LV CABLES
Make: Riyadh Cables, Saudi Arabia.. Project :NEW AL-JOUF 132 KV S/S
Location: AL-JOUF.
Sheet1 of 2
Description
Inspect for physical damage Verify all cable connections per drawing. Check for proper cable support, clamping and blocking etc. Verify shield grounding as per design (single point, both ends, via voltage limiters, etc.) Check tightness of all bolted connections (torque wrench method). Check that phases are identifies and colorcoded. Check cable entry path as ducts are to be properly sealed. Visual Insulation, size and ratings conformation Check cable size against rating required. Electrical Tests
Observation
Remarks
Sl. No.
Description
Observation
Remarks
1. Phase continuity test. 2. Insulation Resistance Test with 2.5KV DC insulation tester.
LV CABLES
Make: Riyadh Cables, Saudi Arabia. Project: NEW AL-JOUF 132 KV S/S
Location: AL-JOUF.
Sheet 2 of 2
TESTED BY: Mohd. Al-Ojaimi Cont. Est. NAME: Ahmad Ibrahim Sabti SIGNATURE: