Task 1:
Figure 1 below is an illustration of two signalised intersections which are to be
optimised. Based on the given data, you are required to determine optimum
common cycle time, green time split for each intersection and offset time.
INTERSECTION 1
Phase 1
Phase 3
INTERSECTION 2
Phase 2
Phase 1
Phase 2
Phase 4
Phase 3
Solution\\
Intersection 1
phase
Number of
lanes
saturation
flow per lane
(pcu/hr)
Saturation
flow
(pcu/hr)
1
2
3
4
2
2
2
2
1800
1800
1800
1800
3600
3600
3600
3600
Actual
flows
(pcu/hr)
Flow / saturation
flow ration
Green time
split
0.33
0.17
0.06
0.29
0.85
0.38
0.20
0.07
0.34
1
1170
625
220
1050
Sum Y
Cycle time
Intersection 2
phase
Number of
lanes
saturation
flow per lane
(pcu/hr)
Saturation
flow
(pcu/hr)
1
2
3
2
2
2
1800
1800
1800
3600
3600
3600
Actual
flows
(pcu/hr)
Flow / saturation
flow ration
Green time
split
0.25
0.13
0.28
0.65
0.38
0.19
0.43
1
900
450
1000
Sum Y
Cycle time
Offset
Ti = (L/S) (Q*H + Losses)
Losses = 2 sec.
Headway = 2 sec/veh
Speed = 10m/sec.
Q= 9 p.c
Ti = 17 sec.