Act

ID

Description

Orig
Dur

Early
Start

Early
Finish

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

2008
JUN

JUL

AUG

SEP

OCT

NOV E

MILESTONE
MAJOR MILESTONE

MI1010 PLANT SHUT DOWN AND TIE-IN WORK


MI1020 MECHANICAL COMPLETION

45d 01NOV08 30NOV08


0

MI1025 PRE-COMMISSIONING

150d 01JUL08

MI1030 START COMMISSIONING

MEC

31OCT08
30NOV08

0 01DEC08

MI1060 REFERENCE

29d 31JUL07

28AUG07

REFERENCE

CONSTRUCTION
CIVIL
PILING WORK
FURNACE FDN.
CCF010 FURNACE FDN.

41d 07SEP07 10OCT07

FURNACE FDN.

CCF011 PIPE RACK FDN.

31d 12SEP07 10OCT07

PIPE RACK FDN.

CCF100 EXCAVATION

5d 13OCT07 17OCT07

EXCAVATION

CCF101 LEAN CONCRETE

2d 18OCT07 19OCT07

LEAN CONCRETE

FOUNDATION WORK
FURNACE FDN.

CCF102 PILE HEAD CUTTING

10d 20OCT07 29OCT07

CCF103 REBAR/FORM FOR FOOTING

10d 30OCT07 08NOV07

CCF104 CONCRETE FOR FOOTING

1d 09NOV07 09NOV07

CCF105 REBAR/FORM FOR PEDESTAL


CCF106 ANCHOR BOLT SETTING

7d 10NOV07 16NOV07
10d 17NOV07 26NOV07

PILE HEAD CUTTING


REBAR/FORM FOR FOOTING
CONCRETE FOR FOOTING
REBAR/FORM FOR PEDESTAL
ANCHOR BOLT SETTING
CONCRETE FOR PEDESTAL

CCF107 CONCRETE FOR PEDESTAL


NEW PIPE RACK

1d 27NOV07 27NOV07

CCF120 DEMOLITION DIV. BOX WALL

7d 10NOV07 16NOV07

CCF121 EXCAVATION

4d 17NOV07 20NOV07

EXCAVATION

CCF122 LEAN CONCRETE

2d 21NOV07 22NOV07

LEAN CONCRETE

CCF123 PILE HEAD CUTTING

7d 23NOV07 29NOV07

Date
29AUG07
26SEP07

Revision
FOR APPROVAL
MONTHL REPORT

Checked Approved
UKH
CSH
UKH
CSH

DEMOLITION DIV. BOX WALL

PILE HEAD CUTTING

DETAILED MASTER CONSTRUCTION SCHEDULE


FOR
NEW PLANT 2
FURNACE PROJECT SCHEDULE

Early bar
Early start point
Early finish point
Progress bar
Critical bar
Summary bar
Start milestone point
Finish milestone point

Act
ID

Description

CCF124 REBAR/FORM FOR FOOTING


CCF125 CONCRETE FOR FOOTING
CCF126 REBAR/FORM FOR PEDESTAL

Orig
Dur

Early
Start

Early
Finish

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

10d 30NOV07 09DEC07

REBAR/FORM FOR FOOTING

2d 10DEC07 11DEC07

CONCRETE FOR FOOTING

10d 12DEC07 21DEC07

2008
JUN

JUL

AUG

SEP

OCT

NOV E

REBAR/FORM FOR PEDESTAL

CCF127 ANCHOR BOLT SETTING

7d 22DEC07 28DEC07

ANCHOR BOLT SETTING

CCF128 CONCRETE FOR PEDESTAL

2d 29DEC07 30DEC07

CONCRETE FOR PEDESTAL

PAVING, DRAINAGE & MISC.


FURNACE FDN.
BACK FILLING FOR FURNACE FDN. AREA

CID1000 BACK FILLING FOR FURNACE FDN. AREA

5d 28NOV07 02DEC07

CID1010 WIRE MESH INSTALL

3d 03DEC07 05DEC07

WIRE MESH INSTALL

2d 06DEC07 07DEC07

CONCRETE FOR PAVING

CID1020 CONCRETE FOR PAVING


NEW PIPE RACK

BACK FILLING FOR NEW PIPE RACK AREA

CID1030 BACK FILLING FOR NEW PIPE RACK AREA

4d 31DEC07 03JAN08

CID1040 WIRE MESH INSTALL

3d 14JAN08 16JAN08

WIRE MESH INSTALL

2d 17JAN08 18JAN08

CONCRETE FOR PAVING

CID1050 CONCRETE FOR PAVING


LOCAL FDN.
CID1060 LOCAL FDN.

10d 04JAN08 13JAN08

LOCAL FDN.

FURNACE PACKAGE ERECTION


RADIANT PANEL ERECTION
CF1000 FOUNDATION CHIPPING & PADDING

10d 28NOV07 07DEC07

FOUNDATION CHIPPING & PADDING


PADDING INSPECTION

CF1110 PADDING INSPECTION

2d 08DEC07 09DEC07

CF1120 RADIANT FLOOR PANLE INSTALL

6d 10DEC07 15DEC07

RADIANT FLOOR PANLE INSTALL

CF1130 RADIANT SIDE PANEL INSTALL

15d 16DEC07 30DEC07

RADIANT SIDE PANEL INSTALL

CF1140 RADIANT END PANEL INSTALL

12d 19DEC07 30DEC07

RADIANT END PANEL INSTALL

CF1150 REAR PANEL INSTALL

15d 30JAN08 13FEB08

REAR PANEL INSTALL

CF1160 ARCH PANEL INSTALL

7d 14FEB08 20FEB08

CF1170 BOLT TIGHTEN'G & ALIGNMENT


CF1180 BASE PLATE GROUTING
CF1190 FLOOR, SIDE & END PLENUM DUCT INSTALL

30d 21FEB08 21MAR08

ARCH PANEL INSTALL


BOLT TIGHTEN'G & ALIGNMENT
BASE PLATE GROUTING

8d 22MAR08 29MAR08

FLOOR, SIDE & END PLENUM DUCT INSTAL

18d 30MAR08 16APR08

RADIANT STRUCTURE ERECTION


UP TO EL. + 16,442
CF1200 STRUCTURE INSTALL
CF1210 ALIGNMENT
CF1220 PLATFORM/ LADDER/ HAND RAIL INSTALL
EL. +16,442 ~ EL. +22,992
CF1230 STRUCTURE INSTALL
CF1240 ALIGNMENT
CF1250 PLATFORM/ LADDER/ HANDRAIL INSTALL

15d 31DEC07 14JAN08


7d 15JAN08 21JAN08
15d 15JAN08 29JAN08
21d 02APR08 22APR08
7d 23APR08 29APR08
18d 23APR08 10MAY08

STRUCTURE INSTALL
ALIGNMENT
PLATFORM/ LADDER/ HAND RAIL INSTALL
STRUCTURE INSTALL
ALIGNMENT
PLATFORM/ LADDER/ HANDRAIL INST

Act
ID
EL. +22,992 ~ EL.+ 28,800

Description

CF1260 STRUCTURE INSTALL


CF1270 ALIGNMENT
CF1280 PLATFORM/ LADDER/ HAND RAIL INSTALL
EL. +28,800 ~ EL. + 33,700
CF1290 STRUCTURE INSTALL
CF1300 ALIGNMENT
CF1310 PLATFORM/ LADDER/ HAND RAIL INSTALL
EL. + 33,700 ~ EL. +38,925
CF1320 STRUCTURE INSTALL
CF1330 ALIGNMENT
CF1340 PLATFORM/ LADDER/ HAND RAIL INSTALL

Orig
Dur

Early
Start

Early
Finish

23d 13MAY08 04JUN08


7d 05JUN08 11JUN08
15d 05JUN08 19JUN08
10d 30JUN08 09JUL08

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

2008
JUN

JUL

AUG

SEP

OCT

NOV E

STRUCTURE INSTALL
ALIGNMENT
PLATFORM/ LADDER/ HAND RA
STRUCTURE INSTALL

7d 10JUL08

16JUL08

ALIGNMENT

10d 10JUL08

19JUL08

PLATFORM/ LADDER/ HA

15d 17JUL08

31JUL08

7d 01AUG08 07AUG08
10d 01AUG08 10AUG08

STRUCTURE INSTALL
ALIGNMENT
PLATFORM/ LADDER

FURNACE EQUIPMENT INSTALLATION


CONVECTION MODULE
CONVECTION MODULE #1

CF1500 CONVECTION MODULE #1

2d 30APR08 01MAY08

CF1510 CONVECTION MODULE#2

2d 11MAY08 12MAY08

CONVECTION MODULE#2

CF1520 CONVECTION MODULE#3

3d 13MAY08 15MAY08

CONVECTION MODULE#3

CF1530 CONVECTION MODULE#4

2d 16MAY08 17MAY08

CONVECTION MODULE#4

CF1540 CONVECTION MODULE#4


REFRACTORY W ORK

2d 18MAY08 19MAY08

CONVECTION MODULE#4

CF1600 SCAFFOLDING INSTALL

10d 23APR08 02MAY08

CF1605 LOWER RADIANT WALL

60d 03MAY08 01JUL08

CF1610 UPPER RADIANT WALL

60d 17JUN08 15AUG08

SCAFFOLDING INSTALL
LOWER RADIANT WALL
UPPER RADIANT WA
PLENUM FLOOR

CF1620 PLENUM FLOOR

10d 22JUL08

31JUL08

CF1630 PLENUM WALLS & COLUMNS

20d 02JUL08

21JUL08

PLENUM WALLS & COLU

CF1640 RADIANT ARCH MODULE/ BLANKET LINING

20d 02JUL08

21JUL08

RADIANT ARCH MODULE

CF1650 RADIANT MISC.

10d 22JUL08

31JUL08

CF1655 FINAL INSPECTION

3d 01AUG08 03AUG08

CF1658 SCAFFOLDING DISMANTLE

5d 04AUG08 08AUG08

CF1660 RADIANT FLOOR

10d 09AUG08 18AUG08

CF1670 STACK

12d 02JUL08

13JUL08

CF1680 STACK STUB

12d 14JUL08

25JUL08

CF1690 TROUGH WALL AND FLOOR


FURNACE PIPING W ORK
CF1700 RADIANT COIL INSTALL & WELDING

RADIANT MISC.
FINAL INSPECTION
SCAFFOLDING DISMA
RADIANT FLOOR
STACK
STACK STUB

20d 01AUG08 20AUG08

TROUGH WALL AN

15d 05JUN08 19JUN08

RADIANT COIL INSTALL & WEL

7d 20JUN08 26JUN08

RADIANT COIL FIELD TEST

CF1720 CROSS OVER PIPING INSTALL & WELDING

15d 20MAY08 03JUN08

CROSS OVER PIPING INSTALL & W

CF1725 CROSS OVER PIPING NDE WORK & TEST

5d 04JUN08 08JUN08

CROSS OVER PIPING NDE WORK

CF1710 RADIANT COIL FIELD TEST

Act
ID

Description

CF1730 JUMP OVER PIPING INSTALL & WELDING


CF1735 JUMP OVER PIPING NDE WORK & TEST

Orig
Dur

Early
Start

Early
Finish

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2008
JUN

MAY

JUL

20d 15AUG08 03SEP08

CF1745 RISER & DOWN COMER PIPING FIELD TEST


FURNACE EQUIPMENT

5d 04SEP08 08SEP08

SEP

RISER & DOWN

4d 20JUN08 23JUN08

PQE INSTALL

CF1810 TQE INSTALL

3d 24JUN08 26JUN08

TQE INSTALL

CF1820 SQE INSTALL

3d 27JUN08 29JUN08

SQE INSTALL

CF1840 ID FAN & DUCT INSTALL


OTHERS
CF1900 BURNER INSTALL
CF1910 PEEP DOOR INSTALL

NOV E

RISER & DOWN

CF1800 PQE INSTALL

CF1830 STEAM DRUM

OCT

JUMP OVER PIPING NDE WOR

5d 19JUN08 23JUN08

CF1740 RISER & DOWN COMER PIPING INSTALL &

AUG

JUMP OVER PIPING INSTALL &

15d 04JUN08 18JUN08

STEAM DRUM

7d 08AUG08 14AUG08

ID FAN & DUCT IN

15d 11AUG08 25AUG08


20d 19AUG08 07SEP08

BURNER INSTA

10d 09AUG08 18AUG08

PEEP DOOR INSTA

STRUCTURE
SHOP FABRICATION
SHOP DRAWING

CS1000 SHOP DRAWING

20d 02MAR08 21MAR08

CS1010 MAIN STRUCTURE

60d 22MAR08 20MAY08

CS1020 HAND RAIL, STAIR, LADDER

30d 06MAY08 04JUN08

CS1030 CONNECTION WALK WAY

30d 21MAY08 19JUN08

CONNECTION WALK WAY

CS1100 MAIN STRUCTURE

30d 21MAY08 19JUN08

MAIN STRUCTURE

CS1110 BOLT TIGHT'N & ALIGNMENT

10d 20JUN08 29JUN08

MAIN STRUCTURE
HAND RAIL, STAIR, LADDER

FIELD ERECTION

CS1120 INSPECTION FOR ALIGNMENT


CS1150 HAND RAIL, STAIR & LADDER

BOLT TIGHT'N & ALIGNMENT

2d 30JUN08 01JUL08

INSPECTION FOR ALIGNMEN

20d 20JUN08 09JUL08

HAND RAIL, STAIR & LADDE

PIPING
SHOP FABRICATION
EXISTING PIPE RACK AREA
CARBON STEEL PIPING

CP1010 CARBON STEEL PIPING

15d 15DEC07 29DEC07

CP1020 LOW ALLOY PIPING

15d 30DEC07 13JAN08

LOW ALLOY PIPING

5d 18FEB08 22FEB08

SUS PIPING

CP1030 SUS PIPING


NEW PIPE RACK AREA
CP1040 CARBON STEEL PIPING

20d 30DEC07 18JAN08

CP1050 LOW ALLOY PIPING

20d 14JAN08 02FEB08

CP1060 SUS PIPING


FURNACE AREA
CP1070 CARBON STEEL PIPING

5d 23FEB08 27FEB08
30d 19JAN08 17FEB08

CARBON STEEL PIPING


LOW ALLOY PIPING
SUS PIPING
CARBON STEEL PIPING

Act
ID

Description

CP1080 LOW ALLOY PIPING


CP1090 SUS PIPING

Orig
Dur

Early
Start

Early
Finish

30d 03FEB08 03MAR08


5d 28FEB08 03MAR08

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

2008
JUN

JUL

AUG

SEP

OCT

NOV E

LOW ALLOY PIPING


SUS PIPING

FIELD ERECTION
EXISTING PIPE RACK AREA
CP1300 CARBON STEEL PIPING

30d 19JAN08 17FEB08

CP1310 LOW ALLOY PIPING

30d 29MAR08 27APR08

CP1320 SUS PIPING


NEW PIPE RACK AREA

CARBON STEEL PIPING


LOW ALLOY PIPING
SUS PIPING

10d 07JUN08 16JUN08

CARBON STEEL PIPING

CP1330 CARBON STEEL PIPING

40d 18FEB08 28MAR08

CP1340 LOW ALLOY PIPING

40d 28APR08 06JUN08

LOW ALLOY PIPING

10d 17JUN08 26JUN08

SUS PIPING

CP1350 SUS PIPING


FURNACE AREA
CP1360 CARBON STEEL PIPING

90d 18FEB08 17MAY08

CP1370 LOW ALLOY PIPING

90d 28APR08 26JUL08

CP1380 SUS PIPING

CARBON STEEL PIPING


LOW ALLOY PIPING
SUS PIPING

20d 27JUN08 16JUL08

PRESSURE TEST
CP1500 CARBON STEEL PIPING

90d 18MAY08 15AUG08

CP1510 LOW ALLOY PIPING

60d 27JUN08 25AUG08

CP1520 SUS PIPING

20d 17JUL08

CARBON STEEL PIP


LOW ALLOY PIPIN
SUS PIPING

05AUG08

ELECTRIC
GROUDING WORK
NEW PIPE RACK AREA
CE1050 GROUNDING WORK
FURNACE AREA

30d 13DEC07 11JAN08

CE1000 GROUNDING WORK

20d 13NOV07 02DEC07

GROUNDING WORK
GROUNDING WORK

LIGHTING
NEW PIPE RACK AREA
CE1200 CABLE TRAY & SUPPORT

30d 10JUL08

08AUG08

CABLE TRAY & SUPP

CE1210 LIGHTING FIXTURE INSTALL

5d 09AUG08 13AUG08

LIGHTING FIXTURE

CE1220 PDB INSTALL

3d 14AUG08 16AUG08

PDB INSTALL

CE1230 CABLE PULLING


CE1240 TERMINATION
FURNACE AREA

15d 17AUG08 31AUG08

CABLE PULLING

5d 01SEP08 05SEP08

TERMINATION

CE1250 CABLE TRAY & SUPPORT

45d 20JUN08 03AUG08

CABLE TRAY & SUPPO

CE1260 LIGHTING FIXTURE INSTALL

10d 04AUG08 13AUG08

LIGHTING FIXTURE

CE1270 CABLE PULLING

20d 14AUG08 02SEP08

CABLE PULLING

CE1280 TERMINATION

10d 03SEP08 12SEP08

TERMINATION

Act
ID

Description

Orig
Dur

Early
Start

Early
Finish

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

2008
JUN

JUL

AUG

SEP

OCT

NOV E

INSTRUMENT
CABLE TRAY & SUPPORT
CI1000

TRAY SUPPORT FABRICATION

120d 10JUL08

06NOV08

TRA

CI1060

TRAY SUPPORT INSTALLATION

120d 20JUL08

16NOV08

TR

CI1070

CABLE TRAY INSTALLATION

120d 30JUL08

26NOV08

INSTRUMENT CALIBRATION
CI1200

TRANSMITTER (DP, PRESSURE,TEMP)

30d 19AUG08 17SEP08

TRANSMITTE

CI1210

CONTROL VALVE

30d 03SEP08 02OCT08

CONTROL

CI1220

ON OFF VALVE

20d 18SEP08 07OCT08

ON OFF V

CI1230

TEMPERATURE ELEMENT

20d 03OCT08 22OCT08

TEMPE

CI1240

PRESSURE GAUGE

20d 08OCT08 27OCT08

PRES

JUCTION BOX & STANCHION


CI1300

JUCTION SUPPORT FABRICATION

45d 09AUG08 22SEP08

JUCTION SU

CI1310

JUNCTION BOX INSTALL

30d 23SEP08 22OCT08

JUNCT

CI1320

STANCHION INSTALL

30d 28SEP08 27OCT08

STAN

FIELD INSTRUMENT INSTALL


CI1600

TRANSMITTER INSTALL(DP, PRESSURE,

60d 12JUL08

09SEP08

TRANSMITTER

CI1610

CONTROL VALVE

60d 12JUL08

09SEP08

CONTROL VALV

CI1620

ON-OFF VALVE

60d 12JUL08

09SEP08

ON-OFF VALVE

CI1630

TEMPERATURE ELEMENT

60d 12JUL08

09SEP08

TEMPERATURE

CI1640

PRESSURE GAUGE

60d 12JUL08

09SEP08

PRESSURE GA

CABLE PULLING & TERMINAION


CI1400

CABLE PULLING

30d 27NOV08 26DEC08

CI1410

TERMINATION & CABLE GLANDING

30d 07DEC08 07JAN09

CI1420

CONTINUITY TEST

30d 17DEC08 21JAN09

AIR PIPING & TUBING


SUPPORT FABRICATION

CI1500

SUPPORT FABRICATION

30d 18MAY08 16JUN08

CI1510

AIR PIPE INSTALL

45d 17JUN08 31JUL08

CI1520

AIR PIPE LEAK TEST

20d 01AUG08 20AUG08

CI1530

TUBING WORK

60d 12JUL08

09SEP08

TUBING WORK

CI1540

IMPLUSE LINE LEAK TEST

20d 10SEP08 29SEP08

IMPLUSE L

SHUT DOWN WORK

AIR PIPE INSTALL


AIR PIPE LEAK TES

Act
ID

Description

CT1000 TIE-IN AND SHUT DOWN WORK

Orig
Dur

Early
Start

Early
Finish

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

2008
JUN

JUL

AUG

SEP

OCT

NOV E

15d 08NOV08 22NOV08

60d 11APR08 09JUN08

SURFACE PREPARATION & PRIM

PAINTING & INSULATION


PAINTING
STRUCTURE
PA1000 SURFACE PREPARATION & PRIMER
PA1010 TOP COAT
PIPING

80d 31MAY08 18AUG08

PA1020 SURFACE PREPARATION & PRIMER

90d 30NOV07 27FEB08

PA1030 TOP COAT

90d 07JUN08 04SEP08

TOP COAT
SURFACE PREPARATION & PRIMER
TOP COAT

FURNACE & EQUIPMENT


PA1040 TOUCH-UP & TOP COAT

130d 27JUN08 03NOV08

TOU

100d 17JUN08 24SEP08

PIPING INSU

INSULATION
PIPING
IN1000 PIPING INSULATION
FURNACE PIPING W ORK

03NOV08

EQU

PC1040 PRESSURE TEST FOR STEAM SYSTEM

25d 26AUG08 19SEP08

PRESSURE T

PC1050 CHEMICAL CLEANING

20d 20SEP08 09OCT08

CHEMICA

IN1010

EQUIPMENT INSULATION

125d 02JUL08

PRE COMMISSIONING
FURNACE PACKAGE ERECTION

PIPING

LINE FLUSHING

PC1000 LINE FLUSHING

60d 27JUN08 25AUG08

PC1100 STEAM BLOWING

15d 27JUL08

PC1110 SYSTEM LEAK TEST

30d 11AUG08 09SEP08

SYSTEM LEAK

PC1060 ID FAN MOTOR NO LOAD TEST

5d 10SEP08 14SEP08

ID FAN MOTO

PC1070 LIGHTING ENERGIZING

3d 13SEP08 15SEP08

LIGHTING ENE

10AUG08

STEAM BLOWING

ELECTRIC

INSTRUMENT

Act
ID

Description

PC1080 LOOP & FUNCTION TEST


PC1090 SAFETY VALV POPPING TEST

Orig
Dur

Early
Start

Early
Finish

60d 26AUG08 24OCT08

JUN

JUL

AUG

2007
SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

MAY

2008
JUN

JUL

AUG

SEP

OCT

NOV E

LOOP

5d 15SEP08 19SEP08

SAFETY VALV

3d 25OCT08 27OCT08

UTILIT

1d 28OCT08 28OCT08

HYDR

15d 29OCT08 12NOV08

HE

COMMISSIOING
FURNACE PACKAGE ERECTION

CO1030 UTILITY INTRODUCE


CO1040 HYDRO CARBON INTRODUCE
CO1060 HEATER DRY OUT

INSTRUMENT

CO1000 CALIBRATION OF IN LINE ANALYZER


CO1010 LEVEL INSTRUMENT CALIBRATION

15d 13NOV08 27NOV08


7d 13NOV08 19NOV08