MS PROJECT-2013

ING. LUIS A. MONCADA CASTRO

FLUJO DE CAJA-PROYECTO MI VIVIENDA


Nombre

Costo Duracin Comienzo

Fin

Proyecto : Vivienda

S/. 5,327.00

45 das

lun 07/10/13

vie 06/12/13

Modulo 1

S/. 3,867.00

28 das

lun 07/10/13

mi 13/11/13

Limpieza de Terreno

S/. 240.00

3 das

lun 07/10/13

mi 09/10/13

Cimientos

S/. 27.00

8 das

jue 10/10/13

lun 21/10/13

Levantar Estructura

S/. 2,800.00

7 das

mar 22/10/13

mi 30/10/13

Secado

S/. 800.00

10 das

jue 31/10/13

mi 13/11/13

S/. 1,060.00

12 das

jue 14/11/13

vie 29/11/13

Acabado de Exteriores

S/. 420.00

4 das

jue 14/11/13

mar 19/11/13

Instalaciones

S/. 160.00

2 das

mi 20/11/13

jue 21/11/13

Acabado de Interiores

S/. 480.00

6 das

vie 22/11/13

vie 29/11/13

S/. 400.00

5 das

lun 02/12/13

vie 06/12/13

Pintado

S/. 240.00

3 das

lun 02/12/13

mi 04/12/13

Jardineria

S/. 160.00

2 das

jue 05/12/13

vie 06/12/13

Modulo 2

Modulo 3

FLUJO DE CAJA-PROYECTO MI VIVIENDA

vie 12/09/14 - 07:00 p.m.