Vous êtes sur la page 1sur 55

SULTANATE OF OMAN

MINISTRY OF TRANSPORT AND COMMUNICATIONS


DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT
MUSCAT

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT


TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 7
JULY 2014

CONSULTANT:

CONTRACTOR:

RENARDET S.A. & PARTNERS CONSULTING


ENGINEERS LLC.
P.O. Box 579, Muscat, P.C. 100,
Sultanate of Oman

CONSOLIDATED CONTRACTORS CO. LLC


P.O. Box 614,
Muscat, P.C. 100,
Sultanate of Oman

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

Table of Contents

S. No.

Description

Page No.

1.

Project Particulars

2.

Scope of Work

3.

Typical Cross Sections

4.

Site visits/ Meetings

Engineers Site Staff

6.

Progress Review

7.

Financial Status

22

8.

Contractors Resources

23

9.

QA/ QC Reports

27

10.

Engineers Comments

31

11.

Project Correspondence

32

12.

Progress Photographs

36

RENARDET S.A. & PARTNERS

Page 1

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

Project Particulars
Client:

Ministry
of
Transport
&
Communications
P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.

Consultant:

Renardet S.A & Partners L.L.C.


P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.

Contractor:

Consolidated Contractors Company


L.L.C.
P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.

Project Commencement Date:

30.10.2013

Mobilization Period:

60 Days

Construction Period:

548 Days

Completion date:

29.06.2015

Original Contract Value:


(Including Contingencies)

R.O. 17,884,403.000

Amount of Contingencies:

R.O. 1,402,155.613

Original Contract Value:


(Excluding Contingencies)

R.O. 16,482,247.387

Planned physical progress


cumulative up to end of July 2014

42.37%

Achieved physical progress


cumulative up to end of July 2014

RENARDET S.A. & PARTNERS

22.55%

Page 2

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:
Removal of existing asphalt surface, extension of existing embankment and earthwork to achieve
the designed profile and gradient.
Removal of existing drainage structures and construction of new ones including protection works
as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and removal/disposal of existing street light
poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous base
course and bituminous wearing course as per details on the construction drawings.
Installation of road side furniture (traffic signs, road marking etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items
(transformers etc.) as per the requirements of concerned authority.
Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and
irrigation) as per the requirements of concerned authorities.
Provision of ducts for future utilities as per the requirements of utility operator.
Construction of concrete safety barriers, fixing of guard rails and paving tiles.
Provision of traffic diversion in coordination with concerned authorities.

RENARDET S.A. & PARTNERS

Page 3

Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report July 2014

Page 4

Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report July 2014

Page 5

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

Site visits/ Meetings


S. No.

Details of Site Visit

Date

Final Outcome/ Decisions

Meeting
with
Director
of
Maintenance, Sohar Municipality for
the approval of MAS for Street
Lighting Luminaires.

01.07.2014

Director informed that the


Luminaires from M/s Majelite
Industries shall be approved.

Meeting
with
Director
of
Maintenance, Sohar Municipality for
the approval of MAS for Street
Lighting Luminaires.

08.07.2014

Director informed that the


Luminaires from M/s Majelite
Industries shall be approved.

Meeting with DGRs QS at Muscat


office.

17.07.2014

Invoice No. 5 was reviewed.

RENARDET S.A. & PARTNERS

Page 6

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

Engineers Site Staff


S.
Name
No.
1. Roberto Benigni

Designation

Date of
Joining

Head Supervision Projects

2.

Muneer Abdul

Resident Engineer

19.03.2014

3.

Hussein Shah

Material Engineer

04.01.2014

4.

Ernesto B. Paredes

Bridge Engineer

16.04.2014

5.

Sande H Tangaras

Civil Engineer

08.06.2014

6.

Danilo

Quantity Surveyor

19.06.2014

6.

Mohamed Safie

Land Surveyor

04.01.2014

7.

Aseef Iqbal

Site Inspector

10.02.2014

8.

Alaa Aldin Abdelfatah

Site Inspector

30.03.2014

9.

Walid Samy Abdoh Mostafa

Material Inspector

01.04.2014

Secretary

13.04.2014

10. Haneefa Mohmmed Al Zadjali

RENARDET S.A. & PARTNERS

Page 7

RENARDET S.A. & PARTNERS

% MONTHLY

Dec

MONTHLY PROGRESS

2013

Jan

CUMULATIVE PROGRESS

MONTHS

10

Jun

May

Apr

Mar

0.01

CL14 Org Plan Cum ulative %

Actual Cum ulative

0.01

Actual per Month

CL14 Org Plan per Month %

Dec

2013

0.28

0.26

0.28

0.25

Jan

CL14 Org Plan per Month %

2014

Jul
0.45

1.67

0.18

1.42

Feb

Aug
1.46

5.91

1.01

4.23

Mar

Sep
4.36

13.15

2.89

7.25

Apr

Oct
10.01

23.21

5.65

10.06

May

15.19

32.64

5.18

9.42

Jun

7.36

9.73

Jul

22.55

42.37

Nov
2014

Actual per Month

Dec
52.58

10.21

Aug

Jan
62.37

9.79

Sep

Apr

Feb
70.86

8.49

Oct

76.59

5.72

Nov

81.13

4.55

Dec

84.69

3.56

Jan

CL14 Org Plan Cumulative %

Mar

12

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMAN


MONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS

May
87.48

2.79

Feb

Jun
91.31

3.83

Mar

2015

Jul
94.86

3.55

Apr

Sep

Aug
98.33

1.67

Jun

100.00

2015

3.47

May

100.00

Jul

Actual Cumulative

Oct
100.00

Aug

100.00

Sep

0.00

20.00

40.00

60.00

80.00

Oct

% Cumulative
100.00

100.00

120.00

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 8

Feb

RENARDET S.A. & PARTNERS

Incidental
Construction

MSE walls

MEP Works &


Ducts

73,724

50,004

14,821

2,063,644

83,264

141,190

275,037

30,920

456,522

788,138

CUMULATIVE PROGRESS

MONTHLY PROGRESS

TOTAL

Drainage Works

Bituminous
Pavement
Concrete for
Box Culvert
/Underpas
Concrete for
Bridge

Structural
Excavation
Subbase &
Aggregate Base

Embankment

19,558

Clearing &
Removal of
Obstructions

74,043

56,423

Road Diversions

Budgeted
Man-Hrs

Description

Item

0.00
0.00

Actual

CL14 Plan %
Actual
CL14 Plan %

0.00
0.00
0.00
0.00
0.00
0.11
-

Actual

CL14 Plan %
Actual
CL14 Plan %

Actual

CL14 Plan %

Actual

CL14 Plan %

Actual

CL14 Plan %

Actual

Revised Plan

Actual Cum

0.01
0.01
-

Actual per Month

CL14 Org Plan Cum ulative %

Actual Cum ulative

Dec

2013

0.00

CL14 Plan %

Actual

CL14 Plan %

0.00

0.00

CL14 Plan %

Actual

Actual

0.00

Actual

CL14 Plan %

0.30

Dec

2013

CL14 Plan %

Plan/
Actual

CL14 Org Plan per Month %

100.000

4.03

6.84

13.33

1.50

22.12

38.19

3.57

2.42

0.72

3.59

0.95

2.73

Wtd.
%

0.28

0.26

0.28

0.25

Jan

0.28

0.25

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00
0.00

0.00

10.09

0.00

6.62

8.67

Jan

0.45

1.67

0.18

1.42

Feb

0.45

0.48

0.00

0.00

0.00

4.02
0.00

0.23

0.00

1.01
0.00

0.00

10.09

0.38

13.03

19.23

Feb

1.46

5.91

1.01

4.23

Mar

1.46

0.76

0.13

0.00

6.16

4.43

0.00

2.50

15.21
0.01
0.00

0.48

1.43

0.00

9.21
5.00
0.00

0.78

17.59

20.37

22.36

26.89

Mar

4.36

13.15

2.89

7.25

Apr

4.36

2.47

5.52

0.00

9.87

17.23

0.00

16.19

34.62
6.05
0.00

1.26

2.97

0.00

29.30
5.00
0.00

4.35

6.58

19.52

47.70

37.31

31.77

Apr

10.01

23.21

5.65

10.06

May

10.01

5.64

9.26

0.17

17.63

33.36

2.61

0.00

14.39

57.89
14.73
0.38

5.59

10.17

0.00

45.91
53.23
0.00

4.89

16.76

77.42

48.33

43.00

36.64

May

15.19

32.64

5.18

9.42

Jun

2014

15.19

12.48

13.38

0.79

25.69

49.13

4.98

0.00

13.24

69.26
18.14
1.21

14.93

23.65

0.00

56.90
62.16
0.00

29.38

69.96

48.33

44.11

41.51

Jun

2014

22.55

42.37

7.36

9.73

Jul

22.55

21.64

16.87

1.43

35.90

65.07

6.42

2.80

16.19

81.40
22.33
2.63

27.72

36.51

0.00

62.24
74.91
0.00

5.27

41.37

70.18

48.33

51.21

46.39

Jul

MANHOURS OVERALL PROJECT S-CURVE

52.58

10.21

Aug

30.78

5.65

80.79

62.37

9.79

Sep

39.87

13.41

93.82

43.85

4.23

3.42
17.87

83.46

63.06

83.38

51.47

0.08

26.27

11.07
0.00

67.94

66.60

48.33

56.13

Sep

64.59

58.64

48.33

51.26

Aug

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN

70.86

8.49

Oct

48.35

21.84

100.00

61.59

5.50

84.50

74.26

7.77

41.98

69.08

74.18

48.33

61.01

Oct

76.59

5.72

Nov

56.26

30.56

100.00

72.98

6.08

92.89

75.97

19.32

59.98

69.08

82.85

48.33

65.88

Nov

81.13

4.55

Dec

64.34

32.94

100.00

81.15

6.08

99.96

77.37

31.22

78.73

75.05

84.75

48.33

70.76

Dec

84.69

3.56

Jan

71.05

70.94

100.00

83.94

34.35

100.00

80.05

44.94

79.90

82.85

84.75

59.91

75.63

Jan

87.48

2.79

Feb

77.31

75.04

100.00

84.42

99.38

100.00

82.40

51.98

79.90

93.48

85.24

77.84

80.50

Feb

91.31

3.83

Mar

81.99

94.02

100.00

85.35

99.76

100.00

88.97

52.14

85.20

98.64

92.34

90.27

85.38

Mar

REV.:
0
PERIOD ENDING:

94.86

3.55

Apr

85.59

96.43

100.00

92.86

99.76

100.00

92.13

90.14

89.45

100.00

92.34

94.93

90.25

Apr

Jul-14

98.33

100.00

1.67

Jun

93.35

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

2015

3.47

May

88.93

100.00

100.00

96.39

100.00

100.00

98.55

90.14

92.60

100.00

98.36

100.00

Jun
100.00

2015
95.13

May

Jul

100.00

Jul

96.64

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Aug

100.00

Aug

98.27

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Sep

100.00

Sep

99.38

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Oct

100.00

Oct

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 9

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

Progress of Permanent Works


Sl.
No.

Description

Unit

BOQ Qty.

Actual
Qty.

% This
Month

% Last
Month

Clearing & Grubbing

M2

161,752

137,490

85.00%

85.00%

Removal of Trees

No.

956

656

68.62%

68.62%

Removal of Existing
Pavement
Removal of Reinforced
Concrete
Removal of Signboards

M3

24,000

13,500

56.25%

56.25%

M3

1,000

493.5

49.35%

0.32%

Nr.

60

15

25.00%

25.00%

Removal of Floodway Marker


posts

Nr.

400
Revised

200

50.00%

50.00%

M3

6,000

1,902

31.70%

31.70%

Removal of Drainage
Protection Works
Expandable Piles

No.

100.0%

100.0%

Working Piles

No.

110
Revised

95

86.36%

83.63%

10

MSE Panels - Precast

M2

13,030

4,742

36.39%

23.72%

832

22.61%

22.61%

938.4

20.40%

12.22%

4
5

Revised
11

RCC Drainage Pipes

LM

12

Steel Fixing

Tons

13

M3

17,200

4,139

24.06%

10.76%

14

Concrete Class 30 Box


Culverts
Concrete Class 15

M3

2,600

2,512

96.61%

81.3%

15

Precast NJB

6,400

2,209

34.51%

21.1%

RENARDET S.A. & PARTNERS

3,680
Revised
4,600
Revised

Page 10

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

PILE MONTHLY SCHEDULE (CASTING)


as of 31 JULY 2014

LOCATION

PILE NO.

CASTING

SETTING OUT

BORING,
REBARS, &
CONCRETE

INTEGRITY
TEST

LOAD TEST (Expendable


Piles)

EP 01
EP 02
EP 03
EP 04

3
2
1
4

26/3/2014
25/3/2014
25/3/2014
26/3/2014

26/3/2014
25/3/2014
25/3/2014
26/3/2014

7-8/5/2014
16-17/4/2014
5-6/4/2014
13-14/5/2014

LOAD TEST (Working


Piles)

P3R
P3R
P3R
P3R
P3R
P1R
P1R
P3R
P3R
P3R
P1R
P1R
P1R
P3R
P3L
P1R
P1R
P1R
P3L
P3L
P3L
P1R
P1L
P1L
P3L
P3L
P3L
P2R
P2R
P2R
P2L
P3L
P3L
P1L
P1L
P1L
P2L
P2L
P2L
P1L

85
87
83
81
79
63
65
86
84
82
68
66
61
80
28
62
67
69
26
30
32
64
6 WP
14
25
27
29
78
76
74
23 WP
24
31
8
10
12
17
18
22
7

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

7/4/2014
7/4/2014
8/4/2014
8/4/2014
8/4/2014
9/4/2014
9/4/2014
10/4/2014
10/4/2014
10/4/2014
12/4/2014
12/4/2014
9/4/2014
13/4/2014
13/4/2014
12/4/2014
14/4/2014
14/4/2014
15/4/2014
15/4/2014
15/4/2014
16/4/2014
16/4/2014
16/4/2014
17/4/2014
17/4/2014

8/4/2014
8/4/2014
9/4/2014
9/4/2014
9/4/2014
10/4/2014
10/4/2014
12/4/2014
12/4/2014
12/4/2014
13/4/2014
13/4/2014
13/4/2014
14/4/2014
14/4/2014
15/4/2014
15/4/2014
15/4/2014
16/4/2014
16/4/2014
16/4/2014
17/4/2014
17/4/2014
17/4/2014
20/4/2014
20/4/2014
20/4/2014
21/4/2014
21/4/2014
21/4/2014
22/4/2014
22/4/2014
22/4/2014
23/4/2014
23/4/2014
23/4/2014
24/4/2014
24/4/2014
24/4/2014
26/4/2014

23/4/2014
23/4/2014
23/4/2014
23/4/2014
23/4/2014
28/4/2014
28/4/2014
23/4/2014
23/4/2014
23/4/2014
28/4/2014
28/4/2014
28/4/2014
23/4/2014
28/4/2014
28/4/2014
28/4/2014
28/4/2014
28/4/2014
28/4/2014
28/4/2014
28/4/2014
11/5/2014
11/5/2014
28/4/2014
28/4/2014
28/4/2014
11/5/2014
11/5/2014
11/5/2014
14/6/2014
28/4/2014
28/4/2014
11/5/2014
11/5/2014
11/5/2014
14/6/2014
14/6/2014
14/6/2014
11/5/2014

30/4/2014 to 1/5/2014
1 - 2/6/2014
-

RENARDET S.A. & PARTNERS

19/4/2014
19/4/2014
19/4/2014
21/4/2014
21/4/2014
20/4/2014
22/4/2014
22/4/2014
22/4/2014
23/4/2014
23/4/2014
23/4/2014
24/4/2014

Page 11

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

LOCATION

PILE NO.

CASTING

SETTING
OUT

BORING,
REBARS, &
CONCRETE

INTEGRITY
TEST

LOAD TEST (Working Piles)

P1L
P1L
P1L
P2L
P2L
P2L
P2R
P2R
P2L
P2L
P2R
P2R
P2R
P2R
P5R
P5R
P5R
P5R
P5R
P5R
P5R
P5R
P5R
P5L
P5L
P5L
P5L
P5L
P5L
P5L
P5L
P5L
AB1 R
AB1 R
AB1 R
AB1 L
AB1 L
AB1 L
AB1 R
AB1 R
AB1 L
AB1 L
AB2 L
AB2 L
AB2 L
AB2 R
AB2 L
AB2 R
AB2 R

9
13
11
16
21
19
72
77
15
20
70
71
73
75
105
104
103
102
101
100
97
98
99
48 WP
49
50
42
44
46
43
45
47
56
58
60
1
3
5
57
59
2
4
51
53
55
106
54
108
110

41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89

24/4/2014
24/4/2014
26/4/2014
26/4/2014
26/4/2014
27/4/2014
27/4/2014
27/4/2014
28/4/2014
27/4/2014
28/4/2014
29/4/2014
29/4/2014
29/4/2014
4/5/2014
4/5/2014
4/5/2014
5/5/2014
5/5/2014
5/5/2014
6/5/2014
6/5/2014
6/5/2014
7/5/2014
7/5/2014
7/5/2014
10/5/2014
10/5/2014
10/5/2014
10/5/2014
10/5/2014
10/5/2014
12/5/2014
12/5/2014
12/5/2014
14/5/2014
14/5/2014
14/5/2014
13/6/2014
13/6/2014
15/5/2014
15/5/2014
19/5/2014
19/5/2014
19/5/2014
19/5/2014
20/5/2014
20/5/2014
20/5/2014

26/4/2014
26/4/2014
27/4/2014
27/4/2014
27/4/2014
28/4/2014
28/4/2014
28/4/2014
29/4/2014
29/4/2014
29/4/2014
30/4/2014
30/4/2014
30/4/2014
5/5/2014
5/5/2014
5/5/2014
6/5/2014
6/5/2014
6/5/2014
7/5/2014
7/5/2014
7/5/2014
8/5/2014
8/5/2014
8/5/2014
11/5/2014
11/5/2014
11/5/2014
12/5/2014
12/5/2014
12/5/2014
13/5/2014
13/5/2014
13/5/2014
15/5/2014
15/5/2014
15/5/2014
14/6/2014
14/6/2014
17/5/2014
17/5/2014
20/5/2014
20/5/2014
20/5/2014
20/5/2014
21/5/2014
21/5/2014
21/5/2014

11/5/2014
11/5/2014
11/5/2014
14/6/2014
14/6/2014
14/6/2014
11/5/2014
11/5/2014
14/6/2014
14/6/2014
11/5/2014
11/5/2014
11/5/2014
11/5/2014
18/5/2014
18/5/2014
18/5/2014
18/5/2014
18/5/2014
18/5/2014
18/5/2014
18/5/2014
18/5/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
21/5/2014
21/5/2014
21/5/2014
21/5/2014
21/5/2014
21/5/2014
21/5/2014
21/5/2014
21/5/2014
21/5/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014
3/6/2014

24/5/2014 to 25/5/2014
-

RENARDET S.A. & PARTNERS

Page 12

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

LOCATION

PILE NO.

CASTING

SETTING OUT

BORING,
REBARS, &
CONCRETE

INTEGRITY
TEST

LOAD TEST (Working


Piles)

AB2 L

52

90

21/5/2014

22/5/2014

3/6/2014

AB2 R

107

91

21/5/2014

22/5/2014

3/6/2014

AB2 R

109

92

21/5/2014

22/5/2014

3/6/2014

P4L

33

93

30/7/2014

31/7/2014

P4L

37

94

30/7/2014

31/7/2014

P4L

39

95

30/7/2014

31/7/2014

BRIDGE SUB-STRUCTURE PROGRESS SCHEDULE


As of 31 JULY 2014
SUB-STRUCTURE WORK PROGRESS (LHS)
AB1 L

P1L

P2L

P3L

P4L

P5L

AB2
L
-

N/A

N/A

2nd Lift

on-going

24-Jul-14

Height (m)

6.920

6.920

6.920

6.920

6.920

1st Lift

23-Jul-14

on-going

29-Jun-14

on-going

Height (m)

1.153

1.210

1.440

1.248

1.225

26-Jun-14

17-May-14

23-Jun-14

18-Jun-14

8-May-14

11-Jun-14

11-Jun-14

1-May-14

3-Jun-14

N/A

ACTIVITY
PEDESTAL

PIER

BIT. PAINTING

PILE CAP

F/P &
BLINDING

N/A

28-May14
17-May14
11-May14

SUB-STRUCTURE WORK PROGRESS (RHS)


AB1 R

P1R

P2R

P3R

P4R

P5R

AB2
R
-

N/A

N/A

2nd Lift

9-Jun-14

28-Jun-14

22-Jun-14

10-Jul-14

Height (m)

6.920

6.920

6.920

6.920

6.920

1st Lift

11-Jun-14

26-May-14

22-Jun-14

Height (m)

0.423

0.649

0.461

0.438

8-May-14

4/30/2014

22-Apr-14

ACTIVITY
PEDESTAL

PIER

20-May14
0.366

BIT. PAINTING

12-May14

PILE CAP

4-May-14

F/P &
BLINDING

N/A

27-Apr-14

PREVIOUS

RENARDET S.A. & PARTNERS

25-May14
13-May14
7-May-14

PREVIOUS
MONTH

31-May14
20-May14
14-May14

N/A

THIS
MONTH

Page 13

STATION

1
0+003 - 0+022
2
0+022 - 0+040
3
0+040 - 0+052
MH
0+043
4
0+052 - 0+070
5
0+070 - 0+100
6
0+100 - 0+104
MH
0+104
7
0+104 - 0+122
8
0+122 - 0+139
9
0+139 - 0+150
10
0+150 - 0+170
MH
0+165
11
0+170 - 0+182
12
0+182 - 0+200
13 0+200 - 0+213.5
14 0+213.5 - 0+225
MH
0+225
15
0+225 - 0+232
16
0+232 - 0+250
17
0+250 - 0+258
18
0+258 - 0+268
MH
0+268
TOTAL LENGTH (m) =
BALANCE (m) =

NO.

19.00
18.00
12.00
18.00
30.00
4.00
18.00
17.00
11.00
20.00
12.00
18.00
13.50
11.50
7.00
18.00
8.00
10.00
265.00
0.00

LENGTH
(m)

1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 2.0
1.0 x 1.5
1.0 x 1.5
1.0 x 1.5
1.0 x 1.5
-

TYPE (1 Cell) &


DIMENSION (m)

RENARDET S.A. & PARTNERS


PREVIOUS

13-Jul-14
28-May-14
15-Apr-14
5-Mar-14
2-Mar-14
10-May-14
10-May-14
10-May-14
5-Mar-14
2-Mar-14
19-May-14
19-May-14
24-Feb-14
28-May-14
28-May-14
10-Apr-14
23-Apr-14
13-Jul-14
-

F/P &
BLINDING

14-Jul-14
4-Jun-14
16-Apr-14
24-Mar-14
5-Mar-14
8-Jun-14
17-May-14
14-May-14
1-Apr-14
6-Mar-14
22-May-14
21-May-14
27-Feb-14
3-Jun-14
3-Jun-14
13-Apr-14
26-Apr-14
14-Jul-14
-

Rebars

P R E V IO US
M ON T H

14-Jul-14
4-Jun-14
16-Apr-14
24-Mar-14
5-Mar-14
8-Jun-14
17-May-14
14-May-14
1-Apr-14
6-Mar-14
22-May-14
21-May-14
27-Feb-14
3-Jun-14
3-Jun-14
13-Apr-14
26-Apr-14
14-Jul-14
-

Concrete

BASE SLAB

THIS MONTH

15-Jul-14
12-Jun-14
19-Apr-14
8-Apr-14
6-Mar-14
14-Jun-14
16-Jul-14
20-May-14
17-May-14
5-Apr-14
5-Apr-14
2-Jun-14
2-Jun-14
25-May-14
1-Mar-14
8-Jun-14
5-Jul-14
8-Jun-14
15-Apr-14
27-Apr-14
15-Jul-14
-

Concrete

WALL

15-Jul-14
12-Jun-14
19-Apr-14
8-Apr-14
6-Mar-14
14-Jun-14
16-Jul-14
20-May-14
17-May-14
5-Apr-14
5-Apr-14
2-Jun-14
2-Jun-14
25-May-14
1-Mar-14
8-Jun-14
5-Jul-14
8-Jun-14
15-Apr-14
27-Apr-14
15-Jul-14
-

Rebars

FALAJ RCBC PROGRESS SCHEDULE


(Chainage 23+411.400)
As of 31 JULY 2014

17-Jul-14
16-Jun-14
21-Apr-14
12-Apr-14
11-Mar-14
17-Jun-14
24-May-14
19-May-14
8-Apr-14
12-Apr-14
5-Jun-14
2-Jun-14
4-Mar-14
17-Jun-14
17-Jun-14
19-Apr-14
1-May-14
17-Jul-14
-

Rebars

17-Jul-14
16-Jun-14
21-Apr-14
12-Apr-14
11-Mar-14
17-Jun-14
24-May-14
19-May-14
8-Apr-14
12-Apr-14
5-Jun-14
2-Jun-14
4-Mar-14
17-Jun-14
17-Jun-14
19-Apr-14
1-May-14
17-Jul-14
-

Concrete

TOP SLAB

22-Jul-14
29-Jun-14
29-Apr-14
19-Apr-14
19-Mar-14
24-Jun-14
29-May-14
29-May-14
12-Apr-14
10-Apr-14
16-Jun-14
16-Jun-14
10-Mar-14
28-Jun-14
28-Jun-14
13-May-14
13-May-14
22-Jul-14
-

Bituminous
Paint (2 Coats)

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 14

21+260
Block 1
Block 2
21+485
Block 1a
Block 1b
Block 2a
Block 2b
21+838
Block 1a
Block 1b
Block 2
Block 3
Block 4a
Block 4b
Block 5
Block 6
21+972.4
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
Block 13
Block 14
Block 15
Block 16
Block 17
Block 18
Block 19
Block 20
Block 21
Block 22

1
LHS
RHS
2

RENARDET S.A. & PARTNERS

RHS

LHS

RHS

LHS

RHS

LHS

RHS

LHS

STATION

NO.

3 cells - 2.0 x 1.5


3 cells - 2.0 x 1.5
3 cells - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
2 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
11 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0

TYPE & DIMENSION

43.039
19.526
23.493
49.750
3.000
17.290
7.710
21.730
57.210
5.000
22.590
22.580
7.000
5.000
22.590
22.580
7.000
57.629
28.038
28.031
28.026
28.022
28.019
28.018
28.019
28.022
28.026
28.031
28.038
21.015
21.010
21.006
21.003
21.001
21.000
21.001
21.003
21.006
21.010
21.015

LENGTH (m)

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

SKEW ( )

1-Jul-14
1-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
24-May-14
24-May-14
17-May-14
18-May-14
18-May-14
18-May-14
18-May-14
26-May-14
26-May-14
28-May-14
28-May-14
27-Jul-14
27-Jul-14
24-Jul-14
16-Jun-14
16-Jun-14
12-Jun-14
12-Jun-14
8-Jun-14
8-Jun-14
8-Jun-14

F/P &
BLINDING

Rebars

24-Jun-14
3-Jun-14
8-Jun-14
1-Jul-14
8-Jul-14
20-Jul-14
30-Jul-14

Concrete

WALL

5-Jun-14 24-Jun-14
10-Jul-14
25-May-14 3-Jun-14
13-Jul-14
29-May-14 8-Jun-14
31-Jul-14
10-Jun-14 1-Jul-14
15-Jun-14 7-Jul-14
19-Jun-14 20-Jul-14
27-Jul-14
25-Jun-14 30-Jul-14

5-Jun-14
9-Jul-14
25-May-14
12-Jul-14
29-May-14
31-Jul-14
10-Jun-14
15-Jun-14
19-Jun-14
27-Jul-14
25-Jun-14

Concrete

Rebars

BASE SLAB

RCBC PROGRESS SCHEDULE (BARREL)


As of 31 JULY 2014

15-Jul-14
23-Jun-14
2-Jul-14
23-Jul-14
-

16-Jul-14
23-Jun-14
2-Jul-14
24-Jul-14
-

Concrete

TOP SLAB
Rebars

Bituminous
Paint (2 Coats)

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 15

RENARDET S.A. & PARTNERS

RHS

LHS

RHS

LHS

RHS

LHS

RHS

LHS

RHS

LHS

Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8

Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
23+492

21+972.4
Block 23
Block 24
Block 25
Block 26
Block 27
Block 28
Block 29
Block 30
Block 31
Block 32
Block 33
22+655

RHS

STATION

NO.

11 x 4 cells - 3.0 x 2.0


1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
2 x 4 cells - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0

TYPE & DIMENSION

6.457
31.546
31.546
7.982
7.039
31.546
31.546
5.525

9.675
32.711
32.711
20.315
19.035
32.711
32.711
10.95
25.03
32.711
32.711
3.130
79.065

57.629
6.635
6.782
6.819
7.217
7.975
8.571
9.267
9.949
10.260
10.262
10.265
95.482

LENGTH (m)

15 R
15 R
15 R
15 R
15 R
15 R
15 R
15 R

45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
15 R

0
0
0
0
0
0
0
0
0
0
0
0
45 R

SKEW ( )

30-Jun-14
24-Jun-14
29-Jun-14
24-Jun-14
28-Jun-14
29-Jun-14
24-Jun-14
24-Jun-14
24-Jun-14
24-Jun-14
-

F/P &
BLINDING

21-Jul-14
27-Jul-14
9-Jul-14
14-Jul-14
-

Rebars

21-Jul-14
27-Jul-14
9-Jul-14
14-Jul-14
-

Concrete

BASE SLAB

RCBC PROGRESS SCHEDULE (BARREL)


As of 31 JULY 2014

30-Jul-14
-

Concrete

WALL

30-Jul-14
-

Rebars

Concrete

TOP SLAB
Rebars

Bituminous
Paint (2 Coats)

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 16

23+756.5
Block 1
Block 2
Block 3a
Block 3b
Block 4
23+997
Block 1
Block 2a
Block 2b
Block 3a
Block 3b
Block 4a
Block 4b
24+235
Block 1a
Block 1b
Block 2a
Block 2b
Block 2c
24+570
Block 1
Block 2a
Block 2b

RENARDET S.A. & PARTNERS

1 cell - 2.0 x 1.5


1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5

TYPE & DIMENSION

67.550
12.090
20.180
14.430
8.700
12.090
70.268
16.128
4.933
13.860
16.300
4.942
7.848
6.197
59.106
15.566
15.000
8.900
15.600
4.020
51.953
25.846
13.500
12.587

LENGTH (m)

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

SKEW ( )

12-Jul-14
12-Jul-14
-

12-Jul-14
12-Jul-14
8-Jul-14
8-Jul-14

F/P &
BLINDING

PREVIOUS

Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations.

RHS

10
LHS

RHS

LHS

RHS

LHS

RHS

LHS

STATION

NO.

P R E V IO US
M ON T H

23-Jul-14
23-Jul-14
-

23-Jul-14
23-Jul-14
23-Jul-14
23-Jul-14

Rebars

23-Jul-14
23-Jul-14
-

23-Jul-14
23-Jul-14
23-Jul-14
23-Jul-14

Concrete

BASE SLAB

RCBC PROGRESS SCHEDULE (BARREL)


As of 31 JULY 2014

THIS MONTH

23-Jul-14
23-Jul-14
-

23-Jul-14
23-Jul-14
-

23-Jul-14
23-Jul-14
23-Jul-14
23-Jul-14

Concrete

WALL

23-Jul-14
23-Jul-14
23-Jul-14
23-Jul-14

Rebars

23-Jul-14
23-Jul-14
-

23-Jul-14
23-Jul-14
23-Jul-14
23-Jul-14

23-Jul-14
23-Jul-14
-

23-Jul-14
23-Jul-14
23-Jul-14
23-Jul-14

Concrete

TOP SLAB
Rebars

24-Jul-14
24-Jul-14
-

24-Jul-14
24-Jul-14
24-Jul-14
24-Jul-14

Bituminous
Paint (2 Coats)

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 17

RENARDET S.A. & PARTNERS

7
8
9
10

23+756.5
23+997
24+235
24+570

23+492

21+260
21+485
21+838
21+972.4
22+655

1
2
3
4

STATION

NO.

3 cells - 2.0 x 1.5


1 cell - 2.0 x 1.5
2 x 4 cells - 2.0 x 1.5
11 x 4 cells - 3.0 x 2.0
2 x 4 cells - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5

TYPE

PREVIOUS

F/P &
BLINDING

Rebars

P R E V IO US
M ON T H

Concrete

INLET

Bit. Paint

RCBC PROGRESS SCHEDULE (INLET & OUTLET)


As of 31 JULY 2014

THIS MONTH

Rebars

Concrete

OUTLET

Bit. Paint

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 18

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

Future Road Crossing Utilities Ducts (As of 31 July 2014)


PIPE
S. NO.

DRAWING NO.

Location

CHAINAGE
DIA

TYPE

NO. OF
PIPES

LEFT STAGE
CCC/FQI/IR/06
MIDDLE STAGE 0+030
SERVICE ROAD-3
RIGHT STAGE

200

uPVC

LEFT STAGE
CCC/FQR/IR/11 SOLMIDDLE STAGE 0+150
2
RIGHT STAGE

300

uPVC

LEFT STAGE
CCC/FQR/IR/10 SOLMIDDLE STAGE 0+300
3
RIGHT STAGE

200

uPVC

LEFT STAGE
CCC/FQR/WA/05 SRMIDDLE STAGE 0+600
1
RIGHT STAGE

300

uPVC

150

uPVC

LEFT STAGE
5

CCC/FQI/EL/01

MIDDLE STAGE

SETOUT/EX
INSTALLATI
BACKFILLIN
C/BED
CONCRETE
ON
G
Setting out/
PREP
Exc/Install

RFI REF.
Concrete

Backfill

5/15/2014 5/15/2014 5/18/2014 6/12/2014 UTL-LAY- 81 UTL-CON- 65 UTL-BF- 01


21+360

6/11/2014 6/11/2014 6/12/2014 7/10/2014 UTL-LAY- 104 UTL-CON- 83 UTL-BF- 20

RIGHT STAGE
LEFT STAGE
6

CCC/FQI/IR/01

MIDDLE STAGE

5/19/2014 5/19/2014 5/20/2014 6/4/2014


21+460

300

uPVC

UTL-LAY- 87 UTL-CON- 66 UTL-BF- 03

6/14/2014 14/06/014 6/14/2014 6/21/2014 UTL-LAY- 108 UTL-CON- 84 UTL-BF- 21

RIGHT STAGE
LEFT STAGE
7

5/19/2014 5/19/2014 5/20/2014 5/31/2014 UTL-LAY- 85 UTL-CON- 63 UTL-BF- 02

CCC/FQI/EL/02 MIDDLE STAGE 21+660

150

uPVC

6/15/2014 6/15/2014 6/15/2014

UTL-LAY- 107 UTL-CON- 85

UTL-BF-

5/20/2014 5/20/2014 5/25/2014 6/4/2014

UTL-LAY- 86 UTL-CON- 64 UTL-BF- 05

RIGHT STAGE
LEFT STAGE
8

CCC/FQI/IR/02

MIDDLE STAGE

21+780

300

uPVC

6/15/2014 6/15/2014 6/15/2014 7/8/2014 UTL-LAY- 109 UTL-CON- 87 UTL-BF- 23

RIGHT STAGE
LEFT STAGE
9

5/25/2014 5/25/2014 5/25/2014 6/4/2014

CCC/FQI/EL/03 MIDDLE STAGE 21+880

150

uPVC

UTL-LAY- 90 UTL-CON-68 UTL-BF- 07

6/16/2014 6/16/2014 6/17/2014 7/10/2014 UTL-LAY- 111 UTL-CON- 88 UTL-BF- 28

RIGHT STAGE
LEFT STAGE
10

CCC/FQI/EL/04

MIDDLE STAGE

6/17/2014 6/17/2014 6/18/2014 7/9/2014 UTL-LAY- 112 UTL-CON- 89 UTL-BF- 33


22+260

150

uPVC

7/20/2014 7/20/2014 7/21/2014 7/27/2014 UTL-LAY- 131

UTL-CON106

UTL-BF-44

RIGHT STAGE
LEFT STAGE
11

CCC/FQI/EL/05

MIDDLE STAGE

6/19/2014 6/19/2014 6/19/2014 7/6/2014 UTL-LAY- 114 UTL-CON- 92 UTL-BF- 31


22+510

150

uPVC

7/20/2014 7/20/2014 7/21/2014 7/17/2014 UTL-LAY- 132

UTL-CON107

UTL-BF-46

RIGHT STAGE
LEFT STAGE
12

CCC/FQI/IR/03

MIDDLE STAGE

6/19/2014 6/19/2014 6/19/2014 7/5/2014 UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30


22+520

200

uPVC

7/20/2014 7/20/2014 7/21/2014 7/17/2014 UTL-LAY- 133

UTL-CON108

UTL-BF-45

RIGHT STAGE
13

LEFT STAGE
CCC/FQI/IR/04
MIDDLE STAGE22+520 LHS
JUNCTION CROSSING
RIGHT STAGE

200

uPVC

14

LEFT STAGE
CCC/FQI/IR/05
MIDDLE STAGE22+587 LHS
JUNCTION CROSSING
RIGHT STAGE

200

uPVC

150

uPVC

300

uPVC

LEFT STAGE
15

CCC/FQI/EL/06

MIDDLE STAGE

5/26/2014 5/26/2014 5/26/2014 6/8/2014


22+760

UTL-LAY- 88 UTL-CON- 69 UTL-BF- 08

6/11/2014 6/11/2014 6/11/2014 7/22/2014 UTL-LAY-106 UTL-CON- 81 UTL-BF-26

RIGHT STAGE
16

LEFT STAGE
CCC/FQI/WA/02
MIDDLE STAGE23+008 LHS
JUNCTION
RIGHT STAGE

RENARDET S.A. & PARTNERS

Page 19

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

PIPE
DIA

TYPE

NO. OF
PIPES

23+020

900

RC

23+060

150

uPVC

23+210

150

uPVC

23+240

150

uPVC

23+560

150

uPVC

23+820

150

uPVC

23+900

600

RC

23+980

150

uPVC

CCC/FQI/WA/04 MIDDLE STAGE 24+000

600

RC

24+020

300

uPVC

24+120

150

uPVC

24+220

150

uPVC

24+340

300

uPVC

24+520

150

uPVC

CCC/FQI/EL/16 MIDDLE STAGE 24+820

150

uPVC

300

uPVC

S. NO.

DRAWING NO.

17

CCC/FQI/WA/01

Location

CHAINAGE

LEFT STAGE
MIDDLE STAGE

SETOUT/EX
INSTALLATI
BACKFILLIN
C/BED
CONCRETE
Setting out/
ON
G
PREP
Exc/Install
6/16/2014 6/16/2014 6/16/2014 7/20/2014 UTL-LAY- 102
7/8/2014

7/8/2014

7/9/2014

RFI REF.
Concrete

Backfill

UTL-CON-

UTL-BF-19

7/27/2014 UTL-LAY- 125 UTL-CON-99 UTL-BF-42

RIGHT STAGE
LEFT STAGE
18

CCC/FQI/EL/07

MIDDLE STAGE

5/25/2014 5/25/2014 5/26/2014 6/14/2014 UTL-LAY- 91 UTL-CON- 71 UTL-BF- 06


11/06/201 6/11/2014 6/11/2014 6/23/2014 UTL-LAY- 105 UTL-CON- 82 UTL-BF- 25

RIGHT STAGE
LEFT STAGE
19

CCC/FQI/EL/13

MIDDLE STAGE

5/27/2014 5/27/2014 5/27/2014 6/17/2014 UTL-LAY- 92 UTL-CON- 72 UTL-BF- 09

RIGHT STAGE
LEFT STAGE
20

CCC/FQI/EL/08

MIDDLE STAGE

5/28/2014 5/28/2014 5/28/2014 6/17/2014 UTL-LAY- 93 UTL-CON- 70 UTL-BF- 10

RIGHT STAGE
LEFT STAGE
21

CCC/FQI/EL/09

MIDDLE STAGE

5/29/2014 5/29/2014 5/29/2014 6/17/2014 UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11


7/30/2014

RIGHT STAGE
LEFT STAGE
22

CCC/FQI/EL/10

MIDDLE STAGE

5/29/2014 6/2/2014

6/2/2014

7/14/2014 7/14/2014 7/14/2014

6/17/2014 UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15


UTL-LAY- 124

UTL-CON102

RIGHT STAGE
LEFT STAGE
23

CCC/FQI/WA/03

MIDDLE STAGE

5/29/2014 6/2/2014

6/2/2014

7/14/2014 7/14/2014 7/15/2014

6/17/2014 UTL-LAY-97 UTL-CON- 76 UTL-BF- 13


UTL-LAY- 127

UTL-CON101

RIGHT STAGE
LEFT STAGE
24

CCC/FQI/EL/11

MIDDLE STAGE

5/29/2014 6/2/2014

6/3/2014

6/19/2014 UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14

6/3/2014

6/4/2014

6/23/2014 UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16

RIGHT STAGE
LEFT STAGE
25

RIGHT STAGE
LEFT STAGE
26

CCC/FQI/IR/07

MIDDLE STAGE

6/4/2014

UTL-LAY-140
R1

UTL-CON114

RIGHT STAGE
LEFT STAGE
27

CCC/FQI/EL/12

MIDDLE STAGE

6/4/2014

6/5/2014

6/10/2014 23/06/201 UTL-LAY- 100 UTL-CON- 79 UTL-BF- 17

7/23/2014 7/24/2014

UTL-LAY-139

RIGHT STAGE
LEFT STAGE
28

CCC/FQI/EL/14

MIDDLE STAGE

6/9/2014

6/9/2014

6/10/2014 6/23/2014 UTL-LAY- 101 UTL-CON- 80 UTL-BF- 18

7/5/2014

7/5/2014

7/5/2014

RIGHT STAGE
LEFT STAGE
29

CCC/FQI/IR/08

MIDDLE STAGE

UTL-LAY- 123 UTL-CON- 94

RIGHT STAGE
LEFT STAGE
30

CCC/FQI/EL/15

MIDDLE STAGE

7/16/2014 7/16/2014 7/17/2014 7/27/2014 UTL-LAY- 130

UTL-CON105

UTL-BF- 43

RIGHT STAGE
LEFT STAGE
31

RIGHT STAGE
LEFT STAGE
32

CCC/FQI/IR/09 MIDDLE STAGE 24+960


RIGHT STAGE

RENARDET S.A. & PARTNERS

Page 20

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

PIPE
S. NO.

DIA

TYPE

NO. OF
PIPES

150

uPVC

21+870

100

uPVC

23+580

100

uPVC

CCC/FQI/NAW.4 MIDDLE STAGE 24+720

100

uPVC

100

uPVC

100

uPVC

22+820

150

uPVC

22+990

150

uPVC

DRAWING NO.

Location

CHAINAGE

SETOUT/EX
INSTALLATI
BACKFILLIN
C/BED
CONCRETE
Setting out/
ON
G
PREP
Exc/Install

RFI REF.
Concrete

Backfill

LEFT STAGE
33

CCC/FQI/EL/17 MIDDLE STAGE 25+160


RIGHT STAGE
LEFT STAGE

34

CCC/FQI/NAW.2

MIDDLE STAGE

5/21/2014 5/21/2014 5/21/2014 6/4/2014

UTL-LAY- 89 UTL-CON- 67 UTL-BF- 04

6/16/2014 6/16/2014 6/18/2014 7/10/2014 UTL-LAY- 110 UTL-CON- 90 UTL-BF- 29

RIGHT STAGE
LEFT STAGE
35

CCC/FQI/NAW.3

MIDDLE STAGE

5/29/2014 5/31/2014 5/31/2014 6/17/2014 UTL-LAY- 96 UTL-CON- 74 UTL-BF- 12


7/10/2014 7/10/2014

UTL-LAY- 120
R1

7/9/2014

7/9/2014

UTL-LAY- 116

7/10/2014 7/10/2014 7/14/2014

UTL-LAY-126

7/22/2014 7/22/2014 7/23/2014

UTL-LAY-136

RIGHT STAGE
LEFT STAGE
36

RIGHT STAGE
LEFT STAGE
37

CCC/FQI/OMANTEL.1MIDDLE STAGE 22+810


RIGHT STAGE
LEFT STAGE

38

CCC/FQI/OMANTEL.2MIDDLE STAGE
0+140 SOL-3
RIGHT STAGE
LEFT STAGE

39

CCC/FQI/SL/03

MIDDLE STAGE
RIGHT STAGE
LEFT STAGE

40

CCC/FQI/SL/04

MIDDLE STAGE
RIGHT STAGE

RENARDET S.A. & PARTNERS

UTL-CON103
UTL-CON110

Page 21

RENARDET S.A. & PARTNERS

PAYMENT APPLICATION No. 2

PAYMENT APPLICATION No. 3

PAYMENT APPLICATION No. 4

PAYMENT APPLICATION No. 5

PAYMENT APPLICATION No. 6

PAYMENT APPLICATION No. 7

PAYMENT APPLICATION No. 8

PAYMENT APPLICATION No. 9

PAYMENT APPLICATION No. 10

PAYMENT APPLICATION No. 11

PAYMENT APPLICATION No. 12

PAYMENT APPLICATION No. 13

PAYMENT APPLICATION No. 14

PAYMENT APPLICATION No. 15

PAYMENT APPLICATION No. 16

PAYMENT APPLICATION No. 17

PAYMENT APPLICATION No. 18

10

11

12

13

14

15

16

17

18

Jun-15

May-15

Apr-15

Mar-15

Feb-15

Jan-15

Dec-14

Nov-14

Oct-14

Sep-14

Aug-14

Jul-14

Jun-14

May-14

Apr-14

Feb&Mar-14

Jan-14

Dec-13

PAYMENT FOR
THE MONTH OF

TOTAL AMOUNT (R.O.)

PAYMENT APPLICATION No. 1


(ADVANCE PAYMENT)

DESCRIPTION

Sl. No.

4,293,764

4,293,764

4,109,460

3,315,692

2,808,644

2,291,277

1,648,225

GROSS
AMOUNT
(R.O.)

4,293,764

184,304

793,768

507,048

517,367

643,052

1,648,225

4,117,632

382,116

650,802

417,900

504,147

514,442

1,648,225

GROSS
NET AMOUNT
AMOUNT
CLAIMED
CLAIMED (R.O.)
(R.O.)

15-Jul-14

05-Jun-14

08-May-14

06-Apr-14

12-Feb-14

23-Nov-13

DATE
SUBMITTED

STATUS OF PAYMENT APPLICATION

3,832,946

382,116

445,708

407,538

434,917

514,442

1,648,225

16-Jul-14

04-Jul-14

05-Jun-14

03-May-14

02-Apr-14

29-Jan-14

AMOUNT
DATE CERTIFIED
CERTIFIED (R.O.)

2,161,833

513,608

1,648,225

AMOUNT
RECEIVED
(R.O.)

14-Sep-14

02-Sep-14

04-Aug-14

02-Jul-14

DATE
PAYMENT DUE

10-Apr-14

6-Feb-14

DATE
PAYMENT
RECEIVED

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 22

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

LIST OF AVAILABLE EQUIPMENTS AT SITE


Sl.
No.
1

DESCRIPTION

CCC

HIRED

TOTAL
AVAILABLE
AT SITE

COMPRESSOR

AIR COMPRESSOR

MILLER WELDING MECHINE

GENERATOR

CRANES

CRANES 30 TON / 25 TON / 70 TON


VEHICLES H.D.

3
-

DIESEL TANKER

FLAT TRAILER

10

HIAB TRUCK

11

P/MOVER + TIPPING TRAILER

12

TIPPER TRUCKS

11

11

13

WATER TANKER 5000 GAL

14

EARTH MOVING PLANT

15

BOBCAT

16

EXCAVATOR

17

JCB 4CX / 3CX

18

SHOVEL / WHEEL LOADER

19

DOZER D9N/D8R

20

TELEHANDLER

4
2

5
3

1
-

21

CIVIL ENGINEERING EQUIPMENT

22

CONCRETE MIXER

23

DYNAPAC S/ROLLER

24

E/WORK ROLLER

25

MOTOR GRADER

26

TITAN PAVER MACHINE

27

TYRE / PTR ROLLER

28

PAVER MACHINE

29

1
1

L. D. VEHICLES & TRUCKS

30

DYNA TRUCK

31

MAINTENANCE TRUCKS

32

ASHOK LEYLAND BUS 55 SEAT

33

TOYOTA COASTER BUS 24 S

34

TOYOTA COROLLA/CIVIC/YARIS

35

TOYOTA PICKUP/ISUZU

36
37
38

11

11

12

NISSAN PATHFINDER/X-TRAIL

TOYOTA LAND CRUISER/FORTUNER

44

88

Total

RENARDET S.A. & PARTNERS

44

Page 23

20

40

60

33

Jan-14

No. of EQUIPMENT

80

55

Feb-14

100

66

Mar-14

120

68

Apr-14

202
66
154

77
May-14

297
68
222

390
77
299

68

86
Jun-14

115
55
88

87

95

Aug-14

47
33
33

88
Jul-14

110
87
607
88
473

93

108
95
715

Sep-14

107
68
497
86
385

107

102
93
817

Oct-14

108

107
93

95

87

68

47

93

110

110
108

82
102
1,184

102

87
108
1,102

98
110
1,015

100
107
917

98

95

PROJECT MONTHS

Nov-14

87

87

68

Dec-14

47

Jan-15

PLANNED TOTAL PER MONTH


REVISED PLANNED TOTAL PER MONTH
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH
ACTUAL CUMULATIVE

82

100

102

100

79
100
1,263

98

77
98
1,340

87

53
1,500

66
1,500

77
1,500

41
79
1,500

53
82
1,459

66
87
1,406

41
1,500

Oct-15

82

79

77
66

53

REVISED PLANNED TOTAL PER MONTH

ACTUAL TOTAL PER MONTH

PLANNED TOTAL PER MONTH

Sep-15

Aug-15

Jul-15

May-15 Jun-15

Apr-15

2015
Jan-15 Feb-15 Mar-15

79

Dec-14

Feb-15

Nov-14

77

Oct-14

Mar-15

Aug-14 Sep-14

66

Jul-14

Apr-15

2014

53

Jun-14

May-15

May-14

41

Apr-14

Jun-15

Mar-14

Jul-15

Feb-14

Aug-15

Jan-14

Sep-15

RENARDET S.A. & PARTNERS

Total

473

1500

41

Oct-15

EQUIPMENT HISTOGRAM

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 24

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

CONTRACTORS MANPOWER AVAILABLE AT SITE

EXPATRIATES

NATIONALS

TOTAL

STAFF & LABOUR


BUDGET

ACTUAL

BUDGET

ACTUAL

BUDGET

ACTUAL

A - MANAGEMENT ***

B - COMMERCIAL STAFF *

C - ENGINEERS

D - FOREMAN & C/H

21

22

E - ENGINEERING TECHNICIANS **

22

29

1 - SKILLED CRAFTSMEN

132

71

203

2 - SEMI-SKILLED/UNSKILLED

494

59

553

10

F - DAILY RATED EMPLOYEES :

TOTAL AS OF END OF THE MONTH

686

139

825

G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor on Company Work :

RENARDET S.A. & PARTNERS

16

Page 25

No. of Men

100

200

300

400

391

Jan-14

500

425

630

222

340

340

18

68

731

391

26

365

848
2,202

748
3,362

638
1,353
603
54
657
2,614

425
715
581
49
630
1,957

1,327

596

46

550

291

222

PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )

596

Feb-14

600

11

57

Mar-14

851

57

691

4,135

773

64

709

3,052

627

851

63

59

565

4,960

825

69

756

3,910

840

858

84

59

756

4,764

838

854

84

6,923

6,383

5,618

7,365

741

442

74

61

667

Dec-14
381

7,691

616

326

61

57

554

Jan-15
269

7,988

573

297

57

51

516

Feb-15
246

306
9,033

330
8,693

8,342

PROJECT MONTHS

340

351

429

354

31

33

43

35

276

44

297

387
47

May-15
305

Apr-15
307

2015
Mar-15
307

REVISED - PLANNED - ( DIRECT + INDIRECT )

725

778

541

764

833

72

61

652

854

78

63

61
83

700

750

60

754

ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )

858
825
Jul-14

322

638
657

Apr-14

57

0
Aug-14

700

11

52

854

Nov-14
480

0
Sep-14

11

848

Oct-14
701

0
Oct-14

800

340

Dec-13

50

854

0
Nov-14

900

57

36

764

0
Dec-14

23

748
May-14

Sep-14
793

541

0
Jan-15

773
Jun-14

Aug-14
794

442

Jul-14
799

9,212

406

179

40

30

365

Jun-15
149

6
57

10
102

15
150

301

4960

383

4577

9,212

8651

9215

862

914

7788

51

92

135

271
30

Total
8301

Oct-15

Sep-15

Aug-15

Jul-15

Aug-15

2014

326

Jun-14
792

297

May-14
791

Feb-15 0

Apr-14
586

354

Mar-14
375

0
Mar-15

Feb-14
186

351
0
Apr-15

Jan-14
34

Jul-15

Dec-13
6

340

0
May-15

PLANNED TOTAL PER MONTH - ( DIRECT )


REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )
PLANNED TOTAL PER MONTH - ( INDIRECT )
REVISED - PLANNED TOTAL PER MONTH-(INDIRECT)
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )
REVISED - PLANNED - ( DIRECT + INDIRECT )
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH - ( DIRECT )
ACTUAL TOTAL PER MONTH - ( INDIRECT )
ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )
ACTUAL CUMULATIVE

Sep-15

MANPOWER HISTOGRAM (DIRECT & INDIRECT)

Oct-15

2013

179
0

RENARDET S.A. & PARTNERS


Jun-15

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 26

Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report July 2014

Page 27

Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report July 2014

Page 28

Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report July 2014

Page 29

RENARDET S.A. & PARTNERS

MAS/CCC/FQI/MSE/003

MAS/CCC/FQI/PVC/004

MAS/CCC/FQI/HDPE/005

MAS/CCC/FQI/PW/006

MAS/CCC/FQI/MC/007

MAS/CCC/FQI/RS/008

MAS/CCC/FQI/PT/009-1

MAS/CCC/FQI/PT/009-2

MAS/CCC/FQI/PT/009-3

MAS/CCC/FQI/PB/010A-Rev.1

MAS/CCC/FQI/PB/010B

MAS/CCC/FQI/HDPE/011

MAS/CCC/FQI/RCBC/012

MAS/CCC/FQI/BP/013

MAS/CCC/FQI/BP/013A

MAS/CCC/FQI/EJ/014A-Rev.1

MAS/CCC/FQI/RC/015

MAS/CCC/FQI/WS/016 B

MAS/CCC/FQI/TW/017

MAS/CCC/FQI/EW/019

MAS/CCC/FQI/EC/020

MAS/CCC/FQI/PS/021

MAS/CCC/FQI/LL/022

MAS/CCC/FQI/LP/023A

MAS/CCC/FQI/FP/024

MAS/CCC/FQI/JS/025

MAS/CCC/FQI/GT/026

CCC/FQI/REN/MAS/003

CCC/FQI/REN/MAS/004

CCC/FQI/REN/MAS/005

CCC/FQI/REN/MAS/006

CCC/FQI/REN/MAS/007

CCC/FQI/REN/MAS/008

CCC/FQI/REN/MAS/009-1

CCC/FQI/REN/MAS/009-2

CCC/FQI/REN/MAS/009-3

CCC/FQI/REN/MAS/010A-Rev.1

CCC/FQI/REN/MAS/010B

CCC/FQI/REN/MAS/011

CCC/FQI/REN/MAS/012

CCC/FQI/REN/MAS/013

CCC/FQI/REN/MAS/013A

CCC/FQI/REN/MAS/014A-Rev.1

CCC/FQI/REN/MAS/015

CCC/FQI/REN/MAS/016 B

CCC/FQI/REN/MAS/017

CCC/FQI/REN/MAS/019

CCC/FQI/REN/MAS/020

CCC/FQI/REN/MAS/021

CCC/FQI/REN/MAS/022

CCC/FQI/REN/MAS/023A

CCC/FQI/REN/MAS/024

CCC/FQI/REN/MAS/025

CCC/FQI/REN/MAS/026

MAS/CCC/FQI/GT/026A

MAS/CCC/FQI/GTI/002

CCC/FQI/REN/MAS/026A

MAS/CCC/FQI/BBC/001

CCC/FQI/REN/MAS/002

MAR No.

CCC/FQI/REN/MAS/001

Reference No.

Geotextile (Bonar NW16)

Geotextile

Joint Sealant (Polyseal)

Street Lighting Feeder Pillar

Street Lighting Poles (Mid-Hinged)

Street Lighting Luminaries

Package Substation

MV & LV Cables

Electrical Works

Telephone Works

Water Stop G EE-25

Reinforced Concrete Pipe (450,600,700mm dia)

Bridge Expansion Joints

Bituminous Paint Material (Rubberized)

Bituminous Paint Material (Rubberized)

Single cell Precast Box Culvert

HDPE Water Pipes

Bridge Pot Bearings

Bridge Pot Bearings

Post Tensioning Work - Strand

Post Tensioning Work - Duct

Post Tensioning Work - Anchorage

Reinforcing Steel

Bitnuminous Prime Coat (MC-70)

Piling Works

HDPE Pipes & Fittings

UPVC Pipes

MSE Wall System

Geotechnical Investigation

Bituminous Base Course

Material/ Work

Bonar Technical Fabrics

Modern East Trading & Con.

Al Inma Building Materilal LLC

Stars Light LLC

Stars Light LLC

United Engineering Projects

United Engineering Projects

United Engineering Projects

United Engineering Projects

National Telephone Services

Sika LLC Oman

Amiantit Oman

Al Ammar International

Henkel Polybit Industries Ltd.

Al Inma Building Materilal LLC

Amiantit Oman

Amiantit Oman

Building Supplies & Services

Al Ammar International

Freyssinet Arabian Sea LLC

Freyssinet Arabian Sea LLC

Freyssinet Arabian Sea LLC

Muscat Steel Industries

Emirates Lube Oil Co. (Muscat)

APCC LLC

Amiantit Oman

Amiantit Oman

Freyssinet Arabian Sea LLC

Swissboring & Company LLC

Tarmac Zawawi LLC Oman

Manufacturer/Supplier/
Subcontractor

Material Approval Status

15/06/2014

21/05/2014

27/03/2014

27/03/2014

22/05/2014

27/03/2014

22/03/2014

19/03/2014

22/03/2014

12/03/2014

25/03/2014

02/03/2014

07/05/2014

17/06/2014

02/03/2014

22/02/2014

22/02/2014

11/05/2014

07/05/2014

22/02/2014

22/02/2014

22/02/2014

02/02/2014

30/01/2014

26/01/2014

26/12/2013

26/12/2013

26/12/2013

26/12/2013

22/12/2013

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

REN/FQI/CCC/111

SO/FQI/CCC/091

SO/FQI/CCC/090

SO/FQI/CCC/089

SO/FQI/CCC/063

SO/FQI/CCC/069

SO/FQI/CCC/026

SO/FQI/CCC/020

SO/FQI/CCC/019

SO/FQI/CCC/014

SO/FQI/CCC/015

SO/FQI/CCC/087

25/03/2014

09/03/2014

SO/FQI/CCC/064

SO/FQI/CCC/038

25/05/2014 REN/FQI/CCC/122

---

27/03/2014

27/03/2014

27/03/2014

20/03/2014

09/03/2014

19/02/2014

09/02/2014

09/02/2014

02/02/2014

02/02/2014

01/04/2014

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

APPROVED
No meet the
HDS

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

SO/FQI/CCC/077

SO/FQI/CCC/082

SO/FQI/CCC/083

---

REN/FQI/CCC/119

16/04/2014 REN/FQI/CCC/100

08/06/2014 REN/FQI/CCC/130

27/03/2014

29/05/2014 REN/FQI/CCC/131

17/03/2014

16/04/2014 REN/FQI/CCC/099

23/03/2014

20/05/2014 REN/FQI/CCC/123

Renardet Not Approved 20/04/2014 REN/FQI/CCC/105

Renardet

Renardet

Renardet

Renardet Not Approved

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

27/05/2014

28/04/2014

16/06/2014

03/04/2014

16/06/2014

03/04/2014

28/04/2014

02/04/2014

31/05/2014

05/05/2014

26/03/2014

11/03/2014

31/05/2014

13/05/2014

14/04/2014

14/04/2014

14/04/2014

24/03/2014

27/03/2014

25/02/2014

18/02/2014

18/02/2014

12/02/2014

12/02/2014

07/04/2014

MOTC
Renardet
Submitte Remarks
Via Renardet
Comment
Letter
d To
By MOTC
Letter Ref. No.
Submitted
s dated
Dated
Date

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 30

Monthly Progress Report July 2014

Upgrading of Falaj Al Qabail Roundabout

Engineers Comments
The Planned percentage of progress as per the construction program is 42.37%.
The Actual percentage of progress is 15.29%.
There is a shortfall of 17.35% in progress which is mainly due to the additional
works due to relocation of Falaj.
Construction works for relocation of Falaj are completed in all respects.
Pile foundation works for Pier No. 4 are recommenced on 22.07.2014.
MSE Wall works are in progress on Abutment No. 1 (Muscat) side.
Site working hours are re-adjusted to accommodate the Break during peak
temperatures of summer and Holy Ramadan .
Future Utility Ducts and Box Culvert works are in progress at various locations.

RENARDET S.A. & PARTNERS

Page 31

7/1/2014

7/1/2014

7/1/2014

7/1/2014

7/1/2014

7/1/2014

7/2/2014

7/3/2014

7/6/2014

7/6/2014

7/6/2014

7/7/2014

7/7/2014

7/7/2014

10

11

12

13

14

S.
Date
No. Received

RENARDET S.A. & PARTNERS

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

From

Subject

1 Cell # 600mm RC Pipe Culvert


Concrete protection 2 CH.23+995 LHS
Bituminous Base Course - Class A (
FQI/RENARDET/191
Tarmac Zawawi )Mix Design
Bituminous Wearing Course - Class A
FQI/RENARDET/192
( Tarmac Zawawi )Mix Design
Interruption to Piling WorksFQI/RENARDET/193
Additional Costs
Abutment and Approach Slab
FQI/REN/TR- 157
Dimension & Reinforcement Details
Pier P1, P2 , P4 & P5 Dimension
FQI/REN/TR- 158
Details

FQI/REN/TR- 156

FQI/RENARDET/185

Integrity Test Reports for pile


foundations
Construction of Utility Ducts FQI/RENARDET/189
Payment for Surround Concrete
Approved General Layout plan from
FQI/RENARDET/190
Sohar Municipality
As- Built Detour Plan Ch.20+941.68 to
FQI/REN/TR- 151
26+010.17
As- Built Detour Plan Ch.21+150.000
FQI/REN/TR- 152
to 25+223.009RHS
Relocation of Existing water pipe
FQI/REN/TR- 153
#125&#250mm @ch.0+750 to 1+100
LHS
Pedestrian Underpass Plan and
FQI/REN/TR- 154
Section Details @ ch.24+360
Dimension and Details of cell Box
FQI/REN/TR- 155
culvert at ch.23+492-Rev-B

Reference
No.

Reference
No.

7/22/2014

7/22/2014

7/20/2014

7/6/2014

7/6/2014

7/6/2014

REN/FQI/CCC/154

REN/FQI/CCC/154

7/8/2014 REN/FQI/CCC/145

Reply
date

CORRESPONDENCE RECORD FOR THE MONTH OF JULY 2014

Approved

Approved

Approved

Approved

Remarks

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 32

RENARDET S.A. & PARTNERS

7/7/2014
7/7/2014
7/7/2014

7/7/2014
7/7/2014

7/8/2014

7/8/2014

7/8/2014

7/9/2014

7/9/2014
7/9/2014

7/9/2014
7/9/2014

7/9/2014

18
19
20

21
22

23

24

25

26

27
28

29
30

31

7/10/2014

7/7/2014
7/7/2014

16
17

32

7/7/2014

15

S.
Date
No. Received

CCC

CCC

CCC
CCC

CCC

CCC

CCC

CCC

CCC

CCC
CCC

CCC
CCC
CCC

CCC
CCC

CCC

From

Subject

Box Girder Section Elevation Details


Bridge Barrier Elevation , Section
FQI/REN/TR- 160
Dimension & Reinforcement Detils
FQI/REN/TR- 161
Access Door Details
Bridge Box Girder Top and Bottom
FQI/REN/TR- 162
Slab Plan Reinforcement Detils
FQI/REN/TR- 163
Prestressing Details Interior WEB
FQI/REN/TR- 164
2.0*1.5*2.0M Box Culvert ( Qty-5 No)
Mitigation of Dust Pollution near
FQI/RENARDET/194
Contractor's Camp
FQI/RENARDET/195 Falaj Shutdown Activity
Grade Sheet for SOL-4 from Ch.0+000
FQI/REN/TR- 165
TO 0+992.46 LHS & CL
Typical Drainage Ditch Inlet Type -II (
FQI/REN/TR- 166
Dimension & Reinforcement Details )
Rev .A
Shop Drawings for Drainage Plan &
FQI/REN/TR- 167
Catchpit Details-SOL-LHS-Rev.C
Drainage plan & catch pite details FQI/REN/TR- 168
SOL-1RHS @ CH.22+647.047 TO
23+252.566
4 Way # 150 mm Upvc street lighting
FQI/REN/TR- 169
Duct @ ch.21+160
FQI/REN/TR- 170
Bearing Location Scheme
Bar bending schedule for 9 cell Box
FQI/REN/TR- 171
culvert Block 1 to 9
FQI/REN/TR- 172
PD8 Arrangement ( AB1-P3)
Drainage plan & catch pite details FQI/REN/TR- 173
SOL-1 LHS @ CH.23+518.071 TO
23+997.000
Typical Section @ Median for 2 Way #
FQI/REN/TR- 174
100mm Upvc street lighting ducts

FQI/REN/TR- 159

Reference
No.

7/10/2014

7/22/2014

7/9/2014

7/22/2014

7/22/2014

7/22/2014

7/22/2014

7/13/2014

7/23/2014
7/7/2014

Reply
date

REN/FQI/CCC/147

Reference
No.

Approved as Noted

Revise & Resubmit

Approved

Revise & Resubmit

Revise & Resubmit

Approved

Revise & Resubmit

Approved
Approved as Noted

Remarks

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 33

RENARDET S.A. & PARTNERS

7/15/2014

7/16/2014

7/16/2014

7/17/2014

7/17/2014

7/17/2014

7/17/2014

39

40

41

42

43

44

45

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC
CCC

7/15/2014
7/15/2014

CCC

37
38

7/13/2014

35

CCC

CCC

7/12/2014

34

CCC

From

36

7/10/2014

33

S.
Date
No. Received
Subject

FQI/REN/TR- 185

FQI/REN/TR- 184

FQI/REN/TR- 183

FQI/REN/TR- 182

Oman Telecommunication - Manholetype 1( falaj alqbail diversion)


Profile ( SOL-6) @CH.0+000TO
0+674.985
Profile ( SOL-6) @CH.0+000TO
0+698.049
Grading plan @ ch.0+000 to 0+420 (
SOL-3)

Drainage plan & catch pite details FQI/REN/TR- 175


SOL-1 LHS @ CH.23+518.071 TO
23+997.000
Pier Bearing Level Details for ( PIL &
PIR ) & ( P5L & P5R ) -Rev .B pier
FQI/REN/TR- 176
Bearing Level Details for ( P3L & P3R)
Rev-A
Detour -1-RHS ( Batinah Highway )
FQI/REN/TR- 177
cross section
Abutment Bearing level Details @
FQI/REN/TR- 178
ch.23+269.500 ( AB1L)&CH.23+509.500(AB-2L&AB-2R)
Warning Tape over water pipelines
FQI/RENARDET/198
Approval from Sohar Municipality
FQI/RENARDET/199 Interim payment application no.6
Detour -1-lhs ( Batinah Highway )
FQI/REN/TR- 179
cross section at ch.0+309.215
SOL-1 ( Batinah Highway) cross
FQI/REN/TR- 180
section at ch.23+960 to ch.24+900
Utilities line layout plan @ ch
FQI/REN/TR- 181
.21+150.000 to 25+223.009-Rev.A

Reference
No.

7/22/2014

7/22/2014

7/23/2014

7/22/2014

7/22/2014

7/16/2014

7/22/2014

Reply
date

REN/FQI/CCC/149

Reference
No.

Approved as Noted

Approved as Noted

Approved

Approved

Approved

Revise & Resubmit

Remarks

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 34

7/17/2014

7/20/2014

7/21/2014
7/22/2014
7/22/2014

7/22/2014

7/22/2014

7/22/2014

7/22/2014

7/22/2014

7/22/2014

7/23/2014

7/23/2014

7/23/2014

7/24/2014

7/22/2014

46

47

48
49
50

51

52

53

54

55

56

57

58

59

60

61

S.
Date
No. Received

RENARDET S.A. & PARTNERS


CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC

CCC
CCC
CCC

CCC

CCC

From

REN/FQI/CCC/153

FQI/RENARDET/211

FQI/RENARDET/208

FQI/REN/TR- 192

FQI/REN/TR- 191

FQI/REN/TR- 190

FQI/REN/TR- 189

FQI/REN/TR- 188

FQI/RENARDET/206

FQI/RENARDET/205

FQI/RENARDET/204

FQI/RENARDET/202
FQI/RENARDET/203

FQI/REN/TR- 187

FQI/REN/TR- 186

FQI/RENARDET/200

Reference
No.
Approved Shop Drawing from water
Department
Statical Calculation Deck Formwork (
PERILLC)
Bar bending schedule for 8 cell Box
culvert ch.21+838-Rev.0
Eid Alfitr Holidays
Working Hours on August 2014
Static load test for working pile #
SOP48
Static load test for working pile #
SOP23
Construction of Utility Ducts Payment for Surround Concrete
Grade Sheet for SOL-6 from Ch.0+000
TO 0+674.985LHS & CL
2Way #150mm upvc street lighting
Ducts @SR-02 CH.1+050
Drainage Ditch Inlet Type-I details @
ch.21+500
Profile ( SOL-5) @CH.0+000TO
0+979.780
Grade Sheet for SOL-6 from Ch.0+000
TO 0+674.985LHS & CL
Relocation of Telecom Utilities Additional works
Project progress Photographs &
Videose with Hard & Printed copy
Approved Shop Drawing for water
pipeline utilities

Subject

7/23/2014

7/23/2014

7/22/2014

7/22/2014

8/13/2014

7/22/2014

Reply
date

REN/FQI/CCC/156

REN/FQI/CCC/200

Reference
No.

Approved

Approved

Approved as Noted

Revise & Resubmit

Remarks

Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report July 2014

Page 35

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

PROGRESS PHOTOGRAPHS

Upstream side of Falaj connection in Progress

Construction of Falaj Connection on Upstream side in Progress

RENARDET S.A. & PARTNERS

Page 36

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

5 Cells Box Culvert at Ch. 23+492 in Progress

Works of 44 Cells Box Culvert in Progress

RENARDET S.A. & PARTNERS

Page 37

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

Installation of Single Cell Pre-cast Box Culverts in Progress

Installation of MSE Walls and Filling Works in Progress

RENARDET S.A. & PARTNERS

Page 38

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

Piling works restarted and in Progress

RENARDET S.A. & PARTNERS

Page 39

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

Installation of Geo-synthetic Straps in MSE Walls in Progress

Compaction of Engineering Fill in MSE Walls in Progress

RENARDET S.A. & PARTNERS

Page 40

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

Testing of Engineering Fill in MSE Wall in Progress

Pouring of Concrete in 5 Cells Box Culvert in Progress

RENARDET S.A. & PARTNERS

Page 41

Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report July 2014

Erection of Scaffolding for Superstructure in Progress

Erection of Shuttering for Pier No. 1 LHS in Progress

RENARDET S.A. & PARTNERS

Page 42

Vous aimerez peut-être aussi