protected spaces to give warning of discharge of the system.

10.3.3a Engine Room Hot Foam Fire Extinguishing System


FIRE STATION
SUB CONTROL PANEL
YAMATO HIGH EXPANSION FORM SYSTEM CONTROL PANEL
ENGINE ROOM
FORM DISCHARGE SECTION VALVE OPEN AV3-1 SECTION VALVE CLOSE AV3-1 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-2 SECTION VALVE CLOSE AV3-2 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-3 SECTION VALVE CLOSE AV3-3 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-4 SECTION VALVE CLOSE AV3-4 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-5 SECTION VALVE CLOSE AV3-5 PIPE LINE DAMAGE

FOAM TANK ROOM

MAIN CONTROL PANEL


SUB CONTROL PANEL
YAMATO HIGH EXPANSION FORM SYSTEM CONTROL PANEL
ENGINE ROOM
FORM DISCHARGE SECTION VALVE OPEN AV3-1 SECTION VALVE CLOSE AV3-1 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-2 SECTION VALVE CLOSE AV3-2 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-3 SECTION VALVE CLOSE AV3-3 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-4 SECTION VALVE CLOSE AV3-4 PIPE LINE DAMAGE SECTION VALVE OPEN AV3-5 SECTION VALVE CLOSE AV3-5 PIPE LINE DAMAGE

ST. GEAR RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-6 SECTION VALVE CLOSE AV3-6

PREPARATION

START

PREPARATION

START

I.G.G. ROOM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-7 SECTION VALVE CLOSE AV3-7

F.O. PUMP RM (S)


FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-8 SECTION VALVE CLOSE AV3-8

INCINERATOR RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-9 SECTION VALVE CLOSE AV3-9

ST. GEAR RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-6 SECTION VALVE CLOSE AV3-6

PREPARATION

START

PREPARATION

START

PREPARATION

START

No.1 D/G RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-10 SECTION VALVE CLOSE AV3-10

No.2 D/G RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-11 SECTION VALVE CLOSE AV3-11

No.1 F.O. HEATING RM


FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-12 SECTION VALVE CLOSE AV3-12

PREPARATION

START

PREPARATION

START

PREPARATION

START

No.2 F.O. HEATING RM


FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-13 SECTION VALVE CLOSE AV3-13

PREPARATION

START

PREPARATION

START

PREPARATION

START

I.G.G. ROOM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-7 SECTION VALVE CLOSE AV3-7

F.O. PUMP RM (S)


FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-8 SECTION VALVE CLOSE AV3-8

INCINERATOR RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-9 SECTION VALVE CLOSE AV3-9

MAIN POWER EM'CY POWER


TO START TO STOP TO START

WATER SPRAY VALVE OPEN AV1-1 FORM CONCENTRATE VALVE OPEN AV2-1 WATER SPRAY VALVE OPEN AV1-2 FORM CONCENTRATE VALVE OPEN AV2-2 WATER SPRAY VALVE OPEN AV1-3 FORM CONCENTRATE VALVE OPEN AV2-3 FORM CONCENTRATE VALVE OPEN AV2-4

WATER SPRAY VALVE CLOSE AV1-1 FORM CONCENTRATE VALVE CLOSE AV2-1 WATER SPRAY VALVE CLOSE AV1-2 FORM CONCENTRATE VALVE CLOSE AV2-2 WATER SPRAY VALVE CLOSE AV1-3 FORM CONCENTRATE VALVE CLOSE AV2-3 FORM CONCENTRATE VALVE CLOSE AV2-4

WATER SPRAY PRESS. LOW No.1 WATER SPRAY PRESS. LOW No.2 WATER SPRAY PRESS. LOW No.3 FORM CONCENTRATE PRESS. LOW MIX IMPROPER ATTENTION SW. POS.

EM'CY FIRE PUMP READY TO START EM'CY FIRE PUMP RUNNING FRESH WATER LINE USE SEA WATER LINE USE F.W. TANK LEVEL LOW

MAIN AC POWER SOURCE MAIN AC POWER SOURCE

ALARM STOP

ALARM TEST

BUZZER STOP

LAMP TEST

SYSTEM STOP

VDR

- DO NOT START EXCEPT FOR FIRE ENGINE ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE STEERING GEAR ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED. (1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE ENGINE ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED. (1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

P DPS

P M AV3-1

STEERING GEAR ROOM


TO START

I.G.G. ROOM
TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE I.G.G. ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

F.O. PUMP. ROOM (S)


(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE PURIFIRE ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

PREPARATION

START

PREPARATION

START

PREPARATION

START

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

INCINERATOR ROOM
TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE INCINERATOR ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

No.1 D/G ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.1 D/G ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

No.2 D/G ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.2 D/G ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

No.1 F.O. HEATING ROOM


(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.1 F.O. HEATING ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

No.1 D/G RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-10 SECTION VALVE CLOSE AV3-10

No.2 D/G RM
FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-11 SECTION VALVE CLOSE AV3-11

No.1 F.O. HEATING RM


FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-12 SECTION VALVE CLOSE AV3-12

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

No.2 F.O. HEATING ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.2 F.O. HEATING ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

(FOAM FILL UP TIME (NORMAL CONDITION))


TANK TOP 4TH DECK F.O. PUMP ROOM (P) F.O. PUMP ROOM (S) 3RD DECK I.G.G. ROOM CHEMICAL STORE ENG. STORE No.1 D/G ROOM No.2 D/G ROOM STEERING GEAR ROOM 3 min 5 min 2 min 2 min 9 min 4 min 3 min 3 min 3 min 2 min 3 min 2ND DECK I.G.G. ROOM No.1 F.O. HEATING RM No.2 F.O. HEATING RM LABORATORY BOG PIPE HOOD ENG. WORK SHOP STAIRWAY UPPER DECK I.G.G. ROOM INCINERATOR. ROOM CASING 11 min 6 min 2 min 2 min 2 min 2 min 2 min 2 min 12 min 7 min 2 min 17 min

(CAUTION)
(1) AFTER THE FIRE EXTINGUISHED, THE PROTECTED SPACE SHOULD BE COOLED AND VENTILATED WELL BEFORE ANY CREW ENTERS THERE. (2) IF THE SYSTEM CAN NOT BE OPERATED AUTOMATICALLY, OPERATE MANUALLY AT FOAM TANK ROOM. (3) AFTER USING THE SYSTEM, THE TANK IS TO BE FILLED WITH FOAM CONCENTRATE UP TO THE REQUIRED LEVEL. (4) BEFORE USING THE SYSTEM, FIXED LOCAL APPLICATION FIRE FIGHTING SYSTEM IS TO BE STOPPED.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

ENGINE RM (S) LOWER


P DPS P M AV3-2

PREPARATION

START

PREPARATION

START

PREPARATION

START

YAmATO PROTECT CORPORATION

No.2 F.O. HEATING RM


FORM DISCHARGE PIPE LINE DAMAGE SECTION VALVE OPEN AV3-13 SECTION VALVE CLOSE AV3-13

PREPARATION

START

WATER SPRAY VALVE OPEN AV1-1 FORM CONCENTRATE VALVE OPEN AV2-1 WATER SPRAY VALVE OPEN AV1-2 FORM CONCENTRATE VALVE OPEN AV2-2 WATER SPRAY VALVE OPEN AV1-3 FORM CONCENTRATE VALVE OPEN AV2-3 FORM CONCENTRATE VALVE OPEN AV2-4

WATER SPRAY VALVE CLOSE AV1-1 FORM CONCENTRATE VALVE CLOSE AV2-1 WATER SPRAY VALVE CLOSE AV1-2 FORM CONCENTRATE VALVE CLOSE AV2-2 WATER SPRAY VALVE CLOSE AV1-3 FORM CONCENTRATE VALVE CLOSE AV2-3 FORM CONCENTRATE VALVE CLOSE AV2-4

WATER SPRAY PRESS. LOW No.1 WATER SPRAY PRESS. LOW No.2 WATER SPRAY PRESS. LOW No.3 FORM CONCENTRATE PRESS. LOW MIX IMPROPER ATTENTION SW. POS.

EM'CY FIRE PUMP READY TO START EM'CY FIRE PUMP RUNNING FRESH WATER LINE USE SEA WATER LINE USE F.W. TANK LEVEL LOW

MAIN AC POWER SOURCE MAIN AC POWER SOURCE

ALARM STOP

ALARM TEST

ENGINE RM (P) LOWER


P DPS P M AV3-3

BUZZER STOP

LAMP TEST

SYSTEM STOP

- DO NOT START EXCEPT FOR FIRE ENGINE ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE ENGINE ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

ENGINE RM (S) MIDDLE & UPPER


F.O. PUMP. ROOM (S)
TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE PURIFIRE ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

STEERING GEAR ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE STEERING GEAR ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

I.G.G. ROOM
TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE I.G.G. ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

FILLING PIPE
AV2-1 M DPS PI1 AV1-1 M

P DPS

P M AV3-4

INCINERATOR ROOM
TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE INCINERATOR ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

No.1 D/G ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.1 D/G ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

No.2 D/G ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.2 D/G ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

No.1 F.O. HEATING ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.1 F.O. HEATING ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

P
PS P DPS MV1 P M AV3-5

ENGINE RM (P) MIDDLE & UPPER


ENGINE WORK SHOP BOG PIPE HOOD LABORATORY STAIRWAY ENGINE STORE CHEMICAL STORE

No.2 F.O. HEATING ROOM


TO START
(1) PUSH THE PREPARATION BUTTON. THE ALARMS SOUND IN THE No.2 F.O. HEATING ROOM FOR EVACUATION AND THE EMERGENCY FIRE PUMP IS STARTED. (2) MAKE SURE THAT THE PREPARATION LAMP FLICKER TO LIGHT CONTINUOUS, AND PUSH THE STSRT BUTTON. THE SELECTION VALVE TO OPEN AND THE HIGH EXPANSION FOAM IS DISCHARGED.

(FOAM FILL UP TIME (NORMAL CONDITION))


TANK TOP 4TH DECK F.O. PUMP ROOM (P) F.O. PUMP ROOM (S) 3RD DECK I.G.G. ROOM CHEMICAL STORE ENG. STORE No.1 D/G ROOM No.2 D/G ROOM STEERING GEAR ROOM 3 min 5 min 2 min 2 min 9 min 4 min 3 min 3 min 3 min 2 min 3 min 2ND DECK I.G.G. ROOM No.1 F.O. HEATING RM No.2 F.O. HEATING RM LABORATORY BOG PIPE HOOD ENG. WORK SHOP STAIRWAY UPPER DECK I.G.G. ROOM INCINERATOR. ROOM CASING 11 min 6 min 2 min 2 min 2 min 2 min 2 min 2 min 12 min 7 min 2 min 17 min

(CAUTION)
(1) AFTER THE FIRE EXTINGUISHED, THE PROTECTED SPACE SHOULD BE COOLED AND VENTILATED WELL BEFORE ANY CREW ENTERS THERE. (2) IF THE SYSTEM CAN NOT BE OPERATED AUTOMATICALLY, OPERATE MANUALLY AT FOAM TANK ROOM. (3) AFTER USING THE SYSTEM, THE TANK IS TO BE FILLED WITH FOAM CONCENTRATE UP TO THE REQUIRED LEVEL. (4) BEFORE USING THE SYSTEM, FIXED LOCAL APPLICATION FIRE FIGHTING SYSTEM IS TO BE STOPPED.

TO STOP
(1) PUSH THE SYSTEM STOP BUTTON. (2) STOP THE EMERGENCY FIRE PUMP MANUALLY.

YAmATO PROTECT CORPORATION

FOAM TANK

AV2-2 M

DPS PI2 AV1-2 M

P
PS

P DPS

P M AV3-6

STEERING GEAR ROOM


MV2 P DPS P M AV3-7

MV4 AV2-4 M

PI4

P
PS AV2-3 M

DPS PI3 AV1-3 M PROPORTIONER

OPERATING INSTRUCTION FOR YAMATO HIGH-EXPANSION FOAM SYSTEM - DO NOT START EXCEPT FOR FIRE THIS SYSTEM CAN BE OPERATED AUTOMATICALLY FROM THE CONTROL PANEL. HOWEVER, IF THE SYSTEM IS OPERATED MANUALLY, PERFORM FOLLOWING OPERATION.
(PREPARATION) CONFIRM THE VALVE MV1, MV2, MV3, MV4 ARE OPENED.

P
PS P MV3

I.G.G. ROOM
P DPS M AV3-8

FOAM CONCENTRATE PUMP


I.G.G. ROOM
TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-7).

ENGINE ROOM
TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1), (PI2), (PI3) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV1-2), (AV1-3), (AV2-1), (AV2-2), (AV2-3), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVES (AV3-1), (AV3-2), (AV3-3), (AV3-4), (AV3-5), (AV3-7), (AV3-8), (AV3-9), (AV3-10), (AV3-11), (AV3-12) AND (AV3-13).

STEERING GEAR ROOM


TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-6).

F.O. PUMP. ROOM (S)


TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-8).

PUMP START PANEL


MICRO FOG PUMP
SOURCE RUNNING OVER LOAD

F.O. PUMP ROOM (S)


P P DPS M AV3-9

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-6).

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-7).

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-8).
A ~

SOURCE

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV1-2), (AV1-3), (AV2-1), (AV2-2), (AV2-3), (AV2-4), (AV3-1), (AV3-2), (AV3-3), (AV3-4), (AV3-5), (AV3-6), (AV3-7), (AV3-8), (AV3-9), (AV3-10), (AV3-11), (AV3-12), AND (AV3-13).

SPACE HEATER

STOP

START

INCINERATOR ROOM
TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-9).

No.1 D/G ROOM


TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-10).

No.2 D/G ROOM


TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-11).

No.1 F.O. HEATING ROOM


TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-12).

POWER SOURCE

SPACE HEATER ON OFF

MAN

REM

INCINERATOR ROOM
Y P
YAmATO PROTECT CORPORATION

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-9).

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-10).

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-11).

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-12).

P DPS

P M AV3-10

No.2 F.O. HEATING ROOM


TO START
(1) START THE EMERGENCY FIRE PUMP. (2) WHEN THE PRESSURE GAUGE (PI1) SHOWS MORE THAN 0.6MPa, OPEN THE VALVES (AV1-1), (AV2-1), (AV2-4) AND START THE FOAM CONCENTRATE PUMP. (3) WHEN THE PRESSURE GAUGE (PI4) SHOWS MORE THAN 0.7MPa, OPEN THE VALVE (AV3-13).

(FOAM FILL UP TIME (NORMAL CONDITION))


TANK TOP 4TH DECK F.O. PUMP ROOM (P) F.O. PUMP ROOM (S) 3RD DECK I.G.G. ROOM CHEMICAL STORE ENG. STORE No.1 D/G ROOM No.2 D/G ROOM STEERING GEAR ROOM 3 min 5 min 2 min 2 min 9 min 4 min 3 min 3 min 3 min 2 min 3 min 2ND DECK I.G.G. ROOM No.1 F.O. HEATING RM No.2 F.O. HEATING RM LABORATORY BOG PIPE HOOD ENG. WORK SHOP STAIRWAY UPPER DECK I.G.G. ROOM INCINERATOR. ROOM CASING 11 min 6 min 2 min 2 min 2 min 2 min 2 min 2 min 12 min 7 min 2 min 17 min

(CAUTION)
(1) AFTER THE FIRE EXTINGUISHED, THE PROTECTED SPACE SHOULD BE COOLED AND VENTILATED WELL BEFORE ANY CREW ENTERS THERE. (2) IF THE SYSTEM CAN NOT BE OPERATED AUTOMATICALLY, OPERATE MANUALLY AT FOAM TANK ROOM.

No.1 D/G ROOM


300 P DPS FIRE MAIN P DPS
TEST LINE

(3) AFTER USING THE SYSTEM, THE TANK IS TO BE FILLED WITH FOAM CONCENTRATE UP TO THE REQUIRED LEVEL. (4) BEFORE USING THE SYSTEM, FIXED LOCAL APPLICATION FIRE FIGHTING SYSTEM IS TO BE STOPPED.

TO STOP
(1) STOP THE EMERGENCY FIRE PUMP AND FOAM CONCENTRATE PUMP. (2) CLOSE THE VALVES (AV1-1), (AV2-1), (AV2-4) AND (AV3-13).

P M AV3-11

FS

ICAS
S

DPS

P PI1
PS AV1-1 M

AV2-1 M

F.W. TANK
FOAM CONCENTRATE TANK
MV4 AV2-4 M PI4 P PS

MV1 DPS

P PI2
PS AV1-2 M

AV2-2 M

STARTER
POWER SOURCE

No.2 D/G ROOM


P M AV3-12

MV2 DPS

P PI3
PS AV1-3 M

AV2-3 M

FCP

PI5 P MV3

FROM EFP
DPS

P DPS P AV3-1 M

P DPS P AV3-2 M

P DPS P AV3-3 M

P DPS P AV3-4 M

P DPS P AV3-5 M

P DPS P AV3-6 M

P DPS P AV3-7 M

P DPS P AV3-8 M

P DPS P AV3-9 M

P DPS P AV3-10 M

P DPS P AV3-11 M

P DPS P AV3-12 M

No.1 F.O. HEATING ROOM


S

P AV3-13 M

ENGINE RM (S) LOWER

ENGINE RM (S) MIDDLE & UPPER

ENGINE RM (P) LOWER

ENGINE RM (P) MIDDLE & UPPER

ENG. WORK SHOP BOG PIPE HOOD LABORATORY STAIRWAY ENGINE STORE CHEMICAL STORE

I.G.G. ROOM

INCINERATOR RM No.1 D/G RM

No.2 D/G RM

No.2 F.O. HTG RM

F.O. PUMP RM (S) STEERING GEAR RM

No.1 F.O. HTG RM

P PI5

P DPS

P M AV3-13

YAmATO PROTECT CORPORATION

OPERATING INSTRUCTION

No.2 F.O. HEATING ROOM

EM'CY FIRE PUMP

AIR TEST CONNECTION

TEST LINE

10.3.4 Engine Room Local Fire Extinguishing System


Water Fog System Maker : Fresh Water tank : Pump unit No. of sets :

Yamato Protec Corporation 2.0 m3 5.5 m3/h x7.2 Mpa, 15kW x1,800rpm 1set

Operation of the system is activated by the control panel when protected area fire detector heads indicate a fire in a particular area or a manual call point is activated for a particular area. Water fog is only released into the protected space in which there is a fire. in which there is a fire. There are remote activation pushbuttons situated on the control panel in the fire control station. The alarm indicator panel is located in the wheelhouse. The system uses fresh water in order to reduce the risk of corrosion but the lines are dry between the solenoid valves and the spray heads unless the system is actually operating. The fresh water is supplied from the general service fresh water system via supply valve 202VPG, which must always be closed. The water fog unit is located at starboard on 3rd deck near the engine store. The fresh water fog system releases water fog into a space automatically when a fire is detected by the protected area fire detection head(s). It can also be activated by pressing the appropriate local area pushbutton.

Description
Pressurized water forced through atomizer heads will break down into very fine droplets. These droplets have a very effective extinguishing effect on fires, even oil fires. The fine droplets remain suspended in the air and so they do not disturb the oil surface nor do they settle to form a water layer on which burning oil could float. Fine water droplets present a large surface area to the fire and so they exert a cooling effect as the droplets rapidly evaporate. The large droplet concentration and the evaporation have the effect of reducing the local oxygen level. The cooling effect and the reduced local oxygen concentration result in the fire being extinguished.

The fresh water fog fire extinguishing system relies upon the delivery of high pressure water to nozzle heads located at sites of fire risk. Ten areas are protected by the water fog system, these are : No.1 main boiler burners platform No.2 main boiler burners platform No.1 diesel generator engine top No.2 diesel generator engine top I.G.G. burner zone Incinerator burner zone Port F.O. pump room Starboard F.O. pump room Port F.O. heating room Starboard F.O. heating room 2 heads 2 heads 3 heads 3 heads 1 head 1 head 1 head 2 heads 1 head 1 head

Procedure for Setting the Water Fog System for Operation a) Check that the fresh water tank has sufficient water level. (Note : There should always be sufficient fresh water available to cover the largest section for a minimum of 20 minutes.) e) Set the valves as in the following table : Description Position Open Pump suction valve Closed FW supply valve Closed Test and air supply valve Closed Drain valves Operational All supply solenoid valves Ensure that the engine room fire alarm monitoring system switch is set to automatic mode.

Valve

201VPG 202VPG

Each protected space can be released locally either by pushbutton located near each protected area inside engine room or remotely on the control panel in fire control station. The protected areas also are monitored by the fire detection system which will operate the water fog system if a detector head is activated. The protected areas are provided with a number of nozzle heads fitted in the supply pipe for that area. The main supply line to the area has a solenoid operated isolating valve. The solenoid valve is activated by the fire control system when a fire detector senses a fire in the protected area. When the system is released, fresh water from the fresh water tank of 2 m is pumped up to 7.0 MPa and is sprayed from the nozzle. The system can be operated with fresh water stored in the tank for 20 minutes. The fresh water will be refilled from the ship's fresh water service system.
3

f)

g) At the water fog main control panel ensure that the panel power lamp is illuminated. h) The water fog system is now operational. Press the START pushbutton for the spray section for more than 2 sec. when manual starting. The nozzle heads and valves should be checked at intervals in order to detect any leakage. The system is stopped by pressing the STOP pushbutton on the control panel in the fire control room.

10.3.4a

Engine Room Local Fire Extinguishing System


FIRE STATION WHEELHOUSE
LOCAL FIRE FIGHTING SYSTEM CONTROL PANEL

FOR VDR
INERT GAS GENERATOR
PRE ALARM FIRE

No.1 MAIN BLR


PRE ALARM FIRE

No.2 MAIN BLR


PRE ALARM FIRE

No.1 AUX. D/G


PRE ALARM FIRE

No.2 AUX. D/G


PRE ALARM FIRE

START

START

START

START

START

LOCAL FIRE FIGHTING SYSTEM EXTENSION INDICATOR PANEL

INCINERATOR

No.1 FO PUMP RM
PRE ALARM FIRE

No.2 FO PUMP RM
PRE ALARM FIRE

No.1 FO HTG RM
PRE ALARM FIRE

No.2 FO HTG RM
PRE ALARM FIRE

FROM F.W.TK SUC.LINE

PRE ALARM

FIRE

FOR ICAS

SOURCE

ABNORMAL

AUTO

START

START

START

START

START

NO.1 MAIN BLR

NO.2 MAIN BLR

NO.1 AUX. D/G

NO.2 AUX. D/G

INERT GAS GENERATOR

POWER

PUMP ACTIVE

WATER LOW PRESS

WATER TK LOW LEVEL

ABNORMAL

INCINERATOR
LAMP & BUZZER TEST SEC. VALVE CLOSED

NO.1 F.O. PUMP RM

NO.2 F.O. PUMP RM

NO.1 F.O. HTG RM

NO.2 F.O. HTG RM

AUTO

MANUAL

STOP ALARM

BUZZER STOP

STOP (RESET)

BUZZER STOP

LAMP TEST

202VPG

PUMP START PANEL


LAL 940

FS

MICRO FOG PUMP


SOURCE RUNNING OVER LOAD

SOURCE

A ~

LOCAL FIRE FIGHTING SYSTEM - OPERATION MANUAL In case of fire, proceed with following operation. (Manual Operation) SYSTEM START Push "START" switch for the discharge section for more than 2 seconds. "FIRE" lamp for the discharge section is turned on and the mist is discharged to the protected area.

40

2.0m F.W.TK

SYSTEM STOP Push "STOP" switch. "FIRE" lamp for the discharge section is turned off and the mist discharge is stopped. The system is returned to "Standby" mode automatically. CHANGE OF DISCHARGE SECTION Push "START" switch for the desired section while operating one section . The mist spray in operating section stops and the mist spray for new section starts. No intermediate operation of "STOP" switch is necessary for changing the discharge section. NOTE a) Do not operate the switches except for fire or test of the system. b) For the operational test of pump, push "SEC. VALVE CLOSED (PUMP TEST)" at first, then push "START" switch for any section. All section valves are kept closed and the pump is operated returning the discharged water tottally to the fresh water tank. c) Relevant ventilations will stop when the system starts.

SPACE HEATER

STOP

START

SPACE HEATER ON OFF

MAN

REM

P ROTEC

AmATO

Y P

YAMATO PROTECT CORPORATION

NO.1 MAIN BLR


MANUAL OPERATING BOX

STOP

LOCAL FIRE FIGHTING SYSTEM

NO.2 MAIN BLR


MANUAL OPERATING BOX

PS
START

STOP

SOLENOID V.PANEL
M
40
201VPG

LOCAL FIRE FIGHTING SYSTEM

P
40 S

NO.1 AUX. D/G


MANUAL OPERATING BOX

STOP

START

LOCAL FIRE FIGHTING SYSTEM

MANUAL OPERATING BOX

S
START LOCAL FIRE FIGHTING SYSTEM

STOP

INERT GAS GENERATOR


MANUAL OPERATING BOX

STOP

TEST V.
15 SERV.AIR

START

LOCAL FIRE FIGHTING SYSTEM

INCINERATOR
MANUAL OPERATING BOX

STOP

START

S
LOCAL FIRE FIGHTING SYSTEM

No.1 F.O. PUMP ROOM


MANUAL OPERATING BOX

STOP

START

LOCAL FIRE FIGHTING SYSTEM

No.2 F.O. PUMP ROOM


S
MANUAL OPERATING BOX

STOP

START

LOCAL FIRE FIGHTING SYSTEM

No.1 F.O. HEATING ROOM


MANUAL OPERATING BOX

STOP

START

LOCAL FIRE FIGHTING SYSTEM

TO CLEAN DRAIN TK

No.2 F.O. HEATING ROOM


MANUAL OPERATING BOX

STOP

START

LOCAL FIRE FIGHTING SYSTEM

CL OS E

OP EN

CL OS E

OP EN

CL OS E

OP EN

CL OS E

OP EN

CL OS E

OP EN

CL OS E

OP EN

CL OS E

OP EN

PUMP UNIT

NO.2 AUX. D/G


CL OS E
EN OP

CL OS E

OP EN

CL OS E

OP EN

CL OS E

OP EN

CL OS E
EN OP

CL OS E
EN OP

CL OS E
EN OP

CL OS E
EN OP

CL OS E
EN OP

CL OS E
EN OP

CL OS E
EN OP

CL OS E
EN OP

CL OS E
EN OP

10.3.5 Quick Closing Valves & Fire Dampers System


Description
All the outlet valves from the fuel oil and lubricating oil tanks, from which oil could flow to feed a fire, are equipped with air operated quick-closing valves, which are controlled from the fire control station. They are supplied from an air receiver situated in the quick-closing valve bottle cabinet, also located in the fire control station. The reservoir is supplied, at a pressure of 0.85 MPa, directly from the service air main system. The inlet valve 161VPE to the quick-closing valve air receiver is locked open. The quick-closing valve air receiver is fitted with a low pressure alarm switch. The tanks are grouped into four systems, with one three-way cock operating each system. In normal operation the supply line to each group of tank valves is vented to atmosphere, but when the cock is turned, air is supplied to pistons, which collapse the bridge of each valve in that group, thus causing the valve to close. C The valves are reset by venting the air supply and operating the valve hand wheel in a closed direction to reset the bridge mechanism and then opening the valve in the normal way. The quick closing valve fitted on the emergency generator gas oil tank and the generator engine diesel oil service tank is operated by a directly so as to enable to feed the fuel to emergency diesel generator or main diesel generator in the event of a fire. D Oil Tank Quick-Closing Valves Group A B Tank Diesel generator DO service tank to diesel generator Diesel generator DO service tank to boiler burner Starboard DO storage tank suction Low sulphur FO tank suction No.1 FO settling tanks suction Starboard FO side tank suction Generator engine LO renovating tank suction Generator engine LO storage tank suction LO renovating tank LO storage tank suction LO gravity tank for main turbine Aux. turbine LO renovating tank suction Aux. turbine LO storage tank suction Incinerator DO service tank suction Waste oil settling tank suction FO additive tank suction IGG gas oil tank Port DO storage tank suction No.2 FO settling tanks suction Port FO side tank suction Emergency generator gas oil service tank suction Valve
701, 711VPL 232, 233VPL 231VPL 204VPL 001, 002VPL 201VPL 152VPK 153VPK 125VPK 123VPK 015VPK 425VPK 423VPK 363VPL 361, 362VPL 261VPL 221VPL 223VPL 101, 102VPL 202VPL 401VPL

Group E

F G

H I J

Applications Engine room supply ventilation fans dampers Engine room exhaust fans dampers Workshop welding space exhaust fan damper Funnel exhaust fire damper No.1 D/G room fire dampers No.2 D/G room fire dampers Starboard FO pump room fire dampers Port FO pump room fire dampers Starboard FO heating room fire dampers Port FO heating room fire dampers Inert gas room fire dampers Incinerator room fire dampers Machinery control room fire dampers Switchboard rooms fire dampers Transfer rooms fire dampers Steering gear room supply ventilation fan damper Emergency generator room air suction damper Emergency generator room exhaust fan damper Emergency generator exhaust duct damper Paint store exhaust fan damper Cargo machinery room exhaust fan damper Cargo compressor motor room ventilation fan damper

CAUTION
Some tanks such as lubricating oil daily use tanks do not have quick closing apparatus fitted. This is because they are normally closed and only opened for short periods when required. It is important to ensure that these are always closed when not in use.

Ventilation Fire Dampers and Emergency Stops Ventilation dampers are installed at various locations in order to shut off the flow of air which would feed a fire in a particular compartment. The dampers are to be closed in the event of a fire and ventilation fans shut off. In the event of a fire in a space where CO2 is used ventilation is automatically shut off when the system is initiated. Ventilation systems in the engine room and cargo machinery and motor rooms are provided with fan stops and fire dampers. Fans and ventilation dampers may be stopped locally or remotely as required depending upon the nature of the incident. The fire dampers for those compartments are equipped with air operated cylinders, which are controlled by the compressed air from the air receiver that is commonly used with the quick-closing valve operation. The dampers are grouped into six systems, with one three-way cock operating each system and a solenoid three-way cock for each compartment. In normal operation, the supply line to each group of tank valves is fed to the cylinders, but when the cock is turned, air is vented to atmosphere from cylinders, and then dampers are closed by the counter weight fitted to the lever for damper operation. The dampers are reset by supplying the air from the fire station.

The fire control station emergency panel has pushbuttons to stop the following : Boiler forced draft fans Supply and exhaust fans Lubricating oil pumps Fuel oil pumps Cargo machinery and motor rooms supply and exhaust fans In the fire control station there are emergency stop panels which contain stops for fans and fire dampers in the engine room and cargo machinery rooms, together with stops for machinery which might aggravate a fire situation. Within the accommodation fire doors provide protection and these must be closed in the event of a fire. The doors are of the self-closing type and are kept open by means of magnetic catches which are released locally or remotely from the bridge panel in the event of a fire.

10.3.5a Quick Closing Valves & Fire Dampers System


FIRE STATION
COMP.MOTOR RM SUPPLY FAN

J I H F D

S S

EMERG.GEN.RM

CARGO MACH.RM EXH.FAN PAINT STORE EXH..FAN E/G RM DAMPER

P
S S

PAL 755

AIR RESERV.
161VPE

401VPL

E/G DO SERV. TK STEER.GEAR RM SUPPLY.FAN

E
S S S S S S S S S S S S S

NO.4 SUPPLY VENT FAN NO.3 SUPPLY VENT FAN NO.2 SUPPLY VENT FAN NO.1 SUPPLY VENT FAN NO.2 EXH.VENT FAN INCINERATOR D.O. SERV. TK W.O.SETT.TK NO.2 NO.1 F.O. ADD.TK NO.1 EXH.VENT FAN W/S WELD.SP EXH.FAN FUNNEL EXH.DAMPER
363VPL 362VPL 361VPL 261VPL

NO.1 D/G RM NO.2 D/G RM PURIF.RM EXH.FAN F.O.PUMP RM (S) IGG RM INCINERATOR RM MACH.CONT.RM NO.1/2 SWICHBOARD RM NO.1 / 2 TRANS.RM FROM G.S. AIR

D.O. STOR. TK (P)

IGG GAS OIL TK

F.O. SIDE TK (P)

No.2 F.O. SETT. TK

F.O.HEATING RM (P) F.O.PUMP RM (P) F.O.HEATING RM (S)

223VPL

221VPL

202VPL

101VPL

102VPL

C A B

711VPL

233VPL

701VPL

232VPL

231VPL

204VPL

201VPL

001VPL

002VPL

425VPK

423VPK

152VPK

153VPK

125VPK

123VPK

015VPK

NO.2 GEN. ENG. NO.1 GEN. ENG. D.O. SERV. TK D.O. SERV. TK

D.O. STOR. TK (S)

LOW SULPHER F.O. TK

F.O. SIDE TK (S)

NO.1 F.O. SETT. TK

AUX. T. L.O. RENOV. TK

AUX. T. L.O. STOR. TK

GEN.. ENG. L.O. GEN.. ENG. L.O. L.O. RENOV. TK STOR. TK RENOV. TK

L.O. STOR. TK

L.O. GRAV. TK

25

Vous aimerez peut-être aussi