MOM between M/s APL & M/s Alstom

M/s APL M/s Alstom


M/s APL

Date: - 24-08-12
M/s

Mr. M.S.Pillai Sterling & Wilson Mr. Sanjay Gulati Mr. Mr.ParsuramVM Mr. Madan Kumar Biswas Mr. Gunanidhi Behera

Mr. Anoar Ali Mr. Ganesh Thakur P.K.Tiwari Mr. Sanjay

Following points discussed/Confirmed during review meeting with M/s ALSTOM at Project site Chandwa. Phase-I 1- 400kV Switchyard
a. Burnt oil pit will be completed by

10th 10th

Sep Sep 30th 30th

2012
b. The completion of leveling of 400KV switch yard -

2012
c. Gravel spreading in switchyard will be completed by -

Sep 2012
d. The road work of switchyard will be completed by

Sep 2012
e. M/s Alstom has agreed to check the source of gravel with M/s

APL quality representative and after certification of the quality, the gravel will be spreading in 400kv switch yard.
f. Electrical works of switch yard will be completed &

The same will be ready for charging by 2012

15th

Sep

i.

400KV Dia-I will be ready for charging by 2012 400KV Dia-II will be ready for charging by 2012

05th 15th 15th

Sep Sep Sep

ii.

iii.

400KV Dia-III will be ready for charging by 2012

g. M/s APL informed that, regarding metering panels it will be conformed after discussion with PGCIL & the same will be informed to M/s Alstom.

2- 33kV Switchyard
a. The 33kV switchyard will be completed in all respect

&

the

same will be ready for charging by 31st Aug 2012

3- Payment related issues


a. M/s Alstom requested M/s APL to forward the 52 Lakhs hold

civil bill to accounts by 31st Aug 2012, M/s Alstom agreed to submit the required documents before 29th Aug 2012.
b. M/s Alstom requested M/s APL to certify the hold 5% civil work

by 31st Aug 2012 & same forwarded to accounts, M/s APL informed that it will be certified after completion of civil works of 400kV switchyard in all respect. Phase-II 1- Material Inspection
a. M/s Alstom requested M/s APL to inspect CB and CVT by 28th to

29th Aug 2012, APL agreed for the same.

b. M/s Alstom requested to APL for clearance of starting the work

in Phase-2 from 1st Sep 2012. M/s APL informed that, we will revert back shortly.