1
2
Task Name
Duration
6
7
SETTING OUT
8
9
EXCAVATION SUBSTRUCTURE
10
11
CONCRETE BLINDING
Start
Finish
Predecessors
608 days
Fri 15/03/13
Tue 14/07/15
178 days
Mon 31/03/14
Wed 03/12/14
14 days
Mon 31/03/14
Thu 17/04/14
174 days
Fri 04/04/14
Wed 03/12/14
8 days
Fri 04/04/14
Tue 15/04/14
10 days
Wed 16/04/14
Tue 29/04/14
5 days
Wed 30/04/14
Tue 06/05/14
February
Feb
March
Mar
April
May
Apr
31/03
June
May
July
Jun
August
Aug
Jul
September
Sep
October
Oct
November
Nov
December
Dec
17/04
04/04
15/04
16/04
29/04
30/04
06/05
12
13
FORMWORK BEAMS
10 days
Wed 07/05/14
Tue 20/05/14
11
14
15
07/05
20/05
REINFORCEMENT BEAMS
10 days
Wed 21/05/14
Tue 03/06/14
13
16
17
ELECTRICAL SLEEVES
5 days
Mon 26/05/14
Fri 30/05/14
26/05
30/05
18
19
MECHANICAL SLEEVES
5 days
Mon 26/05/14
Fri 30/05/14
26/05
30/05
21
7 days
Tue 25/11/14
Wed 03/12/14
22
23
5 days
Thu 30/10/14
Wed 05/11/14
24
25
5 days
Wed 04/06/14
Tue 10/06/14
15
26
27
FILLINGS
5 days
Wed 11/06/14
Tue 17/06/14
25
10 days
Wed 18/06/14
Tue 01/07/14
27
5 days
Wed 02/07/14
Tue 08/07/14
29
110 days
Wed 09/07/14
Tue 09/12/14
15 days
Wed 09/07/14
Tue 29/07/14
21/05
03/06
20
25/11
30/10
04/06
03/12
05/11
10/06
11/06
17/06
28
29
30
31
32
33
34
MILESTONE-2
COLUMNS TO FIRST FLOOR
35
36
4 days
Wed 09/07/14
Mon 14/07/14
31
37
38
4 days
Tue 15/07/14
Fri 18/07/14
36
39
40
CASTING OF COLUMNS
7 days
Mon 21/07/14
Tue 29/07/14
38
18/06
01/07
02/07
08/07
09/07
14/07
15/07
18/07
21/07
29/07
41
42
97 days
Wed 23/07/14
Thu 04/12/14
43
44
14 days
Wed 23/07/14
Mon 11/08/14
45
46
7 days
Wed 06/08/14
Thu 14/08/14
40FS+5 days
06/08
47
48
5 days
Wed 06/08/14
Tue 12/08/14
40FS+5 days
06/08
49
50
10 days
Tue 12/08/14
Mon 25/08/14
44
51
52
10 days
Mon 20/10/14
Fri 31/10/14
50
53
54
15 days
Wed 12/11/14
Tue 02/12/14
52FS+7 days
12/11
55
56
17 days
Wed 12/11/14
Thu 04/12/14
52FS+7 days
12/11
12 days
Tue 12/08/14
Wed 27/08/14
57
58
59
60
5 days
Tue 12/08/14
Mon 18/08/14 44
61
62
5 days
Tue 19/08/14
Mon 25/08/14 60
63
64
CASTING OF STAIRCASE
2 days
Tue 26/08/14
Wed 27/08/14 62
32 days
Mon 27/10/14
Tue 09/12/14
65
66
SWIMMING POOL
23/07
36FS+6 days
67
68
EXCAVATION
3 days
Mon 27/10/14
Wed 29/10/14
69
70
CONCRETE BLINDING
4 days
Thu 30/10/14
Tue 04/11/14
68
71
72
FORMWORK
10 days
Wed 05/11/14
Tue 18/11/14
70
73
74
REINFORCEMENT
13 days
Wed 19/11/14
Fri 05/12/14
72
75
76
7 days
Thu 27/11/14
Fri 05/12/14
72FS+6 days
11/08
14/08
12/08
12/08
25/08
20/10
12/08
02/12
04/12
18/08
19/08
26/08
25/08
27/08
27/10
30/10
29/10
04/11
05/11
18/11
19/11
27/11
77
Project: MSProj11
Date: Wed 09/04/14
31/10
Task
Milestone
Rolled Up Task
Rolled Up Progress
External Tasks
Group By Summary
Progress
Summary
Rolled Up Milestone
Split
Project Summary
Deadline
Page 1
05/12
05/12
January
Jan
February
Feb
March
Mar
April
May
Apr
June
May
July
Jun
Jul
August
Aug
ID
Task Name
Duration
Start
Finish
78
5 days
Thu 27/11/14
Wed 03/12/14
79
80
CONCRETE WORK
4 days
Thu 04/12/14
Tue 09/12/14
70 days
Tue 26/08/14
Mon 01/12/14
15 days
Tue 26/08/14
Mon 15/09/14
Tue 26/08/14
81
82
83
84
MILESTONE-3
COLUMNS TO SECOND FLOOR
Predecessors
4 days
87
88
4 days
89
90
CASTING OF COLUMNS
7 days
July
Jun
Jul
August
Aug
September
Sep
October
Oct
November
Nov
27/11
26/08
Fri 29/08/14 50
01/09
05/09
22/09
5 days
Mon 22/09/14
22/09
9 days
Mon 06/10/14
10 days
Fri 17/10/14
20 days
Fri 31/10/14
31/10
22 days
Fri 31/10/14
31/10
10 days
Mon 06/10/14
105
106
May
Apr
09/12
01/10
26/09
16/10
17/10
30/10
27/11
01/12
Fri 17/10/14
3 days
Mon 06/10/14
Wed 08/10/14 94
3 days
Thu 09/10/14
113
114
CASTING OF STAIRCASE
4 days
Tue 14/10/14
142 days
Fri 17/10/14
Mon 04/05/15
28 days
Fri 17/10/14
Tue 25/11/14
8 days
Fri 17/10/14
Tue 28/10/14
100
119
120
121
122
10 days
Wed 29/10/14
Tue 11/11/14
120
123
124
CASTING OF COLUMNS
10 days
Wed 12/11/14
Tue 25/11/14
122
124 days
Thu 23/10/14
Tue 14/04/15
13 days
Wed 26/11/14
Fri 12/12/14
124
128
06/10
08/10
09/10
13/10
14/10
17/10
17/10
28/10
29/10
11/11
12/11
25/11
127
128
129
130
8 days
Mon 15/12/14
Wed 24/12/14
131
132
20 days
Thu 25/12/14
133
134
15 days
Mon 26/01/15
18 days
Wed 26/11/14
138
15 days
Mon 26/01/15
139
140
20 days
Mon 16/02/15
142
9 days
Thu 23/10/14
Tue 04/11/14
143
144
7 days
Wed 04/03/15
Thu 12/03/15
145
146
4 days
Fri 16/01/15
Wed 21/01/15
128
16/01
147
148
7 days
Fri 16/01/15
Mon 26/01/15
128
16/01
149
150
5 days
Mon 19/01/15
Fri 23/01/15
3 days
Mon 16/02/15
Wed 18/02/15
26/11
12/12
15/12
24/12
25/12
21/01
26/01
13/02
26/01
13/02
135
136
26/11
19/12
137
16/02
13/03
141
23/10
04/11
04/03
19/01
130FS+5 days
12/03
21/01
26/01
23/01
151
152
16/02
138
18/02
153
154
CASTING OF FASCIA
10 days
Mon 16/03/15
155
156
16/03
20 days
Fri 13/03/15
Thu 09/04/15
144
13/03
157
158
23 days
Fri 13/03/15
Tue 14/04/15
144
13/03
159
Project: MSProj11
Date: Wed 09/04/14
Task
Milestone
Rolled Up Task
Rolled Up Progress
External Tasks
Group By Summary
Progress
Summary
Rolled Up Milestone
Split
Project Summary
Deadline
Page 2
June
May
03/10
06/10
Thu 16/10/14 94
16/09
Fri 03/10/14 90
111
112
April
Mon 01/12/14
109
110
MILESTONE-4
March
Mar
15/09
Mon 22/09/14
103
104
February
Feb
04/09
8 days
101
102
January
Jan
29/08
99
100
December
Dec
03/12
04/12
Tue 16/09/14
97
98
125
126
June
May
14 days
117
118
May
Apr
Tue 16/09/14
95
96
115
116
April
55 days
93
94
107
108
March
Mar
78
85
86
91
92
February
Feb
72FS+6 days
27/03
09/04
14/04
July
Jun
Jul
August
Aug
ID
Task Name
160
Duration
Start
Finish
12 days
Mon 02/02/15
Tue 17/02/15
Predecessors
161
162
3 days
Mon 02/02/15
Wed 04/02/15
163
164
3 days
Thu 05/02/15
165
166
CASTING OF STAIRCASE
6 days
Tue 10/02/15
51 days
Mon 23/02/15
Mon 04/05/15
10 days
Mon 23/02/15
Fri 06/03/15
120
167
168
February
Feb
March
Mar
April
May
Apr
June
May
July
Jun
Jul
August
Aug
September
Sep
October
Oct
November
Nov
December
Dec
January
Jan
February
Feb
02/02
March
Mar
April
May
Apr
June
May
04/02
05/02
09/02
10/02
17/02
169
170
EXCAVATION
171
172
CONCRETE BLINDING
4 days
Mon 09/03/15
Thu 12/03/15
170
173
174
FORMWORK
6 days
Fri 13/03/15
Fri 20/03/15
172
175
176
REINFORCEMENT
10 days
Mon 23/03/15
Fri 03/04/15
174
177
178
CONCRETE WORK
3 days
Mon 06/04/15
Wed 08/04/15
176
179
180
11 days
Mon 20/04/15
Mon 04/05/15
513 days
Fri 15/03/13
Tue 03/03/15
181
182
MILESTONE-5
23/02
06/03
09/03
12/03
13/03
20/03
23/03
03/04
06/04
08/04
20/04
183
184
17 days
Mon 26/01/15
185
186
10 days
Wed 18/02/15
187
188
10 days
Mon 03/11/14
Fri 14/11/14 52
189
190
10 days
Fri 31/10/14
191
192
10 days
Fri 14/11/14
193
194
10 days
Fri 15/03/13
Thu 28/03/13
287 days
Tue 15/04/14
Wed 20/05/15
26/01
03/11
04/05
17/02
18/02
03/03
14/11
31/10
13/11
14/11
27/11
195
196
UTILITY BUILDING
197
198
EXCAVATION
5 days
Mon 23/02/15
Fri 27/02/15
199
200
FORMWORK
5 days
Mon 02/03/15
Fri 06/03/15
198
201
202
2 days
Fri 03/04/15
Mon 06/04/15
200
203
204
2 days
Mon 09/03/15
Tue 10/03/15
200
205
206
REINFORCEMENT
5 days
Wed 11/03/15
Tue 17/03/15
200FS+2 days
207
208
4 days
Wed 18/03/15
Mon 23/03/15
209
210
8 days
Tue 24/03/15
Thu 02/04/15
208
211
212
6 days
Fri 03/04/15
Fri 10/04/15
210
214
CASTING OF COLUMNS
5 days
Mon 13/04/15
Fri 17/04/15
212
13/04
17/04
215
216
5 days
Mon 13/04/15
Fri 17/04/15
212
13/04
17/04
217
218
BLOCKWORK
9 days
Mon 04/05/15
Thu 14/05/15
219
220
4 days
Wed 14/01/15
Mon 19/01/15
221
222
4 days
Fri 15/05/15
Wed 20/05/15
223
224
PLASTERING
10 days
Tue 15/04/14
Mon 28/04/14
5 days
Tue 29/04/14
Mon 05/05/14
306 days
60 days
Mon 05/05/14
Fri 24/10/14
Mon 06/07/15
Thu 15/01/15
23/02
27/02
02/03
06/03
03/04
09/03
206
06/04
10/03
11/03
17/03
18/03
23/03
24/03
02/04
03/04
10/04
213
208FS+2 days
04/05
14/01
14/05
19/01
218
15/05
15/04
20/05
28/04
225
226
227
228
229
50 days
Thu 22/01/15
232
233
55 days
Mon 09/03/15
234
235
80 days
Mon 19/01/15
Fri 08/05/15
236
237
103 days
Mon 12/01/15
Wed 03/06/15
10 days
Mon 09/03/15
Fri 20/03/15
5 days
Mon 23/03/15
Fri 27/03/15
EXCAVATION
240
241
CONCRETE BLINDING
05/05
24/10
230
231
238
239
29/04
224
01/04
09/03
192FS+10 days
22/05
19/01
08/05
09/03
239
20/03
23/03
242
Project: MSProj11
Date: Wed 09/04/14
15/01
22/01
Task
Milestone
Rolled Up Task
Rolled Up Progress
External Tasks
Group By Summary
Progress
Summary
Rolled Up Milestone
Split
Project Summary
Deadline
Page 3
27/03
July
Jun
Jul
August
Aug
ID
Task Name
Duration
Start
Finish
Predecessors
243
FORMWORK
12 days
Mon 30/03/15
Tue 14/04/15
241
244
245
REINFORCEMENT
15 days
Wed 15/04/15
Tue 05/05/15
243
246
247
CONCRETE WORK
6 days
Wed 06/05/15
Wed 13/05/15
245
248
249
20 days
Mon 12/01/15
Fri 06/02/15
250
251
15 days
Thu 14/05/15
306 days
Mon 05/05/14
Mon 06/07/15
252
253
February
Feb
March
Mar
April
May
Apr
June
May
July
Jun
Jul
August
Aug
September
Sep
October
Oct
November
Nov
December
Dec
January
Jan
February
Feb
March
Mar
30/03
April
May
Apr
15/04
6 days
Mon 23/03/15
Mon 30/03/15
CONCRETE BLINDING
4 days
Tue 31/03/15
Fri 03/04/15
255
259
FORMWORK
8 days
Mon 06/04/15
Wed 15/04/15
257
260
261
REINFORCEMENT
7 days
Thu 16/04/15
Fri 24/04/15
259
262
263
7 days
Mon 27/04/15
Tue 05/05/15
261
264
265
BLOCKWORKS
9 days
Wed 06/05/15
Mon 18/05/15
266
267
DRAINAGE EXCAVATION
12 days
Mon 04/05/15
Tue 19/05/15
4 days
Wed 20/05/15
Mon 25/05/15
267
10 days
Tue 26/05/15
Mon 08/06/15
269
August
Aug
Jul
13/05
06/02
14/05
256
257
July
Jun
05/05
06/05
12/01
254
255
June
May
14/04
23/03
03/06
30/03
31/03
03/04
258
06/04
15/04
16/04
24/04
27/04
263
05/05
06/05
18/05
04/05
19/05
268
269
CONCRETE BLINDING(DRAINAGE)
270
271
FORMWORK
272
273
REINFORCEMENT
8 days
Tue 09/06/15
Thu 18/06/15
271
274
275
CONCRETE WORK(DRAINAGE)
7 days
Fri 19/06/15
Mon 29/06/15
273
276
277
MANHOLES
30 days
Mon 05/05/14
Fri 13/06/14
278
279
9 days
Mon 09/06/14
Thu 19/06/14
280
281
30 days
Tue 26/05/15
Mon 06/07/15
282
283
LANDSCAPING
68 days
Wed 01/04/15
Fri 03/07/15
284
285
20 days
Mon 27/04/15
Fri 22/05/15
286
287
20 days
Mon 20/04/15
Fri 15/05/15
127 days
Mon 19/01/15
Tue 14/07/15
46 days
Mon 19/01/15
Mon 23/03/15
288
289
290
MILESTONE-7
SWIMMING POOL & POOL DECK
20/05
25/05
26/05
08/06
09/06
18/06
19/06
05/05
29/06
13/06
09/06
19/06
269
26/05
06/07
01/04
03/07
27/04
20/04
291
292
FINISHINGS
30 days
Mon 19/01/15
Fri 27/02/15
293
294
15 days
Mon 02/03/15
Fri 20/03/15
02/03
295
296
16 days
Mon 02/03/15
Mon 23/03/15
02/03
19/01
22/05
15/05
27/02
20/03
23/03
297
298
40 days
Mon 20/04/15
Fri 12/06/15
299
300
55 days
Mon 06/04/15
Fri 19/06/15
301
302
10 days
Mon 22/06/15
22/06
303
304
15 days
Mon 22/06/15
22/06
305
306
55 days
Mon 27/04/15
HANDOVER TO CLIENT
2 days
Mon 13/07/15
20/04
12/06
06/04
19/06
03/07
10/07
27/04
Fri 10/07/15
10/07
307
308
Project: MSProj11
Date: Wed 09/04/14
13/07
Task
Milestone
Rolled Up Task
Rolled Up Progress
External Tasks
Group By Summary
Progress
Summary
Rolled Up Milestone
Split
Project Summary
Deadline
Page 4
14/07