Risk No.

Related Risk
No.
RISK Timeframe Start
1 4 If contract is not awarded before the 30th of
September, then Enersense will loose 1m of
in expiring funds.
20 May 2011
Timeframe End I Po (%) Probablility
of occurence
R (High
/Medium/Low)
30 Sep 2011 70% H
Manage/Mitigate
Use existing task oder contract too
assure award before 30 Sept