Start: 10/15/14
ID: 1
Finish: 6/25/15
Comp: 0%
PreConstructionStage
Start:Oct15'1Finish:Jan1'15
Duration:57dWBS:1.1
ResourceNames:ProjectEngineer
PreDesignPhase
Start:Oct15'1Finish:Nov6'14
Duration:17daWBS:1.1.1
ResourceNames:ProjectEngineer
InitiateProjectPlanning
Start:Oct15'1Finish:Oct15'14
Duration:1dayWBS:1.1.1.1
ResourceNames:ProjectEngineer
ConductPublicConsultation
Start:Oct16'1Finish:Oct16'14
Duration:1daWBS:1.1.1.2
ResourceNames:ProjectEngineer
FinalizeProjectCharter
Start:Oct17'1Finish:Oct17'14
Duration:1dayWBS:1.1.1.3
ResourceNames:
Surveyselectedsites
Start:Oct20'1Finish:Oct31'14
Duration:10dWBS:1.1.1.4
ResourceNames:SurveyCrew
FinalizeFeasibilityAnalysisReport
Start:Nov3'14Finish:Nov4'14
Duration:2dayWBS:1.1.1.8
ResourceNames:
Obtainlandrights
Start:Nov5'14Finish:Nov5'14
Duration:1dayWBS:1.1.1.9
ResourceNames:
FormalizePowerPurchaseagreement
Start:Nov6'14Finish:Nov6'14
Duration:1daWBS:1.1.1.10
ResourceNames:
ConductEnvironmentAssessment
Start:Oct20'1Finish:Oct31'14
Duration:10dWBS:1.1.1.5
ResourceNames:EnvironmentalCrew
ConductGeotechnicalAssessment
Start:Oct20'1Finish:Oct31'14
Duration:10dWBS:1.1.1.6
ResourceNames:GeotechnicalCrew
Assessthesiteswindenergypotential
Start:Oct20'1Finish:Oct31'14
Duration:10dWBS:1.1.1.7
ResourceNames:ProjectEngineer,Technol
DesignPhase
Start:Nov7'14Finish:Nov28'14
Duration:16daWBS:1.1.2
ResourceNames:DesignEngineer,ProjectE
Reviewfoundationrequirements
Start:Nov7'14Finish:Nov13'14
Duration:5dayWBS:1.1.2.1
ResourceNames:DesignEngineer,ProjectE
Reviewspecificationsanddrawingsoftu
Start:11/7/14
ID:16
Finish:11/13/14
Dur:5days
Res:DesignEngineer,ProjectEngineer,
Reviewgeneratorandtransmitterspecif
Start:11/7/14
ID:17
Finish:11/13/14
Dur:5days
Res:DesignEngineer,ProjectEngineer,
Designcivilengineeringinfrastructure
Start:11/14/14
ID:18
Finish:11/27/14
Dur:10days
Res:DesignEngineer,ProjectEngineer,
FinalizeTenderprocurementdocuments
Start:Nov28'1Finish:Nov28'14
Duration:1dayWBS:1.1.2.6
ResourceNames:
Designmechanicalandelectricalsystem
Start:11/14/14
ID:19
Finish:11/27/14
Dur:10days
Res:DesignEngineer,ProjectEngineer,
Bidding Phase
Start: 12/1/14
ID: 21
Finish: 1/1/15
Dur: 24 days
Comp: 0%
ConstructionStage
Start:Jan2'15Finish:May25'15
Duration:102dWBS:1.2
ResourceNames:GeneralContractor,Proje
MobilizationPhase
Start:Jan2'15Finish:Mar6'15
Duration:46daWBS:1.2.1
ResourceNames:GeneralContractor,Proje
Calltender
Start:Dec1'14Finish:Dec18'14
Duration:14daWBS:1.1.3.1
ResourceNames:
Opentender
Start:Dec19'1Finish:Dec19'14
Duration:1daWBS:1.1.3.2
ResourceNames:
Selectcontractor
Start:Dec22'1Finish:Dec30'14
Duration:7dayWBS:1.1.3.3
ResourceNames:
FormalizeContractStatementofWork
Start:Dec31'1Finish:Jan1'15
Duration:2dayWBS:1.1.3.4
ResourceNames:
Obtainbuildingpermits
Start:Jan2'15Finish:Jan15'15
Duration:10dWBS:1.2.1.1
ResourceNames:GeneralContractor,Proje
Developprojectschedule
Start:Jan16'1Finish:Jan16'15
Duration:1dayWBS:1.2.1.2
ResourceNames:GeneralContractor,Proje
Obtainprojectliabilityinsurance
Start:Jan16'1Finish:Jan22'15
Duration:5dayWBS:1.2.1.3
ResourceNames:GeneralContractor,Proje
ConstructionPhase
Start:Mar9'15Finish:Apr30'15
Duration:39daWBS:1.2.2
ResourceNames:GeneralContractor,Proje
ConductProjectKickoffMeeting
Start:Jan23'1Finish:Jan23'15
Duration:1dayWBS:1.2.1.4
ResourceNames:
Mobilizeequipment
Start:Jan26'1Finish:Feb6'15
Duration:10daWBS:1.2.1.5
ResourceNames:GeneralContractor,Proje
Preparationofsite
Start:Feb9'15Finish:Mar6'15
Duration:20dWBS:1.2.1.6
ResourceNames:
Commencebiweeklysiteinspections
Start:Mar9'15Finish:Mar9'15
Duration:1dayWBS:1.2.2.1
ResourceNames:
Procurementofturbines
Start:Mar9'15Finish:Mar9'15
Duration:1dayWBS:1.2.2.2
ResourceNames:GeneralContractor,Proje
Project Close-out
Start: 5/1/15
ID: 41
Finish: 5/25/15
Dur: 17 days
Comp: 0%
CommissioningStage
Start:May26'Finish:Jun25'15
Duration:23dWBS:1.3
ResourceNames:ProjectEngineer,Technici
SystemActivation
Start:May26'Finish:Jun24'15
Duration:22daWBS:1.3.1
ResourceNames:ProjectEngineer,Technici
Warrantyperiod
Start:Jun25'1Finish:Jun25'15
Duration:1dayWBS:1.3.2
ResourceNames:
Prepareconstructionandmaintenanceinfr
Start:Mar10'Finish:Apr27'15
Duration:35dWBS:1.2.2.3
ResourceNames:GeneralContractor,Proje
Performcivilengineeringwork
Start:Apr28'1Finish:Apr28'15
Duration:1dayWBS:1.2.2.4
ResourceNames:
Erectturbines
Start:Apr29'1Finish:Apr29'15
Duration:1dayWBS:1.2.2.5
ResourceNames:
Installandconnectelectricalequipment
Start:Apr30'1Finish:Apr30'15
Duration:1daWBS:1.2.2.6
ResourceNames:
ConductProjectPostMortemMeeting
Start:May1'1Finish:May1'15
Duration:1dayWBS:1.2.3.1
ResourceNames:
Finalizeandcloseallsubcontracts
Start:May4'1Finish:May15'15
Duration:10daWBS:1.2.3.2
ResourceNames:ProjectEngineer,Technol
Archiveprojectdocumentation
Start:May18'Finish:May20'15
Duration:3dayWBS:1.2.3.3
ResourceNames:ProjectEngineer,Technolo
PerformandfinalizeaLessonsLearnedR
Start:May21'Finish:May25'15
Duration:3daWBS:1.2.3.4
ResourceNames:
Performmechanicaltests
Start:May26'Finish:Jun15'15
Duration:15dWBS:1.3.1.1
ResourceNames:ProjectEngineer,Technici
Verifyelectricalandcommunicationsystem
Start:May26'Finish:Jun15'15
Duration:15dWBS:1.3.1.2
ResourceNames:ProjectEngineer,Technici
Restoreconditionofaccessroadsandcont
Start:May26'Finish:Jun15'15
Duration:15dWBS:1.3.1.3
ResourceNames:ProjectEngineer,Technici
Cleansite
Start:May26'Finish:Jun15'15
Duration:15dWBS:1.3.1.4
ResourceNames:ProjectEngineer,Technici
Approvecommercialcommissioning
Start:Jun16'1Finish:Jun18'15
Duration:3dayWBS:1.3.1.5
ResourceNames:ProjectEngineer,Technici
Finalizetransition
Start:Jun19'1Finish:Jun23'15
Duration:3dayWBS:1.3.1.6
ResourceNames:
ProjectCompletion
Start:Jun24'1Finish:Jun24'15
Duration:1daWBS:1.3.1.7
ResourceNames:
Providewarrantyservice
Start:Jun25'1Finish:Jun25'15
Duration:1dayWBS:1.3.2.1
ResourceNames:
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical