SISTEMA DE TRANSMISION
OBRAS PROVISIONALES
TRANSPORTE DE MAQUINARIAS, EQUIPOS Y HERRAMIENTAS
IMPLEMENTOS DE SEGURIDAD
SEALIZACIN Y SEGURIDAD EN OBRA
OBRAS PRELIMINARES
INSTALACION Y LIMPIEZA DE AREA EN PLANTA-REPARACION Y MANTENIMIENTO
TOLVA RECEPTORA
LIMPIEZA GENERAL RASQUETEO, LIJADO Y SOLDADURA, PINTADO CON ANTICORROSIVO
Y ESMALTE
MOTOREDUCTOR
DESMONTAJE Y CAMBIO DE RODAMIENTOS, ACEITE, REBOBINADO DE MOTOR, PINTADO
Y MONTAJE
TENSORES
CAMBIO DE TENSORES EN DUCTO DE TOLVA
ANGULARES DE ARRASTRE
COLOCACION DE NUEVOS ANGULARES DE ARRASTRE
FAJA TRANSPORTADORA DE TOLVA
CAMBIO DE FAJA DE ARRASTRE NUEVA
DUCTO DE ELEVACION
LIMPIEZA Y REPARACION GENERAL,RASQUETEO, PLANCHADO, ALINEAMIENTO, PINTADO
CON ANTICORROSIVO Y ESMALTE
POLINES DE DESLIZAMIENTO
DESMONTAJE, LIMPIEZA GENERAL, ALINEAMIENTO, CAMBIO DE RODAMIENTOS Y
ENGRASE GENERAL, MONTAJE
BABEROS ANTDERRAME
COLOCACION DE NUEVOS BABEROS D/V
TENSOR SUPERIOR
CAMBIO DE TENSORES, LIMPIEZA DE SOPORTES Y REGULACIONES
BABEROS RASCADORES
COLOCACION DE NUEVOS BABEROS TASCADORES TIPO D/V
FAJA TRANSPORTADORA CLASIFICADOR
COLOCADO DE NUEVA FAJA EN UN TRAMO, REGULACION GENERAL, MANTENIMIENTO
DE POLINES Y SIST. ELECTRICO
POLINES GUIAS EN FAJA CLASIFICADOR
LIMPIEZA GENERAL, ENGRASE, SINCRONIZADOR, SEGURIDAD, CAMBIO DE
RODAMIENTOS Y PINTADO
DESGARRADORA DE BOLSAS
LIMPIEZA GENERAL CAMARA DE RECEPCION, RASQUETEO Y LIJADO, AJUSTE DE
CUCHILLAS HELICOIDALES Y PINTADO C/ANTIC.+ESMALTE
(18%)
COSTO
TIEMPO DE EJECUCION
SEMANA 2
SEMANA 3
S/. 27,166.29
S/. 21,229.44
S/. 87,056.39
S/. 2,469.16
S/. 1,166.16
S/. 720.00
S/. 583.00
S/. 3,086.16
SEMANA 1
S/. 10,985.53
S/. 2,469.16
S/. 1,166.16
S/. 720.00
S/. 583.00
S/. 3,086.16
S/. 3,086.16
S/. 3,086.16
S/. 4,028.70
S/. 2,182.21
S/. 1,846.49
S/. 4,028.70
S/. 2,182.21
S/. 1,846.49
S/. 2,115.76
S/. 2,115.76
S/. 2,115.76
S/. 2,115.76
S/. 1,406.40
S/. 1,406.40
S/. 3,660.00
S/. 3,660.00
S/. 5,029.75
S/. 5,029.75
S/. 10,029.75
S/.
S/.
S/.
S/.
S/.
S/.
S/.
1,406.40
1,406.40
3,660.00
3,660.00
5,029.75
5,029.75
5,850.69
S/. 4,179.06
S/. 10,029.75
S/. 5,850.69
S/. 4,179.06
S/. 4,508.40
S/. 4,508.40
S/. 4,508.40
S/. 4,508.40
S/. 4,517.40
S/. 4,517.40
S/. 913.20
S/. 913.20
S/. 1,002.40
S/. 1,002.40
S/. 3,015.00
S/. 4,517.40
S/. 4,517.40
S/. 913.20
S/. 913.20
S/. 1,002.40
S/. 1,002.40
S/. 3,015.00
S/. 3,015.00
S/. 3,015.00
S/. 5,063.50
S/. 2,215.28
S/. 5,063.50
S/. 2,215.28
S/. 3,012.70
S/. 878.70
S/. 3,012.70
S/. 878.70
S/. 2,534.00
S/. 2,534.00
S/. 2,926.00
S/. 2,926.00
S/. 2,926.00
S/. 2,926.00
S/. 1,545.60
S/. 1,545.60
S/. 4,104.00
S/. 322.00
S/. 322.00
S/. 4,104.00
S/. 1,223.60
S/. 1,223.60
S/. 4,104.00
S/. 4,104.00
S/. 6,150.80
S/. 6,150.80
S/. 2,061.70
S/. 2,061.70
S/. 4,583.00
S/. 4,583.00
S/. 1,527.45
S/. 1,527.45
S/. 2,527.20
S/. 2,527.20
S/. 1,929.60
S/. 1,929.60
S/. 2,079.66
S/. 1,929.60
S/. 1,929.60
S/. 2,079.66
S/. 1,229.10
S/. 1,229.10
S/. 87,056.39
S/. 6,964.51
=========
S/. 94,020.90
S/. 16,923.76
=========
S/. 110,944.66
S/. 10,985.53
S/. 878.84
=========
S/. 11,864.37
S/. 2,135.59
=========
S/. 13,999.96
12.62%
12.62%
S/. 27,166.29
S/. 2,173.30
=========
S/. 29,339.59
S/. 5,281.13
=========
S/. 34,620.72
31.21%
43.82%
S/. 21,229.44
S/. 1,698.36
=========
S/. 22,927.80
S/. 4,127.00
=========
S/. 27,054.80
24.39%
68.21%
EJECUCION
SEMANA 4
S/. 21,540.82
S/. 2,848.22
S/. 2,848.22
S/. 2,134.00
S/. 2,134.00
SEMANA 5
S/. 6,134.31
S/. 2,534.00
S/. 2,534.00
S/. 6,150.80
S/. 6,150.80
S/. 2,061.70
S/. 2,061.70
S/. 4,583.00
S/. 4,583.00
S/. 1,527.45
S/. 1,527.45
S/. 2,527.20
S/. 2,527.20
S/. 2,079.66
S/. 2,079.66
S/. 1,229.10
S/. 1,229.10
S/. 21,540.82
S/. 1,723.27
=========
S/. 23,264.09
S/. 4,187.54
=========
S/. 27,451.62
24.74%
92.95%
S/. 6,134.31
S/. 490.74
=========
S/. 6,625.05
S/. 1,192.51
=========
S/. 7,817.56
7.05%
100.00%