(Assembly) Line Balancing - an application of worker-machine relationships to determine the ideal number of
workers (#workstations, #workers/station) to be assigned to a production line
Required production is 3200 units/day, need to produce one unit in 480 min/day = .15 min/unit
3200 units/day
Number of operators = R×3SM = 3200 units/day * 2.61 op-min/unit = 17.4 op (at least 18, maybe more)
E 480 min/day E
Basic logic - Assign operators to a work station until cycle time of that station is about to be exceeded, in order
of decreasing positional weight, as allowed by precedence (i.e. immediate predecessors have been assigned)
Positional weight (for an operator) = 3ST for all operator with a ‘1' relationship
PW1 = (.05) + .03 + .04 + .05 + .01 + .04 + .05 + .04 + .06 = .37
Estimate cycle time and number of workstations based on desired production rate (57 units/8 hrs):