Académique Documents
Professionnel Documents
Culture Documents
CONSULTING ASSOCIATES
PESHAWAR
CNG,
Board
Bazaar,
TABLE OF CONTENTS
EXECUTIVE SUMMARY1
1.1.
INTRODUCTION ............................................................................................................................... 1
1.2.
1.3.
1.4.
CONSTRAINTS .................................................................................................................................. 4
1.5.
LOCATION MAP................................................................................................................................ 4
2.2.
2.3.
2.4.
3.2.
3.3.
3.4.
JV DADO / CCDP........................................................................................................................................... 11
4.1.
4.2.
4.3.
4.4.
5.2.
5.3.
5.4.
6.2.
6.3.
6.4.
ANNEXURE-I
Mini/Micro HPP
EXECUTIVE SUMMARY
1.1.
INTRODUCTION
The main objective of the development of Mini/ Micro Hydropower is to utilize cheap
hydropower potential and to provide reliable and consistent power to local areas specially
those which are deprived of electricity. It will also provide opportunities to local
communities for enhancements of economic activities through establishments of small scale
industries.
For the said purpose a PC-I for Construction of 356 Mini/ Micro Hydropower Projects in
Northern Districts of Khyber Pakhtunkhwa amounting to Rs. 5,524.832 Million was
approved by the PDWP on 1st January 2015.
PEDO has awarded contract for the execution of work to six (6) no. of NGOs covering twelve
(12) districts of Khyber Pakhtunkhwa, following is the detail.
Sr.
District
Date of
Name of NGO/Contractor
Award
1.
(Rs. Million)
Aga Khan Rural Support
Chitral
Contract Amount
1059.6
Programme (AKRSP)
2.
Upper Dir
3.
Lower Dir
4.
Batagram
5.
Abottabad
1st Sept,
6.
Swat
2014
7.
Shangla
8.
Kohistan
9.
Buner
10. Malakand
11. Mansehra
12. Torghar
699.97
Organization/CCDP
JV Green Alternative
728.35
Power/HASHAAR/ZOMO ASHRO/
HYDROLINK
Sarhad Rural Support Programme
(SRSP)
JV Zaif Foundation/ Fatma Welfare
1570.57
437.81
Foundation
JV CEMCO / PCRET
863.35
Mini/Micro HPP
The consultancy agreement was signed for Construction of 356 Mini/ Micro Hydropower
Projects in Northern Districts of Khyber Pakhtunkhwa between Project Director MHP PEDO
and Consulting Associates Peshawar on 24th March, 2014.
This report has been produced under the sub clause 3.7 (consultants obligations) of the
consultancy contract agreement.
1.2.
PHYSICAL STATUS
Till the month of July 2015, out of the total 356 awarded projects 275 were identified.
Whereas 174 were approved for construction, out of the 174 approved projects,
construction work was in progress on 94 sites.
Now during the reporting month i.e. August 2015 the no. of identified sites has increased
from 275 to 276, projects approved by MC from 174 to 187, whereas projects in construction
phase remains 94.
15 projects were expected to complete in the month of August 2015 however due to weather
conditions and financial constraints contractors failed to do so.
Mini/Micro HPP
1.3.
FINANCIAL STATUS
Till July 2015, Rs. 294.604 Million were released to the contractors, this amount remained
same in the reporting month.
Sr.
NGO/Contractor
Bid Price
(Rs. Million)
Payment
(Rs. Million)
%age
Utilization
1.
1059.6
130.62
12.32
2.
699.97
14.93
2.13
3.
JV GAP/HASHAAR/ZOMO
ASHRO/ HYDROLINK
728.35
78.306
10.75
4.
1570.57
55.537
3.53
5.
437.81
15.211
3.47
6.
JV CEMCO / PCRET
863.35
--
--
Mini/Micro HPP
1.4.
CONSTRAINTS
Weather constraints.
1.5.
LOCATION MAP
Mini/Micro HPP
Mini/Micro HPP
Mini/Micro HPP
2.1.
CONTRACT DETAILS
Name of NGO/Contractor:
19th Feburary,2015
55
Duration of Contract
18 months
District
Chitral
2.2.
55 no. of projects are awarded to AKRSP with total capacity of 6.27MW. Contractor is able to
get approval of all the 55 no. of projects. Out of 55 approved projects, contractor has initiated
construction work on 30 projects only.
2.3.
Till the month of July 2015 AKRSP had achieved the progress stated below.
Total
Sites
Total
Approved Sites
Construction
Started
Identified in
this Month
55
55
30
--
--
Financial Progress:
2.4.
Total Approved
Sites
Construction
Started
Identified in
this Month
55
55
30
--
--
Financial Progress:
No Change
Mini/Micro HPP
JV GAP/HASHAAR/HYDROLINK/ZOMO ASHRO
Mini/Micro HPP
3.1.
CONTRACT DETAILS
Name of NGO/Contractor:
Date of Contract Award:
JV GAP/HASHAAR/HYDROLINK/ZOMO
ASHRO
1st September, 2014
19th Feburary,2015
73
Duration of Contract
18 months
District
Abbottabad
Batagram
34
39
3.2.
Till the month of July 2015 JV GAP/Hashaar/Hydrolink/Zomo Ashro had achieved the
progress stated below.
Total
Sites
Total
Construction
Approved Sites
Started
Identified
in this
Month
District Abottabad
34
18
Financial Progress:
--
--
39
35
Financial Progress:
13
--
Mini/Micro HPP
3.4.
Two (2) approved sites in district Abottabad have been dropped due to inconformity with
the contract agreement. In the month of August 2015, JV GAP/Hashaar/Hydrolink/Zomo
Ashro achieved the following progress.
Total
Sites
Total Approved
Sites
Construction
Started
Identified in
this Month
District Abottabad
34
16
--
Financial Progress:
--
No change
District Batagram
39
36
13
Financial Progress:
--
No change
10
Mini/Micro HPP
JV DADO / CCDP
11
Mini/Micro HPP
4.1.
CONTRACT DETAILS
Name of NGO/Contractor:
JV DADO / CCDP
19th Feburary,2015
55
Duration of Contract
18 months
District
Upper Dir
Lower Dir
44
11
4.2.
55 no. of projects are awarded to JV DADO/CCDP with total capacity of 4.72MW. However
till the reporting month contractor is able to get approval for 16 no. of projects with capacity
of 705KW (0.705MW). Contractor has initiated construction work on 4 projects only.
4.3.
Till the month of July 2015 JV DADO/CCDP had achieved the progress stated below.
Total
Sites
Total Approved
Sites
Construction
Started
Identified in
this Month
Financial Progress:
18
11
Financial Progress:
--
10
--
12
Mini/Micro HPP
4.4.
Total
Approved Sites
Construction
Started
Identified in
this Month
14
Financial Progress:
13
--
No Change
District Lower Dir
11
--
Financial Progress:
10
--
No Change
13
Mini/Micro HPP
14
Mini/Micro HPP
5.1.
CONTRACT DETAILS
Name of NGO/Contractor:
19th Feburary,2015
22
Duration of Contract
18 months
District
Buner
Malakand
13
5.2.
22 no. of projects are awarded to JV Zaif Foundation/FWF with total capacity of 2.98MW.
However till the reporting month contractor is able to get approval for 5 no. of projects with
capacity of 240KW (0.240MW). Contractor has initiated construction work on 5 no. of the
approved projects.
5.3.
Till the month of July 2015, JV Zaif Foundation/FWF had achieved the progress stated below.
Total
Sites
Total
Approved Sites
Construction
Started
Identified in
this Month
District Buner
13
Financial Progress:
11
--
--
Financial Progress:
--
-None
15
Mini/Micro HPP
5.4.
In the month of August 2015, JV Zaif Foundation/FWF achieved the following progress.
Total
Sites
Total Approved
Sites
Construction
Started
Identified in
this Month
District Buner
Financial Progress:
13
No change
5
11
--
District Malakand
9
--
--
Financial Progress:
-None
16
Mini/Micro HPP
17
Mini/Micro HPP
6.1.
CONTRACT DETAILS
Name of NGO/Contractor:
Date of Contract Award:
19th Feburary,2015
105
Duration of Contract
18 months
District
Swat
Shangla
Kohistan
45
25
35
6.2.
105 no. of projects are awarded to SRSP with total capacity of 5.42MW. However till the
reporting month contractor is able to get approval for 54 no. of projects with capacity of
3.5MW. Out of 54 approved projects, contractor has initiated construction work on 36
projects only.
6.3.
Till the month of July 2015, SRSP had achieved the progress stated below.
Total
Sites
Total
Approved Sites
Construction
Started
Identified
in this
Month
District Swat
45
17
Financial Progress:
12
17
10
25
13
Financial Progress:
13
10
18
Mini/Micro HPP
Total
Sites
Total
Approved Sites
Construction
Started
Identified
in this
Month
District Kohistan
35
17
Financial Progress:
6.4.
11
17
15
Total
Approved Sites
Construction
Started
Identified
in this
Month
District Swat
45
20
12
Financial Progress:
14
--
No Change
District Shangla
25
16
13
Financial Progress:
--
No Change
District Kohistan
35
18
11
Financial Progress:
17
--
No Change
19
Mini/Micro HPP
JV CEMCO/ PCRET
20
Mini/Micro HPP
7.1.
CONTRACT DETAILS
Name of NGO/Contractor:
JV CEMCO/ PCRET
46
Duration of Contract
18 months
District
Torghar
Mansehra
20
26
After the award of contract the contract initiated its work, and had preliminary identified no.
of sites for MHP development. However, The Ministry of Science and Technology vide letter
No 2(1)/JS (A) Government of Pakistan Ministry of Science and Technology dated
03/12/2014 communicated for immediate withdrawal of PCRET from joint venture. CEMCO
was given notice to clarify the position within 07 days as per contract agreement clause No
45.1 and 45.2.
Reply of CEMCO was not satisfactory and PEDO intended to terminate his contract however
CECMO took stay order from Peshawar High Court. Hence the matter is now in Court and
PEDO is not in position to take any action till the decision of the Court.
21
Mini/Micro HPP
ANNEXURE-I
22