Water Reticulation Works for The Proposed Kampung Jepak Resettlement Scheme, Phase II, Bintulu Division

Summary of Cost Estimate


Item 1 1.1 Description GENERAL AND PRELIMINARY Provide Performance Bond or Bank Guarantee in accordance with Form of Contract Provide Insurance in accordance with Form of Contract C.I.D.B. s Requirements Provide Stamp Duty Mobilization and Demobilization Mobilization of personnel, constructional plant and equipment. Demobilization of personal, constructional plant and equipment. Provide and maintain Contractors site office and site camp. Provide and maintain S.O.'s site office including all furniture, equipment and fitting. Provide and maintain site security including watching, lighting, guarding and other precautions for the Camp Site and S.O.s premises. Provide and maintain one (1) unit handphone for S.O.'s site staff. 10 LS 3,000.00 Quantity Unit Rate Amount (RM)

1.2

LS

3,000.00

1.3 1.4 1.4 a) b)

LS LS

2,500.00 1,288.84

LS LS

10,000.00 2,000.00

1.5

month

2,000.00

20,000.00

1.6

10

month

2,000.00

20,000.00

1.7

10

month

500.00

5,000.00

1.9

10

month

350.00

3,500.00

1.10 Provide for testing by approved laboratory for carry out field tests and laboratory test as specified. 1.11 Provide and maintain one (1) set of First Aid facilities at site office. 1.12 Provide and maintain all necessary temporary road diversion or detour and maintain trafficability of existing tracks affected by construction works. 1.13 Provide necessary coordination for the relocation, protection and temporary diversion of public utility services. 1.14 Provide for work programme, progress report, testing report, QA/AC report and taking progress photographs of works as specified or as directed by S.O. SUB-TOTAL BROUGHT FORWARD 10

LS

3,000.00

month

100.00

1,000.00

LS

1,500.00

LS

1,000.00

LS

2,500.00

RM

79,288.84 79,288.84

CE / 1

Water Reticulation Works for The Proposed Kampung Jepak Resettlement Scheme, Phase II, Bintulu Division
Summary of Cost Estimate
Item Description Quantity Unit LS LS RM Rate Amount (RM) 2,000.00 2,000.00 83,288.84

1.15 Supply Contractors As-Built Drawings 1.16 Clearing up site on completion. Total Cost For General and Preliminaries

CE / 2

Water Reticulation Works for The Proposed Kampung Jepak Resettlement Scheme, Phase II, Bintulu Division
Summary of Cost Estimate
Item 2 2.1 Description WATER RETICULATION SYSTEM Quantity Unit Rate Amount (RM)

Clear all bushes and shrubs and fell, remove and dispose of the site all trees, stumps and roots along the pipeline route as directed.

15,500

m2

1.50

23,250.00

2.2

Supply, deliver and storage of 63mm O.D. HDPE pipe (PN12.5). Supply, deliver and storage of 90mm O.D. HDPE pipe (PN10). Ditto - 160mm O.D. HDPE Pipe Ditto - 225mm O.D. HDPE Pipe Supply, deliver and storage of 150mm D.I pipe. Ditto - 200mm D.I. pipe Excavation of trench to average depth of 750mm, lay, join using electrofusion couplers, with G.I. pipe sleeving, backfill using material as specified, compact in 225mm per layer, disposal of surplus, reinstate of pavement for 63mm O.D. diameter HDPE pipe (PN12.5) complete with bends, tees, studs-end etc. Excavation of trench to average depth of 750mm, lay, join using electrofusion couplers, with G.I. pipe sleeving, backfill using material as specified, compact in 225mm per layer, disposal of surplus, reinstate of pavement for 90mm O.D. diameter HDPE pipe (PN10) complete with bends, tees, stubs-end etc.

1,220

9.38

11,443.60

2.3

590

19.28

11,375.20

2.4 2.5 2.6 2.7 2.8

3,710 90 230 800 1,220

m m m m m

50.00 99.00 135.00 210.00 32.00

185,500.00 8,910.00 31,050.00 168,000.00 39,040.00

2.9

590

32.00

18,880.00

2.10 Excavation of trench to average depth of 1m, lay, join using electrofusion couplers, backfill using material as specified, disposal of surplus and compact in 300mm per layer for 160mm O.D. diameter HDPE pipe (PN10) complete with bends, tees, stubs-end etc.

3,925

36.00

141,300.00

2.11 Ditto - 225mm O.D. diameter HDPE pipe (PN10) 2.12 Excavation of trench to average depth of 1m, lay, join, backfill using material as specified, compact in 300mm per layer, disposal of surplus and reinstate of pavement for 150mm diameter D.I. pipe at road crossing, complete with bends, tees, polyethylene sleeve etc.

90 230

m m

37.00 48.00

3,330.00 11,040.00

SUB-TOTAL

RM

653,118.80

CE / 3

Water Reticulation Works for The Proposed Kampung Jepak Resettlement Scheme, Phase II, Bintulu Division
Summary of Cost Estimate
Item Description BROUGHT FORWARD 2.13 Excavation of trench to average depth of 1m, lay, join, backfill using material as specified, compact in 300mm per layer, disposal of surplus and reinstate of pavement for 200mm diameter D.I. pipe, complete with bends, tees, polyethylene sleeve etc. 850 m 48.00 Quantity Unit Rate Amount (RM) 653,118.80 40,800.00

2.14 Supply, deliver and install of 150mm diameter Ductile Iron pipe, polyethylene sleeve, bend, fittings etc to form up and down culvert and/or drain crossing as per drawing and specification. 2.15 Ditto - 200mm diameter Ductile Iron pipe, bend, fittings etc 2.16 Supply, deliver and installation of the following including reinforced concrete works, precast concrete chambers, surface box etc as per drawings and specification. (Piling measured separately) a) 150mm diameter Sluice Valves b) 200mm diameter Sluice Valves c) Pillar Hydrants corresponding to all pipe sizes. d) Washout corresponding to all pipe sizes. 2.17 Supply, deliver and installation of 25mm single air valve onto 150mm diameter Ductile Iron Pipe. 2.18 Ditto - 200mm diameter Ductile Iron Pipe. 2.19 Construction and completion of R.C thrust blocks as per drawings and specification. (Piling measured separately) 2.20 Supply, deliver and installation of precast concrete marker posts including painting as per drawings and specification. 2.21 Testing

18

No.

4,500.00

81,000.00

No.

6,000.00

24,000.00

23 8 49 1 18

No. No. No. No. No.

1,500.00 2,200.00 2,500.00 1,900.00 250.00

34,500.00 17,600.00 122,500.00 1,900.00 4,500.00

4 90

No. No.

350.00 350.00

1,400.00 31,500.00

160

No.

35.00

5,600.00

and commissioning, flushing and chlorination in accordance with the specification, including coordination with personnels from LAKU and BOMBA to witness the testing. (Cost of supplying water for the above shall deemed to be inclusive).

LS

2,000.00

Total Cost For Water Reticulation System

RM

1,020,418.80

CE / 3

Water Reticulation Works for The Proposed Kampung Jepak Resettlement Scheme, Phase II, Bintulu Division
Summary of Cost Estimate Item
3 3.1

Description
PILING WORKS (PROVISIONAL QUANTITIES) Supply, deliver, handle and pitch of 100mm dia. x 5.4m bakau pile, 638 Nos @ RM 15.00 per No.

Quantity

Unit

Rate (RM)

Total (RM)

638

No.

15.00

9,570.00

3.2

Drive only 100mm dia. x 5.4m bakau piles using approved drop hammer, 3,445.2m @ RM 3.00 per m. Supply, deliver and install 4mm thk, 75mm diameter x 400mm long, mild steel cylindrical sleeve with 12mm diameter MS bar strut weld at centre of sleeve as bakau pile joint, 319 Nos. @ RM 18.00 /No.

3,445.2

3.00

10,335.60

3.3

319

no

18.00

5,742.00

3.4

Cut off bakau pile head to the required level, 319 Nos. @ RM 1.50 per no.

319

no

1.50

478.50

Total Cost For Piling Works

RM

26,126.10

CE / 5

Water Reticulation Works for The Proposed Kampung Jepak Resettlement Scheme, Phase II, Bintulu Division
Grand Summary of Cost Estimate

ITEM 1 2 3

DESCRIPTION GENERAL AND PRELIMINARY WATER RETICULATION SYSTEM PILING WORKS (PROVISIONAL QUANTITIES) TOTAL CARRIED TO THE FORM OF TENDER

PAGE NO. CE/1-2 CE/3-4 CE/5 RM

AMOUNT (RM) 83,288.84 1,020,418.80 26,126.10 1,129,833.74

Amount in words : Ringgit Malaysia

Authorized Signature and Company Chop Signatory Name I. C. No. Position Firm's Address

: : : : :

Tel. No. Fax. No. Date

: : :

CE / 6