Load trials Load trials shall be carried out as agreed between Contractor and Principal and will normally

follow satisfactory completion of all the above tests and the completion of construction and testing of the various systems and sub-systems peripheral to the generator and prime mover. These final tests should be a series of load tests culminating in a protracted run under design conditions at designed maximum power output. These final tests will demonstrate that the generator, prime mover and all ancillary equipment meet the designed performance levels while running continuously at full rated load. For temperature rise and vibration limits reference is made to DEP 33.65.11.31-Gen. Proof of the unit's performance during tests should be in the form of a running log. The log sheets should be formally drawn up and the parameters to be recorded agreed between Principal and Contractor/Vendor. 4.3.2 Emergency and standby generators