1- EARTH FILLING:-

Description 1st Layer 2nd Layer 3rd Layer 4th Layer 5th Layer
Plot No-1
completed (completed means
compaction test results satisfied)
completed (completed means
compaction test results
satisfied)
compaction is In Progress (
ACHIEVED LEVEL WILL BE
100.350 m)
- -
Plot No-2 Completed
2nd layer Dressing &
Compaction Preparation for
Tests is in Progress.(ACHIEVED
LEVEL WILL BE 100.350 m)
- -
Plot No-3 Completed
2nd layer dressing and
compaction in
progress.(ACHIEVED LEVEL WILL
BE 100.350 m)
- -
Pre Mix Bitumen Carpet Road
(1.)1st layer completed from
00+460 to 00+360m RD. (2) .And
1st layer from 00 to 00+40 is also
completed.
(1). 2nd layer completed from
00+460 to 00+340 RD.
(2). Earthfilling of 2nd layer
continue from 00 to 00+40 RD.
(1).Third layer from oo+460 to
00+340 RD is Completed.
(1). 4th layer from s/y gate
towards culvert (from
00+460 to 00+400 RD)
completed.
(2). 2nd layer completed
from 00 to 00+50 RD
(1). 5th layer of earthfilling is
in progress from 00+460 to
00+400 RD. (2).
3rd layer of earthfilling ready
for testing from 00 to 00+50
RD
DESCRIPTION SITE OFFICE Staff Residence
Lab,Mechenical, Cement
Stores
EXCAVATION completed completed completed
LEAN completed completed completed
SUBSTRUCTURE BRICK WORK completed completed completed
DPC completed completed completed
SUPERSTRUCTURE BRICK WORK completed completed completed
ROOF TREATMENT (11-8-12) 85% completed completed completed
electric (wiring work) 85% completed 85% completed 80% completed
sanitary work 85% completed
PLASTERING WORK (External
Wall)
All wall completed
PLASTERING WORK (INTERNAL
WALL)
all wall completed
Flooring topping( 1:2:4) is completed.
Parking Shed (10-08-12)
column plastering work is in
progress
AL-HUSSAIN CONTRACTORS
site office chishtiian
2.Brick work of 2nd septic tank is in progress.
1:plastering work of septic tank is in progress.
220KV SUB STATION CHISHTIAN
DAILY PROGRESS REPORT
DATE:- 11/08/2012
2-CONSTRUCTION WORK
MISCELLANEOUS ACTIVITY:
3.labour bath room brick work is in progress.
NOTE: TODAY THERE IS A HEAVY RAIN.