WEEK ACTIVITY

07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday Briefing FOB
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
BCI CALENDAR
1/2011/2013
FACULTY OF BUSINESS (BIM, BBM, BOM, BOF, BOHR. DAM, DSIM)
06th August 2012 - 18th November 2012 (15 weeks)
Week 3
Week 4
Week 5
Week 6
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 1
Week 2
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
Week 6
BCI CALENDAR
1/2011/2013
FACULTY OF BUSINESS (BIM, BBM, BOM, BOF, BOHR. DAM, DSIM)
06th August 2012 - 18th November 2012 (15 weeks)
Week 7
Week 8
Week 9
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 10
Week 11
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
Week 1 06-Aug-12 Monday
07-Aug-12 Tuesday
08-Aug-12 Wednesday
09-Aug-12 Thursday
10-Aug-12 Friday
11-Aug-12 Saturday
12-Aug-12 Sunday
Week 2 13-Aug-12 Monday
14-Aug-12 Tuesday
15-Aug-12 Wednesday
16-Aug-12 Thursday
17-Aug-12 Friday
18-Aug-12 Saturday
19-Aug-12 Sunday
22-Oct-12 Monday
23-Oct-12 Tuesday
24-Oct-12 Wednesday
25-Oct-12 Thursday
26-Oct-12 Friday
27-Oct-12 Saturday
28-Oct-12 Sunday
03-Dec-12 Monday
04-Dec-12 Tuesday
05-Dec-12 Wednesday
06-Dec-12 Thursday
07-Dec-12 Friday
08-Dec-12 Saturday
09-Dec-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
Week 12
BEGINNING OF INDUSTRIAL TRAINING
Week 12
AFTER TRAINING
Week 11
FACULTY OF BUSINESS (Accountancy)
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
01/2012/2013
WEEK ACTIVITY
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
06th August 2012 - 03rd February 2012 (06 Months)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 5
Week 6
Week 7
Week 1
Week 2
Week 3
Week 4
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
Week 7
Week 8
FACULTY OF BUSINESS (Accountancy)
06th August 2012 - 03rd February 2012 (06 Months)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 9
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
01/2012/2013
Week 10
Week 11
Week 12
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
Week 1 06-Aug-12 Monday
07-Aug-12 Tuesday
08-Aug-12 Wednesday
09-Aug-12 Thursday
10-Aug-12 Friday
11-Aug-12 Saturday
12-Aug-12 Sunday
Week 2 13-Aug-12 Monday
14-Aug-12 Tuesday
15-Aug-12 Wednesday
16-Aug-12 Thursday
17-Aug-12 Friday
18-Aug-12 Saturday
19-Aug-12 Sunday
14-Jan-13 Monday
15-Jan-13 Tuesday
16-Jan-13 Wednesday
17-Jan-13 Thursday
18-Jan-13 Friday
19-Jan-13 Saturday
20-Jan-13 Sunday
18-Feb-13 Monday
19-Feb-13 Tuesday
20-Feb-13 Wednesday
21-Feb-13 Thursday
22-Feb-13 Friday
23-Feb-13 Saturday
24-Feb-13 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
07-May-12 Monday
Week 24
AFTER TRAINING
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
Week 12
BEGINNING OF INDUSTRIAL TRAINING
Week 1
BCI CALENDAR
1/2012/2013
FASBIO -DIPLOMA BIOTEKNOLOGI
06th August 2012 - 30th Disember 2012 (21weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
Week 1
Week 2
Week 6
Week 7
Week 3
Week 4
Week 5
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
Week 7
Week 8
FASBIO -DIPLOMA BIOTEKNOLOGI
06th August 2012 - 30th Disember 2012 (21weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 9
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
Week 10
Week 11
Week 12
29-Jul-12 Sunday
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
10-Dec-12 Monday
11-Dec-12 Tuesday
12-Dec-12 Wednesday
13-Dec-12 Thursday
14-Dec-12 Friday
15-Dec-12 Saturday
16-Dec-12 Sunday
14-Jan-12 Monday
15-Jan-12 Tuesday
16-Jan-12 Wednesday
17-Jan-12 Thursday
18-Jan-12 Friday
19-Jan-12 Saturday
20-Jan-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 1
FASBIO (ISM BIOTECHNOLOGY, ISM BIOINFORMATICS, ISM MATHEMATIC WITH STATISTIC)
Week 1
Week 2
Week 19
AFTER TRAINING
Week 12
BEGINNING OF INDUSTRIAL TRAINING
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2013
06th August 2012 - 18th November 2012 (15 weeks)
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday Briefing FOB
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
Week 4
Week 5
Week 6
Week 7
Week 8
Week 1
Week 2
Week 3
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
Week 1 06-Aug-12 Monday
07-Aug-12 Tuesday
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
Week 8
Week 9
BCI CALENDAR
1/2011/2013
FASBIO (ISM BIOTECHNOLOGY, ISM BIOINFORMATICS, ISM MATHEMATIC WITH STATISTIC)
06th August 2012 - 18th November 2012 (15 weeks)
Week 12
BEGINNING OF INDUSTRIAL TRAINING
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 10
Week 11
08-Aug-12 Wednesday
09-Aug-12 Thursday
10-Aug-12 Friday
11-Aug-12 Saturday
12-Aug-12 Sunday
Week 2 13-Aug-12 Monday
14-Aug-12 Tuesday
15-Aug-12 Wednesday
16-Aug-12 Thursday
17-Aug-12 Friday
18-Aug-12 Saturday
19-Aug-12 Sunday
22-Oct-12 Monday
23-Oct-12 Tuesday
24-Oct-12 Wednesday
25-Oct-12 Thursday
26-Oct-12 Friday
27-Oct-12 Saturday
28-Oct-12 Sunday
03-Dec-12 Monday
04-Dec-12 Tuesday
05-Dec-12 Wednesday
06-Dec-12 Thursday
07-Dec-12 Friday
08-Dec-12 Saturday
09-Dec-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
Week 12
AFTER TRAINING
FK (DEGREE)
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
Week 1
Week 2
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
Week 5
Week 6
Week 7
Week 8
Week 2
Week 3
Week 4
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
23-Apr-12 Monday
24-Apr-12 Tuesday
25-Apr-12 Wednesday
26-Apr-12 Thursday
27-Apr-12 Friday
28-Apr-12 Saturday
Week 8
FK (DEGREE)
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 9
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
Week 1
Week 10
Week 11
Week 12
BEGINNING OF INDUSTRIAL TRAINING
29-Apr-12 Sunday
30-Apr-12 Monday
01-May-12 Tuesday
02-May-12 Wednesday
03-May-12 Thursday
04-May-12 Friday
05-May-12 Saturday
06-May-12 Sunday
22-Oct-12 Monday
23-Oct-12 Tuesday
24-Oct-12 Wednesday
25-Oct-12 Thursday
26-Oct-12 Friday
27-Oct-12 Saturday
28-Oct-12 Sunday
26-Nov-12 Monday
27-Nov-12 Tuesday
28-Nov-12 Wednesday
29-Nov-12 Thursday
30-Nov-12 Friday
01-Dec-12 Saturday
02-Dec-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
Week 1
Week 2
Week 12
AFTER TRAINING
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
DATE
Week 1
Week 2
BCI CALENDAR
1/2011/2012
FK (DIPLOMA)
06th August 2012 - 28th October 2012 (12 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
Week 2
Week 3
Week 4
Week 5
Week 9
Week 6
Week 7
Week 8
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
30-Apr-12 Monday
01-May-12 Tuesday
02-May-12 Wednesday Praktikal start
03-May-12 Thursday
04-May-12 Friday
05-May-12 Saturday
06-May-12 Sunday
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
Week 9
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2012
Week 10
Week 11
Week 12
BEGINNING OF INDUSTRIAL TRAINING
FK (DIPLOMA)
06th August 2012 - 28th October 2012 (12 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 1
Week 2
10-May-12 Thursday
11-May-12 Friday
12-May-12 Saturday
13-May-12 Sunday
08-Oct-12 Monday
09-Oct-12 Tuesday
10-Oct-12 Wednesday
11-Oct-12 Thursday
12-Oct-12 Friday
13-Oct-12 Saturday
14-Oct-12 Sunday
12-Nov-12 Monday
13-Nov-12 Tuesday
14-Nov-12 Wednesday
15-Nov-12 Thursday
16-Nov-12 Friday
17-Nov-12 Saturday
18-Nov-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
FESS ( PSYCHOLOGY)
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
BCI CALENDAR
1/2012/2013
Week 1
Week 2
Week 3
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
Week 2
Week 10
AFTER TRAINING
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
Week 5
Week 6
Week 7
Week 8
Week 3
Week 4
Week 9
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
23-Apr-12 Monday
24-Apr-12 Tuesday
25-Apr-12 Wednesday
26-Apr-12 Thursday
27-Apr-12 Friday
28-Apr-12 Saturday
29-Apr-12 Sunday
30-Apr-12 Monday
01-May-12 Tuesday
02-May-12 Wednesday
03-May-12 Thursday
04-May-12 Friday
05-May-12 Saturday
06-May-12 Sunday
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
Week 1
Week 2
Week 10
Week 11
Week 12
BEGINNING OF INDUSTRIAL TRAINING
FESS ( PSYCHOLOGY)
22-Oct-12 Monday
23-Oct-12 Tuesday
24-Oct-12 Wednesday
25-Oct-12 Thursday
26-Oct-12 Friday
27-Oct-12 Saturday
28-Oct-12 Sunday
26-Nov-12 Monday
27-Nov-12 Tuesday
28-Nov-12 Wednesday
29-Nov-12 Thursday
30-Nov-12 Friday
01-Dec-12 Saturday
02-Dec-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
Week 12
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
AFTER TRAINING
Week 1
Week 2
Week 3
FSSR (Diploma)
06th August 2012 - 30th September 2012 (8 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
Week 4
Week 9
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
Week 5
Week 6
Week 7
Week 8
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
10-Sep-12 Monday
11-Sep-12 Tuesday
12-Sep-12 Wednesday
13-Sep-12 Thursday
BCI CALENDAR
1/2012/2013
Week 10
Week 11
Week 12
BEGINNING OF INDUSTRIAL TRAINING
FSSR (Diploma)
06th August 2012 - 30th September 2012 (8 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
Week 1
Week 2
Week 6
14-Sep-12 Friday
15-Sep-12 Saturday
16-Sep-12 Sunday
15-Oct-12 Monday
16-Oct-12 Tuesday
17-Oct-12 Wednesday
18-Oct-12 Thursday
19-Oct-12 Friday
20-Oct-12 Saturday
21-Oct-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
WEEK ACTIVITY
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday Meeting LI
12-May-12 Saturday
13-May-12 Sunday
14-May-12 Monday
15-May-12 Tuesday
16-May-12 Wednesday
17-May-12 Thursday
18-May-12 Friday
19-May-12 Saturday
20-May-12 Sunday
21-May-12 Monday
22-May-12 Tuesday
23-May-12 Wednesday
24-May-12 Thursday
25-May-12 Friday
26-May-12 Saturday
27-May-12 Sunday
28-May-12 Monday
29-May-12 Tuesday
30-May-12 Wednesday
31-May-12 Thursday
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2012
Week 6
AFTER TRAINING
Week 1
Week 2
Week 3
Week 4
FSSR (DEGREE DIGITAL GRAPHIC)
06th August 2012 - 28th October 2012 (12 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
DATE
01-Jun-12 Friday
02-Jun-12 Saturday
03-Jun-12 Sunday
04-Jun-12 Monday
05-Jun-12 Tuesday
06-Jun-12 Wednesday
07-Jun-12 Thursday
08-Jun-12 Friday
09-Jun-12 Saturday
10-Jun-12 Sunday
11-Jun-12 Monday
12-Jun-12 Tuesday
13-Jun-12 Wednesday
14-Jun-12 Thursday
15-Jun-12 Friday
16-Jun-12 Saturday
17-Jun-12 Sunday
18-Jun-12 Monday
19-Jun-12 Tuesday
20-Jun-12 Wednesday
21-Jun-12 Thursday
22-Jun-12 Friday
23-Jun-12 Saturday
24-Jun-12 Sunday
25-Jun-12 Monday
26-Jun-12 Tuesday
27-Jun-12 Wednesday
28-Jun-12 Thursday
29-Jun-12 Friday
30-Jun-12 Saturday
01-Jul-12 Sunday
02-Jul-12 Monday
03-Jul-12 Tuesday
04-Jul-12 Wednesday
05-Jul-12 Thursday
06-Jul-12 Friday
07-Jul-12 Saturday
08-Jul-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
Week 4
Week 9
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2012
Week 5
Week 6
Week 7
Week 8
FSSR (DEGREE DIGITAL GRAPHIC)
06th August 2012 - 28th October 2012 (12 weeks)
WEEK ACTIVITY
09-Jul-12 Monday
10-Jul-12 Tuesday
11-Jul-12 Wednesday
12-Jul-12 Thursday
13-Jul-12 Friday
14-Jul-12 Saturday
15-Jul-12 Sunday
16-Jul-12 Monday
17-Jul-12 Tuesday
18-Jul-12 Wednesday
19-Jul-12 Thursday
20-Jul-12 Friday
21-Jul-12 Saturday
22-Jul-12 Sunday
23-Jul-12 Monday
24-Jul-12 Tuesday
25-Jul-12 Wednesday
26-Jul-12 Thursday
27-Jul-12 Friday
28-Jul-12 Saturday
29-Jul-12 Sunday
30-Apr-12 Monday
01-May-12 Tuesday
02-May-12 Wednesday Praktikal start
03-May-12 Thursday
04-May-12 Friday
05-May-12 Saturday
06-May-12 Sunday
07-May-12 Monday
08-May-12 Tuesday
09-May-12 Wednesday
10-May-12 Thursday
11-May-12 Friday
12-May-12 Saturday
13-May-12 Sunday
08-Oct-12 Monday
09-Oct-12 Tuesday
10-Oct-12 Wednesday
11-Oct-12 Thursday
12-Oct-12 Friday
13-Oct-12 Saturday
14-Oct-12 Sunday
12-Nov-12 Monday
Week 10
Week 11
Week 12
BEGINNING OF INDUSTRIAL TRAINING
WEEK BEFORE INDUSTRIAL TRAINING
DATE
week 3
Week 1
Week 2
Week 10
AFTER TRAINING
13-Nov-12 Tuesday
14-Nov-12 Wednesday
15-Nov-12 Thursday
16-Nov-12 Friday
17-Nov-12 Saturday
18-Nov-12 Sunday
** Subject to change
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
week 3
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
BCI CALENDAR
1/2011/2013
FACULTY OF BUSINESS (BIM, BBM, BOM, BOF, BOHR. DAM, DSIM)
06th August 2012 - 18th November 2012 (15 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
BCI CALENDAR
1/2011/2013
FACULTY OF BUSINESS (BIM, BBM, BOM, BOF, BOHR. DAM, DSIM)
06th August 2012 - 18th November 2012 (15 weeks)
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
WEEK BEFORE INDUSTRIAL TRAINING
- Send Application Letter to Organization
- Feedback from Organization
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
- Coordinator to Brief Academic Supervisor
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
BEGINNING OF INDUSTRIAL TRAINING
AFTER TRAINING
FACULTY OF BUSINESS (Accountancy)
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
01/2012/2013
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
06th August 2012 - 03rd February 2012 (06 Months)
WEEK BEFORE INDUSTRIAL TRAINING
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
FACULTY OF BUSINESS (Accountancy)
06th August 2012 - 03rd February 2012 (06 Months)
WEEK BEFORE INDUSTRIAL TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
01/2012/2013
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
- Coordinator to Brief Academic Supervisor
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Information about Industrial Training Program
AFTER TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BEGINNING OF INDUSTRIAL TRAINING
BCI CALENDAR
1/2012/2013
FASBIO -DIPLOMA BIOTEKNOLOGI
06th August 2012 - 30th Disember 2012 (21weeks)
WEEK BEFORE INDUSTRIAL TRAINING
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
FASBIO -DIPLOMA BIOTEKNOLOGI
06th August 2012 - 30th Disember 2012 (21weeks)
WEEK BEFORE INDUSTRIAL TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
- Coordinator to Brief Academic Supervisor
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
WEEK BEFORE INDUSTRIAL TRAINING
FASBIO (ISM BIOTECHNOLOGY, ISM BIOINFORMATICS, ISM MATHEMATIC WITH STATISTIC)
AFTER TRAINING
BEGINNING OF INDUSTRIAL TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2013
06th August 2012 - 18th November 2012 (15 weeks)
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2013
FASBIO (ISM BIOTECHNOLOGY, ISM BIOINFORMATICS, ISM MATHEMATIC WITH STATISTIC)
06th August 2012 - 18th November 2012 (15 weeks)
BEGINNING OF INDUSTRIAL TRAINING
WEEK BEFORE INDUSTRIAL TRAINING
- Coordinator to Brief Academic Supervisor
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
AFTER TRAINING
FK (DEGREE)
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
FK (DEGREE)
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
BEGINNING OF INDUSTRIAL TRAINING
- Coordinator to Brief Academic Supervisor
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
AFTER TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2012
FK (DIPLOMA)
06th August 2012 - 28th October 2012 (12 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
- Coordinator to Brief Academic Supervisor
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2012
BEGINNING OF INDUSTRIAL TRAINING
FK (DIPLOMA)
06th August 2012 - 28th October 2012 (12 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
FESS ( PSYCHOLOGY)
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
BCI CALENDAR
1/2012/2013
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
AFTER TRAINING
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
- Coordinator to Brief Academic Supervisor
06th August 2012 - 11th November 2012 (14 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
BEGINNING OF INDUSTRIAL TRAINING
FESS ( PSYCHOLOGY)
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2012/2013
AFTER TRAINING
FSSR (Diploma)
06th August 2012 - 30th September 2012 (8 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
- Information About Placement Made to Faculties
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
- Coordinator to Brief Academic Supervisor
- Industry Visit by Academic Supervisor
BCI CALENDAR
1/2012/2013
BEGINNING OF INDUSTRIAL TRAINING
FSSR (Diploma)
06th August 2012 - 30th September 2012 (8 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
- Student to Submit Industrial Training Report
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
REMARK - BCI
- Information about Industrial Training Program
-Meeting L.I
- Student Briefing (1st Briefing)
- Identify Total Number of Student for Industrial Training
- Process of Selecting Organization by Student
- Process of Selecting Organization by Student
- Send Application Letter to Organization
- Feedback from Organization
- Information About Placement Made to Faculties
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2012
AFTER TRAINING
FSSR (DEGREE DIGITAL GRAPHIC)
06th August 2012 - 28th October 2012 (12 weeks)
WEEK BEFORE INDUSTRIAL TRAINING
- Student Briefing (2nd Briefing)
- Submit Blue Form (UNISEL/InTra/06/04)
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed
BCI CALENDAR
1/2011/2012
FSSR (DEGREE DIGITAL GRAPHIC)
06th August 2012 - 28th October 2012 (12 weeks)
REMARK - BCI
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Send Application Letter to Organization
- Feedback from Organization
- Submit Report Duty Form (UNiSEL/In-Tra/06/05)
- Selection of Academic Supervisor for Industrial Training
- Coordinator to Brief Academic Supervisor
- Industry Visit by Academic Supervisor
- Student to Submit Industrial Training Report
BEGINNING OF INDUSTRIAL TRAINING
WEEK BEFORE INDUSTRIAL TRAINING
AFTER TRAINING
- Final Evaluation of Industrial Training
Note: When a holiday falls on a weekend, the following day becomes a public holiday (Correct at time of printing)
: Student can Submit the BLUE FORM immediately after industrial placement is confirmed