CYCLONE REFRACTORY DAMAGED

AT 35 MTR EL.
WINDBOX REFRACTORY
DAMAGED AT 4.5 MTR EL.

Refractory damaged at Wind box


RHS air inlet duct

Refractory damaged at Wind box


LHS air inlet duct

Wind box front side refractory


damaged and heavy air leakage
observed from this point

Cyclone LHS bull Nose damaged portion.

Cyclone LHS bull nose damaged portion wall

LHS Heavy erosion of cyclone inlet duct wall


Where wall is also bulged.

Cyclone LHS:- furnace outlet duct wall


bulge.

Cyclone LHS:- furnace outlet duct wall is bulge

Cyclone LHS:-furnace outlet duct wall damaged portion

Cyclone LHS flue gas inlet portion


wall observed bulge

Cyclone flue gas inlet duct gap observed

LHS Cyclone inlet bull nose damaged

LHS Cyclone inlet top portion bulged

LHS Cyclone inlet refractory damaged

RHS Cyclone bulged refractory breaking


work under progress

Cyclone RHS refractory breaking near manhole

Cyclone RHS refractory breaking


near manhole

RHS Cyclone inlet bull nose damaged

RHS Cyclone inlet bull nose refractory


damaged

Cyclone RHS inlet refractory damaged