ID

Task Name

Research Timeline

Duration

Seminar presentation
Choosing a seminar topic

Gathering of journals and related materials

8 wks

Review of materials

4 wks

List out factors that affect QoS

Narrow down to a particular factor

2 wks

Identify a research problem

2 wks

Determination of a feasible solution

2 wks

10

Seminar presentation
Write a survey paper

0 wks

1 wk

Write a draft of the survey paper

1 wk

14

Submit to supervisor for correction

1 wk

15

Re-write the draft base on the correction

1 wk

16

Submit the corrected version to supervisor

1 wk

17

Run the draft on TurnITin

1 wk

18

Modify base on TurnITin result

1 wk

19

Submit to Supervisor for final approval

1 wk

20

Submit a copy for conference publication

21

Acceptance notification for conference publication


Identification of a research methodology

23

Learning MatLab

24

Understanding Fuzzy Logic

25

Propose a research methodology

1 wk

60 days
12 wks

Proposal defense and research work

4 wks
2 wks
75 days

Indepth study of the research problem

3 wks

28

Proposal write up

2 wks

29

Coding and simulation

4 wks

30

Modifying the methodology

3 wks

31

Evaluation, re-coding and simulation

2 wks

32

Data analysis and interpretation


Thesis writing

3 wks
55 days

34

Writing of first draft

35

Correction by supervisor

1 wk

36

Writing the second draft

2 wks

37

Internal defense

38

Writing the third draft

39

External defense

40

Writing the final draft

2 wks

1 wk
2 wks
1 wk

Submission of thesis

2 wks
10 days

42

Present the binded copy of thesis for submission

1 wk

43

Clearance and Graduation party

1 wk

Project: M.Sc Research timeline


Date: Thu May 7, '15

5/5

5 wks

27

41

Aug Aug Aug Aug Aug Sep Sep Sep Sep Oct Oct Oct Oct Nov Nov Nov Nov Nov Dec Dec Dec Dec Jan Jan Jan Jan Feb Feb Feb Feb Mar Mar Mar Mar Mar Apr Apr Apr Apr May May May May May Jun Jun

70 days

Source for more journal papers

33

Jul

1 wk

13

26

Jul

1 wk

12

22

Jul

100 days

11

May May May May Jun Jun Jun Jun Jun Jul