GE Energy Services
MS 9001FA
PACKAGED GAS TURBINE
T BASE DESIGN
INSTALLATION GUIDE
(DN504)
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 2
NOTICE OF INTENT
This document provides information concerning the major tasks and
typical responsibilities associated with the installation of GE supplied
equipment. It describes much of the overall scope of unit installation,
but does not detail specific methods used to complete each activity.
The primary purpose of this document is to provide an overview of the
installation process for this unit type in typical configurations available
at the time of publication. Subsequent design advances or changes
in configuration may not be reflected in this guide.
This document does not purport to cover all aspects of a particular
installation. Unit-specific details are provided in the document and
drawing packages supplied with each requisition per contract of sale.
All sketches, descriptions, and dimensions are to be considered
Typical of this type of unit. This document is the property of General
Electric and is considered Company Proprietary Information.
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 3
Contents
1. INTRODUCTION............................................................................................................................................................... 5
2. ADVANCE PLANNING ACTIVITIES ................................................................................................................................ 5
3. DETAILED SCOPE OF WORK ........................................................................................................................................ 5
3.1 INSPECT AND VERIFY INTERFACE AND TERMINAL POINTS ............................................................................... 8
3.2 VERIFY FOUNDATION EMBEDMENTS AND SUPPORT AREAS, ETC., FOR TURBINE, GENERATOR, PIPE
SUPPORT PIERS (BOP)............................................................................................................................................ 8
3.3 SET AND GROUT FOUNDATION/SUB-SOLE PLATES (BOP) ................................................................................. 8
3.4 INLET AND EXHAUST SYSTEM FOUNDATION (BOP) ............................................................................................ 8
3.5 AUXILIARY MODULES, SKIDS AND ENCLOSURE FOUNDATIONS (BOP) ............................................................ 8
3.6 RECEIVE TURBINE, GENERATOR, TURNING GEAR AND ALL OTHER GE SUPPLIED EQUIPMENT ............... 11
3.7 RIGGING AND SETTING EQUIPMENT .................................................................................................................. 11
3.8 FOUNDATION BOLTING ARRANGEMENT (MLI 1603)........................................................................................... 12
3.9 GAS TURBINE ......................................................................................................................................................... 12
3.10 INSTALL LOAD COUPLING TO TURBINE (INLET END) (MLI 1319) .................................................................... 12
3.11 GENERATOR (A013) ............................................................................................................................................. 13
3.12 COLLECTOR ASSEMBLY AND TURNING GEAR ................................................................................................. 13
3.13 INSTALL TURBINE EXHAUST DIFFUSER (MLI 0706).......................................................................................... 13
3.14 ALIGNMENT OF GENERATORTOTURBINE, COLLECTOR ASSEMBLY AND TURNING GEARTO
GENERATOR (MLI 0411) ......................................................................................................................................... 14
3.15 SET ACCESSORY PACKAGE (A160) ................................................................................................................... 22
3.16 SET LIQUID FUEL AND ATOMIZING AIR SKID (A162) ......................................................................................... 22
3.17 SET PACKAGED ELECTRICAL ELECTRONIC CONTROL COMPARTMENT (PEECC) (MLI A059).................... 22
3.18 WATER INJECTION SKID (MLI A035) ................................................................................................................... 23
3.19 FIRE PROTECTION SKID (MLI A068)................................................................................................................... 23
3.20 SET COOLING WATER MODULE (MLI A076)....................................................................................................... 23
3.21 SET LOAD COMMUTATED INVERTER (LCI) EXCITATION COMPARTMENT GEC (MLI A157)....................... 23
3.22 SET DC LINK REACTOR (STATIC START) (MLI A140) ........................................................................................ 23
3.23 SET ISOLATION/EXCITATION TRANSFORMER (STATIC START) (MLI A141) ................................................... 23
3.24 SET BUS ACCESSORY COMPARTMENT (BAC) (MLI A153) ............................................................................... 23
3.25 SET LIQUID FUEL FORWARDING SKID (MLI A045) ............................................................................................ 33
3.26 AIR PROCESSING SKID (MLI A130)..................................................................................................................... 33
3.27 SET WATER WASH SKID (MLI E025) ................................................................................................................... 33
3.28 SET COOLING FAN MODULE (MLI A132) ............................................................................................................ 33
3.29 SET STATIC START EXCITATION SUB-STATION (MLI A141).............................................................................. 33
3.30 SET AND ASSEMBLE ISO PHASE BUS DUCT (MLI A064) .................................................................................. 33
3.31 SET HYDROGEN DRYER AND PURGE ASSEMBLY (GEN) ................................................................................ 34
3.32 SET LIQUID DETECTORS (GEN) ......................................................................................................................... 34
3.33 SET HYDROGEN GAS SUPPLY (BOP) ................................................................................................................ 34
3.34 SET PURGE GAS SUPPLY (BOP) ........................................................................................................................ 34
3.35 INSTALL BATTERIES (MLI 1207) .......................................................................................................................... 34
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 4
Note: MLI items are drawings provided by GE for the installation of GE provided equipment.
BOP items are AE/Customer provided drawings. GEN items are generator equipment.
MSD items are Materials Shipped Direct (by the vendor).
GE Energy Services
GPGS
Subject
1.
DN 504
July 16, 1997
Page 5
INTRODUCTION
The information in this guide is intended to outline the procedures to be followed when
installing a DLN-2.6 standard GE MS 9001FA Packaged Gas Turbine, with a 324S packaged
hydrogen cooled generator, off-base skids and modules, accessory equipment, interconnecting
piping, cable and conduit as described in the Detailed Scope of Work section of this document.
See Exhibit A for a listing of major MS 9001FA equipment packages.
2.
3.
Communication Channels
Installation Schedule
Schedule
Shipping Schedule
Installation Procedures
Performance Testing
FSR/FRN (Field Service Report/Field Report Notice), and Back Charge Procedures
Pre-pour Inspection
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 6
Figure 1
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 7
Figure 2
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 8
FOUNDATION PREPARATION
3.1
3.2
3.3
3.4
3.5
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 9
Note:
3.5.1
This item assumes that foundation anchor bolts are provided in the
foundations. An alternate procedure is to locate, drill, and install expansion
or epoxy anchors in the foundation.
Auxiliary Modules, Skids And Enclosures
Accessory Module MLI A160 consisting of:
Hydraulic accumulators
Liquid Fuel and Atomizing Air Skid MLI A162 consisting of:
GPGS
Subject
Performance monitor
Vibration monitor
DN 504
July 16, 1997
Page 10
GPGS
Subject
DN 504
July 16, 1997
Page 11
3.6.2
3.7
GPGS
Subject
DN 504
July 16, 1997
Page 12
3.7.1
3.7.2
Equipment Erection
Installer will be responsible for verification of the actual lifted weight and
dimensions of equipment and materials per MLI 0408. Estimated weights
and dimensions are shown in Exhibit A.
3.9
The preferred method of setting gas turbine and generator is to rig, pick-up
and set with a crane or gantry crane. Another method is to set the
equipment on skidding device and roll from the truck onto foundation.
GAS TURBINE
Set turbine down on hard wood blocking approximately 24 to 36 high over anchor
bolts. Jack turbine down over anchor bolts on sub-sole plates and shim packs. Adjust
shim packs to correct centerline elevation. Installer will provide all materials such as
anchor bolts, nuts, one inch (1) washers etc., and grout required for setting and
leveling. (See Fig. 4).
3.10
GPGS
Subject
3.11
DN 504
July 16, 1997
Page 13
GENERATOR (A013)
Unbolt and remove generator rotor locking device. Jack the field approximately one inch
(1) aft (toward collector end). (Refer to MLI 0411 Field Alignment Instructions.)
Set the generator down over anchor bolts on sub-sole plates and shim packs. Adjust
shim packs to correct centerline elevation. Installer will provide all materials such as
anchor bolts, nuts, washers, etc., and grout required for setting and leveling (See Fig.
6). (Refer to Contract.)
3.12
3.13
GE Energy Services
GPGS
Subject
3.14
DN 504
July 16, 1997
Page 14
The turbine and generator bases must be in a free standing condition, i.e.,
no off-base air, water, fuel gas, fuel oil or lube oil piping, conduit or bus duct
is to be made up to the turbine and generator bases. The collector assembly
and turning gear shall also be free standing with no lube oil piping wiring or
conduit connected.
3.14.2
3.14.3
Installer will final align generator to turbine, turning gear to generator, install
foundation centerline keying devices and make up couplings per GE
drawings. It is recommended that alignment readings be witnessed and
signed off by the Owner, Installer and General Electric. (See Fig. 9).
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 15
Figure 3
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 16
Figure 4
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 17
Figure 5
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 18
Figure 6
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 19
Figure 7
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 20
Figure 8
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 21
Figure 9
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 22
3.16
3.17
The support legs (6) for the Liquid Fuel and Atomizing Air skids, and the
support legs (8) for the PEECC modules will be set down over anchor bolts,
leveled, and set to the correct elevation with respect to the machine base
line as determined from AE drawings. Anchor bolts, washers and anchor
bolt nuts are normally supplied by installer.
GE Energy Services
GPGS
Subject
3.18
DN 504
July 16, 1997
Page 23
3.19
3.20
3.21
3.22
3.23
3.24
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 24
Figure 10
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 25
Figure 11
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 26
Figure 12
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 27
Figure 13
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 28
Figure 14
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 29
Figure 15
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 30
Figure 16
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 31
Figure 17
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 32
Figure 18
GE Energy Services
GPGS
Subject
3.25
DN 504
July 16, 1997
Page 33
3.26
3.27
3.28
3.29
3.30
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 34
3.32
3.33
3.34
3.35
3.36
3.37
3.38
GPGS
Subject
DN 504
July 16, 1997
Page 35
Assemble the thermocouple radiation shields (31 total) to the inside of the diffuser outer
barrel and weld from the inside. Assemble thermocouples into the radiation shields from
outside of diffuser outer barrel.
3.40
3.41
This work must be coordinated with unit piping assembly. See Activity 3.44.
3.42
3.42.2
3.42.3
Installer will supply and install a rodent guard around the bottom of the
turbine and generator.
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 36
Install Inlet Plenum support steel per installation drawings. (See Fig. 19).
3.43.2
Install upper and lower halves of the Inlet Plenum Inner Cone. (This is an
extension of the turbine inlet case.)
3.43.3
Install inlet plenum lower and upper corner quarter sections, lower and upper
front, and aft center sections. Assemble hardware in accordance with the
supplier drawings. (See Fig. 20).
Note:
3.44
Install all inlet ductwork structural steel supports and inlet filter compartment
supports. (See Fig. 21).
3.44.2
Install one (1) section of inlet transition ducting and hardware on top of inlet
plenum in accordance with suppliers drawings. (See Fig. 21).
3.44.3
Assemble inlet expansion joint in between transition duct and lower inlet
elbow. The expansion joint is shipped in pieces and must be assembled onsite.
3.44.4
Set lower inlet elbow duct and assemble to expansion joint in accordance
with suppliers drawings.
Note:
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 37
Figure 19
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 38
Figure 20
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 39
Figure 21
3.44.5
Set upper elbow duct on support rails and assemble to lower elbow duct and
hardware in accordance with suppliers drawings.
GE Energy Services
GPGS
Subject
3.44.6
3.44.7
Assemble empty duct to silencer duct on ground and set on support rails in
accordance with suppliers drawings.
Note:
3.45
DN 504
Installer will ensure that all joints between ductwork sections are
water and/or air tight.
Assemble and install filter house transition duct in accordance with the
installation instructions. (See Fig. 22).
3.45.2
3.45.3
3.45.4
3.45.5
Install air filter shutoff valve and low pressure alarm switch and gauge in
accordance with the installation instructions.
3.45.6
Field run tubing between Performance Monitor (MLI 0302) and inlet plenum,
turbine inlet case bellmouth, exhaust duct, cooling air connection to
atmosphere and drain.
3.45.7
Mount humidity sensor in the Inlet Duct (MLI 0302). Refer to installation
drawings for location.
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 41
Figure 22
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 42
(GDX) Air Inlet Filter System Module Assembly (MLI A040) Suggested Layout
Figure 23
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 43
(GDX) Air Inlet Filter System Module Assembly (MLI A040) Typical Layout
Figure 24
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 44
Figure 25
3.45.8
Install turbine air inlet filter cartridges (576 pairs) after completion of filter
house installation and painting. (See Fig. 26).
GE Energy Services
GPGS
Subject
Note:
3.46
DN 504
July 16, 1997
Page 45
3.46.2
The exhaust duct is shipped to the site in four (4) pieces. The top
sections (2), and bottom sections (2) will be aligned and bolted
at the cirumferential and horizontal joints using permanent
bolting flanges.
3.46.3
Installer will be responsible for seal welding (inside and outside) of the
exhaust duct longitudinal and cirumferential joints. (See Fig. 28).
3.46.4
Installer will install internal insulation packs at both horizontal joints and
cirumferential joint. (See Fig. 29).
3.46.5
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 46
Figure 26
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 47
Figure 27
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 48
Bolting And Seal Welding (MLI A042) Exhaust Duct Sections Suggested Layout
Figure 28
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 49
Figure 29
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 50
Figure 30
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 51
ASSEMBLE PIPING
3.47
3.47.1
Install No. 2 turbine bearing lube oil feed and drain piping (MLI 0907).
3.47.2
3.47.3
Install No. 1 turbine bearing lube oil feed and drain piping (MLI 0905).
3.47.4
Install piping turbine end of generator or load compartment (MLI 0906). Pipe
includes:
3.47.5
3.47.6
Install Inlet Guide Vane (IGV) hydraulic control oil supply and drain piping
(MLI 0908).
3.47.7
Install Accessory module piping (MLI 0969). (Also see Fig. 31.) Piping
includes:
GPGS
Subject
DN 504
July 16, 1997
Page 52
3.47.8
Install Liquid Fuel/Atomizing Air Skid piping (MLI 0969). Pipe includes:
Note:
3.47.9
Install air extraction pipe and valves (MLI 0944, SUMM and MSD).
3.47.10
Install false start drain pipe and valves (MLI 0920, MIL 1026, SUMM and
MSD).
3.47.11
Install cooling and sealing air piping (MLI 0909 and MSD).
3.47.12
Install cooling fan module pipe (exhaust frame blowers). (MLI 0972 and
MSD).
3.47.13
Install inlet air heater duct piping (BOP); customers connection at turbine
enclosure wall (MLI 0924); control valves (MLI A037, SUMM and MSD).
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 53
Figure 31
GE Energy Services
GPGS
Subject
3.48
DN 504
July 16, 1997
Page 54
3.47.14
3.47.15
Install cooling water piping (MLI 0915 and SUMM) to the turbine flame
scanners (MLI 1121).
3.47.16
3.47.17
Install fire protection piping (MLI 0964, MLI 0995 and MSD).
3.47.18
Install inlet and exhaust plenum drains (MLI 0976, MLI 0979 and MSD).
3.47.19
3.47.20
Install liquid fuel oil to turbine piping (MLI 0961 and MSD).
3.47.21
3.47.22
3.47.23
3.48.2
GPGS
Subject
3.48.3
DN 504
July 16, 1997
Page 55
3.48.4
Drains
Install drain headers from turbine base, water wash drain, inlet and exhaust
plenum drains to collection tank. Install drain headers from starting means,
generator, accessory module and liquid fuel/atomizing air skid to collection
tank. Freeze protection will be provided for all drain lines.
3.48.5
3.48.6
3.48.6
Venting
Install all vent piping required from turbine base, generator base, Accessory
Module (which includes the lube oil tank and oil demister) and Liquid
Fuel/Atomizing Air skid.
3.49
SUPPLY PIPING
3.49.1
Supply piping is usually that piping not provided by GE, which connects the
GE supplied auxiliary modules and skids to the Owner provided supply. All
supply piping is to be supplied and installed per Owner/AE specifications.
This piping may include the gas supply piping (which may also contain GE
provided metering tubes (MLI 0639) to the Accessory Module, liquid fuel
supply to the Liquid Fuel Forwarding Skid (MLI A045), potable water supply
to the Cooling Water Module and Water Wash skid (MLI A076 and MLI
E025), demineralized water supply to the Water Injection skid (MLI E035).
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 56
CAUTION:
Main Unit
Installer will be responsible for installation of all wiring, conduit
instrumentation, loose shipped junction boxes and electrical material
supplied by GE.
3.50.1.1
3.50.1.2
Install turbine enclosure wire and conduit (MLI 1103, MIL 1159).
3.50.1.3
3.50.1.4
3.50.1.5
Install flame detector wire and conduit (MLI 1121, MIL 1127).
3.50.1.6
3.50.1.7
3.50.1.8
3.50.1.9
GPGS
Subject
DN 504
July 16, 1997
Page 57
3.50.2
3.50.3
3.50.3.2
3.50.3.3
3.50.3.4
3.50.3.5
3.50.3.6
3.50.3.7
3.50.3.8
3.50.3.9
GPGS
Subject
3.51
DN 504
July 16, 1997
Page 58
3.51.2
3.51.3
3.51.4
3.51.5
3.51.6
3.51.7
Performance monitor.
3.51.8
Humidity sensor.
3.51.9
3.53
3.54
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 59
3.55.2
3.55.3
3.55.4
3.55.5
3.55.6
3.55.7
3.55.8
3.55 9
3.55.10
3.55.11
3.55.12
3.56
GPGS
Subject
DN 504
July 16, 1997
Page 60
3.56.1.2
3.56.1.3
3.56.1.4
3.56.1.5
3.56.1.6
3.56.1.7
3.56.1.8
3.56.1.9
3.56.1.10 Verify, where possible, flow and pressures of all fluid systems.
4
START-UP
General guidelines for the proper start-up of the Gas Turbine-Generator are provided in the
following sequence of activities:
4.1
Ground checks.
4.1.2
Battery checks.
4.1.3
4.1.4
4.1.5
4.1.6
4.1.7
4.1.8
4.1.9
GPGS
Subject
4.1.10
4.1.11
4.1.12
4.1.13
4.1.14
4.1.15
4.1.16
4.1.17
4.1.17.2
4.1.17.3
Hydraulic System
DN 504
July 16, 1997
Page 61
4.1.17.4
4.1.17.5
Humidity Sensor
4.1.17.6
4.1.17.7
4.1.17.8
GPGS
Subject
4.1.17.9
4.1.19
4.1.20
4.1.18
4.1.19.1
Overspeed
4.1.19.2
Speed control
4.1.19.3
Over-temperature control
4.1.19.4
FSR/Temperature monitoring
4.1.19.5
4.1.19.6
4.1.19.7
Steam injection
4.1.19.8
LVDT calibrations:
4.1.19.9
DN 504
Steam Injection
Servo Valves:
Liquid Fuel
Steam Injection
GPGS
Subject
4.1.21
4.1.22
4.2
DN 504
July 16, 1997
Page 63
Initial Fire
4.1.23
4.1.24
Synchronization checks
4.1.25
4.1.26
4.1.27
Emissions Tests
4.1.28
Performance Tests
Connection Checks
4.2.1.1
Connection checks
4.2.1.2
Sensing voltage
4.2.1.3
Sensing current
4.2.1.4
4.2.1.5
Field
4.2.1.6
4.2.1.7
4.2.1.8
4.2.1.9
Input/Output connections
4.2.2
4.2.3
Off-line checks
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 64
4.2.4
4.2.3.1
4.2.3.2
AC regulator response
On-line checks
4.2.4.1
4.2.4.2
4.2.5
4.2.6
4.2.7
4.2.8
4.2.9
Alarm checks:
4.2.10
4.2.9.1
Stator Temperature
4.2.9.2
Underfrequency
4.2.9.3
4.2.9.4
Voltage Balance
4.2.10.2
4.2.10.3
4.2.10.4
4.2.10.5
4.2.10.6
4.2.10.7
GE Energy Services
GPGS
Subject
4.3
4.4
DN 504
July 16, 1997
Page 65
4.3.2
4.3.3
4.3.4
4.3.5
4.3.6
4.3.7
4.3.8
Roll turbine to ignition speed, observe ignition system operation, and allow
turbine to accelerate to full-speed no-load (FSNL).
4.4.2
4.4.3
4.4.4
4.4.5
4.4.6
4.4.7
GE Energy Services
GPGS
Subject
4.5
4.6
4.7
DN 504
July 16, 1997
Page 66
4.4.8
4.4.9
Perform third mechanical overspeed test. (Turbine must trip within 30 RPM
of second overspeed test trip point).
4.5.2
4.5.3
4.5.4
Perform load checks at 25, 50, 75, and 100 percent load points.
4.5.5
4.5.6
4.6.2
4.6.3
4.6.4
PERFORMANCE TESTS
4.7.1
Conduct Capacity and Heat Rate Tests per the Contract Requirements.
4.7.2
4.7.3
4.7.4
Conduct the Exhaust Gas Emissions Tests per the Contract Requirements
GE Energy Services
GPGS
Subject
4.7.5
DN 504
July 16, 1997
Page 67
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 68
EXHIBIT A
TRUCK
LOADS
WEIGHT
in pounds
(Appx.)
635,000
505,000
SIZE
in Feet
L' x W" x H"
34.6 x 15.3 x 16.4
34.5 x 15.7 x 13.8
5,000
Est. 40 ea.
990
Est. 2,400
4,800
103,260
95,000
52,000
Later
16,121
59,100
20,300
26,200
3,000
4,000
5,600
60,000
Later
2,400
2,300
14,000
25,000
18,500
38,820
15,700
34,600
11,000
5,700
3,270
2,000
26,000
GPGS
Subject
DN 504
July 16, 1997
Page 69
ITEM
- Plenum Support Structure
- Plenum Extension (2 pc.)
- Plenum Cone (inlet case ext.) (2 pc.)
- Lower Quarter Section (2 pc.)
- Upper Quarter Section (2 pc.)
- Lot 1
- Lot 2
- Lot 3
Inlet Ductwork (MLI A041)
Transition Duct (1 pc.)
Expansion Joint (Kit, asm. at site)
Elbow Duct Upper(1 pc.) w/Trash Screen
Elbow Duct Lower (1 pc.)
Heating Duct (1 pc.)
Silencer Duct (1 pc.) w/16 Panels
Empty Duct (1 pc.)
Support Steel
Miscellaneous
- Walkway Assembly (Center)(4 pc.)
- Walkway Assembly (L.H. and R. H.)(2 pc.)
- D15 Weather Hoods (Center Modules)
(15 pc. per module)(4 Modules)
- D15 Weather Hoods (L.H. and R.H.)
(15 pc. per module)(2 Modules)
- Sloped Roof
- Hopper (6 pc.)
- Pipe/Tubing
- Hand Rails
- Hardware
- Filter Cartridges (576 pairs)
Inlet Filter House Transition Duct
- Top Section (1 pc.)
- Floor Section (1 pc.)
- Side Section (1 pc.)
- Side Section (1 pc.)
TRUCK
LOADS
WEIGHT
in pounds
(Appx.)
4,320
800
1,569 ea.
9,500 ea.
5,400 ea.
1,650
2,960
600
SIZE
in Feet
L' x W" x H"
Loose Parts
12.0 x 6.0 x 1.5
10.6 x 5.3 x 3.6
8.5 x 12.2 x 7.9
8.5 x 5.6 x 7.4
12.0 x 6.0 x 1.3
10.9 x 5.5 x 3.4
4.5 x 2.9 x 2.8
4
2
2
11,850
720
17,360
21,750
9,500
44,500
6,185
86,000 ea.
1,440
3,368 ea
5,180 ea
1,650
2,160
1
1
1
1
1
1
2
4,280
20.7 x 7.7 x 3.3
405 ea.
6.7 x 3.8 x 3.1
1,800
42.0 x 1.2 x 0.8
2,142
10.7 x 7.7 x 2.7
2,554
10.0 x 4.0 x 4.0
50 ea. Ea. Shipped in box
9,900
2,508
700
700
34,417
10,170
12,115
11,005
13,577
13,425
2,000
4,500
2
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 70
ITEM
WEIGHT
in pounds
(Appx.)
5,500
5,600
850 ea.
246 ea.
138 ea.
5,600
5,000
1,150
1,445
1.150 ea.
1,950
SIZE
in Feet
L' x W" x H"
12.3 x 22.1 x 1.5
24.5 x 5.4 x 12.7
12.0 x 4.0 x 0.5
8.0 x 3.0 x 0.3
4.5 x 2.1 x 0.3
24.6 x 5.5 x 12.0
10.4 x 5.5 x 4.1
11.0 x 7.5 x 0.5
11.0 x 6.9 x 0.5
11.0 x 7.6 x 0.4
9.0 x 4.2 x 4.3
880
880
1,300
1,080
246
800
18,000
Later
600
Later
1.0 x 0.5 x 2.0
600
600
200
8,000
Later
Later
1.0 x 0.5 x 2.0
1.0 x 0.5 x 0.5
11.6 x 3.3 x 1.5
85
100
110
80
153
595
140
350
80
MSD MISCELLANEOUS
Junction Boxes (ML 1155) 1 Pallet
Junction Boxes (ML 1150) 1 Pallet
Humidity Sensor (ML A122)
135
135
100
TRUCK
LOADS
GE Energy Services
GPGS
Subject
DN 504
July 16, 1997
Page 71
ITEM
Sensor Inlet/Exhaust (ML 0559)
Gas Fuel Flow Metering Tube (ML 0639)
Tool Kit (ML F066)
- Wood Box No. 1
- Wood Box No. 2
- Wood Box No. 3
- Wood Box No. 4
Station Control Cables (ML A062)
- Box No. 1
- Box No. 2
- Box No. 3
- Box No. 4
- Box No. 5
- Box No. 6
Batteries (for PEECC) (ML1207)
- Wooden Case
- Wooden Case
MSD GAS TURBINE ON/OFF-BASE PIPING
Lube Oil Pipe No. 1 Bearing (ML 0905)
Lube Oil Pipe Feed and Drain (ML 0906)
Lube Oil Pipe No. 2 Bearing (ML 0907)
Control Oil Pipe (ML 0908)
Cooling and Sealing Air Pipe (ML 0909)
Cooling Water Pipe (ML 0915)
Air Extraction Pipe (ML 0924)
Water Wash Pipe (ML 0953)
Liquid Fuel Pipe (ML 0961)
Fuel Gas Pipe (ML 0962)
Fire ProtectionTurbine Compt. (ML 0964)
Water Injection Pipe (ML 0968)
Base Interconnect Pipe (ML 0969)
- Wooden Box
Exhaust Frame Cooling Air Pipe (ML 0972)
Exhaust Plenum Drain Pipe (ML 0976)
Inlet Plenum Drain (ML0979)
Performance Monitoring (ML 0987)
Fire ProtectionExhaust (ML 0995)
Lube Oil Flushing Hoses (ML A125)
TRUCK
LOADS
WEIGHT
in pounds
(Appx.)
790
1,000
SIZE
in Feet
L' x W" x H"
4.0 x 4.0 x 4.0
30.0 x 1.5 x 1.5
280
525
1,110
650
971
994
1,328
1,473
1,532
944
5,609
1,220
2,700
3,600
2,650
1,825
30,450
1,220
5,400
1,340
1,400
9,850
790
155
12,500
7,400
10,500
1,310
200
45
160
1,640
GE Energy Services