Académique Documents
Professionnel Documents
Culture Documents
BRIDGE CONSTRUCTION
1. INTRODUCTION
Bridges play an important role in linking different parts of highway networks,
and therefore have a great impact on the capacities of such networks. Bridges are
massive structures that require large amounts of materials, skilled labor, and heavy
machinery for their construction. Therefore, the decision regarding the most
convenient construction system should be based on careful evaluation of all
applicable alternatives, and using evaluation criteria appropriate for each project.
The construction of bridges had started very long time ago. However, the
bridge construction technologies have evolved in the 20th century, and were fueled by
the Industrial Revolution. At the turn of the century, steel bridges were riveted
together, not bolted; concrete bridges were cast in place, not precast; and large bridge
members were built from lacing bars and smaller sections, not rolled in one piece.
Construction techniques such as post-tensioning, slurry walls, soil freezing, and
shield tunneling had not yet been conceived. Bridge construction is changing as the
new millennium begins. New construction techniques and new materials are
emerging. There are also new issues facing the bridge construction technologies
relative to the research needs associated with the new techniques and materials
introduced.
Over many decades, various construction systems for bridges have been
developed and successfully used. Most of these systems, with advances and
modifications, are still in use until today. The objective of this material is to review
the state of the art in the area of bridge construction. This involves the latest
construction systems and future trends for this type of structures.
For each construction system, a brief description is outlined that includes:
system concept, main system components, construction sequence, system advantages,
and system disadvantages and limitations. In addition, the bridge construction in
Egypt is discussed in view of the applicability of various construction systems under
the Egyptian construction environment. This includes the potential of using the
promising systems yet to be applied in Egypt.
-1-
Bridge Construction
-2-
Bridge Construction
-3-
Bridge Construction
Method of Construction
Cast in-situ:
On Falsework
Cantilever Segmental
Span by Span
Post-tensioned Bridges
Precast:
Cable-Stayed Bridges
Suspension Bridges
Incremental Launching
Cantilever Segmental
Span by Span
Incremental Launching
Free Cantilever
Balanced Cantilever
-4-
Bridge Construction
Description
Cable-Stayed Bridges
Suspension Bridges
Site
Structure
Span Lengths
Condition
Level
Short
(40 - 80 m)
Structure
Depth
Inaccessible
High
Inaccessible
High
Inaccessible
High
Inaccessible
High
Inaccessible
High
Inaccessible
Very High
Long
(200 to 1,000 m)
Variable
Inaccessible
Very High
Very Long
(500 to 2,000 m)
Variable
Short
(40 - 80 m)
Long
(up to 250 m)
Long
(up to 200 m)
Short
(40 70 m)
-5-
Variable
Constant
Variable
Variable
Variable
Other Aspects
Sharp horizontal and
vertical curvatures, as
well as roadway
superelevations.
Straight or slightlycurved superstructures.
Crossing navigable
waterways.
Crossing navigable
waterways.
Long viaducts with
short spans.
Crossing deep rivers,
deep valleys, and
mountains.
Crossing deep rivers,
deep valleys, and
mountains.
Bridge Construction
Construction Sequence
1.
2.
3.
4.
5.
6.
System Advantages
1.
2.
3.
4.
The main advantages of the launching truss system include the following:
Suitability for inaccessible sites, where the use of falsework is not economical
or not permitted.
Progress of work without interference with traffic under the bridge.
Economy, speed, and improved quality of mass production.
Adaptability to sharp curvatures, large grades, and roadway superelevations.
-6-
Bridge Construction
Bridge Construction
-8-
Bridge Construction
Bridge Construction
- 10 -
Bridge Construction
System Advantages
The main advantages of the incremental launching construction (deck pushing
system) include the following:
1. Suitability for inaccessible sites, where the use of falsework is not economical
or not permitted.
2. Riding the learning curve through a repetitive pattern of operations.
System Disadvantages and Limitations
The main disadvantages of the deck pushing system include the following:
1. Requirement of a casting yard and pushing equipment.
2. Requirement of a large labor force during the launching operation.
3. Significant increase in longitudinal prestressing to resist the cantilever
moments during the launching operation, which increase proportional to the
square of the cantilever length.
4. Unsuitability for complex roadway geometry. The system is limited to
constant- depth superstructures, with straight or slightly curved alignment.
2.3.3 Cast-in-Place, Balanced Cantilever Construction
(Cantilever Carriage System)
System Concept
In this system, the superstructure is cast in segments in traveling forms. These
forms are supported from one end on the completed part of the superstructure, while
the other end is a free cantilever. After the concrete reaches the required strength, the
forms are moved forward and prepared for the next segments.
Main System Components
The main components of this system include the following:
1. Form Travelers. The basic elements of a typical form traveler include the main
frames, the guide rails, and the suspended platforms (Fig. 2.4). The main
frames run on the upper guide rails and both the frames and the rails are
attached to the finished portion of the bridge superstructure by means of tiedown anchors. All forms for the superstructure are suspended from the main
frames; the forms can be stripped in a single operation by lowering the main
frames. Modern form travelers are reusable and very flexible with respect to
changing geometry of the bridge superstructure and its alignment, including
camber. They allow all operations (such as advancing, adjusting of elevations,
and stripping of forms) to be carried out either hydraulically or electrically, and
controlled by a single central panel.
- 11 -
Bridge Construction
2. Pier Brackets. They are used to provide support for the formwork of pier
tables. There are many types of pier brackets depending upon the local
conditions. If a pier is low, the pier brackets may be supported on the pier
footing or directly on the ground. On the other hand, if a pier is high, the pier
brackets are usually built out from the pier cap and pier shafts.
3. Local Bracings. They are required for the closure pours.
Construction Sequence
The construction of superstructures by the cantilever carriage system starts
with casting the pier tables. Cast-in-place segments (about 5 m long) are then added
to each side of the pier table alternatively in order to maintain balanced cantilevers,
which will minimize the out-of-balance moment at the pier. After the two cantilevers
reach the mid-span, the form travelers are stripped, to be erected on the next
completed pier table. The superstructure is completed by closure pours connecting the
cantilevers at the middle of each span. Fig. (2.5) shows the sequence of construction
using form travelers, whereas Fig. (2.6) shows the closure pour.
System Advantages
The main advantages of the cantilever carriage system include the following:
1. Suitability for inaccessible sites, where the use of falsework is not economical
or not permitted.
2. Spanning long navigation channels, where navigation is not to be interrupted.
3. High labor efficiency compared to other systems.
4. High level of efficiency and effectiveness for long spans, where the
cantilevering operation can be continued for a large number of segments.
System Disadvantages and Limitations
The main disadvantages of the cantilever carriage system include the
following:
1. Requirement of special equipment and skilled labor.
2. Need for very high precision during placement of segments so that the two
cantilevers meeting at the middle of each span have the same level.
3. Significant increase in superstructure reinforcement to resist the cantilever
moments.
4. Limited length of segments (from 2 6 m) according to the capacity of form
travelers and the optimum use of labor force.
5. Low construction progress rate due to the limited length of segments.
- 12 -
Bridge Construction
- 13 -
Bridge Construction
- 14 -
Bridge Construction
- 15 -
Bridge Construction
3. Erection Equipment. A variety of equipment types can be used for erecting the
segments; such as truck cranes, crawler cranes, floating cranes, launching
girders, cableways, etc. However, a launching truss equipped with hoists is
commonly used for precast segmental, balanced cantilever construction.
Fabrication of Precast Segments
To achieve a perfect fit between the ends of adjacent segments, each segment is
cast against the end face of the preceding one. This is called match-casting of
segments. The segments are then erected in the same order in which they were cast.
Segment joint faces need to be clean of any dirt for match-casting.
An epoxy resin, about 0.8 mm thick, is normally applied to the match-cast
contact surface. It serves as a bonding and leveling agent that transfers the shear and
bending stresses to the adjacent segment. Shear keys are usually provided in each
web of the segments to handle the erection stresses prior to the epoxy achieving the
final strength.
Typical Precasting Cycle
A typical precasting cycle involves the following operations:
1. Steam curing of freshly cast segments.
2. Releasing of pre-tensioning strands by cutting them.
3. Quality control and testing of concrete samples.
4. Removal of internal formwork units from the new segment.
5. Lifting of previously cast segment from its position for match-casting into
storage area.
6. Rolling of the new segment out of the formwork, and positioning it for matchcasting according to the required overall alignment.
7. Cleaning of the joint face and the bulkhead prior to casting the next segment.
8. Pre-assembly of reinforcement bars (in cages) to speed up placement.
9. Arrangement and stressing of pre-tensioning strands prior to concrete
placement.
10.Placement and curing of the concrete segment.
Erection of Precast Segments
The precast segments are picked from the transport trailer and launched to their
spans by means of the launching truss. They are then lowered to their level where the
epoxy resin is applied to the contact surface with the previously erected segments.
They are finally tied to the previously erected segments by post-tensioning cables.
- 16 -
Bridge Construction
The precast segments are erected on either sides of the pier alternatively in
order to maintain balanced cantilevers, which will minimize the out-of-balance
moment at the pier. After the two cantilevers reach the mid-span, the launching truss
is moved forward to the next span, where it will be ready for erecting another pair of
balanced cantilevers. The erection procedure is described in detail in Fig. (2.7). The
launching truss at work is shown in Fig. (2.8).
System Advantages
The main advantages of the precast segmental, balanced cantilever
construction include the following:
1. Economy, speed, and improved quality of mass production.
2. Avoidance of interference with traffic or navigation by using an erection truss.
3. Low labor requirement for both fabrication and erection operations.
4. Adaptability to any horizontal or vertical curvature or any required roadway
superelevation.
System Disadvantages and Limitations
The main disadvantages of the precast segmental, balanced cantilever
construction include the following:
1. Requirement of a casting yard and special transport and erection equipment.
2. Need for a high degree of geometry control during the fabrication of precast
segments (match-casting).
3. Need for very high precision during the erection of precast segments so that the
two cantilevers meeting at the middle of each span have the same level.
4. Significant increase in superstructure reinforcement to handle the erection
stresses as well as the cantilever moments.
5. Temperature and weather limitations regarding the mixing and placing of
epoxy joint material.
- 17 -
Bridge Construction
Bridge Construction
Bridge Construction
- 20 -
Bridge Construction
System Advantages
The main advantages of the flying shuttering system include the following:
1. Suitability for long viaducts with short spans (40 70 m), where the work
continues for a large number of spans.
2. Elimination of the need for falsework supports or cranes at the ground level.
3. Progress of work without interference with the traffic under the bridge.
4. High construction progress rate (A typical rate of about 300 m2 of deck surface
area per week for span lengths of 40 m was reported).
System Disadvantages and Limitations
The main disadvantages of the flying shuttering system include the following:
1. Requirement of special equipment (stepping formwork and form trusses).
2. Unsuitability for long spans.
Bridge Construction
Bridge Construction
Bridge Construction
Bridge Construction
(a)
(b)
(d)
(c)
- 25 -
Bridge Construction
Fig. (2.15): Anchorage System for Parallel-Wire Cables, 6th of October Bridge
- 26 -
Bridge Construction
- 27 -
Bridge Construction
- 28 -
Bridge Construction
Bridge Construction
Table (3.1): Bridge Construction Systems and Their Major Applications in Egypt
System
Code
A
B
System
Precast, Prestressed
Concrete Girders
(Launching Truss)
Incremental
Launching
(Deck Pushing)
Cast-in-Place,
Balanced Cantilever
(Cantilever Carriage)
Major Applications
Precast Segmental,
Balanced Cantilever
Stepping Formwork
(Flying Shuttering)
Width
(m)
Completion
Date
33 40
9.0 24.0
1988
40
31@25, 2@23.5
34.2, 7@40.7, 5@40, 34
22.0
16.6
2@10.75
1998
1986
1987
104, 2@69
110, 2@100, 2@70
115, 2@69
130, 2@75
120, 2@69
120, 2@60
34.6
34.0
2@17.8
2@17.8
2@11.0
2@22.5
2@22.5
1969
1976
1986
1990
1990
1998
2000
42
18.4
1998
40
20.0
2001
Span Lengths
(m)
- 30 -
Bridge Construction
Suspension Bridges
- 31 -
2@10.9
1998
404, 2@163
20.0
2001
Bridge Construction
Bridge Construction
Site Conditions
Construction under
Running Traffic
II
III
IV
Construction Across
Navigable
Waterways
Construction Across
Deep Waterways and
Mountains
Construction at
Accessible Sites*
System
Code
System Description
A
B
E
C
D
F
F
G
A*
B*
E*
* These systems may be feasible for accessible sites, particularly when the superstructure is
very high (high approach spans and viaducts).
- 33 -
Bridge Construction
3.4
- 34 -