Table 1: Schedule of Rate

No

Description

Unit

Rate (RM)

Excavate to reduce level average 300 mm deep and remove


surplus spoil

m2

4.00

Excavate for isolated foundation, ground beam, etc not exceeding


1.50 m deep, backfill and remove surplus spoil and deposited,
spread and level.

m3

23.00

Hardcore

m3

35.00

Concrete Grade 25

m3

260.00

50mm concrete blinding

m2

7.00

20mm Waterproof of concrete bed

m2

15.00

Formwork of sides of concrete works

m2

33.00

Fabric reinforcement

m2

14.00

Straight and bend bar reinforcement

kg

4.40

10

Damp-proof membrane

m2

5.50

11

Half brick wall in cement and sand including brick reinforcement

m2

50.00

12

Damp proof course 115mm wide

3.50

13

Cement and sand plaster

m2

16.00

14

One coat cement based paint and two coats emulsion paint

m2

10.50

15

Composite aluminium window and fixed light overall size


600mm x 600mm high

No

150.00

16

4mm Clear sheet glass

m2

50.00

17

900mm x 2100mm high timber flush door including ironmongery


and painting

No

350.00

18

50mm x 150mm Grade A timber frame and painting

15.50

19

20mm Cement and Sand (1:3) screed to floor

m2

9.00

Table 2: Approximate weight of reinforcement for concrete components


No

Component

Unit

Weight

Pad foundation

Kg/m3

80

Ground beam

Kg/m3

200

Roof beam

Kg/m3

160

Column Stump

Kg/m3

190

Column

Kg/m3

160

100mm Floor slab

Kg/m2

10