Vous êtes sur la page 1sur 12

HARGA SATUAN BAHAN DAN UPAH

No.
A
1
2
3
4
5
7
8
9
10
11
12
13
14
15
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35

Uraian
Harga satuan bahan bangunan
Batu kali
Koral
Batu Pecah 2/3
Pasir pasang
Semen
Kayu papan kelas II
Kayu balok Kelas II
Kayu usuk kelas II
Plywood tebal 9 mm
Kayu galam
Besi
Seng BJLS. 20 7"
Kawat ikat
Paku biasa 2" - 5"
Paku seng
Kanstin Baja
Solar
Pelumas/ oli
Grease
Karung Goni
Kawat las
Bit 25 Ton
Minyak begisting
Air Kerja
Vender Karet V 300H 2500L
Tiang Listrik Galvanis t=6m + Plat pengaku
Lampu 2000 watt mercury setara artolite
Anchor bolt 4D22
Kabel listrik NYY 3X4 MM
Solar Cell
Box Accu besi
Accu
Sun Switch

Satuan

m3
m3
kg
m3
kg
m3
m3
m3
lbr
btg
kg
Lbr
kg
kg
Kg
M'
ltr
ltr
kg
Lbr
kg
kg
ltr
ltr
Bh
Bh
Bh
Bh
Rol
Bh
Bh
Bh
Bh

Harga Satuan
(Rp.)

525,000.00
525,000.00
375.00
200,000.00
1,800.00
2,000,000.00
2,000,000.00
2,000,000.00
160,000.00
40,000.00
12,000.00
42,000.00
22,000.00
16,000.00
25,000.00
175,000.00
12,000.00
25,000.00
28,800.00
50,000.00
30,000.00
10,470,000.00
3,000.00
250.00
19,004,700.00
8,500,000.00
3,500,000.00
45,500.00
475,000.00
7,000,000.00
2,500,000.00
3,700,000.00
634,300.00

No.
B
1
2
3
4
5
6
7
8
9
10
11
12
13
14
C
1
2
3
4
5
6
7
8
9
10
11
12
13

Uraian
Harga Satuan Upah
Mandor
Tukang besi
Tukang Batu
Tukang kayu
Kepala tukang
Tukang cat
Pekerja
Surveyor
Tenaga lapangan survey
Operator Crane
Pembantu operator
Operator diesel hammer
Operator Ponton
Tukang las
Harga Satuan Alat
sewa ponton transport
sewa ponton pancang
Sewa Crane dan perlengkapannya
Motor Johnson 40 PK
Diesel Hammer k45
Alat las
genset
sewa blender potong
Water Tank
Pompa Air
Pemipaan dan aksesoris
theodolit
water pass

Satuan

oh
oh
oh
oh
oh
oh
oh
oh
oh
oh
oh
oh

Harga Satuan

oh

135,000.00
120,000.00
120,000.00
120,000.00
130,000.00
120,000.00
80,000.00
1,000,000.00
500,000.00
500,000.00
250,000.00
700,000.00
450,000.00
120,000.00

Jam
Jam
jam
buah
Jam
set/hari
unit/hari
jam
buah
buah
Pkt
unit/hari
unit/hari

1,210,000.00
9,166,740.00
454,850.00
12,100,000.00
700,000.00
2,000,000.00
500,000.00
6,000.00
2,500,000.00
1,500,000.00
600,000.00
300,000.00
100,000.00

DAFTAR ANALISA
NO.

URAIAN

1 1 M'

2 1M'

3 1M2

4 1 Hr

Pemasangan Pagar Pengaman Lokasi


0.02 M3 Balok Kayu Klas II
1.60 LBR Seng Gelombang
0.04 KG Paku
0.04 KG Paku Seng
0.03 OH Pekerja
0.03 OH Tukang Kayu
0.01 OH Kepala Tukang
0.00 OH Mandor
Memasang dan Mengukur Bowplank
0.004 M3 Kayu Matoa
0.06 KG Paku
0.05 JAM Theodolite
0.05 JAM Waterpass
0.05 OH Juru Ukur
0.10 OH Pembantu Surveyor
0.03 OH Pekerja
0.03 OH Tukang Kayu
0.03 OH Kepala Tukang
0.01 OH Mandor
PAMBUATAN GUDANG MATERIAL DAN ALAT-ALAT
0.21 M3 Kayu
0.30 KG Paku biasa 2'-5'
10.50
kg Semen portland
0.03 m3 Pasir Pasang
0.05 m3 Koral
1.50 Lbr Seng gelombang
2.00 OH Pekerja
1.00 OH Tukang Kayu
0.20 OH Kepala Tukang
0.05 OH Mandor
Pengangkutan tiang pancang ke titik pancang
A
Biaya Crane per hari
1.00 OH Operator Alat Berat
2.00 OH Pembantu Operator
5.00 LTR Olie
250.00 LTR Solar
2.00 KG Grease
7.00 JAM Crane
B Biaya Ponton Transport per Hari
1.00 OH Operator Alat Berat
2.00 OH Pembantu Operator
10.00 OH Pekerja
5.00 LTR Olie
200.00 LTR Solar
2.00 KG Grease
1.00 HARI Ponton Transpot
0.28 BUAH Motor Johnson 40 PK

HARGA UPAH
(Rp)

HARGA BAHAN
(Rp)
2,000,000.00
42,000.00
16,000.00
25,000.00

40,000.00
67,200.00
640.00
1,000.00
2,640.00
3,600.00
975.00
108.00
116,163.00

2,000,000.00
16,000.00
42,857.14
14,285.71

8,000.00
880.00
2,040.00
680.00
47,600.00
47,600.00
2,640.00
3,600.00
3,510.00
1,890.00
118,440.00

2,000,000.00
16,000.00
1,800.00
200,000.00
525,000.00
42,000.00

420,000.00
4,800.00
18,900.00
6,000.00
26,250.00
63,000.00
160,000.00
120,000.00
26,000.00
6,750.00
851,700.00

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

1,000,000.00
500,000.00
80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

500,000.00
250,000.00
25,000.00
12,000.00
28,800.00
454,850.00

450,000.00
250,000.00
80,000.00
25,000.00
12,000.00
28,800.00
8,470,000.00
12,100,000.00
Jumlah

1 M'

Dalam sehari dapat diangkut tiang pancang sepanjang (L1)


10 batang x panjang
12,00
Biaya Transport tiang pancang per meter = (A + B)/L1

12.00

10.00

Jumlah
5 1Hr

Pemancangan Tiang Pancang


C
Biaya Diesel Hammer
1.00 OH Operator Alat Berat
2.00 OH Pembantu Operator
3.00 OH Pekerja
4.00 LTR Olie
200.00 LTR Solar
2.00 KG Grease
1.00 HARI Sewa Diesel Hammer
D
1.00 OH
2.00 OH
10.00 OH
4.00 LTR
100.00 LTR
2.00 KG
1.00 HARI

Biaya Ponton Pancang


Operator Alat Berat
Pembantu Operator
Pekerja
Olie
Solar
Grease
Ponton Pancang

500,000.00
500,000.00
125,000.00
3,000,000.00
57,600.00
3,183,950.00

450,000.00
500,000.00
800,000.00
125,000.00
2,400,000.00
57,600.00
8,470,000.00
3,388,000.00
23,557,150.00
120.00
196,309.58

700,000.00
250,000.00
80,000.00
25,000.00
12,000.00
28,800.00
4,900,000.00

450,000.00
250,000.00
80,000.00
25,000.00
12,000.00
28,800.00
64,167,180.00
Jumlah

JUMLAH
(Rp)

700,000.00
500,000.00
240,000.00
100,000.00
2,400,000.00
57,600.00
4,900,000.00

450,000.00
500,000.00
800,000.00
100,000.00
1,200,000.00
57,600.00
64,167,180.00
76,172,380.00

NO.

URAIAN

HARGA UPAH
(Rp)

6 1Ttk
Tiang tegak
Sehari dapat dipancang tiang tegak sepanjang (L2)
2,5 batang x panjang 12.00
Harga pemancangan tiang tegak per meter =
(C+D)/L2 + (A+B)/L1

2.50

HARGA BAHAN
(Rp)

12.00

Jumlah
7 1Ttk
Tiang miring
Sehari dapat dipancang tiang tegak sepanjang (L2)
2,0 batang x panjang 12.00
Harga pemancangan tiang tegak per meter =
(C+D)/L2 + (A+B)/L1
1Pkt Mobilisasi dan Demobilisasi peralatan
1.00 UNIT Crane dan Perlengkapannya
1.00 UNIT Crew Operator + Akomodasi

9 1 Pkt

2.00

12.00

3,370,158.75

21,162,500.00
41,162,500.00
Jumlah

21,162,500.00
41,162,500.00
62,325,000.00

Ltr
bh
bh
pkt
oh

Air Kerja
water tank
Pompa air
Pemipaan dan aksesoris
Pekerja

Pengelasan dengan las listrik


0.4000
kg
Kawat Las (Elektroda)
0.3000
Ltr
Solar
0.0400
Ltr
Minyak Pelumas
0.0400 OH Pekerja
0.0200 OH Tukang Las konstruksi
0.0020 OH Kepala tukang
0.0020 OH Mandor
0.1700 Jam Sewa alat

250.00
2,500,000.00
1,500,000.00
600,000.00

106,050.00
2,500,000.00
1,500,000.00
600,000.00
800,000.00
5,506,050.00

30,000.00
12,000.00
25,000.00

12,000.00
3,600.00
1,000.00
3,200.00
2,400.00
260.00
270.00
61,734.29
84,464.29
8,446.43

80,000.00
Jumlah

80,000.00
120,000.00
130,000.00
135,000.00
363,142.86
Jumlah
Jumlah/cm

11 10 CM

Potong Baja 5mm -20mm DENGAN ALAT POTONG BLENDER


0.0400 OH pekerja
0.0200 OH tukang besi Konstruksi
0.0020 OH kepala tukang
0.0020 OH mandor
0.1700 Jam Sewa alat

80,000.00
120,000.00
130,000.00
135,000.00
363,142.86
Jumlah
Jumlah/cm

12

13

14

24.00

Curring
424
1.00
1.00
1.00
10.00

10 10 CM

30.00

2,735,388.92

Jumlah
8

JUMLAH
(Rp)

1 M2 Pasang bekisting untuk kolom


0.0400 m3 Kayu papan kelas II
0.4000
kg Paku biasa 2" - 5"
0.2000
ltr Minyak begisting
0.0150 m3 Balok kayu kelas II
0.3500
lbr Plywood tebal 9 mm
2.0000 btg Kayu Gelam (Dolkem) 10-12 cm pnjng 4m
0.6600
oh Pekerja
0.3300
oh Tukang kayu
0.0330
oh Kepala tukang
0.0330
oh Mandor
1 M2 Pasang bekisting untuk balok
0.0400 m3 Kayu papan kelas II
0.4000
kg Paku biasa 2" - 5"
0.2000
ltr Minyak begisting
0.0180 m3 Balok kayu kelas II
0.3500
lbr Plywood tebal 9 mm
2.0000 btg Kayu Gelam (Dolkem) 10-12 cm pnjng 3m
0.6600
oh Pekerja
0.3300
oh Tukang kayu
0.0330
oh Kepala tukang
0.0330
oh Mandor
1 M2 Pasang bekisting untuk plat lantai
0.0400 m3 Kayu papan kelas II
0.4000
kg Paku biasa 2" - 5"
0.2000
ltr Minyak begisting
0.0150 m3 Balok kayu kelas II
0.3500
lbr Plywood tebal 9 mm
6.0000 btg Kayu Gelam (Dolkem) 10-12 cm pnjng 3m
0.6600
oh Pekerja
0.3300
oh Tukang kayu
0.0330
oh Kepala tukang
0.0330
oh Mandor

2,000,000.00
16,000.00
3,000.00
2,000,000.00
160,000.00
40,000.00

80,000.00
6,400.00
600.00
30,000.00
56,000.00
80,000.00
52,800.00
39,600.00
4,290.00
4,455.00
354,145.00

2,000,000.00
16,000.00
3,000.00
2,000,000.00
160,000.00
40,000.00

80,000.00
6,400.00
600.00
36,000.00
56,000.00
80,000.00
52,800.00
39,600.00
4,290.00
4,455.00
360,145.00

2,000,000.00
16,000.00
3,000.00
2,000,000.00
160,000.00
40,000.00

80,000.00
6,400.00
600.00
30,000.00
56,000.00
240,000.00
52,800.00
39,600.00
4,290.00
4,455.00
514,145.00

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

3,200.00
2,400.00
260.00
270.00
61,734.29
67,864.29
6,786.43

NO.
15

16

17

18

19 1 m3

URAIAN
1 M3 Beton mutu f'c =26,4 Mpa ( K-300 ) Slump (122)cm, w/c=0,52
413.0000
Kg Semen
681.0000
Kg Pasir Beton
1,021.0000
Kg Batu Pecah 2/3
215.0000
Ltr Air
1.6500
oh Pekerja
0.2750
oh Tukang kayu
0.0280
oh Kepala tukang
0.0830
oh Mandor
10 Kg Pembesian dengan besi polos atau ulir
10.5000
Kg Besi beton (polos/ulir)
0.1500
Kg Kawat beton
0.0700
oh Pekerja
0.0700
oh Tukang kayu
0.0070
oh Kepala tukang
0.0040
oh Mandor

1 M2 Plesteran 1 pc : 4 ps tebal 15 mm
10.2240
kg Semen
0.0200 m3 Pasir pasangan
0.3000
oh Pekerja
0.1500
oh Tukang batu
0.0150
oh Kepala tukang
0.0150
oh Mandor
1 M2 Pek. Acian
3.2500
0.2000
0.1000
0.0100
0.0100

kg
oh
oh
oh
oh

Semen
Pekerja
Tukang batu
Kepala Tukang
Mandor

HARGA UPAH
(Rp)

HARGA BAHAN
(Rp)

JUMLAH
(Rp)

1,800.00
2,858.75
375.00
250.00

743,400.00
1,946,808.75
382,875.00
53,750.00
132,000.00
33,000.00
3,640.00
11,205.00
3,306,678.75

12,000.00
22,000.00

126,000.00
3,300.00
5,600.00
8,400.00
910.00
540.00
144,750.00
14,475.00

1,800.00
200,000.00

18,403.20
4,000.00
24,000.00
18,000.00
1,950.00
2,025.00
68,378.20

1,800.00

5,850.00
16,000.00
12,000.00
1,300.00
1,350.00
36,500.00

2,858,750.00

3,430,500.00
24,000.00
1,350.00
3,455,850.00

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah
Jumlah/kg

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

80,000.00
120,000.00
130,000.00
135,000.00
Jumlah

Urugan pasir padat


1.200
0.300
0.010

m3 Pasir hitam
Oh Pekerja
Oh Mandor

80,000.00
135,000.00
Jumlah

NO.
20 1 bh

URAIAN
Pengadaan dan Pemasangan Fender Karet V300H 2500L
1.0000 BH Fender Karet V300H 2500L
1.0000 OH Operator Alat Berat
4.0000 OH Pekerja
4.0000 JAM Crane
1.0000
LS Alat Bantu
0.2000 HARI Ponton Pancang

HARGA UPAH
(Rp)

HARGA BAHAN
(Rp)
19,004,700.00

500,000.00
80,000.00
454,850.00
500,000.00
450,000.00
Jumlah

21 1 bh

Instalasi Lampu
2.5000
1.0000
0.5000
0.0500

Roll
Ls
oh
oh

Kabel Eterna NYY 3 x 4 (2,5mm)


Bahan lainnya
Tukang listrik
mandor

475,000
15,000
150,000
120,000.00
Jumlah

JUMLAH
(Rp)
19,004,700.00
500,000.00
320,000.00
1,819,400.00
500,000.00
90,000.00
22,234,100.00
1,187,500.00
15,000.00
75,000.00
6,000.00
1,283,500.00

ANALISA HARGA SATUAN PIPA/PLAT BAJA PANCANG


Diameter pipa
Panjang Pipa
Berat pipa
1
2
3
4
5
6
7

cm
m1
kg/m1

Harga pabrik (pipa pancang per kg)


Ongkos Angkut dari pabrik ke pelabuhan pengirim (Tg. Perak)
Biaya handling di pelabuhan pengirim
Biaya sewa lahan penumpukan di pelabuhan
Biaya Kapal dari Surabaya ke Sorong
Pengurusan EMKL
sewa Forklift ( 2 rit cap angkut truck 6 batang)

40.00
12.00
131.60

Rp/kg
RP/9 btg
Rp/36 btg
Rp/106 btg
Rp/106 btg
Rp/106 btg
Rp/3 jam

Keuntungan Perusahan

12,500.0
5,000,000.0
7,500,000.0
12,000,000.0
996,000,000.0
15,000,000.0
5,000,000.0
JUMLAH

12,500.00
351.80
131.92
71.62
5,944.57
89.53
263.61
19,353.04
2,902.96
22,256.00
22,200.00

32,500,000.00
258,750.00
1,500.00
3,500.00
2,500.0
5,000,000.0
5,000,000.0
2,000,000.0

32,500,000.00
5,175,000.00
1,500,000.00
3,500,000.00
2,500,000.0
5,000,000.0
5,000,000.0
2,000,000.0

15%
Harga pipa per 1 kg
PEMBULATAN

ANALISA HARGA PASIR HITAM


1 CONTAINER 20 TON : 20 M3
Sewa Containner 20 FEET
20 m3 pasir hitam
Biaya 1000 Karung
biaya pengisian pasir dalam 1000 karung
biaya angkut ke dalam truck 1000 karung
Biaya angkut Konteneer Ke pelabuhan dasar (Sby)
Biaya Angkut ke pelabuhan Dsnav Sorong
Biaya Bongkar 1000 Karung

Paket
m3
/karung
/karung
/karung
paket
Paket
Paket

20m3
1m3
kg

57,175,000.0
2,858,750.0
2,858.75

REKAPITULASI BIAYA
PEKERJAAN
LOKASI
TAHUN ANGGARAN

LANJUTAN PEMBANGUNAN DERMAGA DISTRIK NAVIGASI KELAS 1 SORONG


KOTA SORONG
2015

NO

URAIAN PEKERJAAN

PEKERJAAN PERSIAPAN

II

Pengangkutan Tiang pancang ketitik pancang

III

Pembersihan akhir lokasi

JUMLAH HARGA

( Rp )

185,215,050.00

10,013,026,834.18

279,788,777.81

A
B
C
D

JUMLAH BIAYA FISIK ( Real Coast )


PPN 10 %
TOTAL JUMLAH
PEMBULATAN

A
B
C
D
E
F

KONSULTAN PENGAWAS
HONOR FISIK PANITIA LELANG FISIK
HONOR PANITIA SUPERVISI
AMDAL
HONOR PANITIA PBHP
ADMINISTRASI & ATK

10,478,030,661.99
1,047,803,066.20
11,525,833,728.19
11,525,833,700.00
11,525,833,700.00

481,810,000.00
TOTAL JUMLAH ( A + B )

12,007,643,700.00

Jayapura,
Dibuat Oleh,
Disetujui Oleh,
KETUA STIKES
SORONG - PAPUA BARAT

(A)

150,000,000.00
14,840,000.00
3,150,000.00
300,000,000.00
8,820,000.00
5,000,000.00

KONSULTAN PERENCANA
CV. ARCANSIA DWITAMA

Mei

2014

(B)

RENCANA ANGGARAN BIAYA


PEKERJAAN
LOKASI
TAHUN ANGGARAN

:
:
:

LANJUTAN PEMBANGUNAN DERMAGA DISTRIK NAVIGASI KELAS 1 SORONG


KOTA SORONG
2015

NO

URAIAN PEKERJAAN

SAT

VOLUME

HARGA SATUAN
( Rp )

JUMLAH HARGA
( Rp )

A
I
1
2
2
3
4
5
6
II

PEKERJAAN PEMBANGUNAN DERMAGA


PEKERJAAN PERSIAPAN
Pemasangan Pagar pengaman lokasi
Pengukuran & pemasangan Bowplank
Foto dokumentasi
Pembuatan Papan nama proyek
Mobilisasi & Demobilisasi
Asuransi Sosial Tenaga Kerja ( ASTEK )
Pembuatan Direksi Keet / Gudang Bahan

M'
M'
ls
Bln
Bln
M
M

350.00
230.00
3.00
1.00
1.00
1.00
54.00

116,163.00
118,440.00
1,000,000.00
1,000,000.00
62,325,000.00
5,000,000.00
851,700.00
Jumlah

40,657,050.00
27,241,200.00
3,000,000.00
1,000,000.00
62,325,000.00
5,000,000.00
45,991,800.00
185,215,050.00

M'

700.00

196,309.58

137,416,708.33

Kg
CM

4,708.79
26,400.00

22,200.00
8,446.43

104,535,138.00
222,985,714.29

Kg
CM
CM

941.22
5,885.93
23,543.97

22,200.00
8,446.43
8,446.43

20,895,084.00
49,715,067.05
198,862,460.89

M'
M'
CM
M
M

1,233.80
386.20
5,885.99
600.00
600.00

2,735,388.92
3,370,158.75
6,786.43
68,378.20
36,500.00

3,374,922,845.38
1,301,555,309.25
39,944,850.71
41,026,920.00
21,900,000.00

M
Kg
M

14.62
2,631.76
106.61

3,306,678.75
14,475.00
354,145.00

48,348,175.95
38,094,791.43
37,753,978.07

M
Kg
M

29.73
11,818.57
149.31

3,306,678.75
14,475.00
354,145.00

98,297,639.20
171,073,862.81
52,877,389.95

- Beton Mutu K. 300


- Pembesian
- Bakesting

M
Kg
M

49.41
19,050.56
297.75

3,306,678.75
14,475.00
354,145.00

163,391,263.73
275,756,859.01
105,446,673.75

4. Plat + Kansten tipe B + fender


- Beton Mutu K. 300
- Pembesian
- Bakesting

M
Kg
M

222.60
68,569.40
810.00

3,306,678.75
14,475.00
354,145.00

736,066,689.75
992,542,046.47
286,857,450.00

PEKERJAAN DERMAGA
1 Pengangkutan Tiang pancang ketitik pancang
2 Pembuatan Sepatu tiang pancang
- Baja Dia. 16 mm
- Pengelasan
3 Penutup tiang pancang
- Baja Dia. 12 mm
- Pengelasan
4 Penyambungan Tiang pancang
5 Pemancangan tiang pancang
- Tegak
- Miring
6 Pemotongan Tiang Pancang
7 Plesteran dinding add. 1 : 2
8 Acian Beton lantai & dinding
9 Cor beton adukan Mutu K.300
1. Beton Isian & selimut tiang pancang
- Beton Mutu K. 300
- Pembesian
- Bakesting
2. Poer type 1 & 2
- Beton Mutu K. 300
- Pembesian
- Bakesting
3. Balok

10 Plat pembimbing tiang pancang


- Baja Dia. 10 mm
- Pengelasan
11 Bit 25 ton
12 Pengadaan & pemasangan fender type FV001-2-4
13 Tes beton /material
14 Pasir isi tiang
15 Curing Plat beton
- Karung goni basah
- Penyiraman beton 3 x 7 hari
16 Kansten type a plat baja

Kg
CM
BH
BH
LS
M
LBR
Paket
M'

2,528.45
4,100.00
6.00
18.00
1.00
258.14

22,200.00
8,446.43
10,470,000.00
22,234,100.00
3,000,000.00
3,455,850.00

56,131,590.00
34,630,357.14
62,820,000.00
400,213,800.00
3,000,000.00
892,093,119.00

750.00
1.00
47.80

40,000.00
5,506,050.00
175,000.00

30,000,000.00
5,506,050.00
8,365,000.00
10,013,026,834.18

Jumlah
III

PEKERJAAN LAIN - LAIN


1 Pembersihan akhir lokasi
2 Lampu penerangan dermaga
a. Penerangan
- Tiang listrik galvanis t = 6 m + plat pengaku
- Lampu 200 watt mercury setara artolite
- Anchor bolt 4D22
- Instalasi Listrik NYM 3x4 mm
- SolarCell
- Box accu
- Accu
- Sun Switch

Ls

1.00

5,000,000.00

5,000,000.00

Btg
Bh
Bh
Ttk
Bh
Ttk
Bh
Ttk

10.00
10.00
40.00
10.00
10.00
1.00
10.00
10.00

8,500,000.00
3,500,000.00
45,500.00
1,283,500.00
7,000,000.00
2,500,000.00
3,700,000.00
634,300.00

85,000,000.00
35,000,000.00
1,820,000.00
12,835,000.00
70,000,000.00
2,500,000.00
37,000,000.00
6,343,000.00

M
Kg
M

3.52
336.59
21.60

3,306,678.75
14,475.00
360,145.00

11,639,505.56
4,872,140.25
7,779,132.00
279,788,777.81

b. Beton tumpuan tiang penerangan


- Beton K. 300
- Pembesian
- Bakesting
Sub Total Real coast

10,478,030,661.99

#REF!
3.2

#REF!

MOBILISASI DAN DEMOB


PERALATAN PANCANG
EXC SORONG
Crane + Hammer
Mesin Las Listrik
General Set
Crew Pancang
Dump Truck
Concrete Mixer
Concrete Vibrator
Cutter Besi

=
=
=
=
=
=
=
=

1
1
1
10
1
2
1
1

Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh

BIAYA MOBILISASI DAN DEMOBILISASI ALAT PANCANG per TRIP


Kapasitas Ponton 1,850
=
Ponton + Tug boat
=
Rp
Jarak Tempuh
=
Kecepatan rata-rata :Isi
=
:Kosong
=
Waktu Tempuh
Berangkat (isi)
=
Loading Material
=
Pengisian BBM + Adm. Plbh
=
Unloading
=
Kembali (kosong)
=
Force Majore
=

280
500,000,000
1
4
6

ton
per bulan
mil
mil/jam
mil/jam

0.25 jam
5.71 jam
6.67 jam
0.17 jam

Transpot Laut (Effective)

0.42 jam
0.42 jam

Ponton + Tug boat


BBM
Biaya Pelabuhan

=
=
=

0.07
0.42

BIAYA MOB./DEMOB. CREW OPERATOR + AKOMODASI per TRIP


=
=

4 orang
6 orang

=
=
=
=
=
=

0.01
0.24
0.50
0.28
0.01
0.00
1.03
2.00

hr
hr
hr
hr
hr
hr
hr/trip
hr/trip

x
x

250,000,000
170
2

x
x
x

x
x

2,000,000
2,000,000

TOTAL BIAYA MOB./DEMOB.

=
7,000 =
2,000,000 =
=

Rp
Rp
Rp
Rp

16,666,667
495,833
4,000,000
21,162,500

=
=
=

Rp
Rp
Rp

8,000,000
12,000,000
20,000,000

Rp

41,162,500

Vous aimerez peut-être aussi