FLOOR
Ground floor
1st floor
2nd floor
3rd floor
4th floor
5th floor
6th floor
7th floor
VO works for kerb
WORK
PROGRESS %
0%
100%
100%
100%
45%
50%
0%
0%
49%
Total:
VALUE
RM146,579.00
RM300,022.50
RM300,022.50
RM135,614.90
RM132,578.75
TARGET TO
COMPLETION
15/1/2014
17/12/2013
11/12/2013
31/12/2013
31/12/2013
31/12/2013
RM1,014,817.65
CORRIDOR
FLOOR
Ground floor
1st floor
2nd floor
3rd floor
4th floor
5th floor
6th floor
7th floor
WORK
PROGRESS %
0%
0%
0%
0%
0%
0%
0%
0%
VALUE
TARGET TO
COMPLETION
20/1/2014
20/12/2013
20/12/2013
20/12/2013
31/12/2013
31/12/2013
7/1/2014
7/1/2014
SCREEDING
FLOOR
Ground floor
1st floor
2nd floor
3rd floor
4th floor
5th floor
6th floor
7th floor
WORK
PROGRESS %
0%
100%
100%
100%
100%
100%
100%
100%
Total:
VALUE
RM32,432.40
RM61,696.80
RM61,696.80
RM61,696.80
RM53,004.60
RM38,154.60
RM38,154.60
RM346,836.60
TARGET TO
COMPLETION
7/12/2013
I.D WORKS
FLOOR
Ground floor
1st floor
2nd floor
3rd floor
4th floor
5th floor
6th floor
7th floor
ONSITE
PROGRESS
0%
70%
70%
70%
70%
70%
70%
70%
OFFSITE
PROGRESS
0%
10%
15%
15%
10%
VALUE
RM312,760.00
RM681,761.00
RM682,325.00
RM561,915.00
RM516,823.00
RM288,074.00
RM288,074.00
WORK
PROGRESS %
0%
80%
85%
85%
70%
80%
70%
70%
RM3,331,732.00
Total:
WORK
PROGRESS %
100%
100%
100%
100%
100%
100%
100%
100%
Total:
VALUE
RM10,920.00
RM22,575.00
RM22,575.00
RM23,310.00
RM16,520.00
RM11,935.00
RM11,480.00
RM119,315.00
TARGET TO
COMPLETION
TARGET TO
COMPLETION
29/1/2014
19/12/2013
19/12/2013
19/12/2013
31/12/2013
26/12/2013
10/1/2014
13/1/2014
TARGET TO
COMPLETION
29/1/2014
19/12/2013
19/12/2013
19/12/2013
31/12/2013
26/12/2013
10/1/2014
13/1/2014