Refresh Activity

on SE1
Status
PRE-REFRESH

Pre-Refresh activities on SE1


25th nov 2013 10:00 a.m ,
check if file system is sufficient
to accommodate PE1 backup

PRE-REFRESH

Take the offline backup

PRE-REFRESH

Save the SAP License

PRE-REFRESH

Export User Master - Transport


Request (Client Dependent)

PRE-REFRESH

Export Developer Access Keys


(Refer List) - Transport Request

PRE-REFRESH

Export RFC Settings - Transport


Request

PRE-REFRESH

Export ALE Connections Transport Request

PRE-REFRESH

Export Logical Connections Transport Request

PRE-REFRESH

Record the Last Transport


Request No. in E070L Table
(Field TRKORR)

PRE-REFRESH

Export Output Devices (SPAD)

PRE-REFRESH

Export IMG Project Management


Settings (SPRO)

PRE-REFRESH

Take Screen Shots of STMS,


SCC4, SM59,SPAD,SMLG, RZ12,
RZ03, RZ04, BD54, WE20( in all
clients), WE21 (in all clients),
STRUSTSS02,SMQS, SMQR,
SMQ1, SMQ2 and schema users
in SQL level

PRE-REFRESH

Change all Background Jobs from


Released to Scheduled Status

PRE-REFRESH

Take a backup of exported


transport requested and keep it
safe

PRE-REFRESH

Check whether all the transports


are released.