Various parts to be covered:

1.Clubbing of Items, Booking of Dimensions ,Measurements ,Description of


items, waste deduction .works to be Measured separately, Bill of quantities,
Measurement in stages.

Works to be Measured Separately:

Work in or under water,


Work in liquid mud,
Work in or under foul positions,
Work interrupted by tides,
Where special pumping due to causes other than rains and subsoil water is r
to, the same shall be measured separately.

SN
o

BW
Applications

Unit
s

Measurement /Deductions and


Remarks

1.

Excavation of
trenches

m3

measurement for excavation of trenches for


laying pipelines

2.

Concrete beds,
haunchings and
coverings,

R.M

Stating size of the pipe, dimensions and


mix of concrete.

3.

Heat Treatment

-------

Described and enumerated separately

4.

Hydrostatic tests R.M


and radiographic
tests

Described and measured in running metres


for hydrostatic tests and per centimetre
length for various sixes of pipes for
radiographic tests.

5.

Pigging, Pickling and


Purging

---------

Pigging, pickling and purging


with inlet gases shall be
separately enumerated.

6.

Insulation

R.M

Stating the type and size of the


pipes and insulation around
valves, and other ancillaries and
to pipe fittings are to be
enumerated and measured
separately.

Miscellaneous Works:
Miscellaneous works, such as crossing of railway lines and
culverts, cutting and reconditioning of pavements, deviation of
piplines and cables, dismantling and reconditioning of works, etc,
shall be measured as per relevant standard.
Connection to submains or other pipelines shall be fully described
and enumerated.