TABLE 1 Production Data Shift Length Short Breaks Meal Break Down Time Ideal Run Rate Total

Pieces Reject Pieces TABLE 2 Support Variable Calculation Planned Shift Length - Breaks Production Time Operating Time Good Pieces TABLE 3 OEE Factor Availability Performance Quality Overall OEE Calculation Operating Time / Planned Prod. Time (Total Pieces/Operating Time)/ Ideal Run Rate Good Pieces / Total Pieces Availability x Performance x Quality / / / / Calculated Data = / = x Planned Production Time - Down Time Total Pieces - Reject Pieces Calculated Data = = = Minutes Minutes Minutes Calculated Data Minutes Minutes Each = Minutes Each =

Hours Breaks @ Breaks @ Minutes PPM (Pieces Per Minute) Pieces Pieces

Minutes Total Minutes Total

= =

OEE % = = = = % % % %