SPECIAL DIRECTIONS FOR VIBRATORY SCREENS
WITH MATS PROVIDED FOR GROSS OR LONGITUDINAL TENSIOWING
1.
General Remarks
Feed the material evenly across the entire width of the Screen at the
least possible height of drop.
Assembly
Tension the screen mat so tight that it rests firmly on the supports and
does not lift off due to the vibrations of the Screen. (Avoid
overtensioning).
Carefully remove any material adhering to the contact surfaces before
mounting a new screen mat. Cover the protruding supports with
rubber or the like.
Tensioning bolts or bars have to rest firmly and fully in the tensioning
folds.
In the case of longitudinal tensioning, install the wedges on the long
sides of the Screen only after the mat is properly tensioned.
Maintenance
Retension a newly installed screen mat after 3 hours of operation and
check correct seat. Retension again after another 10 hours of
operation. Afterwards, check at 2 weeks’ intervals.
If applicable, loosen the lateral wedges and tighten them again after
tensioning. (If the mats are not properly serviced or not regularly
checked, so-called flutter breaks might occur).
Check wear of screen mats frequently. Repair smaller damaged areas
at once, for instance by inserting new wires or attaching screen mat
remnants. Never weld spring steel wires !
If only small areas are worn, turn screen mat or exchange individual
sections.
If the life of a mat is inadequate or the screening efficiency insufficient,
consult IC.