PURCHASE OF EQUIPMENT
INPUT PROCESS OUTPUT COMMENTS
START General Manager Comments and observations from the site and Project Engineers and Manager about the performance of the equipment and the necessity for a new equipment
Instructs the Equipment in-charge to look for a supplier of the equipment and make a purchase order
Calls for a supplier and asks for price quotation. Compares the prices and identifies a supplier for each purchase. Makes a Purchase Order.
At times, there is already an identified supplier. Thus, there is no need for the equipment in-charge to make a canvass of the prices.
General Manager Price Quotation Purchase Order 1 Purchase Order 1 1 Approved & Sgd. by General Manager Equipment In-charge Purchase Order 1 1 Approved & Sgd. by General Manager Faxes the approved purchase order to the supplier Purchase Order 1 Approved & Sgd. by General Manager 2 Checks the accuracy of the purchase order, the prices and the supplier identified. Approves the purchase order. Price Quotation Purchase Order 1 Purchase Order 1 1 2 D Purchase Order File
Supplier
PE02
PURCHASE OF EQUIPMENT
INPUT PROCESS OUTPUT COMMENTS
PE01
Liaison Officer Materials In-charge Receives the construction equipment and checks its specifications vis-vis the delivery receipt Test runs are also done and there are instances, when a deed of sale also needs to be executed.
Delivery Receipt 1 1 1
Freight Forwarder
Delivery Receipt 1 1 1
1 1 1
Receives the sales invoice and makes a voucher payable and attaches the delivery receipt and sales invoice
Voucher Payable Voucher Payable 3 3 1 1 Voucher Payable 2 2 1 Delivery Receipt 11 Sales Invoice 1 11 1
In instances of cash transactions, full payment is required beforehand. Thus, no delivery receipt is attached. And the Project Manager/ General Manager advances cash for the company for travel to purchase the equipment outside the country.
PE03