Vous êtes sur la page 1sur 17

Sequence of work for Commercial Building (Civil Works)

For Foundation
Site Mobilization Fencing Perimeter Site Project Site Surveying Conduct Soil Test Piling -Installation of Steel -Concrete pouring using Treamie Pipe Pile Chipping Excavation for Raft Foundation - Shoring For Support in Excavation - Dewatering Formworks Installation and Support for: -Raft Foundation Concrete pouring (BLINDING CONCRETE) Steel Installation for Raft Foundation Concrete Pouring For Raft Foundation Note: Provide all dowels and sleeves for Structural and MEP.

Going to Basement 1
Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Ramps -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Ramps -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Ramps -Wall -Stairs Water Curing A Day after Concrete Pouring until achieving the required strength. Stripping and dismantle of Formworks after achieving the required strength.

Going to Ground Floor


Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Ramps -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Ramps -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Ramps -Wall -Stairs Water Curing A Day after Concrete Pouring until achieving the required strength. Stripping and dismantle of Formworks after achieving the required strength.

Going to Mezzanine Floor


Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Masonry Works -Blocks Laying -Wall Plastering -Tiles Fixing/Setting (for wall, flooring and Bathrooms) Water Curing - A Day after Concrete Pouring until achieving the required strength. - Stripping and dismantle of Formworks after achieving the required strength.

Going to First Floor


Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Masonry Works -Blocks Laying -Wall Plastering -Tiles Fixing/Setting (for wall, flooring and Bathrooms) Water Curing - A Day after Concrete Pouring until achieving the required strength. - Stripping and dismantle of Formworks after achieving the required strength.

Going to Second Floor


Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Masonry Works -Blocks Laying -Wall Plastering -Tiles Fixing/Setting (for wall, flooring and Bathrooms) Water Curing - A Day after Concrete Pouring until achieving the required strength. - Stripping and dismantle of Formworks after achieving the required strength.

Going to Third Floor


Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Masonry Works -Blocks Laying -Wall Plastering -Tiles Fixing/Setting (for wall, flooring and Bathrooms) Water Curing - A Day after Concrete Pouring until achieving the required strength. - Stripping and dismantle of Formworks after achieving the required strength.

Going to Fourth Floor


Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Masonry Works -Blocks Laying -Wall Plastering -Tiles Fixing/Setting (for wall, flooring and Bathrooms) Water Curing - A Day after Concrete Pouring until achieving the required strength. - Stripping and dismantle of Formworks after achieving the required strength.

Going to Terrace Floor


Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Masonry Works -Blocks Laying -Wall Plastering -Tiles Fixing/Setting (for wall, flooring and Bathrooms) Water Curing - A Day after Concrete Pouring until achieving the required strength. - Stripping and dismantle of Formworks after achieving the required strength.

Going to ROOF
Formworks installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Steel installations for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Concrete Pouring for: -Columns -Beams -Slabs -Shear Wall -Wall -Stairs Masonry Works -Blocks Laying -Wall Plastering -Tiles Fixing/Setting (for wall, flooring and Bathrooms) Water Curing - A Day after Concrete Pouring until achieving the required strength. - Stripping and dismantle of Formworks after achieving the required strength. - Finished all remaining works prior to finishing.

Vous aimerez peut-être aussi