Detailed estimate for second storey including roof of Masjid Sharief at Dara Harwan Srinagar.

S. no. 1 2 3 4 5 6 7 8 9 Sand Bajree Cement R/Fsteel Shuttering Roof truss timber (popular) Chowkhut Timber (silver) Window pan Frames Item of work Brick work Quantity Unit Rate/unit Amount (Rs) 19500 4950 4950 310 48 19.5 355 775 950 875 46 Total @ 15 % G. Total Say Rs 58500 24750 24750 54250 79200 34125 51475 38750 26600 24500 61870 478770 71816 550586 5.50 lacs

3 trucks 5 trucks 5 trucks 175 bags 1650 kgs 1750 sft 145 cft 50 cft 28 no 28 no 1345 sft

10 Wire gauge Frames 11 CGI sheets 12 13 Labour charges 14 15