STATEMENT OF WORK

Project:
D ATE :
Manager:

Converting a Powerful Workshop to an Online Format


November 1, 2015
Tiffany Morlan

Purpose:
Funding from the National Health Foundation has been provided to design and develop an online version of the very successful face-to-face workshop,
Man-to-Man, which has been previously developed by Midwestern State Universitys Professor Essex. This workshop was designed to improve sexual
health for gay and bisexual men. It has been delivered via face-to-face around the United States monthly for the past five years (Portny, Mantel, Meredith,
Shafer, Sutton, & Kramer, 2008).
Objectives:
Develop a HIV/AIDs prevention workshop for gay and bisexual men for delivery online.
Use the ten components of the sexual health model as the foundation of the online workshop.
Incorporate contemporary principles of e-learning into the online workshop (Portny, Mantel, Meredith, Shafer, Sutton, & Kramer, 2008).
Primary Roles:
Tiffany Morlan, Project Manager
Professor Clark Essex, Subject Matter Expert
Professor Pedro Lopez, Instructional Designer
Constraints:
Per the grant provided by the National Health Foundation, this project is to be designed, developed, and evaluated over a two-year period.
While Professor Essex successfully developed the face-to-face workshop, he is not able to develop the workshop in an online format.
Assumptions:
Grant Amount: $5,000.00
Professor Essex and Professor Lopez are both full-time faculty members

PROJECT SCOPE STATEMENT


Project:
D ATE :
Manager:

Converting a Powerful Workshop to an Online Format


November 16, 2015
Tiffany Morlan

Statement of Project Scope:


To design and deliver a HIV/AIDs prevention workshop geared toward gay and bisexual men; which goal is to inform workshop participants of prevention
measures to take when utilizing the Internet to connect with other men. The timeline for development, design, and implementation is 4 months and there
will be deliverables to keep the project on track weekly during the timeline. Deliverables will include reviewing current resources in the face-to-face
workshop, brainstorming ideas to translate the resources into an online form, designing the modules of content, delivering the modules of content, finalizing
any agreed upon content edits, publishing the content to the online learning management system, and implementing (piloting) the workshop. Because
participants will complete the workshop voluntarily, we will also need to organize a group of volunteers to complete the workshop once it is ready to first be
implemented to obtain feedback/data to adjust the workshop for future use.
Project Purpose:
Funding from the National Health Foundation has been provided to design and develop an online version of the very successful face-to-face workshop,
Man-to-Man, which has been previously developed by Midwestern State Universitys Professor Essex. This workshop was designed to improve sexual
health for gay and bisexual men. It has been delivered via face-to-face around the United States monthly for the past five years (Portny, Mantel, Meredith,
Shafer, Sutton, & Kramer, 2008).
Project Objectives:

Develop a HIV/AIDs prevention workshop for gay and bisexual men for delivery online.
Use the ten components of the sexual health model as the foundation of the online workshop.
Incorporate contemporary principles of e-learning into the online workshop (Portny, Mantel, Meredith, Shafer, Sutton, & Kramer, 2008).

Assumptions:

Grant Amount: $5,000.00


Professor Essex and Professor Lopez are both full-time faculty members
Timeline: 4 Months

Stakeholder List and Descriptions:

Tiffany Morlan (Jennie Davenport), Project Manager


o Role: To manage the project and work with Professor Lopez to translate the workshop into an online environment.
o Inclusion: Person to be included in all aspects of the project and consulted with in any form to ensure project deadlines are met and the scope
stay intact.
Professor Clark Essex, Subject Matter Expert
o Role: To provide knowledge and subject knowledge to Professor Lopez.
o Inclusion: Person to be included in aspects of subject matter.
Professor Pedro Lopez, Instructional Designer
o Role: To manage the design aspect of the online workshop and to work closely with both Tiffany Morlan and Professor Essex to ensure design
expectations are being met.
o Inclusion: Person to be included heavily information regarding the management of the project and in all aspects of the project design.

WORK BREAKDOWN STRUCTURE


Converting a Powerful Workshop to an Online Format:
Work Breakdown Structure

Plan

Deliverable Details

Deliverables

Pilot/Implementation

Project Objectives

Kickoff Meeting

Deliverable Chunks in Modules

Strategy for Pilot

Project Scope

Review Face-to-Face Workshop

Assembled Deliverbales in LMS

Assemble Pilot Group

Identification of Deliverables

Design Plans

Review of LMS Workshop

Implement Workshop with Pilot


Group

Timeline for Deliverables

Stakeholder Review

Formal Approval

Gather Feedback from Pilot


Group
Budget Allocations

Formal Approval

Make Revisons per Feedback


Stakeholder Review of Plan

Formal Approval

Formal Approval for Revised and


Completed Workshop

Team Member Responsibilties Chart

Project Manager

Subject Matter Expert

(Tiffany Morlan)

(Prfessor Clark Essex)

Instructional Designer
(Professor Pedro
Lopez)

Manage Overall
Project

Provide Subject
Matter

Manage Deliverables
Timline

Schedule Meetings

Attend Scheduled
Meetings

Design Deliverables

Ensure Deadlines are


Met

Assist with Assembling


Pilot Group

Publish Deliverables to
LMS

Manage Budget

Attend Scheduled
Meetings

Formal Approval

Design Approval

PROJECT SCHEDULE
1/4 1/11 1/18 1/25 2/1
Establish Project Objectives - TM
Create Project Scope - TM
Identify Deliverables - TM
Create Timeline for Deliverables - TM
Create Budget Allocations - TM
Submit Stakeholder Plan Review - TM
Submit Plan for Approval - TM
Receive Plan Approval - TM
Send Invite for Kickoff Meeting - TM
Hold Formal Kickoff Meeting - ALL
Review Face-to-Face Workshop - ALL
Establish Workshop Design Plans - ALL
Submit Deliverable Stakeholder Review - TM
Submit Deliverable Details for Approval - TM
Receive Deliverable Details Approval - TM
Send Invite for Pre-Development Meeting - TM
Hold Pre-Development Meeting - ALL
Complete Module 1 Development - CE & PL
Complete Module 2 Development - CE & PL
Complete Module 3 Development - CE & PL
Complete Module 4 Development - CE & PL
Assemble Module Deliverables in LMS - PL
Review Complied LMS Workshop - ALL
Submit Deliverables for Approval - TM
Receive Deliverables Approval - TM
Send Invite for Pilot Strategy Meeting - TM
Hold Meeting to Discuss Pilot Strategy - ALL
Assemble Pilot Group - CE & PL
Implement Workshop with Pilot Group - CE
Gather Feedback from Pilot Group - CE & PL
Send Invite for Final Revisions Meeting - TM
Meet to Discuss Final Revisions - ALL
Make Final Revisions - PL
Submit Completed Workshop for Approval - TM

2/8 2/15 2/22 2/29 3/7 3/14 3/21 3/28 4/4 4/11 4/18 4/25 5/2

5/9

RESOURCE ALLOCATION PLAN


Task

Establish Project Objectives


Create Project Scope
Identify Deliverables
Create Timeline for Deliverables
Create Budget Allocations
Submit Stakeholder Plan Review
Submit Plan for Approval
Receive Plan Approval
Send Invite for Kickoff Meeting
Hold Formal Kickoff Meeting
Review Face-to-Face Workshop
Establish Workshop Design Plans
Submit Deliverable Stakeholder Review
Submit Deliverable Details for Approval
Receive Deliverable Details Approval
Send Invite for Pre-Development Meeting
Hold Pre-Development Meeting
Complete Module 1 Development
Complete Module 2 Development
Complete Module 3 Development
Complete Module 4 Development
Assemble Module Deliverables in LMS
Review Complied LMS Workshop
Submit Deliverables for Approval
Receive Deliverables Approval

Person(s) Responsible for


Completion
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
All Team Members - ALL
All Team Members - ALL
All Team Members - ALL
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM
All Team Members - ALL
Clark Essex & Pedro Lopez - CE &
PL
Clark Essex & Pedro Lopez - CE &
PL
Clark Essex & Pedro Lopez - CE &
PL
Clark Essex & Pedro Lopez - CE &
PL
Pedro Lopez - PL
All Team Members - ALL
Tiffany Morlan - TM
Tiffany Morlan - TM

Start Date

End Date

Duration
Days

Duration
(Hours per
Day)

1/4/2016
1/4/2016
1/8/2016
1/8/2016
1/11/2016
1/13/2016
1/18/2016
1/22/2016
1/25/2016
1/27/2016
1/28/2016
1/28/2016
2/2/2016
2/5/2016
2/10/2016
2/11/2016
2/15/2016
2/16/2016

1/4/2015
1/4/2015
1/8/2016
1/8/2016
1/12/2016
1/15/2016
1/21/2016
1/22/2016
1/25/2016
1/27/2015
1/29/2016
1/29/2016
2/4/2016
2/5/2016
2/10/2016
2/11/2016
2/15/2016
2/19/2016

1
1
1
1
2
3
4
1
1
1
2
2
4
1
1
1
1
4

2
2
3
3
8
2
1
1
1
2
3
4
2
1
1
1
2
20

Cost of
Effort (In
Dollars)
$40
$40
$60
$60
$160
$40
$20
$20
$20
$120
$180
$320
$40
$20
$20
$20
$120
$400

2/16/2016 2/19/2016

20

$400

2/22/2016 2/25/2016

20

$400

2/22/2016 2/25/2016

20

$400

2/26/2016 2/26/2016
2/29/2016 2/29/2016
3/1/2016 3/1/2016
3/4/2016 3/4/2016

1
1
1
1

2
2
3
1

$100
$120
$60
$60

Send Invite for Pilot Strategy Meeting


Hold Meeting to Discuss Pilot Strategy
Assemble Pilot Group
Implement Workshop with Pilot Group
Gather Feedback from Pilot Group
Send Invite for Final Revisions Meeting
Meet to Discuss Final Revisions
Make Final Revisions
Submit Completed Workshop for Approval

Tiffany Morlan - TM
All Team Members - ALL
Clark Essex & Pedro Lopez - CE &
PL
Clark Essex
Clark Essex & Pedro Lopez - CE &
PL
Tiffany Morlan - TM
All Team Members - ALL
Pedro Lopez - PL
Tiffany Morlan - TM

3/5/2016 3/5/2016
3/8/2016 3/8/2016
3/15/2016 3/18/2015

1
1
4

1
3
16

$60
$60
$640

3/21/2016 4/15/2015
4/18/2016 4/20/2016

26
3

40
8

$300
$320

1
3
3
1

$20
$180
$60
$20
$4,900

4/20/2016
4/22/2016
4/25/2016
4/27/2016

4/20/2016
4/22/2016
4/26/2016
4/27/2016

1
1
2
1
Total Estimated Cost

PROJECT COMMUNICATIONS PLANNER


Receiver
Tiffany Morlan
(Project
Manager)

Information
Individual will house all information in regard
to the project. This person will also schedule
meetings, etc. with team members, so they will
be the point of contact for such occurrences.

Clark Essex
(Subject
Matter Expert)

Individual will need to receive meeting invites


and attend meetings. They will also be involved
with information regarding module
development and heavily involved in the pilot
group phase.

Pedro Lopez
(Instructional
Designer)

Individual will need to receive meeting invites


and attend meetings. They will be heavily
beloved with the information in module
development, involved in the pilot phase, and
heavily involved in the revision phase.

National

As the source of the funding for this project,

Type of Communication
N/A

Email
Team Meetings
Face-to-face
Internet
Ad hoc
verbal/written

Email
Team Meetings
Face-to-face
Internet
Ad hoc
verbal/written

Email status report

How Often (Weekdays Only)


Weekly: 1/4/16-2/15/16
Project plan and deliverable details stages
Daily: 2/29/16-3/5/16
Review workshop and deliverables stages
start of pilot stage planning
Daily: 4/20/16-4/27/16
Final revisions stage

Daily: 1/27/16-1/29/16
Kickoff meeting, workshop review and
design planning stages
Daily: 2/15/2016-2/25/16
Module development stage
Daily: 2/29/16
Review workshop meeting
Weekly: 3/8/16-4/20
Pilot stage
Daily: 4/22/16
Final revision meeting
Daily: 1/27/16-1/29/16
Kickoff meeting, workshop review and
design planning stages
Daily: 2/15/2016-2/26/16
Module development and assembly stages
Daily: 2/29/16
Review workshop meeting
Daily: 3/8/16-3/18/16
Pilot group meeting and assembly stage
Daily: 4/18/16-4/20/16
Pilot group feedback stage
Daily: 4/22/16-4/26/16
Final revisions stage
Monthly

Health
Association
(Stakeholder)
eduLearning
Systems
(Stakeholder)

this stakeholder will be informed of major


milestone completion items throughout the
project and once the project is completed for a
review.
As the project managers employer, this
stakeholder will also be informed of major
milestone completion items throughout the
project and once the project is completed.

Email status report

Monthly

COMMUNICATION POINTS TRACKING REPORT


Task

Person(s) Responsible for


Completion

Start Date

End Date

Submit Stakeholder Plan Review


Submit Plan for Approval
Send Invite for Kickoff Meeting

Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM

1/13/2016 1/15/2016
1/18/2016 1/21/2016
1/25/2016 1/25/2016

Hold Formal Kickoff Meeting


Review Face-to-Face Workshop
Establish Workshop Design Plans
Submit Deliverable Stakeholder Review
Submit Deliverable Details for Approval
Send Invite for Pre-Development Meeting

All Team Members - ALL


All Team Members - ALL
All Team Members - ALL
Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM

1/27/2016
1/28/2016
1/28/2016
2/2/2016
2/5/2016
2/11/2016

1/27/2015
1/29/2016
1/29/2016
2/4/2016
2/5/2016
2/11/2016

Hold Pre-Development Meeting


Complete Module 1 Development
Complete Module 2 Development
Complete Module 3 Development
Complete Module 4 Development
Review Complied LMS Workshop
Submit Deliverables for Approval
Send Invite for Pilot Strategy Meeting

All Team Members - ALL


Clark Essex & Pedro Lopez - CE & PL
Clark Essex & Pedro Lopez - CE & PL
Clark Essex & Pedro Lopez - CE & PL
Clark Essex & Pedro Lopez - CE & PL
All Team Members - ALL
Tiffany Morlan - TM
Tiffany Morlan - TM

2/15/2016
2/16/2016
2/16/2016
2/22/2016
2/22/2016
2/29/2016
3/1/2016
3/5/2016

2/15/2016
2/19/2016
2/19/2016
2/25/2016
2/25/2016
2/29/2016
3/1/2016
3/5/2016

Hold Meeting to Discuss Pilot Strategy


Assemble Pilot Group
Implement Workshop with Pilot Group
Gather Feedback from Pilot Group
Send Invite for Final Revisions Meeting

All Team Members - ALL


Clark Essex & Pedro Lopez - CE & PL
Clark Essex
Clark Essex & Pedro Lopez - CE & PL
Tiffany Morlan - TM

3/8/2016
3/15/2016
3/21/2016
4/18/2016
4/20/2016

3/8/2016
3/18/2015
4/15/2015
4/20/2016
4/20/2016

Meet to Discuss Final Revisions


Submit Completed Workshop for Approval

All Team Members - ALL


Tiffany Morlan - TM

4/22/2016 4/22/2016
4/27/2016 4/27/2016

Type of
Communication
Email
Email
Email
(Calendar Feature)
Face-to-face
Face-to-face
Face-to-face
Email
Email
Email
(Calendar Feature)
Face-to-face
Face-to-face/Email
Face-to-face/Email
Face-to-face/Email
Face-to-face/Email
Face-to-face
Email
Email
(Calendar Feature)
Face-to-face
Email/Internet
Internet
Email/Internet
Email
(Calendar Feature)
Face-to-face
Email

Complete
X
X
X
X
X
X
X
X
X
X

PROJECT MONITORING MATRIX


Item
Bold Dates
Complete (Initials)
Behind (initials)

Task

Project Monitoring Matrix Key


Indicates
Date change from scheduled date
(Green) Task complete and was marked complete by
indicated initials of team member
(Yellow) Task has fallen behind scheduled date and was
marked by initials of a team member assigned to the task
that is behind, requires attention of PM

Establish Project Objectives

Person(s)
Responsible for
Completion
Tiffany Morlan - TM

Create Project Scope

Start Date
(Scheduled)

End Date
(Scheduled)

Actual
Start Date

1/4/2016

1/4/2015

1/4/2016

Tiffany Morlan - TM

1/4/2016

1/4/2015

1/4/2016

Identify Deliverables

Tiffany Morlan - TM

1/8/2016

1/8/2016

1/8/2016

Create Timeline for Deliverables

Tiffany Morlan - TM

1/8/2016

1/8/2016

1/8/2016

Create Budget Allocations

Tiffany Morlan - TM

1/11/2016

1/12/2016

1/11/2016

Submit Stakeholder Plan Review

Tiffany Morlan - TM

1/13/2016

1/15/2016

1/13/2016

Submit Plan for Approval

Tiffany Morlan - TM

1/18/2016

1/21/2016

1/18/2016

Receive Plan Approval

Tiffany Morlan - TM

1/22/2016

1/22/2016 1/21/2016

Send Invite for Kickoff Meeting

Tiffany Morlan - TM

1/25/2016

1/25/2016 1/24/2016

Hold Formal Kickoff Meeting

All Team Members ALL


All Team Members ALL
All Team Members -

1/27/2016

1/27/2015

1/27/2016

1/28/2016

1/29/2016

1/28/2016

1/28/2016

1/29/2016

1/28/2016

Review Face-to-Face Workshop


Establish Workshop Design Plans

Actual
End Date

Status
Column

1/4/2015 CompleteTM
1/4/2015 CompleteTM
1/8/2016 CompleteTM
1/8/2016 CompleteTM
1/12/2016 CompleteTM
1/15/2016 CompleteTM
1/21/2016 CompleteTM
1/21/2016 CompleteTM
1/24/2016 CompleteTM
1/27/2015 CompleteTM
1/29/2016 CompleteTM
1/29/2016 Complete-

Notes

Approval received 1
day early
Sent 1 day early

Submit Deliverable Stakeholder


Review
Submit Deliverable Details for
Approval
Receive Deliverable Details
Approval
Send Invite for Pre-Development
Meeting
Hold Pre-Development Meeting
Complete Module 1 Development
Complete Module 2 Development
Complete Module 3 Development
Complete Module 4 Development
Assemble Module Deliverables in
LMS
Review Complied LMS Workshop
Submit Deliverables for Approval
Receive Deliverables Approval
Send Invite for Pilot Strategy
Meeting
Hold Meeting to Discuss Pilot
Strategy
Assemble Pilot Group
Implement Workshop with Pilot
Group
Gather Feedback from Pilot
Group
Send Invite for Final Revisions
Meeting
Meet to Discuss Final Revisions

ALL
Tiffany Morlan - TM

2/2/2016

2/4/2016

2/2/2016

2/4/2016

Tiffany Morlan - TM

2/5/2016

2/5/2016

2/5/2016

2/5/2016

Tiffany Morlan - TM

2/10/2016

2/10/2016

2/10/2016

2/10/2016

Tiffany Morlan - TM

2/11/2016

2/11/2016

2/11/2016

2/11/2016

All Team Members ALL


Clark Essex & Pedro
Lopez - CE & PL
Clark Essex & Pedro
Lopez - CE & PL
Clark Essex & Pedro
Lopez - CE & PL
Clark Essex & Pedro
Lopez - CE & PL
Pedro Lopez - PL

2/15/2016

2/15/2016

2/15/2016

2/15/2016

2/16/2016

2/19/2016

2/19/2016

2/22/2016

2/16/2016

2/19/2016

2/22/2016

2/25/2016

2/22/2016

2/25/2016

2/26/2016

2/26/2016

All Team Members ALL


Tiffany Morlan - TM
Tiffany Morlan - TM
Tiffany Morlan - TM

2/29/2016

2/29/2016

3/1/2016
3/4/2016
3/5/2016

3/1/2016
3/4/2016
3/5/2016

All Team Members ALL


Clark Essex & Pedro
Lopez - CE & PL
Clark Essex

3/8/2016

3/8/2016

3/15/2016

3/18/2015

3/21/2016

4/15/2015

Clark Essex & Pedro


Lopez - CE & PL
Tiffany Morlan - TM

4/18/2016

4/20/2016

4/20/2016

4/20/2016

All Team Members ALL

4/22/2016

4/22/2016

TM
CompleteTM
CompleteTM
CompleteTM
CompleteTM
CompleteTM
Behind - PL

Make Final Revisions


Submit Completed Workshop for
Approval

Pedro Lopez - PL
Tiffany Morlan - TM

4/25/2016
4/27/2016

4/26/2016
4/27/2016

PROJECT SIGN-OFF FOR COMPLETED PROJECT


Project:
D ATE :
Manager:

Converting a Powerful Workshop to an Online Format


April 27, 2015
Tiffany Morlan

Team Members and Stakeholders

Tiffany Morlan (Jennie Davenport), Project Manager


Professor Clark Essex, Subject Matter Expert
Professor Pedro Lopez, Instructional Designer
eduLearning Systems, Project Manager Employer
National Health Association, Funding Provided By
Team members have reviewed completed deliverables as of date indicated:

Approved final workshop revisions Clark Essex (and team)


Completed final workshop revisions Pedro Lopez
Approved final workshop revisions and submitted for final project approval Tiffany Morlan

I, the Project Approver, consider this project complete:

Yes
No (If not, form will be returned to PM without signature and further instructions.)

___________________________________________________ (Project Approver Signature)


___________________ (Date)

References
Portny, S. E., Mantel, S. J., Meredith, J. R., Shafer, S. M., Sutton, M. M., & Kramer, B. E. (2008). Project management: Planning, scheduling, and controlling
projects. Hoboken, NJ: John Wiley & Sons, Inc.