Project Work Schedule

A. General Information

Project Title: Facilitating Culiat High School students in learning MS Word , AdobePrepared By: Izrael Zenar C. Bautista
Photoshop and Movie Maker Gerald Allan Perez
Date Prepared: 18-Oct-09 Version: 2

B. Project Schedule
These are the key elements of your project that must be completed on-time and on-budget for your project to be successful and therefore require monitoring by the project
manager and stakeholders. The status of these items should be reported in your Project Status Report.

The element column below demonstrates the pattern to report milestones, tasks, and activities, i.e., a milestone is achieved by a series of tasks and each task is achieved by a
series of activities. A deliverable, or group of deliverables, should be given for each milestone. Overwrite the example given with the milestones, tasks, and activities for this
project.

Element Description Deliverable Assigned To Required Hours Due Date Dependencies


milestone 1 Initiation of Project
task 1 talk with the sponsor about the project Project Charter/Sponsor Interview Izrael Zenar C. Bautista 4 hours Sept 7. Sponsor and stakeholder
activity 1 Make the Project Charter Izrael Zenar C. Bautista 3 hours Sept 7. Project charter
activity 2 Revise Project charter Izrael Zenar C. Bautista 4 hours Sept 14. Sponsor and stakeholder
task 2 Checking/repairing of computers installation software Whole group 3 hours Nov 7. Computers
activity 1 Fixing of computers Whole group 3 hours Nov 7. Computers
activity 2 Installing Adobe PS/MM trial software installation software Whole group 2 hours Nov 7. Software and computers
milestone 2 Start of Project
task 1 teaching of Adobe PS/MM/MS Word lectures Whole group at least 3 hours per week
Mar 15 2010Students
activity 1 preparation of lectures Whole group 5 hours Nov 7. lectures
activity 2 official start of teaching lectures Whole group 3 hours per week Mar 15 2010
task 2 testing students comprehension exam paper Whole group 6 hours Feb 22. exam paper
activity 1 first exam exam paper Whole group 3 hours Jan 11. exam paper
activity 2 second exam exam paper Whole group 3 hours Feb 22. exam paper

Project_Work_Schedule_Excel.xls rev. 4/4/2008 Page 1 of 11