ASSENT STEEL STRUCTURAL ERECTION STATUS

1. 03/02/2016
Steel structural column erected on 03/02/2016 for GTB 13 Grit line GG and GF
(GG1, GG2, GG3, and GG4) and (GF1, GF2, GF3) Without QA/QC Approved
1.
2.
3.
4.

Without Approved Method statement.


Without Approved ITP.
Without Approved Erection Drawing.
Without Closed NCR -008 by OE.

2. 04/02/2016
Assent Raised Receiving Inspection (UHP-SCT-RRI-S-13-0009) Column and Girder
for GTB10 GG and GF at 04/02/2016.
1.
2.
3.
4.

Without Approved ITP.


Without Approved Erection Drawing.
Without Closed NCR -008 by OE.
Without Approved Method statement.
5. (UHP-SCT-RRI-S-13-0009 RRI Was Rejected.
6. QA/QC Raised NCR for Column Erection

3. 06/02/2016
They raised RFI (UHP-SCT-RFI-S-13-0001 AND 2) for Survey of Setting out of
Anchor bolt GG and GF. But they already erected Column (GG1, GG2, GG3 and
GG4)
1. Without Approved ITP
2. Without Approved Erection Drawing.
3. RFI was HOLD

4. 06/02/2016

They raised RRI (UHP-SCT-RRI-S-13-0010) for receiving Inspection (Column and


Grid, beams, Splice plate, post, Bet plate
1. Without Approved ITP
2. Without Approved Erection Drawing.
3. RRI was HOLD
5. 07/02/2016
They raised RRI (UHP-SCT-RRI-S-13-0011) receiving Inspection for fasteners
(Column and Grid, beams, Splice plate, post, Bet plate)
1. Without Approved ITP
2. Without Approved Erection Drawing.
3. RRI was HOLD

5. 08/02/2016
Installed Column & Beams Without proper Support
1. QA/QC raised QOR-0074 to ASSENT

6. 08/02/2016
Column and girder splice joint Paint. Assent Submitted paint removal
Procedure for Approval
7. 08/02/2016
They raised RRI (UHP-SCT-RRI-S-13-0012) receiving Inspection for (Column and
Grid, beams, Splice plate, post, Vertical bracing, Loos plates)
1. Without Approved ITP.
2. RRI was HOLD

Painting damage

Galvanizing problem

Anchor bolt damage