Vous êtes sur la page 1sur 7

BILL OF MATERIALS

I. GENERAL REQUIREMENTS DESCRIPTION


MOBILIZATION/ DEMOBILIZATION PERMITS ( BUILDING PERMITS, OCCUPANCY PERMITS & ELECTRICAL CONNECTION) HOUSING & TRANSPORTATION SERVICE OF WORKERS ELECTRICAL & WATER CONSUMPTION PROFESSIONAL FEES, AS-BUILT PLANS GENERAL CLEANING & HAULING SUB-TOTAL

QUANTITY 1 LOT ASSITANCE 1 LOT 1 LOT 1 LOT 1 LOT

UNIT COST (PHP) 10,000.00 ASSITANCE 15,000.00 15,000.00 20,000.00 10,000.00

TOTAL COST(PHP) 10,000.00 ASSITANCE 15,000.00 15,000.00 20,000.00 10,000.00 70,000.00

REMARKS FEES BY THE OWNER

II.

SITE WORK- STRUCTURAL DESCRIPTION


LAYOUT AND STAKING

QUANTITY 1 LOT 1 LOT 1 LOT

UNIT COST (PHP)

TOTAL COST(PHP)

REMARKS

EXCAVATION WORKS BACKFILLING AND COMPACTION SUB-TOTAL

45,000.00

LABOR INCLUDED

III.

CONCRETE WORKS- STRUCTURAL a. FOOTINGS AND COLUMNS

DESCRIPTION BAGS OF CEMENT SAND CU. M. GRAVEL CU. M 10MM DIAMETER REBARS G.I. TIES
SUB-TOTAL

QUANTITY 58 4 7 165 1

UNIT COST (PHP) 220 700.00 800.00 235.00 80.00/KG

TOTAL COST(PHP) 12,760.00 2,800.00 5,600.00 38,775.00 80.00 60,015.00

REMARKS

b. SLABS ON FILL DESCRIPTION BAGS OF CEMENT SAND CU. M. GRAVEL CU. M 10MM DIAMETER REBARS G.I. TIES
SUB-TOTAL

QUANTITY 112 8 15 587 5

UNIT COST (PHP) 220 700.00 800.00 235.00 80.00/KG

TOTAL COST(PHP) 24,640.00 5,600.00 12,000.00 137,945.00 400.00 180,585.00

REMARKS

c. BEAMS AND GIRDERS DESCRIPTION BAGS OF CEMENT SAND CU. M. GRAVEL CU. M 10MM DIAMETER REBARS G.I. TIES
SUB-TOTAL

QUANTITY 550 30 60 1,049 10

UNIT COST (PHP) 220 700.00 800.00 235.00 80.00/KG

TOTAL COST(PHP) 121,000.00 21,000.00 48,000.00 246,515.00 800.00 436,515.00

REMARKS

d. FORMWORKS DESCRIPTION COCO LUMBER 2 X 4 X 12 COCO LUMBER 2 X 3 X 12 ORDINARY PLYWOOD CONCRETE WIRE NAILS
SUB-TOTAL

QUANTITY 480 120 80 40

UNIT COST (PHP) 120 100 540 60.00

TOTAL COST(PHP) 57,600.00 12,000.00 43,200.00 2,400.00 23,980.00

REMARKS

IV.

MASONRY WORKS DESCRIPTION QUANTITY 200 15 UNIT COST (PHP) 220.00 700.00 TOTAL COST(PHP) 44,000.00 10,500.00 54,000.00 REMARKS

BAGS OF CEMENT (PLASTERING) SAND CU. M. (PLASTERING)


SUB-TOTAL

V.

CARPENTRY WORKS a. CIELING DESCRIPTION GYPSUM BOARD FIBER CEMENT BOARD CIELING EAVES CIELING FRAMING METAL ACCESSORIES
SUB-TOTAL

QUANTITY 40 20 40SQM 1 1

UNIT COST (PHP) 350 420 300 25,000.00 5,000.00

TOTAL COST(PHP) 14,000.00 8,400.00 12,000.00 25,000.00 5,000.00 64,400.00

REMARKS

VI.

ROOFING WORKS a. ROOFING ( COLORSTEEL SYSTEMS CORP.) DESCRIPTION QUANTITY 131.10 15 17 4 1,500 1,000 5 UNIT COST (PHP) 473.72 680.80 837.38 2,100.00 0.90 0.35 115 TOTAL COST(PHP) 62,104.69 10,212.00 10,212.00 14,235.46 8,400.00 1,350.00 575.00 97,227.15 REMARKS LABOR/INSTALLATION INCLUDED

CSC SUPREME RIDGE ROLL SPANISH GUTTER STAINLESS SMOKED (VALLEY GUTTER) TEK SCREW 55MM STEEL BLIND RIVETS SILICON SEALANT
SUB-TOTAL

b. ROOF FRAMING DESCRIPTION C- PURLING 2 X 4 C- PURLING 2 X 3 4.5 X 2 X 2 ANGLE BAR 12MM PLAIN ROUND BAR CUTTING BLADE/ WELDING MATERIAL RED LEAD PRIMER/ PAINT
SUB-TOTAL

QUANTITY

UNIT COST (PHP)

TOTAL COST(PHP)

REMARKS LABOR/INSTALLATION INCLUDED

1 SET

20,000.00

20,000.00

20,000.00

VII.

ELECTRICAL WORKS DESCRIPTION QUANTITY 4 2 8 4 25 1 1 22 16 1 SET UNIT COST (PHP) 360.00 380.00 1,200.00 1,100.00 140.00 30.00 2,000.00 900.00 800.00 4,000.00 TOTAL COST(PHP) 1,440.00 760.00 9,600.00 4,400.00 3,500.00 30.00 2,000.00 19,800.00 12,800.00 4,000.00 58,330.00 REMARKS

CONVENIENCE OUTLETS SWITCH OUTLETS DODGEWIRES ROYAL CORD PVC CONDUIT UTILITY BOX PANELBOX CIRCUIT BREAKER FLUORESCENT LIGHTS ELECTRICAL ACCESSORIES
SUB-TOTAL

VIII. PLUMBING WORKS DESCRIPTION FLOOR DRAINS


SUB-TOTAL

QUANTITY 6

UNIT COST (PHP) 450.00

TOTAL COST(PHP) 2,700.00 2,700.00 TOTAL COST (PHP) PER DAY 1,600.00 1,200.00 2,800.00

REMARKS

IX.

LABOR QUANTITY 4 8 WORKER COST (PHP) PER DAY 400.00 300.00 NUMBER OF DAYS 120 120 336,000.00

DESCRIPTION OF WORKER MASON/ CARPENTER LABORER


SUB-TOTAL

SUMMARY GRAND TOTAL DESCRIPTION MATERIALS LABOR SUPRV/MCO TOTAL


NOTE: SUPRV- SUPERVISION MCO- MISCELLENIOUS, CONTIGENCY, OVERHEAD

TOTAL COST(PHP) 1,118,352.00 336,000.00 134,000.00 1,588,352.15

KAREN ANDRES BOB CALUMBA ERL CHRISTIAN ALORA PREPARED BY ARCH. ROSAURO JAMANDRI INSTRUCTOR