COSTO DE PROYECTO

EMPRESA: dlv contratistas generales E.I.R.L

FECHA

2013- 4-Jun

PROYECTO

PORTON EFATA
EFATA

CLIENTE

Tipo de Cambio :

MATERIALES (1)
TOTAL MATERIALES

272.00

MANO DE OBRA
DESCRIPCION

SALARIO

2000
1800
1200
900
1500

HORAS TRAB.

49.5
18
17.5
18.5
18.5

RONALD CACERES
EDWIN CACERES
DIEGO CALDERON
HAROLD ONCEBAY
RIBERT FLORES

COSTO POR HORA


66.67
60.00
40.00
30.00
50.00

SUB-TOTAL

TOTAL MANO DE OBRA

3,300.17
1,080.00
700.00
555.00
925.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
6,560.17

TOTAL

215.00

OTROS GASTOS

0.00

MATERIALES 272.00
MANO DE OBRA
6,560.17
TERCEROS
215.00
TOTAL

COSTO TOTAL PROYECTO

7,047.17

TERCEROS
3%

MATERIALES
4%

MANO DE
OBRA
93%

Fecha de Actulizacin: 14/8/2013 12:27 PM

7,047.17

COSTO DE PROYECTO
EMPRESA: dlv contratistas generales E.I.R.L

FECHA

2013- 4-Jun

PROYECTO

PORTON EFATA
EFATA

CLIENTE

Tipo de Cambio :

MATERIALES (1)
TOTAL MATERIALES

1,016.70

MANO DE OBRA
DESCRIPCION

SALARIO

1800
1200
1500
1200
1200

HORAS TRAB.

8.5
8.5
24
24
8.5

Ronald
Joaho
juan lima
luis tapia
diego calderon

COSTO POR HORA

7.06
4.71
5.88
4.71
4.71

SUB-TOTAL

TOTAL MANO DE OBRA

60.00
40.00
141.18
112.94
40.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
394.12

TOTAL

127.00

OTROS GASTOS
COSTO DE EQUIPOS

19.49

MATERIALES 1,016.70
MANO DE OBRA
394.12
COSTO DE EQUIPOS
19.49
TERCEROS
127.00
TOTAL

COSTO TOTAL PROYECTO

1,557.31

COSTO DE
EQUIPOS
1%

TERCEROS
8%

MANO DE
OBRA
26%

Chart Title

Fecha de Actulizacin: 14/8/2013 12:27 PM

MATERIALES
65%

1,557.31

COSTO DE PROYECTO
EMPRESA: dlv contratistas generales E.I.R.L
FECHA

2013- 4-Jun
TECHO CARPINTERIA

PROYECTO

ELABORADO EN EL GRANALLADO
EFATA

CLIENTE

Tipo de Cambio :

MATERIALES
Soles ITEM 1 2 3

4634.37 Dolares ITEM 1 2 13,710.10

TOTAL MATERIALES

5339.57

MANO DE OBRA
DESCRIPCION

SALARIO

1800.00
1200.00
1500.00
1500.00
900.00

FELIX RAMIREZ
PEDRO MIGUEL
ALDO JARAMILLO
RIVERT FLORES
HAROLD ONCEBAY

HORAS TRAB.

48
48
48
8.5
8.5

COSTO POR
HORA
7.06
4.71
5.88
5.88
3.53

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

SUB-TOTAL

338.82
225.88
282.35
50.00
30.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

TOTAL MANO DE OBRA

927.06

TOTAL

105.21

OTROS GASTOS
COSTO DE EQUIPOS
30.00

MATERIALES
5,339.57
MANO DE OBRA 927.06
COSTO DE EQUIPOS 30.00
OTROS GASTOS
105.21
TOTAL

COSTO TOTAL PROYECTO

6,401.84
COSTO DE
EQUIPOS
1%

OTROS GASTOS
8%

MANO DE OBRA
26%

Chart Title

Fecha de Actulizacin: 14/8/2013 12:27 PM

MATERIALES
65%

6,401.84

COSTO DE PROYECTO
EMPRESA: dlv contratistas generales E.I.R.L

FECHA

2013- 4-Jun
TECHO EFATA PROVISIONAL

PROYECTO

EFATA

CLIENTE

Tipo de Cambio :

MATERIALES (1)
DESCRIPCION

CANTIDAD

1
1
4

factura 14090 - la economia


factura 14132- la economia
tubo negro 1 1/2 x 1,8 x 6,4 mt

COSTO UNIT.
35.00
86.00
43.87

TOTAL MATERIALES

SUB-TOTAL

35.00
86.00
175.48
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
296.48

MANO DE OBRA
SALARIO

750 CRISTIAN CHIUAN


1200 JOAO NAVA

DESCRIPCION

HORAS TRAB.

COSTO POR HORA

28.5
29

2.94
4.71

SUB-TOTAL

83.82
136.47

1500
900
1500
1200
1200
1200

14
14
2.5
2.5

RIVER FLORES
HAROLD ONCEBAY
JUAN LIMA
LUIS TAPIA

5.88
3.53
5.88
4.71
0.00
14.5
4.71
2.5
4.71
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
TOTAL MANO DE OBRA

DIEGO CALDERON
DAVID ZAVALA

82.35
49.41
14.71
11.76
0.00
68.24
11.76
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
458.53

OTROS GASTOS
DESCRIPCION

CODIGO

Q REQUERIDA

movilidad para la compra de tubo


movilidad compras

1
1

en soles

43.36

COSTO UNIT.
13.00
3.00

TOTAL

SUB-TOTAL

13.00
3.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
16.00

COSTO DE EQUIPOS
15.00

MATERIALES
0.00
MANO DE OBRA 458.53

COSTO TOTAL PROYECTO

786.01

COSTO DE EQUIPOS
15.00
TERCEROS
43.36
TOTAL

516.89

COSTO DE
EQUIPOS
1%

TERCEROS
8%

MANO DE OBRA
26%

MATERIALES
65%

Chart Title