No: DIR-37-0021
This manual is the property of SEADRILL and for the use of designated staff only
Revision requests and comments should be forwarded to: Seadrill Corporate Attn.: Operations Excellence Approved 18.08.2011
Page 1 of 45
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................................................................ 4 1.01 1.02 1.03 1.04 PURPOSE........................................................................................................... 4 SCOPE AND APPLICABILITY ...................................................................................... 4 RESPONSIBILITIES................................................................................................ 4 DEFINITIONS OF TERMS.......................................................................................... 4
3. GENERAL REQUIREMENTS................................................................................................................................... 8 3.01 CONDUCT OF OPERATION ........................................................................................ 8 3.01.01 Drills and exercises................................................................................................................................ 9 3.01.02 Maintenance and repair work ................................................................................................................ 9 3.01.03 Safety organisation................................................................................................................................. 9 3.01.04 Operational planning meetings............................................................................................................ 10 3.01.05 Damage control.................................................................................................................................... 10 3.01.06 Storm preparedness.............................................................................................................................. 10 3.02 ATTENDING PERSONNEL ....................................................................................... 10 3.02.01 OIM ..................................................................................................................................................... 10 3.02.02 Marine Section Leader......................................................................................................................... 11 3.02.03 Rig Mover............................................................................................................................................. 11 3.02.04 Seadrill appointed Marine Warranty Surveyor (MWS)........................................................................ 12 3.02.05 Client Representative ........................................................................................................................... 12 3.02.06 AHTSV Master ..................................................................................................................................... 13 3.02.07 Positioning Surveyor............................................................................................................................ 13 3.02.08 Manning - Crewmembers ..................................................................................................................... 13 3.03 ATTENDING AHTSV ........................................................................................... 16 3.03.01 Minimum bollard pull requirements..................................................................................................... 17 3.03.02 Criteria for rotating around one pinned Leg (walking the Jack-up).................................................... 17 3.04 SITE SPECIFIC PROCEDURES .................................................................................. 17 3.05 WEATHER ........................................................................................................ 18 3.05.01 Weather window standard requirements.............................................................................................. 18 3.05.03 Measuring sea conditions .................................................................................................................... 19 3.06 GENERAL SOIL AND LOCATION SURVEY REQUIREMENTS ................................................... 20 3.06.01 Potential risks and survey methods...................................................................................................... 20 3.06.02 Location categories.............................................................................................................................. 21 3.06.03 Location coordinates ......................................................................................................................... 21 3.06.04 Water depth at location........................................................................................................................ 22 3.06.05 Survey line spacing .............................................................................................................................. 22 3.06.06 Bathymetric survey............................................................................................................................... 23 3.06.07 Seabed debris survey............................................................................................................................ 23 3.06.08 Shallow seismic survey......................................................................................................................... 23 3.06.09 Geotechnical investigations ................................................................................................................. 23 3.06.10 Sampling and testing ............................................................................................................................ 24 3.06.11 Site investigation requirements ............................................................................................................ 24 3.06.12 Geophysical site survey requirements.................................................................................................. 24 3.06.13 Requirements to individual subcontractors.......................................................................................... 25 3.07 LOAD AND STABILITY CALCULATIONS ........................................................................ 26 3.08 PASSAGE PLAN AND NAVIGATIONAL PROCEDURES .......................................................... 26
Approved 18.08.2011
Page 2 of 45
Approved 18.08.2011
Page 3 of 45
1. INTRODUCTION
1.01 Purpose
The purpose of this manual is to outline and provide minimum requirements to ensure that planning, towage, positioning and preloading of Seadrill Jack-ups are carried out in a safe and efficient manner.
1.02
1.03
Responsibilities
This manual and its subsequent revisions shall be approved by the COO. The local Marine Superintendent (or Marine Responsible) is responsible for ensuring that these requirements are incorporated into the site specific procedures. Seadrill Corporate is responsible for the continuous review and update of this manual based on lessons learned and feedback from the rigs and regional offices.
1.04
Definitions of terms
Definitions in this manual are in accordance with ISO 8402 standard. Those definitions which are not included in that standard are in accordance with the terms of ISO 9004 or the Company's own definitions. AHTSV Bathymetric Survey BP Certificate of Location Approval (COLA) Anchor Handling Towing supply Vessel To determine the water depth and any slope of the seabed at the desired location site and to ensure a safe navigable approach to the site. Bollard Pull. The document which verifies that a specific offshore unit can be safely installed on a specific location and be safely operated within the limitations of the Jack-up Marine Operation Manual (MOM) applicable to the unit and the planned operations. The COLA will be issued by a recognised Marine Warranty Surveyor. To obtain soil resistance data to enable the prediction of leg penetration. A move where the duration of towage exceeds 12 hours and standby location(s) are required. A move where the duration of towage is below 12 hours.
Approved 18.08.2011
Page 4 of 45
Approved 18.08.2011
Page 5 of 45
2.01
Step 1 to 12
The planning and sequence of operations have been divided into the following 12 steps: Preparation 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Client location request? Requesting soil and seabed information from client Geotechnical investigation Preparing site specific procedures Requesting Location Certificate of Approval (COA) Marine Warranty Surveyors requirements (MWS) Onboard review of the site specific procedures Preload simulation Onshore pre-move meeting Preparing for rig move Rig move Preloading and final accepting Post Rig Move report
Execution
Step 1 Client location request? This step will be the result of successful negotiations leading to a drilling contract, and does normally not include anything else than collecting various operational information which may be required by the Seadrill Regional Office. Step 2 Requesting soil and seabed information from client This step will under normal circumstances be handled by Seadrill Regional Office. It is essential that this data is requested in such a time that all geotechnical examinations and calculations can be carried out in a professional and satisfactory manner. Especially in areas with special soil conditions which could lead to rapid penetration and/or punch-through. (See section 3.06). Step 3 Geotechnical investigation In order to have the full understanding of the sub-seabed soil all available data shall be forwarded to the Seadrill Marine Engineering Group or geotechnical subcontractor for analysis. That will result in a foundation assessment being issued, giving estimated penetrations and ascertain any risk of rapid penetration and/or punch-through. The sub-contractor shall be approved as per section 3.06.13
Approved 18.08.2011
Page 6 of 45
Approved 18.08.2011
Page 7 of 45
3. GENERAL REQUIREMENTS
3.01 Conduct of operation
While Jack-ups are departing a location, in transit or during emplacement at a new location they operate outside their normal mode wherefore the OIM shall be aware of the requirements set in the specific rig move procedure. Furthermore, it is of paramount importance that the attending AHTSV and other involved services have been verified to have the capability and capacity to perform the functions required to accomplish the operation. The MWS plays a vital and central role in this verification process.
Approved 18.08.2011
Page 8 of 45
Drills and exercises shall be carried out as specified in TMS. Additional special drills may be required if the rig move operation involves a number of non-regular crew members. Where alterations to the Station Bill are required for the intended voyage or upcoming operation, they shall be prepared in due time and the crew shall be instructed accordingly. Drills shall be carried out to ensure that all crew members have understood the changes and are able to act promptly. Exercises and drills should always be recorded in the appropriate log book. 3.01.02 Maintenance and repair work
Maintenance and repair work during the rig move shall be planned with the responsible parties, i.e. Rig Manager, OIM, Marine Section Leader, Technical Section Leader and the Rig Mover. Care shall be exercised to ensure that all systems and equipment vital to sea-worthiness remains unaffected throughout all phases of the operation. Heavy equipment shall only be used or dismantled when conditions are such that safe handling can take place within the pitch/ roll and heave imposed on the Jack-up. Large modification work should be conducted only by a dedicated Project Manager, who works in close contact with the OIM, Marine Section Leader, Technical Section Leader and Rig Mover. The Permit to Work System shall be strictly followed and all permits to be signed by the OIM. If work has been commenced and cannot be completed prior to adverse conditions, the work shall be suspended and the area shall be secured with adequate barriers and signage. 3.01.03 Safety organisation
During rig moves the number of personnel on board will be reduced and the OIM shall ensure that the valid Station Bill, and the positions stated herein, can be manned with the personnel available on board. If this is not the case, the OIM and the rig management must, prior to commencement, create an alternative safety organisation and Station Bill addressing the situation. The personnel onboard has to be instructed and trained accordingly.
Approved 18.08.2011
Page 9 of 45
The operation plan is acknowledged by the Client in the formal pre-move meeting conducted onshore. Prior to commencing each step of the operation, it is important that the OIM conducts meetings with management of the rig move as well as TBRA (Task based risk assessment) and Toolbox Talks with the participating crew. 3.01.05 Damage control
The OIM shall have damage control equipment readily available on board the Jackup to facilitate temporary repairs. 3.01.06 Storm preparedness
During the transit of a Jack-up, the weather can change rapidly wherefore close monitoring is essential. Despite weather reporting services being arranged, the unit shall be prepared at all times for adverse weather conditions. If the weather situation deteriorates in such a way that safe jacking on an alternative location cannot take place, the OIM must, in consultation with the MWS and Rig Mover, evaluate the possibility of lowering the legs to a predetermined position to improve the stability and reduce the stress imposed on the legs. This decision should be carefully evaluated and executed well in advance before reaching the limitations stipulated in the Jack-ups Marine Operations Manual especially for units with leg fixation systems as these can take several hours to disengage. The maximum towing speed when lowering the legs shall be adhered to. Whenever the weather deteriorates, additional monitoring shall be undertaken to confirm the watertight integrity and to verify all lashings and tie downs are still in place and secure.
3.02
Attending personnel
All work related communication shall be in English. OIM
3.02.01
The OIM has a total responsibility for the safety of the rig and personnel at all times as per statutory requirements and he/she is responsible for ensuring that all operations are conducted in such a manner as to safeguard the integrity of all Seadrill assets and third party equipment. The OIM decides when it is safe and practical to commence operations within the limitations of the Marine Operations Manual, having consulted with the Marine Section Leader, Rig mover, MWS and Client Representative. The OIM approves commencement of jacking operations. The OIM reports the progress of the operation to the onshore management every 6 hours as a minimum.
Approved 18.08.2011
Page 10 of 45
The Marine Section Leader is responsible for ensuring that all aspects of the rig move are performed safely and efficiently. He/she liaises with the OIM, MWS, Rig Mover and Client Representative on all matters concerned with the move. He/ she is responsible for operating the jacking control panel. He/she ensures that the stability complies with the Marine Operations Manual at all times, including making any adjustments to trim or heel as necessary in consultation with the MWS. He/she ensures that the watertight integrity of the unit is not impaired and that all watertight closing devices are functioning properly, reference is made to 4.02.02. Note: - It is essential that watertight openings are kept closed, whilst the unit is afloat, or during jacking operations. If it is necessary to open a watertight opening to allow passage between one compartment and another - this may be done, but the opening shall be closed immediately after passing through. He/she ensures that the towing and emergency towing gear are in place, in good condition, complete with certification and ready for immediate deployment. He/she ensures that competent Seadrill personnel are available for the safe deployment of the rigs towing gear to the AHTSV. He/she ensures that all jacking and jetting systems are function tested prior to commencement of the operation and that all pumping systems are fully operational. All bilges and strum boxes are to be checked and cleaned if required. He/she ensures that the sea fastenings of all equipment and cargo are adequate and completed to the satisfaction of the Marine Warranty Surveyor. The Marine Section Leader is responsible for verifying that all checklists pertaining to the move have been completed and signed off prior to commencement of the move. 3.02.03 Rig Mover
The Rig Mover liaises with the Seadrill OIM, MWS, Technical Section Leader and Client Representative on all matters concerned with the operation. He/she confirms that the rig's towing equipment is suitably certified and in good condition and that all communication systems are functioning correctly. He/she is responsible for the conduct and safety of the rig during the tow and will give instructions to the towing vessels with respect to tow wire deployment, passage planning, courses and speeds, after consultation with the Seadrill OIM, MWS and AHTSV Masters.
Approved 18.08.2011
Page 11 of 45
He/she liaises with the AHTSV Masters on all manoeuvres from hooking up boats, under tow, disconnecting, moving to stand off position, running of anchors prior to moving to the final positioning including direct communication with the jacking control room. He/she requests commencement of jacking operations and preloading operations in consultation with the OIM, Marine Section Leader, Marine Warranty Surveyor and Client Representative. 3.02.04 Seadrill appointed Marine Warranty Surveyor (MWS)
The MWS liaises with the Rig Mover, Marine Section Leader and OIM on all aspects of the move to ensure the operation is carried out in compliance with the Marine Operations Manual and site specific procedures. The MWS issues a Towage Approval Certificate when he is satisfied that the Jack-up and attending AHTSV(s) are in a seaworthy condition and can commence the tow in a safe manner. Th e MWS will veri fy t hat t h e t owing eq uip m en t is i n g ood con dition an d t hat all communication systems are functioning correctly. The MWS, in conjunction with the OIM, Marine Section Leader and Rig Mover, decides when it is safe and practicable to commence operations within the limitations of the unit's Marine Operations Manual and the long range weather forecast(s). The MWS monitors jacking, rig move and pre-loading operations. The MWS liaises when necessary with the Client Representative as required on all matters concerned with the rig move operation. The MWS verifies that the rig has acceptable stability at all times and he shall advise on making adjustments to trim or heel as necessary. The MWS verifies, in consultation with the Marine Section Leader and the Rig Mover, that the rig has sufficient positive stability and water depths throughout all stages of the operation. 3.02.05 Client Representative
The Client Representative is responsible for protecting the Oil Companys assets. He/she verifies compliance with the site specific and approved rig move and preload procedures. He/she verifies that the operation is carried out in accordance to the clients procedures where required when approaching a platform or subsea structure/pipeline.
Approved 18.08.2011
Page 12 of 45
The AHTSV Master is responsible for the safety of own vessel. He/she is responsible for ensuring that all towing operations are conducted in a safe manner with due regards to safe navigation, safe working practices and good seamanship. He/she has the obligation to request for a consultation with the Rig Mover, OIM, Marine Section Leader, MWS, and Client Representative to turn the tow and head for shelter in the event of an increasing weather forecast or encounters unexpected bad weather. The OIM is overall responsible and may instruct the Rig Mover to inform the vessels to head for shelter should he deem the situation warrants it. He/she ensures that AHTSV crew is familiar with the towing operation. By the use of a risk assessment process, he/she shall ensure that all hazards have been identified and communicated to the crew prior to each towing operation. He/she reports on any known damage to equipment or vessel to the OIM, Marine Section Leader and Rig Mover at the time of being aware of the damage or at the earliest opportunity thereafter. This information will be communicated to all other relevant parties by the OIM. He/she ensures that appropriate navigation warnings, similar to below, are transmitted on the hour or on approach of other vessels on the Safety Distress VHF Channel 16 or appropriate navigational channel for specific area. 3.02.07 Positioning Surveyor
The Positioning Surveyor is responsible for the proper operation of the positioning equipment and providing constant data showing the position of the unit at all times during the tow and at the proposed location including the stand-off position. He/she performs system checks to prove navigation system confidence prior to departure from the present location and at intervals during the tow and during location positioning operations. He/she will immediately report failures and/or shortfalls in navigation equipment to the OIM, Marine Section Leader, Rig Mover and Client Representative. 3.02.08 Manning - Crewmembers
The minimum manning shall comply with the requirements stipulated by the Country of Registration (Flag State) and the Continental Shelf Authority. The
Approved 18.08.2011
Page 13 of 45
ACTIVITY & SERIOUS HIGH-POTENTIAL POB OF UP HELICOPTER AVAILABLE ALWAYS WITHIN 15 RISKS PRESENT DURING ACTIVITY TO 60 in < 60mins MILES radius 1. Jacking Down a. Wind above operational limits b. Sea-state above operational limits c. Structural failure of legs d. Failure of jacking gear e. In-field vessel collision f. Errant passing vessel collision g. Live pipeline(s) in vicinity of platform YES YES YES YES YES YES YES 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper up to 90 POB up to 90 POB up to 90 POB up to 90 POB up to 90 POB up to 90 POB
Approved 18.08.2011
Page 14 of 45
b. Sea-state above operational limits c. Loss of tow (hawser/tug failure) d. Loss of stability (shifting loads) e. Loss of water-tight integrity f. Shallow water depth (unknown) g. Extreme water depth (unknown) h. In-field vessel collision i. Errant passing vessel collision
3. Jacking Up a. Wind above operational limits b. Sea-state above operational limits c. Structural failure of legs/jacking gear d. Failure of jacking gear e. Punch through f. Rapid penetration g. Collision with platform h. In-field vessel collision i. Errant passing vessel collision j. Live pipeline(s) in vicinity of platform
YES YES YES YES YES YES YES YES YES YES
60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper 60 POB + capacity of chopper
A TBRA Shall be completed and signed by the participating persons including the client rep for carrying more persons than 60 POB. That is to ensure definite conformation of helicopters, boats, etc. will be available. The signed TBRA shall be included in the appendix to the rig move procedure. The minimum core crew recommended on board a Jack-up during a field move or ocean tow should consist of following: 1 OIM 2 (two) Marine Section Leaders depending on duration of preloading operations. 1 Maintenance supervisor 2 (two) Electricians
Approved 18.08.2011
Page 15 of 45
It is not always required to have a Marine Warranty Surveyor attending during the entire move, however, in order to issue a COLA the Marine Warranty Surveyor shall attend the Jack-up prior to commencement of the move for surveying the unit and issuing the COLA.
3.03
Attending AHTSV
All AHTSV shall be fit for the purpose for the intended operation. All involved vessels shall be in compliance with standards stipulated in the COLA, the Jack-up Marine Operations Manual and recommendations issued by the attending MWS. All trading certificates shall be valid and all vessels shall be able to communicate in English around the clock. The AHTSV and its equipment shall be inspected and approved prior to commencement of the towing or any anchor handling operation. In situations when this inspection is not practicable, the record from a previous inspection should be consulted and/or a valid certificate from a recognized MWS shall be presented e.g. Marine Warranty Towing Vessel Approval Certificate. The inspection shall as a minimum include the following items: Bollard pull/ BHP meet the minimum requirements for the particular unit Towing and work winches primary and secondary Auxiliary winches Stern rollers and mechanic stoppers (E.g. Shark Jaws / Karm Forks) Main and spare towing wires Work wires, shackles, connecting links and any other equipment planned to be utilized during intended work scopes Crew list including position on board and qualification notes All vessels shall be suitable manned in accordance to legislation and work scope and shall be capable of operating on a 24 hours continuously basis, if required within the work scope The following certificates shall be available and presented upon request. All certificates shall be valid without any notation of restrictions which could affect required performances and have an impact on intended operations: Certificate of Registration Class Certificates for Hull and Machinery Safety Construction Certificate Safety Equipment Certificate
Approved 18.08.2011
Page 16 of 45
Verification shall be obtained to ensure that sufficient fuel, lube oil and potable water are available for the expected duration of operation including 25% spare. General suitability check shall be performed to confirm that communication and navigation equipment are suitable, sufficient and operational. In shall be confirmed that there are no operational limitations placed on the vessel. 3.03.01 Minimum bollard pull requirements
The minimum required bollard pull, as specified for the individual Jack-up, shall be stated in the rig move procedure. Refer to TMS doc for more details on bollard pull requirements 3.03.02 Criteria for rotating around one pinned Leg (walking the Jack-up)
Positioning any Jack-up by rotating around a pinned leg is not normally allowed and can only be approved by the COO. Such approval will require information and calculations as follows: Maximum pull applied from the AHTSV Maximum penetration of the leg which the Jack-up is rotating around Maximum seabed torsion resistance Maximum torsion arm Angle of rotation (degrees of turn) shall be minimized and stated in the approval.
3.04
Approved 18.08.2011
Page 17 of 45
The content of the site specific pre-load procedure shall address: Summary of precautionary standard operations Summary of precautions for punch through potential Settlement and rapid penetration Action in the event of slow settlement Action in the event of rapid settlement or punch through Contact details Soil foundation assessment Pre-loading sequence Precautions during pre-load operations Where plans are forwarded by the client, the details shall be reviewed by the regional Marine Responsible and incorporated into Seadrill procedures. The final site specific procedures will be forwarded to all involved parties for their approval and signature and constitute the basic guidelines for the rig move to be executed.
3.05
Weather
The establishment of good quality weather forecasting, which should be both site and route specific, is essential for identifying the weather window required and for the safe conduct of the operation. The established arrangement should as a minimum provide forecasting twice a day and the arrangement has to include immediate update if there is a significant change (e.g. gale warning) in the predictions. It is advisable to commence the forecasting timely thus having a possibility of evaluating the development of weather pattern etc. and making the necessary comparison between the forecasted and actual weather. Besides the established forecasting all other available meteorological data and information related to the area of operation and route should be studied closely. Units that do not have a weather facsimile installed should consider taking a portable instrument in use, especially where ocean tow is being planned. The decision to commence a rig move shall be based on a suitable window.
3.05.01
During Field Moves two independent weather centres shall have identified and documented a weather window suitable for: The safe lowering of the unit on location of departure The safe transit from location to location The safe installation of the unit and preloading The safe elevation of the unit on location of arrival
Approved 18.08.2011
Page 18 of 45
Field Moves two independent weather centres shall have identified a weather window suitable for: The safe lowering of the unit at the location of departure The safe transit from the location of departure to a nominated and accepted location of refuge on the route where the tow can be in a sheltered area or the unit can safely jack out of the water and take the required preload on board.
During Ocean Tow two independent weather centres shall have identified and documented a weather window suitable for: The safe lowering of the unit at the location of departure and a minimum of three days route forecast where acceptable weather conditions prevail. There should be no indication that a tropical cyclone is under development which could have a severe impact on the tow. 3.05.03 Measuring sea conditions
Weather forecasts should always be compared with the actual weather observations made onboard the Jack-up. If instrumentation for recording weather and sea condition is available, data should be captured frequently and logged. Self-elevating units, which are not equipped with instrumentation for wave recording, can besides the general observation and recording use the following method for establishing sea-conditions as wave height, period and length: Observe from a suitable position in the leg well, the ladder steps or rack teeth at the waterline. Observe and note for 10 minutes at hourly intervals the number and height of waves passing and record the number of waves and their respective heights. List the number of waves 2', 3', 4', 5', 6', etc. When a 10 minute period of observation has been noted calculate as follows: Multiply the wave height by the number of waves to obtain multiplier. Add all the multipliers together. Divide by the number of waves, which will give the average wave height. Divide the number of waves by 600; this being the number of seconds in 10 minutes. This will give you the average wave period per second.
The average wave height and period should then be plotted on an hourly graph. After several hours a trend will become apparent and this could predict a potential jacking period well in advance.
Approved 18.08.2011
Page 19 of 45
Bearing failure & settlement under storm loading conditions Site specific assessment to be carried out Sliding failure
Scour
Approved 18.08.2011
Page 20 of 45
Submerged metal objects / wrecks pipelines and cables Shallow gas / Gas pockets Sub-surface faults Geological hazards Seabed faults (depressions), reefs, rock pinnacles, wrecks etc.
3.06.02
Location categories
The various locations have been divided into four categories as follows: Category A A COLA has previously been issued for this particular Jack-up at this location. Category B A COLA has previously been issued for similar type of Jack-up and all soil and location survey data is available for this location. Category C Any type of Jack-up has previously been emplaced on this location. Category D No JACK-UP has previously been emplaced at this location.
Note:
Of above four location categories Type A & B can be approved by the Seadrill Regional Office. Categories C & D can be approved by the Regional Office unless these locations have a risk of rapid penetration or punch through, in which case Seadrill Corporate shall approve the site specific pre-load procedure. Corporate approval could involve third party review of all procedures as well as attendance by an observer (Marine Surveyor) appointed by Corporate.
3.06.03
Location coordinates
The location coordinates are expressed by latitude and longitude in degrees, minutes and seconds and should be at least 2 but preferably 3 decimal places for accuracy and shall include the datum used. I.e. international spheroid, WGS 84 ED50 etc. and the projection used UTM zone.
Approved 18.08.2011
Page 21 of 45
This should be provided in relation to chart datum, meaning sea level or lowest astronomical tide stating which reference has been used. 3.06.05 Survey line spacing
In general, the surveyed area shall as a minimum be 1 x 1 km square centered on the designated location. Two line grids each consisting of a minimum of 11 lines, spaced at 100 meters intervals shall be acquired in orthogonal directions to cover the survey area. The centre lines of the line grids shall intersect at right angles at the designated location. The program of lines shall total be (11+11) x 1= 22 kilometers, excluding any necessary extensions to accommodate towed equipment or to enhance data interpretations. Line separations shall be reduced to a maximum of 50 meters within 200 meters of the designated location, where indicated, by the complexity of seabed relief and sub seabed soil conditions. The grid may be modified in accordance with the characteristics of the equipment used. However deviations from the overall orthogonal grid pattern should be avoided. The survey grid orientation shall be defined to optimize data coverage based on pre-existing knowledge of seabed and morphology, geology and local environmental conditions. Tie lines to other known locations and geotechnical borehole sites shall be included in the survey line plan whenever possible.
For Category A and B locations, a surveyed area of minimum 300 x 300 meters square centered on the designated location can be accepted. Two line grids each consisting of a minimum of 7 lines, spaced at 50 meters intervals shall be acquired in orthogonal directions to cover the survey area. The centre lines of the line grids shall intersect at right angles at the designated location. The program of lines shall total (7+7) x 300= 4200 meters, excluding any necessary extensions to accommodate towed equipment or to enhance data interpretations. The grid may be modified in accordance with the characteristics of the equipment used and local site conditions; however deviations from the overall orthogonal grid pattern shall be avoided. The survey grid orientation shall be defined to optimize data coverage based on pre-existing knowledge of seabed and local environmental conditions.
Approved 18.08.2011
Page 22 of 45
The water depth shall be measured over the entire length of each grid line using a high precision echo sounder. The measured depths shall be reduced to the Lowest Astronomical Tide Datum. The tolerance for water depth measurements is 0.5 meters. Swathe bathymetry techniques should be used to survey rig access routes. 3.06.07 Seabed debris survey
Seabed surface surveys should be carried out using side scan sonar, Swathe bathymetry and high resolution echo sounder techniques. The survey should be such that it covers the immediate area around the location (1 km squared) and identifies seabed features and obstructions. The site survey should also include a magnetometer (this may be waived based on the type of side scan and echo sounder used) survey to identify objects below the mud line such as pipelines, wrecks and other metallic objects. Seabed surveys that are older than 6 months prior to rig emplacement should not be used. 3.06.08 Shallow seismic survey
This is required to provide the general near surface geological structure to identify reflectors which may represent changes in the soil characteristics. The data may also indicate any shallow gas within the vicinity of the location. The seismic equipment shall be able to provide detailed information to a minimum depth of 50 meters below the mud line or to the anticipated penetration + 2.5 times the spud can diameter. The report shall include at least 2 vertical cross sections passing through the location showing all relevant reflectors and any other pertinent information that will assist in carrying out analysis. The shallow seismic survey shall be interpreted by the competent persons who carried out the survey and every effort shall be made to comment on the types of soil and their strengths. This will require correlation with the results from the borehole / coring. Note: Seismic surveys alone are not normally sufficient to enable an analytical appraisal of the foundation with regards to predicted leg penetration. 3.06.09 Geotechnical investigations
These are site specific and required in areas where no soil data is available or where the foundation conditions are known to be hazardous. As a minimum at least one borehole should be made to a depth of 30 meters or to the anticipated leg penetration + 1.5 times the spud can diameter and as close to
Approved 18.08.2011
Page 23 of 45
For Category D Locations and where no other geotechnical information is available one bore sample (coring) shall be taken under each spud can All layers should be investigated so that the properties of all layers are known with confidence and that there is no uncertainty in the formation record. The site investigation report should include but not be limited to the following: Profile of undrained shear strength versus depth for cohesive soils Effective stress strength parameters for cohesion-less soils Piezocone penetration test (PCPT) records Appropriate soil classification tests including Atterberg limits (clays), water contents, particle size distributions, unit weights, relative densities (sands) and Sensitivity (clays) The over-consolidation ratio (OCR) for cohesive soils should be determined especially where foundation fixity is an issue. 3.06.10 Sampling and testing
The site investigation should comprise undisturbed soil sampling and/or Piezocone penetrometer testing or a combination of both.
3.06.11
Review all known Geotechnical and Geophysical field data and compare with selfelevated Jack-up historical performance data (Desk Study). 3.06.12 Geophysical site survey requirements BATHYMETRY survey using echo sounder, tuned transducer & swathe techniques SEABED SURFACE SURVEY divers, side-scan sonar, ROV or scanning radar
Approved 18.08.2011
Page 24 of 45
ADDITIONAL SURVEYS FOR SPECIFIC LOCATIONS MAY BE REQUIRED AS FOLLOWS: 3D SUB-SURFACE PROFILING SINGLE OR MULTIPLE BOREHOLES Sufficient geotechnical and geophysical data shall be available to ensure a proper analysis can be carried out to ensure the safe emplacement and operation of the Jack-up. Site specific assessments may be required to be undertaken depending on the results of the foundation assessments and may require a reduced max preload value and Variable deck load value to enable the rig to be safely positioned on the location. This would require the assessment to meet the requirements of SNAME. 3.06.13 Requirements to individual subcontractors
Marine Warranty Surveyor A Surveyor representing a company approved by the Underwriters and which has been authorized by the COO of Seadrill to issue both the COLA for emplacement of the self-elevating drilling rig and verification documents (Towing Certificate, Tie Down Certificate etc.) on the accomplishment of intermediate stages of the operation. Geotechnical Contractor The approved contractor(s) shall be well recognized within the industry and be acceptable to the underwriters and MWS. The approved contractor(s) shall operate a formal quality management system, specifically encompassing seabed survey and/or soil investigation procedures, processing and reporting. The approved contractors quality management system(s) should have been audited and be accredited by a third party to international standards. The approved contractors documented procedures and records of competency assessment shall be available to the MWS and to Seadrill Corporate upon request. The surveys and investigations completed shall satisfy all legal, regulatory and statutory requirements in force in the area of operations. Site survey work will normally adhere to the current UKOOA Guidelines for the Conduct of Mobile Drilling Rig Site Surveys. (Volumes 1 and 2) These documents are to be supplied to all clients by Seadrill.
Approved 18.08.2011
Page 25 of 45
3.07
3.08
Approved 18.08.2011
Page 26 of 45
3.09
Approved 18.08.2011
Page 27 of 45
3.10
Towing gear
The following guidelines cover technical and marine r eq u i r e m en t s t o t h e Ja c ku p ' s towing gear and its use. All equipment required for the passage or operation shall be confirmed fully functional and operational. General guidelines: All towing gear like tow lines, tow line connection points, chain, bridle legs, bridle apex and shackles shall be certified by a 3rd party inspection company. The equipment used shall correspond with the maximum bollard pull which can be obtained from the most capable attending towing
Approved 18.08.2011
Page 28 of 45
Towing bridles shall be construed as follows: The bridle leg should consist of either stud link chain or a combination of chain and wire rope. If the latter is used, the chain part should as a minimum reach from the connecting point beyond the deck edge to prevent chafing of the wire rope. The end of all chains shall be equipped with enlarged links to fit into connecting points on deck and allow easy application of shackles. The connection points on deck have to be of the Smitt-Bracket type. The bridle legs (chain or chain and wire) shall be connected to a Delta plate or towing ring. An intermediate pennant wire can be attached to the delta plate or towing ring for easier handling when connecting the towing vessel. This wire has to have a sufficient length to enable the vessel to connect or reconnect at safe manoeuvring distance from the hull. The breaking strength of the intermediate pennant shall not be less than that of the main tow line. The use of fuse wire or weak links is not recommended. However, if unavoidable due to local requirements the reduction on the fuse wire should never exceed 10% of the main tow line strength. Synthetic springs shall not be accepted in connection with towing with the exception of harbour towing. In order to obtain sufficient spring load the use of anchor chain length as weight is recommended.
Approved 18.08.2011
Page 29 of 45
Emergency towing wires shall be installed in addition to the main tow bridle and shall be secured to the edge of the units deck outside all obstructions for easy deployment in an emergency The securing shall be with soft lashings at sufficient intervals but not exceeding 3 meters, enabling release by strong pulling of a towing vessel. The emergency tow connection can be supplied with an extension wire long enough to ensure safe handling and avoid chafing. A messenger line should be attached and extended one unit length aft of the stern. A conspicuous plastic float should be attached and trailed.
3.11
Approved 18.08.2011
Page 30 of 45
It is the duty of the OIM to be conversant with the Clients plans and to ensure that the rig crew and participating vessel crews are adhering to the contingency requirements. The crew participating in the rig move shall be instructed as to their duties prior to commencement of the rig move. The proper co-ordination of procedures between the vessels participating in the tow should be considered and agreed upon between the Masters, however, without interfering with the integrity of the Masters to act in an emergency as dictated by the relevant rules for vessels in distress.
3.12
Communication
Jack-ups are equipped with several means for both internal and external communication. Maintaining a radio link between the rig and the attending Vessels shall be confirmed prior to departure including primary and secondary methods. Communication links shall be maintained on a 24 hour basis. The primary link should be a marine VHF working channel. VHF channel 16 shall be monitored continuously. Agreed alternative links shall be maintained. These links may be provided by any other communication means available on all units concerned. If direct phone lines are not available, Satellite communication should be the primary media for contacts to shore and for data transmission. Where available and as a supplement to VHF communication, it may be practicable to utilize portable UHF radios. This can have the advantage of communication without interference where heavy traffic on VHF-channels is dominating. It is a good practice to establish a list of radio stations, which may be utilized by the participating vessels or by shore contacts in an emergency.
4.
4.01
OPERATION
Moving off location
General procedures The general procedures for moving off location are influenced by several factors and require widely differing approaches, which cannot be covered in the Marine Operations Manual for the Jack-up. Upon completion of the preparation for the rig move it is the responsibility of the OIM to inform the relevant authorities and/or other involved parties about the intended rig move. Requirements that pertain to the area of operation can be extensive and it is recommended to coordinate the information that needs to be transmitted with both the local shore base and the Client's Representative.
4.01.01
Approved 18.08.2011
Page 31 of 45
Confirmation that the attending vessels have been inspected by the MWS and approved fit for purpose are available, prepared and ready to commence the rig move should be verified. Acceptance by the MWS, is confirmed through a Certificate of Tow Approval (COTA) in connection with all rig moves including extended field moves or ocean tow/transport, as required by the underwriters. Any delays, caused by reasons which cannot be considered part of the moving off location procedure or which could give reason for dispute in relation to the contract or part of the contract, e.g. applicable rates, should be duly noted and reported either as part of the rig move report or, if deemed necessary, in separate documentation. 4.01.02 Jacking operation
Moving off location should only commence when the conditions are in compliance with the limitations stated in the Marine Operations Manual. However, jacking to a more convenient air gap waiting the final decision can be of advantage and is acceptable. If the air gap is reduced below the minimum requirements for the area and time of the year, it shall be possible to resume safe air gap within the time limit dictated by the advance warning system for excessive weather. Units equipped with leg clamping systems or other means of securing the legs in a fixed position can commence deactivating the system in preparation for jacking prior to completion of the securing, if approved by the OIM and subject to no extreme weather being imminent or anticipated for the rig move period. The period between jacked and afloat condition of a Jack-up should be kept to a minimum, as this is an especially vulnerable exposure position. Extra emphasis on reducing this period should be made where/when marginal conditions exist. Connecting of towing vessels should take place at a safe air gap meaning that the vessels are given the optimum conditions for manoeuvring without restrictions imposed by the hull and/or helicopter-deck. Prior to the Jack-up reaching the afloat condition (preferable when having reached a draft of 2-3 meters) the jacking should be halted and a thorough check of the water-tight closures will be conducted. Only if/when the water-tight integrity has been confirmed, the final jacking and leg retrieval should be attempted. The time of confirmation of the water-tight integrity shall be noted and reported in the rig move report. The retrieval of legs and spud cans can be achieved by jacking the hull to a draft in excess of the calculated displacement. The limitations allowed are stated in the Marine Operations Manual.
Approved 18.08.2011
Page 32 of 45
When soil conditions and/or deep penetration restrict the timely retrieval or even keep the spud cans fixed, the high and low pressure jetting systems arranged on the spud can should be utilised. The freeing of one leg at a time can be of advantage as the water flow can be maintained at a higher capacity, however, caution should be exercised when this approach is used to avoid unnecessary strain in the leg or leg guides resulting from hull rotation when one leg breaks free. Guidance and information that could assist in evaluating the risk when using alternative methods should be tried obtained from any available source either locally or from the Seadrill Regional Office. When retrieving the legs a leg responsible person shall be sited at the leg well and in radio communications with the jacking control room to give immediate warning to the Jacking Control Room about any damages or hazards that can been seen. This could be loose pipes, damaged bracings or debris caught in the leg structure. In addition there shall be sufficient personnel for greasing the leg racks/ guides. Special attention should be paid to the accumulated soil on top of the spud cans when approaching the final stage of retrieval. Especially when deep penetration has been achieved in clay, the accumulated amount could become critical and result in damage to the hull. Close observation of power consumption or pressure indicators at the control stations can likewise indicate that a hazardous situation is under development. Accumulated soil on top of the spud cans can be washed off by utilising the high pressure system installed (top of spud cans) or by towing the legs in a partly lowered condition, subject to weather and sea conditions. The Rig Mover should advise the towing vessels of his decision and position of the legs/ spud cans enabling in safe navigation route due to excessive draft, reduced speed or drifting of the tow due to current or wind. 4.01.03 Use of towing vessels
Assisting vessels should be utilised to the extent possible to keep the unit in position during the leg retrieval. Where only one assisting vessel is available, the most convenient position should be chosen taking into account the wind, sea and current conditions during the period of time needed. During very short field moves the assisting vessel(s) can be kept in their position at the starboard or port quarter, however, if reconnection to assist at the bow is required, this should only be attempted at a safe distance from any obstructions in the area. During reconnection of the towing vessels the unit should be kept at a stable position without making headway.
Approved 18.08.2011
Page 33 of 45
The use of anchors for moving the unit off location is not considered a standard requirement but can be advantageous where special circumstances warrant this or it is required by the Operator or attending MWS. The anchors shall always be secured in their anchor racks during field moves. In connection with extended field move extra securing with chain or wire together with quick release should be added. For ocean tow and upon request by the MWS for extended field move in adverse weather areas, the anchors should be double secured on the bolster to prevent movement or loss.
4.02
Transit
The period to be considered as towing period will be the time from completion of going off location to commencement of the going on location time.
4.02.01
General procedure
During the towing period the OIM and Rig Mover shall ensure:
Approved 18.08.2011
Page 34 of 45
4.02.02
Watch keeping
Radio communication is maintained with the attending vessels 24 hours of each day. During the tow a sea watch, enabling an around-the-clock (24 hours) control of the safety and integrity of the unit, is maintained in all respects as dictated by regulations and proper seamanship. The duties of the engine watch will be to maintain the needed power supply and other necessities as dictated by the circumstances, and be prepared to respond to any emergency that might develop. The deck watch shall maintain communication with the attending vessels and establish a routine tour on the unit to check that the weather-tight integrity is maintained, that securing is maintained and that re-securing takes place should this be necessary. Observation of the navigational lights and signals are exhibited properly shall also form part of the tour. The towing gear shall, weather permitting, be inspected for chafing or other damage that could have an undesired impact on the safety of the established towing connection. The tour shall, as a minimum, take place at intervals of 2 hours. However, when deemed necessary by the OIM, a higher frequency should apply. The watch shall, during the tour, carry a portable radio enabling immediate contact with the control room. As part of the daily routines the Person in Charge or his delegate shall keep records of all occurrences or observations that could be of interest to the safety of the unit. This includes but is not limited to: 2 hourly water tight integrity checks including checking /sounding all spaces/tanks/voids below deck. Daily calculation of the water and fuel supplies.
Approved 18.08.2011
Page 35 of 45
Note: In certain areas the potential for activity by pirates warrants the use of extra personnel for the sea watch. This shall be included in the planning of the day-to-day work to ensure that excessive working hours are avoided and alertness is at the optimum at the most crucial hours. 4.02.03 Weather observations
The motion characteristics of the vessel shall be observed closely and where/when weather limitations are approached, corrective actions shall be taken e.g. by altering the heading of the tow or altering the pull exercised by the towing vessel(s) or altering length of tow wire. Should the unit be unable to maintain the motions within the values derived from the critical motion curves, steps shall be taken to minimize the danger for the crew and damages to the unit. The influence on tows by weather and the dangers of adverse conditions are wellknown and documented, thus the observation of weather and especially the changes compared to predictions can give trained observers early indication of potential upcoming risk. As a minimum, a record at intervals of 4 hours of the following shall be maintained during all rig moves: Position and speed Wind force Wind direction Sea height Sea period Swell height Swell period Barometric reading Temperature Cloud observation Actual weather shall be monitored and compared to the forecasted weather prior to the move to gauge the accuracy of the forecasted weather. The observation shall be compared with the forecast received from the weather bureaus and where development is in contradiction to the forecast, contact with the bureaus should be made for verification or clarification. Alternative weather forecasting sources can be sought to obtain further details. Whenever adverse weather (gale warning) is forecasted for the planned route, the frequency for observation shall be increased.
Approved 18.08.2011
Page 36 of 45
Generally, all Jack-ups have equipment on board to determine the unit's position at any given time. During field rig moves in some parts of the world, the operator will provide position survey companies who, with their equipment and expertise, will assist the Rig Mover by providing exact information concerning the position, and other relevant navigational details, in order for the Jack-up to perform a safe transit from one location to the next. The navigational experience of the Rig Mover and visual observations, supplemented with survey companies and towing vessels information, will enable the Rig Mover to perform safe manoeuvring between locations. If the positioning equipment of the Jack-up fails for any reason, during an extended field move or ocean tow it is a requirement that the Rig Mover establishes the necessary routines to have the rigs position and any navigational information recorded by obtaining information from the towing vessel(s). The position of the tow shall be recorded at a minimum interval of four (4) hours, depending on transit area. The Marine Section Leader and Rig Mover shall ensure that the units own navigational means are utilised to the greatest possible extent and any deviation observed, shall be brought to the attention of the Master(s) of the towing vessels and clarification obtained. During extended field move or ocean tow the daily position, together with other information, shall be forwarded to the shore base with copy to Seadrill Regional Office. Where Operators or local authorities require advice about the transit of Jackups either directly or through the local shore base, the OIM will ensure that data as requested is submitted either directly or through alternative routes. Even if such local reporting is not requested, it is advisable to report the intended move and frequent position to the local authorities that could have an interest,
Approved 18.08.2011
Page 37 of 45
Crane operation during the rig move shall be limited to an absolute minimum, and, as a general rule, the cranes shall remain in the support structure secured against vertical or lateral movement. Any use of the cranes during a rig move has to be approved on a case-to-case basis by the OIM and a PTW issued. Where the situation permits the use of a crane, this shall be limited and the return to the support structure shall be executed immediately upon completion of the crane operation. For ocean tow and where required by the MWSs recommendation for an extended field move, the cranes have to be secured to avoid revolving. When crane operation is required over the side during rig move, e.g. in case of personnel transfer (injuries) or if equipment has to be transferred from attending vessels, the Jack-up has to be stopped or kept into the wind without making headway. Attention to the dynamic forces and manoeuvrability of the vessel will always have to be evaluated carefully prior to any crane operation while under tow. 4.02.06 Minimum bunkers of diesel and portable water for passage
The Marine Section Leader shall ensure that adequate bunkers of diesel fuel and potable water are on board prior to the rig move. Bunkered volumes will take into consideration the number of personnel on board, the duration of the rig move, the possibility of the move being extended due to inclement weather or diverting to a stand by location or near by port of refuge and elevating the rig above the wave crests.
4.03
Going on location
Going on Location, on completion of the sea passage the Rig Mover shall be responsible for manoeuvring the rig into final position by providing the tow vessels with detailed instructions on vessel headings and engine power to be applied.
Approved 18.08.2011
Page 38 of 45
Before commencing the final approach, certain items have to be checked or verified as follows: Positioning equipment installed and confirmed operational. Location marking confirmed placed in position as agreed for both location and obstructions. Auxiliary vessels and/or assisting tow/ anchor handling vessel(s) in readiness. Platform(s) advised of the approach and installation of the Jack-up and confirmation obtained that 'hot' platform(s) is (are) ready to shut-in if required. Final approach to a platform shall normally commence during the hours of daylight. Final approach to platform during the hours of darkness can be allowed provided the following criteria are met: o The platform, its surroundings and the Jack-up are well lit providing adequate visibility to the rig move team (Rig Mover, Warranty Surveyor, Offshore Installation Manager and Barge Master) onboard during the final approach. o Positioning equipment to be verified to be fully functioning by the positioning surveyor and the rig move team when the rig is at the standoff position. o Anchor winches to be tested at the standoff position to verify they are in satisfactory condition prior departing from standoff position. o Should any adverse situation arise during the final approach to the platform, all operations will be stopped and the rig soft pinned until the situation is resolved. The Rig Move Team will then decide, depending on circumstances, to resume with the approach during darkness or wait till daylight. Weather and sea conditions within limitation as stated in the Marine Operations Manual. Acceptance from the Marine Warranty Surveyor is obtained for commencing the approach. The crew of the Jack-up and other personnel are instructed about duties and advised about the operation. 4.03.02 Conditions on location
Whenever approaching the final location, whether an open sea location or a platform or other installation, the Rig Mover shall have in his possession the COLA issued by the appointed Marine Warranty Surveyor. The details contained in the same shall be checked and verified and particular attention shall be given to any recommendations or limitation incorporated in the approval. In case of vessels being observed within the exclusion zone (500 metres) of final location or in the approach channel, radio warning about the imminent approach shall be broadcasted with a request to clear the area.
Approved 18.08.2011
Page 39 of 45
The approach to a Wildcat Location should be made in a manner that maintained the rigs heading in the direction of the prevailing weather. In certain cases, the operation of helicopters and supply vessels require that the rig is emplaced on a heading that is not in the direction of the prevailing weather. This is only acceptable when the rigs stability remains within the limitations set out in the MOM. Prior to final approach to the location, the Rig Mover Shall ensure that there is sufficient power available, a spare generator should be on standby for immediate use. The tow should reduce the speed in time for the re-positioning of the towing vessel and the lowering of the legs. The crew shall be alerted in due time and a TBRA and tool box talk shall be performed involving all participants. Positioning equipment and jacking system shall be checked and confirmed in satisfactory operational conditions. The spud cans shall always be kept sufficiently above the seabed during the final approach within the surveyed area to ensure a minimum clearance of 5 meters above any seabed obstructions or to compensate for inaccuracy in the water depth expected. The legs shall only be lowered to 1.5 metres once the rig is within 100 metres of the location with minimal headway. The final lowering of the legs and engagement of the seabed with the spud cans shall preferably be executed with the unit making no/very limited headway. Where some headway is unavoidable, it shall preferably be ensured that the first bottom engagement is made by the two stern legs. Single leg touch down shall be avoided at all times. Furthermore this approach will minimize the change of the heading during the bottom engagement period. Even though the approach of a Wildcat Location generally does not require the greatest accuracy in positioning, it might be necessary to use anchors for the final and accurate positioning. The Seadrill Regional Office, Marine Section Leader and
Approved 18.08.2011
Page 40 of 45
The running of anchors shall take place based on a pre-agreed anchor pattern, which has the acceptance of the Operator and the Marine Warranty Surveyor. The anchor pattern shall, whenever possible, be laid in such a way that crossing of pipelines, cables or other subsea obstructions is avoided. If necessary, the maximum safe distance from such obstructions shall be obtained by means of spring buoys. Close attention shall be paid to the fact that the anchor handling vessel is maintaining sufficient pull to ensure vertical clearance of pipelines and cables while running anchor moorings.
Approved 18.08.2011
Page 41 of 45
4.04
Preloading
The Jack-up has to be preloaded to the minimum required seabed reaction as stated in the Marine Operations Manual and in accordance with the Certificate of Location Approval (COLA) and strictly in accordance with the site specific pre-load procedure issued by the Seadrill Regional Office. Preloading shall only commence when the final acceptance of the location has been received from the Client's representative.
Approved 18.08.2011
Page 42 of 45
This preload shall be based on the year-round operational requirements, and only where special circumstances have been accepted prior to going on the location, a deviation will be incorporated in the location approval. The on board Marine Section Leader shall carry out a preload simulation and forward same to the Seadrill Regional office for approval. Preloading shall not commence unless there is a minimum weather window of 72 hours. As an alternative to the 72 hours requirement, a procedure for dumping the preload water and jacking up to safe height should be considered. Depending on the expected duration of the preload operation it may be necessary to have an even longer weather window or at least be in a position to have taken on sufficient preload to allow it to be dumped and the hull jacked above the wave crests to await the next suitable weather window to complete the preload operation. The default method of preloading shall be single leg with the hull in the water. Preload holding time will depend on the type of formation soil which is described in the foundation site assessment report. The minimum acceptable preload holding time is three (3) hours without any settlement. This may be reduced to 1 hour if previous experience of the area is known. Preloading shall take place with a minimum air gap, taking into account the tidal influences and the actual and expected weather criteria during the preload period. When an acceptable minimum air gap cannot be maintained, the Marine Section Leader and Marine Warranty Surveyor shall evaluate the overall situation and, if deemed necessary, abandon the operation and await improved conditions. If, due to weather conditions, a preload operation has to be abandoned, dump as much preload as possible and jack the unit to a height which ensures that the waves will not reach the bottom of the hull. The unit shall thus maintain alertness to any change in the weather and be prepared to adjust on short or immediate notice to any development in the wave action. The preload shall preferably be taken on board in an uninterrupted sequence to avoid thixotropic effect (building a crust). This effect has relevance in soil of clay or clay nature and shall be considered a high risk for punch-through. If the above effect is allowed to develop, it can become necessary to abandon the location or reposition the unit on a virgin soil. Preload shall be taken on board in a pre-planned sequence ensuring equal distribution on the legs. It is recommended to prepare a written instruction based on the approved simulation of the preload operation. When the Jack-up is positioned close to a platform and where a potential risk of punch-through or rapid penetration is apparent, extra care shall be exercised
Approved 18.08.2011
Page 43 of 45
4.05
4.06
Approved 18.08.2011
Page 44 of 45
4.07
5.
5.01
5.02
Templates
.01 .02 .03 .04 .05 .06 Rig move procedure Preload procedure End of rig move report Daily positioning reports during tow Rig move log book Final position record
Approved 18.08.2011
Page 45 of 45