DESIGN OF PURLIN 1.

Cenre to Centre of Truss = So, Span of Purlin = Roof angle = Load on Purlin Spacing of Purlin Dead load ( Vertically Downward) S.wt purlin = wt. of sheeting = Udl on Purlin For s.wt = For sheeting= Live Load( Vertically Downward) @ Udl on Purlin DL/LL

5 m, say 5 m, Continuous over the Truss support 20 Deg Say 1.2 m 10.7 kg/m 15 kg^2/m 10.7 18 28.7 75 90 kg/m kg/m kg/m kg/m^2 kg/m

Can be reduced depends on roof angle see IS 875 part-2

Load on Purlin alog local axis

angle see IS 875 part-2