Task Name
Duration
August 2014
10 13 16 19 22 25 28 31 3 6 9
12 15 18 21 24 27 30
September 2014
Octo
2 5 8 11 14 17 20 23 26 29 2
1
2
Scoping
Design Submission
Prototype Development
5 days?
0 days
Sales
21 days?
Procurement
21 days?
Finance
30 days?
Accounting
10 days?
Report Development
10 days?
10
Sales
10 days?
11
Procurement
10 days?
12
13
Finance
10 days?
10 days?
14
Installation
5 days?
15
MasterData Migration
4 days?
16
17
Testing
1 day?
Trial
10 days?
18
Sales
10 days?
19
Procurement
10 days?
20
21
Finance
10 days?
GoLive
22.5 days?
22
Golive Start
23
3 Months Supervision
Project: ProjectSAI
Date: Tue 8/19/14
7/18
30 days?
0 days
9/1
22.5 days?
Task
Milestone
External Tasks
Split
Summary
External Milestone
Progress
Project Summary
Deadline
Page 1