= Rs 2237.28 / m
3
Wages given to labour is Rs 250 for mason & 200 for unskilled labour.
So, per m
3
labour cost=Rs 9450 for 49 m
3
? for 1 m
3
= Rs 192.86/ m
3
Total cost incurred per m
3
= Rs 2237.28 + 192.86
= Rs 2430.14 / m
3
Now, rate as per BOQ = Rs 4224 / m
3
Hence, (profit +overheads) / m
3
=Rs 1793.86/ m
3
2. Form work
(a) Manpower employed
No of labours for shuttering=12
Time taken for shuttering =8 hours
Area covered
o Area for C=4.691 m
2
o Area for SC=1.119 m
2
46
o Area for CS=0.941 m
2
o Area for 2C=0.92 m
2
o Area for PD=4.675 m
2
o Area for P= 8.46 m
2
o Area for lift shuttering= 37.4 m
2
o Total area = 58.286 m
2
Where C, SC, CS, 2C, PD & P notations are given in drawing of formwork layout.
(b) Productivity
Estimated productivity=0.375 m
2
/labour/hour
Actual productivity= Area covered/ (no of labour time taken)
= 58.286 / (12 m
2
8)
= 0.607 m
3
/labour/hour
(c) Cost aspect
Cost for Peri domino wall panel=Rs 8000/ m
2
o No of repetitions (approx.) = 200 times
So, cost for one time = Rs 40 / m
2
Cost for ply-wood formwork=Rs 590/ m
2
o No of repetitions (approx.) = 30 times
So, cost for one time= Rs 19.67/ m
2
Total material cost per m
2
=Rs 59.67 / m
2
Total labour cost per m
2
= Rs 120 / m
2
So, total shuttering cost= Rs 179.67 / m
2
Rate quoted as per BOQ= Rs 475 / m
2
Hence, (profit +overheads) / m
2
=Rs 295.33 / m
2
(164.37%)
3. Reinforcement laying
(a) Manpower employed
No of labours for reinforcement laying=18
Time taken for reinforcement laying=5 days (12 hours in one day)
(b) Productivity
Estimated productivity= 18.75 kg/labour/hour
Actual productivity=(Total weight of reinforcement)/(No of labours time)
= 21226 kg / (18 60)= 19.65 kg/ labour hour
Where, 21226 kg= quantity of reinforcement in raft calculated in BBS= 4888 kg (shear
wall reinf.) + 16338 kg (raft reinf.)
(c) Cost aspect
Material cost = Rs 43 / kg
Labour cost= Rs 3.5 / kg
Total cost= Rs 46.5 / kg
47
Rate quoted in BOQ= Rs 60.645 / kg
Hence, (profit +overheads) / kg= Rs 14.145 / kg (30.41%)
4. Concrete work
(a) Manpower employed
No. of labour for concrete work=14 (4 masons + 10 labours)
Time taken for concrete work= 20 hours
1 supervisor and 1 site engineer was on site during the time of concreting.
(b) Productivity
Productivity of concrete work estimated is based on productivity of concrete pump.
Estimated productivity= 30 m
3
/hour
Actual productivity = Total volume of concreting actually consume/ time
= 478.95 m
3
/ 20 hours=23.947 m
3
/hour
(c) Cost aspect
Volume of concreting estimated as per plan dimensions and thickness of raft which was
750 mm is as below,
o Total volume of concreting
=418.07 m
3
(volume of whole rectangle) + 9.4 m
3
(volume of slope corner) + 31.54 m
3
(volume of lift pit) 6.67 m
3
(Volume of hollow lift gap)
=470.95 m
3
Proportion of mix design for concrete was:
[1(cement):1.787(FA):2.324(CA):0.3255(water):0.321(GGBS)]
Material in one m
3
o Cement=265 kg/ m
3
o GGBS=85 kg/ m
3
o FA= 826 kg/ m
3
o CA=1074.5 kg/ m
3
o Water=150.5 kg/ m
3
o Admixture=1.575 litres
Cost of material per m
3
= 2655.2 + 853.128 + 8260.67 + 644.70.6 +429.80.53 +
1.57554 = Rs 2896.96 / m
3
Labour cost / m
3
=Rs 15.65
Total cost incurred=Rs 2912.61/ m
3
Rate quoted in BOQ=Rs 5456/ m
3
Hence, (profit +overheads) in Rs / m
3
=2543.12/ m
3
(87.31%)
5. Anti-termite treatment
Material used=BIFLEX TC
Coverage=3 litres/ m
2
Proportion is 1 time chemical with 49 times water
48
o So, in 3 litres, quantity of chemical= 0.06 litres
o And, spray of chemical per m
2
=0.06 litres
Now, cost of chemical per m
2
=Rs 30
Rate quoted in BOQ per m
2
=Rs 52
Hence, (profit+overheads) per m
2
=Rs 22 (73.33%)
Table 2.1.23 TOTAL COST FOR RAFT
Sr. no Activity Price as per BOQ(Rs) Cost incurred (Rs)
Profit
overheads(Rs)
1 PCC 4224 75.6=3,19,3334 2430.1449=1,19,077 2,00,257.4
2 Formwork 47558.936=28,007.43 141.5550.535=7153 20,854.43
3 Reinforcement 60.64521226=12,84,250 46.521226=9,87,009 3,00,241
4
Concrete
works-M30
5456474.7=25,89,963 2912.61478.95=13,94,994 11,35,998
5
Anti-termite
treatment
53554.43=29,543 30557.43=16,772 12821
6 Total 42,54,097.43 25,25,005
17, 29,092.43
(68.48%)
Formwork area(considered by client) = 0.3m depth (38.31m + 33.565m)
= 21.563 m
2
(non-lift area)
o Lift area = (8.5m 2) (2.2m height)= 37.4 m
2
o Total area= 58.936 m
2
2.2.8 INSPECTION AND QUALITY CHECKS
Inspection and quality checks for any construction activity involves filling up of
CHECKLIST which covers following points.
1. Checks for surveying work for raft
Checking of co-ordinates of raft corners and shear walls corners by surveyor from client
side.
They check that the points located by SPCL surveyor is correct or not.
Tolerance of 1mm in horizontal direction is allowed.
2. Checklist for reinforcement
Checklist for form work.
Test conducted on received material & report.
Structural drawing checked & last revision being used.
Bar bending schedule prepared & bar bending and cutting is done satisfactorily.
Bar sizes, spacing, grades, shapes & lengths as per drawing.
Adequate laps
49
Chairs/cover blocks placed
Binding wire not touching shuttering and proper binding
Dowels & positioning as per drawings.
Joggling is avoided and if it is to be done then it should not be more than 1 in 6.
3. Checklist for shuttering
Are all the safety norms being covered as per HSEM (health & safety executive minute)
process?
Check for shuttering for availability and arrangement.
Are all plates and ply-woods cleaned and polished properly.
Type of oil/polish used on the surface of shuttering.
Check for suitability, stability, safety and rigidity of assembled forms
Check for provisions for service piping.
Vertical member-Shear walls
Checking alignment of all vertical members at floor level with respect to grid lines.
Check plumb for vertical members (minimum 2 sides).
Check right angles and diagonals of the vertical members from the top.
Check for alignment with respect to adjacent vertical members.
Check for adequate support as per shuttering design.
Check for adequacy of cover blocks.
4. Checklist prior to concreting
All the safety norms being covered as per HSEM process?
Check whether the concrete is as per approved mix design.
Check for formwork, reinforcement and cleanliness of the area to be concreted, is it OK?
Check for completion of preceding activities such as fixing of inserts and embedment.
Check for completion of preceding activities such as fixing of services conduits, electrical
conduits etc.
Check whether the location of expansion joints are as per drawings?
Is the sequence of concreting decided and explained to all concerned?
Check for readiness of electrical equipment during concreting.
Are protective covers against rain provided?
Check whether sufficient material and manpower are available?
Check the availability of sufficient no. of cube modules, slumps quality apparatus?
Are the reference levels transferred from TBM marked?
Mode of concreting proposed (mixer machine, Batching plant)
Grade of concrete
Total quantity of concrete
Date & time of concreting
50
5. Checking during concreting
Check for slump.
Check for temperature of concrete in case of temperature controlled concrete.
Check for placing methodology of concrete. Is it OK?
Is concrete being consumed within the initial setting period of concrete?
Check for provision of construction joints as per drawings?
Check for levelling and finishing of exposed concrete surface for planner structures like
slabs/rafts & pavements.
6. Check list after concreting
Check for suitable curing arrangements.
Check for casting date is marked on the structural element.
Check whether inserts which are embedded with concrete surface are exposed properly.
Check for alignment of construction joints, if any.
Is the line/level of concrete surface is OK?
Check for defects on exposed concrete
o Honey combing
o Dimension variance
o Bulging
o Exposed reinforcement
o Damaged edges and corners