S/N 1 2 3 4 5 6
DESCRIPTION OF WORK Works documentation and procurement of materials Materials preparation, fabrication and construction of tanks Test, inspection, preparation for painting Painting and finishing works Transportation to CBN site and installation at site Pressure testing and acceptance by client's representative
WEEK 1 2 3