PROJECT : PUB’S “PEDESTRIAN BRIDGE ACROSS SUNGEI DATE OF ATTACHMENT : 17 DEC 2009
SERANGOON LORONG HALUS WETLANDS”. (TEST PULL STUBS/DOLLIES)
OWNER’S CONSULTANT : CPG CONSULANTS PTE LTD DURATION OF LAST COAT : > 14 Days
MAIN CONTRACTOR : WAN SHENG HAO CONSTRUCTION PTE LTD (DRY TIME)
APPLICATOR : EASTERN BLASTING & COATING PTE LTD DATE OF TEST : 18 DEC 2009
SPECIFICATION REF : TOTAL Paint Specification.
TYPE OF ADHESIVE USED : ARALDITE 2-PACK EPOXY GLUE.