SULTANATE OF OMAN

MINISTRY OF TRANSPORT AND COMMUNICATIONS


DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT
MUSCAT

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT


TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 10
OCTOBER 2014

CONSULTANT:

CONTRACTOR:

RENARDET S.A. & PARTNERS CONSULTING


ENGINEERS LLC.
P.O. Box 579, Muscat, P.C. 100,
Sultanate of Oman

CONSOLIDATED CONTRACTORS CO. LLC


P.O. Box 614,
Muscat, P.C. 100,
Sultanate of Oman

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report October 2014

Table of Contents
1.

PROJECT PARTICULARS .............................................................................................................................................. 2

2.

SCOPE OF WORK ....................................................................................................................................................... 3

3.

TYPICAL CROSS SECTIONS .......................................................................................................................................... 4

4.

SITE VISITS/ MEETINGS .............................................................................................................................................. 6

5.

ENGINEERS SITE STAFF ............................................................................................................................................. 7

6.

PROGRESS S-CURVE ................................................................................................................................................... 8

7.

STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10

8.

BRIDGE SUB-STRUCTURE PROGRESS SCHEDULE ...................................................................................................... 11

9.

MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12

10.

BOX CULVERTS PROGRESS SCHEDULE...................................................................................................................... 15

11.

PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 19

12.

PROJECT STRIP CHART ............................................................................................................................................. 23

13.

FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 29

14.

DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 30

15.

DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 32

16.

QA/QC REPORTS...................................................................................................................................................... 34

17.

STATUS OF MATERIAL APPROVALS .......................................................................................................................... 39

18.

ENGINEERS COMMENTS ......................................................................................................................................... 40

19.

DETAILS OF CORRESPONDENCE DURING THE MONTH ............................................................................................. 41

20.

PROGRESS PHOTOGRAPHS ...................................................................................................................................... 42

RENARDET S.A. & PARTNERS

Page 1

Monthly Progress Report October 2014

Project: Upgrading of Falaj Al Qabail Roundabout

1.

Project Particulars

Client:

Ministry of Transport & Communications


P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.

Consultant:

Renardet S.A & Partners L.L.C.


P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.

Contractor:

Consolidated Contractors Company L.L.C.


P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.

Project Commencement Date:

30.10.2013

Mobilization Period:

60 Days

Construction Period:

548 Days

Completion date:

29.06.2015

Original Contract Value:


(Including Contingencies)

R.O. 17,884,403.000

Amount of Contingencies:

R.O. 1,402,155.613

Original Contract Value:


(Excluding Contingencies)

R.O. 16,482,247.387

Planned Physical Progress for September


2014

8.49%

Actual Physical Progress for September


2014

6.20%

Planned physical progress cumulative up to


end of September 2014
Achieved physical progress cumulative up
to end of September 2014

RENARDET S.A. & PARTNERS

48.35%

45.39%

Page 2

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report October 2014

2. Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:

Removal of existing asphalt surface, extension of existing embankment and earthwork to


achieve the designed profile and gradient.
Removal of existing drainage structures and construction of new ones including protection
works as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and removal/disposal of existing street
light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous
base course and bituminous wearing course as per details on the construction drawings.
Installation of road side furniture (traffic signs, road marking etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items
(transformers etc.) as per the requirements of concerned authority.
Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and
irrigation) as per the requirements of concerned authorities.
Provision of ducts for future utilities as per the requirements of utility operator.
Construction of concrete safety barriers, fixing of guard rails and paving tiles.
Provision of traffic diversion in coordination with concerned authorities.

RENARDET S.A. & PARTNERS

Page 3

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report October 2014

3. Typical Cross Sections

RENARDET S.A. & PARTNERS

Page 4

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report October 2014

Page 5

Monthly Progress Report October 2014

Project: Upgrading of Falaj Al Qabail Roundabout

4. Site visits/ Meetings


S. No.

Details of Site Visit/ meeting

Date

Final Outcome/ Decisions

Meeting with Dr. Ramadan, Director


of Planning, Sohar Municipality

14.10.2014

Land owner of Plot adjacent to


Sohar Airport Access Road details
are obtained.

RENARDET S.A. & PARTNERS

Page 6

Monthly Progress Report October 2014

Project: Upgrading of Falaj Al Qabail Roundabout

5. Engineers Site Staff


S.
Name
No.
1. Roberto Benigni

Designation

Date of
Joining

Head Supervision Projects

2.

Muneer Abdul

Resident Engineer

19.03.2014

3.

Hussein Shah

Material Engineer

04.01.2014

4.

Ernesto B. Paredes

Bridge Engineer

16.04.2014

5.

Sande H Tangaras

Civil Engineer

08.06.2014

6.

Danilo

Quantity Surveyor

19.06.2014

6.

Mohamed Safie

Land Surveyor

04.01.2014

7.

Aseef Iqbal

Site Inspector

10.02.2014

8.

Alaa Aldin Abdelfatah

Site Inspector

30.03.2014

9.

Walid Samy Abdoh Mostafa

Material Inspector

01.04.2014

Secretary

13.04.2014

10. Haneefa Mohmmed Al Zadjali

RENARDET S.A. & PARTNERS

Page 7

6. Progress S-Curve
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMAN
MONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS

12

120.00

MONTHS

Actual per Month

2013

CL14 Org Plan Cumulative %

Revised Sch. Cummulative %

2014
Jan

Feb

Mar

Apr

May

Jun

Actual Cumulative

2015
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

CL14 Org Plan per Month %

0.01

0.25

1.42

4.23

7.25

10.06

9.42

9.73

10.21

9.79

8.49

5.72

4.55

3.56

2.79

3.83

3.55

3.47

1.67

Revised Sch. per Month %

0.11

0.14

0.23

0.28

1.71

3.18

6.84

9.16

9.14

9.08

8.49

7.90

8.08

6.71

6.25

4.68

3.59

3.34

4.42

Actual per Month

0.28

Oct

Sep

Aug

Jul

Jun

May

Apr

Mar

2015

Revised Sch. per Month %

Dec

CUMULATIVE PROGRESS

Feb

2014

CL14 Org Plan per Month %

MONTHLY PROGRESS

Nov

Sep

Jun

2013

Jan

0.00

Dec

Oct

20.00

Aug

Jul

40.00

May

Apr

60.00

Mar

Feb

80.00

Jan

% Cumulative

100.00

Dec

% MONTHLY

10

0.18

1.01

2.92

5.63

5.18

7.36

7.30

9.33

6.20

Jul

Aug

3.29
-

1.64
-

Sep
1.11
-

Oct
0.62
-

CL14 Org Plan Cum ulative %

0.01

0.26

1.67

5.91

13.15

23.21

32.64

42.37

52.58

62.37

70.86

76.59

81.13

84.69

87.48

91.31

94.86

98.33

100.00

100.00

100.00

100.00

100.00

Revised Sch. Cum m ulative %

0.11

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

48.35

56.26

64.34

71.05

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

Actual Cum ulative

0.28

0.45

1.46

4.38

10.01

15.19

22.55

29.86

39.18

45.39

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN

REV.:
0
PERIOD ENDING:

Oct-14

MANHOURS OVERALL PROJECT S-CURVE

Item

Description

Budgeted
Man-Hrs

56,423

Road Diversions

Wtd.
%

2.73

Plan/
Actual

2013
Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

CL14 Plan %

0.30

8.67

19.23

26.89

31.77

36.64

41.51

46.39

51.26

56.13

61.01

65.88

70.76

75.63

80.50

85.38

90.25

95.13

100.00

100.00

100.00

100.00

100.00

80.93

84.74

88.56

92.37

96.18

100.00

100.00

100.00

100.00

100.00

100.00

100.00

80.66

87.59

88.57

100.00

100.00

100.00

Revised Plan %
Actual

CL14 Plan %

Clearing &
Removal of
Obstructions

19,558

Embankment

74,043

0.95

3.59

14,821

Subbase &
Aggregate Base

50,004

Bituminous
Pavement

73,724

0.72

42.78

46.60

50.41

54.23

44.11

51.21

56.24

60.13

65.67

0.00

0.38

20.37

47.70

48.33

48.33

48.33

48.33

3.57

48.33

48.33

29.85

78.13

78.13

78.13

78.13

Actual

10.09

10.09

17.59

19.52

77.42

69.96

70.18

70.18

70.18

83.49

0.00

0.00

0.78

0.00

Revised Plan %

Actual

Revised Plan %

Revised Plan %

0.00
0.00
-

0.00
0.00
-

1.01
0.00
-

9.21
5.00
0.00
-

6.58
4.35
29.30
5.00
0.00
-

16.76
4.89
45.91

29.38

41.37

58.64

Revised Plan %

66.60

3.32

12.89

28.83

43.89

5.27

14.93

29.52

47.15

56.90

62.24

64.59

67.94

0.00
-

0.00
-

0.00
-

0.00
-

69.08

4.26

8.17

16.03

32.68

53.13

67.05

53.23
0.00

62.16
0.00

74.91
0.00

78.29
11.07

91.86
26.27

98.62
41.98

1.26
0.00

74.18

Actual
0.00
-

0.00
-

0.00
-

0.00
-

0.08
-

58.04
48.33
78.13
82.85
60.03
69.08
67.47
59.98
3.58

61.86
48.33
78.13
84.75
74.82
75.05
67.47
78.73
17.42

65.67
59.91
78.13
84.75
90.03
82.85
67.90
79.90
31.37

69.48
77.84
78.13
85.24
95.24
93.48
68.32
79.90
51.32

73.30
90.27
78.13
92.34
95.95
98.64
68.32
85.20
75.82

77.11
94.93
78.13
92.34

100.00

100.00

100.00

100.00

100.00

95.95

96.09

98.30

99.46

99.54

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

68.32

81.11

93.02

97.11

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

75.82

87.25

87.25

98.60

100.00

100.00

100.00

100.00

100.00

100.00

51.97

86.66

90.05

93.03

100.00

89.45
75.82

98.36

92.60
75.82

3.19
7.77
-

19.32
-

31.22
-

44.94
0.08

51.98
8.44

52.14
22.42

90.14
46.57

90.14
51.97

Actual
CL14 Plan %

Concrete for
Box Culvert
/Underpas

788,138

Concrete for
Bridge

456,522

38.19

22.12

1.50

Incidental
Construction

275,037

MSE walls

141,190

13.33

6.84

MEP Works &


Ducts

83,264

2,063,644

4.03

100.000

0.00

0.23

1.43

2.97

10.17

51.47

63.06

74.26

0.26

2.64

7.33

20.62

35.14

50.06

62.76

68.40

Actual

0.48

1.26

5.59

14.93

27.72

40.08

55.38

66.20

Revised Plan %

0.00
0.00

0.00
0.00

4.02
0.00

Revised Plan %

Actual

0.00

0.00

0.00

15.21
0.01
0.00
2.50
0.00

34.62

71.33

6.05
0.00

14.73
0.38

18.14
1.21

22.33
2.63

26.30
3.42

30.75
4.23

34.14
5.50

6.08

6.08

61.45

74.69

90.19

17.74

14.39

13.24

16.19

16.72

27.56

21.22

0.00

0.00

2.80

0.00

Actual

0.00

0.00

0.00

Revised Plan %

Actual

Revised Plan
Actual Cum

0.11
-

4.43
6.16
0.00
-

99.96

59.51

Actual

92.89

49.64

0.00

84.50

39.02

83.46

29.64

0.00

83.38

74.07

22.09

81.40

77.37

13.76

0.00

69.26

72.78

7.75

Revised Plan %

Revised Plan %

57.89

75.97

2.77

17.23
9.87
0.00
-

0.13

5.52

2.61
33.36

4.98

6.42
65.07

17.87
8.31
80.79

43.85

61.59

7.02

10.67

12.36

93.82

72.98

81.15

100.00

100.00

100.00

100.00

100.00

74.67

83.42

84.04

84.30

87.32

95.58

98.11

99.44

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

85.14

87.00

93.50

100.00

100.00

100.00

100.00

100.00

100.00

100.00

99.76

100.00

100.00

100.00

100.00

100.00

100.00

94.70

98.41

100.00

100.00

100.00

100.00

34.35
94.70
83.94

82.40

99.38
94.70
84.42

88.97

99.76
94.70
85.35

92.13

94.70
92.86

98.55

100.00

100.00

100.00

100.00

100.00

20.33

38.29

50.60

59.52

72.89

81.07

96.39
83.55

86.89

90.26

95.34

98.27

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

2.30

17.26

33.64

49.01

64.70

79.88

95.44

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

17.63

25.69

35.90

49.03

65.95

72.27

0.17

0.79

1.43

5.65

70.94

75.04

94.02

96.43

49.13

80.05

0.99

13.41

21.84

0.33

2.34

9.42

17.07

9.26

13.38

16.87

17.75

20.45

14.38

30.56

100.00

100.00

100.00

100.00

100.00

100.00

23.51

32.94
31.40

41.66

47.49

47.55

47.55

83.28

93.95

97.61

100.00

100.00

100.00

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

48.35

56.26

64.34

71.05

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

0.28

0.45

1.46

4.38

10.01

15.19

22.55

29.86

39.18

45.39

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jun

Jul

Aug

2014

2013
Jan

Feb

Mar

Apr

2015
Jan

Feb

Mar

Apr

May

Sep

Oct

CL14 Org Plan per Month %

0.01

0.25

1.42

4.23

7.25

10.06

9.42

9.73

10.21

9.79

8.49

5.72

4.55

3.56

2.79

3.83

3.55

3.47

1.67

Revised Sch. per Month %

0.11

0.14

0.23

0.28

1.71

3.18

6.84

9.16

9.14

9.08

8.49

7.90

8.08

6.71

6.25

4.68

3.59

3.34

4.42

3.29

1.64

1.11

0.62

Actual per Month

CUMULATIVE PROGRESS

36.51

Dec

MONTHLY PROGRESS

23.65

Actual
CL14 Plan %
30,920

0.00

Revised Plan %
CL14 Plan %

Drainage Works

TOTAL

38.97

43.00
7.40

CL14 Plan %

35.16

37.31
-

CL14 Plan %

30.90

22.36
-

CL14 Plan %

24.18

13.03
-

CL14 Plan %

17.58

6.62
-

Actual
CL14 Plan %
2.42

0.00

9.30

CL14 Plan %

Structural
Excavation

2015

Revised Plan %
CL14 Plan %

4.11

2014

0.28

0.18

1.01

2.92

5.63

5.18

7.36

7.30

9.33

6.20

CL14 Org Plan Cum ulative %

0.01

0.26

1.67

5.91

13.15

23.21

32.64

42.37

52.58

62.37

70.86

76.59

81.13

84.69

87.48

91.31

94.86

98.33

100.00

100.00

100.00

100.00

100.00

Revised Sch. Cum m ulative %

0.11

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

48.35

56.26

64.34

71.05

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

0.28

0.45

1.46

4.38

10.01

15.19

22.55

29.86

39.18

45.39

Actual Cum ulative

7.

Sl.
No.

Status of Major Activities

Description

Unit

BOQ Qty.
(Revised)

Actual
Qty.

%
Completion

Clearing & Grubbing

M2

162,000

129,901

80.19%

M3

340,000

108,670

31.96%

Borrow Excavation (to


embankment)
Granular Sub-base

M3

28,700

3,900

13.59%

Concrete for Culverts

M3

15,000

12,421

82.81%

Concrete for Bridge

M3

13,805

3,286

23.80%

Steel reinforcement Fixing

ton

4,900

2,063

42.10%

Working Piles

M3

2,826

2,826

100.00%

Mortared Stone Riprap

M3

5,210

0.00

0.00%

MSE Walls

M2

13,200

5,100

39.39%

11

RCC Drainage Pipes

LM

4,530

788

17.39%

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

8. Bridge Sub-Structure Progress Schedule


SUB-STRUCTURE WORK PROGRESS (LHS)
ACTIVITY

AB1 L

P1L

P2L

P3L

P4L

P5L

AB2 L

N/A

N/A

2nd Lift

13-Aug-14

19-Aug-14

24-Jul-14

29-Sep-14

4-Sep-14

Height (m)

6.920

6.920

6.920

6.920

6.920

1st Lift

23-Jul-14

7-Aug-14

29-Jun-14

15-Sep-14

10-Aug-14

Height (m)

1.153

1.210

1.440

1.248

1.225

BIT. PAINTING

28-May-14

26-Jun-14

17-May-14

4-Sep-14

23-Jun-14

PILE CAP (Pier & Abut.)

17-May-14

18-Jun-14

8-May-14

25-Aug-14

11-Jun-14

21-Oct-14

11-May-14

11-Jun-14

1-May-14

17-Aug-14

3-Jun-14

AB2 R

PEDESTAL/POT BEARING

PIER

F/P & BLINDING

SUB-STRUCTURE WORK PROGRESS (RHS)


ACTIVITY

AB1 R

P1R

P2R

P3R

P4R

P5R

PEDESTAL/POT BEARING

16-Oct-14

14-Oct-14

14-Oct-14

16-Oct-14

N/A

N/A

N/A

9-Jun-14

28-Jun-14

22-Jun-14

20-Sep-14

10-Jul-14

N/A

6.920

6.920

6.920

6.920

6.920

N/A

20-May-14

11-Jun-14

26-May-14

10-Sep-14

22-Jun-14

N/A

0.366

0.423

0.649

0.461

0.438

PIER
2nd Lift
Height (m)
1st Lift
Height (m)

12-May-14

25-May-14

8-May-14

4-Sep-14

31-May-14

PILE CAP (Pier & Abut.)

9-Oct-14

4-May-14

13-May-14

4/30/2014

27-Aug-14

20-May-14

F/P & BLINDING

2-Oct-14

27-Apr-14

7-May-14

22-Apr-14

20-Aug-14

14-May-14

BIT. PAINTING

PREVIOUS

RENARDET S.A. & PARTNERS

PREVIOUS
MONTH

THIS MONTH

Page 11

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

9. MSE Walls Progress Schedule


MSE WALLS FOUNDATION AT APPROACH 1
as of 31 OCTOBER 2014

LOCATION (LHS)
Elevation

El. 20.40

El. 21.20

FROM

TO

22+702.653

22+760

22+760

22+825

22+825

22+840

22+840

22+880

22+880

22+908.387

22+908.387 22+969.478
22+969.478

23+000

23+000

23+025

23+025

23+070

23+070

23+140

El. 22.00

23+140

El. 22.80
El. 22.00

23+164.573

23+164.573 23+237.536
23+237.536 23+270.762

PREVIOUS

RENARDET S.A. & PARTNERS

DATE

Elevation

FOUNDATION
/BLINDING

2-Oct-14
3-Oct-14
30-Sep-14
1-Oct-14
13-Jul-14
14-Jul-14
6-Jul-14
13-Jul-14
10-Aug-14
11-Aug-14
3-Jul-14
5-Jul-14
4-Aug-14
5-Aug-14
20-Jul-14
21-Jul-14
17-Jul-14
18-Jul-14
30-Jun-14
1-Jul-14
16-Jun-14
17-Jun-14
23-Jun-14
24-Jun-14
17-Jun-14
18-Jun-14
P R E V IO US
M ON T H

El. 20.40

El. 21.20

El. 22.00

El. 22.80

El. 22.00

LOCATION (RHS)
FROM

TO

22+718.936

22+810

22+810

22+893.032

22+893.032 22+976.294
22+976.294

23+040

23+040

23+088.046

23+088.046

23+130

23+130

23+191.774

23+191.774 23+270.800

LOCATION (AB 1)
Elevation
El. 22.00

FROM

TO

23+270.762 (L) 23+270.800 (R )

DATE
FOUNDATION
/BLINDING

17-Sep-14
18-Sep-14
9-Aug-14
10-Aug-14
13-Aug-14
14-Aug-14
18-Aug-14
19-Aug-14
26-Jul-14
27-Jul-14
21-Jul-14
22-Jul-14
7-Jul-14
10-Jul-14
26-Jun-14
27-Jun-14

DATE
FOUNDATION
/BLINDING

26-Jun-14
27-Jun-14

THIS MONTH

Page 12

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

MSE WALL FOUNDATIONS PROGRESS AT APPROACH 2


as of 31 OCTOBER 2014

LOCATION (LHS)
Elevation

El. 23.30

FROM

TO

23+508.239

23+520

23+520

23+580.877

23+580.877

23+650

15-Sep-14
16-Sep-14
20-Aug-14
21-Aug-14
26-Aug-14
27-Aug-14

23+650

23+735

1-Sep-14

23+735

23+790

2-Sep-14
19-Sep-14
20-Sep-14

23+790

23+827.635

El. 24.10

El. 24.90

LOCATION (AB 2)

DATE
FOUNDATION
/BLINDING

23+827.635 23+949.895

Elevation
El. 23.30

TO

15-Sep-14
16-Sep-14

23+508.239 (L) 23+508.197 (R)

LOCATION (RHS)
Elevation
El. 23.30

El. 24.10

P R E V IO US
M ON T H

PREVIOUS

FROM

DATE
FOUNDATION
/BLINDING

DATE
FOUNDATION
/BLINDING

FROM

TO

23+508.197

23+607.634

23+607.634

23+740

23+740

23+950.153

8-Sep-14
9-Sep-14
22-Sep-14
23-Sep-14

THIS MONTH

MSE WALL PANELS FIXING AT APPROACH 2


as of 31 OCTOBER 2014
ELEV.
34.500
33.700
32.900
32.100
31.300
30.500
29.700
28.900
28.100
27.300
26.500
25.700
24.900
24.100
23.300

ELEV.
33.700
32.900
32.100
31.300
30.500
29.700
28.900
28.100
27.300
26.500
25.700
24.900
24.100
23.300

LHS (AB 2), from Sta. 23+508.239 to Sta. 23+949.895


23+520

23+580.877

29-Oct-14 29-Oct-14
13-Oct-14 13-Oct-14
25-Sep-14 25-Sep-14
-

23+650

23+703

26-Sep-14 26-Sep-14
-

23+750

23+827.635

23+949.895

AB 2 Face

RHS (AB 2), from Sta. 23+508.197 to Sta. 23+950.153


23+690
23+740 23+950.153
16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14
30-Sep-14 30-Sep-14 9-Oct-14
-

2 3 +5 0 8 .2 3 9 ( L)
2 3 +5 0 8 .19 7 ( R )23+607.634

RENARDET S.A. & PARTNERS

Page 13

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

MSE WALL PANELS FIXING @ APPROACH 1


as of 31 OCTOBER 2014
LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762
ELEV.
34.800
34.000
33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400

22+825
-

22+840

22+880

22+908.38 22+969.47

22-Sep-14 22-Sep-14 22-Sep-14


3-Sep-14 3-Sep-14 3-Sep-14
28-Aug-14 28-Aug-14 28-Aug-14
-

22+991

23+084

20-Oct-14
16-Sep-14
29-Oct-14 29-Oct-14 4-Sep-14
21-Sep-14 17-Sep-14 27-Aug-14
11-Sep-14 24-Aug-14 9-Aug-14
28-Aug-14
-

23+164.57 23+237.53 23+270.76


19-Oct-14
18-Oct-14
20-Sep-14
9-Sep-14
4-Sep-14
26-Aug-14
18-Aug-14
13-Aug-14
28-Jul-14
-

33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400

22+810
-

22+893.03 22+976.29
19-Oct-14
23-Sep-14
4-Sep-14
-

23-Oct-14
25-Sep-14
18-Sep-14
26-Aug-14
-

PREVIOUS

RENARDET S.A. & PARTNERS

RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800

ELEV.

1-Oct-14
24-Sep-14
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
-

23+088.04 23+191.77 23+270.80

2 3 +2 7 0 .8 0 0
(R )

20-Oct-14
18-Oct-14
20-Sep-14
8-Sep-14
21-Aug-14
-

20-Oct-14
18-Oct-14
20-Sep-14
8-Sep-14
18-Aug-14
-

30-Sep-14
24-Sep-14
18-Sep-14
13-Sep-14
31-Aug-14
18-Aug-14
6-Aug-14
24-Jul-14
13-Jul-14
-

28-Sep-14
24-Sep-14
19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-

28-Sep-14
24-Sep-14
19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-

P R E V IO US
M ON T H

30-Sep-14
27-Sep-14
13-Sep-14
2-Sep-14
24-Aug-14
13-Aug-14
9-Aug-14
-

AB 1 Face
2 3 +2 7 0 .7 6 2
( L)

23+035

1-Oct-14
24-Sep-14
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
13-Jul-14
-

THIS MONTH

Page 14

10. Box Culverts Progress Schedule


NO.

STATION

1
LHS
RHS
RHS
2

21+260
3 cells - 2.0 x 1.5
Block 1
3 cells - 2.0 x 1.5
Block 2
3 cells - 2.0 x 1.5
Block 3
3 cells - 2.0 x 1.5
21+485
1 cell - 2.0 x 1.5
Block 1a
1 cell - 2.0 x 1.5
Block 1b
1 cell - 2.0 x 1.5
Block 2a
1 cell - 2.0 x 1.5
Block 2b
1 cell - 2.0 x 1.5
Block 2C
1 cell - 2.0 x 1.5
21+838 2 x 4 cells (8) - 2.0 x 1.5
Block 1a
1 x 4 cells - 2.0 x 1.5
Block 1b
1 x 4 cells - 2.0 x 1.5
Block 2
1 x 4 cells - 2.0 x 1.5
Block 3
1 x 4 cells - 2.0 x 1.5
Block 4a
1 x 4 cells - 2.0 x 1.5
Block 4b
1 x 4 cells - 2.0 x 1.5
Block 5
1 x 4 cells - 2.0 x 1.5
Block 6
1 x 4 cells - 2.0 x 1.5
21+972.4 11 x 4 cel l s (44) - 3.0 x 2.0
Block 1
1 x 4 cells - 3.0 x 2.0
Block 2
1 x 4 cells - 3.0 x 2.0
Block 3
1 x 4 cells - 3.0 x 2.0
Block 4
1 x 4 cells - 3.0 x 2.0
Block 5
1 x 4 cells - 3.0 x 2.0
Block 6
1 x 4 cells - 3.0 x 2.0
Block 7
1 x 4 cells - 3.0 x 2.0
Block 8
1 x 4 cells - 3.0 x 2.0
Block 9
1 x 4 cells - 3.0 x 2.0
Block 10
1 x 4 cells - 3.0 x 2.0
Block 11
1 x 4 cells - 3.0 x 2.0

LHS
RHS
3
LHS
RHS
LHS
RHS
4

LHS

TYPE & DIMENSION

BASE SLAB

WALL

TOP SLAB

LENGTH (m)

SKEW ( )

F/P &
BLINDING

Rebars

Concrete

Rebars

Concrete

Rebars

25.546
19.526
14.473
6.000
39.750
3.000
17.290
7.710
10.000
11.730
57.210
5.000
17.600
22.600
11.970
5.000
17.600
22.600
11.970
57.629
28.038
28.031
28.026
28.022
28.019
28.018
28.019
28.022
28.026
28.031
28.038

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

18-Oct-14
1-Jul-14
1-Jul-14
21-Oct-14
21-Jul-14
3-Jul-14
3-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
24-May-14
24-May-14
17-May-14
18-May-14
18-May-14
18-May-14
18-May-14
26-May-14
26-May-14
28-May-14
28-May-14

26-Oct-14
31-Aug-14
31-Aug-14
25-Oct-14
4-Sep-14
4-Sep-14
20-Aug-14
10-Sep-14
10-Sep-14
23-Sep-14
5-Jun-14
9-Jul-14
25-May-14
12-Jul-14
29-May-14
31-Jul-14
10-Jun-14
9-Aug-14
15-Jun-14
17-Aug-14
19-Jun-14

26-Oct-14
31-Aug-14
31-Aug-14
25-Oct-14
5-Sep-14
5-Sep-14
20-Aug-14
12-Sep-14
12-Sep-14
24-Sep-14
5-Jun-14
10-Jul-14
25-May-14
13-Jul-14
29-May-14
31-Jul-14
10-Jun-14
10-Aug-14
15-Jun-14
18-Aug-14
19-Jun-14

31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
18-Oct-14
18-Oct-14
24-Oct-14
24-Jun-14
3-Aug-14
3-Jun-14
5-Aug-14
8-Jun-14
12-Aug-14
1-Jul-14
25-Aug-14
7-Jul-14
14-Sep-14
20-Jul-14

31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
19-Oct-14
19-Oct-14
25-Oct-14
24-Jun-14
4-Aug-14
3-Jun-14
6-Aug-14
8-Jun-14
13-Aug-14
1-Jul-14
26-Aug-14
8-Jul-14
14-Sep-14
20-Jul-14

31-Aug-14
31-Aug-14
25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
18-Oct-14
18-Oct-14
24-Oct-14
15-Jul-14
13-Aug-14
23-Jun-14
18-Aug-14
2-Jul-14
27-Aug-14
23-Jul-14
9-Sep-14
4-Aug-14
24-Sep-14
2-Sep-14

Concrete

Bituminous
Paint (2 Coats)

31-Aug-14 1-Sep-14
31-Aug-14 1-Sep-14
25-Oct-14 25-Oct-14
13-Oct-14
13-Oct-14
30-Oct-14
19-Oct-14
19-Oct-14
25-Oct-14
16-Jul-14 16-Aug-14
14-Aug-14 8-Sep-14
23-Jun-14 8-Sep-14
19-Aug-14 1-Oct-14
2-Jul-14
1-Oct-14
28-Aug-14 1-Oct-14
24-Jul-14 5-Oct-14
10-Sep-14
5-Aug-14
25-Sep-14
3-Sep-14 25-Sep-14

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

NO.

RHS

RHS

5
LHS
RHS
LHS
RHS
LHS
RHS
6

STATION

TYPE & DIMENSION

Block 12
1 x 4 cells - 3.0 x 2.0
Block 13
1 x 4 cells - 3.0 x 2.0
Block 14
1 x 4 cells - 3.0 x 2.0
Block 15
1 x 4 cells - 3.0 x 2.0
Block 16
1 x 4 cells - 3.0 x 2.0
Block 17
1 x 4 cells - 3.0 x 2.0
Block 18
1 x 4 cells - 3.0 x 2.0
Block 19
1 x 4 cells - 3.0 x 2.0
Block 20
1 x 4 cells - 3.0 x 2.0
Block 21
1 x 4 cells - 3.0 x 2.0
Block 22
1 x 4 cells - 3.0 x 2.0
21+972.4 11 x 4 cells - 3.0 x 2.0
Block 23
1 x 4 cells - 3.0 x 2.0
Block 24
1 x 4 cells - 3.0 x 2.0
Block 25
1 x 4 cells - 3.0 x 2.0
Block 26
1 x 4 cells - 3.0 x 2.0
Block 27
1 x 4 cells - 3.0 x 2.0
Block 28
1 x 4 cells - 3.0 x 2.0
Block 29
1 x 4 cells - 3.0 x 2.0
Block 30
1 x 4 cells - 3.0 x 2.0
Block 31
1 x 4 cells - 3.0 x 2.0
Block 32
1 x 4 cells - 3.0 x 2.0
Block 33
1 x 4 cells - 3.0 x 2.0
2 x 4 cells (8) - 2.0 x 2.0
22+655
(9 cells)
1 cell - 2.0 x 2.0
Block 1
1 x 4 cells - 2.0 x 2.0
Block 2
1 x 4 cells - 2.0 x 2.0
Block 3
1 x 4 cells - 2.0 x 2.0
Block 4
1 x 4 cells - 2.0 x 2.0
Block 5
1 x 4 cells - 2.0 x 2.0
Block 6
1 x 4 cells - 2.0 x 2.0
Block 7
1 x 4 cells - 2.0 x 2.0
Block 8
1 x 4 cells - 2.0 x 2.0
Block 9
1 cell - 2.0 x 2.0
Block 10
1 cell - 2.0 x 2.0
Block 11
1 cell - 2.0 x 2.0
Block 12
1 cell - 2.0 x 2.0
23+492 1 x 4 cells (4) - 3.0 x 2.0
(5 cells)
1 cell - 3.0 x 2.0

RENARDET S.A. & PARTNERS

LENGTH (m)

SKEW ( )

21.015
21.010
21.006
21.003
21.001
21.000
21.001
21.003
21.006
21.010
21.015
57.629
6.635
6.782
6.819
7.217
7.975
8.571
9.267
9.949
10.260
10.262
10.265
95.482

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
45 R

9.675
32.711
32.711
20.315
19.035
32.711
32.711
10.95
25.03
32.711
32.711
4.960
79.065

45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
15 R

BASE SLAB

WALL

TOP SLAB

F/P &
BLINDING

Rebars

Concrete

Rebars

Concrete

Rebars

Concrete

Bituminous
Paint (2 Coats)

10-Aug-14
27-Jul-14
27-Jul-14
25-Jul-14
16-Jun-14
16-Jun-14
12-Jun-14
12-Jun-14
8-Jun-14
8-Jun-14
8-Jun-14
30-Jun-14
24-Jun-14
11-Sep-14
29-Jun-14
24-Jun-14
28-Jun-14
29-Jun-14
-

25-Aug-14
22-Sep-14
12-Oct-14
23-Aug-14
27-Jul-14
14-Sep-14
24-Oct-14
16-Sep-14
29-Sep-14
1-Sep-14
25-Jun-14
6-Aug-14
21-Jul-14
12-Oct-14
27-Jul-14
28-Aug-14
20-Aug-14
3-Aug-14
-

26-Aug-14
22-Sep-14
12-Oct-14
23-Aug-14
27-Jul-14
15-Sep-14
24-Oct-14
16-Sep-14
30-Sep-14
2-Sep-14
25-Jun-14
7-Aug-14
21-Jul-14
13-Oct-14
28-Jul-14
28-Aug-14
23-Aug-14
4-Aug-14
-

2-Sep-14
29-Sep-14
15-Oct-14
8-Sep-14
14-Aug-14
23-Sep-14
30-Oct-14
21-Oct-14
1-Oct-14
21-Sep-14
30-Jul-14
1-Sep-14
17-Aug-14
22-Oct-14
13-Sep-14
24-Sep-14
2-Oct-14
2-Oct-14
-

3-Sep-14
29-Sep-14
15-Oct-14
8-Sep-14
14-Aug-14
24-Sep-14
30-Oct-14
21-Oct-14
1-Oct-14
21-Sep-14
30-Jul-14
2-Sep-14
18-Aug-14
22-Oct-14
14-Sep-14
26-Sep-14
3-Oct-14
3-Oct-14
-

1-Oct-14
18-Oct-14
26-Oct-14
18-Sep-14
3-Sep-14
14-Oct-14
30-Oct-14
21-Oct-14
30-Sep-14
16-Sep-14
1-Sep-14
17-Aug-14
22-Oct-14
13-Sep-14
24-Sep-14
2-Oct-14
2-Oct-14
-

1-Oct-14
19-Oct-14
26-Oct-14
19-Sep-14
4-Sep-14
15-Oct-14
30-Oct-14
21-Oct-14
30-Sep-14
17-Sep-14
2-Sep-14
18-Aug-14
22-Oct-14
14-Sep-14
26-Sep-14
3-Oct-14
3-Oct-14
-

25-Sep-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
13-Oct-14
-

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

NO.

LHS
RHS
LHS
RHS
7
LHS
RHS
8
LHS

RHS
9
LHS
RHS
10
LHS
RHS

STATION

TYPE & DIMENSION

LENGTH (m)

SKEW ( )

Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8

1 x 4 cells - 3.0 x 2.0


1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0

6.457
31.546
31.546
7.982
7.039
31.546
31.546
5.525

15 R
15 R
15 R
15 R
15 R
15 R
15 R
15 R

23+756.5
Block 1
Block 2
Block 3a
Block 3b
Block 4
23+997
Block 1
Block 2a
Block 2b
Block 3a
Block 3b
Block 4a
Block 4b
24+235
Block 1a
Block 1b
Block 2a
Block 2b
Block 2c
24+570
Block 1
Block 2a
Block 2b

1 cell - 2.0 x 1.5


1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5

67.550
12.090
20.180
14.430
8.700
12.090
70.268
16.128
4.933
13.860
16.300
4.942
7.848
6.197
59.106
15.566
15.000
8.900
15.600
4.020
51.953
25.846
13.500
12.587

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

F/P &
BLINDING

BASE SLAB
Rebars

Concrete

WALL
Rebars

24-Jun-14 9-Jul-14
9-Jul-14
30-Jul-14 30-Jul-14
24-Jun-14 14-Jul-14 15-Jul-14 3-Aug-14 3-Aug-14
9/172014 23-Sep-14 24-Sep-14 28-Sep-14 28-Sep-14
24-Jun-14 5-Aug-14 5-Aug-14 9 & 20/8/2014 9 & 23/8/2014
24-Jun-14 6-Aug-14 6-Aug-14 11 & 25/8/2014 11 & 26/8/2014
17-Sep-14 28-Sep-14 28-Sep-14 2-Oct-14 2-Oct-14
11-Oct-14 11-Oct-14
12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
11-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14
8-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
8-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14
10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14

RENARDET S.A. & PARTNERS

Rebars

Concrete

Bituminous
Paint (2 Coats)

16-Aug-14
21-Aug-14
1-Oct-14
28-Aug-14
31-Aug-14
11-Oct-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

17-Aug-14
21-Aug-14
2-Oct-14
28-Aug-14
1-Sep-14
11-Oct-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

6-Sep-14
6-Sep-14
18-Oct-14
4-7/9/2014
4-7/9/2014
18-Oct-14
24-Jul-14
24-Jul-14
28-Aug-14
24-Jul-14
24-Jul-14
31-Aug-14
31-Aug-14

12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14


12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14
10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14
14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
-

Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations.
PREVIOUS

Concrete

TOP SLAB

P R E V IO US
M ON T H

THIS MONTH

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

VEHICLE UNDERPASS PROGRESS SCHEDULE (BARREL) As of 31 OCTOBER 2014

NO.

STATION

TYPE & DIMENSION

1
LHS
RHS
2
LHS
RHS

21+300
Block 1
Block 2
24+300
Block 1
Block 2

2 cells - 4.0 x 3.0


2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0
2 cells - 4.0 x 3.0

LENGTH (m) SKEW ()

37.700
15.780
21.900
44.051
21.620
22.411

0
0
0
0
0
0

F/P &
BLINDING

BASE SLAB
Rebars

Concrete

9-Oct-14 26-Oct-14 26-Oct-14


22-Oct-14
-

WALL

TOP SLAB

Rebars

Concrete

Rebars

Concrete

Bituminous
Paint (2 Coats)

Concrete

Bituminous
Paint (2 Coats)

PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)

NO.

STATION

1 23+290, SOL-1
LHS Block 1
RHS Block 2
2 24+360, SOL-1
LHS Block 1
LHS Block 2
RHS Block 3
RHS Block 4
3 0+050, SOL-3
LHS Block 1
LHS Block 2
LHS Block 3
RHS Block 4

BASE SLAB

TYPE & DIMENSION

LENGTH (m)

SKEW
()

F/P &
BLINDING

Rebars

Concrete

1 cells - 4.0 x 4.0


1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0
1 cells - 4.0 x 4.0

59.614
9.000
20.777
22.777
7.000
83.223
17.721
17.721
17.721
30.000

0
0
0
0
0
0
0
0
0
0
0
0
0

15-Sep-14
-

1-Oct-14
-

1-Oct-14
-

PREVIOUS

RENARDET S.A. & PARTNERS

PREVIOUS
MONTH

WALL
Rebars

Concrete

TOP SLAB
Rebars

19-Oct-14 19-Oct-14 30-Oct-14 30-Oct-14


-

THIS MONTH

11. Progress Status of Utility Crossing Ducts


S.
NO.

4A

10

11

12

13

14

15

16

17

18

19

20

DRAWING

PIPE
CHAINAGE

NO.

Stages

LEFT
CCC/FQI/IR/06
MIDDLE
SERVICE ROAD-3
RIGHT
LEFT
CCC/FQR/IR/11
MIDDLE
SOL-2
RIGHT
LEFT
CCC/FQR/IR/10
MIDDLE
SOL-3
RIGHT
LEFT
CCC/FQR/WA/0
MIDDLE
5 SR-1
RIGHT
LEFT
CCC/FQI/SL/01 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/01 MIDDLE
RIGHT
LEFT
CCC/FQI/IR/01 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/02 MIDDLE
RIGHT
LEFT
CCC/FQI/IR/02 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/03 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/04 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/05 MIDDLE
RIGHT
LEFT
CCC/FQI/IR/03 MIDDLE
RIGHT
CCC/FQI/IR/04 LEFT
JUNCTION
MIDDLE
CROSSING
RIGHT
CCC/FQI/IR/05 LEFT
JUNCTION
MIDDLE
CROSSING
RIGHT
LEFT
CCC/FQI/EL/06 MIDDLE
RIGHT
LEFT
CCC/FQI/WA/02
MIDDLE
JUNCTION
RIGHT
LEFT
CCC/FQI/WA/01 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/07 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/13 MIDDLE
RIGHT
LEFT
CCC/FQI/EL/08 MIDDLE
RIGHT

NO.
OF

SETOUT/
EXCV/BE INSTALL CONCRE BACKFIL

ATION

DIA TYPE WAYS


0+030

200

UPVC

0+150

300

UPVC

0+300

200

UPVC

0+600

300

UPVC

21+160

150

UPVC

21+360

150

UPVC

21+460

300

21+660

TE

LING

RFI REF.
LAYING

CONCRETE

BACKFILL

9/24/14

9/24/14

10/18/14

UTL-LAY- 104 UTL-CON-131A

5/15/14
6/11/14

5/15/14
6/11/14

5/18/14
6/12/14

6/12/14
7/10/14

UTL-LAY- 81 UTL-CON- 65 UTL-BF- 01


UTL-LAY- 104 UTL-CON- 83 UTL-BF- 20

UPVC

5/19/14
6/14/14

5/19/14 5/20/14
14/06/14 6/14/14

6/4/14
6/21/14

UTL-LAY- 87 UTL-CON- 66 UTL-BF- 03


UTL-LAY- 108 UTL-CON- 84 UTL-BF- 21

UPVC

5/19/14
6/15/14

5/19/14
6/15/14

5/20/14
6/15/14

5/31/14

150

UTL-LAY- 85 UTL-CON- 63 UTL-BF- 02


UTL-LAY- 107 UTL-CON- 85

21+780

300

UPVC

5/20/14
6/15/14

5/20/14
6/15/14

5/25/14
6/15/14

6/4/14
7/8/14

UTL-LAY- 86 UTL-CON- 64 UTL-BF- 05


UTL-LAY- 109 UTL-CON- 87 UTL-BF- 23

21+880

150

UPVC

5/25/14
6/16/14

5/25/14
6/16/14

5/25/14
6/17/14

6/4/14
7/10/14

UTL-LAY- 90 UTL-CON-68 UTL-BF- 07


UTL-LAY- 111 UTL-CON- 88 UTL-BF- 28

22+260

150

UPVC

6/17/14
7/20/14

6/17/14
7/20/14

6/18/14
7/21/14

7/9/14
7/27/14

UTL-LAY- 112 UTL-CON- 89 UTL-BF- 33


UTL-LAY- 131 UTL-CON- 106UTL-BF-44

22+510

150

UPVC

6/19/14
7/20/14

6/19/14
7/20/14

6/19/14
7/21/14

7/6/14
7/17/14

UTL-LAY- 114 UTL-CON- 92 UTL-BF- 31


UTL-LAY- 132 UTL-CON- 107UTL-BF-46

22+520

200

UPVC

6/19/14
7/20/14

6/19/14
7/20/14

6/19/14
7/21/14

7/5/14
7/17/14

UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30


UTL-LAY- 133 UTL-CON- 108UTL-BF-45

22+520 LHS

200

UPVC

22+587 LHS

200

UPVC

22+760

150

UPVC

5/26/14
6/11/14

5/26/14
6/11/14

5/26/14
6/11/14

6/8/14
7/22/14

UTL-LAY- 88 UTL-CON- 69 UTL-BF- 08


UTL-LAY-106 UTL-CON- 81 UTL-BF-26

23+008 LHS

300

UPVC

23+020

900

RC

6/16/14
7/8/14

6/16/14
7/8/14

6/16/14
7/9/14

7/20/14
7/27/14

UTL-LAY- 102 UTL-CONUTL-BF-19


UTL-LAY- 125 UTL-CON-99 UTL-BF-42

23+060

150

UPVC

5/25/14 5/25/14
11/06/201 6/11/14

5/26/14
6/11/14

6/14/14
6/23/14

UTL-LAY- 91 UTL-CON- 71 UTL-BF- 06


UTL-LAY- 105 UTL-CON- 82 UTL-BF- 25

5/27/14

5/27/14

5/27/14

6/17/14

UTL-LAY- 92 UTL-CON- 72 UTL-BF- 09

23+210

150

UPVC

4
5/28/14

5/28/14

5/28/14

6/17/14

UTL-LAY- 93 UTL-CON- 70 UTL-BF- 10

23+240

150

UPVC

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

S.
NO.

DRAWING

PIPE
CHAINAGE

NO.

21

CCC/FQI/EL/09

22

CCC/FQI/EL/10

23

CCC/FQI/WA/03

23A

24

CCC/FQI/EL/11

25

CCC/FQI/WA/04

26

CCC/FQI/IR/07

27

CCC/FQI/EL/12

28

CCC/FQI/EL/14

29

CCC/FQI/IR/08

30

CCC/FQI/EL/15

31

CCC/FQI/EL/16

32

CCC/FQI/IR/09

33

CCC/FQI/EL/17

34

CCC/FQI/NAW.2

35

CCC/FQI/NAW.3

36

CCC/FQI/NAW.4

37

CCC/FQI/OMAN
TEL.1

38

CCC/FQI/OMAN
TEL.2

39

CCC/FQI/SL/03
Rev A

40

CCC/FQI/SL/04

41

CCC/FQI/SL/02

Stages
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT

NO.
OF

SETOUT/
EXCV/BE INSTALL CONCRE BACKFIL

ATION

DIA TYPE WAYS

TE

LING

RFI REF.
LAYING

CONCRETE

BACKFILL

23+560

150

UPVC

5/29/14
7/30/14

23+820

150

UPVC

5/29/14
7/14/14

6/2/14
7/14/14

6/2/14
7/14/14

6/17/14
8/20/14

UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15


UTL-LAY- 124 UTL-CON- 102UTL-BF- 36

23+900

600

RC

5/29/14
7/14/14

6/2/14
7/14/14

6/2/14
7/15/14

6/17/14
8/20/14

UTL-LAY-97 UTL-CON- 76 UTL-BF- 13


UTL-LAY- 127 UTL-CON- 101UTL-BF- 38

UPVC

8/10/14 8/11/14
10/27/14
5/29/14 6/2/14
8/6/14
8/6/14

8/11/14 8/26/14
10/27/14
6/3/14
6/19/14
8/9/14
8/13/14

UTL-LAY-149AUTL-CON- 120A
UTL-BF- 58
UTL-LAY- 206 UTL-CON- 153
UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14
UTL-LAY- 134-R1
UTL-CON- 109A
UTL-BF- 53

UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16


UTL-LAY-140 R1
UTL-CON-114UTL-BF- 52

23+960

5/29/14
8/12/14

5/29/14
7/30/14

6/17/14
8/26/14

UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11


UTL-LAY-142 UTL-CON- 115UTL-BF-48

23+980

150

UPVC

24+000

600

RC

24+020

300

UPVC

6/3/14
8/11/14

6/4/14
8/11/14

6/4/14
8/19/14

6/23/14
8/26/14

24+120

150

UPVC

6/4/14
7/23/14

6/5/14
7/24/14

6/10/14
8/19/14

23/06/201 UTL-LAY- 100 UTL-CON- 79 UTL-BF- 17


8/26/14 UTL-LAY-139 UTL-CON-112-R1
UTL-BF- 47

24+220

150

UPVC

6/9/14
8/6/14

6/9/14
8/6/14

6/10/14
8/6/14

6/23/14
8/26/14

UTL-LAY- 101 UTL-CON- 80 UTL-BF- 18


UTL-LAY-138-R1
UTL-CON-111-B
UTL-BF- 56

7/5/14

7/5/14

7/5/14

8/19/14

UTL-LAY- 123 UTL-CON- 94 UTL-BF- 39R1

24+340

300

UPVC

24+520

150

UPVC

7/16/14 7/16/14 7/17/14


UTL-LAY- 130 UTL-CON- 105
10/27/14 10/27/14 10/27/14 10/27/14 UTL-LAY-190R1
UTL-CON- 148UTL-BF- 72

24+820

150

UPVC

9/14/14 9/14/14 10/14/14 10/20/14 UTL-LAY- 166 UTL-CON-125UTL-BF-81


10/27/14 10/27/14 10/27/14
UTL-LAY- 205 UTL-CON- 150

24+960

300

UPVC

9/16/14 9/20/14
10/27/14 10/27/14 10/27/14

25+160

150

UPVC

21+870

100

UPVC

5/21/14
6/16/14

5/21/14
6/16/14

5/21/14
6/18/14

6/4/14
7/10/14

UTL-LAY- 89 UTL-CON- 67 UTL-BF- 04


UTL-LAY- 110 UTL-CON- 90 UTL-BF- 29

23+580

100

UPVC

5/29/14
7/10/14

5/31/14
7/10/14

5/31/14
8/13/14

6/17/14
8/26/14

UTL-LAY- 96 UTL-CON- 74 UTL-BF- 12


UTL-LAY- 120 UTL-CONR1
95 UTL-BF- 49

24+720

100

UPVC

22+810

100

UPVC

7/21/14
8/8/14
9/16/14
7/7/14
8/12/14

8/4/14
8/9/14
9/16/14
7/8/14
8/13/14

8/5/14
8/9/14
9/16/14
7/8/14
8/14/14

0+140 SOL-3 100

UPVC

22+820

150

UPVC

22+990

150

UPVC

7/9/14
8/12/14
10/12/14
7/2/14
7/10/14
7/22/14
8/30/14

7/9/14
8/13/14
10/13/14
7/3/14
7/10/14
7/22/14
8/31/14

7/9/14
8/14/14 9/25/14
10/12/14
7/3/14
7/14/14
7/23/14 8/20/14
9/14/14 9/30/14

22+080

150

UPVC

RENARDET S.A. & PARTNERS

UTL-LAY- 173
UTL-LAY- 203 UTL-CON- 149

9/22/14

8/15/14

UTL-LAY-137-R1
UTL-CON- 118
UTL-LAY-148AUTL-CON- 117UTL-BF- 57
UTL-LAY-172 UTL-CON- 126
UTL-LAY-103AUTL-CON-98
UTL-LAY-150 UTL-CON-122A
UTL-BF- 37A

UTL-LAY- 116 UTL-CON-100


UTL-LAY-151 UTL-CON-121UTL-BF-81
UTL-LAY-187 UTL-CON-137
UTL-LAY-122 UTL-CON-93R1
UTL-LAY-126 UTL-CON-103
UTL-LAY-136 UTL-CON-110UTL-BF- 50
UTL-LAY-158 UTL-CON-96 UTL-BF-64

Page 20

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

44

NO.

Stages

LEFT
CCC/FQI/EL/19 MIDDLE
RIGHT
LEFT
CCC/FQI/SL/01 MIDDLE
RIGHT
LEFT
CCC/FQI/SD/07 MIDDLE
RIGHT
LEFT
CCC/FQI/SD/08 MIDDLE
RIGHT

23+740

150

24+850

150

21+500

450

21+560

450

CCC/FQI/SD/09 MIDDLE 21+620

450

RIGHT
LEFT
46

CCC/FQI/SD

ATION

DIA TYPE WAYS

LEFT
45

SETOUT/
EXCV/BE INSTALL CONCRE BACKFIL

MIDDLE 23+400

600

RIGHT

9/7/14
UPVC
2
9/15/14
10/27/14
9/16/14
UPVC 2-4WAY 10/14/14
10/27/14
10/2/14

TE

LING

RFI REF.
LAYING

CONCRETE

BACKFILL

9/7/14
9/15/14
10/28/14
9/17/14
10/18/14
10/27/14
10/2/14

10/14/14 10/27/14 UTL-LAY-162 UTL-CON-124UTL-BF-69


UTL-LAY-162R1
10/27/14 10/30/14 UTL-LAY-207 UTL-CON-152UTL-BF-92
9/30/14 10/16/14 UTL-LAY-174 UTL-CON-127UTL-BF-83
10/14/14
UTL-LAY-188 UTL-CON-138
10/27/14
UTL-LAY-204 UTL-CON-151
10/2/14
UTL-LAY-184 UTL-CON-135

10/2/14

10/2/14

10/2/14

UTL-LAY-164 R1
UTL-CON-134

10/2/14

10/2/14

10/2/14

UTL-LAY-185 UTL-CON-136

CONC PIPE

43

CHAINAGE

NO.
OF

CONC PIPE

42

PIPE

CONC PIPE

42

DRAWING

CONC PIPE

S.
NO.

Buraimi Road (SOL-3)


S.
NO.
1

2A

DRAWING

PIPE
CHAINAGE

NO.

Stages

LEFT
CCC/FQI/Omant
MIDDLE
el/02
RIGHT
LEFT
CCC/FQI/SL/13 MIDDLE
RIGHT
LEFT
CCC/FQI/Omant
MIDDLE
el/02
RIGHT
LEFT
CCC/FQI/SL/14 MIDDLE
RIGHT

NO.
OF

CCC/FQI/SL/15

CCC/FQI/SL/16

CCC/FQI/SL/17

ATION

DIA TYPE WAYS


9/4/14
0+138.348

110

UPVC

0+130

150

UPVC

0+140

150

UPVC

0+415

150

UPVC

Setting Out
, Excavation
MIDDLE and Laying
150
of UPVC
Street
RIGHT
Lighting
LEFT
Existing
MIDDLE Road front 150
RIGHT SOL-3 Ch.
Existing
LEFT
MIDDLE Road front 150
RIGHT SOL-3 Ch.
LEFT

SETOUT/
EXCV/BE INSTALL CONCRE BACKFIL

RENARDET S.A. & PARTNERS

9/16/14
UPVC

UPVC

UPVC

9/17/14

TE

LING

RFI REF.
LAYING

CONCRETE

BACKFILL

9/28/14

UTL-LAY-159-B
UTL-CON-132

9/30/14

10/18/14 UTL-LAY-167 UTL-CON-128UTL-BF-78

Page 21

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

SERVICE ROAD-01
S.
NO.
1

DRAWING

PIPE
CHAINAGE

NO.

Stages

LEFT
MIDDLE
RIGHT
LEFT
CCC/FQI/SL/06 MIDDLE
RIGHT
LEFT
CCC/FQI/SL/08 MIDDLE
RIGHT
LEFT
CCC/FQI/OMAN
MIDDLE
TEL/04
RIGHT
LEFT
CCC/FQI/OMAN
MIDDLE
TEL/05
RIGHT
LEFT
CCC/FQI/OMAN
MIDDLE
TEL/06
RIGHT
CCC/FQI/SL/07

NO.
OF

DIA TYPE WAYS


0+530

150

UPVC

0+060

150

UPVC

0+600

100

UPVC

0+472.8

100

UPVC

0+550

100

UPVC

0+648.103

100

UPVC

SETOUT/
EXCV/BE INSTALL CONCRE BACKFIL

ATION

TE

LING

RFI REF.
LAYING

CONCRETE

BACKFILL

SERVICE ROAD-02
S.
NO.

DRAWING

PIPE
CHAINAGE

NO.

CCC/FQI/SL/10

CCC/FQI/SL/12

Stages

NO.
OF

DIA TYPE WAYS

LEFT
MIDDLE 1+050
RIGHT
LEFT
MIDDLE 1+530
RIGHT
LEFT
MIDDLE
RIGHT

150

UPVC

150

UPVC

SETOUT/
EXCV/BE INSTALL CONCRE BACKFIL

ATION

TE

LING

RFI REF.
LAYING

CONCRETE

BACKFILL

SERVICE ROAD-03
S.
NO.

DRAWING

PIPE
CHAINAGE

NO.

CCC/FQI/SL/23

CCC/FQI/SL/24

CCC/FQI/SL/08

Stages
LEFT
MIDDLE 0+020
RIGHT
LEFT
MIDDLE 0+120
RIGHT
LEFT
MIDDLE
RIGHT

RENARDET S.A. & PARTNERS

NO.
OF

DIA TYPE WAYS


150

UPVC

SETOUT/
EXCV/BE INSTALL CONCRE BACKFIL

ATION

TE

LING

RFI REF.
LAYING

CONCRETE

BACKFILL

Page 22

12. Project Strip Chart

FQI PROJECT - PROGRESS STRIP CHART FOR ROAD WORKS


SUBGRADE IN CUT

21+150-21+500

COMPLETED

As of Oct 2014

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Subgra de
La yr 9
La yr 8
La yr 7
La yr 6
La yr 5
La yr 4
La yr 3
La yr 2

21+280

21+300

21+320

21+340

21+360

21+380

21+400

21+420

21+440

21+460

21+480

21+500

21+780

21+800

21+820

21+840

21+860

21+880

21+900

21+920

21+940

21+960

21+980

22+000

21+260

21+240

21+220

21+200

21+180

21+160

21+140

21+120

21+100

21+080

21+060

21+040

21+020

21+000

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
Subgra de

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

21+500-22+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
s ub gra de
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
s ub gra de

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

21+760

21+740

21+720

21+700

21+680

21+660

21+640

21+620

21+600

21+580

21+560

21+540

21+520

21+500

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

22+000-22+500

22+500

22+480

22+460

22+440

22+420

22+400

22+380

22+360

22+340

22+320

22+300

22+280

22+260

22+240

22+220

22+200

22+180

22+160

22+140

22+120

22+100

22+080

22+060

22+040

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

As of Oct 2014

SUB GRADE LAYER

22+020

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

22+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

LHS

COMPLETED

SUBGRADE

RHS

5th layer of rock


layer 15

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
SUB G
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

23+000

22+980

22+960

22+940

22+920

22+900

22+880

22+860

22+840

22+820

22+800

22+780

22+760

22+740

22+720

22+700

22+680

22+660

22+640

22+620

22+600

22+580

22+560

22+540

4th layer roock soil

22+520

22+500

22+500-23+000

4th layer roock soil

layer 15
5th layer of rock

Page 25

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

As of Oct 2014

23+260

23+280

23+300

23+320

23+340

23+360

23+380

23+400

23+420

23+440

23+460

23+480

23+500

24+760

23+780

23+800

23+820

23+840

23+860

23+880

23+900

23+920

23+940

23+960

23+980

24+000

23+240

23+220

23+200

23+180

23+160

23+140

rock siol layer no 3


layer no 28

23+120

23+100

23+080

23+060

23+040

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 11st layer of rock siol
layer 2
2nd layer of rock siol
layer 3
3rd layer of rock siol
layer 4
4th layer of rock siol
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

23+020

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
4th layer of Rock siol
Layer 3
3rd layer of Rock siol
Layer 2
2nd layer of Rock siol
EMBANKMENT Layer 11st layer of Rock siol
BED PREPRATION
OGL SURVEY

23+000

LHS
RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 15 of embankment
layer 7
5th layer of rock soil
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

LHS

23+000-23+500

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
5th layer of rock soil
Layr 8
layer 15 of embankment
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

COMPLETED

layer no 28
rock siol layer no 3

RENARDET S.A. & PARTNERS

24+740

24+720

24+700

24+680

24+660

24+640

24+620

24+600

24+580

24+560

24+540

24+520

24+500

23+500-24+000

Page 26

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

24+000-24+500

COMPLETED

As of Oct 2014

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

24+400

24+420

24+900

24+920

24+500

24+380
24+880

25+000

24+360
24+860

24+480

24+340
24+840

24+980

24+320
24+820

24+460

24+300
24+800

24+960

24+280
24+780

24+440

24+260
24+760

24+940

24+240
24+740

24+220

24+200

24+180

24+160

24+140

24+120

24+100

24+080

24+060

24+040

24+020

24+000

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
24+500-25+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

24+720

24+700

24+680

24+660

24+640

24+620

24+600

24+580

24+560

24+540

24+520

24+500

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

Page 27

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

COMPLETED

25+000-25+500

As of Oct 2014

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm

LHS

Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5

RHS

layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

Page 28

25+500

25+480

25+460

25+440

25+420

25+400

25+380

25+360

25+340

25+320

25+300

25+280

25+260

25+240

25+220

25+200

25+180

25+160

25+140

25+120

25+100

25+080

25+060

25+040

25+020

25+000

OGL SURVEY

13. Financial Status of Payments


Sl. No.

DESCRIPTION

PAYMENT FOR
THE MONTH OF

GROSS
AMOUNT
(R.O.)

GROSS
NET AMOUNT
AMOUNT
CLAIMED
CLAIMED (R.O.)
(R.O.)

DATE
SUBMITTED

AMOUNT
DATE CERTIFIED
CERTIFIED (R.O.)

AMOUNT
RECEIVED
(R.O.)

DATE
PAYMENT DUE

DATE
PAYMENT
RECEIVED

PAYMENT APPLICATION No. 1


(ADVANCE PAYMENT)

Dec-13

1,648,225

1,648,225

1,648,225

23-Nov-13

1,648,225

29-Jan-14

1,648,225

28-Mar-14

6-Feb-14

PAYMENT APPLICATION No. 2

Jan-14

2,291,277

643,052

514,442

12-Feb-14

514,442

02-Apr-14

513,608

30-May-14

10-Apr-14

PAYMENT APPLICATION No. 3

Feb&Mar-14

2,808,644

517,367

504,147

06-Apr-14

434,917

03-May-14

414,674

30-Jun-14

6-Aug-14

PAYMENT APPLICATION No. 4

Apr-14

3,315,692

507,048

417,900

08-May-14

407,538

05-Jun-14

395,257

2-Aug-14

6-Aug-14

PAYMENT APPLICATION No. 5

May-14

4,109,460

793,768

650,802

05-Jun-14

445,708

04-Jul-14

374,172

31-Aug-14

6-Aug-14

PAYMENT APPLICATION No. 6

Jun-14

4,293,764

184,304

382,116

15-Jul-14

382,116

16-Jul-14

418,721

12-Sep-14

9-Sep-14

PAYMENT APPLICATION No. 7

Jul&Aug-14

5,749,546

1,455,782

1,164,626

14-Sep-14

1,123,023

18-Sep-14

1,123,023

15-Nov-14

27-Oct-14

PAYMENT APPLICATION No. 8

Sep-14

6,857,752

1,108,206

928,167

21-Oct-14

PAYMENT APPLICATION No. 9

Oct-14

10

PAYMENT APPLICATION No. 10

Nov-14

11

PAYMENT APPLICATION No. 11

Dec-14

12

PAYMENT APPLICATION No. 12

Jan-15

13

PAYMENT APPLICATION No. 13

Feb-15

14

PAYMENT APPLICATION No. 14

Mar-15

15

PAYMENT APPLICATION No. 15

Apr-15

16

PAYMENT APPLICATION No. 16

May-15

17

PAYMENT APPLICATION No. 17

Jun-15

6,857,752

6,857,752

6,210,425

TOTAL AMOUNT (R.O.)

4,955,969

4,887,679

14. Details of Equipment Available At Site


Sl.
No.
1

DESCRIPTION

CCC

HIRED

TOTAL
AVAILABLE
AT SITE

COMPRESSOR

AIR COMPRESSOR

MILLER WELDING MECHINE

GENERATOR

CRANES

CRANES 30 TON / 25 TON / 70 TON


VEHICLES H.D.

4
-

DIESEL TANKER

FLAT TRAILER

10

HIAB TRUCK

11

P/MOVER + TIPPING TRAILER

12

TIPPER TRUCKS

11

15

13

WATER TANKER 5000 & 10000 GAL

14

EARTH MOVING PLANT

15

BOBCAT

16

EXCAVATOR

17

JCB 4CX / 3CX

18

SHOVEL / WHEEL LOADER

19

DOZER D9N/D8R

20

TELEHANDLER

21

CIVIL ENGINEERING EQUIPMENT

22

GREENE STABILIZER PLANT

23

DY NAPAC S/ROLLER

24

E/WORK ROLLER

25

MOTOR GRADER

26

TITAN PAVER MACHINE

27

TY RE / PTR ROLLER

28

PAVER MACHINE

29

1
-

L. D. VEHICLES & TRUCKS

30

DY NA TRUCK

31

MAINTENANCE TRUCKS

32

ASHOK LEY LAND BUS 55 SEAT

33

TOY OTA COASTER BUS 24 S

34

TOY OTA COROLLA/CIVIC/Y ARIS

35

TOY OTA PICKUP/ISUZU

36
37
38

Total

12

12

13

NISSAN PATHFINDER/X-TRAIL

TOY OTA LAND CRUISER/FORTUNER

65

112

47

2014
Feb-14

Mar-14

Apr-14

May-14

Jun-14

Jul-14

47

68

87

95

93

47
33
33

115
55
88

202
66
154

297
68
222

390
77
299

107
68
458
86
385

110
87
545
88
473

Aug-14 Sep-14

108
95
640
100
573

102
93
733
109
682

Jan-15 Feb-15 Mar-15

Apr-15

May-15 Jun-15

100
107
840
112
794

98
110
950

87
108
1,058

82
102
1,160

66
87
1,445

53
82
1,527

110

100

107

68

79
100
1,260

77
98
1,358

41
79
1,606

Jul-15

Aug-15

Sep-15

Oct-15

Total

1500
77
1,683

66
1,749

53
1,802

41
1,843
794

PLANNED TOTAL PER MONTH

108
102

ACTUAL TOTAL PER MONTH

100

98

REVISED PLANNED TOTAL PER MONTH

87

88

93

87
82

79

77

79

82

87

77

86

87

Dec-14

77

66

68

66

53

55

60

66

68

80

41

47

53
41

33

40

20

PROJECT MONTHS

Oct-15

Sep-15

Aug-15

Jul-15

Jun-15

May-15

Apr-15

Mar-15

Feb-15

Jan-15

Dec-14

Nov-14

Oct-14

Sep-14

Aug-14

Jul-14

Jun-14

May-14

Apr-14

Mar-14

Feb-14

Jan-14

No. of EQUIPMENT

Nov-14

112

109
95

93

95

100

102

108
100

107

110

120

Oct-14

98

PLANNED TOTAL PER MONTH


REVISED PLANNED TOTAL PER MONTH
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH
ACTUAL CUMULATIVE

2015

Jan-14

15. Details of Manpower Available At Site


EXPATRIATES

NATIONALS

TOTAL

STAFF & LABOUR


BUDGET

ACTUAL

BUDGET

ACTUAL

BUDGET

ACTUAL

A - MANAGEMENT ***

B - COMMERCIAL STAFF *

C - ENGINEERS

D - FOREMAN & C/H

21

23

23

29

1 - SKILLED CRAFTSMEN

143

65

208

2 - SEMI-SKILLED/UNSKILLED

506

53

559

E - ENGINEERING TECHNICIANS

**

10

F - DAILY RATED EMPLOYEES :

TOTAL AS OF END OF THE MONTH

711

G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor on Company Work :

29

127

838

2013
Jan-14
34

Feb-14
186

Mar-14
375

Apr-14
586

May-14
791

23

36

50

52

57

11

57

222

425

Sep-14
793

Oct-14
701

Nov-14
480

Dec-14
381

Jan-15
269

Feb-15
246

Mar-15
307

Apr-15
307

May-15
305

Jun-15
149

Jul-15

Aug-15

Sep-15

Oct-15

Total
8301

565

756

754

750

700

652

667

554

516

387

297

276

365

271

135

92

51

7788

59

59

60

61

63

61

61

57

51

47

44

35

30

63

84

84

83

78

72

74

61

57

43

33

31

40

30

15

10

851

858

854

854

764

541

442

326

297

354

351

340

179

627

840

838

833

778

725

741

616

573

429

330

306

406

301

150

102

57

6,923

7,365

7,691

7,988

8,342

8,693

9,033

9,212

68

291

715

1,353

2,202

3,052

3,910

4,764

5,618

6,383

550

581

603

691

709

756

734

773

767

18

26

46

49

54

57

64

69

68

70

71

340

391

596

630

657

748

773

825

802

843

838

340

731

1,327

1,957

2,614

3,362

4,135

4,960

5,762

6,605

7,443

6851
592
0

7443

541

340

351

297

326

354

442

425

391
340

400

179

222

300

200

Oct-15

0
Jun-15

Sep-15

0
May-15

Aug-15

0
Apr-15

Jul-15

0
Jan-15

PROJECT MONTHS

Mar-15

0
Dec-14

Oct-14

Sep-14

Aug-14

Jul-14

Jun-14

May-14

Feb-14

Jan-14

Dec-13

Feb-15 0

0
Nov-14

11

57

100

8651
9,212

764

500

862
9215

838

854
843

854

858
825

851

914

REVISED - PLANNED - ( DIRECT + INDIRECT )

ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )

773

848
638
657
Apr-14

748
630
Mar-14

596

Aug-14
794

365

800

No. of Men

Jul-14
799

11

PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )

600

848

2015

Jun-14
792

322

900

700

638

802

PLANNED TOTAL PER MONTH - ( DIRECT )


REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )
PLANNED TOTAL PER MONTH - ( INDIRECT )
REVISED - PLANNED TOTAL PER MONTH-(INDIRECT)
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )
REVISED - PLANNED - ( DIRECT + INDIRECT )
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH - ( DIRECT )
ACTUAL TOTAL PER MONTH - ( INDIRECT )
ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )
ACTUAL CUMULATIVE

2014

Dec-13
6

16. QA/QC Reports

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 35

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 36

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 37

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 38

17. Status of Material Approvals


Re fe re nce No.

MAR No.

Mate rial/ Work

Manufacture r/Supplie r/
Subcontractor

MOTC
Submitte Re marks
Via Re narde t
Comme nt
d To
By MOTC
Le tte r Re f. No.
Submitte d
s date d
Date

Re narde t
Le tte r
Date d

CCC/FQI/REN/MAS/001

MAS/CCC/FQI/BBC/001

Bituminous Base Course

Tarmac Zawawi LLC Oman

22/12/2013

Renardet

APPROVED

01/04/2014

SO/FQI/CCC/087

07/04/2014

CCC/FQI/REN/MAS/002

MAS/CCC/FQI/GTI/002

Geotechnical Investigation

Swissboring & Company LLC

26/12/2013

Renardet

APPROVED

02/02/2014

SO/FQI/CCC/015

12/02/2014

CCC/FQI/REN/MAS/003

MAS/CCC/FQI/MSE/003

MSE Wall System

Freyssinet Arabian Sea LLC

26/12/2013

Renardet

APPROVED

02/02/2014

SO/FQI/CCC/014

12/02/2014

CCC/FQI/REN/MAS/004

MAS/CCC/FQI/PVC/004

UPVC Pipes

Amiantit Oman

26/12/2013

Renardet

APPROVED

09/02/2014

SO/FQI/CCC/019

18/02/2014

CCC/FQI/REN/MAS/005

MAS/CCC/FQI/HDPE/005

HDPE Pipes & Fittings

Amiantit Oman

26/12/2013

Renardet

APPROVED

09/02/2014

SO/FQI/CCC/020

18/02/2014

CCC/FQI/REN/MAS/006

MAS/CCC/FQI/PW/006

Piling Works

APCC LLC

26/01/2014

Renardet

APPROVED

19/02/2014

SO/FQI/CCC/026

25/02/2014

CCC/FQI/REN/MAS/007

MAS/CCC/FQI/MC/007

Bitnuminous Prime Coat (MC-70)

Emirates Lube Oil Co. (Muscat)

30/01/2014

Renardet

APPROVED

09/03/2014

SO/FQI/CCC/069

27/03/2014

CCC/FQI/REN/MAS/008

MAS/CCC/FQI/RS/008

Reinforcing Steel

Muscat Steel Industries

02/02/2014

Renardet

APPROVED

20/03/2014

SO/FQI/CCC/063

24/03/2014

CCC/FQI/REN/MAS/009-1

MAS/CCC/FQI/PT/009-1

Post Tensioning Work - Anchorage

Freyssinet Arabian Sea LLC

22/02/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/089

14/04/2014

CCC/FQI/REN/MAS/009-2

MAS/CCC/FQI/PT/009-2

Post Tensioning Work - Duct

Freyssinet Arabian Sea LLC

22/02/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/090

14/04/2014

CCC/FQI/REN/MAS/009-3

MAS/CCC/FQI/PT/009-3

Post Tensioning Work - Strand

Freyssinet Arabian Sea LLC

22/02/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/091

14/04/2014

CCC/FQI/REN/MAS/010A-Rev.1

MAS/CCC/FQI/PB/010A-Rev.1

Bridge Pot Bearings

Al Ammar International

07/05/2014

Renardet

Not Approved

---

REN/FQI/CCC/111

13/05/2014

CCC/FQI/REN/MAS/010B

MAS/CCC/FQI/PB/010B

Bridge Pot Bearings

Building Supplies & Services

11/05/2014

Renardet

APPROVED

25/05/2014

REN/FQI/CCC/122

31/05/2014

CCC/FQI/REN/MAS/011

MAS/CCC/FQI/HDPE/011

HDPE Water Pipes

Amiantit Oman

22/02/2014

Renardet

APPROVED

09/03/2014

SO/FQI/CCC/038

11/03/2014

CCC/FQI/REN/MAS/012

MAS/CCC/FQI/RCBC/012

Single cell Precast Box Culvert

Amiantit Oman

22/02/2014

Renardet

APPROVED

25/03/2014

SO/FQI/CCC/064

26/03/2014

CCC/FQI/REN/MAS/013

MAS/CCC/FQI/BP/013

Bituminous Paint Material (Rubberized)

Al Inma Building Materilal LLC

02/03/2014

Renardet

Not Approved

20/04/2014

REN/FQI/CCC/105

05/05/2014

CCC/FQI/REN/MAS/013A

MAS/CCC/FQI/BP/013A

Bituminous Paint Material (Rubberized)

Henkel Polybit Industries Ltd.

17/06/2014

Renardet

APPROVED

03/07/2014

REN/FQI/CCC/146

13/07/2014

CCC/FQI/REN/MAS/014A-Rev.1

MAS/CCC/FQI/EJ/014A-Rev.1

Bridge Expansion Joints

Al Ammar International

07/05/2014

Renardet

APPROVED

20/05/2014

REN/FQI/CCC/123

31/05/2014

CCC/FQI/REN/MAS/015

MAS/CCC/FQI/RC/015

Reinforced Concrete Pipe (450,600,700mm dia)

Amiantit Oman

02/03/2014

Renardet

APPROVED

23/03/2014

SO/FQI/CCC/077

02/04/2014

CCC/FQI/REN/MAS/016 B

MAS/CCC/FQI/WS/016 B

Water Stop G EE-25

Sika LLC Oman

25/03/2014

Renardet

APPROVED

16/04/2014

REN/FQI/CCC/099

28/04/2014

CCC/FQI/REN/MAS/017

MAS/CCC/FQI/TW/017

Telephone Works

National Telephone Services

12/03/2014

Renardet

APPROVED

17/03/2014

SO/FQI/CCC/082

03/04/2014

CCC/FQI/REN/MAS/019

MAS/CCC/FQI/EW/019

Electrical Works

United Engineering Projects

22/03/2014

Renardet

APPROVED

29/05/2014

REN/FQI/CCC/131

16/06/2014

CCC/FQI/REN/MAS/020

MAS/CCC/FQI/EC/020

MV & LV Cables

United Engineering Projects

19/03/2014

Renardet

APPROVED

27/03/2014

SO/FQI/CCC/083

03/04/2014

CCC/FQI/REN/MAS/021

MAS/CCC/FQI/PS/021

Package Substation

United Engineering Projects

22/03/2014

Renardet

----

CCC/FQI/REN/MAS/021A

MAS/CCC/FQI/PS/021A

Package Substation

Voltamp Energy SAOG

16/09/2014

Renardet

CCC/FQI/REN/MAS/022

MAS/CCC/FQI/LL/022

Street Lighting Luminaries

Majees Lighting Industries LLC

27/03/2014

Renardet

APPROVED

14/08/2014

REN/FQI/CCC/158

17/08/2014

22/05/2014

Renardet

APPROVED

14/08/2014

REN/FQI/CCC/157

17/08/2014

CANCELLED

----

CCC/FQI/REN/MAS/023A

MAS/CCC/FQI/LP/023A

Street Lighting Poles (Mid-Hinged)

Al Babtain Power &


Telecomunication Co., S.Arabia

CCC/FQI/REN/MAS/024

MAS/CCC/FQI/FP/024

Street Lighting Feeder Pillar

Stars Light LLC

27/03/2014

Renardet

APPROVED

08/06/2014

REN/FQI/CCC/130

16/06/2014

CCC/FQI/REN/MAS/025

MAS/CCC/FQI/JS/025

Joint Sealant (Polyseal)

Al Inma Building Materilal LLC

27/03/2014

Renardet

APPROVED

16/04/2014

REN/FQI/CCC/100

28/04/2014

CCC/FQI/REN/MAS/026

MAS/CCC/FQI/GT/026

Geotextile

Modern East Trading & Con.

21/05/2014

Renardet

No meet the
HDS

---

REN/FQI/CCC/119

27/05/2014

CCC/FQI/REN/MAS/026A

MAS/CCC/FQI/GT/026A

Geotextile (Bonar NW16)

Bonar Technical Fabrics

15/06/2014

Renardet

APPROVED

14/08/2014

REN/FQI/CCC/159

17/08/2014

CCC/FQI/REN/MAS/027

MAS/CCC/FQI/MS/027

Masterseal 915
(formerly known as Masterflow 410 Plus)

OBasf The Chemical Company

10/08/2014

Renardet

Required
latest test
Reports

---

REN/FQI/CCC/166

24/08/2014

CCC/FQI/REN/MAS/028

MAS/CCC/FQI/GG/028

Gully Gratings & Frames

RBA Ferro Industries PVT. Ltd.

17/08/2014

Renardet

APPROVED

25/09/2014

REN/FQI/CCC/192

15/10/2014

CCC/FQI/REN/MAS/030

MAS/CCC/FQI/FLC/030

MasterRoc FLC 100 (Cable Grout Admixture)

BASF-The Chemical Company

02/10/2014

Renardet

CCC/FQI/REN/MAS/032

MAS/CCC/FQI/GR/032

Guardrails

GK Wire Industries LLC

29/10/2014

Renardet

18. Engineers Comments


The Planned progress as per the revised Project Execution Program for the month of
October is 8.49% and the Actual progress is 6.20% which shows 2.29% of delay
during the month of October. The actual cumulative progress up to October is
45.39% against Planned Cumulative Progress of 48.35% showing a lagging of
3.00% . Though four working days are reduced during the month due to holidays,
the delayed progress must be recovered in the coming month.
MSE Wall works are commenced on Abutment No. 2 side, and progressing.
Superstructure works are in progress in the Bridge and bottom slab of Bridge No. 1
is casted.

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

19. Details of Correspondence during the month


S.
No.

Date
Received

From

1
10/1/2014

CCC

Reference
No

FQI-REN-TR258

Subject

CCC

10/2/2014

CCC

10/18/2014

CCC

10/19/2014

CCC

10/19/2014

CCC

10/20/2014

CCC

20/10/201

CCC

10/22/2014

CCC

10/29/2014

CCC

11

10/29/2014

CCC

FQIRENARDET/264 Hijra New Year


Access gate for Flyover Box
FQIGirder -Test Certification of
RENARDET/265 Materials
Shop Drawing for
Pedestrian underpass
FQI-REN-TRsection Elavation
278
Reinforcement Details
Additional Item - Friction
FQIslab for Barrier above MSE
RENARDET/269 Wall
CCC/FQI/REN/ Approval Guardrails MAR .
MAS/032
NO. MAS/CCC/FOI/GR/032

12

10/30/2014

CCC

FQIProject monthly progress


RENARDET/262 Videos & Pictures

10

Remarks

FQIRENARDET/258 Project Road Signs

10/2/2014

Reference
No.

Shop Drawing for 4 way #


150mm upvc Street Lighting
Ducts at SOL-02 CH.0+130

Reply
date

FQIMonthly Progress Report


RENARDET/257 No.9
Dimension & Details of 3
FQI-REN-TRCell Box Culvert 3(2.0*1.5)
261
Skew Angle 0 @ ch.21+260

10/18/2014

Approved

FQIConfirmation of vethal
RENARDET/261 Instruction ( CVI)
Bar Bending Schedule for
Vehicular underpass at
FQI-REN-TRch.21+300 block (1-2) LHS267
RHS

11/2/2014

Approved as
Noted

RENARDET S.A. & PARTNERS

REN/FQI/CC
10/28/2014 C/193

11/1/2014

Approved

Page 41

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Muscat Side Approach getting Ready

20. PROGRESS PHOTOGRAPHS

RENARDET S.A. & PARTNERS

Page 42

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Abutment No. 2 side Approach Works in Progress

Scaffolding for LHS Flyover Superstructure in Progress

RENARDET S.A. & PARTNERS

Page 43

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Installation of Pot Bearings in Progress

Concrete Pouring in Box Girder Bottom Slab

RENARDET S.A. & PARTNERS

Page 44

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Field Tests of Earthwork Filling in Progress

Vehicular Underpass Works in Progress

RENARDET S.A. & PARTNERS

Page 45

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Earthworks for Soar Airport Approach Road in Progress

Asphalt Wearing Course in Sohar Airport Approach Road

RENARDET S.A. & PARTNERS

Page 46

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Completed View of 9 Cells Box Culvert

Status of 8 Cells Box Culvert Progress

RENARDET S.A. & PARTNERS

Page 47

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

44 Cells Box Culvert Works in Progress

Pedestrian Underpass Works in Progress

RENARDET S.A. & PARTNERS

Page 48