Cost Summary Site Development Cost Coffin Elementary School Brunswick Junior High School Total Additional costs:

Bus garage Energy code (Coffin) Energy code (BJHS) Total with additional costs PDT Architects' recommendation Alternatives: New 660-capacity school at Coffin New 600-capacity school at J.A. Source: PDT Architects

Light Touch: Major Renovation: 3073064 13743627 10529357 27346048 3073064 17288191 13106051 33467306

2503921

2503921 872360 1459080 38302667

29849969

22575930 24096930