Vous êtes sur la page 1sur 160

Page no 1

Name of work : Construction of IBRAHIM MEDICAL COLLEGE at Darussalam, Mirpur, Dhaka. Sub Head : Construction of Academic Building with ancillary works.
Part A : Civil construction work of Academic Building. 1 Layout and marking for earthwork in excavation in foundation accepted by the Engineer. ( Plinth area of the structure (CE 5.a ) shall be considered for measurement ). 02.1.1 125 '- 0 " X 205 ' -0 " = 25625.00 sft @ Tk 7.00 / sqm = TK = 2380.62 sqm 2 (CE 5 ) Earth work in excavation in all kinds of soil for foundation trenches in/c. layout, providing center lines, local benchmark pillars, leveling, ramming and preparing the base, fixing bamboo spikes & marking layout with chalk powder, providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning the excavated earth at a safe distance of out of the area enclosed by the layout etc. all complete and accepted by the Engineer, subject to submit method statement of carrying out excavation work to the Engineer for approval. However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under the contract. Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead : In medium stiff clayey soil. area of excavation = 125 '- 0 " upto 1.5 mm depth 25625.00 X 205 ' 0 " X 5 ' - 0" = 25625.00 sft = 128125 cft = 3628.575 cum Marked A @ Tk 46.00 / cum = TK 1.669 lac

0.167 lac

CE 5 c 02.1.3

CE 5 f 02.1.6

Extra Rate for each additional 0.5 meter depth exceeding 1.5 meter
1.50 m to 2.0 m depth

25625.00 25625.00

X 1 ' - 8" X 1 ' - 6"

= 42793.75 cft = 1211.944 cum = 38437.5 cft = 1088.573 cum 170918.8 cft )

@ Tk @ Tk

53.00 60.00

/ cum = TK / cum = TK

0.642 lac 0.653 lac

1.50 m to 2.0 m depth

( Total earth work =

3(A) Bailing out of water caused by inundation or rain, by pump from foundation trenches. (CE 6a ) = 100 hours 2.2

@ Tk

178.00 / hour = TK

0.178 lac

3(B) Supplying wooden ballah having an average diameter not less than 150 mm with a minimum end diameter of 100 (CE 6c ) mm for retaining purpose and driving to a depth as per design and drawing by any method including all arrangements 2.4 for staging, hoisting, carrying etc. complete and accepted by the Engineer. = 202 rm @ Tk 252.00 / rm = TK 0.509 lac

3(C) Palisding work by supplying bitumen drum sheet walling tied with 20 BWG G.I. Wire fixing the same with already (CE 6d ) driven borrak bamboo posts with half split borrak bamboo runners @ 450 c/c horizontally with iron nails, G.I wire etc. All 2.5 complete and accepted by the Engineer. ( Rate is excluding the cost of bamboo post ) 250 '- 0 " 410 '- 0 " X X 8 ' -2 " 8 ' -2 " = 2041.67 sft = 3349.70 sft = 5391.37 sft = 500.87 sqm

@ Tk

390.00 / sqm = TK

1.953 lac

4 One layer of brick flat soling in foundation or in floor with 1st class or picked jhama bricks in/c preparation of bed and CE 11 a filling the interstices with local sand, leveling in/c the supply of water, electricity and other charges and costs of tools and 3.1 plants etc. all complete and accepted by the Engineer. 125 '- 0 " X 205 ' -0 " deduction : Pile area 850 X 1'- 2" X 1' - 2" = = = = 25625.00 1157.606 24467.39 2273.08 sft sft sft sqm

( Marked B ) @ Tk 162.00 / sqm = TK

3.682 lac

Page no 2

5 Mass concrete (1:3:6) in foundation with cement, sand (F.M.1.2) and picked jhama chips including breaking chips, CE 12.a.i screening, mixing, laying, compacting to levels and curing for at least 7 days in/c the supply of water, electricity and other charges and costs of tools and plants etc. all complete and accepted by the Engineer. 3.4.1 Basement lift side 30 '- 0 " X 23 ' -0 " 2X Add , Area same as item 4 Marked "B" Total = 1380.00 sft = 24467.39 sft = 25847.39 sft = 6461.85 cft = 183.00 cum

0 '- 3 " @ Tk 3907.00 /cum = TK 7.150 lac

6 CE 58

Supplying, best quality pliable, cold applied pre-formed self adhesive rubberized/ bituminous water proofing membrane of approved brand / origin / manufacturer from an authorized local agent or manufacturer having minimum thickness 1.5 mm, lined with 2 ply cross laminated high density polyethylene film performances and properties all conforming to ASTM standards and laying, placing, fixing on made up firm and dry surfaces free from hollows, sharp protrusions, contaminates etc. laid over-lap by at least 75 mm along the edges and 125 mm at ends ensuring good initial bond with the surfaces all complete under the strict accordance with the manufacturer recommendations and instructions providing all safety provisions in all respects and accepted by the Engineer. Water proofing membrane on external surface of vertical or inclined wall ( excluding cost of back fill / brick wall on back/ plaster when membrane laid on back wall and concrete cast against membrane which to be paid as per corresponding items ) Basement wall 2 2 2 1 X 190 ' X 60 ' X 3.1 X X 60 ' 0 0 25 0 " " ' " = = = = = = = = = = = = = = = = = = = 380.00 120.00 157.00 60.00 717.00 717.00 7170.00 1260.00 174.00 516.00 843.33 167.50 76.00 124.00 3160.83 3160.83 11853.13 19023.13 1767.29 rft rft rft rft rft X sft

(A) CE 58a 07.21.1

Ramp wall

10

sft

Mark D Sides of pile cap PC 12 PC 7 PC 10 PC 14 PC 3 PC 9 PC 6 28 6 12 20 10 2 4 X X X X X X X 45 29 43 42 16 38 31 ' ' ' ' ' ' ' 0 0 0 2 9 0 0 " " " " " " "

Mark E Total

rft rft rft rft rft rft rft rft rft X 3' - 9" sft

sqm

@ Tk 721.00

/sqm = TK

12.742 lac

(B) Water proofing membrane on made up surface below the floor or below the horizontal surfaces below grades with (CE 58b ) temporary protective cover using polysterene / 1.5 " thick sand - cement mortar in 4 : 1 / or by equally effective 07.21.2 alternative ( rate is excluding the cost of protective cover which to be paid as per corresponding items) quantity same as mark B of Item 4 = 24467.39 sft = 2273.08 sqm
43490.52

@ Tk

648.00 / sqm = TK

14.730 lac 4040.368

7(A) Sand filling in foundation trenches and plinth with coarse sand having min. F.M. 0.80 in 150 mm layers including (CE 8a ) leveling, watering and compaction to specified percent by ramming each layer up to finished level as per design 02.10.1 supplied by the design office only etc. all complete and accepted by the Engineer. Below basement slab & between pile caps quantity same as mark B of Item 4 Deduct, pile cap From Item 10(A)

= = = =

24467.39 8424.83 16042.56 60159.60

sft sft sft cft

3 '- 9 "

Page no 3

sides of Basement wall upto 5' depth 2 X 190 ' - 0 " = 2 X 60 ' - 0 " = 2 X 3.14 X 25 ' = mark A = = = Total = = 380.00 120.00 157.00 657.00 657.00 8212.5 68372.10 1936.34 rft rft rft rft X 5 ' X 2' - 6" cft cft cft cum 406.00 / cum = TK 7.862 lac

@ Tk

7(B) Sand filling in foundation trenches and plinth with coarse sand having min. F.M. 1.20 in 150 mm layers including (CE 8b ) leveling, watering and compaction to specified percent by ramming each layer up to finished level as per design 02.10.2 supplied by the design office only etc. all complete and accepted by the Engineer. Basement lift side 30 ' - 0 " X 25 ' -0 " = 1500.00 sft = 1500.00 sft = 2250.00 cft = 657.00 rft = 657.00 rft X = 6570.00 cft Total 8 (A) CE 9 a 02.13. = 8820.00 cft = 249.79 cum

1 '- 6 "

sides of Basement wall from 5' depth to GL quantity same as mark A of Item 5

4 ' X 2.5 '

@ Tk

652.00 / cum = TK

1.629 lac

Earth filling in foundation trenches and plinth in 150 mm layer with earth available within 90 m of the building site, including carrying, watering, leveling , dressing and compacting to a specified percent each layer up to finished level etc. all complete and accepted by the Engineer. quantity same as item 2 = ######## cft = 4840.52 cum

@ Tk

55.00

/ cum = TK

2.662 lac

Earth filling in foundation trenches and plinth in 150 mm layers with carted earth carried by truck or any other means 8(B) CE 10 a loading & unloading at both ends in/c. leveling, watering and consolidating including local carriage each layer up to 02.15.1 finished level. in/c cost of water & test (carried from beyond 300 m) etc. all complete and accepted by the Engineer. 1 X 340 ' - 2 " X 1 X 190 ' - 0 " X 176 ' 110 ' 0 " = 59869.33 0 " = 20900.00 = 38969.33 = 241220.17 sft sft sft X 6.19 ' cft

deduct , building area

deduct, earth obtained from earth work in excavation net volume

= 170918.75 cft = = 70301.42 cft 1990.98 cum @ Tk 304.00 /cum = TK 6.053 lac

Sub Total

62.281 lac

Page no 4

Rate 2008

2011

Total 2008

2011

Increase 06 to 08

Increase 08 to 11

7.00

9.00

0.167

0.214

0.0%

28.6%

59.00

79.00

2.141

2.867

28.3%

33.9%

69.00

92.00

0.836

1.115

30.2%

33.3%

69.00

92.00

0.751

1.001

15.0%

33.3%

237.00

271.00

0.237

0.271

33.1%

14.3%

344.00

430.00

0.695

0.869

36.5%

25.0%

417.00

475.00

2.089

2.379

6.9%

13.9%

234.00

317.00

5.319

7.206

44.4%

35.5%

Page no 5

4,749.00

5641.00

8.691

10.323

21.6%

18.8%

734.00

798.00

12.972

14.103

1.8%

8.7%

655.00

712.00

14.889

16.184

1.1%

8.7%

Page no 6

476.00

549.00

9.217

10.630

17.2%

15.3%

776.00

857.00

1.938

2.141

19.0%

10.4%

70.00

93.00

3.388

4.502

27.3%

32.9%

264.00

393.00

5.256

7.825

-13.2%

48.9%

68.586 81.6296045

10.1%

19.0%

Page No 4 B.F Tk 62.281 lac

9. (A)

09.09.3

(CE 70 c )

Pre-cast driven pile with reinforced cement concrete works with minimum cement content relates to mix ratio (1.1.5:3) having minimum fcr = 30 Mpa, and satisfying a specified compressive strength f'c = 25 Mpa at 28 days on standard cylinders as per standard practice of Code ACI / BNBC / ASTM & cement conforming to BDS EN - 197 - 1 - CEM 1 ( 32.5 to 52.5 N ) ASTM -C 150 Type - I, best quality coarse sand (F.M.2.2), 20 mm down well graded stone chips conforming to ASTM C - 33 , mixing in standard mixture machine and fed by standard measuring boxes, in/c cost of breaking chips, screening through proper sieves, cleaning and washing, centering and shuttering with M.S sheet, M.S angle, F.I bar, nuts & bolts, preparation of bed, laying polythene, placing of reinforcement cage in position, casting, compacting by vibrators and tapered rods, curing for 28 days etc. in/c cost of water, electricity & other charges, providing pile shoe as per design & drawing, driving the pile up to the design depth as per standard practice or specified method providing head cushion, all equipments including mobilization, demobilization & hire charge of driving set, labour, shampering, test of materials & concrete etc. all complete as per design, drawing and accepted by the Engineer. (rate is excluding the cost of reinforcement and its fabrication , binding, welding and placing and driving pile).

14" X 14" size pre cast pile ( 1:1.5:3 ) with stone chips 850 X ( Total volume of RCC in pile =
9. (B)
CE 70 d

45 ' -

0" = =

38250.00 rft 11661.59 rm @ TK

885.00 / r m cft )

= TK 103.205 lac

14 X 14 X 45 X 850 / 144 cft =

52062.50

Pile shoe as per design and drawing

09.09.4
9. (C)
(CE 72a )

850.00 no @ TK

1444.00 each

12.274 lac

Mobilization and demobilization of automatic diesel hammer mounted pre-cast pile driving complete rig set

09.14.
9. (D)
(CE 72d )

2 set @ TK

161634.00 / set

= TK

3.233 lac

09.17.

Driving 14" X 14" size pre-cast pile with automatic rig fitted with automatic diesel hammer . Before commencing driving operation by rig fitted with automatic diesel operated hammer, contractor shall submit method statement for carrying the operation including sequence of driving to the Engineer for approval. However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under contract.

=
9. (E) (CE 68 )

11661.59 rm @ TK

458.00

/ rm

53.410 lac

09.6.

Labour for breaking head of hardened cast in situ bored pile/pre-cast pile up to a required length by any means but without damaging the rest and removing the dismantled materials such as concrete to a safe distance including scraps and cleaning concrete from steel/M.S. rods, straightening & bending of pile bars, preparation and making platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and dressing the situ and clearing the bed etc. complete in all respect and accepted by the Engineer. (Measurement will be given for the actual pile head volume to be broken).

850 X

3 ' X 14 " X 14 " = =

3470.83 cft 98.30 cum @ TK

1688.00 / cum

= TK

1.659 lac

9 (F) (CE 69 )

09.7.

Conducting static load test for the cast in situ/pre-cast pile providing required scaffolding, bracing, jacks, pressure test gauge, loading unloading loads, Kent ledge and other plants and equipment including staging, mobilization, demobilization, hire charge, gunny bags & sand and filling sacs/gunny bags for loading, recording readings & preparation of results in standard forms & other incidental charges as per standard practice and procedures in/c submission of load test report, furnishing all graph and chart etc. complete in all respects approved and accepted by the Engineer. Before commencing load test, contractor shall submit method statement for conducting load test to the Engineer for approval. However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under contract

09.7.2 09.7.3 09.8.2

For 75 tonne load For 125 tonne load

= = =

2 test @ TK 2 test @ TK 30.00 tonne @ TK

52397.00 / test 78740.00 / test 500.00/ tonne Sub Total

= TK = TK = TK

1.048 lac 1.575 lac 0.150 lac 238.684 lac

For intermediate loading from 75 tonne to 125 tonne for each additiional tonne

Page No 5

Rate 2008 2011

Total 2008

2011

Increase Increase 06 to 08 08 to 11

BF 1,032.00 1277.00

68.586 120.348

81.629605 148.918 16.61% 23.74%

1,924.00

2191.00

16.354

18.624

33.24%

13.88%

106,963.00

117704.00

2.139

2.354

-33.82%

10.04%

571.00

633.00

66.588

73.818

24.67%

10.86%

2,318.00

2950.00

2.279

2.900

37.32%

27.26%

63,628.00 96,222.00

84508.00 117936.00

1.273 1.924

1.690 2.359

21.43% 22.20%

32.82% 22.57%

650.00 Sub Total

881.93

0.195 279.685

0.265 332.55666

30.00% 17.18

35.68% 18.90%

Page No 5 BF 238.684 lac

10
CE 53

07.6.

Reinforced cement concrete works using steel shutter with minimum cement content relates to mix ratio (1.1.5:3) having minimum fcr = 30 Mpa, and satisfying a specified compressive strength f'c = 25 Mpa at 28 days on standard cylinders as per standard practice of Code ACI / BNBC / ASTM & cement conforming to BDS EN - 197 - 1 - CEM 1 ( 32.5 to 52.5 N ) ASTM -C 150 Type - I, best quality coarse sand (F.M.2.2), 20 mm down well graded stone chips conforming to ASTM C 33 , making, placing shutter in position and maintaining true to plumb, making shutter water tight properly, placing reinforcement in position , mixing in standard mixture machine with hopper fed by standard measuring boxes,casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering including cost of water, electricity, testing and other charges etc. all complete approved and accepted by the Engineer. (rate is excluding the cost of reinforcement and its fabrication , binding, welding and placing ) ( A ) In Individual and combined footing of column

CE 53 a

07.6.1.1 Pile cap


(I) concrete

PC 7 PC 12 PC 6 PC 9 PC 14 PC 3 PC 10

6 deduct -12 28 4 2 20 deduct -40 10 deduct -10 12

X X X X X X X X X X

8 2 13 9 9 14 3 6 3 13

' ' ' ' ' ' ' ' ' '

4 8 0 6 6 6 4 0 0 0

" " " " " " " " " "

X X X X X X X X X X

9 3 9 6 9 11 5 5 1 8

''''''''''-

6 0 6 0 6 6 9 6 6 6

" " " " " " " " " "

= = = = = = = = = =

475.00 -96.00 3458.00 228.00 180.50 3335.00 -766.67 330.00 -45.00 1326.00

sft sft sft sft sft sft sft sft sft sft

= 8424.83 sft X 3 ' 9 " = 31593.13 cft = 894.74 cum @ TK 6126.00 / cum

= TK

54.812 lac

07.6.1.2 (ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Perimeter of PC 7 Perimeter of PC 12 Perimeter of PC 6 Perimeter of PC 9 Perimeter of PC 14 Perimeter of PC 3 Perimeter of PC 10 PC 7 PC 12 PC 6 PC 9 PC 14 PC 3 PC 10 6 28 4 2 20 10 12 X X X X X X X 29 45 31 38 42 20 43 ' ' ' ' ' ' ' 0 0 0 0 2 8 0 " " " " " " " X X X X X X X 3 3 3 3 3 3 3 '''''''9 9 9 9 9 9 9 " " " " " " " = = = = = = = = = = = = = = 29.00 45.00 31.00 38.00 42.17 20.68 43.00 652.50 4725.00 465.00 285.00 3162.50 775.00 1935.00 rft rft rft rft rft rft rft sft sft sft sft sft sft sft @ TK 289.00 / sqm = TK 3.222 lac

= 12000.00 sft = 1114.83 sqm

Page No 6

CE 53b

( B ) In raft / mat / floor slab at plinth level Basement floor

07.6.2

07.6.2.1 (I) concrete


1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft 2 X 0.5 X 3.1 X 25 ' - 0 " X 25 ' - 0 " = 1962.50 sft = 24698.50 sft X 1 ' 0 " = 24698.50 cft = 699.48 cum @ TK 6126.00 / cum

= TK

42.850 lac

07.6.2.2 (ii) Formwork / shuttering, prop and necessary supports etc ( steel )
2 X 116 ' - 0 " X 2 X 196 ' - 0 " X 2 X 3.1 X 25 ' - 0 " X 1'- 0" = 1'- 0" = 1'- 0" = = = Floor slab of Ground Floor
(I) Concrete

232.00 sft 392.00 sft 78.50 sft 702.50 sft 65.26 sqm @ TK 306.00 / sqm = TK 0.200 lac

1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft (semi circular portion ) 0.5 X 3.14 X 25 ' X 25 ' X 2 = 1962.5 sft = 24698.50 sft Deduction ( lift wall) ( Ramp ) ( stair) 4X 1X 1X 10 ' - 10 " X 18 ' - 4 " X 8' - 0" X 7'- 6" = 50 ' - 0 " = 12 ' - 0 " = = Net Area (mark A) Net volume 325.00 sft 916.67 sft 96.00 sft 1337.67 sft (-)
sft

= 24698.50 - 1337.67 = 23360.83 sft

= 23360.83 sft X 0 ' 6 " = 11680.42 cft = 330.80 cum @ TK 6126.00 / cum

= TK

20.265 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel )

Bottom sides

area same as mark A of above = 23360.83 sft 2 X 116 ' - 0 " X 0 ' - 6 " = 116.00 sft 2 X 196 ' - 0 " X 0 ' - 6 " = 196.00 sft 2 X 3.1 X 25 ' - 0 " X 0'- 6" = 78.50 sft = 23751.33 sft = 2206.55 sqm @ TK 306.00 / sqm = TK 6.752 lac

Page No 7

CE 53f

( C ) In Roof slab of all types, cantilever slab and drop panel ( i ) Ground Floor Roof slab
(I) Concrete

07.6.7.1

1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft (semi circular portion ) 0.5 X 3.14 X 25 ' X 25 ' = 981.25 sft = 23717.25 sft Deduction (void at Dept of Forensic medicine ) (void at middle) ( Lobby area ) ( middle stair) : 0.5 X 0.5 X 0.5 X 2X 1X 1X 11 ' - 4 " X 11 ' - 4 " X 28 ' - 4 " X 38 ' - 0 " X 30 ' - 0 " X 23 ' - 2 " X 15 ' - 3 " X 15 ' - 0 " X 10 ' - 1 " X 7' - 4" X 10 ' - 0 " = 10 ' - 0 " = 5 ' - 10 " = 28 ' - 0 " = 20 ' - 6 " = 11 ' - 10 " = 18 ' - 4 " = 18 ' - 4 " = 6'- 0" = 14 ' - 9 " = = Net Area (mark A ) 56.67 sft 56.67 sft 82.64 sft 2128.00 sft 615.00 sft 274.14 sft 279.58 sft 275.00 sft 121.00 sft 108.17 sft 3996.86 sft (-)

( side stairs void) 1 X 1X (side stair area) 2X

(corner stair area) 1 X

= 23717.25 - 3996.86 sft = 19720.39 sft X 0 ' 6 " = 9860.19 cft = 279.25 cum @ TK 6126.00 / cum

= TK

17.107 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel )

Bottom sides

area same as above 2 X 116 ' - 0 " X 2 X 196 ' - 0 " X 2 X 3.1 X 25 ' - 0 " X

= 19720.39 sft 0 ' - 6 " = 116.00 sft 0 ' - 6 " = 196.00 sft 0'- 6" = 78.50 sft = 20110.89 sft = 1868.35 sqm @ TK 488.00 / sqm = TK 9.118 lac

(ii) 1st Floor roof slab


(I) Concrete

add projected area Deduction :

1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft 2 X 30 ' - 0 " X 15 ' - 0 " = 900.00 sft = 23636.00 sft

(void at middle) 2X ( middle stair) 1X ( side stairs void) 1 X 1X ( side stair area) 2 X

38 23 15 15 10

' ' ' ' '

0 2 3 0 1

" " " " "

X X X X X

28 11 18 18 6

'''''-

0 10 4 4 0

" " " " "

= = = = = =

2128.00 274.14 279.58 275.00 121.00

sft sft sft sft sft (-)

3077.72 sft

Page No 8

Net Area ( mark B )

= 23636.00 - 3077.72 sft = 20558.28 sft X 0 ' 6 " = 10279.14 cft = 291.11 cum @ TK 6166.38 / cum

= TK

17.951 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel )

Bottom sides

area same as mark B of above = 20558.28 sft 2 X 116 ' - 0 " X 0 ' - 6 " = 116.00 sft 2 X 196 ' - 0 " X 0 ' - 6 " = 196.00 sft 2 X 3.1 X 25 ' - 0 " X 0'- 6" = 78.50 sft = 20948.78 sft = 1946.19 sqm @ TK 502.90 / sqm = TK 9.787 lac

(iii) 2nd Floor roof slab


(I) Concrete area same as 1st floor roof slab = 20558.28 sft X 0 '

6"

(mark C)

= 10279.14 cft = 291.11 cum


(ii) Formwork / shuttering, prop and necessary supports etc ( steel ) area same as 1st floor

@ TK 6206.76 / cum

= TK

18.069 lac

= 20948.78 sft = 1946.19 sqm

@ TK 517.80 / sqm

= TK

10.077 lac

(iv ) 3rd Floor roof slab


(I) Concrete area same as 2nd floor

= 20558.28 sft X 0 ' 6 " = 10279.14 cft = 291.11 cum @ TK 6247.14 / cum

= TK

18.186 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel ) area same as 2nd floor

= 20948.78 sft = 1946.19 sqm

@ TK 532.70 / sqm

= TK

10.367 lac

(v) 4th Floor roof slab


(I) Concrete area same as 3rd floor

= 20558.28 sft X 0 ' 6 " = 10279.14 cft = 291.11 cum @ TK 6287.52 / cum

= TK

18.304 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel ) area same as 3rd floor

= 20948.78 sft = 1946.19 sqm

@ TK 547.60 / sqm

= TK

10.657 lac

Page No 9

(vi) 5th Floor roof slab


(I) Concrete

1 X 196 ' - 0 " X 116 ' - 0 " = 22736.00 sft Deduction


Open front & back

: 2X 28 ' - 4 " X 23 15 15 10 ' ' ' ' 2 3 0 1 " " " " X X X X 80 ' - 0 " = 11 18 18 6 ''''10 4 4 0 " " " " = = = = = Net Area (mark D) 4533.33 sft 274.14 279.58 275.00 121.00 sft sft sft sft (-)

( middle stair) 1X ( side stairs void) 1 X 1X ( side stair area) 2 X

5483.06 sft

= 22736.00 - 5483.06 sft = 17252.94 sft X 0 ' 6 " = 8626.47 cft = 244.31 cum @ TK 6327.90 / cum

= TK

15.459 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel )

Bottom sides

area same as above 2 X 116 ' - 0 " X 2 X 196 ' - 0 " X

= 17252.94 sft 0 ' - 6 " = 116.00 sft 0 ' - 6 " = 196.00 sft = 17564.94 sft = 1631.82 sqm @ TK 562.50 / sqm = TK 9.179 lac

( vii ) 6th Floor roof slab ( chillakota )


(I) Concrete

1 X 116 ' - 0 " X

30 ' - 0 " = = = =

3480.00 3480.00 1740.00 49.28

sft sft X 0 ' 6 " cft cum @ TK 6380.53 / cum

= TK

3.144 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel )

Bottom sides

area same as above 2 X 116 ' - 0 " X 2 X 30 ' - 0 " X

= 0'- 6" = 0'- 6" = = =

3480.00 sft 116.00 sft 30.00 sft 3626.00 sft 336.86 sqm @ TK 584.86 / sqm = TK 1.970 lac

CE 53h

( D ) In Waffle or ribbed floor / roof slab waffle roof slab of 1st floor
(I) Concrete

07.6.11
0.5 X 3.14 X 25 ' X 1 X 30 ' X 25 ' 10 ' = = = = 981.25 sft 300 sft 1281.25 sft X 0 ' 6 " 640.63 cft

Page No 10 Ribbed beam

20 10 4 12

X X X X

12 25 30 10

' ' ' '

6 0 0 0

" " " "

X X X X

2 2 2 2

''''-

0 0 0 0

" " " "

= = = = = =

500.00 500.00 240.00 240.00

sft sft sft sft

1480.00 sft X 0 ' 6 " 740.00 cft 1380.63 cft 39.10 cum

Total ( mark A )

= =

@ TK 6349.38 / cum

= TK

2.483 lac

(ii) Formwork / shuttering, prop and necessary supports etc ( steel )

Bottom sides

area same as above 1 X 78 ' - 6 " X 2 X 30 ' - 0 " X

= 0'- 6" = 0'- 6" = =

1281.25 sft 39.25 sft 30.00 sft 1350.50 sft 3330.00 sft 4680.50 sft 434.83 sqm

add, Ribbed beam 1 X 740 ' - 0 " X 4'- 6" = Total


( mark B )

= =

@ TK 466.90 / sqm

= TK

2.030 lac

(Total Slab volume ) GF Floor Slab GF Roof slab 1st Floor Roof Slab 1st Floor waffle roof 2nd Floor Roof slab 3rd Floor roof Slab 4th Floor Roof Slab 5th Floor Roof Slab 6th Floor roof Slab = = = = = = = = = 9860.19 9860.19 10279.14 640.63 10279.14 10279.14 10279.14 8626.47 1740.00 cft cft cft cft cft cft cft cft cft

= 71844.04 cft

sub total

= TK

540.673 lac

Page No 11

Rate 2008 2011

Total 2008 2011 Increase Increase 06 to 08 BF 279.6846 332.5567 08 to 11

7,099.00

8,858.00

63.517 79.25571

15.9%

24.8%

255.00

326.00

2.843 3.634337

-11.8%

27.8%

Page No 12

7,099.00

8,858.00

49.656 61.95959

15.9%

24.8%

260.00

328.00

0.170 0.214065

-15.0%

26.2%

7,099.00

8,858.00

23.483 29.30193

15.9%

24.8%

260.00

328.00

5.737 7.237493

-15.0%

26.2%

Page No 13

21540.61 7,099.00 8,858.00 19.824 24.73566 15.9% 24.8%

387.00

437.00

7.231 8.164677

-20.7%

12.9%

Page No 14

7,149.00

8,925.00

20.812 25.98168

15.9%

24.8%

406.00

462.00

7.902 8.991393

-19.3%

13.8%

7,199.00

8,992.00

20.957 26.17673

16.0%

24.9%

425.00

487.00

8.271

9.47794

-17.9%

14.6%

7,249.00

9,059.00

21.103 26.37177

16.0%

25.0%

444.00

512.00

8.641 9.964487

-16.7%

15.3%

7,299.00

9,126.00

21.248 26.56681

16.1%

25.0%

463.00

537.00

9.011 10.45103

-15.4%

16.0%

Page No 15

2112.226

509.3883

1602.838 7,349.00 9,193.00 17.954 22.45912 16.1% 25.1%

482.00

562.00

7.865 9.170846

-14.3%

16.6%

7,415.00

9,282.00

3.654 4.573968

16.2%

25.2%

510.00

600.00

1.718 2.021182

-12.8%

17.6%

Page No 16

7,435.00

9,295.00

2.907 3.634356

17.1%

25.0%

458.00

568.00

1.992 2.469829

-1.9%

24.0%

sub total

606.179 735.3713

12.1%

21.3%

Page No 11

BF 540.673 lac

CE 53 g ( E ) In Stair case slabs and steps. 7.6.10 (i) Ground Floor (I) Concrete Basement to GF Ramp GF entrance ramp Basement stair : slab landing steps 22 X Side stair : slab landing steps 44 X middle stair : slab landing steps 44 X long side stair : slab landing steps 44 X corner stair : slab landing steps 22 X Entrance stair : slab steps 5 X Back Entrance : slab steps 5 X Side Entrance : slab steps 20 X

1 2 2 0.5 0.5 4 3.1 0.5 4 1 0.5 4 3.1 0.5 2 0.5 0.5 1 0.5 1 0.5 4 0.5

X 61 ' - 0 " X 18 ' - 4 " X 0 ' - 10 " = 931.94 cft X 8 ' - 0 " X 6 ' - 0 " X 0 '- 8 " = 64.00 cft X 9 ' - 9 " X 3 ' - 0 " X 0 '- 8 " = 39.00 cft X 3.14 X 3 ' X 3 ' X 0 '- 8 " = 9.42 cft X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 0 " = 13.75 cft X 11 ' - 8 " X 3 ' - 0 " X 0 ' - 8 " = 326.67 cft X 3 ' - 0 " X 3 ' - 0 " X 0 '- 8 " = 84.00 cft X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 0 " = 27.50 cft X 11 ' - 8 " X 5 ' - 0 " X 0 ' - 8 " = 544.44 cft X 11 ' - 10 " X 4 ' - 10 " X 0 ' - 8 " = 533.81 cft X 0 ' - 10 " X 0 ' - 6 " X 5 ' - 0 " = 45.83 cft X 11 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 508.15 cft X 4 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 203.26 cft X 0 ' - 10 " X 0 ' - 6 " X 4 ' - 8 " = 42.78 cft X 11 ' - 8 " X 3 ' - 6 " X 0 ' - 8 " = 381.11 cft X 3.14 X 4 ' X 4 ' X 0 '- 8 " = 16.75 cft X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 6 " = 16.04 cft X 28 ' - 4 " X 4 ' - 2 " X 0 ' - 8 " = 78.70 cft X 0 ' - 10 " X 0 ' - 6 " X 28 ' - 4 " = 29.51 cft X 5 ' - 10 " X 4 ' - 2 " X 0 ' - 8 " = 16.20 cft X 0 ' - 10 " X 0 ' - 6 " X 5 ' - 10 " = 6.08 cft X 8 ' - 6 " X 4 ' - 2 " X 0 '- 8 " = 94.44 cft X 0 ' - 10 " X 0 ' - 6 " X 8 ' - 6 " = 35.42 cft = 4048.82 cft = 114.6649 cum @ TK 6309.00 / cum = TK

7.234 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Basement to GF Ramp GF entrance ramp Basement stair : slab landing steps Side stair : slab landing steps middle stair : slab landing steps long side stair : slab landing steps corner stair : slab landing steps Entrance stair : slab steps Back Entrance : slab steps Side Entrance : slab steps 1 2 2 0.5 22 4 3.1 44 4 1 44 4 3.1 44 2 0.5 22 1 5 1 5 4 20 X 61 ' - 0 " X 18 ' - 0 " X 8 ' - 0 " X 6 '- 0 " X 9 ' - 9 " X 3 '- 0 " X 3.14 X 3 ' X 3 ' X 3 ' - 0 " X 0 '- 6 " X 11 ' - 8 " X 3 ' - 0 " X 3 ' - 0 " X 3 '- 0 " X 3 ' - 0 " X 0 '- 6 " X 11 ' - 8 " X 5 ' - 0 " X 11 ' - 10 " X 4 ' - 10 " X 4 ' - 10 " X 0 ' - 6 " X 11 ' - 8 " X 4 ' - 8 " X 4 ' - 8 " X 4 '- 8 " X 4 ' - 8 " X 0 '- 6 " X 11 ' - 8 " X 3 ' - 6 " X 3.14 X 4 ' X 4 ' X 4 ' - 0 " X 0 '- 6 " X 28 ' - 4 " X 4 ' - 2 " X 28 ' - 4 " X 0 ' - 6 " X 5 ' - 10 " X 4 ' - 2 " X 5 ' - 10 " X 0 ' - 6 " X 8 ' - 6 " X 4 '- 2 " X 8 ' - 6 " X 0 '- 6 " = 1098.00 sft = 96.00 sft = 58.50 sft = 5.09 sft = 33.00 sft = 140.00 sft = 28.26 sft = 66.00 sft = 233.33 sft = 57.19 sft = 106.33 sft = 217.78 sft = 68.38 sft = 102.67 sft = 81.67 sft = 6.95 sft = 44.00 sft = 118.06 sft = 70.83 sft = 24.31 sft = 14.58 sft = 141.67 sft = 85.00 sft

Page No 12

Ramp side Basement stair side steps side Entrance stair side Back stair side Side stair side

2 1 7 2 2 2

X X X X X X

61 2 2 5 5 5

' - 0 " X 0 ' - 10 " X 22.20 sft X 22.20 sft ' - 0 " X 1 '- 0 " ' - 0 " X 1 '- 0 " ' - 0 " X 1 '- 0 "

= 101.67 sft = 44.40 sft = 310.80 sft = 10.00 sft = 10.00 sft = 10.00 sft = 3384.46 sft = 314.42 sqm @ TK 390.00 / sqm = TK 1.226 lac

(ii) 1st Floor (I) Concrete Side stair : slab landing steps 44 X middle stair : slab landing steps 44 X long side stair : slab landing steps 44 X

4 3.1 0.5 4 1 0.5 4 3.1 0.5

X X X X X X X X X

11 3 0 11 11 0 11 4 0

' ' ' ' ' ' ' ' '

8 0 10 8 10 10 8 8 10

" " " " " " " " "

X X X X X X X X X

3 4 0 5 4 0 4 4 0

'''''''''-

0 8 6 0 10 6 8 8 6

" " " " " " " " "

X X X X X X X X X

0 0 3 0 0 5 0 0 4

'''''''''-

8 8 0 8 8 0 8 8 8

" " " " " " " " "

= 326.67 cft = 130.67 cft = 27.50 cft = 544.44 cft = 533.81 cft = 45.83 cft = 508.15 cft = 203.26 cft = 42.78 cft = 2363.11 cft = 66.9247 cum @ TK 6349.38 / cum = TK

4.249 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Side stair : slab landing steps middle stair : slab landing steps long side stair : slab landing steps Stair slab side 4 3.1 44 4 1 44 4 3.1 44 6 X X X X X X X X X X 11 3 3 11 11 5 11 4 4 2 ' ' ' ' ' ' ' ' ' 8 0 0 8 10 0 8 8 8 " " " " " " " " " X 3 '- 0 X 4 '- 8 X 0 '- 6 X 5 '- 0 X 4 ' - 10 X 0 '- 6 X 4 '- 8 X 4 '- 8 X 0 '- 6 X 22.20 sft " " " " " " " " " = 140.00 sft = 43.96 sft = 66.00 sft = 233.33 sft = 57.19 sft = 110.00 sft = 217.78 sft = 68.38 sft = 102.67 sft = 266.40 sft = 1305.71 sft = 121.3038 sqm @ TK 404.90 / sqm = TK

0.491 lac

(iii) 2nd Floor (I) Concrete Side stair : slab landing steps 44 X middle stair : slab landing steps 44 X long side stair : slab landing steps 44 X

4 3.1 0.5 4 1 0.5 4 3.1 0.5

X X X X X X X X X

11 3 0 11 11 0 11 4 0

' ' ' ' ' ' ' ' '

8 0 10 8 10 10 8 8 10

" " " " " " " " "

X X X X X X X X X

3 4 0 5 4 0 4 4 0

'''''''''-

0 8 6 0 10 6 8 8 6

" " " " " " " " "

X X X X X X X X X

0 0 3 0 0 5 0 0 4

'''''''''-

8 8 0 8 8 0 8 8 8

" " " " " " " " "

= 326.67 cft = 130.67 cft = 27.50 cft = 544.44 cft = 533.81 cft = 45.83 cft = 508.15 cft = 203.26 cft = 42.78 cft = 2363.11 cft = 66.9247 cum @ TK 6389.76 / cum = TK

4.276 lac

Page No 13

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Side stair : slab landing steps middle stair : slab landing steps long side stair : slab landing steps Stair slab side 4 3.1 44 4 1 44 4 3.1 44 6 X X X X X X X X X X 11 3 3 11 11 5 11 4 4 2 ' ' ' ' ' ' ' ' ' 8 0 0 8 10 0 8 8 8 " " " " " " " " " X 3 '- 0 X 4 '- 8 X 0 '- 6 X 5 '- 0 X 4 ' - 10 X 0 '- 6 X 4 '- 8 X 4 '- 8 X 0 '- 6 X 22.20 sft " " " " " " " " " = 140.00 sft = 43.96 sft = 66.00 sft = 233.33 sft = 57.19 sft = 110.00 sft = 217.78 sft = 68.38 sft = 102.67 sft = 266.40 sft = 1305.71 sft = 121.3038 sqm @ TK 419.80 / sqm = TK

0.509 lac

(iv) 3rd Floor (I) Concrete area same as 2nd Floor ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) area same as 2nd Floor (v) 4th Floor (I) Concrete area same as 3rd Floor = 2363.11 cft = 66.9247 cum @ TK 6470.52 / cum = TK 4.330 lac = 1305.71 sft = 121.3038 sqm @ TK 434.70 / sqm = TK = 2363.11 cft = 66.9247 cum @ TK 6430.14 / cum = TK 4.303 lac

0.527 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) area same as 3rd Floor = 1305.71 sft = 121.3038 sqm @ TK 449.60 / sqm = TK (vi) 5th Floor (I) Concrete Side stair : slab 4X landing 3.1 X steps 44 X 0.5 X middle stair : slab 4X landing 1X steps 44 X 0.5 X

0.545 lac

11 3 0 11 11 0

' ' ' ' ' '

8 0 10 8 10 10

" " " " " "

X X X X X X

3 4 0 5 4 0

''''''-

0 8 6 0 10 6

" " " " " "

X X X X X X

0 0 3 0 0 5

''''''-

8 8 0 8 8 0

" " " " " "

= 326.67 cft = 130.67 cft = 27.50 cft = 544.44 cft = 533.81 cft = 45.83 cft = 1608.93 cft = 45.56573 cum @ TK 6510.90 / cum = TK

2.967 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Side stair : slab landing steps middle stair : slab landing steps Stair slab side 4 3.1 44 4 1 44 4 X X X X X X X 11 3 3 11 11 5 2 ' ' ' ' ' ' 8 0 0 8 10 0 " " " " " " X 3 '- 0 X 4 '- 8 X 0 '- 6 X 5 '- 0 X 4 ' - 10 X 0 '- 6 X 22.20 sft " " " " " " = 140.00 = 43.96 = 66.00 = 233.33 = 57.19 = 110.00 = 177.60 = 828.09 = 76.93123 sft sft sft sft sft sft sft sft sqm @ TK 464.50 / sqm = TK

0.357 lac

(Total RCC volume in stair from Basement to 5th floor = 15110.19

cft )

Page No 14

CE 53 e ( F ) In Tee beam, Ell beam , Rectangular beam 7.6.6 (i) Ground Floor (I) Concrete GF Floor beams Long direction

4 2 Short direction 10 21 semi circular , 2 X 3.1 GF Roof beams Long direction 4 2 Short direction 10 14 Stair beam 2 semi circular , 2 X 3.1

X 190 ' - 0 " X 219 ' - 0 " X 80 ' - 0 " X 30 ' - 0 " X 25 ' - 0 "

X X X X X

1 1 1 1 1 1 1 1 1 1 1

'''''''''''-

0 0 0 0 0 0 0 0 0 0 0

" " " " " " " " " " "

X X X X X X X X X X X

2 2 2 2 2 2 2 2 2 2 2

'''''''''''-

0 6 0 6 0 0 6 0 6 0 0

" " " " " " " " " " "

= = = = = = = = = = = = =

1520.00 1095.00 1600.00 1575.00 314.00 1520.00 1095.00 1680.00 1050.00 44.00 314.00 11807.00 334.38

cft cft cft cft cft cft cft cft cft cft cft cft cum @ TK 6126.00 / cum = TK

X 190 ' - 0 " X X 219 ' - 0 " X X 84 ' - 0 " X X 30 ' - 0 " X X 11 ' - 0 " X X 25 ' - 0 " X

20.484 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) GF Floor beams Long direction

4 2 Short direction 10 21 semi circular , 2 X 3.1 GF Roof beams Long direction 4 2 Short direction 10 14 Stair beam 2 semi circular , 2 X 3.1

X 190 ' - 0 " X 219 ' - 0 " X 80 ' - 0 " X 30 ' - 0 " X 25 ' - 0 "

X( X( X( X( X(

1 1 1 1 1 1 1 1 1 1 1

'''''''''''-

0 0 0 0 0 0 0 0 0 0 0

" " " " " " " " " " "

+ + + + + + + + + + +

3 4 3 4 3 3 4 3 4 3 3

'''''''''''-

0 0 0 0 0 0 0 0 0 0 0

")= ")= ")= ")= ")= ")= ")= ")= ")= ")= ")= = =

3040.00 2190.00 3200.00 3150.00 628.00 3040.00 2190.00 3360.00 2100.00 88.00 628.00 23614.00 2193.794

sft sft sft sft sft sft sft sft sft sft sft sft sqm @ TK 386.00 / sqm = TK

X 190 ' - 0 " X( X 219 ' - 0 " X( X 84 ' - 0 " X( X 30 ' - 0 " X( X 11 ' - 0 " X( X 25 ' - 0 " X(

8.468 lac

(ii) 1st Floor (I) Concrete Long direction 4 2 Short direction 10 15 semi circular , 2X 3.1 stair landing beam 2 X 190 ' - 0 " X X 219 ' - 0 " X X 80 ' - 0 " X X 30 ' - 0 " X X 25 ' - 0 " X X 11 ' - 0 " X 1 1 1 1 1 1 ''''''0 0 0 0 0 0 " " " " " " X X X X X X 2 2 2 2 2 2 ''''''0 6 0 6 0 0 " " " " " " = = = = = = = = 1520.00 1095.00 1600.00 1125.00 314.00 44.00 5698.00 161.37 3040.00 2190.00 3200.00 2250.00 628.00 88.00 11396.00 1058.714 cft cft cft cft cft cft cft cum @ TK 6166.38 / cum = TK sft sft sft sft sft sft sft sqm @ TK 400.90 / sqm = TK

9.951 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) 4 2 Short direction 10 15 semi circular , 2X 3.1 stair landing beam 2 Long direction X 190 ' - 0 " X( X 219 ' - 0 " X( X 80 ' - 0 " X( X 30 ' - 0 " X( X 25 ' - 0 " X( X 11 ' - 0 " X( 1 1 1 1 1 1 ''''''0 0 0 0 0 0 " " " " " " + + + + + + 3 4 3 4 3 3 ''''''0 0 0 0 0 0 ")= ")= ")= ")= ")= ")= = =

4.244 lac

Page No 15

(iii) 2nd Floor (I) Concrete Quantity same as 1st floor = 5698.00 cft = 161.37 cum @ TK 6206.76 / cum = TK 10.016 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Quantity same as 1st floor = 11396.00 sft = 1058.714 sqm @ TK 415.80 / sqm = TK (iv) 3rd Floor (I) Concrete Quantity same as 2nd floor = 5698.00 cft = 161.37 cum @ TK 6247.14 / cum = TK

4.402 lac

10.081 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Quantity same as 2nd floor = 11396.00 sft = 1058.714 sqm @ TK 430.70 / sqm = TK (v) 4th Floor (I) Concrete Quantity same as 3rd floor = 5698.00 cft = 161.37 cum @ TK 6287.52 / cum = TK

4.560 lac

10.146 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Quantity same as 3rd floor = 11396.00 sft = 1058.714 sqm @ TK 445.60 / sqm = TK (vi) 5th Floor (I) Concrete Long direction Short direction

4.718 lac

4 2 20 20 4

X 190 ' - 0 " X 190 ' - 0 " X 20 ' - 0 " X 20 ' - 0 " X 30 ' - 0 "

X X X X X

1 1 1 1 1

'''''-

0 0 0 0 0

" " " " "

X X X X X

2 2 2 2 2

'''''-

0 6 0 6 6

" " " " "

= 1520.00 cft = 950.00 cft = 800.00 cft = 1000.00 cft = 300.00 cft = 4570.00 cft = 129.43 cum @ TK 6327.90 / cum = TK 3040.00 1900.00 1600.00 2000.00 600.00 9140.00 849.1267 sft sft sft sft sft sft sqm @ TK 460.50 / sqm = TK

8.190 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Long direction 4 X 190 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 2 X 190 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= Short direction 20 X 20 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 20 X 20 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 4 X 30 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= = = (vii) 6th Floor (I) Concrete Long direction Short direction 1 ' - 0 " X 2 '- 0 " = 1 ' - 0 " X 2 '- 0 " 1 ' - 0 " X 2 '- 6 " = = = ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Long direction 3 X 110 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= Short direction 4 X 30 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3 X 30 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= = = ( Total RCC in Beam From GF to 6th Floor = 45992.00 cft ) 3 X 110 ' - 0 " X 4 X 30 ' - 0 " X 3 X 30 ' - 0 " X

3.910 lac

660.00 240.00 225.00 1125.00 31.86 1320.00 480.00 450.00 2250.00 209.0301

cft cft cft cum @ TK 6380.53 / cum = TK sft sft sft sft sqm @ TK 482.86 / sqm = TK

2.033 lac

1.009 lac

Page No 16

CE 53d ( G ) In Pedestal, Column, Capital, Lift wall and wall 7.6.4 (i) Below PL & in GF (I) Concrete Below PL Column C1 column C2 Column C3 Column C4 GF column Column C1 column C2 Column C3 Column C4 Basement wall Short direction Semi circular Long direction

32 28 4 18

X X X X

3 3 1 1

' ' ' '

0 0 3 0

" " " "

X X X X

3 2 2 2

''''-

0 3 6 1

" " " "

X X X X

10 10 10 10

''''-

0 0 0 0

" " " "

= 2880.00 cft = 1890.00 cft = 125.00 cft = 375.00 cft = 5270.00 cft = 2904.00 cft = 1848.00 cft = 150.00 cft = 450.00 cft = 5352.00 cft cft cft cft cft cft cft cft cft

32 28 4 18

X X X X

2 2 1 1

' ' ' '

9 9 3 0

" " " "

X X X X

2 2 2 2

''''-

9 0 6 1

" " " "

X X X X

12 12 12 12

''''-

0 0 0 0

" " " "

2 X 60 ' - 0 " X 2 X 3.14 X 25 ' X 2 X 192 ' - 0 " X

1 ' - 0 " X 10 ' - 0 " = 1200.00 1 ' - 0 " X 10 ' - 0 " = 1570.00 1 ' - 0 " X 10 ' - 0 " = 3840.00 = 6610.00 1 ' - 0 " X 10 ' - 0 " = 502.40 0 ' - 10 " X 10 ' - 6 " = 1283.33 0 ' - 10 " X 12 ' - 6 " = 1527.78 = 3313.51

614.084

Shear wall around side stair 4 X 3.14 X 4 ' X Lift wall in basement floor 4 X 36 ' - 8 " X Lift wall in GF 4 X 36 ' - 8 " X

Total (col+ lift wall+basement wall) = 20545.51 cft = 581.86 cum @ TK 6195.00 / cum = TK ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) basement floor column Column C1 32 X 2 X( Column C2 28 X 2 X( Column C3 4X 2 X( Column C4 14 X 2 X( 3 3 1 1 ' ' ' ' 0 0 3 0 " " " " + + + + 3 2 2 2 ''''0 3 6 1 ") = ") = ") = ") = = = 384.00 294.00 30.00 86.33 794.33 7943.33 rft rft rft rft ' X 10 ' sft

36.046 lac

Basement floor lift wall Shear wall

4X 2X

75 ' - 0 " X 10 ' - 6 " = 3150.00 sft 26 ' - 2 " X 10 ' - 6 " = 549.50 sft 500.00 rft 157.00 rft 657.00 rft X 10 ' 13140.00 sft 352.00 266.00 30.00 111.00 759.00 9108.00 3750.00 654.17 rft rft rft rft ' X12 ' sft sft sft sft sqm

Basement floor RCC wall 2 X( 190 ' - 0 " + 60 ' - 0 ") = 2 X 3.1 X 25 ' - 0 " = = = GF column face Column C1 32 X 2 X( 2 ' - 9 " + 2 ' - 9 ") = Column C2 28 X 2 X( 2 ' - 9 " + 2 ' - 0 ") = Column C3 4X 2 X( 1 ' - 3 " + 2 ' - 6 ") = Column C4 18 X 2 X( 1 ' - 0 " + 2 ' - 1 ") = = = GF lift wall 4 X 75 ' - 0 " X 12 ' - 6 " = Shear wall 2 X 26 ' - 2 " X 12 ' - 6 " = Total

X 2 ( for both sides )

= 38295.00 = 3557.69

@ TK 319.00 / sqm = TK

11.349 lac

Page No 17

(ii) 1st Floor (I) Concrete Column C1 column C2 Column C3 Column C4 Lift wall Shear wall

32 28 4 18

= = = = = 4 X 36 ' - 8 " X 0 ' - 10 " X 12 ' - 6 " = 2 X 3.14 X 4 ' X 1 ' - 0 " X 12 ' - 0 " = total lift & shear wall = total ( column + lift wall )

X X X X

2 2 1 1

' ' ' '

9 9 3 0

" " " "

X X X X

2 2 2 2

''''-

9 0 6 1

" " " "

X X X X

12 12 12 12

''''-

0 0 0 0

" " " "

2904.00 1848.00 150.00 450.00 5352.00 1527.78 301.44 1829.22

cft cft cft cft cft cft cft cft

= 7181.22 cft = 203.38 cum @ TK 6235.38 / cum = TK

12.681 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) column face Column C1 32 X Column C2 28 X Column C3 4X Column C4 18 X

2 2 2 2

X( X( X( X(

lift wall Shear wall

4X 2X

") = ") = ") = ") = = = 75 ' - 0 " X 12 ' - 6 " = 26 ' - 2 " X 12 ' - 6 " = Total

2 2 1 1

' ' ' '

9 9 3 0

" " " "

+ + + +

2 2 2 2

''''-

9 0 6 1

352.00 266.00 30.00 111.00 759.00 9108.00 3750.00 654.17

rft rft rft rft rft X 12' sft sft sft

= 13512.17 sft = 1255.31 sqm

@ TK 333.90 / sqm = TK

4.191 lac

(iii) 2nd Floor (I) Concrete Quantity same as 1st floor = 7181.22 cft = 203.38 cum @ TK 6275.76 / cum = TK

12.763 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Quantity same as 1st floor = 13512.17 sft = 1255.31 sqm @ TK 348.80 / sqm = TK (iv) 3rd Floor (I) Concrete Quantity same as 2nd floor = 7181.22 cft = 203.38 cum @ TK 6316.14 / cum = TK

4.379 lac

12.846 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Quantity same as 2nd floor = 13512.17 sft = 1255.31 sqm @ TK 363.70 / sqm = TK (v) 4th Floor (I) Concrete Quantity same as 3rd floor = 7181.22 cft = 203.38 cum @ TK 6356.52 / cum = TK

4.566 lac

12.928 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Quantity same as 3rd floor = 13512.17 sft = 1255.31 sqm @ TK 378.60 / sqm = TK (vi) 5th Floor (I) Concrete Column C1 column C2 Column C3 Column C4 Lift wall Shear wall 32 28 4 16 = = = = = 4 X 36 ' - 8 " X 0 ' - 10 " X 12 ' - 0 " = 2 X 3.14 X 4 ' X 1 ' - 0 " X 12 ' - 0 " = lift & shear wall = X X X X 2 2 1 1 ' ' ' ' 9 9 3 0 " " " " X X X X 2 2 2 2 ''''9 0 6 1 " " " " X X X X 11 11 11 11 ''''6 6 6 6 " " " " 2783.00 1771.00 143.75 383.33 5081.08 1466.67 301.44 1768.11 cft cft cft cft cft cft cft cft

4.753 lac

total ( column + lift wall + shear wall) = 6849.19 cft = 193.97 cum @ TK 6396.90 / cum = TK

12.408 lac

Page No 18

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Column Column Column Column C1 C2 C3 C4 : : : : lift wall Shear wall 2X 2X 2X 2X 32 28 4 16 X( X( X( X( 2 2 1 1 ' ' ' ' 9 9 3 0 " " " " + + + + 2 2 2 2 ''''9 0 6 1 ") X ") X ") X ") X 11 11 11 11 ''''6 6 6 6 " " " " = = = = = 4048.00 3059.00 345.00 1134.67 8586.67 sft sft = 12814.67 sft = 1190.51 sqm @ TK 393.50 / sqm = TK sft sft sft sft sft

4X 2X

75 ' - 0 " X 12 ' - 0 " = 3600.00 26 ' - 2 " X 12 ' - 0 " = 628.00 Total

4.685 lac

(vii) 6th Floor (I) Concrete Column C1 column C2 Column C4 Lift wall Shear wall

8X 4X 6X

2 ' - 9 " X 11 ' - 6 " = 2 ' - 0 " X 11 ' - 6 " = 2 ' - 1 " X 11 ' - 6 " = = 4 X 36 ' - 8 " X 0 ' - 10 " X 12 ' - 0 " = 2 X 3.14 X 4 ' X 1 ' - 0 " X 12 ' - 0 " = lift & shear wall = total ( column + lift wall + shear wall) = =

2'- 9"X 2'- 9"X 1'- 0"X

695.75 253.00 143.75 1092.50 1466.67 301.44 1768.11 2860.61

cft cft cft cft cft cft cft cft 5.225 lac

81.01 cum @ TK 6449.53 / cum= TK

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) Column Column Column C1 C2 C3 : : : lift wall Shear wall 2X 2X 2X 8 X( 4 X( 6 X( 4X 2X 2 ' - 9 ") X 11 ' - 6 " = 1012.00 2 ' - 0 ") X 11 ' - 6 " = 437.00 2 ' - 1 ") X 11 ' - 6 " = 425.50 = 1874.50 75 ' - 0 " X 12 ' - 0 " = 3600.00 sft 26 ' - 2 " X 12 ' - 0 " = 628.00 sft Total 2'- 9"+ 2'- 9"+ 1'- 0"+ sft sft sft sft

= 6102.50 sft = 565.36 sqm @ TK 415.86 / sqm = TK

2.351 lac

( Total RCC in Column below GF = ( Total RCC in Column above GF = ( Total RCC in lift wall + shear wall =

5270.00 32933.58 12900.89

cft ) cft ) cft ) sub Total = TK 815.073 lac

Page No 19

Rate 2008 2011 BF

Total 2008 606.17903 2011 735.3713 Increase 06 to 08 Increase 08 to 11

7,335.00

9161.00

8.411

10.50445

16.3%

24.9%

Page No 20

301.00

362.00

0.946

1.138214

-22.82

20.3%

7,385.00

9228.00

4.942

6.175811

16.31

25.0%

320.00

387.00

0.388

0.469446

-20.97

20.9%

7,435.00

9295.00

4.976

6.220651

16.36

25.0%

Page No 21

339.00

412.00

0.411

0.499772

-19.25

21.5%

7,485.00

9362.00

5.009

6.26549

16.40

25.1%

358.00

437.00

0.434

0.530098

-17.64

22.1%

7,535.00

9429.00

5.043

6.31033

16.45

25.1%

377.00

462.00

0.457

0.560424

-16.15

22.5%

7,585.00

9496.00

3.456

4.326922

16.50

25.2%

396.00

487.00

0.305

0.374655

-14.75

23.0%

Page No 22

7,099.00

8858.00

23.738

29.61949

15.88

24.8%

298.00

361.00

6.538

7.919597

-22.80

21.1%

7,149.00

8925.00

11.536

14.40234

15.94

24.8%

317.00

386.00

3.356

4.086637

-20.93

21.8%

Page No 23

7,199.00

8992.00

11.617

14.51045

15.99

24.9%

336.00

411.00

3.557

4.351315

-19.19

22.3%

7,249.00

9059.00

11.698

14.61857

16.04

25.0%

355.00

436.00

3.758

4.615994

-17.58

22.8%

7,299.00

9126.00

11.778

14.72669

16.09

25.0%

374.00

461.00

3.960

4.880673

-16.07

23.3%

7,349.00

9193.00

9.511

11.89805

16.14

25.1%

393.00

486.00

3.337

4.126756

-14.66

23.7%

7,415.00

9282.00

2.362

2.957307

16.21

25.2%

421.00

524.00

0.880

1.095318

-12.81

24.5%

Page No 24

7,188.00

8971.00

41.824

52.19875

16.03

24.8%

254.00

314.00

9.037

11.17115

-20.38

23.6%

Page No 25

7,238.00

9038.00

14.720

18.38115

16.08

24.9%

273.00

339.00

3.427

4.255504

-18.24

24.2%

7,288.00

9105.00

14.822

18.51741

16.13

24.9%

292.00

364.00

3.666

4.569332

-16.28

24.7%

7,338.00

9172.00

14.924

18.65368

16.18

25.0%

311.00

389.00

3.904

4.883159

-14.49

25.1%

7,388.00

9239.00

15.025

18.78994

16.23

25.1%

330.00

414.00

4.143

5.196987

-12.84

25.5%

7,438.00

9306.00

14.428

18.05114

16.28

25.1%

Page No 26

349.00

439.00

4.155

5.226346

-11.31

25.8%

7,504.00

9395.00

6.079

7.611271

16.35

25.2%

377.00

477.00

2.131

2.696769

-9.34

26.5%

900.87027

1102.76

10.53

22.4%

Page No 19

BF 815.07273 lac

11 CE 51 7.4

Reinforced cement concrete works using steel shutter with minimum cement content relates to mix ratio (1:2:4) having minimum fcr = 27 Mpa, and satisfying a specified compressive strength f'c = 22 Mpa at 28 days on standard cylinders as per standard practice of Code ACI / BNBC / ASTM & cement conforming to BDS EN - 197 - 1 - CEM 1 ( 32.5 to 52.5 N ) ASTM -C 150 Type - I, best quality coarse sand (F.M.2.2), 20 mm down well graded stone chips conforming to ASTM C - 33 , making, placing shutter in position and maintaining true to plumb, making shutter water tight properly, placing reinforcement in position , mixing in standard mixture machine with hopper fed by standard measuring boxes,casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering including cost of water, electricity, testing and other charges etc. all complete approved and accepted by the Engineer. (rate is excluding the cost of reinforcement and its fabrication , binding, welding and placing )

CE 51 e ( H ) In Tie Beams and Lintels. 7.4.5 (I) GF (I) Concrete Lintel for 10" wall Basement ramp side wall GF walls semi circular part

1X

60 ' - 0 " = 0 3 0 0 4 0 6 1 5 4 10 5 11 6 9 3 " " " " " " " " " " " " " " " " = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = =

60.00 rft 78.50 22.50 280.00 160.00 18.33 10.00 10.50 14.17 10.83 17.33 7.83 2.42 11.67 7.50 15.50 7.25 734.33 734.33 305.97 113.33 58.33 10.00 9.58 47.00 17.00 11.17 19.58 11.25 19.00 8.50 8.33 rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft X 0 ' - 10 " X 0 ' - 6 " cft rft rft rft rft rft rft rft rft rft rft rft rft

3.1 2 Dept of Forensic medicine side14 General office side 8 1 1 1 2 2 1 1 1 between lift 4 side stair c .g 1 2 1

X 25 ' X 11 ' X 20 ' X 20 ' X 18 ' X 10 ' X 10 ' X 7'X 5'X 17 ' X 7'X 2'X 2'X 7'X 7'X 7'( mark A )

Lintel for 5" wall Basement back entry lift side inspection room Male toilet 4 4 2 1 4 4 1 1 1 4 1 2 X X X X X X X X X X X X 28 14 5 9 11 4 11 19 11 4 8 4 ' ' ' ' ' ' ' ' ' ' ' ' 4 7 0 7 9 3 2 7 3 9 6 2 " " " " " " " " " " " "

Page No 20

Female toilet

void box

1 X 11 2 X 19 1X 8 4X 4 12 X 7 4X 8 2X 8 ( mark B )

' ' ' ' ' ' '

2 7 6 9 6 4 0

" " " " " " "

= 11.17 = 39.17 = 8.50 = 19.00 = 90.00 = 33.33 = 16.00 = 550.25 = 114.64

rft rft rft rft rft rft rft rft X 0 ' - 5 " X 0 ' - 6 " cft

= 420.61 cft = 11.91 cum @ TK ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) 10 " lintel 5 " lintel Total (ii) 1st Floor (I) Concrete Lintel for 10" wall Dept of anatomy = 734.33 rft X1.83 = 550.25 rft X1.43 = 2130.69 sft = 197.95 sqm rft rft

Total in GF

6400 / cum

= TK

0.762 lac

= 1343.83 = 786.86

sft sft

@ TK

319

/ sqm

= TK

0.631 lac

between lift office block side

3.1 2 14 4 12

X X X X X

25 ' - 0 13 ' - 0 20 ' - 0 2 ' - 11 20 ' - 0 (mark C)

" " " " "

Lintel for 5" wall lobby side semicircular side wall lift side inspection room corner stair side Male toilet 2 1 4 1 1 1 1 1 4 1 2 1 2 1 4 15 5 2 X X X X X X X X X X X X X X X X X X 20 ' - 11 28 ' - 4 16 ' - 0 10 ' - 3 21 ' - 3 11 ' - 2 19 ' - 7 11 ' - 3 4'- 9 8'- 6 4'- 2 11 ' - 2 19 ' - 7 8'- 6 4'- 9 7'- 6 8'- 4 8'- 0 (mark D) " " " " " " " " " " " " " " " " " "

= 78.50 = 26.00 = 280.00 = 11.67 = 240.00 = 636.17 = 265.07 = 41.83 = 28.33 = 64.00 = 10.25 = 21.25 = 11.17 = 19.58 = 11.25 = 19.00 = 8.50 = 8.33 = 11.17 = 39.17 = 8.50 = 19.00 = 112.50 = 41.67 = 16.00 = 491.50 = 102.40 = =

rft rft rft rft rft rft X 0 ' - 10 " X 0 ' - 6 " cft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft X 0 ' - 5 " X 0 ' - 6 " cft @ TK 6440.38 / cum = TK 0.670 lac

Female toilet

void box

Total in 1st Floor

367.47 cft 10.41 cum

Page No 21

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) 10 " lintel 5 " lintel Total (iii) 2nd Floor (I) Concrete Lintel for 10" wall 2 2 2 2 2 2 X 2X X 3.1 X X 2X X 1X X 14 X X 2X 2 ' - 11 25 ' - 0 13 ' - 0 28 ' - 4 20 ' - 0 10 ' - 1 (mark E) " " " " " " = 11.67 = 157.00 = 52.00 = 56.67 = 560.00 = 40.33 = 877.67 = 365.69 rft rft rft rft rft rft rft X 0 ' - 10 " X 0 ' - 6 " cft = 636.17 rft X1.83 = 491.50 rft X1.43 = 1867.03 sft = 173.45 sqm rft rft = 1164.19 = 702.85 333.9 / sqm sft sft = TK 0.579 lac

@ TK

Total lintel for 10" wall =

Lintel for 5" wall Male toilet 1 1 1 4 1 2 4 1 2 1 4 17 4 3 X X X X X X X X X X X X X X 11 ' 19 ' 11 ' 4'8'4'16 ' 11 ' 19 ' 8'4'7'8'8'(mark F) 2 7 3 9 6 2 0 2 7 6 9 6 4 0 " " " " " " " " " " " " " " = = = = = = = = = = = = = = = = = = 11.17 19.58 11.25 19.00 8.50 8.33 64.00 11.17 39.17 8.50 19.00 127.50 33.33 24.00 404.50 84.27 rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft X 0 ' - 5 " X 0 ' - 6 " cft @ TK 6480.76 / cum = TK 0.826 lac

lift side inspection Female toilet

void box

Total in 2nd Floor

449.97 cft 12.74 cum

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) 10 " lintel 5 " lintel Total = 877.67 rft X1.83 = 404.50 rft X1.43 = 2184.57 sft = 202.95 sqm rft rft = 1606.13 = 578.44 sft sft

@ TK

348.8 / sqm

= TK

0.708 lac

Page No 22

(iv) 3rd Floor (I) Concrete Lintel for 10" wall Lintel for 5" wall ( same as 2nd floor ) ( same as 2nd floor ) = 877.67 rft X 0 ' - 10 " X 0 ' - 6 " = 365.69 cft

= 404.50 rft X 0 ' - 5 " X 0 ' - 6 " = 84.27 cft Total in 3rd Floor = 449.97 cft = 12.74 cum @ TK 6521.14 / cum ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) ( same as 2nd floor ) = 2184.57 sft = 202.95 sqm @ TK 363.7 / sqm (v) 4th Floor (I) Concrete Lintel for 10" wall Lintel for 5" wall ( same as 3rd floor ) ( same as 3rd floor ) Total in 4th Floor = 877.67 rft X 0 ' - 10 " X 0 ' - 6 " = 365.69 cft = 404.50 rft X 0 ' - 5 " X 0 ' - 6 " = 84.27 cft 6561.52 / cum

= TK

0.831 lac

= TK

0.738 lac

= 449.97 cft = 12.74 cum @ TK ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) ( same as 3rd floor ) = 2184.57 sft = 202.95 sqm @ TK (vi) 5th Floor (I) Concrete Lintel for 10" wall outer wall 2X 2X 20 X 2X 20 ' - 0 " = 800.00 2 ' - 11 " = 11.67 (mark G) = 811.67 = 338.19 16 11 20 19 11 4 8 4 11 19 8 4 20 7 8 8 ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' 0 2 0 7 3 9 6 2 2 7 6 9 0 6 4 0 " " " " " " " " " " " " " " " " = = = = = = = = = = = = = = = = = = 64.00 11.17 20.00 19.58 11.25 19.00 8.50 8.33 11.17 39.17 8.50 19.00 40.00 127.50 33.33 24.00 464.50 96.77

= TK

0.836 lac

378.6 / sqm

= TK

0.768 lac

Total lintel for 10" wall = Lintel for 5" wall lift side inspection Male toilet 4 1 1 1 1 4 1 2 1 2 1 4 2 17 4 3 X X X X X X X X X X X X X X X X

rft rft rft X 0 ' - 10 " X 0 ' - 6 " cft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft X 0 ' - 5 " X 0 ' - 6 " cft @ TK 6601.9 / cum = TK 0.813 lac

Female toilet

void box

Total

= 434.97 cft = 12.32 cum

Page No 23

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) 10 " lintel 5 " lintel Total (vii) 6th Floor (I) Concrete Lintel for 10" wall 2 X 115 ' - 0 " = 230.00 rft 6 X 20 ' - 0 " = 120.00 rft = 350.00 rft X 0 ' - 10 " X 0 ' - 6 " = 145.83 cft = 4.13 cum @ TK 6654.53 / cum ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) 10 " lintel ( Total RCC in Lintel = 2718.77 cft ) = 811.67 rft X1.83 rft = 1485.35 sft = 137.99 sqm @ TK 415.86 / sqm = 811.67 rft X1.83 = 464.50 rft X1.43 = 2149.59 sft = 199.70 sqm rft rft = 1485.35 = 664.24 sft sft

@ TK

393.5 / sqm

= TK

0.786 lac

= TK

0.275 lac

= TK

0.574 lac

CE 51 h ( I ) Cornice , Railing , Drop walls , Louver, Fins etc.

7.4.8 ( i ) GF (I) Concrete Railing , Stair void side

stair railing , basement stair GF Stair : corner stair 1X short side stairs 2X long side stairs 2X 2X middle stairs stair side Flower bed Entry stair Entry ramp

4 4 4 4 4 3.1 4 4 3.1 4 2 2 2 2 2 4

X X X X X X X X X X X X X X X X

18 8 8 9 11 3 11 11 5 11 28 11 11 15 4 9

' ' ' ' ' ' ' ' ' ' ' ' ' ' ' '

0 7 0 9 8 8 8 8 6 8 2 8 5 0 4 0

" " " " " " " " " " " " " " " "

Drop wall : void side

stair side

4 4 4 2 2

X X X X X

18 8 8 11 11

' ' ' ' '

0 7 0 8 5

" " " " "

= 72.00 rft = 34.33 rft = 32.00 rft = 39.00 rft = 46.67 rft = 11.51 rft = 93.33 rft = 93.33 rft = 34.54 rft = 46.67 rft = 56.33 rft = 23.33 rft = 22.83 rft = 30.00 rft = 8.67 rft = 36.00 rft = 680.55 rft X 0 ' - 6 " = 340.28 sft = 72.00 rft = 34.33 rft = 32.00 rft = 23.33 rft = 22.83 rft = 184.50 rft X 3 ' - 0 " = 553.50 sft

Outer side of bldg

2 X 312 ' - 0 " = 624.00 rft = 624.00 rft X 6 ' - 0 " = 3744.00 sft Total Railing & Dropwall = = = = 4637.78 4637.78 1159.44 32.8361 sft sft X 3 " cft cum @ TK

6010.00 / cum

= TK

1.973 lac

Page No 24

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) total quantity = 4637.78 sft X 2 = 9275.55 sft = 861.72 sqm @ TK

296.00 / sqm

= TK

2.551 lac

( ii ) 1st Floor (I) Concrete Railing :Stair void side

lobby short side stairs long side stairs middle stairs stair side

4 4 4 1 2X 4 2X 4 2 X 3.1 4 2 2 2

X X X X X X X X X X X

18 8 8 30 11 11 5 11 28 11 11

' ' ' ' ' ' ' ' ' ' '

0 7 0 0 8 8 6 8 2 8 5

" " " " " " " " " " "

= 72.00 = 34.33 = 32.00 = 30.00 = 93.33 = 93.33 = 34.54 = 46.67 = 56.33 = 23.33 = 22.83 = 538.71 = 269.35 = 72.00 = 34.33 = 32.00 = 23.33 = 22.83 = 184.50 = 553.50

rft rft rft rft rft rft rft rft rft rft rft rft X 0 ' - 6 " sft rft rft rft rft rft rft X 3 ' - 0 " sft

Drop wall : void side

stair side

4 4 4 2 2

X X X X X

18 8 8 11 11

' ' ' ' '

0 7 0 8 5

" " " " "

Outer side of bldg

2 X 312 ' - 0 " = 624.00 rft = 624.00 rft X 6 ' - 0 " = 3744.00 sft Total Railing & Dropwall = 4566.85 sft = 4566.85 sft X 3 " = 1141.71 cft = 32.33 cum @ TK

6050.38 / cum

= TK

1.956 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) = 4566.85 sft X 2 = 9133.71 sft = 848.54 sqm @ TK ( iii ) 2nd Floor (I) Concrete ( quantity same as 1st floor )= 32.33 cum @ TK

310.9 / sqm

= TK

2.638 lac

6090.76 / cum

= TK

1.969 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) ( quantity same as 1st floor )= 848.542 sqm @ TK

325.8 / sqm

= TK

2.765 lac

( iv ) 3rd Floor (I) Concrete

( quantity same as 1st floor )=

32.33 cum

@ TK

6131.14 / cum

= TK

1.982 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) ( quantity same as 1st floor )= 848.542 sqm @ TK

340.7 / sqm

= TK

2.891 lac

Page No 25

( v ) 4th Floor (I) Concrete

( quantity same as 1st floor )=

32.33 cum

@ TK

6171.52 / cum

= TK

1.995 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) ( quantity same as 1st floor )= 848.542 sqm @ TK ( vi ) 5th Floor short side stairs long side stairs middle stairs stair side 2X 4 2X 4 2 X 3.1 4 2 2 2 X X X X X X X 11 11 5 11 28 11 11 ' ' ' ' ' ' ' 8 8 6 8 2 8 5 " " " " " " " = 93.33 = 93.33 = 34.54 = 46.67 = 56.33 = 23.33 = 22.83 = 370.37 = 185.19 rft rft rft rft rft rft rft rft X 0 ' - 6 " sft rft rft rft X 3 ' - 0 " sft

355.6 / sqm

= TK

3.017 lac

drop wall stair side

2X 2X

11 ' - 8 " = 23.33 11 ' - 5 " = 22.83 = 46.17 = 138.50

Outer side of bldg

2 X 312 ' - 0 " = 624.00 rft = 624.00 rft X 6 ' - 0 " = 3744.00 sft = 4067.69 sft = 4067.69 sft X 3 " = 1016.92 cft = 28.80 cum @ TK

Total railing + drop wall

6211.90 / cum

= TK

1.789 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) = 755.795 sqm @ TK ( Total Volume of RCC in cornice & 6743.22 dropwall = cft )
CE 51 I

370.50 / sqm

= TK

2.800 lac

( I ) Sun shade, false ceiling


GF (I) Concrete

7.4.9 15 ' - 0 " = 240.00 rft X 2 ' - 0 " = 480 sft = 480.00 sft = 480.00 sft X 3 " = 120.00 cft = 3.40 cum @ TK 6010.00 / cum ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) = 480.00 X 2 = 960.00 sft = 89.19 sqm @ TK 353.00 / sqm 16 X

= TK

0.204 lac

= TK

0.315 lac

Page No 26

1St floor (I) Concrete

15 ' - 0 " = 300.00 rft X 2 ' - 0 " = 600 sft = 600.00 sft = 600.00 sft X 3 " = 150.00 cft = 4.25 cum @ TK 6050.38 / cum ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) = 600.00 X 2 = 1200.00 sft = 111.48 sqm @ TK 367.90 / sqm 2nd floor (I) Concrete

20 X

= TK

0.257 lac

= TK

0.410 lac

15 ' - 0 " = 360.00 rft X 2 ' - 0 " = 720 sft = 720.00 sft = 720.00 sft X 3 " = 180.00 cft = 5.10 cum @ TK 6090.76 / cum ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) = 720.00 X 2 = 1440.00 sft = 133.78 sqm @ TK 382.80 / sqm 3rd floor (I) Concrete

24 X

= TK

0.310 lac

= TK

0.512 lac

quantity same as 2nd Floor =

5.10 cum

@ TK

6131.14 / cum

= TK

0.313 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) quantity same as 2nd Floor = 133.78 sqm 4th floor (I) Concrete

@ TK

397.70 / sqm

= TK

0.532 lac

quantity same as 3rd Floor =

5.10 cum

@ TK

6171.52 / cum

= TK

0.315 lac

( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) quantity same as 3rd Floor = 133.78 sqm 5th floor (I) Concrete

@ TK

412.60 / sqm

= TK

0.552 lac

15 ' - 0 " = 600.00 rft X 2 ' - 0 " = 1200 sft = 1200.00 sft = 1200.00 sft X 3 " = 300.00 cft = 8.50 cum @ TK 6211.90 / cum ( ii ) Formwork / shuttering, prop and necessary supports etc ( steel ) = 1200.00 X 2 = 2400.00 sft = 222.97 sqm @ TK 427.50 / sqm

40 X

= TK

0.528 lac

= TK

0.953 lac

sub total =

TK

858.400 lac

Page No 27

Rate 2008 2011

Total 2008 2011 Increase Increase 06 to 08 BF 900.8703 1102.76 08 to 11

Page No 28

7,040.00

9004.00

0.839 1.072544

10.0%

27.9%

259.00

320.00

0.513 0.633426

-18.8%

23.6%

636.17

7,090.00

9071.00

0.738 0.944004

10.1%

27.9%

Page No 29

278.00

345.00

0.482 0.598407

-16.7%

24.1%

7,140.00

9138.00

0.910 1.164481

10.2%

28.0%

297.00

370.00

0.603 0.750919

-14.9%

24.6%

Page No 30

7,190.00

9205.00

0.916 1.173019

10.3%

28.0%

316.00

395.00

0.641 0.801657

-13.1%

25.0%

7,240.00

9272.00

0.923 1.181557

10.3%

28.1%

335.00

420.00

0.680 0.852394

-11.5%

25.4%

7,290.00

9339.00

0.898 1.150422

10.4%

28.1%

Page No 31

354.00

445.00

0.707 0.888671

-10.0%

25.7%

7,356.00

9428.00

0.304 0.389384

10.5%

28.2%

382.00

483.00

0.527 0.666503

-8.1%

26.4%

6,922.00

8852.00

2.273 2.906655

15.2%

27.9%

Page No 32

240.00

298.00

2.068 2.567925

-18.9%

24.2%

6,972.00

8919.00

2.254 2.883869

15.2%

27.9%

259.00

323.00

2.198 2.740791

-16.7%

24.7%

7,022.00

8986.00

2.270 2.905533

15.3%

28.0%

278.00

348.00

2.359 2.952926

-14.7%

25.2%

7,072.00

9053.00

2.287 2.927196

15.3%

28.0%

297.00

373.00

2.520 3.165062

-12.8%

25.6%

Page No 33

7,122.00

9120.00

2.303

2.94886

15.4%

28.1%

316.00

398.00

2.681 3.377197

-11.1%

25.9%

7,172.00

9187.00

2.066

2.64584

15.5%

28.1%

335.00

423.00

2.532 3.197011

-9.6%

26.3%

6,922.00

8852.00

0.235 0.300833

15.2%

27.9%

278.00

337.00

0.248 0.300557

-21.2%

21.2%

Page No 34

6,972.00

8919.00

0.296 0.378887

15.2%

27.9%

297.00

362.00

0.331 0.403567

-19.3%

21.9%

7,022.00

8986.00

0.358

0.45808

15.3%

28.0%

316.00

387.00

0.423 0.517726

-17.5%

22.5%

7,072.00

9053.00

0.361 0.461495

15.3%

28.0%

335.00

412.00

0.448 0.551171

-15.8%

23.0%

7,122.00

9120.00

0.363 0.464911

15.4%

28.1%

354.00

437.00

0.474 0.584615

-14.2%

23.4%

7,172.00

9187.00

0.609 0.780544

15.5%

28.1%

373.00

462.00

0.832

1.0301

-12.7%

23.9%

sub total

943.3387 1156.478

9.89

22.6%

Page No 27

B.F = Tk

858.400 lac

12 CE 59

Supplying, fabrication and fixing to details as per design deformed bar reinforcement in concrete in accordance with BSTI standard in/c straightening and cleaning rust, if any, bending & binding in position in/c supply of G.I. wires etc. complete in all respects and accepted by the Engineer. ( A ) 60 grade deformed bar wtih minimum fy = 415 Mpa, ultimate strength 620 Mpa ( I ) GF ( A ) Pre cast pile ( Ref : Item 9 ) (B ) Pile cap ( Ref : Item 10 ) (C) Basement ( Ref : Item 10 ) (D) Basement wall ( Ref : Item 10 )

CE 59 b 8.1.2

52062.50 cft @

2 %=

1041.25 cft = 2313.89 quintal

31593.13 cft @ 24698.50 cft @ 6610.00 cft @

4 %= 2 %= 2 %=

1105.76 cft = 2457.24 quintal 432.22 cft = 960.50 quintal 99.15 cft = 220.33 quintal

(E) Slabs ( GF floor & roof slab ) ( Ref : Item 10 ) 21540.61 cft @ (F) Stair ( Ref : Item 10 ) (G) Beam ( Ref : Item 10 ) (H) Column upto GF ( Ref : Item 10 )

2 %=

323.11 cft = 718.02 quintal

4048.82 cft @

2 %=

60.73 cft = 134.96 quintal

11807.00 cft @

3 %=

295.18 cft = 655.94 quintal

5270.00 cft @

4 %=

184.45 cft = 409.89 quintal

(I) Column above GF ( Ref : Item 10 ) 5352.00 cft @ (J) lift wall & shear wall ( Ref : Item 10 ) 3313.51 cft @ (k) Lintel ( Ref : Item 11 ) 420.61 cft @

3 %=

133.80 cft = 297.33 quintal

2 %= 1 %=

49.70 cft = 110.45 quintal 3.36 cft = 7.48 quintal = 8286.04 quintal @ TK5400.00 / quintal = TK 447.446 lac

Page No 28

( II ) 1st Floor (A) Slabs ( Ref : Item 10 ) (B) Stair ( Ref : Item 10 ) (C) Beam ( Ref : Item 10 ) (D) Column ( Ref : Item 10 ) 10279.14 cft @ 2 %= 154.19 cft = 342.64 quintal

2363.11 cft @

2 %=

35.45 cft =

78.77

quintal

5698.00 cft @

3 %=

142.45 cft = 316.56 quintal

5352.00 cft @

3 %=

133.80 cft = 297.33 quintal

(E) lift wall & shear wall ( Ref : Item 10 ) 1829.22 cft @ (F) Lintel ( Ref : Item 11 )

2 %=

27.44 cft =

60.97

quintal

367.47

cft @

1 %=

2.94 cft = 6.53 quintal = 1102.80 quintal @ TK5419.06 / quintal = TK 59.762 lac

( III ) 2nd Floor (A) Slabs ( Ref : Item 10 ) (B) Stair ( Ref : Item 10 ) (C) Beam ( Ref : Item 10 ) (D) Column ( Ref : Item 10 )

10279.14 cft @

2 %=

154.19 cft = 342.64 quintal

2363.11 cft @

2 %=

35.45 cft =

78.77

quintal

5698.00 cft @

3 %=

142.45 cft = 316.56 quintal

5352.00 cft @

3 %=

133.80 cft = 297.33 quintal

(E) lift wall & shear wall ( Ref : Item 10 ) 1829.22 cft @ (F) Lintel ( Ref : Item 11 )

2 %=

27.44 cft =

60.97

quintal

449.97

cft @

1 %=

3.60 cft = 8.00 quintal = 1104.27 quintal @ TK5438.12 / quintal = TK 60.052 lac

( IV ) 3rd Floor (A) Slabs ( Ref : Item 10 ) (B) Stair ( Ref : Item 10 )

10279.14 cft @

2 %=

154.19 cft = 342.64 quintal

2363.11 cft @

2 %=

35.45 cft =

78.77

quintal

Page No 29

(C) Beam ( Ref : Item 10 ) (D) Column ( Ref : Item 10 )

5698.00 cft @

3 %=

142.45 cft = 316.56 quintal

5352.00 cft @

3 %=

133.80 cft = 297.33 quintal

(E) lift wall & shear wall ( Ref : Item 10 ) 1829.22 cft @ (F) Lintel ( Ref : Item 11 )

2 %=

27.44 cft =

60.97

quintal

449.97

cft @

1 %=

3.60 cft = 8.00 quintal = 1104.27 quintal @ TK5457.18 / quintal = TK 60.262 lac

( V ) 4th Floor (A) Slabs ( Ref : Item 10 ) (B) Stair ( Ref : Item 10 ) (C) Beam ( Ref : Item 10 ) (D) Column ( Ref : Item 10 )

10279.14 cft @

2 %=

154.19 cft = 342.64 quintal

2363.11 cft @

2 %=

35.45 cft =

78.77

quintal

5698.00 cft @

3 %=

142.45 cft = 316.56 quintal

5352.00 cft @

3 %=

133.80 cft = 297.33 quintal

(E) lift wall & shear wall ( Ref : Item 10 ) 1829.22 cft @ (F) Lintel ( Ref : Item 11 )

2 %=

27.44 cft =

60.97

quintal

449.97

cft @

1 %=

3.60 cft = 8.00 quintal = 1104.27 quintal @ TK5476.24 / quintal = TK 60.473 lac

( VI ) 5th Floor (A) Slabs ( Ref : Item 10 ) (B) Stair ( Ref : Item 10 ) (C) Beam ( Ref : Item 10 )

8626.47 cft @

2 %=

129.40 cft = 287.55 quintal

1608.93 cft @

2 %=

24.13 cft =

53.63

quintal

4570.00 cft @

3 %=

114.25 cft = 253.89 quintal

Page No 30

(D) Column ( Ref : Item 10 )

5081.08 cft @

3 %=

127.03 cft = 282.28 quintal

(E) lift wall & shear wall ( Ref : Item 10 ) 1768.11 cft @ (F) Lintel ( Ref : Item 11 )

2 %=

26.52 cft =

58.94

quintal

434.97

cft @

1 %=

3.48 cft = 7.73 quintal = 944.02 quintal @ TK5495.30 / quintal = TK 51.877 lac

( VII ) 6th Floor (A) Slabs ( Ref : Item 10 ) (B) Beam ( Ref : Item 10 ) (C) Column ( Ref : Item 10 )

1740.00 cft @

2 %=

26.10 cft =

58.00

quintal

1125.00 cft @

3 %=

28.13 cft =

62.50

quintal

1092.50 cft @

3 %=

27.31 cft =

60.69

quintal

(D) lift wall & shear wall ( Ref : Item 10 ) 1768.11 cft @ (E) Lintel ( Ref : Item 11 )

2 %=

26.52 cft =

58.94

quintal

145.83

cft @

1 %=

1.17 cft = 2.59 quintal = 242.72 quintal @ TK5532.56 / quintal = TK 13.429 lac

CE 59 a 8.1.1

( B ) 40 grade deformed bar wtih minimum fy = 276 Mpa, ultimate strength 482 Mpa ( I ) GF (A) Cornice, railing, drop wall ( Ref : Item 11 ) 1159.44 cft @

1 %=

9.28 cft =

20.61

quintal

(B) Sun shade ( Ref : Item 11 )

120.00

cft @

1 %= total

0.96 cft = =

2.13 22.75

quintal quintal @ TK5256.00 / quintal = TK 1.196 lac

( II ) 1st Floor (A) Cornice, railing, drop wall ( Ref : Item 11 ) 1141.71 cft @

1 %=

9.13 cft =

20.30

quintal

Page No 31

(B) Sun shade ( Ref : Item 11 )

150.00

cft @

1 %= total

1.20 cft = =

2.67 22.96

quintal quintal @ TK5275.06 / quintal = TK 1.211 lac

( III ) 2nd Floor (A) Cornice, railing, drop wall ( Ref : Item 11 ) 1141.71 cft @

1 %=

9.13 cft =

20.30

quintal

(B) Sun shade ( Ref : Item 11 )

180.00

cft @

1 %= total

1.44 cft = =

3.20 23.50

quintal quintal @ TK5294.12 / quintal = TK 1.244 lac

( IV ) 3rd Floor (A) Cornice, railing, drop wall ( Ref : Item 11 ) 1141.71 cft @

1 %=

9.13 cft =

20.30

quintal

(B) Sun shade ( Ref : Item 11 )

180.00

cft @

1 %= total

1.44 cft = =

3.20 23.50

quintal quintal @ TK5313.18 / quintal = TK 1.248 lac

( V ) 4th Floor (A) Cornice, railing, drop wall ( Ref : Item 11 ) 1141.71 cft @

1 %=

9.13 cft =

20.30

quintal

(B) Sun shade ( Ref : Item 11 )

180.00

cft @

1 %= total

1.44 cft = =

3.20 23.50

quintal quintal @ TK5332.24 / quintal = TK 1.253 lac

( VI ) 5th Floor (A) Cornice, railing, drop wall ( Ref : Item 11 ) 1016.92 cft @

1 %=

8.14 cft =

18.08

quintal

(B) Sun shade ( Ref : Item 11 )

300.00

cft @

1 %= total

2.40 cft = =

5.33 23.41

quintal quintal @ TK5351.30 / quintal = TK Sub Total 1.253 lac

= TK 1619.105 lac

Page No 32

Rate 2008 2011 BF

Total 2008 943.3386852 2011 1156.478041 Increase 06 to 08 Increase 08 to 11

7,258.00

8100.00

601.401

671.1690738

34.4%

11.6%

Page No 33

7,282.00

8132.00

80.306

89.68001024

34.4%

11.7%

7,306.00

8164.00

80.678

90.15264614

34.3%

11.7%

Page No 34

7,330.00

8196.00

80.943

90.50601271

34.3%

11.8%

7,354.00

8228.00

81.208

90.85937928

34.3%

11.9%

Page No 35

7,378.00

8260.00

69.650

77.97612134

34.3%

12.0%

7,425.00

8323.00

18.022

20.20191235

34.2%

12.1%

6,418.00

7240.00

1.460

1.646786803

22.1%

12.8%

Page No 36

6,442.00

7272.00

1.479

1.669926997

22.1%

12.9%

6,466.00

7304.00

1.519

1.716230078

22.1%

13.0%

6,490.00

7336.00

1.525

1.723749158

22.1%

13.0%

6,514.00

7368.00

1.531

1.731268238

22.2%

13.1%

6,538.00

7400.00

1.531 1,964.591

1.732483615 2,297.244

22.2% 21.34

13.2% 16.9%

Sub Total

Page No 32

B.F

1619.105 lac

13 (CE14) 04.1.

Brick works with 1st class bricks in cement sand ( F.M of sand 1.2 ) mortar (1:6) in foundation and plinth, filling the joints/interstices fully with mortar, racking out the joints, cleaning and soaking the bricks at least for 24 hours before use and curing at least for 7 days etc. all complete including cost of water, electricity & other charges and accepted by the Engineer. ( Cement : CEM - II / A - M )
10 " brick work in foundation

By the side of pile cap ( mark E of Item 6 A ) = By the side of basement ( wall mark D of Item 6A ) = side of basement ramp 60 ' X 10 ' 0"= = = =

####### 7170 600.00 ####### ####### 463.115

sft sft sft sft X 10 " cft cum @ TK

2630.00 / cum

TK

12.180 lac

14 Brick work with 1st class bricks in cement sand ( F.M. 1.2 ) mortar ( 1:4 ) in exterior walls in/c filling (CE 16) the interstices with mortar, raking out joints, cleaning and socking the bricks at least for 24 hours before use and washing of sand, necessary scaffolding, curing at least for 7 days etc. all complete including cost 04.3. of water, electricity & other charges (measurement to given as 250 mm width for one brick length and 375 mm for one brick and a half brick length). accepted by the Engineer. ( Cement : CEM - II / A - M ) (i) GF Wall length same as 10" Lintel area Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light = 734.33 rft X 0 ' - 10 " X 10 ' - 6 " = 6425.42 cft = = = = = 1127.25 605 1336.83 3069.08 2557.57 sft sft sft sft X 10 " cft @ TK 3038 / cum = TK 3.328 lac

Total volume (ii) 1st floor Wall length same as 10" Lintel area Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light

= 3867.85 cft = 109.54 cum

= 636.17 rft X 0 ' - 10 " X 10 ' - 6 " = 5566.46 cft = = = = = 1608 331 1535.63 3474.63 2895.52 sft sft sft sft X 10 " cft @ TK 3100.96 / cum = TK 2.346 lac

Total volume (iii) 2nd floor Wall length same as 10" Lintel area Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light

= 2670.94 cft = 75.64 cum

= 877.67 rft X 0 ' - 10 " X 10 ' - 6 " = 7679.58 cft = 1711.50 sft = 60.00 sft = 1463.58 sft = 3235.08 sft X 10 " = 2695.9 cft = 4983.68 cft = 141.141 cum @ TK 3163.92 / cum = TK 4.466 lac

Total volume

Page No 33

(iv) 3rd floor same as 2nd floor (v) 4th floor same as 3rd floor (v1) 5th floor Wall length same as 10" Lintel area deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light = 4983.68 cft = 141.14 cum @ TK 3289.84 / cum = TK 4.643 lac = 4983.68 cft = 141.14 cum @ TK 3226.88 / cum = TK 4.554 lac

= 811.67 rft X 0 ' - 10 " X 10 ' - 6 " = 7102.08 cft = = = = = 2589.00 60.00 2259.83 4908.83 4090.69 sft sft sft sft X 10 " cft

Total volume (vii) 6th floor Chillakota stair wall

= 3011.39 cft = 85.28 cum

@ TK

3352.80 / cum

TK

2.859 lac

2X 6X

110 ' 0 " = 220.00 20 ' 0 " = 120.00 (marked G) = 340.00 = 2975.00 20 ' -

rft rft rft X 0 ' - 10 " X 10 ' - 6 " cft

Parapet wall

4X

10 X

0 " = 800.00 rft X 0 ' - 10 " X 5 ' - 0 " = 3333.33 cft = 432.00 sft = 136.67 sft = 568.67 sft X 10 " = 473.89 cft = 5834.44 cft = 165.23 cum @ TK 3440.94 / cum = TK 5.686 lac

deduct window door

Total

15 125 mm brick work with 1st class bricks in cement sand ( F.M.1.2 ) mortar ( 1:4 ) and making bond (CE 21b ) with connected walls in/c necessary scaffolding, raking out joints, cleaning and soaking the bricks for at 04.16. least 24 hours before use and washing of sand curing at least for 7 days in all floors including cost of water, electricity & other charges etc. all complete and accepted by the Engineer. ( Cement : CEM - II / A - M ) (i) GF Wall length same as 5" Lintel area Deduction doors Partex single swing flush door Upvc plastic door = = 550.25 rft X 12 ' - 0 " 6603 sft 35.00 20.00 55.00 rft X 7 ' - 0 " 385 sft @ TK 423.00 / sqm = TK 2.444 lac

10 X 8X

3'6"= 2'6"= (marked A) = =

Total volume

= 6218.00 sft = 577.67 sqm

Page No 34

(ii) 1st floor Wall length same as 5" Lintel area Deduction doors Partex single swing flush door Upvc plastic door

= =

491.50 rft X 12 ' - 0 " 5898 sft 21.00 22.50 43.50 rft X 7 ' - 0 " 304.5 sft

6X 9X

3'6"= 2'6"= (marked D) = =

Total volume

= 5593.50 sft = 519.65 sqm

@ TK

434.51 / sqm

TK

2.258 lac

(iii) 2nd floor Wall length same as 5" Lintel area Deduction doors Partex single swing flush door Upvc plastic door

= 404.50 rft X 11 ' - 6 " = 4651.75 sft 21.00 22.50 43.50 rft X 7 ' - 0 " 304.5 sft

6X 9X

3'6"= 2'6"= (marked D) = =

Total volume

= 4347.25 sft = 403.87 sqm

@ TK

446.02 / sqm

TK

1.801 lac

(iv) 3rd floor Quantity same as 2nd floor = 4347.25 sft = 403.87 sqm @ TK 457.53 / sqm = TK 1.848 lac

(v) 4th floor Quantity same as 3rd floor = 4347.25 sft = 403.87 sqm @ TK 469.04 / sqm = TK 1.894 lac

(vi) 5th floor Wall length same as 5" Lintel area

= =

464.50 rft X 12 ' - 0 " 5574 sft

Deduction doors Partex single swing flush door Upvc plastic door

6X 9X

3'6"= 2'6"= (marked D) = =

21.00 22.50 43.50 rft X 7 ' - 0 " 304.5 sft

Total volume

= 5269.50 sft = 489.55 sqm

@ TK

480.55 / sqm

TK

2.353 lac

Page No 35

16 Providing brick work in facing for 200 x 50 mm in superstructure with 200 x 50 x 50 mm machine made CE 20 b hard pressed klinker facing bricks of approved quality pressed with 20 mm thick cement sand (F.M.1.2) 04.13. mortar (1:4), 10 mm thick cement mortar in adjacent sites in/c racking out joints and cutting the bricks to required sizes wherever necessary with high class recessed pointing, cleaning and soaking the bricks for at least 24 hours before use and washing of sand necessary scaffolding, curing at least for 7 days for all floors up to 4th floor including cost of water, electricity & other charges etc. all complete and accepted by the Engineer. ( Cement : CEM - II / A - M ) GF 2X 2X 195 ' 115 ' 0 " = 390.00 rft 0 " = 230.00 rft = 620.00 rft X 12 ' - 6 " = 7750.00 sft = 719.993 sqm @ TK 911

/ sqm

TK

6.559 lac

1st Floor

2X 2X

195 ' 115 ' -

0 " = 390.00 rft 0 " = 230.00 rft = 620.00 rft X 3 ' - 0 " = 1860.00 sft = 172.798 sqm @ TK 922.51 / sqm

TK

1.594 lac

17
CE 24 b

04.22.3

Klinker paving bricks work in floor/ pavement with machine made pressed bricks of approved quality in cement sand (F.M.1.2) mortar (1:4) on minimum 12 mm thick cement sand (F.M.1.2) mortar (1:4) in/c raking out joints, cutting the bricks to required size soaking the same 24 hours before use wherever necessary in/c high class flush pointing in cement mortar (1:2), cleaning, curing at least for 7 days etc. in/c washing and screening of sand, cost of water, electricity & other charges complete and standard practice accepted by the Engineer. ( Cement : CEM - II / A - M ) 50 mm thick flat brick pavement with 200 X 100 X 50 mm klinker paving bricks in 1:4 cement sand mortar having 200 X 100 mm face at top basement floor 40 ' - 0 " X 50 ' - 0 " = 2000.00 sft = 185.805 sqm

@ TK

922.51 / sqm

TK

Sub Total =

TK

1.714 lac . . . . . . . . . . . . . . 1671.764 lac

Page No 36

Rate 2008 2011 BF

Total 2008 2011 Increase 06 to 08 1964.591 2297.244 Increase 08 to 11

1823.033 3,636.00 4688.00 16.839 21.71085 38.3% 28.9%

4,147.00

5264.00

4.543

5.76617

36.5%

26.9%

4,226.00

5370.00

3.197 4.062004

36.3%

27.1%

62.96

4,305.00

5476.00

6.076 7.728869

36.1%

27.2%

Page No 37

4,384.00

5582.00

6.188 7.878478

35.9%

27.3%

4,463.00

5688.00

6.299 8.028087

35.7%

27.4%

4,542.00

5794.00

3.874 4.941373

35.5%

27.6%

4,652.00

5942.00

7.687 9.818258

35.2%

27.7%

576.00

730.00

3.327 4.216964

36.2%

26.7%

Page No 38

590.00

749.00

3.066

3.89217

35.8%

26.9%

604.00

768.00

2.439 3.101717

35.4%

27.2%

618.00

787.00

2.496 3.178452

35.1%

27.3%

632.00

806.00

2.552 3.255187

34.7%

27.5%

646.00

825.00

3.162 4.038775

34.4%

27.7%

Page No 39

1,149.00

1423.00

8.273 10.24549

26.1%

23.8%

1,163.00

1442.00

2.010

2.49175

26.1%

24.0%

1,091.00

1362.00

2.027 2.530658

18.3%

24.8%

2048.646 2404.129

22.54

17.4%

Page No 36

B.F

1671.764 Lac

Minimum 12 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement to wall both inner-and outer CE 120a surface, finishing the corner and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for 15.1. 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and accepted by the Engineer. ( Cement : CEM - II / A - M )
18

(i) GF for 10 " wall both side for 5 " wall both side Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

2X 2X

734.33 550.25

rft X rft X

12 ' 12 ' -

0" = 0" = = = = = = 0" = =

17624.00 sft 13206.00 sft 30830.00 sft 1127.25 605.00 1336.83 227.78 140.00 sft sft sft sft sft

8X

2' -

6" X

7'-

3436.86 sft 27393.14 sft 2544.88 sqm 15268.00 sft 11796.00 sft 27064.00 sft 1608.00 331.00 1535.63 136.67 157.50 sft sft sft sft sft

Net area
(ii) 1st Floor for 10 " wall both side for 5 " wall both side Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

= = 12 ' 12 ' 0" = 0" = = = = = = 0" = =

@ Tk

120.00

/ sqm

= Tk

3.054

lac

2X 2X

636.17 491.50

rft X rft X

9X

2' -

6" X

7'-

3768.79 sft 23295.21 sft 2164.18 sqm 21064.00 sft 9708.00 sft 30772.00 sft 1711.50 60.00 1463.58 136.67 157.50 sft sft sft sft sft

Net area
(iii) 2nd Floor for 10 " wall both side for 5 " wall both side Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

= = 12 ' 12 ' 0" = 0" = = = = = = 0" = = = = = = = =

@ Tk

125.35

/ sqm

= Tk

2.713

lac

2X 2X

877.67 404.50

rft X rft X

9X

2' -

6" X Net area

7'-

3529.25 sft 27242.75 sft 2530.91 sqm 27242.75 sft 2530.91 sqm 27242.75 sft 2530.91 sqm

@ Tk

130.70

/ sqm

= Tk

3.308

lac

(iv) 3rd Floor

Quantity same as 2nd floor

@ Tk

136.05

/ sqm

= Tk

3.443

lac

(v) 4th Floor

Quantity same as 3rd floor

@ Tk

141.40

/ sqm

= Tk

3.579

lac

Page No 37

(vi) 5th Floor for 10 " wall both side for 5 " wall both side Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

2X 2X

811.67 464.50

rft X rft X

12 ' 12 ' -

0" = 0" = = = = = = 0" = =

19480.00 sft 11148.00 sft 30628.00 sft 2589.00 60.00 2259.83 136.67 157.50 sft sft sft sft sft

9X

2' -

6" X

7'-

5203.00 sft 25425.00 sft 2362.04 sqm 8400.00 8666.67 432.00 136.67 sft sft sft sft @ Tk 154.77 / sqm = Tk 2.372
lac

Net area
(vii) 6th Floor for 10 " wall both side

= = 12 ' - 0 " = 10 ' - 10 " = = = = =

@ Tk

146.75

/ sqm

= Tk

3.466

lac

parapet

2X 4X 10 X

350 ' 20 ' -

0" X 0" X

Deduct, windows Deduct, Doors

16498.00 sft 1532.70 sqm

Minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall (1:4) with cement up to 19 CE 120 b 150 mm below ground level with neat cement finishing in/c washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and accepted by the 15.2. Engineer. ( Cement : CEM - II / A - M )
GF

2 X ( 195 ' -

0 " + 115 ' -

0 ") = = = =

620.00 620.00 1240.00 115.20

rft rt X 2 ' - 0 " sft sqm @ Tk 138.00

/ sqm

= Tk

0.159

lac

Minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to dado (1:4) with cement up to 150 20 CE 120 c mm below ground level with neat cement finishing in/c washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and accepted by the 15.3. Engineer. ( Cement : CEM - II / A - M )
(i) GF for 10 " wall inside for 5 " wall both side Deduction partex flush door 10 X plastic door

1X 2X

734.33 550.25

rft X rft X

0'0'-

6" = 6" = =

367.17 sft 550.25 sft 917.42 sft 17.50 sft 10.00 sft 27.50 sft 889.92 sft 82.68 sqm 318.08 sft 491.50 sft 809.58 sft 10.50 sft 11.25 sft 21.75 sft 787.83 sft 73.19 sqm

8X

3' 2' -

6" X 6" X

0'0'-

6" = 6" = =

Net area
(ii) 1st Floor for 10 " wall inside for 5 " wall both side Deduction partex flush door plastic door

= = 0'0'6" = 6" = =

@ Tk

149.00

/ sqm

= Tk

0.123

lac

1X 2X

636.17 491.50

rft X rft X

6X 9X

3' 2' -

6" X 6" X

0'0'-

6" = 6" = =

Net area

= =

@ Tk

154.35

/ sqm

= Tk

0.113

lac

Page No 38

(iii) 2nd Floor for 10 " wall inside for 5 " wall both side Deduction partex flush door plastic door

1X 2X

877.67 404.50

rft X rft X

0'0'-

6" = 6" = =

438.83 sft 404.50 sft 843.33 sft 10.50 sft 11.25 sft 21.75 sft 821.58 sft 76.33 sqm 821.58 sft 76.33 sqm 821.58 sft 76.33 sqm 405.83 sft 464.50 sft 870.33 sft 10.50 sft 11.25 sft 21.75 sft 848.58 sft 78.84 sqm 175.00 sft 10.50 sft 164.50 sft 15.28 sqm @ Tk 183.77 / sqm = Tk 0.028
lac

6X 9X

3' 2' -

6" X 6" X

0'0'-

6" = 6" = =

Net area

= = = = = = 0'0'6" = 6" = =

@ Tk

159.70

/ sqm

= Tk

0.122

lac

(iv) 3rd Floor

Quantity same as 2nd floor

@ Tk

165.05

/ sqm

= Tk

0.126

lac

(v) 4th Floor (vi) 5th Floor for 10 " wall inside for 5 " wall both side Deduction partex flush door plastic door

Quantity same as 3rd floor

@ Tk

170.40

/ sqm

= Tk

0.130

lac

1X 2X

811.67 464.50

rft X rft X

6X 9X

3' 2' -

6" X 6" X

0'0'-

6" = 6" = =

Net area
(vii) 6th Floor for 10 " wall inside Deduct, Doors

= = 0'0'6" = 6" = = =

@ Tk

175.75

/ sqm

= Tk

0.139

lac

1X 6X

350 ' 3' -

0" X 6" X

Minimum 12 mm thick cement sand (F.M. 1.2) plaster (1:6) having with fresh cement to wall both inner-and outer 21 CE 120 d surface, finishing the corner and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of water, electricity and other charges etc all complete as per drawing and accepted by the Engineer. 15.4. ( Cement : CEM - II / A - M )

GF outside

2X 2X

190 ' 110 ' -

0" X 0" X

2'2'-

0" = 0" = = =

760.00 sft 440.00 sft 1200.00 sft 111.48 sqm @ Tk 109.00 / sqm = Tk 0.122
lac

Page No 39

22 Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement (conforming to BDS 232) to ceiling CE 120 e R.C.C. columns, beams, surface of stair case, sunshades, cornices, railings, drop wall, louvers, fins and finishing

15.5.

the corners and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-incharge. ( Cement : CEM - II / A - M )
(i) GF Basement floor ceiling
3.14

1X X X( X( X( X(

196 ' 25 ' 3 3 1 1 ' ' ' ' -

0 " X 116 ' 0 " X 25 ' 0 0 3 0 " " " " + + + + 3 2 2 2 ' ' ' ' -

0" = 0" = 0 3 6 1 ") ") ") ") = = = = = =

22736.00 sft 1962.50 sft 192.00 147.00 15.00 43.17 rft rft rft rft

Basement floor column face Column C1 Column C2 Column C3 Column C4

32 28 4 14

397.17 rft X 10 ' 0 X 2 7943.33 sft 3150.00 sft 500.00 rft 157.00 rft 657.00 rft X 10 ' 0 X 2 13140.00 sft 1118.33 sft 70.00 sft 25.12 sft 95.12 sft 1140.00 876.00 1200.00 945.00 235.50 sft sft sft sft sft 2 ( 2 sides of beam )

Basement floor lift wall Basement floor RCC wall

4X

75 ' -

0" X

10 ' -

6" = 0 ") = = = =

2 X ( 190 ' - 0 " + 60 ' 2 X 3.14 X 25 ' - 0 "

Ramp bottom face

1X

61 ' -

0" X

18 ' 3'4'

4" = 0" = = =

Basement stair bottom , slab 2X landing 0.5 X Basement ceiling beam side Long direction Short direction

11 ' - 8 " X 3.14 X 4 ' X

4 2 10 21 2

X X X X X

190 219 80 30 78

' ' ' ' '

0 0 0 0 6

" " " " "

X X X X X

1 2 1 1 1

' ' ' ' '

6 0 6 6 6

" " " " "

= = = = = = =

4396.50 sft X 8793.00 sft

( Total plaster in basement floor =


GF ceiling, col, lift wall, stair Ceiling GF column face Column C1 Column C2 Column C3 Column C4

58938.29

sft )

quantity same as GF roof slab

19720.39 sft

32 28 4 18

X( X( X( X(

2 2 1 1

' ' ' '

9 9 3 0

" " " "

+ + + +

2 2 2 2

' ' ' '

9 0 6 1

") ") ") ")

= = = =

176.00 133.00 15.00 55.50

rft rft rft rft 2

GF lift wall

4X

75 ' -

0" X

12 ' -

= = 6" =

379.50 rft X 12 ' X 9108.00 sft 3750.00 sft

Page No 40

GF ceiling beam side Long direction Short direction

4 2 10 14 3.1

X X X X X

190 219 84 30 25

' ' ' ' '

0 0 0 0 0

" " " " "

X X X X X

1 2 1 1 1

' ' ' ' '

6 0 6 6 6

" " " " "

= = = = = = =

1140.00 876.00 1260.00 630.00 117.75

sft sft sft sft sft 2 ( 2 sides of beam )

4023.75 sft X 8047.50 sft 140.00 28.26 217.78 68.38 233.33 57.19 81.67 19.23 sft sft sft sft sft sft sft sft

Stair case slab bottom & landing Short side stair long side stair Middle stair landing

4X 4X

landing 3.1 X landing 3.1 X

4X 1X Corner stair 2 X landing 0.5 X 3.1 X

11 3 11 4 11 11 11 3

' ' ' ' ' ' ' '

- 8" X - 0" X - 8" X - 8" X - 8" X - 10 " X - 8" X - 6" X

3 3 4 4 5 4 3 3

' ' ' ' ' ' ' '

- 0" = - 0" = - 8" = - 8" = - 0" = - 10 " = - 6" = - 6" = =

845.85 sft 2

Railing, drop wall

= 4637.78 sft X = 9275.55 sft = = 480.00 sft X 960.00 sft

Sun shade

Total plaster area in GF


(ii) 1st Floor Ceiling

= 110645.58 sft = 10283.05 sqm

(mark B) @ Tk

99.00

/ sqm

= Tk

10.180

lac

quantity same as 1st Flor roof slab , mark B of Item 2

20558.28 sft

column face Column C1 Column C2 Column C3 Column C4

32 28 4 18

X( X( X( X(

2 2 1 1

' ' ' '

9 9 3 0

" " " "

+ + + +

2 2 2 2

' ' ' '

9 0 6 1

") ") ") ")

= = = =

176.00 133.00 15.00 55.50

rft rft rft rft

lift wall ceiling beam side Long direction Short direction Semi circular

4X

75 ' -

0" X

12 ' -

= = 6" =

379.50 rft X 12 ' 0 X 2 9108.00 sft 3750.00 sft

2X

stair landing beam

X X X X 3.1 X 2X

4 2 10 15

190 219 80 30 25 11

' ' ' ' ' '

0 0 0 0 0 0

" " " " " "

X X X X X X

1 2 1 1 1 1

' ' ' ' ' '

6 0 6 6 6 6

" " " " " "

= = = = = = = =

1140.00 876.00 1200.00 675.00 235.50 33.00

sft sft sft sft sft sft 2 ( 2 sides of beam )

4159.50 sft X 8319.00 sft 140.00 28.26 217.78 68.38 233.33 57.19 sft sft sft sft sft sft

Stair case slab bottom & landing Short side stair long side stair Middle stair landing

4X 4X 4X 1X

landing 3.1 X landing 3.1 X

11 3 11 4 11 11

' ' ' ' ' '

- 8 - 0 - 8 - 8 - 8 - 10

" " " " " "

X X X X X X

3 3 4 4 5 4

' ' ' ' ' '

- 0 - 0 - 8 - 8 - 0 - 10

" " " " " "

= = = = = = =

744.95 sft

Page No 41

Railing, drop wall

= 4566.85 sft X = 9133.71 sft = = = = 600.00 sft X 1200.00 sft 52813.93 sft 4908.36 sqm

Sun shade

Total plaster area in 1st Floor


(iii) 2nd Floor Ceiling column face Column C1 Column C2 Column C3 Column C4

(mark C ) @ Tk

104.35

/ sqm

= Tk

5.122

lac

quantity same as 2nd Floor roof slab , mark C of Item 2 32 28 4 18 X( X( X( X( 2 2 1 1 ' ' ' ' 9 9 3 0 " " " " + + + + 2 2 2 2 ' ' ' ' 9 0 6 1 ") ") ") ")

20558.28 sft

= = = =

176.00 133.00 15.00 55.50

rft rft rft rft

lift wall ceiling beam side

4X

75 ' -

0" X

12 ' -

= = 6" = =

379.50 rft X 12 ' 0 X 2 9108.00 sft 3750.00 sft 8319.00 sft

quantity same as 1st Floor

Stair case slab bottom & landing Short side stair long side stair Middle stair landing

4X 4X 4X 1X

landing 3.1 X landing 3.1 X

11 3 11 4 11 11

' ' ' ' ' '

- 8 - 0 - 8 - 8 - 8 - 10

" " " " " "

X X X X X X

3 3 4 4 5 4

' ' ' ' ' '

- 0 - 0 - 8 - 8 - 0 - 10

" " " " " "

= = = = = = =

140.00 28.26 217.78 68.38 233.33 57.19

sft sft sft sft sft sft

744.95 sft 2

Railing, drop wall

= 4566.85 sft X = 9133.71 sft = = = = = = = = 720.00 sft X 1440.00 sft 53053.93 sft 4930.66 sqm 53053.93 sft 4930.66 sqm 53053.93 sft 4928.83 sqm

Sun shade

Total plaster area in 2nd Floor

(mark D ) @ Tk

109.70

/ sqm

= Tk

5.409

lac

(iv) 3rd Floor

quantity same as 2nd floor

@ Tk

115.05

/ sqm

= Tk

5.673

lac

(v) 4th Floor

quantity same as 3rd floor

@ Tk

120.40

/ sqm

= Tk

5.934

lac

(vi) 5th Floor Ceiling :

quantity same as 5th Floor roof slab , mark D of Item 2

17252.94 sft

Page No 42

column face Column C1 Column C2 Column C3 Column C4

32 28 4 6

X( X( X( X(

2 2 1 1

' ' ' '

9 9 3 0

" " " "

+ + + +

2 2 2 2

' ' ' '

9 0 6 1

") ") ") ")

= = = =

176.00 133.00 15.00 18.50

rft rft rft rft

lift wall ceiling beam side Long direction

4X

75 ' -

0" X

12 ' -

= = 6" =

342.50 rft X 12 ' 0 X 2 8220.00 sft 3750.00 sft

4 2 Short direction 20 20 4

X X X X X

190 190 20 20 30

' ' ' ' '

0 0 0 0 0

" " " " "

X X X X X

1 1 1 1 1

' ' ' ' '

6 6 6 6 6

" " " " "

= = = = = = =

1140.00 570.00 600.00 600.00 180.00

sft sft sft sft sft 2 ( 2 sides of beam )

3090.00 sft X 6180.00 sft 140.00 28.26 217.78 68.38 233.33 57.19 sft sft sft sft sft sft

Stair case slab bottom & landing Short side stair long side stair Middle stair landing

4X 4X 4X 1X

landing 3.1 X landing 3.1 X

11 3 11 4 11 11

' ' ' ' ' '

- 8 - 0 - 8 - 8 - 8 - 10

" " " " " "

X X X X X X

3 3 4 4 5 4

' ' ' ' ' '

- 0 - 0 - 8 - 8 - 0 - 10

" " " " " "

= = = = = = =

744.95 sft 2

Railing, drop wall

= 4067.69 sft X = 8135.37 sft = = = = 1200.00 sft X 2400.00 sft 46683.27 sft 4336.98 sqm

Sun shade

Total plaster area in 5th floor


(vii) 6th Floor Ceiling column face Column C1 Column C2 Column C3 Column C4

( mark E ) @ Tk 125.75

/ sqm

= Tk

5.454

lac

1X 8 4 4 2 X( X( X( X(

116 ' 2 2 1 1 ' ' ' ' -

0" X 9 9 3 0 " " " " + + + +

30 ' 2 2 2 2 ' ' ' ' -

0" = 9 0 6 1 ") ") ") ") = = = = = =

3480.00 sft 44.00 19.00 15.00 6.17 rft rft rft rft

84.17 rft X 12 ' 0 X 2 2020.00 sft 495.00 sft 180.00 sft 180.00 sft 855.00 sft X 1710.00 sft 7210.00 sft 669.83 sqm 2 ( 2 sides of beam )

ceiling beam side

3 X 110 ' 4 X 30 ' 3 X 30 ' -

0" X 0" X 0" X

1'1'2'-

6" = 6" = 0" = = =

Total Plaster in 6th Floor

= =

( mark F )

@ Tk

133.77

/ sqm

= Tk

0.896

lac

Page No 43

23
CE 122

15.8.

Rule pointing to brick wall with cement sand (F.M. 1.2) mortar (1:2) with fresh cement (conforming to BDS 232) and raking out the joints, scaffolding, curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and accepted by the Engineer. ( Cement : CEM - II / A - M ) = = = = 7750.00 sft 719.99 sqm 1860.00 sft 172.80 sqm

GF

quantity same as Facing brick work

@ Tk

79.00

/ sqm

= Tk

0.569

lac

1st Floor

quantity same as Facing brick work

@ Tk

84.35

/ sqm

= Tk

0.146

lac

24 15.10.

Providing drip course/ Nosing/ throating at the edge of sunshade or cornice with cement sand (F.M. 1.2) mortar (1:2) charges etc. all complete in all respect as per drawing accepted by the Engineer. ( Cement : CEM - II / A - M ) 7 X 20 X 15 ' 0" = =

(CE 124) with fresh cement (conforming to BDS 232) in/c. scaffolding, curing at least for 7 days, cost of water, electricity & other

2100.00 rft 640.24 rm

@ Tk

47.00

/ rm

= Tk

0.301

lac

25
CE 127

15.13.

Average 100 mm thick finished lime terracing with 20 mm down graded 1st class brick chips (Khoa), surki from 1st class bricks and lime (stone lime brought at site, not being powdered in open air and to be slaked in presence of engineer-incharge and to be measured in volume three days after slaking for using in the mix) in the proportion 7:2:2 (brick chips : surki : lime) including preparation of the mix on the ground by making a suitable platform under proper polythene cover. Cutting the mix twice daily with limewater (1:10) at least for 7 days until the mix attain desirable consistency. Laying the mix in proper slope, beating the same with standard koppa for minimum 7 days to gain maximum consolidation, making ghoondy and neat finishing with lime Surki mortar (1:2) and curing for 21 days providing polythene cover after each day work and cleaning etc. complete in all respect accepted by the Engineer. ( Cement : CEM - II / A - M )

5th Floor roof

1X

195 ' -

0 " X 115 ' -

0" = = = =

22425.00 22425.00 7475.00 211.70

sft sft X cft cum

4" @ Tk 5323.00 / cum = Tk 11.269


lac

SubTotal = Tk

1745.712

lac

Page No 44

Rate 2008

2011

Total 2008

2011

Increase 06 to 08

Increase 08 to 11

BF

2048.646

2404.13

151.00

175.00

3.843

4.45

25.8%

15.9%

158.00

184.00

3.419

3.98

26.0%

16.5%

165.00

193.00

4.176

4.88

26.2%

17.0%

172.00

202.00

4.353

5.11

26.4%

17.4%

179.00

211.00

4.530

5.34

26.6%

17.9%

Page No 45

186.00

220.00

4.393

5.20

26.7%

18.3%

196.00

234.00

3.004

3.59

26.6%

19.4%

174.00

202.00

0.200

0.23

26.1%

16.1%

188.00

216.00

0.155

0.18

26.2%

14.9%

195.00

225.00

0.143

0.16

26.3%

15.4%

Page No 46

202.00

234.00

0.154

0.18

26.5%

15.8%

209.00

243.00

0.160

0.19

26.6%

16.3%

216.00

252.00

0.165

0.19

26.8%

16.7%

223.00

261.00

0.176

0.21

26.9%

17.0%

233.00

275.00

0.036

0.04

26.8%

18.0%

137.00

161.00

0.153

0.18

25.7%

17.5%

Page No 47

Page No 48

125.00

152.00

12.854

15.63

26.3%

21.6%

Page No 49

132.00

161.00

6.479

7.90

26.5%

22.0%

139.00

170.00

6.854

8.38

26.7%

22.3%

146.00

179.00

7.199

8.83

26.9%

22.6%

153.00

188.00

7.541

9.27

27.1%

22.9%

Page No 50

160.00

197.00

6.939

8.54

27.2%

23.1%

170.00

211.00

1.139

1.41

27.1%

24.1%

Page No 51

100.00

120.00

0.720

0.86

26.6%

20.0%

107.00

129.00

0.185

0.22

26.9%

20.6%

59.00

73.00

0.378

0.47

25.5%

23.7%

8,319.00

10258.00

17.611

21.72

56.3%

23.3%

SubTotal = 2145.604 2521.4787

22.91

17.5%

Page No 44

B.F

1745.712 lac

26
CE 44-I a

06.8.1

Supplying, fitting and fixing unglazed homogeneous floor tiles (local made) on 20 mm thick cement sand (F.M.1.2) mortar (1:4) base and raking out the joints with white cement and colored pigment including cutting and laying tiles in proper way and finishing with care etc, all complete and accepted by the Engineer. ( Cement : CEM - II / A - M ) Size : GP Homogeneous 305 mm X 305 mm .
GP Homogeneous 305 mm X 305 mm floor tiles in Toilet (i) GF
male gen toilet Female gen toilet

1X 1X

19 ' 19 ' -

7" X 7" X

14 ' 14 ' -

6" = 6" = = =

283.96 sft 283.96 sft 567.92 sft 52.76 sqm @ Tk 867.00 / sqm = TK 0.457 lac

(ii) 1st Floor


male gen toilet Female gen toilet

1X 1X

19 ' 19 ' -

7" X 7" X

14 ' 14 ' -

6" = 6" = = =

283.96 sft 283.96 sft 567.92 sft 52.76 sqm @ Tk 870.84 / sqm = TK 0.459 lac

(iii) 2nd Floor


male gen toilet Female gen toilet

1X 1X

19 ' 19 ' -

7" X 7" X

14 ' 14 ' -

6" = 6" = = =

283.96 sft 283.96 sft 567.92 sft 52.76 sqm @ Tk 874.68 / sqm = TK 0.461 lac

(iv) 3rd Floor

Quantity same as 2nd floor

= 567.9167 sft = 52.76 sqm = 567.9167 sft = 52.76 sqm = 567.9167 sft = 52.76 sqm = 3407.50 sft )

@ Tk

878.52 / sqm

= TK

0.464 lac

(v) 4th Floor

Quantity same as 3rd floor

@ Tk

882.36 / sqm

= TK

0.466 lac

(vi) 5th Floor

Quantity same as 4th floor

@ Tk

886.2

/ sqm

= TK

0.468 lac

(Marked A) ( total floor tiles in toilet in all floors

27 06.9.2

Supplying, fitting and fixing mirror polished floor tiles (local made) on 20 mm thick cement sand (F.M.1.2) in proper way and finishing with care etc, all complete and accepted by the Engineer. ( Cement : CEM - II / A - M ) Size : GP ( mirror polished ) 396 mm X 396 mm floor tiles
(i) GF
Side stair and lift front stair corridor

CE 44 -IIb mortar (1:4) base and raking out the joints with white cement and colored pigment including cutting and laying tiles

deduct, middle stair

2 2 1 1 -1

X X X X X

27 3 28 19 23

' ' ' ' '

6 11 0 0 2

" " " " "

X X X X X

28 6 28 5 11

' ' ' ' '

0 6 0 0 10

" " " " "

= = = = = = =

1540.00 50.92 784.00 95.00 -274.14

sft sft sft sft sft @ Tk 1848.00 / sqm = TK 3.770 lac

2195.78 sft 203.99 sqm

(ii) 1st Floor

area same as GF

= =

2195.78 sft 203.99 sqm

@ Tk 1851.84 / sqm

= TK

3.778 lac

Page No 45

(iii) 2nd Floor

area same as 1st Floor

= =

2195.78 sft 203.99 sqm

@ Tk 1855.68 / sqm

= TK

3.785 lac

(iv) 3rd Floor

Quantity same as 2nd floor

= 2195.778 sft = 203.99 sqm = 2195.778 sft = 203.99 sqm

@ Tk 1859.52 / sqm

= TK

3.793 lac

(v) 4th Floor

Quantity same as 3rd floor

@ Tk 1863.36 / sqm

= TK

3.801 lac

(vi) 5th Floor

Quantity same as 4th floor

= 2195.778 sqm = 203.99 sqm

@ Tk 1867.20 / sqm

= TK

3.809 lac

28
CE 42 b

06.6.2

Supplying , fitting and fixing glazed wall tiles ( local made ) on 20 mm thick cement sand ( F.M 1.2 ) mortar (1:3) base and raking out the joints with white cement including cutting , laying and hire charge of machine and finishing with care etc including water, electricity and other charges complete in all respect and accepted by the Engineer. ( Cement : CEM - II / A - M ) Size : Coloured wall tiles of different sizes
(i) GF
male gen toilet

Basement lift wall Female gen toilet

9 10 8 4 4 1 4 9 10 8 4 4 1

X X X X X X X X X X X X X

3 4 2 4 6 15 36 3 4 2 4 6 15

' ' ' ' ' ' ' ' ' ' ' ' '

6 9 0 2 10 0 8 6 9 0 2 10 0

" " " " " " " " " " " " "

X X X X X X X X X X X X X

7 7 7 7 7 7 10 7 7 7 7 7 7

' ' ' ' ' ' ' ' ' ' ' ' '

0 0 0 0 0 0 0 0 0 0 0 0 0

" " " " " " " " " " " " "

= = = = = = = = = = = = = = =

220.50 332.50 112.00 116.67 191.33 105.00 1466.67 220.50 332.50 112.00 116.67 191.33 105.00

sft sft sft sft sft sft sft sft sft sft sft sft sft @ Tk 908.00 / sqm = TK 3.056 lac

3622.67 sft 336.55 sqm

(ii) 1st Floor


male gen toilet

Female gen toilet

9 10 8 4 4 1 9 10 8 4 4 1

X X X X X X X X X X X X

3 4 2 4 6 15 3 4 2 4 6 15

' ' ' ' ' ' ' ' ' ' ' '

6 9 0 2 10 0 6 9 0 2 10 0

" " " " " " " " " " " "

X X X X X X X X X X X X

7 7 7 7 7 7 7 7 7 7 7 7

' ' ' ' ' ' ' ' ' ' ' '

0 0 0 0 0 0 0 0 0 0 0 0

" " " " " " " " " " " "

= = = = = = = = = = = = = =

220.50 332.50 112.00 116.67 191.33 105.00 220.50 332.50 112.00 116.67 191.33 105.00

sft sft sft sft sft sft sft sft sft sft sft sft @ Tk 911.84 / sqm = TK 1.826 lac

2156.00 sft 200.30 sqm

Page No 46

(iii) 2nd Floor

Quantity same as 1st floor

= =

2156.00 sft 200.30 sqm

@ Tk

915.68 / sqm

= TK

1.834 lac

(iv) 3rd Floor

Quantity same as 2nd floor

2156.00 sft 200.30 sqm

@ Tk

919.52 / sqm

= TK

1.842 lac

(v) 4th Floor

Quantity same as 3rd floor

2156.00 sft 200.30 sqm

@ Tk

923.36 / sqm

= TK

1.849 lac

(vi) 5th Floor ( Total wall tiles area =

Quantity same as 3rd floor

= =

2156.00 sft 200.30 sqm

@ Tk

927.2

/ sqm

= TK

1.857 lac

14402.67

sft )

29
CE 27 c

05.1.4

10 mm thick finished and 12 mm laying thickness situ mosaic work on floor with one part of 10 mm machine crushed well graded dust free and properly washed marble chips and one part of mixture containing white cement and grey cement in proportion ( 9:1 ) in/c. preparation of mix. and laying the same over minimum 25 mm thick artificial patent stone flooring in/c making suitable panel, compacting, curing at least for 7 days, cutting with pumic stone (No. 40, No. 80, No.120)/cutting with mosaic machine and finishing with Minar stone & spreading oxalic acid in/c breaking brick chips, screening, washing mosaic chips and supply of all necessary materials& water, electricity & other charges in all respect accepted by the Engineer. ( Cement : CEM - II / A - M ) With Indian chips and without glass strip approved by the Engineer .
( I ) GF Basement floor deduct
Basement stair :landing

Tread
short side stair :landing

Tread
middle stair :landing

Tread
long side stair :landing

Tread
corner stair :landing

Tread

2 2 -4 0.5 22 1 44 1 44 1 44 0.5 22

X 30 ' 0 " X 15 ' X 30 ' 0 " X 25 ' X 12 ' 0" X 9'X 3.14 X 3' X 3' X 3' 0" X 0'X 3.14 X 3' X 3' X 3' 0" X 0'X 11 ' - 10 " X 4'X 5' 0" X 0'X 3.14 X 4.67 ' X 4.67 ' X 4' 8" X 0'X 3.14 X 3.5 ' X 3.5 ' X 3' 6" X 0'-

0" = 0" = 0" = = 10 " = = 10 " = 10 " = 10 " = = 10 " = = 10 " = = =

900.00 1500.00 -432.00 14.13 55.00 28.26 110.00 57.19 183.33 68.48 171.11 6.01 64.17

sft sft sft sft sft sft sft sft sft sft sft sft sft @ Tk 813.00 / sqm = TK 2.059 lac

2725.68 sft 253.22 sqm

(ii ) 1st floor


short side stair :landing

1 44 middle stair :landing 1 Tread 44 long side stair :landing 1 Tread 44 Tread

X X X X X X

X 3' 3' 0" 11 ' - 10 " 5' 0" 3.14 X 4.67 ' 4' 8"
3.14

X 3' X 0' X 4' X 0' X 4.67 ' X 0'

= 10 " = 10 " = 10 " = = 10 " = = =

28.26 110.00 57.19 183.33 68.48 171.11

sft sft sft sft sft sft @ Tk 816.84 / sqm = TK 0.469 lac

618.38 sft 57.45 sqm

Page No 47

(iii) 2nd floor

area same as 1st Floor

= =

618.38 sft 57.45 sqm

@ Tk

820.68 / sqm

= TK

0.471 lac

(iv) 3rd floor

area same as 2nd Floor

= =

618.38 sft 57.45 sqm

@ Tk

824.52 / sqm

= TK

0.474 lac

(v) 4th floor

area same as 3rd Floor

= =

618.38 sft 57.45 sqm

@ Tk

828.36 / sqm

= TK

0.476 lac

(vi) 5th floor

area same as 4th Floor

= =

618.38 sft 57.45 sqm

@ Tk

832.20 / sqm

= TK

0.478 lac

30
CE 31 a

05.5.1

10 mm thick finished and laying thickness 12.5 mm situ mosaic work on wall with one part of 10 mm machine crushed well graded dust free and properly washed marble chips and one part of mixture containing white cement and grey cement in proportion (9:1) including preparation of mix and laying the same on 12 mm thick cement plaster (1:4) to wall, compacting, curing at least for 7 days, cutting with pumic stone (No. 40, No. 80, No. 120) including finishing the corners and edges and also finishing with Minar stone and supplying all necessary materials in & water, electricity & other charges in all respect accepted by the Engineer. ( Cement : CEM - II / A - M ) With Indian chips ( I ) GF
Basement Basement stair rise railing
short side stair : Railing landing side railing

Rise
middle stair : Railing

Rise
long side stair : Railing

Rise
corner stair :landing

Rise

4 4 24 4 8 2 48 8 48 8 48 4 24

X X X X X X X X X X X X X

30 25 3 11 11
3.14

' ' ' ' '

3 11 5 11 4 11 3

0" X 0" X 0" X 8" X 8" X X 4.67 ' X ' 0" X ' 8" X ' 0" X ' 8" X ' 8" X ' 8" X ' 6" X

1 1 0 1 1 1 0 1 0 1 0 1 0

' ' ' ' ' ' ' ' ' ' ' ' '

6 6 6 11 11 11 6 11 6 11 6 11 6

" " " " " " " " " " " " "

= = = = = = = = = = = = = = =

180.00 150.00 36.00 89.44 178.89 29.33 72.00 178.89 120.00 178.89 112.00 89.44 42.00

sft sft sft sft sft sft sft sft sft sft sft sft sft @ Tk 862.00 / sqm = TK 1.167 lac

1456.88 sft 135.35 sqm

(ii) 1st Floor


short side stair : Railing landing side railing

Rise
middle stair : Railing

Rise
long side stair : Railing

Rise

8 2 48 8 48 8 48

X X X X X X X

3.14

11 ' 8" X X 4.67 ' X 3' 0" X 11 ' 8" X 5' 0" X 11 ' 8" X 4' 8" X

2 2 0 2 0 2 0

' ' ' ' ' ' '

3 3 6 3 6 3 6

" " " " " " "

= = = = = = = = =

210.00 58.66 72.00 210.00 120.00 210.00 112.00

sft sft sft sft sft sft sft @ Tk 865.84 / sqm = TK 0.798 lac

992.66 sft 92.22 sqm

Page No 48

(iii) 2nd Floor

Quantity same as 1st floor

= =

992.66 sft 92.22 sqm

@ Tk

869.68 / sqm

= TK

0.802 lac

(iv) 3rd Floor

Quantity same as 2nd floor

= 992.6552 sft = 92.22 sqm = 992.6552 sft = 92.22 sqm = 992.6552 sft = 92.22 sqm

@ Tk

873.52 / sqm

= TK

0.806 lac

(v) 4th Floor

Quantity same as 3rd floor

@ Tk

877.36 / sqm

= TK

0.809 lac

(vi) 5th Floor

Quantity same as 4th floor

@ Tk

881.2

/ sqm

= TK

0.813 lac

31
(CE 40 )

06.2.

Marble stone flooring with 20 mm thick grey or colored marble stone ( SAARC countries origin ) of approved quality, texture & size over 25 mm thick cement sand (F.M.1.2) mortar (1:2) in/c placing cement slurry below the stone, cutting the marble stone to desired size, grinding, polishing and finishing the edges setting in position in proper level, filling the gaps with white cement and coloring pigments including supplying all necessary equipments/materials and finishing the top by pumic stone and necessary auxiliary materials & water, electricity & other charges all complete in all respect and accepted by the Engineer. ( Cement : CEM - II / A - M )
(i) GF
Entrance platform Lobby Front entrance stair tread

side entrance platform side entrance stair tread

4X

1 1 4 4 4

X X X X X

9 30 28 7 7

' ' ' ' '

7 0 4 6 6

" " " " "

X X X X X

28 40 0 10 0

' ' ' ' '

4 0 10 0 10

" " " " "

= = = = = = =

271.53 1200.00 94.44 300.00 100.00

sft sft sft sft sft 5884.00 / sqm = TK 10.747 lac

1965.97 sft 182.64 sqm @ Tk

32
CE 38 b

06.4.

Marble stone flooring with 18 mm thick European origin marble stone of approved quality, texture & size over 25 mm thick cement sand (F.M.1.2) mortar (1:2) in/c. placing cement slurry below the stone, cutting the marble stone to desired size, grinding and finishing the edges, setting in position in proper level filling the gaps with white cement and coloring pigments including supplying all necessary equipments/materials and finishing the top by pumic stone and necessary auxiliary materials & water, electricity & other charges complete in all respect and accepted by the Engineer. ( Cement : CEM - II / A - M )
GF backside entrance

4X

5' -

10 " X

0'-

10 " = =

19.44 sft 1.81 sqm @ Tk

7483.00 / sqm

= TK

0.135 lac

33
CE 39 b

06.3.2

Supplying and setting 12 mm thick De carrara/Ariston/ Venous marble stone (Italy) or equivalent of approved quality/texture & size on wall over 12 mm thick cement sand (F.M.1.2) mortar (1:2) in/c. cutting the marble stone to desired size, grinding and finishing the edges, setting on position keeping correct horizontal and vertical alignment filling the joints with white cement and coloring pigments including supplying all necessary equipments/ materials and finishing the top by pumic stone and necessary auxiliary materials & water, electricity & other charges complete in all respect and accepted by the Engineer. ( Cement : CEM - II / A - M )
( i ) GF
Entrance stair rise Entrance side stair rise Backside entrance stair rise Flower bed side wall Lift wall sides

5 20 5 2 4

X X X X X

28 7 5 15 22

' ' ' ' '

4 6 10 0 6

" " " " "

X X X X X

0 0 0 2 12

' ' ' ' '

6 6 6 3 6

" " " " "

= = = = =

70.83 75.00 14.58 67.50 1125.00

sft sft sft sft sft

= 1352.92 sft = 125.74 sqm @ Tk 5641.00 / sqm = TK 7.093 lac

Page No 49

( ii ) 1st Floor
Lift wall front & back face

4X

22 ' -

6" X

12 ' -

6 " = 1125.00 sft = 104.55 sqm @ Tk

5644.84 / sqm

= TK

5.902 lac

( iii ) 2nd Floor


Lift wall front & back face

4X

22 ' -

6" X

12 ' -

6 " = 1125.00 sft = 104.55 sqm @ Tk

5648.68 / sqm

= TK

5.906 lac

( iv ) 3rd Floor
Lift wall front & back face

4X

22 ' -

6" X

12 ' -

6 " = 1125.00 sft = 104.55 sqm @ Tk

5652.52 / sqm

= TK

5.910 lac

( v ) 4th Floor Lift wall front & back face 4X 22 ' 6" X 12 ' 6 " = 1125.00 sft = 104.55 sqm @ Tk

5656.36 / sqm

= TK

5.914 lac

( vi ) 5th Floor
Lift wall front & back face

4X

22 ' -

6" X

12 ' -

6 " = 1125.00 sft = 104.55 sqm @ Tk

5660.20 / sqm

= TK

5.918 lac

34
CE 26 f

04.31.

38 mm thick artificial patent stone ( 1:1.5:3 ) flooring with cement, best quality coarse sand (50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.2 and 50% best local sand of FM 1.2) & 12 mm down well graded stone chips , in/c breaking chips, screening, laying the concrete in alternate panels, compacting and finishing the top with neat cement and curing at least 7 days in all floors in/c cost of water, electricity & other charges etc. all complete in all respect and accepted by the Engineer. ( Cement : CEM - II / A - M )
(i) Basement floor 1X 2 X 0.5 X 3.1 X Deduction -2 X -2 X 110 25 15 25 ' ' ' ' 0 0 0 0 " " " " X 190 ' X 25 ' X 30 ' X 30 ' 0 0 0 0 " " " " = 20900.00 sft = 1962.50 sft = -900.00 sft = -1500.00 sft = 20462.50 sft = 1901.01 sqm @ Tk (ii) Ground Floor 1 X 116 ' (semi circular portion ) 0.5 X 3.14 X Deduction Mid lift & stair block mid stair block toilet 0 " X 196 ' 25 ' X 25 ' X 0 " = 22736.00 sft 2 = 1962.5 sft = 24698.50 sft 1X 1X 2X 30 ' 30 ' 20 ' 0 " X 150 ' 0 " X 80 ' 0 " X 15 ' 0" = 0" = 0" = = Net Area 4500.00 sft 2400.00 sft 600.00 sft 7500.00 sft (-)
sft

308.00 / sqm

= TK

5.855 lac

= 24698.50 - 7500.00 = 17198.50 sft = 1597.78 sqm @ Tk

308.00 / sqm

= TK

4.921 lac

Page No 50

( iii ) 1st Floor 1 X 116 ' (semi circular portion ) 0.5 X 3.14 X Deduction : (void at Dept of Forensic 0.5 X 0.5 X medicine ) 0.5 X Mid lift & stair block Side stair block Toilet lobby void 1 1 2 1 X X X X 0 " X 196 ' 25 ' X 25 ' 0 " = 22736.00 sft = 981.25 sft = 23717.25 sft 11 ' 11 ' 28 ' 30 30 15 30 ' ' ' ' 4" X 4" X 4" X 0 0 0 0 " " " " 10 ' 10 ' 5'0" = 0" = 10 " = 0 0 0 0 " " " " = = = = = Net Area (mark A ) 56.67 sft 56.67 sft 82.64 sft 3300.00 2400.00 600.00 600.00 sft sft sft sft (-)
sft

X 110 ' X 80 ' X 20 ' X 20 ' -

7095.97 sft

= 23717.25 - 7095.97 = 16621.28 sft = 1544.15 sqm @ Tk

319.51 / sqm

= TK

4.934 lac

(iv) 2nd Floor

area same as 1st Floor add , lobby void

1X

30 ' -

0" X

20 ' -

= 16621.28 sft 0 " = 600.00 sft = 17221.28 sft = 1599.90 sqm @ Tk

331.02 / sqm

= TK

5.296 lac

(v) 3rd Floor


area same as 2nd floor

= 17221.28 sft = 1599.90 sqm @ Tk

342.53 / sqm

= TK

5.480 lac

(vi ) 4th Floor area same as 3rd floor = 17221.28 sft = 1599.90 sqm @ Tk

354.04 / sqm

= TK

5.664 lac

(vii) 5th Floor deduct, toilet 4X -2 X 86 ' 15 ' 0" X 0" X (mark D) 46 ' 20 ' 0 " = 15824.00 sft 0 " = -600.00 sft = 15224.00 sft = 1414.34 sqm @ Tk

365.55 / sqm

= TK

5.170 lac

( viii ) 6th Floor ( chillakota ) 1X 117 ' 0" X 30 ' 0" = = 3510.00 sft 326.09 sqm @ Tk

380.90 / sqm

= TK

1.242 lac

Sub Total

= TK

1879.196 lac

Page No 51

Rate 2008 2011

Total 2008 2011 Increase 06 to 08 Increase 08 to 11

BF

2145.604069 2521.479

1,084.00

1321.00

0.572 0.696969

25.0%

21.9%

1,089.00

1327.00

0.575 0.700135

25.1%

21.9%

1,094.00

1333.00

0.577 0.703301

25.1%

21.8%

1,099.00

1339.00

0.580 0.706466

25.1%

21.8%

1,104.00

1345.00

0.582 0.709632

25.1%

21.8%

1,109.00

1351.00

0.585 0.712798

25.1%

21.8%

1,890.00

1565.00

3.855 3.192486

2.3%

-17.2%

1,895.00

1571.00

3.866 3.204726

2.3%

-17.1%

Page No 52

1,900.00

1577.00

3.876 3.216965

2.4%

-17.0%

1,905.00

1583.00

3.886 3.229205

2.4%

-16.9%

1,910.00

1589.00

3.896 3.241445

2.5%

-16.8%

1,915.00

1595.00

3.906 3.253684

2.6%

-16.7%

1,007.00

1107.00

3.389 3.725652

10.9%

9.9%

1,012.00

1113.00

2.027 2.229309

11.0%

10.0%

Page No 53

1,017.00

1119.00

2.037 2.241327

11.1%

10.0%

1,022.00

1125.00

2.047 2.253344

11.1%

10.1%

1,027.00

1131.00

2.057 2.265362

11.2%

10.1%

1,032.00

1137.00

2.067

2.27738

11.3%

10.2%

887.00

1215.00

2.246 3.076647

9.1%

37.0%

892.00

1221.00

0.512

0.70145

9.2%

36.9%

Page No 54

897.00

1227.00

0.515 0.704897

9.3%

36.8%

902.00

1233.00

0.518 0.708344

9.4%

36.7%

907.00

1239.00

0.521 0.711791

9.5%

36.6%

912.00

1245.00

0.524 0.715238

9.6%

36.5%

963.00

1321.00

1.303 1.787944

11.7%

37.2%

968.00

1327.00

0.893 1.223758

11.8%

37.1%

Page No 55

973.00

1333.00

0.897 1.229292

11.9%

37.0%

978.00

1339.00

0.902 1.234825

12.0%

36.9%

983.00

1345.00

0.907 1.240358

12.0%

36.8%

988.00

1351.00

0.911 1.245891

12.1%

36.7%

4,885.00

5125.00

8.922 9.360468

-17.0%

4.9%

6,932.00

7269.00

0.125

0.13131

-7.4%

4.9%

4,189.00

5039.00

5.267 6.335824

-25.7%

20.3%

Page No 56

4,194.00

5045.00

4.385 5.274744

-25.7%

20.3%

4,199.00

5051.00

4.390 5.281018

-25.7%

20.3%

4,204.00

5057.00

4.395 5.287291

-25.6%

20.3%

4,209.00

5063.00

4.401 5.293564

-25.6%

20.3%

4,214.00

5069.00

4.406 5.299837

-25.6%

20.3%

364.00

416.00

6.920 7.908213

18.2%

14.3%

364.00

416.00

5.816 6.646763

18.2%

14.3%

Page No 57

378.00

435.00

5.837 6.717072

18.3%

15.1%

392.00

454.00

6.272 7.263527

18.4%

15.8%

406.00

473.00

6.496 7.567507

18.5%

16.5%

420.00

492.00

6.720 7.871487

18.6%

17.1%

434.00

511.00

6.138 7.227298

18.7%

17.7%

453.00

537.00

1.477 1.751087

18.9%

18.5%

2278.601542 2669.836

21.25

17.2%

Page No 51

B.F

1879.196 lac

35
CE 166 b

22.3.

Supplying , fitting, fixing of swing door shutter provided by 10 mm thick Tempered Clear glass ( foreign made ) in/c locking arrangements, shutter closer, handle & other necessary fittings etc, all complete in all respect and accepted by the Engineer.
Front Entrance door inGF

2X

4' -

2" X

7'-

0" = =

58.33 sft 5.42 sqm

@ Tk

14906.00 / sqm

= Tk

0.808 lac

36
analysis

Supplying , fitting, fixing of fixed 10 mm thick Tempered Clear glass ( foreign made ) with 15.75 mm , 14.81 mm fixed glass protector aluminium section and other necessary fitting, fixtures complete in all respect as per direction of the engineer in charge.
Front Entrance door inGF deduct, glass door

1X -2 X

43 ' 4' -

6 " X 24 ' 2" X 7'-

0" = 0" = = =

1044.00 -58.33 985.67 91.60

sft sft sft sqm

@ Tk

6539.00 / sqm

= Tk

5.990 lac

37
CE 76 e

11.1.5

Supplying and making door and window frames (Chowkat) for all floors with matured natural seasoned wood of required size including painting two coats of coal tar to the surface in contact with wall, fitting and fixing in position etc. all complete and accepted by the Engineer. (All sizes of wood are finished). Door frame of Chittagong Teak wood
Single swing door ( per swing 3'-4") GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor 6th Floor

10 6 6 6 6 6 6

X X X X X X X

17 17 17 17 17 17 17

'''''''-

6 6 6 6 6 6 6

" " " " " " "

= = = = = = = = = =

175.00 105.00 105.00 105.00 105.00 105.00 105.00

rft rft rft rft rft rft rft

805.00 rft X 0 ' 6 " X 0 ' 2.5 " 83.85 cft 2.37 cum @ Tk 133119.00 / cum

= Tk

3.161 lac

38
CE 86 a

12.7.1

Supplying, fitting & fixing 36 mm thick & having density 400 kg/cum. solid particle board single leaf flush door for all floors for internal use made of well matured mechanical seasoned garjan/other approved wooden frame having finished size 35 x 50 mm around upon which 1.4 mm thick veneer (total two Nos. of veneers one of 0.7 mm horizontally and another of 0.7 mm vertically made of Burma Teak/Champa/Chapalish /Garjan wood) with necessary screws are pested on each side by mechanized process and provided with best quality 4 Nos. 100 mm iron hinges, 2 Nos. best quality 12 mm iron dia 300 mm and 225 mm long iron tower and socket bolts, 2 (two) Nos. heavy type nickel plated handles, 1 No. hatch-bolt, hinged cleats, buffer blocks etc. complete and accepted by the Engineer. Burma Teak veneered.

GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor 6th Floor

10 6 6 6 6 6 6

X X X X X X X

3 3 3 3 3 3 3

' ' ' ' ' ' '

4 4 4 4 4 4 4

" " " " " " "

X X X X X X X

6 6 6 6 6 6 6

'''''''-

10 10 10 10 10 10 10

" " " " " " "

= = = = = = = = =

227.78 136.67 136.67 136.67 136.67 136.67 136.67

sft sft sft sft sft sft sft @ Tk 3251.00 / sqm = Tk 3.165 lac

1047.78 sft 97.34 sqm

Page No 52

39
Analysis

Extra rate for punching in veneered board door shutter and Supplying, fitting & fixing fixed glass on punched veneered board door shutter providing 25 mm wide & 12 mm thick wooden bit/frame of Teak chambal wood , 5 mm foreign made clear glass in/c nails, putty, etc, all complete in all respect in all floors as per design and direction of the engineer in charge.
GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor

2 2 2 2 2 2

X X X X X X

2 2 2 2 2 2

' ' ' ' ' '

0 0 0 0 0 0

" " " " " "

X X X X X X

2 2 2 2 2 2

''''''-

0 0 0 0 0 0

" " " " " "

= = = = = = = =

8.00 8.00 8.00 8.00 8.00 8.00

sft sft sft sft sft sft @ Tk 2269.00 / sqm = Tk 0.101 lac

48.00 sft 4.46 sqm

40
CE 111 d

14.6.2.3

Supplying, fitting and fixing of Aluminium sliding window as per the U.S. Architectural Aluminium Manufacturers Association (AAMA) standard specification having 1.5 mm thick outer bottom (size 75.50 mm, 32mm), 1.5 mm thick outer top (size 75.50 mm, 16.80 mm), 1.5 mm thick shutter top (size 33 mm.26.80, 22 mm), 1.5 mm thick shutter bottom (size 60mm, 24.40 mm), 1.5 mm thick outer side(size 75.50 mm,19.90 mm), 1.5 mm thick sliding fixed side (size 31 mm, 26 mm),1.5 mm thick shutter lock (size 49.20 mm 26.20 mm) & 1.5 mm thick inter lock (size 34.40 mm, 32.10 mm) sections all Aluminium members (Total weight kg/sqm) will be anodized to Aluminium Bronze/Silver color with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc. including all accessories like sliding door key lock, sliding door wheel, sliding door mohiar, sliding door neoprene, bolts & nuts in/c sealants, keeping provision for fitting 5 mm thick glass including labour charge for fitting of accessories, making grooves & mending good damages, carriage, and electricity complete in all respect as per drawing and accepted by the Engineer. Size : 900 mm X 1400 mm ( total weight minimum 7.409 kg ) , Colour : Silver colour.

GF 12 2 2 3 X X X X 15 16 9 6 ' ' ' ' 0 8 7 0 " " " " X X X X 4 4 4 4 ''''6 6 6 6 " " " " = = = = 810.00 150.00 86.25 81.00 sft sft sft sft sft ( Total length = 250.50 rft )

= 1127.25 1st floor 14 3 4 2 3 2 X X X X X X 15 16 6 12 10 8 ' ' ' ' ' ' 0 8 0 11 0 9 " " " " " " X X X X X X 4 4 4 4 4 4 ''''''6 6 6 6 6 6 " " " " " " = = = = = = = 2nd floor 16 4 4 8 X X X X 15 6 16 6 ' ' ' ' 0 5 8 0 " " " " X X X X 4 4 4 4 ''''6 6 6 6 " " " " = = = = = 3rd floor 4th floor same as 2nd floor same as 3rd floor = = 1080.00 115.50 300.00 216.00 945.00 225.00 108.00 116.25 135.00 78.75

sft sft sft sft sft sft ( Total length = 357.33 rft )

1608.00 sft

sft sft sft sft ( Total length = 380.33 rft )

1711.50 sft 1711.50 sft 1711.50 sft

Page No 53

5th floor 28 X 8X 4X 15 ' 16 ' 5' 0" X 8" X 6" X 4'4'4'6" = 6" = 6" = = Total 1890.00 sft 600.00 sft 99.00 sft 2589.00 sft ( Total length = ( mark A ) @ Tk 3613.00 / sqm = Tk 35.105 lac 575.33 rft )

= 10458.75 sft = 971.64 sqm

41
CE 112 b

14.8.3

Supplying, fitting and fixing of Aluminium fixed composite window as per the U.S. Architectural Aluminium Manufacturers Association (AAMA) standard specification having 1.5 mm thick outer bottom (size 75.50 mm, 32 mm, 0.695 kg/m), 1.5 mm thick outer top (size 75.50mm, 26.80 mm, 0.78 kg/m), 1.5 mm thick shutter top (size 33 mm, 26.80 mm, 0.536 kg/m), 1.5 mm thick shutter bottom (size 60 mm, 24.40 mm, 0.736 kg/m), 1.5 mm thick outer side (size 75.50 mm, 19.90 mm, 0.616 kg/m), 1.5 mm thick sliding fixed side (size 31 mm, 26 mm, 0.422 kg/m), 1.5 mm thick shutter lock (size 49.20 mm, 26.20 mm, 0.661 kg/m), 1.5 mm thick inter lock (size 34.40 mm, 32.10 mm 0.665 kg/m) 1.5 mm thick bottom cover (size 37.78 mm, 31.78 mm, 0.313 kg/m), 1.5 mm thick grouve cover (76.20 mm, 38.10 mm, 0.912 kg/m), 1.5 mm thick grouve cover ( size 57.15 mm, 15.80 mm, 0.452 kg/m) and 1.5 mm thick top & side (size 76.20 mm, 38.10 mm, 0.3 kg/m) sections all Aluminium members (Total weight 12.297 kg) will be anodized to Bronze/Silver color with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc. including all accessories like sliding door key lock, sliding door wheel, sliding door mohiar, sliding door neoprene, bolts & nuts in/c sealants, keeping provision for fitting 5mm thick glass including labour charge for fitting of accessories, making grooves & mending good damages, carriage, and electricity complete in all respect as per drawing and accepted by the Engineer. Size: 1500mm x 2100 mm , Colour : Silver colour.

GF

1 1 4 2 5 1

X X X X X X

28 7 6 10 2 7

' ' ' ' ' '

4 4 0 5 6 10

" " " " " "

X X X X X X

6 6 6 6 6 6

''''''-

0 0 0 0 0 0

" " " " " "

= = = = = = =

170.00 44.00 144.00 125.00 75.00 47.00

sft sft sft sft sft sft ( Total length = 100.83 rft )

605.00 sft 35.00 46.50 37.50 51.00 47.00 75.00 39.00 sft sft sft sft sft sft sft

1st floor 1 1 1 1 1 5 1 X X X X X X X 5 7 6 8 7 2 6 ' ' ' ' ' ' ' 10 9 3 6 10 6 6 " " " " " " " X X X X X X X 6 6 6 6 6 6 6 '''''''0 0 0 0 0 0 0 " " " " " " " = = = = = = = = 2nd floor 3rd floor 4th floor 5th floor 6th floor 4X 2' 6" X 6'0" = = = = 6" X 0" X Total 6'6'0" = 0" = =

331.00 sft 60.00 sft 60.00 sft 60.00 sft 60.00 sft 60.00 sft 432.00 sft 1608.00 sft

( Total length =

55.17

rft )

( Total length =

10.00

rft )

same as 2nd floor same as 3rd floor 4X 12 X 2' 6' -

( Total length = ( mark A )

72.00

rft )

Page No 54

149.39 sqm

@ Tk

2672.00 / sqm

= Tk

3.992 lac

Page No 55

42
CE 115b

14.11.3

Supplying fitting and fixing of Aluminium fixed fan light as per the U.S. Architectural Aluminium Manufacturers Association (AAMA) standard specification mm, 0.313 kg/m) 1.5 mm thick bottom cover (size 76.2 mm, 38.10 mm, 0.76 kg/m) & 2.5 mm thick grouve cover section (size 57.15mm, 15.80 mm, 0.425 kg/m) and 1.5 thick top & side section (76.20 mm, 16 mm, 38.10 mm, 0.961 kg/m) fixed with above mentioned frames and all Aluminium members (Total weight 5.365kg) will be anodized to Aluminium Bronze/Silver color with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc. including all accessories, neoprene, sealant, nut & bolt etc. complete in all respect as per drawing and accepted by the Engineer. Colour : Silver colour.

(Basement) GF

24 X

12 ' -

0" X 0" X X X

3'3'3'3'Total

3" = 3" = 3" = 3" = = 3" = 3" = 3" = =

936.00 sft 195.00 sft 814.13 sft 327.71 sft 1336.83 sft 195.00 sft 1161.33 sft 179.29 sft 1535.63 sft 195.00 sft 1236.08 sft 32.50 sft 1463.58 sft 1463.58 sft 1463.58 sft 195.00 sft 1869.83 sft 195.00 sft 2259.83 sft

4 X 15 ' 1 X 250.50 1 X 100.83

rft rft

1st Floor

4 X 15 ' 1 X 357.33 1 X 55.17

rft rft

0" X X X

3'3'3'-

2nd Floor

4 X 15 ' 1 X 380.33 1 X 10.00

rft rft

0" X X X

3'3'3'-

3" = 3" = 3" = =

3rd Floor 4th Floor 5th Floor

area same as 2nd floor area same as 2nd floor 4 X 15 ' 1 X 575.33 1 X 60.00 0" X X X 3'3'3'-

= = 3" = 3" = 3" = = Total

rft rft

= 10459.04 sft = 971.67 sqm

@ Tk

2884.00 / sqm

= Tk

28.023 lac

43
CE 113 b

14.9.3

Supplying, fitting and fixing of Aluminium top hung/casement windows as per the U.S. Architectural Aluminium Manufacturers Association (AAMA) standard specification having 1.5 mm thick casement outer (size 38.86 mm, 36.36 mm, 0.395kg/m), 1.9 mm thick casement shutter (size 47.62 mm, 28.57 mm, 0.692 kg/m), & 1.245 mm thick shutter glass clip (size 15.87 mm, 27 mm, 0.188 kg/m) sections of all Aluminium members will (Total weight 7.584 kg) be anodized to Aluminium Bronze/Silver color with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc. including all accessories 4-bar hinge, casement handle, bolts & nuts keeping provision for fitting 5 mm thick glass including labour charge for fitting of accessories, making grooves & mending good damages, carriage, and electricity complete in all respect as per drawing and accepted by the Engineer. Colour : Silver colour.

GF - 5 th Floor

100.00

rft

3'-

3" = =

325.00 sft 30.19 sqm

@ Tk

5768.00 / sqm

= Tk

1.742 lac

Page No 56

44
CE 107b

14.2.3

Supplying fitting and fixing of Aluminium composite swing doors as per the U.S. Architectural Aluminium Manufacturers Association (AAMA) standard specification having 1.8 mm thick wall frame size 101.60 mm. 44.45 mm. 83.21 mm). 2.33 mm thick shutter size (54 mm, 46 mm), 0.99 mm thick door glass bit (size 16.54 mm. 14.49mm .115 kg/m), 2.5 mm thick clousure section (size 101.60 mm, 42.93 mm 1.5 mm), 106.60 mm clousure cover (0.45 kg/m), 4 mm thick floor bottom (size 101.60 mm. 12.70 mm 1 kg/m),1.8 mm thick shutter bottom (size 82.6 mm, 43.99 mm, 0.60 kg/m), 1.8 mm thick shutter top (size 51 mm, 43.99 mm, 1.88 kg/m) & 2.3 mm to 4.01 mm thick handle (size 101.60 mm, 38.10 mm, 25.40 mm short, 1.35 kg/m) section of all aluminum members will be anodized to Aluminium Bronze/Silver colour with a coat not less than 15 micrones in thickness and density of 4 mg per square cm etc. including all accessories like swing door clousure, swing door lock, swing door mohiar, labor charge, fabrication, fitting fixing in position, carriage & electricity charge keeping provision for fitting 5 mm thick glass including neoprene. sealant etc. complete in all respect as per drawing and accepted by the Engineer. (Total weight min 23 kg/m2) , Silver colour.

GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor

1 1 1 1 1 1

X X X X X X

4 4 4 4 4 4

' ' ' ' ' '

0 0 0 0 0 0

" " " " " "

X X X X X X

7 7 7 7 7 7

''''''-

0 0 0 0 0 0

" " " " " "

= = = = = = = =

28.00 28.00 28.00 28.00 28.00 28.00

sft sft sft sft sft sft @ Tk 5112.00 / sqm = Tk 0.798 lac

168.00 sft 15.61 sqm

45
CE 109 b

14.4.3

Supplying, fitting and fixing of Aluminium sliding doors as per the U.S. Architectural Aluminium Manufacturers Association (AAMA) standard specification having 1.5 mm thick outer bottom (size 75.50 mm, 17.79 mm, 0.528 kg/m), 1.5 mm thick outer top (size 75.50 mm, 26.80 mm, 0.78 kg/m) 1.5 mm thick shutter top (size 33 mm, 26.80 mm, 0.536 kg/m), 1.5 mm shutter bottom (size 60 mm, 24 mm, 0.736 kg/m), 1.5 mm thick outer side(size 75.50 mm, 19.90 mm,0.616 kg/m) 1.5 mm thick shutter lock (size 49.20 mm, 26.20 mm, 0.661 kg/m), 1.5 mm thick inter lock (size 34.40 mm, 32.10 mm, 0.665 kg/m), 1.5 mm thick shutter divider (size 31.75 mm, 0.535 kg/m) sections all Aluminium members (Total weight 14.789 kg) will be anodized to Aluminium Bronze/Silver colour with a coat not less than 15 micrones in thickness and density of 4 mg per square cm etc. including all accessories like handle, sliding door key lock , sliding door wheel, sliding door mohiar, sliding door neoprene, bolts & nuts in/c sealants, keeping provision for fitting 5mm thick glass including labour charge for fitting of accessories, making grooves & mending good damages, carriage, and electricity complete in all respect as per drawing and accepted by the Engineer. Size: 2100 mm x 2100mm , Colour : Silver colour.

GF 1st Floor

1X 1X

4' 4' -

0" X 0" X

7'7'-

0" = 0" = = =

126.00 sft 210.00 sft 336.00 sft 31.22 sqm @ Tk 2187.00 / sqm = Tk 0.683 lac

46
CE 104 a
13.4.1

Supplying fitting, fixing window grills of any design made with 25 x 6 mm F.I. bar in/c fabrication, welding, cost of electricity workshop charges, carriage, cutting grooves, mending good the damages, tools & plants etc. complete for all floors as per direction of the engineer-in-charge. (Total weight per sqm should be min 42.88 kg. & add or deduct @ Tk.9.04 for each kg. excess or less respectively)

Quantity same as aluminium sliding window Quantity same as aluminium composite fixed window Quantity same as aluminium fixed fanlight

= 10458.75 sft = 1608.00 sft

= 10459.04 sft = 22525.79 sft = 2092.70 sqm @ Tk 1822.00 / sqm = Tk 38.129 lac

Page No 57

47
(CE 106 )
13.8.

Supplying, fitting and fixing of verandah grills made of 3/8" dia M.S rod placed @ 3 " c/c both ways fitted with outer frame of M.S. Angle 1" X 1" X 1/4 " as per drawing and approved and accepted by the Engineer.
Mid void

stair side

24 24 24 24 24

X X X X X

8 8 20 7 3

' ' ' ' '

0 7 0 9 11

" " " " "

X X X X X

6 6 6 6 6

'''''-

0 0 0 0 0

" " " " "

= = = = = = =

1152.00 1236.00 2880.00 1116.00 564.00

sft sft sft sft sft @ Tk 1392.00 / sqm = Tk 8.985 lac

6948.00 sft 645.48 sqm

48
CE 116 b
14.12.3

Supplying fitting and fixing of Aluminium fixed louver as per the U.S. Architectural Aluminium Manufacturers Association (AAMA) standard specification having 1.5mm thick wall frame (size 76.20 mm, 38.10 mm, 0.707 kg/m), 5 mm thick louver section (size 55.02 mm, 37.39 mm, 0.22kg/m) & 2.50 mm thick louver outer section (size 39.67 mm, 15.06 mm, 0.265 kg/m) and inner inclined Aluminium louver section fixed with above mentioned frame and all Aluminium members (Total weight 7.992 kg) will be anodized to Aluminium Bronze/silver color with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc. including all accessories, neoprene, sealant, nuts & bolts etc. complete in all respect as per drawing and accepted by the Engineer. Colour : Silver colour.

quantity same as aluminium top hung window deduct, basement top hung window area net area

= 10459.04 sft = 936.00 sft = = 9523.04 sft 884.71 sqm @ Tk 5346.00 / sqm = Tk 47.297 lac

49
CE 117 b
14.14.1

Supplying, fitting and fixing in Aluminium door frames Partitions/ windows distortion free foreign made 5 mm thick glass of approved quality and shade including cost of fitting fixing all necessary accessories etc. complete in all respect as per drawing and direction of the engineer-in-charge. Clear glass.
Quantity BF from aluminium swing door Quantity BF from aluminium sliding door Quantity BF from aluminium sliding window Quantity BF from aluminium fixed composite window Quantity BF from aluminium fixed fanlight

= 168.00 sft = 336.00 sft = 10458.75 sft = 1608.00 sft = 10459.04 sft = 23029.79 sft = 2139.52 sqm @ Tk 593.00 / sqm = Tk 12.687 lac

50
CE 117 d

Supplying, fitting and fixing or pesting screen colour paper on glass pan approved and accepted by the Engineer. = 100.00 sqm @ Tk 3113.00 / sqm = Tk 3.113 lac

51
CE 171
22.9.

Supplying, fitting, fixing of uPVC plastic door/window frame having specific gravity 1.35 - 1.45, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacurer standards or ASTM, BS/ISO/IS standards fitted & fixed in brick wall/ R.C.C wall with 6 nos GI clamp, 4nos inner joint GI clamp, 2 nos outer GI joint clamp, 16 nos revit making necessary grooves & and mending good the damages, finishing, curing, carraige etc complete in all respect accepted by the Engineer. 8 9 9 9 9 9 X X X X X X 16 16 16 16 16 16 ' ' ' ' ' ' 6 6 6 6 6 6 " " " " " " = = = = = = = = 132.00 148.50 148.50 148.50 148.50 148.50 874.50 266.62 rft rft rft rft rft rft rft rm @ Tk 410.00 / rm = Tk 1.093 lac

GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor

Page No 58

52
CE 172 b
22.10.2

Supplying, fitting, fixing of uPVC/hollow or solid plastic door shutter having specific gravity 1.35 - 1.45, thckness 1.7 mm-2.2 mm, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacurer standards or ASTM, BS/ISO/IS standards of different sizes fitted fixed with uPVC plastic door frame weigning 5.82 kg/m2 with at least 3 nos hinges by min 64 nos 3.17 mm & 3.97 mm 12.7 mm long revits, 12 nos 25.4 mm screws, 9.38 mm, 150 mm long tower bolts 2 nos, 146 mm plastic handle by revit 2 nos, plastic inner joint 234.95 mm x 127 mm clamp, 76.2 mm x 57.15 mm, 25 mm dia 1 no hasbolt, special type roundlock, carraying the same to the site & local carraige etc. complete in all respect accepted by the Engineer. 760 mm X 2130 mm uPVC plastic shutter ( solid )

GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5 th Floor

8 9 9 9 9 9 total = 53

nos nos nos nos nos nos @ Tk 3447.00 each = Tk 1.827 lac

53
CE 77 a
11.2.

Supplying , fitting and fixing M.S. Flat bar clamp of 225 X 38 X 6 mm size having bifurcated ends to door and window frames with necessary screws and uncasing inside the wall with cement concrete ( 1:2:4 ) etc. Complete and accepted by the Engineer.
GF to 5th floor

46 X 2 X 3 = 276

nos

@ Tk

49.00

each

= Tk

0.135 lac

54
CE 100
12.25

Supplying, fitting & fixing best quality heavy type 19 mm dia and to 300 mm long brass hasp bolt including cutting grooves in door shutter and frames, screws etc all complete approved and accepted by the Engineer.

Total no of hasp bolt

46

nos

@ Tk

305.00

each

= Tk

0.140 lac

55
CE 99 a
12.22.

Supplying, fitting , fixing of "King Brand" ( made in Korea / equivalent ) hydraulic door closer ( big size ) including all necessary tools and accessories etc all complete approved and accepted by the Engineer. = 20 nos @ Tk 1768.00 each = Tk 0.354 lac

56
CE 99 a
12.22.

Supplying, fitting , fixing of "King Brand" ( made in Korea / equivalent ) hydraulic door closer ( big

size ) including all necessary tools and accessories etc all complete approved and accepted by the Engineer. = 20 nos @ Tk 1768.00 each = Tk 0.354 lac

57
CE 99 c
12.24.

Supplying, fitting and fixing of best quality magnetic door shock absorber in/c all necessary tools and accessories etc. all complete approved and accepted by the Engineer. = 50 nos @ Tk 267.00 each = Tk 0.134 lac

58
CE 99 b
12.23.1

Supplying, fitting and fixing MORTICE door lock approved and accepted by the Engineer. = 50 nos @ Tk 1055.00 each = Tk 0.528 lac

59
CE 98 a
12.21.1

Extra cost for using brass fittings in place of iron fittings in doors for all floors approved and accepted by the Engineer. 46 X 3' 6" X 7'0" = = 1127.00 sft 104.70 sqm

@ Tk

154.00

/ sqm

= Tk = Tk

0.161 lac 2077.700 lac

Sub Total

Page No 59

Rate 2008 2011 BF

Total 2008 2011 Increase 06 to 08 2278.6015 2669.836 Increase 08 to 11

10,173.00

10399.00

0.552 0.563762

-31.8%

2.2%

1,084.00

0.993

-83.4%

-100.0%

190,899.00

214544.00

4.533

5.09499

43.4%

12.4%

3,755.00

4156.00

3.655 4.045489

15.5%

10.7%

Page No 60

Page No 61

2,879.00

3120.00

27.974 30.31522

-20.3%

8.4%

Page No 62

2,193.00

2436.00

3.276 3.639064

-17.9%

11.1%

Page No 63

2,665.00

2975.00

25.895 28.90714

-7.6%

11.6%

6,945.00

7994.00

2.097 2.413647

20.4%

15.1%

Page No 64

4,817.00

5193.00

0.752 0.810502

-5.8%

7.8%

1,823.00

2030.00

0.569 0.633668

-16.6%

11.4%

2,266.00

2570.00

47.421 53.78232

24.4%

13.4%

Page No 65

1,842.00

2070.00

11.890 13.36154

32.3%

12.4%

4,803.00

5674.00

42.493 50.19857

-10.2%

18.1%

787.00

856.00

16.838 18.31429

32.7%

8.8%

176.00

217.00

0.469 0.578556

-57.1%

23.3%

Page No 66

2,737.00

2960.00

1.451

1.5688

-20.6%

8.1%

60.00

73.00

0.166

0.20148

22.4%

21.7%

317.00

322.00

0.146

0.14812

3.9%

1.6%

1,931.00

2014.00

0.386

0.4028

9.2%

4.3%

1,931.00

2014.00

0.386

0.4028

9.2%

4.3%

190.00

215.00

0.095

0.1075

-28.8%

13.2%

1,218.00

1293.00

0.609

0.6465

15.5%

6.2%

360.00

382.00

0.377 0.399957 2471.6227 2886.373

133.8% 18.96

6.1% 16.8%

Page No 58

BF

2077.700 lac

60
CE 131 b

16.4.

on exterior surface applying as per manufacturer instruction 3 coat of Weather coat of approved quality and colour delivered from authorized local agent of the manufacturer in a sealed container complete in all respect in all floors and accepted by the Engineer.

1st floor to 4th floor

5th floor

6th floor

2 2 semi circular 2 2 22 2 2 2

X X X X X X X X

190 60 78 190 20 30 110 30

' ' ' ' ' ' ' '

0 0 6 0 0 0 0 0

" " " " " " " "

X X X X X X X X

60 60 60 12 12 12 12 12

' ' ' ' ' ' ' '

0 0 0 0 0 0 0 0

" " " " " " " "

= = = = = = = = = =

22800.00 7200.00 9420.00 4560.00 5280.00 720.00 2640.00 720.00

sft sft sft sft sft sft sft sft @ Tk 102.00 / sqm = Tk 5.055 lac

53340.00 sft 4955.41 sqm

61
CE 133 b

16.8.2

Plastic emulsion paint of approved best quality and colour delivered from authorized local agent of the manufacturer in a sealed container, applying to wall and ceiling in two coats over lime putty of specified brand applied on primer or sealer elapsing specified time for drying/recoating including cleaning drying, making free from dirt, grease, wax, removing all chalked & scaled materials, fungus, mending good the surface defects, sand paparing the surface and necessary scaffolding, spreading by brush/ roller/spray etc. all complete in all floor accepted by the Engineer. lime putty to be applied as per manufacturer instructions approved and accepted by the Engineer.

Walls
(i) GF for 10 " wall inside for 5 " wall both side Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

1 X 734.33 2 X 550.25

rft X 12 ' rft X 12 ' -

0" = 0" = = = = = = 0" = =

8812.00 sft 13206.00 sft 22018.00 sft 1127.25 605.00 1336.83 227.78 140.00 sft sft sft sft sft

8X

2' -

6" X

7'-

3436.86 sft 18581.14 sft

Net area
(ii) 1st Floor for 10 " wall inside for 5 " wall both side Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

1 X 636.17 2 X 491.50

rft X 12 ' rft X 12 ' -

0" = 0" = = = = = = 0" = =

7634.00 sft 11796.00 sft 19430.00 sft 1608.00 331.00 1535.63 136.67 157.50 sft sft sft sft sft

9X

2' -

6" X

7'-

3768.79 sft 15661.21 sft

Net area
(iii) 2nd Floor

Page No 59

for 10 " wall inside for 5 " wall both side Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

1 X 877.67 2 X 404.50

rft X 12 ' rft X 12 ' -

0" = 0" = = = = = = 0" = =

10532.00 sft 9708.00 sft 20240.00 sft 1711.50 60.00 1463.58 136.67 157.50 sft sft sft sft sft

9X

2' -

6" X

7'-

3529.25 sft 16710.75 sft 16710.75 sft

Net area
(iv) 3rd Floor Quantity same as 2nd floor (v) 4th Floor Quantity same as 3rd floor (vi) 5th Floor for 10 " wall inside for 5 " wall both side parapet wall Deduction aluminium sliding window aluminium composite fixed window aluminium fixed fan light partex flush door plastic door

= =

16710.75 sft

1 X 811.67 2 X 464.50 10 X4X 20.00

rft X 12 ' - 0 " = rft X 12 ' - 0 " = rft X 10 ' - 10 " = = = = = = 0" = = Net area =

9740.00 sft 11148.00 sft 8666.67 sft 29554.67 sft 2589.00 60.00 2259.83 136.67 157.50 sft sft sft sft sft

9X

2' -

6" X

7'-

5203.00 sft 24351.67 sft

(vii) 6th Floor for 10 " wall both side Deduct, windows Deduct, Doors

2X

350 ' -

0 " X 12 ' -

0" = = = =

8400.00 sft 432.00 sft 136.67 sft 7831.33 sft

Total wall area to be painted Ceiling, column, lift wall etc


GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor 6th Floor

= 116557.60 sft

Ref , mark B of Item 16 deduct , basement plaster area Ref , mark C of Item 16 Ref , mark D of Item 16 same as 2nd floor same as 3rd floor Ref , mark E of Item 16 Ref , mark F of Item 16

= 110645.58 sft = 58938.29 = 52813.93 sft = 53053.93 sft = 53053.93 sft = 53053.93 sft = 46683.27 sft = 7210.00 sft = 317576.28 sft

Page No 60

Total wall + ceiling and others deduct wall tiles area Net area

= 434133.88 sft = 14402.67 sft

= 419731.21 sft = 38993.98 sqm

@ Tk

144.00 / sqm = Tk

56.151 lac

Approved best quality and colour synthetic polyvinyl distemper delivered from authorized local agent of the manufacturer in a sealed container, applying to wall & ceiling in 2 coats over a coat of brand specified primer or CE 132 sealer elapsing specified time for drying/ recoating matt finish including cleaning and sand papering making the 16.7 surface free from loose and flaky materials, dirt, grease, wax, polish, scraping all chalked & scaled materials, applying the paint by brush/rooller and necessary scaffolding etc. all complete in all floor accepted by the Engineer.

62

Basement floor

= =

58938.29 sft 5475.50 sqm

@ Tk

83.00 / sqm = Tk

4.545 lac

63
CE 129

16.1.

White washing by three coats, lime mixture prepared at least 12 hours before use, slacking stone lime, supply of gums, blue, stirring thoroughly, removing the floating materials from the mixer, surface cleaning to free from all foreign materials before application of each coat, applying one vertical & one horizontal wash for each coat & successive coat is to be applied after drying up of previous coat in/c hair brass, providing necessary scaffolding and cleaning plinth, floors, doors, windows, portions & ventilators by washing, rubbing, oiling if necessary after white wash for all floors in/c cost of water, electricity & other charges etc. complete in all respect accepted by the Engineer.

GF 1st Floor

1X 1X

40 ' 40 ' -

0 " X 40 ' 0 " X 40 ' -

0" = 0" = = =

1600.00 sft 1600.00 sft 3200.00 sft 297.29 sqm @ Tk 8.50 / sqm = Tk 0.025 lac

64
CE 137

French polishing to door and window frames and shutters three coats over a coat of priming including putty, cleaning finishing and polishing with sand paper etc. all complete in all floor accepted by the Engineer. 46 X 3' 4" X 7'0" = = = = 1073.33 1073.33 2683.33 249.29 sft sft X 2.5 sft sqm @ Tk

16.14 single swing

96.00 / sqm = Tk

0.239 lac

65
CE 131d

16.6.

Painting to door and window frames and shutters in two coats with approved best quality and colour of synthetic enamel paint delivered from authorized local agent of the manufacturer in a sealed container, having highly water resistant, high bondibilty, flexible, using specfic brand thinner applied by brass/roller/spray over a coat of priming elapsing time for drying including surface cleaning from dust, oil or dirt, smoothening, finishing and polishing with sand paper and necessary tools, scaffolding, testing charges etc. all complete in all floors approved and accepted by the Engineer.

area same as window grill area

= 22525.79 sft 2092.70 sqm

@ Tk

101.00 / sqm = Tk

2.114 lac

Page No 61

66
CE 61

08.4.

Supplying fan hook of 16 mm diameter M.S. Rod ( one meter straight length ) having rounded hook at the middle of bar in proper size so as to be concealed within fan cup including fabrication and fitting fixing in all floors accepted by the Engineer.
GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor

40 42 64 64 64 64 338

nos nos nos nos nos nos nos

@ Tk

61.00 each

= Tk

0.206 lac

67
CE 157 d

20.7.4

Providing nosing to the Nose of tread of stair including supplying 3 nos of 75 mm long 12 mm X 3 mm F.I bar clamp with bifurcated ends in each treads including fitting and fixing with the angle by welding including fitting and fixing the angle by cutting grooves in RCC , fixing and finishing and the same with CC ( 1:2:4 ) etc., cost of electricity all complete and accepted by the Engineer. Providing 1.5 " X 1.5 " X 1/4 " brass angle to the nosing of stair case.

GF

1st Floor

2nd Floor

3rd Floor

4th Floor

5th Floor

2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

X X X X X X X X X X X X X X X X X X

2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2

X X X X X X X X X X X X X X X X X X

12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12

X X X X X X X X X X X X X X X X X X

3 4 3 5 3 4 5 3 4 5 3 4 5 3 4 5 3 5

' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' ' '

0 8 6 0 0 8 0 0 8 0 0 8 0 0 8 0 0 0

" " " " " " " " " " " " " " " " " "

= = = = = = = = = = = = = = = = = = = =

144.00 224.00 168.00 240.00 144.00 224.00 240.00 144.00 224.00 240.00 144.00 224.00 240.00 144.00 224.00 240.00 144.00 240.00

rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft @ Tk 817.00 /rm = 8.947 lac

3592.00 rft 1095.12 rm

Supplying 100 mm inside diameter best quality uPVC rain water down pipe fitting, fixed in positon with head and 68 CE 230 b1 shoes, bends, min.20 mm width F.I bar clamp and nails, and including all accessories such as round grating / 26.31 doomed roof grating bands, sockets approved and accepted by the Engineer. 60 X 72 ' 0" = 4320 rft = 1317.07 rm

@ Tk

311.00 /rm

= Tk

4.096 lac

Sub Total =

Tk

2159.078 lac

Page No 62

Rate 2008 2011

Total 2008 2011 Increase 06 to 08 Increase 08 to 11

BF

2471.623 2886.373

138.00

166.00

6.838 8.225975

35.3%

20.3%

Page No 63

Page No 64

161.00

186.00

62.780 72.52881

11.8%

15.5%

105.00

122.00

5.749 6.680111

26.5%

16.2%

12.00

15.00

0.036 0.044593

41.2%

25.0%

178.00

230.00

0.444 0.573362

85.4%

29.2%

123.00

150.00

2.574 3.139046

21.8%

22.0%

Page No 65

81.00

95.00

0.274

0.3211

32.8%

17.3%

888.00

966.00

9.725 10.57888

8.7%

8.8%

552.00

524.00

7.270 6.901463

77.5%

-5.1%

2567.313 2995.366

18.91%

16.7%

Page no 62

B.F

2159.078 lac

69
CE 140

17.2.

Constructing surface drain of 600 mm (Av) depth and 225 mm clear width at the bottom and 525 mm at the top having 125 mm thick cement concrete (1:2:4) curb up to 300 mm from the bottom over one layer of polythene on top brick flat soling and the side slopes of the remaing 300 mm height provided with 125mm thick lst class brick work in cement mortar (1:6) in/c minimum 12mm thick cement sand ( F.M 1.2 ) plaster (1:3) in/c neat cement finishing the surfaces and back of the drain up to 150 mm below ground level with fresh cement , curing at least for 7 days in/c excavation of all kinds of soil, back filling with fine sand (F.M. 0.8) consolidating and dressing, in/c cost of water, electricity, other charges etc complete and accepted by the Engineer. ( Cement : CEM - II / A - M )

2X 1X

200 ' - 0 " = 150 ' - 0 " = = =

400.00 150.00 550.00 167.68

rft rft rft rm

@ Tk

1280.00 / rm

= TK

2.146 lac

70

CE 139

Constructing surface drain of 300 mm clear width and depth up to 300 mm in brick masonry with 125 mm thick check wall in cement mortar (1:6) over av. 75 mm thick cement concrete base (1:3:6) over one layer of brick flat soling. The surface having 17.1 minimum 12mm thick cement sand ( F.M 1.2 ) plaster (1:3) and neat cement finishing with cement , curing at least for 7 days in/c excavation in all kinds of soil, back filling with fine sand (F.M. 0.8), consolidating and dressing, cost of water, electricity, other charges etc complete and accepted by the Engineer. ( Cement : CEM - II / A - M )

Ramp front

1X 1X 2X

30 ' - 0 " = 120 ' - 0 " = 40 ' - 0 " = = =

30.00 120.00 80.00 230.00 70.12

rft rft rft rft rm @ Tk 624.00 / rm = TK 0.438 lac

71
CE 141

17.3.

Providing apron with 50 mm thick cement concrete (1:2:4) with cement (conforming to BDS 232), coarse sand and picked jhama chips in/c breaking chips and one layer brick flat soling at bottom with lst class or picked jhama bricks in/c cutting earth for preparation of bed and filling the interstices with local sand (F.M. 0.8) in/c finishing, dressing, curing at least for 7 days etc. all complete, in/c cost of water, electricity, other charges accepted by the Engineer. ( Cement : CEM - II / A - M )

left and right side front and back side

2X 2X

192 ' - 0 " = 122 ' - 0 " = = = =

384.00 244.00 628.00 3140.00 291.71

rft rft rft X 5'-0" sft sqm

@ Tk

434.00

/ sqm = TK

1.266 lac

Page no 63

72
CE 155 c

20.4.

Supplying, fitting and fixing 12 mm dia G.I pipe stair railing of any standard height of any design & shape with 50 x 50 x 6 mm M.S. plate at the base f 12 mm dia G.I. Pipe and fitted andfixed by welding. Placing the pipes vertically @ 125 mm c/c (2 Nos. in each steps) 150 mm ecbeded into the R.C.C tread of stair case after cutting grooves and mending good the damages with C.C. & providing 38 x 6 mm F.I. bar on the top of G.I. pipe to provide wooden/G.I. pipe hand rail of any design in/c polishing painting etc. all complete and accepted by the Engineer. ( Exposed area of railing will be considered for measurement. rate is excluding cost of paint) Supplying , fitting and fixing stainless steel ( S S ) stair railing of standard height with 2 mm thick 2.5 " dia pipe for hand - rail as per drawing and accepted by the Engineer. ( i ) GF
main entry stair railing , basement stair GF Stair : corner stair short side stairs long side stairs

5 4 4 3.14 8 8

2X
middle stairs

X X X X X X 3.14 X 4X 2X

4 9 11 3 11 11 5 11 28

' ' ' ' ' ' ' ' '

0 9 8 8 8 8 6 8 2

" " " " " " " " "

= 20.00 = 39.00 = 46.67 = 11.51 = 93.33 = 93.33 = 34.54 = 46.67 = 56.33 = 441.39

rft rft rft rft rft rft rft rft rft rft

( ii ) 1st Floor
short side stairs long side stairs

2X
middle stairs

8X 8X 3.14 X 4X 2X

11 11 5 11 28

' ' ' ' '

8 8 6 8 2

" " " " "

= = = = = =

93.33 93.33 34.54 46.67 56.33 324.21

rft rft rft rft rft rft

( iii ) 2nd Floor


( quantity same as 1st floor ) =

324.21

( iv ) 3rd Floor
( quantity same as 2nd floor = )

324.21

( v ) 4th Floor
( quantity same as 3rd floor = )

324.21

( vi ) 5th Floor
short side stairs long side stairs

2X
middle stairs

8X 8X 3.14 X 4X 2X

11 11 5 11 28

' ' ' ' '

8 8 6 8 2

" " " " "

= = = = = =

93.33 93.33 34.54 46.67 56.33 324.21

rft rft rft rft rft rft

Total

= 2062.42 rft = 2062.42 X 3 ' - 0" = 6187.26 = 574.81 sft sqm = =

sft @ Tk 6169.00 /sqm = TK 35.460 lac

Page no 64

73
CE 156c

Supplying , fitting and fixing verandah railing with 2 mm thick 50 mm , 25 mm and 20 mm diameter stainless steel pipes as per approved design and accepted by the Engineer.

20.6
( i ) GF
Railing , Stair void side

stair side Flower bed

4 4 4 2 2 2

X X X X X X

18 8 8 11 11 15

' ' ' ' ' '

0 7 0 8 5 0

" " " " " "

= 72.00 = 34.33 = 32.00 = 23.33 = 22.83 = 30.00 = 214.50

rft rft rft rft rft rft rft

( ii ) 1st Floor
Railing :Stair void side

lobby stair side

4 4 4 1 2 2

X X X X X X

18 8 8 30 11 11

' ' ' ' ' '

0 7 0 0 8 5

" " " " " "

= = = = = = =

72.00 34.33 32.00 30.00 23.33 22.83

rft rft rft rft rft rft

214.50 rft

( iii ) 2nd Floor


( quantity same as 1st floor excluding = 184.50 lobby) rft

( iv ) 3rd Floor
( quantity same as 2nd floor = )

184.50 rft

( v ) 4th Floor
( quantity same as 3rd floor = )

184.50 rft

( vi ) 5th Floor
stair side

2X 2X

11 ' - 8 " = 11 ' - 5 " = =

23.33 rft 22.83 rft 46.17 rft

Total

= 1028.67 = 1028.67 = 2571.67 = 238.914 rft X 2 ' - 6" sft sqm sft @ Tk 6633.00 /sqm = TK 15.847 lac

74

CE 186 a

Single layer brick flat soling in road work with lst class or picked jhama bricks as per alignment, camber and grade including filling joints with sand (F.M. 0.50) etc. complete as per direction of the engineer-in-charge including cost of all materials and 24.4 accepted by the Engineer. 2X 2X 340 ' - 0 " X 120 ' - 0 " X 20 ' 20 ' 0" = 0" = = = 13600.00 sft 4800.00 sft 18400.00 sft 1709.40 sqm @ Tk 169.00 /sqm = TK 2.889 lac

75
CE 186 b

24.5.

Brick on edges pavement in herring bone bond with lst class or picked jhama bricks as per alignment, camber and grade over 12 mm thick sand cushion (F.M. 0.50) including filling the joints with the same sand including cost of all materials and accepted by the Engineer. 2X 2X 340 ' - 0 " X 120 ' - 0 " X 20 ' 20 ' 0" = 0" = = = 13600.00 sft 4800.00 sft 18400.00 sft 1709.40 sqm @ Tk 276.00 /sqm = TK 4.718 lac

Page no 65

76
CE 187

24.7.

Brick on end edging (75 mm across the road) with lst class or picked jhama bricks and filling the gaps with fine sand (F.M. 0.50) in/c cutting trenches. true to level & grade, removing earth, refilling and ramming the sides properly including cost of all materials and accepted by the Engineer. 2 X 920 ' 0" = = 1840.00 rft 560.98 rm

@ Tk

40.00

/ rm = TK

0.224 lac

77
CE 152

19.6.

Supplying. fitting and fixing of rolling shutter of any design & shape made of 24 SWG G.P, sheet unit minimum 69 mm width having 10 mm & 12 mm dia Circular folding at ends ,rolled in machine, locked together properly to form rolling shutter, top of the shutter to be fitted w with circular spring box made of 22 BWG sheet, containing best quality spring made in China, nutted with 38 mm G.I. pipe at one end and the other end nutted to shutter in/c fitting the G.I. pipe again with 375 x 300 x 6 mm pankha at ends with side guide channel (side channel consist of 50 x 100 x 6 mm M.S. plate with 2 x 19 x 3 mm F.I. bar, middle channel consist of 2 x 150 mm x 6 mm M.S. plate with 2 x19 mm x 6 mm Fixed to wall or coloumn with clamps embeded in R.C.C. part by cement concrete (1:2:4) in/c cutting holes (minimumm 3 x 25 mm x6 mm) mending the damages, finishing, curing, bottom end of shutter fitted to folded G.P. sheet (min 125 mm width in two layers), which is again fitted to 25 x 25 x 3 mm angle, providing handle (with F.I. bar 25 x 6 mm riveted) and locking arrangement in both sides, painting two coats with approved colour and brand of synthetic enamel paint over a coat of priming etc. complete in all respect as per drawing design accepted by the Engineer. ( Rate is excluding cost of paint)

Front entrance

2X

18 ' - 0 " X

10 ' -

0" = =

360.00 sft 33.44 sqm

@ Tk

3165.00

/sqm = TK

1.059 lac

78
CE 147 a

19.1.1

Manufacturing, supplying, fitting and fixing collapsible gate of any design & shape made of 3/4" x 3/8" x 1/8" channel placed @ 112 mm c/c vertically and connecting the same with each other by 20 x 3 mm M.S flat bar scissors 525 mm/ 600 mm long provided in 3 rows in/c cutting the different M.S. members to required sizes, fabricating, welding, riveting with required size rivets, providing requried size wheels, pulling handles on both sides, suitable locking arrangement, electrodes, greees and finally placing the same in position in between 2 (two) Nos. 50 x 50 x 6 mm M.S. Tee rail made by welding 2 Nos. 50 x 6 mm M.S. flat bar fitted and fixed at top and bottom with R.C.C. lintel/roof slab. floors and side wall with required Nos. 150 mm to 225 mm long 38 x 6 mm M.S. flat bar clamps one end welded with the gate member and the other end bifurcated and embedded in C.C. at the respective point in/c cutting holes and mending good the damages by pouring concrete (1:2:4) into the holes & finishing, etc complete, painting 2 (two) coats with approved best quality synthetic enamel paint over a coat of anticorrosive painting, both end carraige, in/c greesing, electodes, curing etc. complete as per drawing & design and accepted by the Engineer. (Rate is excluding cost of paint)

Side entrance

2X 1X 1X

7' - 9" X 7' - 6" X 7' - 3" X

7'7'7'-

0" = 0" = 0" = = =

108.50 sft 52.50 sft 50.75 sft 211.75 sft 19.67 sqm @ Tk 2104.00 /sqm = TK 0.414 lac

79

Supplying fitting and fixing of 62 mm X 62mm X 10 mm M.S angle each of 3'-0" height in each of four corner of column , all

analysis placing in position with clamping with royal plug or any other means as per design , mending good the damages, etc. all complete in

Basement floor

56 X

3'-

0" = =

672.00 rft 204.88 rm

@ Tk

250.00

/ rm = TK

0.512 lac

Page no 66

80

CE 56 a

Extra rate over the rate of concrete ( materials, consumables and laying / placing concrete ) of RCC works in Columns, Capitals, lift walls and walls where the free height of the structure exceeds 4 meter ( Rate is considered for the height of each additional 4 ( four ) 26.31 meter or part)
GF to 1st Floor exposed column ( double ht column )

8X

2' - 0" X

2'-

0" = = =

32.00 sft X 10 ' 320.00 cft 9.06 cum @ Tk

92.00

/ cum = TK

0.008 lac

81
CE 56 c

Extra rate over the rate of formwork / shuttering ( steel ) of RCC works in Columns , Capitals, lift walls and walls where the free height of the structure exceeds 4 meter ( Rate is considered for the height of each additional 4 ( four ) meter or part)

26.31

GF to 1st Floor exposed col

8 X ( 2'

+ 2' ) X 2 X 10 '

= =

640.00 sft 59.46 sqm

@ Tk

16.00

/ sqm = TK

0.010 lac

82

CE 56 d

Extra rate over the rate of concrete ( materials, consumables and laying / placing concrete ) of RCC works in Tee beams, Ell beams and rectangular beams where the free height of the structure exceeds 4 meter ( Rate is considered for each additional meter height 26.31 )
waffle roof beams

1/2 X 3.14 X 25'-0" X 1'-0" X 1'-6"

= =

58.87 cft 1.67 cum

@ Tk

94.00

/ sqm = TK

0.002 lac

83
CE 56 f

Extra rate over the rate of formwork / shuttering ( steel ) of RCC works in Tee beams, Ell beams and rectangular beams where the free height of the structure exceeds 4 meter ( Rate is considered for each additional meter height )

26.31
1/2 X 3.14 X 25'-0" X ( 1'-0" + 3'-0" ) = = 157.00 sft 14.59 sqm

@ Tk

39.00

/ sqm = TK

0.006 lac

84

CE 56 g

Extra rate over the rate of concrete ( materials, consumables and laying / placing concrete ) of RCC works in floor/roof slab, cantilever slab, waffle slab and drop panels where the free height of the structure exceeds 4 meter ( rate is considered for each 26.31 additional meter height )

quantity same as mark A of item 10 (D)

39.10 cum

@ Tk

94.00

/ cum = TK

0.037 lac

85
CE 56 h

Extra rate over the rate of formwork / shuttering for RCC works in floor/roof slab, cantilever slab, waffle slab and drop panels where the free height of the structure exceeds 4 mm ( rate is considered for each additional meter height )

26.31
quantity same as mark B of item 10 (D) = 434.83 sqm @ Tk 23.00 / sqm = TK 0.100 lac

86
CE 67

Providing and making welded splice by welding of minimum 300 mm length at the lap of main reinforcement in re-bar cage to be placed in bore-hole / where necessary by electric arc welding with highly oxidized electrodes making the joint prominent and accepted 26.31 by the Engineer. ( Rate is inclusive of all materials labour, tools, plants, electricity and all equipment )

In Column / Beam

100 X

25

0'-

6" =

1250.00 inch

@ Tk

3.57

/inch = TK

0.045 lac

Page no 67

87

CE 118

Supplying , fitting and fixing of 4 mm thick Aluminium composite Panel ( European origin ) in column , beam and wall surface providing with minimum 50 X 50 X 1.5 mm aluminium section including supply of necessary hardwares, consumables, scaffolding etc. approved 14.15 and accepted by the Engineer. Before commencing the work, the Contractor shall submit sample of aluminium composite panel, aluminium sections, hardware and consumables along with evidence of origin / brand / manufacturer, catalogue and method statement for executing the work to the Engineer for approval. However, Engineer's approval shall not relieve the Contractor of his responsibilities and obligations under contract.

6 X 2 X 3.14 X ( 12.5 / 12 ) X 24'-0" = =

942.00 sft 87.51 sqm

@ Tk

6542.00

/ sqm = TK

5.725 lac

88
CE 1c

01.1.3

Engineer's site office of minimum 38 sqm plinth area with providing security fencing, 5 kva stand by Generator , IBM compatible PC with monitor, uninterrupted power supply ( UPS ), Laserjet printer ( minimum 25 ppm ) , furniture, first aid box, safety helmet, level / theodolite / EDM, consumables, stationaries etc

1 office

( L.S )

= TK

3.506 lac

Grand Total

2233.489

lac

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Page no 68

Rate 2008

2011

Total 2008

2011

Increase 06 to 08

Increase 08 to 11

BF

2567.31291 2995.366

1,663.00

2000.00

2.789 3.353659

29.9%

20.3%

818.00

1010.00

0.574 0.708232

31.1%

23.5%

581.00

723.00

1.695 2.109086

33.9%

24.4%

Page no 69

5,664.00

5839.00

32.557 33.56318

-8.2%

3.1%

Page no 70

7,862.00

8717.00

18.783

20.8261

18.5%

10.9%

243.00

327.00

4.154 5.589744

43.8%

34.6%

396.00

535.00

6.769 9.145299

43.5%

35.1%

Page no 71

61.00

83.00

0.342

0.46561

52.5%

36.1%

4,033.00

4818.00

1.349 1.611371

27.4%

19.5%

2,675.00

3066.00

0.526 0.603145

27.1%

14.6%

Page no 72

Page no 73

5,313.00

5455.00

4.650 4.773885

-18.8%

2.7%

364,472.00 427192.00

3.645

4.27192

4.0%

17.2%

2645.145

3082.4

18.43%

16.5% 0.380078

Page no 34

Rate Analysis for Item No 4 (b) Supplying , fitting & fixing of Tempered glass ( fixed ) considering 1 no of glass ( 3' - 0" X 7' - 0" ) A. Cost of Materials (i) Tempered glass in/c 5% wastage (ii) Protector bit (iii) Alu. Fixed Section ( CE 117 b ) silver color : : : 22.05 21.00 24.00 sft sft sft @ Tk @ Tk @ Tk 300.00 / sft 6.00 / sft 167.30 / sft = Tk = Tk 6615.00 126.00 = 21.00 sft

Contractor's Profit 10 % Overhead expenses 3.50% Vat 4.50 % Grand Total Rate per sft Rate per sqm Say Tk = = Tk Tk 607.51 6539.21

= Tk 4015.20 Tk 10756.20 = Tk 1075.62 = Tk 376.47 Tk 12208.29 = Tk 549.37 = Tk 12757.66

6539 /= per sqm

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Page no 35

Rate Analysis for Item No 27

Providing weather coat Taking 100.00 sft (i) Cost of weather coat ( 4 liter covers 350 sft area ) (ii) Cost of wall primer (iii) Painter (iv) Ordinary labour (iv) Scaffolding, carrying, cleaning, sand papering, : : : : 1.14 0.80 1.50 1.50 Liter @ Tk Liter @ Tk nos nos @ Tk @ Tk 162.50 / Liter = Tk 156.00 / Liter = Tk 160.00 /person = Tk 100.00 /person = Tk ( L.S ) = Tk Tk Tk = Tk = Tk = Tk 185.71 124.80 240.00 150.00 50.00 750.51 101.32 851.83 38.33 890.17

making the surface defect : free etc

Add 10% contractors profit , 3.50% overhead charge = 13.50 % Vat = 4.50 % Grand Total Rate per sft Rate per sqm Say Tk = = Tk Tk 96.00 8.90 95.82 / sqm

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Page no 36

Page no 37

Rate analysis for Item no 55 Manufacturing, supplying, fitting and fixing of stainless steel pipe stair railing Taking 29'-0" X 3'-0" = 87.00 sft

A. Cost of material (i) 2.5" dia SS pipe ( foreign made ) Horizontal

Vertical

1 1 1 0.5

X X X X

13 0 13 3

' ' ' '

6 8 4 3

5% wastage (ii) 1" dia SS pipe ( foreign made ) Vertical 10 10

" = 13.50 " = 0.67 " = 13.33 " = 1.63 = 29.13 = 1.4563 30.58

rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft rft 0.50 0.50 5.00 10.00 10.00 23.00 nos nos nos nos nos nos

@ Tk

190.00 / rft

= Tk

5810.44

X 2 ' 11 1/2 " = 29.58 X 3 ' 1 1/2 " = 31.25 = 60.83 5% wastage = 3.0417 63.88 (iii) 3/4" dia SS pipe ( foreign made ) Horizontal 10 X 13 ' 10 " = 138.33 5 X 1' 0 " = 5.00 = 143.33 5% wastage = 7.1667 150.50 (iv) 2.5" dia SS ball top ( 2 nos/4) (v) 2.5" dia SS pipe socket ( 2 nos/4) (vi) 2.5" dia SS Elbow (vii) 1" dia SS Elbow (viii) 15 mm thick SS base plate ( 3" X 8" ) (ix) Anchor B. Cost of labour (i) Cost of labour for fabrication including welding rod, hire charge of welding machine, grinding machine etc (ii) Polishing work including polish materials, labour, hire charge of polish machine (iii) Carrying charge from market to workshop and workshop to site (iv) Labour charge for fitting , fixing including groove cutting and mending good the damages

@ Tk

70.00 / rft

= Tk

4471.25

@ Tk @ Tk @ Tk @ Tk @ Tk @ Tk @ Tk

55.00 625.00 160.00 600.00 200.00 120.00 35.00

/ rft each each each each each each

= = = = = = =

Tk Tk Tk Tk Tk Tk Tk

8277.50 312.50 80.00 3000.00 2000.00 1200.00 805.00

: : : :

87.00 87.00 87.00 87.00

sft sft sft sft

@ Tk @ Tk @ Tk @ Tk

120.00 / sft 20.00 / sft 6.00 / sft 6.00 / sft

= Tk 10440.00 = Tk = Tk = Tk 1740.00 522.00 522.00

sub total Add 10% contractors profit , 3.50% overhead charge 13.50 % Vat 4.50 % Total Rate per sft Rate per sqm = = Tk Tk 534.15 5749.61

= Tk 39180.69 Tk 5289.39 Tk 44470.08 Tk 2001.15 = Tk 46471.23

say Tk 5750 / sqm

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Assistant Engineer (Estimator )

Assistant Engineer (Staff Officer )

Executive Engineer

Page no 38

Mirpur PWD Division, Dhaka

Mirpur PWD Division, Dhaka

Mirpur PWD Division, Dhaka

Rate analysis for Item no 56 Manufacturing, supplying, fitting and fixing of stainless steel pipe stair railing Taking 16'-3" X 3'-0" = 48.75 sft

A. Cost of material (i) 2.5" dia SS pipe ( foreign made ) Horizontal

1 X 16 ' 5% wastage

4 " = 16.33 rft = 0.8167 rft @ Tk 190.00 / rft = Tk 3258.50

(ii) 1" dia SS pipe

17.15 rft ( foreign made ) Vertical 8 X 2 ' 9 1/2 " = 22.33 rft 5% wastage = 1.1167 rft 23.45 rft ( foreign made ) Horizontal 6 X 16 ' 4 5% wastage

@ Tk

70.00 / rft

= Tk

1641.50

(iii) 3/4" dia SS pipe

"= =

98.00 rft 4.9 rft 102.90 rft @ Tk 55.00 / rft = Tk 5659.50

(iv) M.S flat bar 1" X 1/4" 5% wastage (v) Anchor 3X 1X

= = = 6 = 8 = =

5.00 rft 4.25 lb ( 0.85 lb per rft ) 0.21 lb 4.46 lb 18.00 nos 8.00 nos 26.00 nos 2.00 12.00 4.00 nos nos nos @ Tk 15.43 / lb = Tk 68.86

(vi) 2.5" dia side Cap (vii) 3/4" dia side Cap (viii) 15 mm thick SS base plate ( 3" X 8" ) B. Cost of labour (i) Cost of labour for fabrication including welding rod, hire charge of welding machine, grinding machine etc (ii) Polishing work including polish materials, labour, hire charge of polish machine (iii) Carrying charge from market to workshop and workshop to site (iv) Labour charge for fitting , fixing including groove cutting and mending good the damages : : : :

@ Tk @ Tk @ Tk @ Tk

35.00 70.00 30.00 120.00

each each each each

= = = =

Tk Tk Tk Tk

910.00 140.00 360.00 480.00

48.75 48.75 48.75 48.75

sft sft sft sft

@ Tk @ Tk @ Tk @ Tk

120.00 / sft 25.00 / sft 8.00 / sft 7.50 / sft

= Tk = Tk = Tk = Tk

5850.00 1218.75 390.00 365.63

sub total Add 10% contractors profit , 3.50% overhead charge 13.50 % Vat 4.50 % Total Rate per sft Rate per sqm = = Tk Tk 494.93 5327.46

= Tk 20342.73 Tk 2746.27 Tk 23089.00 Tk 1039.01 = Tk 24128.01

say Tk 5327 / sqm

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Page no 39

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Rate analysis for Item no 57 Manufacturing, supplying, fitting and fixing of stainless steel pipe stair Hand rail Taking 1 X 10'-0" = 10.00 rft

A. Cost of material (i) 2.5" dia SS pipe ( foreign made ) Inclined

1 X 10 ' 5% wastage

0 "= =

10.00 rft 0.5 rft 10.50 rft @ Tk @ Tk @ Tk @ Tk 190.00 / rft 35.00 each 70.00 each 120.00 each = Tk = Tk = Tk = Tk 1995.00 70.00 140.00 240.00

(ii) Anchor (iii) 2.5" dia side Cap (iii) 15 mm thick SS base plate ( 3" X 8" ) B. Cost of labour

1X 1X

2 = 2 =

2.00 nos 2.00 nos 2.00 nos

(i) Cost of labour for fabrication including welding rod, hire charge of welding machine, grinding machine etc (ii) Polishing work including polish materials, labour, hire charge of polish machine (iii) Carrying charge from market to workshop and workshop to site (iv) Labour charge for fitting , fixing including groove cutting and mending good the damages

: : : :

10.00 10.00 10.00 10.00

rft rft rft rft

@ Tk @ Tk @ Tk @ Tk

120.00 / rft 25.00 / rft 8.00 / rft 7.50 / rft

= Tk = Tk = Tk = Tk = Tk Tk Tk Tk

1200.00 250.00 80.00 75.00 4050.00 546.75 4596.75 206.85 4803.60

sub total Add 10% contractors profit , 3.50% overhead charge 13.50 % Vat 4.50 % Total Rate per rft Rate per rm = Tk = Tk 480.36038 1575.582

= Tk

say Tk 1576 / rm

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Page no 40

Rate Analysis for Item no 5

Supplying, fitting and fixing of Alico bond Considering 16'-0"X3'-0" = 48.00 A. Cost of Materials (i) Alico bon in/c 5% wastage (ii) 2" X 1.5 " Aluminium box in/c 5% wastage (iii) Rubber gaskit 3/4" X 3/4" (iv) Silicon, screw, Royel plugs etc B. Labour cost (i) Fitting, fixing (ii) Scaffolding in/c materials : : 48.00 48.00 sft sft @ Tk @ Tk 90.00 / sft 3.00 / sft Sub Total "B" = Tk = Tk Tk 4320.00 144.00 4464.00 : : : : 50.40 48.48 48.48 sft rft rft @ Tk @ Tk @ Tk 275.00 / sft 95.00 / rft 6.00 / rft ( L.S ) Sub Total "A" = Tk 13860.00 = Tk = Tk 4605.60 290.88 sft

= Tk 350.00 Tk 19106.48

C. Carrying cost

( L.S ) Sub total A + B + C Add 10% contractors profit , 3.50% overhead charge = 13.50 % Add 4.50% VAT Grand Total Rate per sft Rate per sqm = = Tk Tk 586.13 6309.11

= Tk 150.00 = Tk 23720.48 = Tk 3202.26 = Tk 26922.74 = Tk 1211.52 Tk 28134.27

Say Tk 6309.00 / sqm

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Page no 41

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Rate analysis for Item no 16 (b )

Supplying, fitting and fixing of fixed glass on door shutter Considering 01 X 2' -0" X 2' - 0" = A. Cost of material (i) Teak chambal wood for bit
Bit all around the glass Bit in middle of glass ( cross )

sft

8 4

X 2' X 2'

5% wastage

0 " = 16.00 0 " = 8.00 = 24.00 = 0.083 = 0.0415

rft rft rft X 1" X 0.5 " cft cft @ Tk 1010.00 / cft = Tk 125.75

0.12 cft (ii) 5 mm glass 1X 2' 0" X 2' 5% wastage 0 "= = 4.00 sft 0.2 sft 4.20 sft (iii) Cost of nails, screw, putty etc B. Labour cost (i) Carpenter (ii) Carpenter helper (L.S)

@ Tk

100.00 / sft

= Tk = Tk

420.00 40.00

: :

0.50 0.50

nos @ Tk nos @ Tk

150.00 each 100.00 each Sub Total

= Tk = Tk Tk = Tk = Tk = Tk

75.00 50.00 710.75 95.95 806.70 36.30 843.00

Add 10% contractors profit , 3.50% overhead charge = 13.50 % Vat = 4.5 % Grand Total Rate per sft Rate per sqm = = Tk Tk 210.75 2268.50

Tk

Say Tk 2269 / sqm

Page no 42

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Rate analysis for Item no 4(a)


Analysis of Item 4 Supplying , fitting & fixing of Tempered glass swing door shutter considering 1 no of glass ( 3' - 0" X 7' - 0" ) door A. Cost of Materials (i) Tempered glass door in/c all fitting and fixturers such as door closer, handle, bottom lock, bottom fittings, top fittngs etcin/c 5% wastage B. Cost of Labor fitting , fixing C. Cost of carrying : 1.00 nos @ Tk 21000.00 each = Tk 21000.00 = 21.00 sft

: :

1.00 nos sft ( L.S)

@ Tk

3500.00 each

= Tk = Tk

3500.00 500.00

Contractor's Profit 10 % Overhead expenses 3.50% Vat 4.50 % Grand Total

Tk 25000.00 = Tk 2500.00 = Tk 875.00 Tk 28375.00 = Tk 1276.88 = Tk 29651.88

Rate per sft Rate per sqm

= =

1412 Tk 15199 Tk

Sub-Assistant Engineer 1

Sub Divisional Engineer

Page no 43

Mirpur PWD Sub Division 2 Mirpur, Dhaka

Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Assistant Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Page no 44

Page no 45

Page no 46

Page no 47

Page no 48

Page no 49

Page no 50

Page no 51

Page no 52

Page no 53

Construction of IBRAHIM MEDICAL COLLEGE at Darussalam, Mirpur, Dhaka. Sub Head : Construction of Academic Building with Ancillary works.

ABSTRACT OF COST
( TK in lac )

SL NO 1 2 3 4 5 6

ITEM Civil construction work of Academic Building Internal Sanitary & water supply works of Academic Building Construction of Pump House Construction of 50,000 gallon capacity underground water reservoir Sinking of 38 mm dia Test and Observation Well & Installation of 150 mm X 300 mm dia shrouded production well with G.I pipe Internal Electrification work of Academic Building Total

AMOUNT 2233.489 34.644 4.429


18.693

15.142

2291.255

Sub-Assistant Engineer 1 Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub Divisional Engineer Mirpur PWD Sub Division 2 Mirpur, Dhaka

Sub-Asstt Engineer (Estimator ) Mirpur PWD Division, Dhaka

Assistant Engineer (Staff Officer ) Mirpur PWD Division, Dhaka

Executive Engineer Mirpur PWD Division, Dhaka

Construction of Ibrahim medical college


Calculation of depth of earth filling 1st line 2nd line 3rd line 4th line 5th line 6th line 7th line 8th line 9th line 97.27 + 96.09 + 96.14 + 94.21 + 93.04 + 93.12 + 94.37 + 93.75 + 92.72 + 93.49 + 93.33 + 93.49 = 1131.02 96.94 + 95.15 + 95.49 + 93.59 + 92.76 + 92.01 + 88.30 + 88.06 + 88.56 + 89.48 + 90.34 + 93.51 = 1104.19 96.91 + 95.18 + 93.57 + 93.46 + 91.91 + 89.01 + 86.83 + 88.67 + 90.91 + 90.86 + 90.31 + 91.21 = 1098.83 96.71 + 94.21 + 94.01 + 93.06 + 91.88 + 90.90 + 90.72 + 86.76 + 91.49 + 91.44 + 91.57 + 91.88 = 1104.63 96.21 + 93.22 + 92.87 + 91.62 + 90.86 + 90.91 + 86.50 + 87.71 + 92.39 + 88.39 + 90.44 + 93.04 = 1094.16 96.05 + 93.54 + 91.93 + 90.98 + 90.65 + 88.05 + 87.34 + 89.41 + 92.59 + 92.39 + 92.26 + 93.01 = 1098.20 96.61 + 92.25 + 90.80 + 89.79 + 88.24 + 87.53 + 87.88 + 92.36 + 94.09 + 93.69 + 93.84 + 95.10 = 1102.18 95.65 + 89.69 + 89.52 + 90.63 + 88.38 + 88.70 + 92.75 + 93.44 + 93.99 + 94.20 + 95.14 + 97.22 = 1109.31 95.75 + 90.39 + 90.14 + 90.94 + 91.02 + 91.74 + 93.54 + 94.59 + 94.65 + 98.02 + 98.60 + 98.05 = 1127.43 Total = 9969.95 Avg RL = 9969.95 9 X 12 = 92.31 ft

Avg Depth of filling

= 100.00 - 92.31 = 7.69 ft

ft

Construction of IBRAHIM MEDICAL COLLEGE Sub Head : Civil Construction of College Building
( Estimated cost :Tk 2233.489 lac only )

Vous aimerez peut-être aussi