Design Class Detail


Fireproofing, Concrete

PROJECT

Date

Operability and Maintainability


Design
Item

Design Class
Class 1

Class 2

Class 3

Vessel Skirt
Fireproofing

Surface preparation:
None

Structural Steel
Fireproofing

Surface preparation:
Surface preparation: Prime
None or prime, depending or galvanize, depending
on life of unit.
on life of unit.

Surface preparation:
Galvanize

Rain shields/caps: None

Rain shields/caps: Rain


caps on top surfaces of
fireproofed beams only
where severe freeze/thaw
conditions exist.

Concrete
Inspection/Testing

Surface preparation: Blast and prime

Water sealing: None.

Water sealing: Caulk water intrusion points in


accordance with DEP 34.19.20.11-Gen.
Costs 8% more than Class 1

In accordance with
DEP 34.19.20.11-Gen.

In accordance with DEP 34.19.20.11-Gen.

DEP 00.00.07.77-Gen. September 2011

Page 1 of 1