Vous êtes sur la page 1sur 25

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

1 Introduction : This document covers R.C. design of Standard Pile-caps for 1 pile, 2 piles, 3 piles,4 piles, 5 Piles & 6 Piles The R.C. design conforms to IS456-2000. Some Clauses from BS8110 are referred and used wherever IS clauses are not too clear. 2 Reference Documents : 1) IS 456-2000 2) SP 16 3) IS 1786-1985 : : : Plain and Reinforced Concrete Code of Practice ( Limit State Method) Design Aids for Reinforced Concrete to IS 456 Specification for High Strength Deformed Steel Bars and Wires for Concrete Reinforcement Structural Use of Concrete, Part 1: Code of Practice for design and construction.

4) BS8110 Part 1: 1997

3 Design Philosophy : Refer sketches furnished at the end of respective calculations for dimensional details of standard pile-caps. For description of symbols refer "Design Parameters" furnished at the start of each calculation. The Standard pile-caps are designed for the full Compression,Tension and Shear capacities of pile. Following three checks are carried out in design of pile-caps. A. Check for Punching Shear: ( For Factored Load) This check is carried out for pile caps having more than 2 piles where 2 way action of pilecap exists. The critical section for punching shear shall be at a distance of Dt eff/2 from the face of Clause 31.6 pedestal (while considering punching of pedestal into pilecap) .IS456 Actual Shear stress = Tv =Shear force at that section / (Dteff*Shear perimeter) Actual Shear stress shall not exceed Permissible shear stress ( ks x Tc ) Where Tc = 0.25 x Sqrt( fck) ks = (0.5 + bc) but not greater than 1 bc = ratio of short side to long side of the pedestal. If Tv < ks x Tc. No shear reinforcement is required for punching shear.. The pilecap depth is to be adjusted such that Tv is always less than ksTc. B. Check for Bending: ( For Factored Load)

Clause 31.6.3 .IS456

The critical section for bending shall be at the face of Pedestal. Bending moment Clause34.2. (Mxx and Mzz) is calculated at the face of pedestal. For calculating the bottom 3.2 ..IS456 reinforcement, bending moment due to the full Compression (for Conservative results) capacity of piles is calculated about the pedestal face in each direction and Bending moment due to the selfweight of pilecap is deducted from it. (Soil Wt. & Surcharge pressure ignored while calculating the bending moment for Conservative results.)
JOB NO CALCULATION NUMBER CIC-8002-00
DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


CLIENT: PROJECT: SUBJECT:
RIL KG-D6

2090/1419
REV PREPD. BY

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06

SH

OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

B. Check for Bending:continued Clause 26.3.3 Table 15 ..IS456 Ast min = 0.2% B x Dteff (Minimum Beam reinforcement ...for pilecaps with 2 pile and 3 piles Clause26.5.1.1 as these pilecaps predominintaly behave as beams.) ....IS456 The calculated bottom reinforcement is compared with Ast min and the greater of them is provided. The horizontal distance between main bars shall not be more than 180mm. Ast min = 0.12% B x Dt (Minimum slab reinforcement.for pilecaps with 4 pile and above as Clause26.5.2.1 ....IS456 these pilecaps predominantly behave like flat slab) For calculating the top reinforcement, bending moment due to the full tension capacity of piles, the selfweight of pilecap, soil weight and Surcharge weight is calculated about the pedestal face in each direction . The calculated top reinforcement is compared with 50% of Ast min and the greater of them is provided. (The minimum steel at Top is meant only for temperature and shrinkage crack control. For temperature and shrinkage control Astmin is the total minimum reinforcement for that section and hence only 50% Astmin is considered for top steel.) Ast min =0.5 x 0.2% B x Dteff (Minimum Beam reinforcement ...for pilecaps with 2 pile and 3 piles as these pilecaps predominintaly behave as beams.) Ast min = 0.5 x 0.12% B x Dt (Minimum slab reinforcement.for pilecaps with 4 pile and above as these pilecaps predominantly behave like flat slab) C. Check for One way shear: ( For Facotred Load) Clause 34.2.4.1 .IS456

The critical section for one-way shear shall be at a distance of Dteff from the face of the pedestal for maximum Compression load condition. The critical section for shear is at face of pedestal for maximum tension load condition. Design Shear strength of concrete 'Tc' shall be calculated based on %tension steel. Actual Shear stress =Tv=Shear force at that section / (Dteff*Pilecap Width) The enhancement of shear strength shall be taken into account in the design of sections near support by increasing design shear strength of concrete to 2Dteff x Tc / av av is the distance from the face of pedestal to the critical section = Dteff / 2 (The Clause for "Enhanced shear strength of sections close to support" is a new addition to IS456..2000. It has been based on and is in conformance to BS8110. The clause in British code( cl no 3.11.4.3 to 3.11.4.5) is referred here as it clearly defines "av" to be considered for Pile-caps.) Minimum shear reinforcement is not required in pile caps where Tv < Tc (enhanced if appropriate) D. Side Face Reinforcement: Side face reinforcement is provided to control temperature and shrinkage cracks. = 500 mm Width of pilecap prone to shrinkage & temperature cracks assumed
JOB NO CALCULATION NUMBER CIC-8002-00
DATE CHKD BY

Table 19IS456

Clause 40.5 .IS456

Clause 3.11.4.4 BS8110 Clause 3.11.4.4 BS8110

Clause 3.12.5.4 BS8110


EQPT. NO.

Aker Kvaerner Powergas


REV CLIENT: PROJECT:
RIL KG-D6

2090/1419
PREPD. BY

DATE

SUBJECT:

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06

SH

. OF .

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

R.C. Design of Pile Cap IPC1


2) Design Parameters: = 350 mm Assumed Pedestal Length = ' l2 ' = Assumed Pedestal Width = ' b2 ' = Depth of pilecap top = h=(FGL- TOC ) = Density of Soil = gd = Grade of Concrete = fck = Grade of Steel = fy = Surcharge intensity = sr = Clear Cover to Pilecap Reinforcement Bottom Cover d'b = Top Cover d't = Side Cover d's = 500 500 1.2 18 35 415 10 75 50 50 mm mm m 3 kN/m N/mm2 2 N/mm 2 kN/m mm mm mm

1) Pile and Pilecap Data: Diameter/size of Pile = d Capacity of Pile : Axial Compression = C Axial Tension = T Shear = S Thickness of Pile cap = Dt Spacing of Piles in Group = nd c/c distance between piles Dist. bet edge of pile & pilecap = E Length of Pile Cap = L Breadth of Pile Cap = B 3) Check for Punching Shear :

= 1040 kN = 350 kN = 68 kN = 800 mm = 5.7143 x ' d' = 2 m = 250 mm = 1.0 m = 1.0 m

This check is not applicable for Pilecap with 1 pile as the pedestal and pile are concentric and co-axial. 4) Check For Bending : Pile cap for single pile does not undergo bending as the pedestal and pile is concentric. The pilecap needs to be checked for axial compression and axial tension. The magnitude of compression and tension equal to the Pile capacities. a) Check for Axial compresssion : Maximum Compressive force = 1560 kN 2 Area of cross-section of pilecap = A = L x B = 1000 x 1000 = 1E+06 mm 2 Area of concrete Ac = A - Asc = 997587 mm Axial load carrying capacity of concrete (ignore reinforcement) Pu = 0.4 fck Ac = 13966 kN > 1560 kN Safe As the Concrete strength without any longitudinal reinforcement is more than the maximum compressive force provide nominal longitudinal reinforcement not less than 0.15 of cross-sectional area..... Clause 26.5.3.1 h ...IS456. Astmin required = 1500 mm2 Provide T 16 @ 6 Nos. top & bottom both ways Ast provided = 2412.7 mm2 b) Check for Axial tension : Maximum Tensile force = 525 kN Tension carrying capacity of reinforcement alone = 0.87 fy Ast = 871 kN > 525 kN Provided reinforcement Sufficient 5) Check for One Way Shear : This check is not applicable for Pilecap with 1 pile as the pedestal and pile is concentric. JOB NO CALCULATION NUMBER
CIC-8002-00
DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV

2090/1419
PREPD. BY

CLIENT: PROJECT: SUBJECT:

RIL KG-D6

Design Calculation for


Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

OF

C940001 R3

1 2 3 6) Side Face Reinforcement: 4 Side face reinforcement is provided to control temperature and shrinkage cracks. 5 Width of pilecap prone to shrinkage & temperature cracks = 500 mm from each face 6 7 a. Parallel to X axis Ast on E/F = 350.5 mm2 Provide 4 Nos - T 12 226.5 c/c 8 b. Parallel to Z axis Ast on E/F = 350.5 mm2 Provide 4 Nos - T 12 226.5 c/c 9 Astprovi. on E/F= 452.39 mm2 <300 SAFE 10 11 12 Provide Horizontal Ties to prevent Bursting due to high principal Tension 13 Provide 4 Nos - T 10 227 c/c 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

JOB NO

CALCULATION NUMBER

EQPT. NO.

Aker Kvaerner Powergas


REV CLIENT: PROJECT: SUBJECT:
RIL KG-D6

2090/1419
PREPD. BY DATE

CIC-8002-00
CHKD BY DATE

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

. OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

R.C. Design of Pile Cap IPC2


2) Design Parameters: = 350 mm Assumed Pedestal Length = ' l2 ' = Assumed Pedestal Width = ' b2 ' = Depth of pilecap top = h=(FGL- TOC ) = Density of Soil = gd = Grade of Concrete = fck = Grade of Steel = fy = Surcharge intensity = sr = Clear Cover to Pilecap Reinforcement Bottom Cover d'b = Top Cover d't = Side Cover d's = 1000 750 1.2 18 35 415 10 75 50 50 mm mm m kN/m3 N/mm2 N/mm2 kN/m2 mm mm mm

1) Pile and Pilecap Data: Diameter/size of Pile = d Capacity of Pile : Axial Compression = C Axial Tension = T Shear = S Thickness of Pile cap = Dt Spacing of Piles in Group = nd c/c distance between piles Dist. bet edge of pile & pilecap = E Length of Pile Cap = L Breadth of Pile Cap = B 3) Check for Punching Shear :

= 1040 kN = 350 kN = 68 kN = 1000 mm = 5.71428 x ' d' = 2 m = 250 mm = 2.85 m = 1.0 m

This check is not applicable for Pilecap with 2 piles as the pilecap spans only in one direction. 4) Check For Bending : a) Bottom Steel : Bending Moment at face of Pedestal : (Soil Wt. & Surchrage pressure Mxxmax=1.5{C(0.5nd-l2/2)-B*Dt*25((L-l2)/2)2 *.5 } = 763.96 kN-m Dteff(req) = Sqrt(Mxxmax/(0.138*fck*B)) = 397.70 mm ignored for Conservative results) Dteff(prov) = Dt - d'b -0.5*bar dia. = 915.00 mm Safe 2387.51 Ast(req) (for Mxx) = (0.5*fck*B*Dteff /fy)*{1-Sqrt(1-4.6Mxx/(fck*B*Dteff 2)} = mm2 1830.00 Ast(min) (for Mxx) = (0.2/100)*B*Dteff = mm2 a. Parallel to Z axis Required 20 T@ 132 c/c OR 7.604 Nos Ast(prov) = 2512 mm2 Provided 8 Nos - T 20 b) Top Steel : Mxxmax = 1.5*(T (0.5nd-0.5l2)+(Dt*25+gd*h+sr)*B*((L-l2)/2)2/2 ) = 298.82 kN-m Ast (req) (for Mxx) = (0.5*fck*B*Dteff /fy)*{1-Sqrt(1-4.6Mxx/(fck*B*Dteff 2)} 915.85 mm2 = Ast (min) (for Mxx) = 50% of (0.2/100)*B*Dteff = 915.00 mm2 a. Parallel to Z axis Required 16 T@ 219 c/c 4.557 Nos Ast(prov) = 1608 mm2 Provided 8 Nos - T 16 5) Check for One Way Shear : a) For Maximum Compressive load Shear Section Parallel to X axis Shear plane location 0.958 m from pedestal centre , Shear Force= 969.4 kN av = 0.4575 m from pedestal face % Steel = 0.275 Tc = 0.388 N/mm2 Enhanced Shear stress =2*Dteff * Tc /av = 1.552 N/mm2 Tv = 1.059 N/mm2 Tcmax= 3.70 N/mm2 Tcmax > Tv Safe Tc enhanced > Tv ... Hence Provide nominal shear reinforcement JOB NO CALCULATION NUMBER CIC-8002-00
DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


CLIENT: PROJECT: SUBJECT:
RIL KG-D6

2090/1419
REV PREPD. BY

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06

SH .

OF .

C940001 R3

1 Vus= 0.00 kN 2 Asvreq= 0.00 mm2 3 Asvmin required= 221.58 mm2 4 Shear reinforcement Provided T legged stirrups @ 12 2 200 c/c 5 Ast(prov) = 226.1 mm2 O.K 6 7 b) For Maximum Tensile load 8 The critical section for Shear (Parallel to X axis) is at the face of pedestal 9 Shear Force= 603.5 kN % Steel = 0.18 10 Tc = 0.318 N/mm2 11 Tcmax > Tv Safe Tv = 0.660 N/mm2 12 Vus= 312.90 kN 13 Asvreq= 189.43 mm2 14 15 Provided Shear Reinforcement OK Asvmin provided = 221.58 mm2 16 legged stirrups @ Provide T 12 2 200 c/c 17 Ast(prov) = 226.1 mm2 OK 18 6) Side Face Reinforcement: 19 Side face reinforcement is provided to control temperature and shrinkage cracks. 20 Width of pilecap prone to shrinkage & temperature cracks = 500 mm from each face 21 22 a. Parallel to X axis Ast on E/F = 457.5 mm2 Provide 5 Nos - T 12 215.5 c/c 23 b. Parallel to Z axis Ast on E/F = 457.5 mm2 Provide 5 Nos - T 12 215.5 c/c 24 Astprovi. on E/F= 565.49 mm2 <300 SAFE 25 Provide Horizontal Ties to prevent Bursting due to high principal Tension 26 Provide 5 Nos - T 12 216 c/c 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

JOB NO

CALCULATION NUMBER
CIC-8002-00
DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV CLIENT: PROJECT: SUBJECT:
RIL KG-D6

2090/1419
PREPD. BY

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH .

OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

R.C. Design of Pile Cap IPC3


General: This Pilecap is assumed to be comprised of 2 beams. The first beam spans between two piles and the second beam spans between the third pile and mid-span of first beam. Width of both beams = (d + 2xE). The top and bottom reinforcement (both directions) is calculated and provided within the beam width. Nominal steel (50% of Astmin in both directions) is provided in the balance portion of pile cap.
(Refer sketches at end of calc.)

1) Pile and Pilecap Data: Diameter/size of Pile = d = 350 mm Capacity of Pile : Axial Compression = C = 1040 kN Axial Tension = T = 350 kN Shear = S = 68 kN Thickness of Pile cap = Dt = 1000 mm Spacing of Piles in Group = nd = 5.7143 x ' d' c/c distance between piles = 2 m Dist. bet edge of pile & pilecap = E = 250 mm Length of Pile Cap = L = 2.582 m Breadth of Pile Cap = B = 2.850 m 3) Check for Punching Shear : a. For pile group : perimeter = (l2+Dteff+b2+Dteff)*2 = 7150.00 Tv=1.5(3C)/(Dteff*perimeter)= 0.717 ks calculated = 1.250 Tc = 1.479 4) Check For Bending : a) Bottom Steel : Bending Moment : X1 = 0.577nd-l2/2 = 0.654 X2 = 0.288nd-l2/2 = 0.078 Mzzmax=1.5{C(.5nd-b2/2)-Dt*25(d+.4)*((B-b2)/2)2*.5 }= Mxxmax=1.5{C*X1-Dt*(d+0.4)*25*(X1+d/2+0.2)^2/2 } = or 1.5{2*C*X2-Dt*B*25*(X2+d/2+0.2)^2/2 } Dteff(req) (for Mzz) = Sqrt(Mzz/(0.138*fck*beff)) = Dteff(req) (for Mxx) = Sqrt(Mxx/(0.138*fck*beff)) = Dteff(prov) = Dt - d'b -0.5*bar dia. =

2) Design Parameters: Assumed Pedestal Length = ' l2 ' = 1000 mm Assumed Pedestal Width = ' b2 ' = 750 mm Depth of pilecap top = (FGL- TOC) = h = 1.2 m Density of Soil = gd = 18 kN/m3 Grade of Concrete = fck = 35 N/mm2 Grade of Steel = fy = 415 N/mm2 Surcharge intensity = sr = 10 kN/m2 Clear Cover to Pilecap Reinforcement Bottom Cover d'b = 75 mm Top Cover d't = 50 mm Side Cover d's = 50 mm

mm N/mm2 > 1 2 N/mm

ks = 1 Tc > Tv Safe

m (Dist of pile from Pedestal face in -ve Z dir) m (Dist of pile from Pedestal face in +ve Z dir) 959.5 kN-m beff= 850 mm 1005.3 kN-m beff= 850 mm 483.44 mm 494.85 mm 912.50 mm

Safe

Ast (req) (for Mzz) = 3056.6 mm2 ( Parallel to X axis ) Ast (req) (for Mxx) = 3210.6 mm2 ( Parallel to Z axis ) Ast (min) (for Mzz) = 1551.3 mm2 Ast (min) (for Mxx) = 1551.3 mm2 i) Parallel to X axis in strip of width (d+2E)/2 on either side of the 2 lower piles (Beam in X direction). Required 6.23 Nos - T 25 Provide 7 Nos - T 25 Ast(prov) = 3434.4 mm2 ii) Parallel to Z axis in strip of width (d+2E)/2 on either side of the 3rd top pile (beam in Z direction) Required 6.544 Nos - T 25 Provide 7 Nos - T 25 Ast(prov) = 3434.4 mm2

Aker Kvaerner Powergas


CLIENT:
RIL

JOB NO 2090/1419
REV PREPD. BY

CALCULATION NUMBER CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

PROJECT: SUBJECT:

KG-D6

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

. 28/08/06 SH

. OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

iii) Parallel to X and Z axis in balance portion (portion other than beams) 50% of Ast(min)= 912.50 mm2 (Calculated per meter width) Required T 16 @ 220.34 mm c/c Provide T 16 @ 200 mm c/c Ast(prov) = 1005.3 mm2 b) Top Steel : Mzzmax=1.5{T(.5nd-b2/2)+(Dt*25+gd*h+sr)*(d+.4)*((B-b2)/2)2/2)} = 367.91 kN-m 2 Mxxmax=1.5{T*X1+(Dt*25+gd*h+sr)*(d+.4)*(X1+d/2+0.2) /2 ) = 381.55 kN-m or 1.5{2*T*X2+(Dt*25+gd*h+sr)*(d+.4)*(X2+d/2+0.2)^2/2 } Ast(req) (for Mzz) = 1100.19 mm2 Ast(req) (for Mxx) = 1141.72 mm2 Ast(min) (for Mzz) = 50% of (0.2/100)*B*Dteff = 775.63 mm2 Ast(min) (for Mxx) = 50% of (0.2/100)*B*Dteff = 775.63 mm2 i) Parallel to X axis in strip of width (d+2E)/2 on either side of the 2 lower piles (Beam in X direction). Required 5.475 Nos - T 16 Provide 7 Nos - T 16 Ast(prov) = 1406.7 mm2 ii) Parallel to Z axis in strip of width (d+2E)/2 on either side of the 3rd top pile (beam in Z direction) Required 5.681 Nos - T 16 Provide 7 Nos- T 16 Ast(prov) = 1406.7 mm2 iii) Parallel to X and Z axis in balance portion (portion other than beams) 50% of Ast(min)= 912.50 mm2 (Calculated per meter width) Required T 16 @ 220.34 mm c/c Provide T 16 @ 200 mm c/c Ast(prov) = 1005.3 mm2 5) Check for One Way Shear : a) For Maximum Compressive load i). Shear Section Parallel to Z axis shear plane location 0.831 m from centre , Shear Force = 1532.1 kN av = 0.3313 m from pedestal face % Steel = 0.443 Tc = 0.478 N/mm2 Tcmax = 3.70 N/mm2 Tcmax > Tv Safe Enhanced Shear stress =2*Dteff * Tc /av = 2.631 N/mm2 Tv = 1.975 N/mm2 As Tc enhanced > Tv , Vus = 0.0 kN Asvreq = 0.00 mm2 Asvmin = 144.02 mm2 Shear reinforcement is not required legged stirrups @ Provide T 10 2 200 c/c ii) Shear Section Parallel to X axis shear plane location 0.956 m from centre , Shear Force(1)= 1560.0 kN av = 0.4563 m from pedestal face Shear Force(2)= 0.00 kN % Steel = 0.443 Tc = 0.478 N/mm2 Enhanced Shear stress =2*Dteff * Tc /av = 1.910 N/mm2 Tv = 2.011 N/mm2 As Tc enhanced < Tv , Vus= 78.19 kN Asvreq= 47.47 mm2 Asvreq= 144.02 mm2 Shear reinforcement legged stirrups @ Provide T 10 2 200 c/c

Aker Kvaerner Powergas


CLIENT:
RIL KG-D6

JOB NO 2090/1419
REV PREPD. BY

CALCULATION NUMBER CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

PROJECT: SUBJECT:

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

OF

C940001 R3

1 Beff. Rev.= 850 mm 2 b) For Maximum Tensile load 3 i). Shear Section Parallel to Z axis Dteff. = 942 mm 4 The critical section for Shear (Parallel to Z axis) is at the face of pedestal ( dt'=50) 5 Shear Force= 525.0 kN 6 % Steel = 0.18 Tc = 0.318 N/mm2 7 Tcmax > Tv Safe Tv = 0.656 N/mm2 8 Vus= 270.7 kN 9 Asvreq= 164.32 mm2 10 Asvmin = 144.02 mm2 11 Shear reinforcement 12 legged stirrups @ Reqiured T 12 2 200 c/c 13 legged stirrups @ Provided T 12 2 200 c/c 14 ii). Shear Section Parallel to X axis 15 16 The critical section for Shear (Parallel to X axis) is at the face of pedestal 17 Shear Force 1 = 525.0 kN Shear Force 2 = 1050.0 kN 18 Note-Refer in attached Figure Pedestal resting Partialy on along X direction Beam therefore 19 ignore Shear Force 2 20 % Steel = 0.18 Tc = 0.322 N/mm2 21 Tcmax > Tv Safe Tv = 1.354 N/mm2 22 Vus= 278.6 kN 23 Asvreq= 169.15 mm2 24 Asvmin = 144.02 mm2 25 26 ` 27 Shear reinforcement 28 legged stirrups @ Required T 12 2 200 c/c 29 legged stirrups @ 30 Provided T 12 2 200 c/c 31 32 6) Side Face Reinforcement: 33 Side face reinforcement is provided to control temperature and shrinkage cracks. 34 Width of pilecap prone to shrinkage & temperature cracks = 500 mm from each face 35 36 Ast on E/F =0.1% of ( beff x Overall depth)= 500 mm2 37 Required T 12 226.2 c / c 38 Provide 5 T 12 ( 218.75 c/c) 39 2 Ast provided on E/F= 565 <300 SAFE mm 40 41 42 43 44 45 46 47 48 49 50

Aker Kvaerner Powergas


CLIENT:
RIL KG-D6

JOB NO 2090/1419
REV PREPD. BY

CALCULATION NUMBER CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

PROJECT: SUBJECT:

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Aker Kvaerner Powergas


CLIENT:
RIL KG-D6

JOB NO 2090/1419
REV PREPD. BY

CALCULATION NUMBER CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

PROJECT: SUBJECT:

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

R.C. Design of Pile Cap IPC4


1000 750 1.2 18 35 415 10 mm mm m 3 kN/m N/mm2 2 N/mm 2 kN/m

1) Pile and Pilecap Data: 2) Design Parameters: Assumed Pedestal Length = ' l2 ' = Diameter/size of Pile = d = 350 mm Assumed Pedestal Width = ' b2 ' = Capacity of Pile : Axial Compression = C = 1040 kN Depth of pilecap top = (FGL- TOC) =h= Density of Soil = gd = Axial Tension = T = 350 kN Shear = S = 68 kN Grade of Concrete = fck = Thickness of Pile cap = Dt = 1000 mm Grade of Steel = fy = Surcharge intensity = sr = Spacing of Piles in Group = nd = 5.714 x ' d' c/c distance between piles = 2 m Clear Cover to Pilecap Reinforcement Bottom Cover d'b = Dist. bet edge of pile & pilecap = E = 250 mm Top Cover d't = Length of Pile Cap = L = 2.85 m Side Cover d's = Breadth of Pile Cap = B = 2.85 m 3) Check for Punching Shear : a. For individual pile : perimetre = (E+d+Min of (Dteff/2,nd/2-d/2) )*2 = 2115.0 mm Tv = C*1.5/(Dteff*Perimeter) = 0.806 N/mm2 Tc = 1.479 N/mm2 Tc > Tv Safe b. For pile group : perimetre = (l2+Dteff+b2+Dteff)*2 = 7160.00 mm Tv=1.5(4C)/(Dteff*perimeter)= 0.952 N/mm2 ks calculated = 1.25 > 1 ks = 1 Tc = 1.479 N/mm2 Tc > Tv Safe

75 mm 50 mm 50 mm

4) Check For Bending: a) Bottom Steel : Bending Moment : Mzzmax=1.5{2C(.5nd-b2/2)-L*Dt*25((B-b2)/2)2*.5}= Mxxmax=1.5{2C(.5nd-l2/2)-B*Dt*25((L-l2)/2)2*.5 }= Dteff(req) (for Mzz) = Sqrt(Mzz/(0.138*fck*L)) = Dteff(req) (for Mxx) = Sqrt(Mxx/(0.138*fck*B)) = Dteff(prov) = Dt - d'b -0.5*bar dia. = Ast (req) (for Mzz) = Ast (req) (for Mxx) = Ast (min) (for Mzz) = (0.12/100)*B*Dt = Ast (min) (for Mxx) = (0.12/100)*B*Dt = i) Parallel to X axis Required 20 = T@ 152

1891.08 1514.27 370.65 331.67 915.00 5884.61 4685.83 3420.00 3420.00 c/c OR Provide

kN-m kN-m mm mm mm mm2 mm2 mm2 mm2

Safe ( Parallel to X axis ) ( Parallel to Z axis )

18.741 Nos 20 Nos - T 20

Ast(prov) ii) Parallel toZ axis Required 20

6280 mm2 T@ 191 c/c OR Provide 14.923 Nos 20 Nos - T 20

Ast(prov)

6280 mm2

Aker Kvaerner Powergas


CLIENT:
RIL KG-D6

JOB NO 2090/1419
REV PREPD. BY

CALCULATION NUMBER CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

PROJECT: SUBJECT:

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

b) Top Steel : 2 Mzzmax = 1.5*(2T(0.5nd-0.5b2)+(Dt*25+gd*h+sr)*L*((B-b2)/2) /2) = 2 Mxxmax = 1.5*(2T (0.5nd-0.5l2)+(Dt*25+gd*h+sr)*B*((L-l2)/2) /2 ) = Ast(req) (for Mzz) = Ast(req) (for Mxx) = Ast(min) (for Mzz) = 50% of (0.12/100)*B*Dt = Ast(min) (for Mxx) = 50% of (0.12/100)*B*Dt = i) Parallel to X axis Required 16 T@ 335 Ast(prov) ii) Parallel to Z axis Required 16 = = 4019.2 T@ 4019.2 mm
2

552.74 439.96 1686.92 1340.59 1710.00 1710.00 c/c Provide

kN-m kN-m mm2 2 mm mm2 2 mm 8.509 Nos 20 Nos - T 16

335 mm2

c/c Provide

8.509 Nos 20 Nos - T 16

Ast(prov)

5) Check for One Way Shear : a) For Maximum Compressive load a. Shear Section Parallel to Z axis shear plane location 0.833 m from centre , Shear Force = 3053.1 kN av = 0.458 m from pedestal face % Steel = 0.241 Tc = 0.366 N/mm2 Tcmax = 3.70 N/mm2 Tcmax > Tv Safe Enhanced Shear stress =2*Dteff * Tc /av = 1.464 N/mm2 Tv = 1.171 N/mm2 As Tc enhanced > Tv , Vus = 0.0 kN Asvreq = 0.00 mm2 Asvmin = 0.00 mm2 Shear reinforcement is not required legged stirrups @ Provide T 0 c/c b. Shear Section Parallel to X axis shear plane location 0.958 m from centre , av = 0.458 m from pedestal face % Steel = 0.241 Tc = 0.366 N/mm2 Enhanced Shear stress =2*Dteff * Tc /av = 1.464 N/mm2 Tv = 0.743 N/mm2 As Tc enhanced > Tv , Vus= Asvreq= Asvreq= 0.0 kN 0.00 mm2 0.00 mm2

Shear Force= 1938.8 kN

Provide T

Shear reinforcement is not required legged stirrups @ 0

c/c

JOB NO

CALCULATION NUMBER CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV
CLIENT:
RIL KG-D6

2090/1419
PREPD. BY

PROJECT: SUBJECT:

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

OF

C940001 R3

1 b) For Maximum Tensile load 2 i). Shear Section Parallel to X or Z axis 3 The critical section for Shear (Parallel to X or Z axis) is at the face of pedestal 4 This pile cap is designed for 70% of pile tension capacity as net tensile force of 600kn is not anticipated. 5 Dteff = Dt - d't -0.5*bar dia. = 942 mm (considered only for shear check for Tension Face) 6 Shear Force= 735.0 kN (160x1.5x2x0.8) 7 2 % Steel = 0.15 Tc = 0.308 N/mm 8 Tcmax > Tv Safe Tv = 0.274 N/mm2 9 Vus= 0.0 kN 10 Asvreq= 0.00 mm2 11 2 Asvmin = 0.00 12 mm Shear reinforcement is not required 13 14 legged stirrups @ Provide T 0 0 0 c/c 15 16 6) Side Face Reinforcement: 17 Side face reinforcement is provided to control temperature and shrinkage cracks. 18 Width of pilecap prone to shrinkage & temperature cracks = 500 mm from each face 19 20 (Clause 26.5.1.3...IS456) Ast on E/F = 0.1% of ( beff x Overall depth) = 500 mm2 21 Required T 12 226.2 c / c 22 Provide 5 T 12 ( 218.75 c/c) 23 Ast provided on E/F= 565 <300 SAFE mm2 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

JOB NO

CALCULATION NUMBER CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


CLIENT: PROJECT:
SUBJECT:
RIL KG-D6

2090/1419
REV PREPD. BY

Design Calculation for Warehouse no 1 & 2 pilecap

3 2 1 0

SPKN

28/08/06

AVD

28/08/06 SH

OF

C940001 R3

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

5 Design Of Pile Cap IPC5


1) Pile and Pilecap Data: Diameter/size of Pile = d = 350 1080 350 mm kN kN kN mm m m mm m m 2) Design Parameters: Ped. Length = ' b2 ' = Ped. Width = ' l2 ' = Depth of pilecap top = (FGL- TOC) = h= Density of Soil = gd = Grade of Concrete = fck = Grade of Steel = fy = Surcharge intensity = sr = Clear Cover to Pilecap Reinforcement Bottom Cover d'b = Top Cover d't = Side Cover d's = 750 1000 1.2 18 35 415 10 75 50 50 mm mm m kN/m3 N/mm2 N/mm2 kN/m2 mm mm mm

Capacity of Pile :
Axial Compression, C = Axial Tension, T =

Shear = S =
Thickness of Pile cap = Dt = Spacing of Piles along z dir, s1 = Spacing of Piles along x dir, s2 = Dist. bet edge of pile & pilecap 'E' = Length of Pile Cap = L = Breadth of Pile Cap = B =

68
1000 2.8 2.8 250 3.650 3.650

3) Check for Punching Shear : a. For individual pile : perimetre = (E+d+Min of (Dteff/2,nd/2-d/2) )*2 = Tv = C/(Dteff*Perimeter) = Tc = b. For pile group : perimetre = (l2+Dteff+b2+Dteff)*2 = Tv=(4C-L*B*Dt*25)/(Dteff*perimeter)= ks calculated = Tc = 7160 mm 0.913 N/mm2 1.25 > 1 1.479 N/mm2 Tc > Tv Safe ks = 1 2115.0 mm 0.837 N/mm2 1.479 N/mm2 Tc > Tv Safe

4) Check For Bending: a) Bottom Steel : Bending Moment : Muzz ={2C(0.5*s2-l2/2)-L*Dt*25((B-l2)/2)2*.5}= Muxx={2C(.5*s1-b2/2)-B*Dt*25((L-b2)/2)2*.5 }= Dteff(req) (for Muzz) = Sqrt(Mzz/(0.138*fck*L)) = Dteff(req) (for Muxx) = Sqrt(Mxx/(0.138*fck*B)) = Dteff(prov) = Dt - d'b -0.5*bar dia. = Ast (req) (for Muzz) = Ast (req) (for Muxx) = Ast (min) (for Muzz) = Ast (min) (for Muxx) = 1863.90 kN-m 2118.07 kN-m 325.16 mm 346.62 mm 915.00 mm
2

Safe

5762.74 mm 6567.74 mm2

( Parallel to X axis ) ( Parallel to Z axis )

(0.12/100)*B*Dt = 4380.00 mm2 (0.12/100)*B*Dt = 4380.00 mm2

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


CLIENT: PROJECT: SUBJECT:

2090-1419
REV PREPD. BY

RIL KG-D6 Design calculations for Warehouse no 1 & 2 pilecap

SPKN

28.08.06

AVD

28.08.06

SH

OF

C940001 R3

ssasassss

1 2 i) Parallel to Z axis Required 20 Y@ 199 c/c OR 18.353 Nos 3 Provide 22 Nos - Y 20 4 2 Ast(prov) = 6908 mm 5 6 7 ii) Parallel to X axis Required 20 Y@ 175 c/c OR 20.916 Nos 8 Provide 22 Nos - Y 20 9 Ast(prov) = 6908 mm2 10 11 12 b) Top Steel : 13 Muxx = (2T(0.5s2-0.5l2)+(Dt*25+gd*h+sr)*L*((B-l2)/2)2/2) = 811.35 kN-m 14 Muzz = (2T (0.5s1-0.5b2)+(Dt*25+gd*h+sr)*B*((L-b2)/2)2/2 ) = 934.68 kN-m 15 16 Ast(req) (for Muzz) = 2478.99 mm2 17 Ast(req) (for Muxx) = 2859.71 mm2 18 Ast(min) (for Muxx) = 50% of (0.12/100)*B*Dt = 2003.85 mm2 19 Ast(min) (for Muzz) = 50% of (0.12/100)*B*Dt = 2003.85 mm2 20 21 i) Parallel to Z axis Required 12 Y@ 166 c/c 21.930 Nos 22 Provide 24 Nos - Y 12 23 2 Ast(prov) = 2713 mm 24 25 26 ii) Parallel to X axis Required 12 Y@ 144 c/c 25.298 Nos 27 Provide 24 Nos - Y 12 28 2 Ast(prov) = 2713 mm 29 30 31 5) Check for One Way Shear : 32 a) For Maximum Compressive load 33 a. Shear Section Parallel to Z axis 34 35 shear plane location 0.958 m from centre , Shear Force = 2160.0 kN 36 av = 0.4575 m from pedestal face 37 % Steel = 0.207 Tc = 0.342 N/mm2 Tcmax = 3.70 N/mm2 38 2 Tcmax > Tv Safe Enhanced Shear stress =2*Dteff * Tc /av = 1.368 N/mm 39 2 40 Tv = 0.647 N/mm 41 42 As Tc enhanced > Tv , Vus = 0.0 kN 43 Asvreq = 0.00 mm2 44 45 Asvmin = 0.00 mm2 46 Shear reinforcement is not required 47 legged stirrups @ Provide Y 0 c/c 48 49 50

Aker Kvaerner Powergas


REV
CLIENT: PROJECT:

JOB NO: 2090-1419


PREPD. BY

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

RIL KG-D6 SUBJECT: Design calculations for Warehouse no 1 & 2 pilecap


C940001 R3

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

b. Shear Section Parallel to X axis shear plane location av = % Steel = 0.207 0.833 m from centre , 0.4575 m from pedestal face Tc = Tv = As Tc enhanced > Tv , Vus= Asvreq= Asvreq= Provide Y b) For Maximum Tensile load i). Shear Section Parallel to X or Z axis The critical section for Shear (Parallel to X or Z axis) is at the face of pedestal Dteff = Dt - d't -0.5*bar dia. = Shear Force= % Steel = 0.08 Tc = Tv = Vus= Asvreq= Asvmin = Provide Y 6) Side Face Reinforcement: Side face reinforcement is provided to control temperature and shrinkage cracks. Width of pilecap prone to shrinkage & temperature cracks = 500 mm from each face 500 mm2 218.75 c/c <300 SAFE (Width assumed based on Clause 3.12.5.4 BS8110) Ast on E/F = 0.1% of ( beff x Overall depth)= Required Provide Y 12 5 Ast provided on E/F= 565 226.2 Y 12 mm2 c/c 944 mm 700.0 kN 0.2192 N/mm2 0.2032 N/mm2 0.0 0.00 0.00 0.00 kN mm2 (considered only for shear check for Tension Face) (350x2) Tcmax > Tv Safe 0.342 N/mm2 1.368 N/mm2 0.647 N/mm2 0.0 kN 0.00 mm2 0.00 mm2 0 legged stirrups @ c/c Shear Force= 2160.0 kN

Enhanced Shear stress =2*Dteff * Tc /av =

Shear reinforcement is not required

mm2 Shear reinforcement is not required legged stirrups @ c/c

JOB NO:

CALCULATION NO.
DATE

EQPT. NO.
DATE

Aker Kvaerner Powergas


REV
CLIENT: PROJECT: SUBJECT:

2090-1419

PREPD. BY

CIC-8002-00

CHKD BY

RIL KG-D6 Design calculations for Warehouse no 1 & 2 pilecap

SPKN

28.08.06

AVD

28.08.06

SH

OF

C940001 R3

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Mxx x

Mzz

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV CLIENT:

2090-1419
PREPD. BY

RIL PROJECT: KG-D6 SUBJECT: Design calculations for Warehouse no 1 & 2 pilecap
C940001 R3

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

6 R.C. Design of Pile Cap IPC6


1) Pile and Pilecap Data:
Diameter/size of Pile = d = 350 1080 350 mm kN kN kN mm x ' d' m mm m m

2) Design Parameters:
Ped. Length = ' l2 ' = Ped. Width = ' b2 ' = Depth of pilecap top = (FGL- TOC) =h= Density of Soil = gd = Grade of Concrete = fck = Grade of Steel = fy = Surcharge intensity = sr = Clear Cover to Pilecap Reinforcement Bottom Cover d'b = Top Cover d't = Side Cover d's = 75 50 50 mm mm mm 1000 750 1.2 18 35 415 10 mm mm m kN/m3 N/mm2 N/mm2 kN/m2

Capacity of Pile :
Axial Compression, C = Axial Tension, T =

Shear = S =
Thickness of Pile cap = Dt = Spacing of Piles in Group = nd = = c/c distance between piles

68
1200 5.7 2 250 6.85 2.85

Dist. bet edge of pile & pilecap = E =

Length of Pile Cap = L = Breadth of Pile Cap = B = 3) Check for Punching Shear : a. For individual pile :

perimeter = (E+d+Min of (Dteff/2,nd/2-d/2) )*2 = Tv = C/(Dteff*Perimeter) = Tc = b. For pile group : perimeter = (l2+Dteff+b2+Dteff)*2 = Tv=(6C)/(Dteff*perimeter)= ks calculated = Tc = 4) Check For Bending: a) Bottom Steel : Bending Moment : Muxx={3C(0.5nd-b2/2)-L*Dt*25((B-b2)/2)2*.5}= Muzz={2C(nd-l2/2)-B*Dt*25((L-l2)/2)2*.5 }= Dteff(req) (for Muxx) = Sqrt(Mzz/(0.138*fck*L)) = Dteff(req) (for Muzz) = Sqrt(Mxx/(0.138*fck*B)) = Dteff(prov) = Dt - d'b -0.5*bar dia. = Ast (req) (for Muxx) = Ast (req) (for Muzz) = Ast (min) (for Muxx) = (0.12/100)*B*Dt = Ast (min) (for Muzz) = (0.12/100)*B*Dt = 7960 mm 1.095 N/mm2 1.25 > 1 1.479 N/mm2

2315.0 mm 0.628 N/mm2 1.479 N/mm2 Tc > Tv Safe

ks =

Tc > Tv Safe

1911.72 kN-m 2874.25 kN-m 240.38 mm 456.95 mm 1115.00 mm 4786.72 mm2 7344.6 mm2 9864.00 mm 4104.00 mm2
2

Safe ( Parallel to Z axis ) ( Parallel to X axis )

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV

2090-1419
PREPD. BY

CLIENT: RIL PROJECT: KG-D6 SUBJECT: Design calculations for Warehouse no 1 & 2 pilecap C940001 R3

SPKN

28.08.06

AVD

28.08.06

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

i) Parallel to X axis

Required

20 Ast(prov) =

Y@

218
2

c/c OR Provide

31.414 Nos 20 Nos - Y 20

6280 mm Y@

ii) Parallel to Z axis

Required

20 Ast(prov) =

122
2

c/c OR Provide

23.390 Nos 22 Nos - Y 20

6908 mm

b) Top Steel : Muxx = (3T(0.5nd-0.5b2)+(Dt*25+gd*h+sr)*L*((B-b2)/2)2/2) = Muzz = (2T (nd-0.5l2)+(Dt*25+gd*h+sr)*B*((L-l2)/2) /2 ) = Ast(req) (for Muxx) = Ast(req) (for Muzz) = Ast(min) (for Muxx) = Ast(min) (for Muzz) = i) Parallel to X axis Required 50% of (0.12/100)*B*Dt = 50% of (0.12/100)*B*Dt = 12 Ast(prov) ii) Parallel to Z axis Required 16 Ast(prov) 5) Check for One Way Shear : a) For Maximum Compressive load a. Shear Section Parallel to X axis shear plane location av = % Steel = 0.082 0.9325 m from centre , 0.5575 m from pedestal face Tc = Tv = As Tc enhanced > Tv , Vus = Asvreq = Asvmin = Provide Y 0.224 N/mm2 0.895 N/mm2 0.294 N/mm2 0.0 kN 0.00 mm2 0.00 mm2 0 legged stirrups @ c/c Tcmax = 3.70 N/mm2 Tcmax > Tv Safe Shear Force = 2244.9 kN Y@ 157
2

888.86 kN-m 1801.01 kN-m 2160.11 mm2 4434.05 mm2 4932.00 mm2 2052.00 mm2 c/c Provide ( Parallel to Z axis ) ( Parallel to X axis ) 20 Nos - Y 12

43.631 Nos

= 2260.8 mm2 Y@ 129 c/c Provide = 4421.1 mm2 22.064 Nos 22 Nos - Y 16

Enhanced Shear stress =2*Dteff * Tc /av =

Shear reinforcement is not required

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV CLIENT: RIL PROJECT: KG-D6 Design calculations for SUBJECT: Warehouse no 1 & 2 pilecap C940001 R3

2090-1419
PREPD. BY

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

b. Shear Section Parallel to Z axis shear plane location av = % Steel = 0.217 1.058 m from centre , 0.5575 m from pedestal face Tc = Tv = As Tc enhanced > Tv , Vus= Asvreq= Asvreq= 0.350 N/mm2 1.399 N/mm2 0.680 N/mm2 0.0 kN 0.00 mm2 0.00 mm2 Shear Force= 2160.0 kN

Enhanced Shear stress =2*Dteff * Tc /av =

Shear reinforcement is not required Provide Y b) For Maximum Tensile load i). Shear Section Parallel to X or Z axis The critical section for Shear (Parallel to X or Z axis) is at the face of pedestal Dteff = Dt - d't -0.5*bar dia. = % Steel = 0.14 Tc = Tv = Vus= Asvreq= 1144 mm 0.282 N/mm2 0.322 N/mm2 129.9 kN (considered only for shear check for Tension Face) (350x3) Tcmax > Tv Safe 0 legged stirrups @ c/c

Shear Force= 1050.0 kN

62.91 mm2 Asvmin = 631.49 mm2 Shear reinforcement Provide Y 12 6) Side Face Reinforcement: Side face reinforcement is provided to control temperature and shrinkage cracks. Width of pilecap prone to shrinkage & temperature cracks = 500 mm from each face 600 mm2 (
2

legged stirrups @

200

c/c

Ast on E/F = 0.1% of ( beff x Overall depth) = Required Provide Y 12 6 679 Y 12 mm

(Clause 26.5.1.3...IS456) 215 c/c) <300 SAFE

188.496 c / c

Ast provided on E/F=

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV

2090-1419
PREPD. BY

CLIENT: RIL PROJECT: KG-D6 SUBJECT: Design calculations for Warehouse no 1 & 2 pilecap C940001 R3

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Mxx x Mzz z

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV
CLIENT:

2090-1419
PREPD. BY

RIL PROJECT: KG-D6 Design calculations for SUBJECT: Warehouse no 1 & 2 pilecap
C940001 R3

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

6 R.C. Design of Pile Cap IPC9


1) Pile and Pilecap Data:
Diameter/size of Pile = d = 350 1080 350 mm kN kN kN mm x ' d' m mm m m

2) Design Parameters:
Ped. Length = ' l2 ' = Ped. Width = ' b2 ' = Depth of pilecap top = (FGL- TOC) =h= Density of Soil = gd = Grade of Concrete = fck = Grade of Steel = fy = Surcharge intensity = sr = Clear Cover to Pilecap Reinforcement Bottom Cover d'b = Top Cover d't = Side Cover d's = 75 50 50 mm mm mm 1000 750 1.2 18 35 415 10 mm mm m kN/m3 N/mm2 N/mm2 kN/m2

Capacity of Pile :
Axial Compression, C = Axial Tension, T =

Shear = S =
Thickness of Pile cap = Dt = Spacing of Piles in Group = nd = = c/c distance between piles

68
1200 5.7 2 250 4.85 2.85

Dist. bet edge of pile & pilecap = E =

Length of Pile Cap = L = Breadth of Pile Cap = B = 3) Check for Punching Shear : a. For individual pile :

perimeter = (E+d+Min of (Dteff/2,nd/2-d/2) )*2 = Tv = C/(Dteff*Perimeter) = Tc = b. For pile group : perimeter = (l2+Dteff+b2+Dteff)*2 = Tv=(6C)/(Dteff*perimeter)= ks calculated = Tc = 4) Check For Bending: a) Bottom Steel : Bending Moment : Muxx={3C(0.5nd-b2/2)-L*Dt*25((B-b2)/2)2*.5}= Muzz={2C(nd-l2/2)-B*Dt*25((L-l2)/2)2*.5 }= Dteff(req) (for Muxx) = Sqrt(Mzz/(0.138*fck*L)) = Dteff(req) (for Muzz) = Sqrt(Mxx/(0.138*fck*B)) = Dteff(prov) = Dt - d'b -0.5*bar dia. = Ast (req) (for Muxx) = Ast (req) (for Muzz) = Ast (min) (for Muxx) = (0.12/100)*B*Dt = Ast (min) (for Muzz) = (0.12/100)*B*Dt = 7960 mm 1.095 N/mm2 1.25 > 1 1.479 N/mm2

2315.0 mm 0.628 N/mm2 1.479 N/mm2 Tc > Tv Safe

ks =

Tc > Tv Safe

1944.79 kN-m 3081.58 kN-m 288.13 mm 473.14 mm 1115.00 mm 4885.69 mm2 7890.9 mm2 6984.00 mm 4104.00 mm2
2

Safe ( Parallel to Z axis ) ( Parallel to X axis )

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV

2090-1419
PREPD. BY

CLIENT: RIL PROJECT: KG-D6 SUBJECT: Design calculations for Warehouse no 1 & 2 pilecap C940001 R3

SPKN

28.08.06

AVD

28.08.06

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

i) Parallel to X axis

Required

20 Ast(prov) =

Y@

218
2

c/c OR Provide

22.242 Nos 20 Nos - Y 20

6280 mm Y@

ii) Parallel to Z axis

Required

20 Ast(prov) =

113
2

c/c OR Provide

25.130 Nos 22 Nos - Y 20

6908 mm

b) Top Steel : Muxx = (3T(0.5nd-0.5b2)+(Dt*25+gd*h+sr)*L*((B-b2)/2)2/2) = Muzz = (2T (nd-0.5l2)+(Dt*25+gd*h+sr)*B*((L-l2)/2) /2 ) = Ast(req) (for Muxx) = Ast(req) (for Muzz) = Ast(min) (for Muxx) = Ast(min) (for Muzz) = i) Parallel to X axis Required 50% of (0.12/100)*B*Dt = 50% of (0.12/100)*B*Dt = 12 Ast(prov) ii) Parallel to Z axis Required 16 Ast(prov) 5) Check for One Way Shear : a) For Maximum Compressive load a. Shear Section Parallel to X axis shear plane location av = % Steel = 0.116 0.9325 m from centre , 0.5575 m from pedestal face Tc = Tv = As Tc enhanced > Tv , Vus = Asvreq = Asvmin = Provide Y 0.263 N/mm2 1.051 N/mm2 0.415 N/mm2 0.0 kN 0.00 mm2 0.00 mm2 0 legged stirrups @ c/c Tcmax = 3.70 N/mm2 Tcmax > Tv Safe Shear Force = 2244.9 kN Y@ 157
2

820.94 kN-m 1375.28 kN-m 1997.07 mm2 3372.68 mm2 3492.00 mm2 2052.00 mm2 c/c Provide ( Parallel to Z axis ) ( Parallel to X axis ) 20 Nos - Y 12

30.892 Nos

= 2260.8 mm2 Y@ 170 c/c Provide = 4421.1 mm2 16.783 Nos 22 Nos - Y 16

Enhanced Shear stress =2*Dteff * Tc /av =

Shear reinforcement is not required

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV CLIENT: RIL PROJECT: KG-D6 Design calculations for SUBJECT: Warehouse no 1 & 2 pilecap C940001 R3

2090-1419
PREPD. BY

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

b. Shear Section Parallel to Z axis shear plane location av = % Steel = 0.217 1.058 m from centre , 0.5575 m from pedestal face Tc = Tv = As Tc enhanced > Tv , Vus= Asvreq= Asvreq= 0.350 N/mm2 1.399 N/mm2 0.680 N/mm2 0.0 kN 0.00 mm2 0.00 mm2 Shear Force= 2160.0 kN

Enhanced Shear stress =2*Dteff * Tc /av =

Shear reinforcement is not required Provide Y b) For Maximum Tensile load i). Shear Section Parallel to X or Z axis The critical section for Shear (Parallel to X or Z axis) is at the face of pedestal Dteff = Dt - d't -0.5*bar dia. = % Steel = 0.14 Tc = Tv = Vus= Asvreq= 1144 mm 0.282 N/mm2 0.322 N/mm2 129.9 kN (considered only for shear check for Tension Face) (350x3) Tcmax > Tv Safe 0 legged stirrups @ c/c

Shear Force= 1050.0 kN

62.91 mm2 Asvmin = 631.49 mm2 Shear reinforcement Provide Y 12 6) Side Face Reinforcement: Side face reinforcement is provided to control temperature and shrinkage cracks. Width of pilecap prone to shrinkage & temperature cracks = 500 mm from each face 600 mm2 (
2

legged stirrups @

200

c/c

Ast on E/F = 0.1% of ( beff x Overall depth) = Required Provide Y 12 6 679 Y 12 mm

(Clause 26.5.1.3...IS456) 215 c/c) <300 SAFE

188.496 c / c

Ast provided on E/F=

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV

2090-1419
PREPD. BY

CLIENT: RIL PROJECT: KG-D6 SUBJECT: Design calculations for Warehouse no 1 & 2 pilecap C940001 R3

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Mxx x Mzz z

JOB NO:

CALCULATION NO. CIC-8002-00


DATE CHKD BY DATE

EQPT. NO.

Aker Kvaerner Powergas


REV
CLIENT:

2090-1419
PREPD. BY

RIL PROJECT: KG-D6 Design calculations for SUBJECT: Warehouse no 1 & 2 pilecap
C940001 R3

SPKN

28.08.06

AVD

28.08.06

SH

OF

ssasassss

Vous aimerez peut-être aussi