DOCUMENT NUMBER

Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

1/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

METHOD OF STATEMENT
TRAFFIC DIVERSION

OWNER
Approval:
Name:
Date (DD-MMMYY):
Signature:
Document class:

Pages modified under this revision:


WCT BERHAD

00
REV.

IFA - Issued For Approval


DATE
DD-MMM-YY

STATUS REVISION MEMO

WRITTEN BY
(Name &
Designation)

CHECKED BY
(Name & Designation

APPROVED BY
(Name & Designation

Sections changed in last revision are identified by a vertical line in the margin

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

2/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

3/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

TABLE OF CONTENT

1.0

INTRODUCTION

2.0

OBJECTIVE

3.0

REFERENCE

4.0

MACHINERY AND EQUIPMENT

5.0

MANPOWER REQUIREMENT

6.0

PROCEDURE

6.1

DEFINITION

6.2

PLANNING

6.3

WORK INSTRUCTION

6.4

STAGE OF TRAFFIC AND SAFETY MANAGEMENT SCHEME

4
6.5

DUTIES AND RESPONSIBILITY OF TRAFFIC MANAGEMENT OFFICER


5

6.6

ROAD AND SIGNAGE MAINTENANACE

6.7

TRAFFIC MANAGEMENT SCHEME PREPARATION PROCEDURE

6.8

TRAFFIC MANAGEMENT ARRANGEMENT

6.9

TRAFFIC DIVERSION PLANNING

6.10 TRAFFIC MANAGEMENT EQUIPMENT

6.11 SIGNAGE

7.0

INSPECTION AND TESTING

8.0

QUALITY CONTROL

10

10
9.0

SAFETY AND HEALTH

10

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

4/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

1.0

INTRODUCTION
This method statement introduces the proposed activities to be undertaken
and acts as a general methodology for traffic diversion during road
construction in RAPID site. This has been prepared to identify the work stages
and the construction methodology for ensuring the works are carried out in
compliance with contract requirements.

2.0

OBJECTIVE
This method statement describes the overall sequence of the traffic diversion
that will carry out at RAPID site. It also outlines the materials used, machinery
and equipment involved for ensuring the works are carried out safely and in
compliance with contract requirements.

3.0

REFERENCE
Compliance to Local Authority Requirement

4.0

MACHINERY AND EQUIPMENT


Light weight movable plastic barriers
Light weight movable plastic hoardings
Concrete Barriers
Arrow flasher (power by solar)
Light weight movable traffic cone
Temporary signage

5.0

MAN POWER
Construction Manager
HSSE Manager
HSE Supervisor
Site Engineer
Supervisor
Skilled Workers
General Workers
Operator
Flagman
Traffic Controller

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

5/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

6.0

PROCEDURE
6.1 Definition
LIGHT VEHICLES

HEAVY VEHICLES
SLOW VEHICLES
IN HOUSE
VEHICLES

Lorries with gross weight of less than 10 tons, pick


up
trucks and saloon cars
Lorries exceeding gross weight up to 10 tons or
more such as mobile and crawler cranes, dump
trucks, concrete mixer lorries, and etc.
Crawlers cranes, trailers, low loaders, excavators,
forklifts backhoe and etc.
Vehicles consist
of
WCT Berhad
company cars, consultant and clients vehicles

PUBLIC VEHICLES All non-in-house vehicles


The traffic management shall be implemented in a safe and accident
free manner and the following measures shall be carried out without fail
at site. The details stages of temporary internal/external road, control of
junction with flag (men) or traffic signage, cones, barriers and blinkers
shall be shown sufficiently at site for the information of project site
workers.
6.2 Planning
Before any road closure can be implemented, the Work Package Contractor
will submit the proposed road closure plan complete with schedule of
closure for review and approval. The road closure will only be implemented
after the approval is obtained from the OWNER (IPMT).
6.3 Work Instruction
The persons involved should be informed about the possible presence of
traffic diversion in the working and transportation area, the safety
clearances and the possible instructions from the local authority. Also, the
persons involved should be acquainted with the local authority and its
telephone number. Local authority will be informed about all incidents in
relation to traffic diversions.
6.4

Stage of Traffic and Safety Management Scheme


Traffic control during road closure
Traffic diversion
Traffic control during construction stage (haul road)

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

6/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

6.5 Duties and Responsibility of Traffic Management Officer (HSSE


Manager)
To ensure all roads signages are in place and in good condition at all
time.
To ensure that all permits are obtained before any diversion, closure,
changes of traffic flow are made.
To ensure to coordinate to all parties and to brief all parties from
time to time on the traffic management issues.
To ensure that the preventive maintenance of the road and signage's
are carried out on daily basis.
To ensure that all flagman are always in their designated area at all
time
To ensure to comply with all requirement as per stated in the traffic
management write up.
To carry out investigation, report to relevant parties and coordinate if
there are any accident happened at the site.
6.6 Road and Signage Maintenance
The road will be cleaned everyday by using water browser and general
workers. The traffic officer will ensure that the road is clean and safe to use
at all time. The traffic officer will also ensure that daily inspection is
carrying out.
6.7

Traffic Management Scheme Preparation Procedure


6.7.1 Collecting Data
In carry out traffic management, respective person will visit the site for
field check and collect the entire inventory on the existing facilities
including:
i.
ii.
iii.

Identify all roads crossings


Any necessary working permit to commence utilities diversion
Identify the needs of temporary road diversion

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

7/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

6.7.2 Select the Traffic and Construction Duration Categories


Duration categories
Classification
Temporary
Short term diversion

Duration
< 1 day
< 1 month

Long term diversion

>1 month

6.7.3 Determine the Extent of Roadway Occupancy


The location of the road crossing will generally dictate the degree which
the roadway will be occupied and closed or diverted the normal traffic.
To define the extent of the occupancy, the following factors should be
determined.
i.
ii.
iii.
iv.

Beginning / ending points


Length of the occupied roadway
Portion of the roadway that will be closed / diverted
Work duration on the designated location

6.8 Traffic Management Arrangement


Since the works involved are roadwork, construction of bridge and culvert
across the road, and maintenance road, a proper traffic management
within site area is required.
6.9 Traffic Diversion Planning
For the bridge or culvert construction, the road will be totally closed and
new route diversion will be proposed. In case where there is two or more
bridge or culvert need to be constructed in one zone, a proper planning will
be done in order to determine which area to be constructed first. As
example, in Figure 1 shown there are two bridges to be constructed. In
this case, bridge 18 will be constructed first. New road of diversion will be
proposed in order to allow the vehicle to enter the work area. Once bridge
18 is completed and ready to use, the bridge will be opened to construct
bridge 17. A proper signage will be erected. Road at bridge 17 will be
closed and NO ENTRY signage will be erected. Plastic barrier will be placed
at the proposed location. Refer to Figure 2 for the detailed proposed
signage and road condition.

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

8/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

Bridge
17 in
constru
ction
Bridge
progre
18ss
to
be
(Worki
constru
ng
cted
Area)
earlier

Figure 1: Bridge Construction

Figure 2: Proposed Signage and Road Condition

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

9/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

For one side working condition, one lane will be opened and plastic barrier
or traffic cone will be placed at the work area. Proper signage will be
erected. Refer to Figure 3 for the detail work diversion.

Figure 3: Road Diversion for One Side Working Condition


For work zone which is at the middle of the road, two lanes will be opened
on the both side of the road. Plastic barrier or traffic cone will be placed at
the respective location and proper signage will be erected. Refer to
Figure 4 for the detail. The temporary equipments and signage will be
removed accordingly upon the completion.

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

10/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

Figure 4: Road Diversion for the Middle Working Condition


6.10 Traffic Management Equipment
The traffic management equipments used in the project are:

Light weight movable plastic barriers


Light weight movable plastic hoardings
Concrete Barriers
Arrow flasher (power by solar)
Light weight movable traffic cone
Temporary signage

6.11 Signage
A proper signage which classified as advance warning area will be
placed according to the condition. Within the advance warning area,
approaching drivers are informed that they are entering a work zone,
and given an initial indication of any action to be taken ahead. If a
temporary reduce speed limit applies in the work zone, signing for this
is located in the advanced warning area.

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

11/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

7.0 Inspection and Testing


The inspection and frequency of testing shall follow the approved Inspection and
Test Plan (ITP) for Traffic Diversion found in Project Quality Plan.
All sampling testing of road materials will be carried out in the Material Testing
Laboratory which is set up at the site, equipped and operated by the Contractor
under the supervision of the Engineer.
8.0

Quality Control
8.1 All the works to be carried out shall in accordance with the approved
Work Quality Plan and Material Quality Plan in the Project Quality Plan.
8.2

Work Quality Plan and Material Quality Plan are the documents that to

be referred to identify the key parameter of inspection and testing. It is


also to ensure that the work is complying with the specifications.
8.3

The related site personnel shall review all the test reports based on the

criteria set in the Work Quality Plan or Material Quality Plan for all
completed works and materials.
8.4
9.0

All inspection and test record are to be kept and maintained.

Safety and Health


9.1 All the works to be carried out shall in accordance with the approved
Project Safety Plan. Safety & Health Induction shall be given to all new
workers and staff before the commencement of works at site to ensure
they have full knowledge on all the precautions for safety and health at
site.
9.2

All the work to be carried out shall comply and in accordance to the

approved Job Hazard Analysis (JHA) requirement set up by the OWNER.


9.3

All workers shall be equipped with sufficient Personal Protective

Equipment (PPE) such as safety helmets, safety shoes, safety vest, hand
gloves, goggles and etc. whichever suitable to the activity to be carried
out.

DOCUMENT NUMBER
Project

Package

Originator

Discipline

Doc. Type

Unit n0

Serial n0

Rev

Page

RAPID

20C1

WCTB

QAC

PRC

0001

0016

12/11

PETRONAS RAPID PROJECT

PACKAGE 20C1: COMMON CONSTRUCTION


ACCESS AND PERMANENT ROADS WITHIN
THE RAPID SITE AT PENGERANG JOHOR
Method of Statement for Traffic Diversion

________________________________________________________________________________________________
_

9.4

Toolbox meeting shall be carried out weekly in order to ensure the

safety procedures are complied at all times through-out the construction


period.