SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 1 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

NAME PLATE DETAILS


1.

Model. No. 9T83C9064

2.

Make. GE ENERGY.

3.

Rated Power: 75 KVA.

4.

Frequency: 60 HZ.

5.

Vector Group: DYn1

6.

Class Insulation: AA

7.

Percent Impedance: 5

8.

Type: QL.

9.

Taps Number: 7 Taps.


Primary

Secondary

1-

400 V

220 V

2-

389 V

220 V

3-

380 V

220 V

4-

370 V

220 V

5-

362 V

220 V

6-

351 V

220 V

7-

344 V

220 V.

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 2 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

MECHANICAL CHECK AND VISUAL INSPECTION


Sl. No.

Description

Remarks

1.

Inspect for Physical damage and defects (Cracks, Chips, etc of


the cast resin).

2.

Check name plate information for correctness.

3.

Check Tightness of all bolted connections (Torque Wrench


Method).

4.

Check all grounding is securely connected, including star point


neutral.

5.

Perform all specific checks manufacturer's instructions.

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 3 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

WINDING INSULATION RESISTANCE TEST


Instrument: CPC 100.

Applied Points Between


HV -

ACCEPTED(1000M )
IR Value
60 Sec. ( G Ohms )

LV

HV - GND
LV - GND

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________

Result

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 4 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

POLARISATION INDEX ( P.I ) TEST


Instrument used
P.I.
Applied Voltage

: 5kV Insulation Resistance Tester (MEGER .MIT5012).


: IR Value at 10 Min
IR Value at 1 Min
1000
V .DC.
ACCEPTED PI > 1.2

Applied time

IR Values
HV to G

LV to G

HV to LV

1
2
3
4
5
6
7
8
9
10
PI

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 5 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

VECTOR RELATIONSHIP TEST


Instrument Used

: 380 V Supply and Fluk Meter.

Vector Group

Relation to be checked :
1.
2.
3.
4.

H1H2 = H2H3 = H3H1


H3X3 = H3X2
H1n + nH3 = H1H3
H2X2 < H2X3

Measurements :

H1 H2
H2 H3
H3 H1

H3- X2
H3 X3
n H1

H3 n
H2 X3
H2 X2

Result:
Vector Group (

) and Polarity are confirmed.

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 6 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

TRANSFORMER TURNS RATIO TEST


Instrument: CPC 100.

Tap
Changer
Position

Rated HV
Tap
Voltage V

Calculated
Turns
Ratio

Measured Ratio
PHASE B
H1 H2
%
Error
X2 - X0

PHASE A
H3 H1
%
Error
X1 - X0

PHASE C
H2 H3
%
Error
X3 - X0

1.
2.
3.
4.
5.
6.
7.

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 7 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

WINDING RESISTANCE MEASUREMENT


Instrument: CPC 100.

Criteria

HV - Winding Resistance ( milli Ohms )


Tap No.

Cal.

H1 - H2

Test Temperature 10 C
Cal.

H2 - H3

H3 - H1

At 75C

At 75C

Cal.
At 75C

Tap 1
Tap 2
Tap 3
Tap 4
Tap 5
Tap 6
Tap 7

LV Winding Resistance (milli ohms):


Cal.
X1 X0
X2 X0

Cal.

At 75C

X3 X0

At 75C

At 75C

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Cal.

Signature: ________________

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 8 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

WINDING EXCITATION CURRENT TEST

Instrument : CPC 100.

Tap Position

Nominal Tap No. Three

Voltage Applied

380 V

H1 - H2

H2 - H3

H3 - H1

Current (A)

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________

SITE TEST REPORT

Date :

Contractors name:
ABB CONTRACTING CO. LTD.

Customer:
SEC-EOA
SEC EOA Contract No. :

Name of substation: Al-MURJAN 115/13.8kV S/S

31031061/00
Page 9 of 9

DRY TRANSFORMER TEST.


Panel No:

Equip. No.:

Dwg. Ref.:

Record No.:

BACK ENERGIZATION TEST.


Instrument Used
Connection :

Fluke Meter 187

220V 3, 60Hz A.C. Source applied to Secondary of Transformer for 15min


Primary should be open

Measurements :
Secondary Current (A)
First Reading
After 15min
Secondary Voltage (V)
First Reading
After 15min
Secondary Voltage (V)
First Reading
After 15min
Primary Voltage (V)
First Reading
After 15min

Ia

Ib

Ic

X1 X2

X2 X3

X3 X1

X1 Xo

X2 Xo

X3 Xo

H1 - H2

H2 H3

H3 H1

Date:
TESTING ENGINEER

Name

: ABDULRAHMAN ABDO

Signature: ________________

CSD- Engineer

Name

Signature: ________________