25801271 DALHOUSIE UNIVERSITY

HIGH VOLTAGE SWITCHING PROCEDURE

DATE: December 18, 2009 Est Start Time: 23:30/ Dec 18th

LOCATION: Arena Electrical Vault, & Killam Vault (Meet in Arena


Est Finish Time: 03:00/ Dec 19th
lobby at [22:30], [December 18, 2009])
PURPOSE: Maintenance of the Arena magna blast breaker at Killam Vault.

PERFORMED INITIAL
STEP PROCEDURE TIME
BY S
Arena Electrical Vault - Notify Security (6400); Thermal Plant
1 control room Operators (2435); UCIS Help Desk (2662) that switching Dal
procedure to isolate equipment is starting.
Arena Electrical Vault - Ensure all personnel are standing clear of
2 Dal
all electrical gear before beginning the switching procedure.
Killam Vault - Open and rack down 1200A draw-out type breaker,
feeding the "Arena (Rink)". Ensure all control circuits are de-
3 energized and that the breaker is removed out from the switchiboard Dal/Siemens
unit. This will de-energize the Memorial Arena, Wickwire Field, and
Studley Gym. Lock/ Tag out door.
Arena Electrical Vault - Open 600A Disconnect Switch and verify no
4 voltage is present on the 4.16kV main bus. Apply grounds (See Dal/Siemens
attached diagram)
Killam Vault/Arena Electrical Vault - Work may now begin at the
Killam Vault and Arena Vault simultaneously with two crews to
perform the following: 1- The maintenance of the magna blast
5 Siemens
breaker that feeds the Arena located in Killam Vault, and 2- The
maintenance of the 4.16kV 600A (100E) Switch and the 750kVA
4.16kV-600/347VTransformer located at Arena Electrical Vault.

Killam Vault - Make sure that all tools and equipment have been
6 Dal/Siemens
removed from the cabinets.
Arena Electrical Vault - Remove ground from the 4.16kV main bus
7 and close the 600A Disconnect Switch. Ensure all cabinets are shut Dal
and locked, and that there are no exposed connections.
Killam Vault - Close and rack up the 1200A draw-out type breaker,
feeding the "Arena (Rink)". This will energize the Memorial Arena,
8 Dal
Wickwire Field, and Studley Gym.Visually confirm the breaker is
closed.
Arena Electrical Vault - Notify Security (6400); Thermal Plant
9 control room Operators (2435); UCIS Help Desk (2662) that switching Dal
procedure is complete and all building loads are back to normal.

PROCEDURE REVIEWED BY
SIGNATURES: DATE: REPRESENTING:

///

1
25801271 DALHOUSIE UNIVERSITY
HIGH VOLTAGE SWITCHING PROCEDURE

///

///

///